constancia site visit presentation -...

54
CONSTANCIA SITE VISIT PRESENTATION July 17, 2018

Upload: buidang

Post on 21-Sep-2018

222 views

Category:

Documents


3 download

TRANSCRIPT

  • CONSTANCIA SITE VISIT PRESENTATION

    July 17, 2018

  • Cautionary Information

    2

    This presentation contains forward-looking information within the meaning of applicable Canadian and United States securities legislation. All information contained in this presentation, other than statements of current and historical fact, is forward-looking information. Often, but not always, forward-looking information can be identified by the use of words such as plans, expects, budget, guidance, scheduled, estimates, forecasts, strategy, target, intends, objective, goal, understands, anticipates and believes (and variations of these or similar words) and statements that certain actions, events or results may, could, would, should, might occur or be achieved or will be taken (and variations of these or similar expressions). All of the forward-looking information in this presentation is qualified by this cautionary note. Forward-looking information includes, but is not limited to, production, cost and capital and exploration expenditure guidance, anticipated production at Hudbays Constancia mines, the anticipated timing, cost and benefits of developing the Pampacancha deposit, the anticipated impact of any delays to the start of mining the Pampacancha deposit, anticipated exploration plans, including the planned exploration strategy for the properties surrounding Constancia, anticipated mine plans, anticipated optimization initiatives and the expected benefits of such initiatives, anticipated cash flows from operations and related liquidity requirements, the anticipated effect of external factors on revenue, such as commodity prices, estimation of mineral reserves and resources, mine life projections, reclamation costs, economic outlook, government regulation of mining operations, and business and acquisition strategies. Forward-looking information is not, and cannot be, a guarantee of future results or events. Forward-looking information is based on, among other things, opinions, assumptions, estimates and analyses that, while considered reasonable by the company at the date the forward-looking information is provided, inherently are subject to significant risks, uncertainties, contingencies and other factors that may cause actual results and events to be materially different from those expressed or implied by the forward-looking information. The material factors or assumptions that Hudbay identified and were applied by the company in drawing conclusions or making forecasts or projections set out in the forward-looking information include, but are not limited to: the success of mining, processing, exploration and development activities; the scheduled maintenance and availability of the processing facilities; the accuracy of geological, mining and metallurgical estimates; anticipated metals prices and the costs of production; the supply and demand for metals the company produces; the supply and availability of all forms of energy and fuels at reasonable prices; no significant unanticipated operational or technical difficulties; the execution of Hudbays business and growth strategies, including the success of its strategic investments and initiatives; the availability of additional financing, if needed; the ability to complete project targets on time and on budget and other events that may affect the companys ability to develop its projects; the timing and receipt of various regulatory, governmental and joint venture partner approvals; the availability of personnel for the exploration, development and operational projects and ongoing employee relations; the ability to secure required land rights to develop the Pampacancha deposit; maintaining good relations with the communities in which the company operates, including the communities surrounding the Constancia mine; no significant unanticipated challenges with stakeholders at the companys various projects; no significant unanticipated events or changes relating to regulatory, environmental, health and safety matters; no contests over title to the companys properties, including as a result of rights or claimed rights of aboriginal peoples; the timing and possible outcome of pending litigation and no significant unanticipated litigation; certain tax matters, including, but not limited to current tax laws and regulations and the refund of certain value added taxes from the Canadian and Peruvian governments; and no significant and continuing adverse changes in general economic conditions or conditions in the financial markets (including commodity prices and foreign exchange rates). The risks, uncertainties, contingencies and other factors that may cause actual results to differ materially from those expressed or implied by the forward-looking information may include, but are not limited to, risks generally associated with the mining industry, such as economic factors (including future commodity prices, currency fluctuations, energy prices and general cost escalation), uncertainties related to the development and operation of Hudbays projects, dependence on key personnel and employee and union relations, risks related to the schedule for mining the Pampacancha deposit (including the timing and cost of acquiring the required surface rights and the cost and impact of any schedule delays), risks related to political or social unrest or change, risks in respect of aboriginal and community relations, rights and title claims, operational risks and hazards, including unanticipated environmental, industrial and geological events and developments and the inability to insure against all risks, failure of plant, equipment, processes, transportation and other infrastructure to operate as anticipated, compliance with government and environmental regulations, including permitting requirements and anti-bribery legislation, depletion of Hudbays reserves, volatile financial markets that may affect Hudbays ability to obtain additional financing on acceptable terms, the failure to obtain required approvals or clearances from government authorities on a timely basis, uncertainties related to the geology, continuity, grade and estimates of mineral reserves and resources, and the potential for variations in grade and recovery rates, uncertain costs of reclamation activities, the companys ability to comply with its pension and other post-retirement obligations, Hudbays ability to abide by the covenants in its debt instruments and other material contracts, tax refunds, hedging transactions, as well as the risks discussed under the heading Risk Factors in the companys most recent Annual Information Form. Should one or more risk, uncertainty, contingency or other factor materialize or should any factor or assumption prove incorrect, actual results could vary materially from those expressed or implied in the forward-looking information. Accordingly, you should not place undue reliance on forward-looking information. Hudbay does not assume any obligation to update or revise any forward-looking information after the date of this presentation or to explain any material difference between subsequent actual events and any forward-looking information, except as required by applicable law. This presentation has been prepared in accordance with the requirements of the securities laws in effect in Canada, which may differ materially from the requirements of United States securities laws applicable to U.S. issuers. All amounts are in U.S. dollars unless otherwise noted.

  • SAFETY REVIEW

  • Health & Safety Statistics

    TARGET 2018

    F.I. 0.12

    S.I. 8.1

    Indicators obtained based on 200,000 man-hours worked

    0.652

    0.00 0.00 0.050 0.130 0.1278 0.1282 0.1271 0.1266 0.1284 0.1320 0.1393 0.00 0.00

    0.030 0.030 0.0256 0.0256 0.0254 0.0253 0.0257 0.0264 0.0279

    0.00

    0.02

    0.04

    0.06

    0.08

    0.10

    0.12

    0.14

    0.0

    1.0

    2.0

    3.0

    4.0

    5.0

    6.0

    7.0

    8.0

    9.0

    10.0

    Jul/17 Aug/17 Sep/17 Oct/17 Nov/17 Dec/17 Jan/18 Feb/18 Mar/18 Apr/18 May/18 Jun/18

    Freq

    uenc

    y In

    dex

    (FI)

    Sev

    erity

    Inde

    x(SI

    )

    SI 2017 -2018 FI 2017 - 2018

    Target SI: 9

    Target FI: 0.13

    Target FI: 0.12

    Target SI: 8.1

    4

  • Environmental Performance KPIs

    Target : 93% June Performance : 100% Year-todate Performance : 98%

    INDICATOR WEIGHT YTD TARGET

    ENVIRONMENTAL MANAGEMENT INDICATORS (EMI) 0.7 Jan Feb Mar Apr May Jun KPI EMI

    INSPECTIONS (Opportuni ties for Improvement) 0.4 100 100 94 100 100 100 99 90

    OEFA-LIKE AUDIT 0.1 100 100 100 100 100 100 100 94

    OEFA AUDIT 0.15 100 100 100 100 100 100 100 95

    ENVIRONMENTAL INCIDENTS 0.3 94 91 98 80 96 100 93 92

    ENVIRONMENTAL TRAINING 0.05 86 86 96 96 100 100 94 93

    98 97 97 94 99 100 97 92

    ENVIRONMENTAL QUALITY INDICATORS (EQI) 0.2 Ene Feb Mar Abr May Jun KPI EQI

    WATER QUALITY 1 100 100 100 100 100 100 100 93

    100 100 100 100 100 100 100 93

    SUSTAINABILITY (IS) 0.1 Ene Feb Mar Abr May Jun KPI IS

    WATER CONSUMPTION 0.5 100 100 100 100 100 100 100 96

    ENERGY CONSUMPTION AND GHG 0.5 100 100 100 100 100 100 100 96

    100 100 100 100 100 100 100 96

    98 98 98 96 99 100 98 93

    MONTH

    * NOTE: Each indicator resul t wi l l be multipl ied by i ts weight

    TOTAL

    TOTAL

    TOTAL

    CONSTANCIA MONTHLY KPI

    5

  • Constancia Permits

    Environmental Certification

    Mine permit

    EIA, Amendment 1 and 2 EIA Amendment 3 under evaluation

    Authorization for construction and operation and amendments Amendment 2 under development

    Permits for Plant and TMF Authorization for construction and operation and amendments

    Water permits Water use licences Water dicharge permits

    Main permits:

    6

  • Anti-Fatigue and Collision Project 1:40 am . Operator is tired

    Potential safety event!.

    7

  • Objective and background: To reduce the probability of fatigue and collision events through the use of technology

    Constancia Mine Collision & Fatigue Events

    Historically more collision than fatigue events at Constancia Going from Administrative to Engineering controls

    8

    2016 2017 2018 Collision 4 6 4 Fatigue 1 1 Total 5 7 4

    0

    1

    2

    3

    4

    5

    6

    7

    8

    Num

    ber o

    f Ev

    ents

    Anti-Fatigue and Collision Project

  • Alternatives Non-invasive: Hexagon SafeMine and FatigueMonitor

    Safe Mine (CAS) Fatigue Monitor Primary function of a fatigue system: Wake-up alarm in case of micro sleep to avoid immediate danger for operator and equipment Secondary function: Alarming for Perclos (Slow Eye Blinking) Alarming for Distraction (looking down e.g. on a cell phone) Third function: Provide the control room with real time data of fatigue related events Provide detailed reports to management for desicions based in benchmarked data

    Surrounding Awareness Collision Avoidance

    9

    Anti-Fatigue and Collision Project

  • GuardVants Safe Mine and Fatigue Monitor

    Collision Guard Op Guard Using peer to peer communication between equipment, Collision Guard increases awareness of the situation by showing the location of any other equipment near the operator. The fully configurable solution is integrated with all the designs and equipment of the mine to ensure complete coverage of the equipment.

    Historic data

    Check fatigue and distraction events in real time

    Sound alarm and seat vibrator

    Alternatives Non-invasive:

    10

    Anti-Fatigue and Collision Project

  • CORPORATE AFFAIRS & SOCIAL RESPONSIBILITY

  • Government and Community Institutions We work with all levels of Government and the Communities to develop stable operations and

    to maximize the impact of our social investment in our area of influence and beyond

    12

    District District Municipality of Chamaca District Municipality of Livitaca District Municipality of Velille District Municipality of Coporaque District Municipality of Condoroma

    Communities Chilloroya, Uchucarcco, among others

    Level Applicable Area Election Frequency

    Next Election New Term Start Date

    National Peru Every 5 years April 2021 July 28, 2021

    Regional Cusco Every 4 years October 2018 January 1, 2019

    Provincial Chumbivilcas Every 4 years October 2018 January 1, 2019

    District Chamaca, Livitaca & Velille,

    Every 4 years October 2018 January 1, 2019

    Local Community Chilloroya, Uchucarcco

    Every 2 years November 2018 January 1, 2019

    National: Ministry of Development & Social Inclusion Ministry of Energy & Mines Ministry of Labor Ministry of Agriculture Ministry of Finance

    Regional: Regional Government of Cusco

    Provincial: Provincial Municipality of Chumbivilcas

    Agreements signed with:

  • Local Political Context

    13

    Uchucarcco: In Q1 2018 we signed cooperation agreements for sustainable development

    During Q1 and Q2 2018 Hudbay has signed specific agreements with municipalities of Velille and Chamaca

    Livitaca: 2017 cooperation agreement

    under execution

    Hudbays transportation route (shared with other large miners) will be considered as a national critical asset by the Government

    This year, for the first time, Chumbivilcas will receive

    CANON coming from operation of Constancia

    11 Candidates for Mayor of Chumbivilcas, 11 for

    Livitaca, 7 for Chamaca, and 7 for Velille

    Chilloroya: Fulfillment of 2017 commitments;

    ongoing negotiation for Pampacancha

    Coporaque: 2017 cooperation agreement under execution

    On October 7th there will be elections for regional

    Governors and local mayors

  • Mining Properties Near Constancia

    Exploration work to be conducted on newly acquired properties near Constancia with potential to provide higher-grade feed to the Constancia mill post-Pampacancha

    14

    MINERAL PROPERTIES WITHIN TRUCKING DISTANCE OF CONSTANCIA PROCESSING FACILITY

    0 5,000 10,000

    Meters

    Constancia Pit Pampacancha Pit

    Caballito

    Maria Reyna

    Hudbay

    Kusiorcco

    Caballito/ Maria Reyna

    LEGEND Process Plant

  • On June 10th the technical committee submitted a written report to the Steering Committee of Chilloroya

    On July 5th an ordinary assembly was held in Chilloroya Pampacancha discussions were tabled

    The assembly plans to resume discussions with respect to Pampacancha after anniversary celebrations of the community

    15

    Pampacancha: Negotiation Status

    The communitys headquarters during last assembly on July 5, 2018

  • Maria Reyna, Caballito, Kusiorcco

    Uchucarcco: Has agreed to commence negotiations

    Qquehuincha: Ongoing process to conclude negotiation of exploration agreement for 3 years

    Aahuichi: Ongoing dialogue to start negotiation of exploration agreement for 3 years

    Collana-Livitaca: Dialogue process delayed due to community internal conflicts

    16

    Exploration Properties : Negotiation Status

  • MINE OPERATIONS REVIEW

  • Physicals H1 and Q2 2018

    18

    2018 has more plant availability and increased the throughput against 2017 2018 is positive in model reconciliation (more tonnes to stockpiles), with lower headgrade than 2017

    Ore Mined Kt 18,234 14,551 25% 8,744 7,338 19% 9,490 7,213 32%

    Waste Mined Kt 17,741 12,628 40% 9,900 6,617 50% 7,841 6,011 30%

    Rehandle Kt 1,464 767 91% 766 280 174% 698 487 43%

    Material Moved Kt 37,439 27,946 34% 19,410 14,235 36% 18,029 13,711 31%

    Stripping Ratio waste:Ore 1.0:1 0.9:1 12% 1.1:1 0.9:1 26% 0.8:1 0.8:1 1%

    Average Ore Grade Mined - - - -

    Grade - Copper % 0.49% 0.55% 11% 0.47% 0.55% 15% 0.50% 0.55% 8%

    Grade - Moly % 0.01% 0.02% 27% 0.01% 0.02% 23% 0.01% 0.02% 31%

    Grade - Gold g/t 0.05 0.04 10% 0.05 0.04 23% 0.05 0.05 1%

    Grade - Silver g/t 4.11 3.92 5% 4.03 3.81 6% 4.19 4.03 4%

    Additionals - -

    Ore Milled Kt 15,578 13,249 18% 7,727 6,932 11% 7,851 6,318 24%

    Throughput ktpd 86 73 18% 85 76 11% 87 70 24%

    Grade Milled - Copper % 0.47% 0.54% 13% 0.44% 0.53% 18% 0.50% 0.54% 7%

    Fine Tonnes - Copper t 58,369 57,009 2% 26,817 29,798 10% 31,551 27,211 16%

    End Inventory - -

    Ore stockpile kt 5,201 3,580 45% 5,201 3,580 45% 4,416 3,309 33%

    Grade - Copper % 0.40% 0.43% 8% 0.40% 0.43% 8% 0.39% 0.42% 9%

    Grade - Moly % 0.01% 0.01% 7% 0.01% 0.01% 7% 0.01% 0.01% 9%

    Grade - Gold g/t 0.06 0.07 10% 0.06 0.07 10% 0.06 0.07 13%

    Grade - Silver g/t 4.81 4.57 5% 4.81 4.57 5% 4.89 4.58 7%

    MINING PHYSICALS %2017Q22018Q2

    2017Q1

    2018Q1 %

    2018H1

    2017H1 %

    NOTE: Reported tonnes and grade for ore mined are estimates based on mine plan assumptions and may not reconcile fully to ore milled.

  • YTD 2018 Mining Reconciliation

    Blue areas are forecast production for 2018; red are YTD actuals Actual production is 93% consistent with mine plan

    19

  • Over a period of 10 months, the 2018 LTP Model used for reserves reporting reconciles with actual production within +/-15% for all the elements except Zn

    The Au and Mo grade are conservative (-14% and -10% respectively). The performance of the 2018 LTP model for these two elements could potentially be improved through current modifications to the resource modeling process, i.e. integration of blasthole assays

    Zn shows an under-estimation problem which deserves further investigations. However, the Zn/Cu ratio of the reserves is well below the problematic threshold of 0.5. Localised high Zn zones are managed through blending with low Zn ore from stockpiles

    Long-term Model Reconciliation

    Conclusion: Mining progress is according to the Plan and reconciliations show that the Reserves Model is a reliable basis for the long-term plan

    20

  • MINE OPERATIONS

  • Instrumentation and Monitoring - PIT

    Pit geotechnical instrumentation has gone from 38 in 2017 to 60 instruments in 2018 Continuous identification and monitoring of potential areas of instability Weekly Monitoring Report All geotechnical zones monitored are currently in green alert (< 5 mm/day)

    Phase II

    Phase I

    ZCG04

    ZCG 08

    ZCG 06 ZCG 07

    Phase VII

    Instrumentation Number of instruments Total instruments

    Prisms 35

    Extensometer 1

    Radar Slope (*) 1

    Piezometers Open Stand Pipe 21

    Vibrating Wire Piezometers 2

    Total Geotechnical Instrumentation - Constancia Pit April 2018

    60

    (*) Currently in tests.

    Extensometer

    Prism Existing instrumentation

    Prisms

    Extensometer SP Piezometer

    Critical zones monitoring

    22

  • Instrumentation and Monitoring - WRF

    In June 2018 the geotechnical instrumentation project was completed; consisted of the installation of 01 inclinometer pipe, 01 VWP, 01 settlement cell and 01 pressure cell

    To date no significant movements are reported. Facility presents a STABLE condition

    Weekly WRF stability monitoring report

    Existing instrumentation 2017

    Prisms

    VW Piezometer SP Piezometer

    VWP Inclinometer

    Instrumentation campaign 2018

    Settlement & Pressure cells

    WRF

    Nv 4100

    Nv 4120

    PVW-18-04

    Nv 4180

    Nv 4220 PVW-18-05

    PVW-18-03

    CELP-18-01

    Nv 4100

    CELA-18-01

    Instrumentation Number of instruments Total instrumentsPrisms 25

    Piezometers Open Stand Pipe 4Vibrating Wire Piezometers 7

    Settlement Cells 1Pressure Cells 1Inclinometer 1

    Total Geotechnical Instrumentation - WRF June 2018

    39

    23

  • Instrumentation and Monitoring - TMF

    Accelerographs

    Legend Prisms Inclinometer

    New Piezometers

    Parshall Flume

    Instrumentation Number of instruments Total instruments

    Prisms 22Inclinometer (*) 2

    Vibrating Wire Piezometers (*) 167Parshall Flume 2

    Accelerographs (**) 2

    Total Geotechnical Instrumentation - TMF June 2018

    195

    (*) In the research campaign, 23 new piezometers and 2 inclinometers were installed.(**) In May, 2 accelerographs were installed.

    Improvements in the stability monitoring program in 2018 Weekly and quarterly reports; STABLE conditions in the TMF A total of 14 new instruments installed in 2018

    24

  • MINE OPERATIONS: IMPROVEMENT INITIATIVES

  • Objective: To increase truck engine life in Constancia operations CAT has agreed to increase truck engine PCR from 16,000 to 18,000 hrs. Decision is supported by historical data, conditions monitoring, world class maintenance practices, favourable haul profile and appropriate payload policy. This will improve operative cost in the LOM.

    Constancia Mine Engines for CAT 793F

    Historical analysis for Constancia diesel engines

    CAT 793F ENGINE LIFE EXTENSION

    26

    Mine Maintenance

  • Objective: Detecting the best moment to change components before failures but normally after the PCR, increasing life for components while controlling safety for the equipment and people

    Constancia Mine brakes for Wheels and Final drives for CAT 793F

    Historical analysis for Constancia components

    COMPONENT CHANGE PLAN BASED ON CONDITION MONITORING

    27

    J.CRUZADO C. RAMIREZ

    06-06-18 18-06-18

    NROTULA

    PROFUNDIDAD DE DISCUNTINUIDAD CONDICIN

    NROTULA

    PROFUNDIDAD DE DISCUNTINUIDAD CONDICIN

    1 --- NORMAL 1 --- NORMAL

    2 --- NORMAL 2 --- NORMAL3 --- NORMAL 3 --- NORMAL4 --- NORMAL 4 --- NORMAL5 --- NORMAL 5 --- NORMAL6 --- NORMAL 6 --- NORMAL7 --- NORMAL 7 --- NORMAL8 --- NORMAL 8 --- NORMAL

    INSPECCIN A LAS RTULAS DE DIRECCIN MEDIANTE ULTRASONIDO

    LOCALIZACIN DE RTULAS DE DIRECCIN CATERPILLAR

    N De reporte:10

    INSPECTOR:

    FECHA DE INSPECIN:

    OBSERVACIONES: - Se cambiaron las 3 Rotulas con indicaciones, se realiz la inspeccin sin detectar ninguna incacin relevante, seguiremos con su monitoreo programado.

    N De reporte:10

    INSPECTOR:

    FECHA DE INSPECIN:

    OBSERVACIONES:

    Constancia steering system for CAT 793F

    27

    Mine Maintenance

  • Objective Increasing life of truck tires. Improves cost per hour ratio by approximately 20%

    TIRE RETREAD FOR TRUCKS

    28

    Mine Maintenance

  • Geotechnical & Hydrogeology

    1. IMPLEMENTATION OF RADAR SYSTEM:

    In June 2018 radar monitoring tests started in the pit using REUTECH and IBIS technologies (3 months each) to determine the best performer and accuracy according to our operational conditions

    Also planed to be used for stability monitoring at the TMF and WRF

    RADAR REUTECH IN CONSTANCIA

    BENEFITS: "Real time monitoring" (24/7) and alarm system according to

    threshold Key for failure prediction

    CONSTANCIA PIT TMF

    WRF

    Monitoring Point 01

    Monitoring Point 02 Monitoring

    Point 01

    Monitoring Point 01 Monitoring

    Point 02

    Monitoring Point 02

    29

  • 2. IMPLEMENTATION OF MAPPING BY DRONE (UAV)

    Mapping deposit sites Exploring for minerals Monitoring stockpile volumes Tracking equipment Time-lapse photography

    MAPPING AND ANALYSIS WITH 3D visualization of blocks in real space Volume in m3 or Mass in kgs Sliding Vector

    Geotechnical bench mapping began in May 2018; supported by drones and "Sirovision" technology.

    VIDEO

    30

    Geotechnical & Hydrogeology

  • 3. IMPLEMENTATION OF THE TELEMETRIC SYSTEM:

    BENEFITS: Acquisition and reporting of data in real time Remote switch on/off of Electrical Boards Fault detection and error alarm Custom software, achieving autonomous processes Wireless technology with a reception range of 20

    km in open field Improves personnel safety by reducing exposure

    G7 G7

    G21

    G20

    G16

    G18

    G19

    G5

    G10

    G14

    G25

    Optimizes analysis of the maintenance process to minimize pit dewatering interruptions 31

    Geotechnical & Hydrogeology

  • 4. INTEGRATION FOR GEOTECHNICAL INSTRUMENTATION

    Improves the processing time and analysis of Geotechnical and Hydrogeological instrumentation data Real-time integrated alerts for all the instrumentation, which will arrive by email or text messages to cell phones,

    tablets and to the control room (Fleet Management System) Compare and evaluate information from different instrument types at the same time for a better understanding of

    anomalous behavior or potential instabilities

    SHMS (Slope Health Monitoring System)- QSI

    5. IMPLEMENTATION OF SUBMERSIBLE CAMERA FOR INSPECTION OF PUMPING WELLS

    Identify faults / obstructions in the pumping systems Periodic inspection of filters and pipes Reduce costs and early fault detection Time-lapse video

    32

    Geotechnical & Hydrogeology

  • Mine Planning

    DRONES & SURVEY Use of drones for Mine Surveying:

    Waste Rock Facility (WRF) as-builts Tailings dam construction advances Pipeline as-builts Surveying of risky or inaccessible areas within the pit Constancia Mine Site flyovers

    Technology reduces crew workload by 20%. Flying time 45-50 min covers around 10,000 m2 Achieve survey-grade accuracy in a photogrammetric

    map or 3D model

    IMPLEMENTED USE OF NSR IN MINE POLYGONS Optimizes the NSR value of ore mine polygons, to provide the best feed to the crusher Improves quality of ore concentrate by limiting the levels of contaminants (Zn, Pb)

    MINE - PROCESSING PLANT INTEGRATION Provides real time Mine to Crusher information, detailing productivity and quality of the material being fed. Data includes throughput, tonnages, Cu%, Pb%, Ox%,Zn%, Ratio Zn/Cu and recoveries

    33

  • MINE OPERATIONS: LAYOUTS

  • Current General Overview

    35

  • TMF 2018, YTD & FY Source of suitable material:

    Pit Phase VII and II

    Destination:

    Ramps

    TMF Embankment

    Actual Jan to Jun: 6.3 Mt

    Forecast Jul to Dec: 5.5 Mt

    West Dam, AA Section East Dam, BB Section

    36

  • PROCESS PLANT

  • 38

    Production KPIs 2018

  • 39

    Production KPIs Q2 Gold and Silver

    Au Head Grade g/tonne 0.05 0.041 23% 0.05 0.038 31% 0.05 0.044 15%

    Au Recovery % 44.90 44.67 1% 44.80 44.84 0% 44.90 44.51 1%

    Ag Head Grade g/tonne 4.01 4.08 -2% 3.92 3.91 0% 4.10 4.27 -4%

    Ag Recovery % 61.90 62.42 -1% 61.20 62.62 -2% 62.50 62.22 0%

    2018Q1

    2017Q1 %PRODUCTION

    2018H1

    2017H1 %

    2018Q2

    2017Q2 %

  • 0

    5,000

    10,000

    15,000

    20,000

    25,000

    30,000

    35,000 Ja

    nuar

    y

    Febr

    uary

    Mar

    ch

    April

    May

    June

    July

    Augu

    st

    Sept

    embe

    r

    Oct

    ober

    Nov

    embe

    r

    Dece

    mbe

    r

    KT

    Cumulative Treatment

    Real Budget

    40

    Cumulative Treatment (KT) Q1

    Actual 7,851Budget 7,763Variation 1.1%

    Cumulative Treatment (KT)Actual 7,727Budget 7,497Variaton 3.1%

    Q2

    Cumulative Treatment

  • 95.8

    99.5

    93.4 96.3

    81.6

    97.7 96.0

    95.5 96.0 95.8

    83.2 95.8

    96.0 96.0

    95.8 96.0

    86.0

    96.0 95.2 96.8

    95.0 96.8

    86.0

    96.0

    10

    20

    30

    40

    50

    60

    70

    80

    90

    100

    Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

    %

    Actual Availability Budget Availabilty Disponibilidad Forecast

    November: Scheduled maintenance Replacement of liners in SAG

    Mills 01/03 and Ball Mill 04. Replacement of trommel

    screens in SAG Mills 01. Maintenance of pumps PU

    01/02.

    May: Scheduled maintenance Replacement of liners in

    SAG Mills 01/03 and Ball Mill 02.

    Replacement of trommel screens in SAG Mills 01/03.

    Maintenance of pumps PU 01/02

    41

    QUARTER FYMONTH JAN FEB MAR APR MAY JUN JUL AUG SEP OCT NOV DEC 2018Actual Availability (%) 95.8 99.5 93.4 96.3 81.6 97.7Forecast (%) 96.0 95.5 96.0 95.8 81.5 96.7 95.2 96.8 95.0 96.8 86.0 96.0 94.0Budget Availablity (%) 96.0 95.5 96.0 95.8 83.2 95.8 96.0 96.0 95.8 96.0 86.0 96.0 94.0Actual Availability (%)Forecast (%)Budget Availablity (%) 95.8 91.5 95.9 92.72

    Q1 Q2 Q3 Q4

    96.1 91.895.8 91.2 95.7 92.99

    Mechanical Availability

  • 2018 IMPLEMENTED IMPROVEMENTS

  • 43

    Description Progress 1. Mine to Plant

    100%

    2. On-line analyzers PSI 300 100%

    3. On-line analyzers Courier 6 ISL 100%

    4. Split cameras in crushing bays and Belt CV01 (On-line granulometry) 100%

    5. Met Rock cameras (SAG mill feed granulometry) 100%

    6. Changed SGS expert system in Ball-SAG mill 100%

    7. Expert system implementation in flotation 100%

    8. Geo-metallurgy (microscopy and mineralogical characterization) 100%

    9. Evaluation of new reagents (collectors, frothers and flocculants) 90%

    2018 Implemented Improvements

  • FLOTACION ROUGHER BULK

    FLOTACION ROUGHER BULK

    FLOTACION ROUGHER

    NIDO DE CICLONES REMOLIENDA

    MOLINO DE REMOLIENDA

    ESPESADOR DE RELAVES

    CLEANER I CLEANER SCAVENGER CLEANER II

    CLEANER III(COLUMNAR CELL)

    REMOLIENDA DE COBRE

    16

    15

    17

    18

    192021

    22

    42

    PU-032

    PU-012

    PU-021PU-024

    PU-014

    CHANCADORAPRIMARIA

    STOCK PILE

    FAJA TRANSPORTADORA CV 001

    FEEDER 001

    ALIMENTADORES

    1

    23

    4

    6

    4

    1

    2

    1

    5

    6

    3

    7

    8

    9

    44

    Location of Implemented Improvements

  • METALLURGICAL PROJECTS

  • Metallurgical Projects Several metallurgical initiatives are being implemented

    with the intention of supporting us in getting copper recoveries up to the levels forecast in our latest 43-101 Technical Report for Constancia, dated March 29, 2018:

    1. ProFlote Magnets

    2. Jameson Cell

    3. HydroFloat Cell

    4. CiDRA

    5. Air Evaluation

    46

  • FEED

    FEED

    JAMESON CELLS

    FINAL CONCENTRATE

    LL

    SV S S S S S S

    SV S S S S S S

    SS S SV SV

    S SV SV SV

    L1 COPPER ROUGHER FLOTATION

    COPPER REGRIND MILL

    COPPER CLEANER 1FLOTATION

    L2 COPPER ROUGHER FLOTATION

    COPPER CLEANER SCAVENGERFLOTATION

    PROFLOTE MAGNETS (ALTERNATIVE 1)

    JAMESON CELL CLEANER SCALPER

    (For Ultrafines)

    HYDROFLOAT (For Extracoarse)

    PROFLOTE MAGNETS (ALTERNATIVE 2)

    47

    Location of Metallurgical Projects

  • Intended Benefit: By aggregating fine particles by magnetic force, ProFlote magnets are intended to recover metal from ultrafine particles (less than 20 microns) that may otherwise end up in tailings

    Timeline: Location of magnets currently under evaluation; installation expected to be

    completed by Jan 2019

    Electrodos ProFlote

    48

    ProFlote Magnets

  • 49

    Jameson Cell Intended Benefit: Technology intended to allow removal of liberated and fast floating

    minerals to final concentrate, reducing load in downstream circuit

    Timeline: Jameson cell sizing performed in May 2018; engineering expected to be completed by end of August 2018

  • Worldwide HydroFloat Pilot Campaigns

    50

    HydroFloat Cell Intended Benefit: By using an aeration system to disperse fine bubbles into a

    fluidized-bed environment, HydroFloat is intended to improve the selective recovery of extracoarse particles (greater than 140 microns) by applying flotation fundamentals to gravity separation

    Timeline: Site visits of other operations with similar technology completed in 2017;

    studies are underway

  • Particle Size Tracking (PST) (On-line granulometric analysis per cyclones in regrinding; three sizes)

    PST is made up of a set of sensors, a junction

    box and a computer in the control room

    The set of sensors consists of a reinforced probe in contact with the overflow and a set of integrated electronic elements protected by a sealed metal box

    The probe is covered by an extremely hard layer that makes it resistant to wear

    When the pulp flow hits the probe, it creates an impact acoustic signal; the response is then processed by a set of integrated electronic elements to obtain a measurement of the particle size in the pulp flow

    Intended Benefit: Enables real-time closed grind

    circuit control and improved recovery without loss of throughput

    51

    CiDRA

  • EVALUATION OF SUCTIONED AIR

    Sampling campaign was performed (two days of sampling with open vent (ON) during four hours, followed by closed vent (OFF) for another four hours, successively)

    Results of the evaluation of the Rougher flotation circuit (ON-OFF), in Line 01

    In general, based on the results and metallurgical balance, observed an increase in valuable particles recovery smaller than 400 micron (-400)

    Percentage of improvement in recovery is yet to be determined; additional testing will be conducted

    52

    Air Evaluation

  • 53

    Air Evaluation: Results

  • FOR MORE INFORMATION CONTACT:

    Carla Nawrocki, Director, Investor Relations

    416.362.7362 | [email protected]

    mailto:[email protected]

    Slide Number 1Cautionary InformationSlide Number 3Health & Safety Statistics Environmental Performance KPIs Constancia PermitsAnti-Fatigue and Collision ProjectObjective and background:Alternatives Non-invasive:Alternatives Non-invasive:Slide Number 11Government and Community InstitutionsLocal Political Context Mining Properties Near ConstanciaPampacancha: Negotiation StatusExploration Properties : Negotiation StatusSlide Number 17Physicals H1 and Q2 2018Slide Number 19Slide Number 20Slide Number 21Instrumentation and Monitoring - PITInstrumentation and Monitoring - WRFInstrumentation and Monitoring - TMFSlide Number 25Objective: To increase truck engine life in Constancia operationsObjective:ObjectiveGeotechnical & HydrogeologySlide Number 30Slide Number 31Slide Number 32Mine PlanningSlide Number 34Current General OverviewSlide Number 36Slide Number 37Production KPIs 2018Production KPIs Q2 Gold and SilverCumulative TreatmentMechanical Availability Slide Number 422018 Implemented ImprovementsLocation of Implemented ImprovementsSlide Number 45Metallurgical ProjectsLocation of Metallurgical ProjectsProFlote MagnetsJameson CellHydroFloat CellCiDRA Evaluation of Suctioned Air Slide Number 54