constancia mine site visit presentation sept 2014 final1030 v001 o569aq
DESCRIPTION
Constancia Mine Site Visit Presentation Sept 2014TRANSCRIPT
ACCORDING TO PLAN
CONSTANCIA MINE SITE VISIT
September 2014
CONSTANCIA PRESENTATION l 2
Cautionary Information
Forward Looking Information
This presentation contains “forward-looking statements” and “forward-looking information” (collectively, “forward-looking information”) within the meaning of applicable
Canadian and United States securities legislation. All information contained in this presentation, other than statements of current and historical fact, is forward-looking
information. Often, but not always, forward-looking information can be identified by the use of words such as “plans”, “expects”, “budget”, “guidance”, “scheduled”,
“estimates”, “forecasts”, “strategy”, “target”, “intends”, “objective”, “goal”, “understands”, “anticipates” and “believes” (and variations of these or similar words) and
statements that certain actions, events or results “may”, “could”, “would”, “should”, “might” “occur” or “be achieved” or “will be taken” (and variations of these or similar
expressions). All of the forward-looking information in this presentation is qualified by this cautionary note.
Forward looking information includes, but is not limited to, statements with respect to the anticipated timing, mechanics, completion of the subsequent acquisition
transaction to acquire the remaining shares of Augusta Resource Corporation (“Augusta”) the permitting, development and financing of Augusta’s Rosemont copper
project (the “Rosemont project”), Hudbay’s objectives, strategies, intentions, expectations and guidance and future financial and operating performance and prospects,
production at Hudbay’s 777, Lalor and Reed mines and initial production from the Constancia project, continued processing at Hudbay’s Flin Flon concentrator, Snow
Lake concentrator and Flin Flon zinc plant, Hudbay’s ability to complete the development of Hudbay’s Lalor and Constancia projects and the anticipated scope and cost
of any development plans for these projects, anticipated timing of Hudbay’s projects and events that may affect the company’s projects, including the anticipated issue
of required licenses and permits, Hudbay’s expectation that it will receive the remaining deposit amount under its amended precious metals stream transaction with
Silver Wheaton Corp. (“Silver Wheaton”) and that additional funding will be available if needed under Hudbay’s standby credit facility for Constancia, the anticipated
effect of external factors on revenue, such as commodity prices, anticipated exploration and development expenditures and activities and the possible success of such
activities, estimation of mineral reserves and resources, mine life projections, timing and amount of estimated future production, reclamation costs, economic outlook,
government regulation of mining operations, and business and acquisition strategies.
Forward-looking information is not, and cannot be, a guarantee of future results or events. Forward-looking information is based on, among other things, opinions,
assumptions, estimates and analyses that, while considered reasonable by us at the date the forward-looking information is provided, inherently are subject to
significant risks, uncertainties, contingencies and other factors that may cause actual results and events to be materially different from those expressed or implied by
the forward-looking information.
The material factors or assumptions that Hudbay identified and were applied by the company in drawing conclusions or making forecasts or projections set out in the
forward looking information include, but are not limited to: the success of mining, processing, exploration and development activities; the accuracy of geological, mining
and metallurgical estimates; the costs of production; the supply and demand for metals Hudbay produces; no significant and continuing adverse changes in financial
markets, including commodity prices and foreign exchange rates; the supply and availability of reagents for Hudbay’s concentrators; the supply and availability of
concentrate for Hudbay’s processing facilities for the company’s concentrate; the supply and the availability of third party processing facilities for Hudbay’s concentrate;
the supply and availability of all forms of energy and fuels at reasonable prices; the availability of transportation services at reasonable prices; no significant
unanticipated operational or technical difficulties; the execution of Hudbay’s business and growth strategies, including the success of Hudbay’s strategic investments
and initiatives; the availability of financing for Hudbay’s exploration and development projects and activities; the ability to complete project targets on time and on
budget and other events that may affect Hudbay’s ability to develop Hudbay’s projects; the timing and receipt of various regulatory and governmental approvals; the
availability of personnel for Hudbay’s exploration, development and operational projects and ongoing employee relations; Hudbay’s ability to secure required land rights
to complete its Constancia project; maintaining good relations with the communities in which Hudbay operates, including the communities surrounding the Constancia
project and First Nations communities surrounding the Lalor project and Reed mine; no significant unanticipated challenges with stakeholders at Hudbay’s various
projects, including the company’s newly acquired Rosemont project; no significant unanticipated events or changes relating to regulatory, environmental, health and
safety matters; no contests over title to Hudbay’s properties, including as a result of rights or claimed rights of aboriginal peoples; the timing and possible outcome of
pending litigation and no significant unanticipated litigation; certain tax matters, including, but not limited to current tax laws and regulations and the refund of certain
value added taxes from the Canadian and Peruvian governments; no significant and continuing adverse changes in general economic conditions or conditions in the
financial markets; and the timing and completion of a subsequent acquisition transaction in connection with Hudbay’s acquisition of Augusta.
CONSTANCIA PRESENTATION l 3
Cautionary Information (continued)
Forward Looking Information (continued)
The risks, uncertainties, contingencies and other factors that may cause actual results to differ materially from those expressed or implied by
the forward-looking information may include, but are not limited to, the development of the Rosemont project not occurring as planned, the
exercising of dissent and appraisal rights by Augusta shareholders should a subsequent acquisition transaction be undertaken in connection
with Hudbay’s acquisition of Augusta, Augusta continuing as a majority-owned subsidiary of Hudbay should a subsequent acquisition
transaction not be completed, the inaccuracy of Augusta’s public disclosure and representations in the support agreement upon which Hudbay’s
offer to acquire Augusta was predicated, the failure to obtain required approvals or clearances from government authorities on a timely basis,
risks generally associated with the mining industry, such as economic factors (including future commodity prices, currency fluctuations, energy
prices and general cost escalation), uncertainties related to the development and operation of Hudbay’s projects (including the impact on
project cost and schedule of construction delays and unforeseen risks and other factors beyond the company’s control), depletion of Hudbay’s
reserves, risks related to political or social unrest or change and those in respect of aboriginal and community relations, rights and title claims,
operational risks and hazards, including unanticipated environmental, industrial and geological events and developments and the inability to
insure against all risks, failure of plant, equipment, processes, transportation and other infrastructure to operate as anticipated, compliance with
government and environmental regulations, including permitting requirements and anti-bribery legislation, dependence on key personnel and
employee relations, volatile financial markets that may affect Hudbay’s ability to obtain financing on acceptable terms, uncertainties related to
the geology, continuity, grade and estimates of mineral reserves and resources and the potential for variations in grade and recovery rates,
uncertain costs of reclamation activities, Hudbay’s ability to comply with its pension and other post-retirement obligations, the company’s ability
to abide by the covenants in Hudbay’s debt instruments or other material contracts, tax refunds, hedging transactions, as well as the risks
discussed under the heading “Risk Factors” in this presentation and Hudbay’s most recent Annual Information Form.
Should one or more risk, uncertainty, contingency or other factor materialize or should any factor or assumption prove incorrect, actual results
could vary materially from those expressed or implied in the forward-looking information. Accordingly, you should not place undue reliance on
forward-looking information. Hudbay does not assume any obligation to update or revise any forward-looking information after the date of this
presentation or to explain any material difference between subsequent actual events and any forward-looking information, except as required by
applicable law.
CONSTANCIA PRESENTATION l 4
Cautionary Information (continued)
The scientific and technical information in respect of Hudbay contained in this presentation related to the Constancia project has been prepared by or under the supervision of Cashel Meagher, P.Geo., Hudbay’s Vice President, South America Business Unit. The scientific and technical information related to all other sites and projects of Hudbay contained in this presentation has been prepared by or under the supervision of Robert Carter, P.Eng., Hudbay’s Director, Technical Services. Messrs. Meagher and Carter are Qualified Persons for the purposes of NI 43-101 – Standards of Disclosure for Mineral Projects. (“NI 43-101”). The mineral reserve and resource estimates included in or underlying assumptions referenced in this presentation were prepared in accordance with NI 43-101 and the Canadian Institute on Mining, Metallurgy and Petroleum Standards on Mineral Resources and Reserves: Definitions and Guidelines. Mineral resources that are not mineral reserves do not have demonstrated economic viability. For a description of the key assumptions, parameters and methods used to estimate mineral reserves and resources, as well as data verification procedures and a general discussion of the extent to which the estimates may be affected by any known environmental, permitting, legal, title, taxation, socio-political, marketing or other relevant factors, please see the Technical Reports for each of Hudbay’s properties as filed on SEDAR at www.sedar.com.
The disclosure in this presentation uses mineral resource classification terms and mineral resource estimates that comply with NI 43-101. NI 43-101 establishes standards for all public disclosure a Canadian issuer makes of scientific and technical information concerning mineral projects. Unless otherwise indicated, all reserve and resource estimates contained herein have been prepared in accordance with NI 43-101. These standards differ significantly from the mineral reserve disclosure requirements of the SEC set forth in Industry Guide 7. Consequently, reserve and resource information contained herein is not comparable to similar information that would generally be disclosed by U.S. companies in accordance with the rules of the SEC.
In particular, the SEC’s Industry Guide 7 applies different standards in order to classify mineralization as a reserve. As a result, the definitions of proven and probable reserves used in NI 43-101 differ from the definitions in SEC Industry Guide 7. Under SEC standards, mineralization may not be classified as a “reserve” unless the determination has been made that the mineralization could be economically and legally produced or extracted at the time the reserve determination is made. Among other things, all necessary permits would be required to be in hand or their issuance imminent in order to classify mineralized material as reserves under the SEC standards. Accordingly, mineral reserve estimates referred to herein may not qualify as “reserves” under SEC standards.
In addition, the terms “measured mineral resources,” “indicated mineral resources” and “inferred mineral resources” are used to comply with the reporting standards in Canada. The SEC’s Industry Guide 7 does not recognize mineral resources and U.S. companies are generally not permitted to disclose resources in documents they file with the SEC. Investors are specifically cautioned not to assume that any part or all of the mineral deposits in these categories will ever be converted into SEC defined mineral reserves. Further, “inferred resources” have a great amount of uncertainty as to their existence and as to whether they can be mined legally or economically. Therefore, investors are also cautioned not to assume that all or any part of an inferred resource exists. It cannot be assumed that all or any part of “measured mineral resources,” “indicated mineral resources,” or “inferred mineral resources” will ever be upgraded to a higher category. Investors are cautioned not to assume that any part of the reported “measured mineral resources,” “indicated mineral resources,” or “inferred mineral resources” contained herein is economically or legally mineable. For the above reasons, information contained herein containing descriptions of mineral reserve and resource estimates is not comparable to similar information made public by U.S. companies subject to the reporting and disclosure requirements of the SEC.
1. Project Overview
2. Project Management
3. Mine Operations
4. Human Resources Staffing & Training
5. Corporate Affairs & Social Responsibility
6. Exploration
Appendix
Table of Contents
CONSTANCIA PRESENTATION l 5
1 Project Overview
CONSTANCIA PRESENTATION l 6
CONSTANCIA PRESENTATION l 7
Project Timeline & History
2010 2011 2012 2013 2014 2015
ESIA permit
received
Nov 2010
Note: All timelines are estimates
US$116mm
Constancia pre-
construction
program begins
Mar 2011
Initial resource
announced at
higher grade
Pampacancha
deposit
Apr 2012
Neighbouring
community
agreements
reached
H1 2012
Beneficiation
concession
permit received
Jun 2012
Updated capital
cost estimate
indicates
increase of
~10%
Aug 2013
ESIA Modification
1 approved
Sep 2013
Hudbay’s board
approves
construction of
Constancia
Aug 2012
All critical
path families
resettled
Apr 2014
Pre-stripping
commences
Mar 2014
Powerline
energized
Aug 2014
Hudbay acquires
Constancia
Jul 2011
Expected first
ore production
Q4 2014
Expected
commercial
production
Q2 2015
CONSTANCIA PRESENTATION l 8
Construction Progress
Lima
PERU
Constancia
2013
Over 16 million man-
hours without lost time
accident recently
achieved
Project ~85% complete
as at June 30, 2014
On track for first
production in Q4 2014,
commercial production
in Q2 2015
2014
Location & Infrastructure
Infrastructure & power expected to be available to meet Constancia project schedule
CONSTANCIA PRESENTATION l 9
83km access road from Yauri
> Upgraded for concentrate haulage post
commissioning
Tintaya power substation 70km away
> Construction of power transmission line from Tintaya
complete and was energized in August 2014
> Socabaya to Tintaya 220kV transmission line
upgrade is complete and was energized in April 2014
Rail-head at Imata 150km away
> Pursuing bi-modal transportation solution
~475km from Matarani Port by road
Port access and power supply secured under
10-year contracts
CONSTANCIA PRESENTATION l 10
Key Project Metrics
Ownership 100%
Mine life 22 years
Daily ore throughput 80k tpd
Mine and mill unit cost1,2 US$7.48/tonne
Years 1-51 Years 6-221 Life of Mine1
Avg. annual Cu production3 116k tonnes 71k tonnes 82k tonnes
Cash cost per Cu lb4 US$0.98/lb US$1.37/lb US$1.25/lb
Avg. annual sustaining capital US$80 million US$38 million US$47 million
Source: Hudbay company disclosure
1. LOM as per NI 43-101 Technical Report on the Constancia Project dated October 15, 2012 and subsequent updates to project estimates in public disclosure
2. Combined mine and mill unit operating costs per tonne of ore processed
3. Production is contained metal in concentrate
4. Net of by-products. Includes impact of silver and gold streams. Assumed metal prices per the Silver Wheaton stream agreement are as follows: Gold US$400/oz, Silver US$5.90/oz. Other metal price assumptions
include: Molybdenum 2014-US$12/lb, 2015-US$13/lb, 2016-US$13/lb, LT-US$13.50/lb; Gold 2014-US$1,350/oz, 2015-US$1,325/oz, 2016-US$1,300/oz, 2017-US$1,275/oz, LT-US$1,250/oz. Excludes profit sharing
> The March 2014 reserve update incorporated an expected tailings facility
expansion allowing for the conversion of a portion of the mineral resources into
reserves, resulting in a mine life extension to 22 years (from 16 years)
CONSTANCIA PRESENTATION l 11
Flow Sheet
2 Project Management
CONSTANCIA PRESENTATION l 12
Safety Share
Constancia project has over 30 M man-hours worked with only 13 LTI´s
and has completed over 16 million man-hours since the last LTI
CONSTANCIA PRESENTATION l 13
Lightning Protection at Constancia
Richard Kithil, President, National
Lightning Safety Institute (NLSI)
LIGHTNING PROTECTION
FOR FACILITIES, OPERATIONS &
PERSONNEL
> NLSI Lightning Protection Defenses Template
> Grounding, Bonding & Surge Protection
> Air Terminals, other forms of protection
> Safe Shelter Details
> Alert methods & protocol
Project Summary
Lima
PERU
Constancia
Lima
PERU
Constancia
CONSTANCIA PRESENTATION l 14
Project has US$1.4 billion incurred
and has committed an additional
US$0.2 billion as of June 30, 2014
Highlights:
> Project approximately 85% complete as
at June 30, 2014
> Structures in place for water capture,
2015 dry season
> Mine pre-stripping started in March 2014
> All 4 mills in place with drives; alignment
in progress
> Flotation cells in place, concentrate
filters placed, thickener under
construction
> Power transmission line energized in
August 2014
Orientation from Site Visit
AREA 4
TEMASEK PRESENTATION l 15
1
2
3
4
CONSTANCIA PRESENTATION l 15
External Partners
CONSTANCIA PRESENTATION l 16
Stratcon GyM – Mining Contractor and Major Earth Works
> Established labour force and operating team
> Experience operating in Peru (Toromocho, El Brocal, Marcona, La Arena)
> Constancia earth works responsibilities include: bog dam, TMF East and West,
WRF and ponds, main sediment pond, haul road, construction roads, access
roads, diversion channels, Cunahuiri reservoir
Ausenco – Plant Construction
> Constructed and delivered similar plants in remote locations (Lumwana, Phu
Kham, Cadia East)
> Assembled sizable team in Latin America
Knight Piesold – Engineering
> Detailed engineering design
> Permit modification assistance (environmental compliance)
TEMASEK PRESENTATION l 17
Heavy Civil Works
and Mining
CONSTANCIA PRESENTATION l 17
Heavy Civil Works and Mining Milestones
CONSTANCIA PRESENTATION l 18
> Tailing liner well under way and toe dam in progress
> Water capture initiated Dec 2013 in main sediment pond
> Mine pre stripping started in Mar 2014, on schedule for Q4 start-up
Main sediment pond Pre-stripping activities
Pre-Stripping Progress
CONSTANCIA PRESENTATION l 19
> Approximately 19 million tonnes of
material moved to-date
> Approximately 400k tonnes of ore on
the ROM pad
Month Waste (tons) Ore (tons) Total (tons)
March 531,976 531,976
April 2,357,194 2,357,194
May 3,479,965 3,479,965
June 4,305,408 4,305,408
July 3,848,495 434,205 4,282,700
August 3,779,699 3,779,699
18,302,737 434,205 18,736,942
Total Pre-Strip Requirement 26 Million
Current ore stockpile at ROM pad
Heavy Civil Scope of Work
TEMASEK PRESENTATION l 20
Facilities List • Bog Dam • TMF East • TMF West • WRF and Ponds • Main Sediment Pond • Topsoil Stockpile • Haul Road • Access Roads • Diversion Channels • Landfill Area
CONSTANCIA PRESENTATION l 20
Site Water Management
TEMASEK PRESENTATION l 21
CONSTANCIA PRESENTATION l 21
TEMASEK PRESENTATION l 22
Process Plant
Engineering,
Procurement and
Construction
Management
CONSTANCIA PRESENTATION l 22
Process Plant Construction - Current Status
TEMASEK PRESENTATION l 23
Ma
n-h
ou
rs
Time
CONSTANCIA PRESENTATION l 23
> Engineering is substantially complete and procurement is at 93% complete
> In the primary crusher area, crusher and the modules of the reclaim conveyors to
the grinding area are being completed
> SAG and ball mill shells and heads are 100% assembled, including trunnion
installation, pinion and girth gears, currently under alignment
> In the flotation area, all rougher cells are assembled as well as all cleaning cells
and internal equipment installation
TEMASEK PRESENTATION l 24
Offsite Infrastructure
& Services
CONSTANCIA PRESENTATION l 24
Power
TEMASEK PRESENTATION l 25
CONSTANCIA PRESENTATION l 25
Power Transmission Line
> Engineering and procurement are 100% complete, tie in to high voltage side of
substation was completed in April, tower construction is 100% complete
> Successful negotiations with Glencore Tintaya for ROW agreement
> System was energized in August 2014
Power Supply
> Signed 10-year power purchase contract, with 5 year extension right
> Costs are in-line with expectations
Concentrate Transport
TEMASEK PRESENTATION l 26
CONSTANCIA PRESENTATION l 26
> Route from Constancia to Matarani is
460 kms total
> Proposals have been received and
reviewed 4 transport companies –
trucking firms have lowest rate
> Final contract negotiations underway
and contract expected to be awarded
in Q3 2014
> Service start date of Dec 2014
> Potential for bimodal transportation in
long-term
• Rail head located 150km away at
Imata
Port Services
TEMASEK PRESENTATION l 27
CONSTANCIA PRESENTATION l 27
TISUR – Port Operator
Under concession from the State
Facilities & Expansion plans
TISUR Grain Warehouse A5
> Enclose for concentrate service to
capacity of 25,000 wmt
Expansion Options
> Discussions with Ares warehouse
for addition capacity
TEMASEK PRESENTATION l 28
Plant
Commissioning
CONSTANCIA PRESENTATION l 28
Commissioning Stages
TEMASEK PRESENTATION l 29
Responsibility
Construction Team
C0
Verification of Plant
and Equipment
Verification by the construction team that
the installation of an individual item of
plant or equipment meets the design
intent.
CONSTANCIA PRESENTATION l 29
Commissioning Stages
TEMASEK PRESENTATION l 30
Responsibility
Construction Team
C0
Verification of Plant
and Equipment
Inspection and no-load energisation of an
item of plant or equipment by the
commissioning team to verify
conformance with design.
C1
Dry Commissioning
C0
Checksheets
+ Punch lists
CONSTANCIA PRESENTATION l 30
Commissioning Stages
TEMASEK PRESENTATION l 31
Responsibility
Construction Team
C0
Verification of Plant
and Equipment
Testing of an individual or group of
integrated items of plant or equipment
under benign load (air or water) ultimately
demonstrating stable operation of a
process commissioning module under this
load.
C1
Dry Commissioning
C2
Wet Commissioning
C0
Checksheets
+ Punch lists
C1
Checksheets
+ Punch lists
CONSTANCIA PRESENTATION l 31
Commissioning Stages
Responsibility
Construction Team
Commissioning Team
C0
Verification of Plant
and Equipment
Initial introduction of ore and process
fluids and testing of an individual or group
of integrated process commissioning
modules to demonstrate stable operation
at pre-determined operation parameters.
C1
Dry Commissioning
C2
Wet Commissioning
C3
Ore Commissioning
C0
Checksheets
+ Punch lists
C1
Checksheets
+ Punch lists
C2 Checksheets +
Practical Completion
Certificate
CONSTANCIA PRESENTATION l 32
Commissioning Stages
Responsibility
Construction Team
Commissioning Team
Client Operation Team
C0
Verification of Plant
and Equipment
Completion of all commissioning
activities including preparation of
a Commissioning Closeout
Report and handover of agreed
commissioning documentation
deliverables to the Client
C1
Dry Commissioning
C2
Wet Commissioning
C3
Ore Commissioning
C4
Performance
Verification
C5
Area Acceptance
C6
Commissioning
Closeout
C0
Checksheets
+ Punch lists
C1
Checksheets
+ Punch lists
C2 Checksheets +
Practical Completion
Certificate
CONSTANCIA PRESENTATION l 33
Projected Ramp-up vs. Antapaccay
> The near-by Antapaccay mine recently commenced production and has similar
size and flowsheet to Constancia (direct comparable)
> Projected 9-month ramp-up at Constancia is more conservative than actual ramp-
up achieved at Antapaccay
CONSTANCIA PRESENTATION l 34
100
929292
7979
66
66
45
0
90
104104
63
8692
85
48
24
00
20
40
60
80
100
120
(% D
esig
n)
Month
Ore Grinding Ramp-up
CONSTANCIA
ANTAPACCAY
Project Closure Planning – De-mobilization
CONSTANCIA PRESENTATION l 35
> Effective and efficient handover of documentation – data > information >
knowledge
> Closeout of punch lists – defects, warranty issues, early life failures and incomplete
work
> Commissioning and operational ramp-up – roles and responsibilities
> Multiple systems in commissioning, early operations complexity – steep learning
curve
> Post contract support
> Integration with Hudbay’s IT systems and ERP
> Progressive closeout
> Asset protection – security assessment and implementation
> Post closeout reviews
3 Mine Operations
CONSTANCIA PRESENTATION l 36
Annual Tonnage Movement
0
10,000,000
20,000,000
30,000,000
40,000,000
50,000,000
60,000,000
70,000,000
80,000,000
2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036
Annual Total Movement
Crusher Waste Dump Rehandle
CONSTANCIA PRESENTATION l 37
To
nn
ag
e
Constancia Project - General Flowsheet of Haulage Network
Hi Zn SP
Constancia Pit
Pampacancha Pit
MG SPHG SP
WRF PAG/NAG
NAG SP
Legend
Direct Movement
Rehandle Movement
Aternative: Pampacancha as Backfill
Process Plant
Copper Concentrate
Molybdenum Concentrate PORT
4.4 Km2.9 Km
2.5 Km 2.5 Km 2.5 Km
7.0 Km6.6 Km
4.5 Km
5.0 Km
5.6Km
9.3 Km
6.7Km
3.3 Km
2.4 Km2.4 Km
2.4 Km
Haulage Network
CONSTANCIA PRESENTATION l 38
Mine Equipment
0
10
20
30
40
50
60
70
80
90
0
5
10
15
20
25
30
35
40
2014 2015 2016 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 2027 2028 2029 2030 2031 2032 2033 2034 2035 2036
Mine Equipment Requirement
Truck - CAT 793F Drill Rig - Pit Viper 271 - RCS Shovel, Hirachi EX5600 - 6 Loader - CAT 994H P13DEC, Tonnage Movement, Mt
T
o
n
n
a
g
e
x
m
i
l
l
o
n
U
n
i
t
s
o
f
E
q
u
i
p
m
e
n
t
CONSTANCIA PRESENTATION l 39
1. Mine Planning – MTP (2014-2015)
CONSTANCIA PRESENTATION l 40
Mine Operation – Drilling & Blasting
• Burden (m): 8
• Spacing (m): 9
• Stemming (m): 8.5
• Blasting projects to date: 14
• Blasted holes to date: 1,614
• Tonnage blasted to date: 4,474,852 t
• Types of blast holes: Production ,buffer and pre-splitting
• Explosives used: HA28, HA37, HA46, HA64 (depending on
the presence of water and the strength of the rock)
• Powder factor(explosive kg/break tonnage): 0.14
Pit Viper 271
• Average blast
hole length (m):
15.8
• Blast hole
diameter (inch): 9
7/8
• Instant Drilling
Speed (m/h): 81
• Average Drilling
Speed (m/h): 55
• Mechanical
Availability (%):
95
• Utilization (%): 86
CONSTANCIA PRESENTATION l 41
Mine Operation - Loading
Hitachi EX-5600
• Bucket capacity (m3): 27
• Equipment performance (tph):
3,364
• Mechanical Availability (%): 94
• Utilization (%): 95
CAT 994 H
• Bucket Capacity (m3): 19
• Equipment performance (tph):
1,764
• Mechanical Availability (%): 94
• Utilization (%): 97
CONSTANCIA PRESENTATION l 42
Mine Operation - Hauling
CAT 793 F
• Max gradient (%): 10
• Rolling Resistance (%): 2-4
• Payload (t): 227
• Equipment performance (tph):
510
• Mechanical Availability (%): 86
• Utilization (%): 85
CONSTANCIA PRESENTATION l 43
Mine Geology: Ore Control Routine – Sampling &
Logging BH
Blasthole Sampling Blasthole logging
Pit Face Mapping Database Validation
CONSTANCIA PRESENTATION l 44
Weekly Plan – Polygons by Destination
(Bench 4335- 4350)
MATPS: Pre-Stripping Material
4335
4350
CONSTANCIA PRESENTATION l 45
Mine Maintenance Reconciliation
MIÉ JUE VIE SÁB DOM LUN MAR
20 21 22 23 24 25 26
EQUIPOS DE OPERACIÓN
1 PE-C0001 250 12 Horas 8 Horas2 PE-C0002 125 1 Horas 1.5 Horas6 CF-C0001 125 1 Horas 0 Horas7 PH-C0001 125 6 Horas 10 Horas8 PH-C0002 125 2 Horas 2.5 Horas
12 CM-C0001 125 1 Horas 1 Horas13 CM-C0002 125 1 Horas 0 Horas14 CM-C0003 250 8 Horas 0 Horas15 CM-C0004 2000 24 Horas 19.7 Horask CM-C0005 125 1 Horas 1 Horas
18 CM-C0007 125 1 Horas 1 Horas CM-C0008 125 1 Horas 0 Horas
22 CM-C0011 250 12 Horas 16.7 Horas23 CM-C0012 2000 24 Horas 24.5 Horas24 CM-C0013 500 8 Horas 11.5 Horas25 CM-C0014 500 10 Horas 19 Horas26 CM-C0015 125 1 Horas 1 Horas28 CM-C0017 125 1 Horas 0 Horas29 CM-C0018 125 1 Horas 0 Horas35 TO-C0001 125 1 Horas 1.6 Horas36 TO-C0002 125 1 Horas 1 Horas37 TR-C0001 125 1 Horas 0 Horas38 MO-C0001 125 1 Horas 0 Horas
MO-C0002 250 5 Horas 8.5 Horas
3 2 1 1 2 2 3 125 Horas 128.5 Horas 103% TIEMPO (Hrs)
3 3 3 3 4 4 4 24 16 67% CANT. (PMs Ejecutados)
21.0 26.0 33.0 13.0 2.0 2.0 2.0 125 Horas
HORAS DE
INTERVENCIONHORAS REALES
OK
OKse aprovecha euna parada correctiva
Se reprograma por horas de trabajoDemora en la prueba de hermeticidad
OKDemora en la evaluacion de parametros
Equipo en stand by por produccion se re-Se aprovecha el stand by del equipo
OK
DETALLE DE LAS DESVIACIONES
Se reprograma el cambio de parabrisas OK
TODOS
ItemCODIGO EQUIPO
AMT
OKSe reprograma por horas de trabajo
Inoperativo por recarga del sistema contra
Demoras en las pruebas de OK
Se reprograma por horas de trabajoInoperativo por recarga del sistema contra
Se reprograma por horas de trabajoSe aprovecha el stand by del equipo
OKOK
Se reprograma por horas de trabajo
CONSTANCIA PRESENTATION l 46
Mine Maintenance KPI´s
CONSTANCIA PRESENTATION l 47
3. G&H: Geotechnical Work
A
Section A–A:
View of
achieved angles
versus design
angles. The
achieved angles
are 60°.
PIT OPERATIONAL WORK NAG OPERATIONAL WORK
The current discharge
on the WRF – NAG is
been developed to
form the final lifts 4140
and 4160, and to form
the lift 4180.
Panoramic view of bench 4425 – 4410, Constancia Pit.
CONSTANCIA PRESENTATION l 48
Water Management Plan
Panoramic View Actual - WRF
CONSTANCIA PRESENTATION l 49
4 Human Resources Staffing & Training
CONSTANCIA PRESENTATION l 50
Operations Management
Operations DirectorEric Caba
23 yrs / Metallurgical Engineer
Process Plant Manager
Hugo Granados35 yrs/ Metallurgical
Engineer
Mine Manager
John Gutierrez40 yrs / Mining
Technical Services ManagerJavier Toro
17 yrs/ Mining Engineer
Health & SafetyManager
Felix Galvez12 yrs / Work
Relations
Logistics &Admin Manager
John Cederberg24 yrs / Public
Accountant
HR Superintendent
Jose Bandini19 yrs / Bussiness
Administration
EnvironmentalManager
Julio Roncal21 yrs / Civil Engineer
Total HC 269
Operations
Management
Technical
Services
Process
Plant Mine HSE
Logistics &
Administration
Other
Functional
Support
Finance HR
Operations 2 26 149 3 17 37 16 10 9
CONSTANCIA PRESENTATION l 51
Production Superintendent
Oscar Alvarez27 yrs/ Chemical Engineer
Electrical/Instrumental Superintendent
Carlos Herrera32 yrs / Mechanical &
Electrical Engineer
Metallurgical SuperintendentMarcial Medina
13 yrs / Metallurgical
Engineer
Mechanical Maintenance SuperintendentManuel Sanchez
30 yrs / Mechanical Eng
Process Plant Manager
Hugo Granados35 yrs/ Metallurgical
Engineer
Administrative Assistant
Vacant
OperationsDirectorEric Caba
23 yrs / Metallurgical Engineer
TailingSuperintendent
Vacant
Process Plant
Total HC 149
Admin
Ope
Maintenance Metallurgical Electrical /
Instrumental
Production
Tailing
Operations 2 41 16 32 42 16
CONSTANCIA PRESENTATION l 52
“The objective is to have the right person for the right
job at the right time, and well trained”
TRAINING • Train the Trainers:
train staff in safety,
technical and
leadership
competences.
• Training for Engineers,
Technicians
• Training for Workers &
Workers from
Communities
STAFFING FOR
SAP • Recruit 6
colleagues for SAP
Maintenance
• Interaction with
Ausenco-Rylson in
SAP maintenance
STAFFING FOR
COMMISSIONING • Recruit 27 colleagues to
support the pre-
commissioning and
commissioning phase.
• A total of 33 colleagues are
involved in Commissioning.
READY TO START • 100% of positions
duly fit
• 100% of positions
duly trained.
JAN
2014
NOV 2014
Master Plan for Staffing & Training
STAFFING FOR
OPERATIONS Recruit colleagues for
Operations phase,
based on recruitment
and training planning.
CONSTANCIA PRESENTATION l 53
28 28 28 28 28 28 28 28 28
0
59 70 76
89 91 93 105 109
134
195 250
11 6
13 2 2
12 4
25
61
27
19
98 104
117 119 121
133 137
162
223
250
269
0
20
40
60
80
100
120
140
160
180
200
220
240
260
280
Jan '14 P0
Feb '14 P0a
Mar '14 P1
Apr '14 P2
May '14 P3
Jun '14 P4
Jul '14 P5
Aug '14 P6
Sep '14 P7
Oct '14 P8 y P8-C
Nov '14 P9
HeadCount Planning Forecast September 2014
Current HC Lima Current HC Campsite # of HC to Recruit Total HC
Workforce Planning Forecast
CONSTANCIA PRESENTATION l 54
CONSTANCIA PRESENTATION l 55
Manpower will significantly decline over the coming months as
contractors are being demobilized
Total Site Staffing 2014 - Including Contractors
-
1,000
2,000
3,000
4,000
5,000
6,000
Total Site Staffing
Recruitment Schedule 2014
(*) Priority P8-C: 17 positions that will be filled by communities’ members, whom were trained by CETEMIN.
Area / Positions Priority
Start
Recruitment
Process
Effective Hire
Month
# of
Colleagues to
Recruit
Technical Services & Commissioning P0 Nov-13 Jan-14 11
Superintendent / Commissioning P0a Dec-13 Feb-14 6
SAP & Commissioning P1 Dec-13 Mar-14 13
Supervisors P2 Jan-14 Apr-14 2
Superintendent / Supervisor P3 Jan-14 May-14 2
Supervisors / Senior / Auxiliary / Commissioning P4 Feb-14 Jun-14 12
Managers / Technicians P5 Mar-14 Jul-14 4
Supervisors / Senior / Technicians / Auxiliaries P6 Mar-14 Aug-14 25
Supervisors / Operators P7 Apr-14 Sep-14 61
Superintendent / Seniors / Operators P8 y P8-C (*) Apr-14 Oct-14 27
Administratives P9 Jun-14 Nov-14 19
182
Current Positions for Operations - Support Areas 87
269Total HC
Total to Recruit
75
CONSTANCIA PRESENTATION l 56
Ensure the successful of the start up of the plant process, training our
colleagues since the beginning, using our own resources, their knowledge, and
giving the opportunity to develop our people, and creating our own Hudbay
mind-set
> Focus in safety, technical & leadership skills:
• Safety DS 055-2010 (ISEM / IGH / IPEN)
• Filters/ Couriers/ Thickeners / Cells (OUTOTEC)
• Crusher & Mills / Leadership Competencies/ Train of Trainers Simulator
(TECSUP)
• Simulator (ANDRITZ / TECSUP)
• DCS (SIEMENS)
• Mill & Crusher (FLSMIDTH)
> Tools
• Training presentation
• Manuals
• Simulator
• On the job training in the commissioning phase
Training Strategy
CONSTANCIA PRESENTATION l 57
Jan - May June July Aug Sep Oct Nov Training for
Commissioning Siemens Electrical /
Instrumental Lima
Training for Workers & Community Workers
Sep '14
Process Plant Construction Completed
Hire for Commissioning
Phase (2)
Hire for Commissioning
& SAP Maintenance
Phase (3)
Training for Engineers & Technicians
Aug - Sep'14
Hire for Commissioning
& SAP Maintenance
Phase (13)
Hire for Commissioning
Phase (14)
CETEMIN Training Nov ‘13 – May ’14
To fill 17 positions:
2 Mechanical Workshop
6 Samplers operators
6 Tailing Dump Operator 3 Crusher Conveyor Operator
Training Schedule
Start the hiring for Operations (115), based on the schedule
Training for Commissioning Siemens
Electrical / Instrumental Site
Aug – Sep ‘14
Tecsup Supervisors
Arequipa Jul – Aug ‘14
Mills & Primary Crusher FLSmidth
Supervisors / Engineers Arequipa
Simulator - Tecsup Supervisors / Ctrl Room Ope
Site
Train the Trainers
Jul - Aug ‘14
Training under Scope of Work of the PO
Outotec Supervisors
Lima Sep – Oct ‘14
Done
Training in Gold Fields La Cima
Aug - Sep ‘14
CONSTANCIA PRESENTATION l 58
5 Corporate Affairs & Social
Responsibility
CONSTANCIA PRESENTATION l 59
Permitting (1/2)
CONSTRUCTION
• PERMITS FOR CONSTRUCTION ARE IN PLACE:
• Earthmoving activities, process plant and ancillary facilities, TMF, camps,
MSP, WRF and collection and retention ponds, NAG stockpile, topsoil
stockpiles, sediment ponds, haul and access roads and Cunahuiri
reservoir.
• Other permits obtained: authorizations to use and collect water, discharge
permits, fuel permits, water treatment plant permits, permits for power
generation and environmental certifications.
OPERATIONS
• PERMITS TO START PRE-STRIPPING AND CONSTANCIA
DEPOSIT EXPLOITATION ARE IN PLACE
• Mine permit and its amendment, certificate of mine operator, authorization
to use explosives and permanent magazines and warehouses.
• PENDING CRITICAL PERMITS FOR OPERATING
PROCESS PLANT
• Underground Water License Stage 4 / FD: Late Sept-2014
• Surface Water License Stage 4 / FD: Oct-2014
• Operation license for TMF 4050 and Process Plant line 2 / FD: Nov-2014
• Operation license for Process Plant line 1 & moly plant / FD: Jan-2015
CONSTANCIA PRESENTATION l 60
76%
10%
10%
4%
Obtained
Pending (not required for operation)
Pending (required for operations - not critical)
Pending (required for operations - critical)
Permitting (2/2)
RISK DESCRIPTION / ACTIONS
CUNAHUIRI
CONTINGENCY
PLAN
• DUE TO LACK OF ACCESS TO ICHUNI VALLEY, A CONTINGENCY PLAN (CP) WAS DEVELOPED IN ORDER TO MITIGATE the lack of the Cunahuiri reservoir and the possibility to capture water therein for operations and compensation.
• CP poses a risk because it changes compensation commitment and water balance reflected in other permits.
• In order to address this change, Hudbay is exploring the possibility to prepare a second environmental
technical report or to include the CP during the round of observations of the ESIA´s second amendment.
• Likewise, in order to allow construction of infrastructure comprised in the CP (specially NC4 channel), Hudbay has included the CP within the surface water license (Stages 2 and 3). It was approved on April, 2014.
CRITICAL
PERMITS TIED TO
CONSTRUCTION
SCHEDULE
• SOME PERMITS REQUIRE INSPECTIONS TO BE GRANTED. This means that the corresponding facility must be completed and ready to operate in order to be inspected by the authority.
• This poses a risk in the case of the Surface water license stage 4 and the Process plant operation licenses.
• ANY DELAY IN CONSTRUCTION ALSO DELAYS THESE PERMITS.
CONSTANCIA PRESENTATION l 61
Resettlement: Ichuni
NEGOTIATION
PROCESS
# of
families
Public deed signed 34
In negotiation 2
Total: 36
HOUSING STATUS # of
houses
Delivered-To-Owner 32
Pending Delivery 0
Total: 32
CONSTANCIA PRESENTATION l 62
Local Employment and Procurement
CONSTANCIA PRESENTATION l 63
LABOR FORCE
˃ 727 workers from direct & indirect area of Influence
CONTRACT OF RENTAL
EQUIPMENT BY COMMUNITIES
˃ Chiloroya: 223
˃ Uchucarco: 164
FOOD SUPPLIERS IN OPERATION CONTRACT SERVICE
˃ 9 from Uchucarco
˃ 4 from Chilloroya
2013 Business Invoicing to Project
Chilloroya Uchuccarcco
S/. 30,703,201
S/. 10,022,381
S/. 2,988,900 S/. 2,443,488
Rent a Car Food Services
Rent a Car- Equipment and Heavy Equipment
CONSTANCIA PRESENTATION l 64
2014 Business Invoicing to Project (1/2)
S/. 0
S/. 1,000,000
S/. 2,000,000
S/. 3,000,000
S/. 4,000,000
S/. 5,000,000
S/. 6,000,000
Jan Feb Mar Apr
Rent a Car- Equipment and Heavy Equipment
Chilloroya Uchuccarcco
CONSTANCIA PRESENTATION l 65
2014 Business Invoicing to Project (2/2)
S/. 0
S/. 50,000
S/. 100,000
S/. 150,000
S/. 200,000
S/. 250,000
S/. 300,000
S/. 350,000
S/. 400,000
S/. 450,000
Jan Feb Mar Apr May Jun
Food Services
Chilloroya Uchuccarcco
CONSTANCIA PRESENTATION l 66
Demobilization
637 local workers have been
demobilized (January – August 2014)
Owned RentedUn-
registeredExternal TOTAL
Heavy
equipment9 16 7 77 109
Light
equipment22 10 7 34 73
Machinery-
yellow line5 4 4 25 38
EQUIPMENT AND MACHINERY DEMOBILIZED
CONSTANCIA PRESENTATION l 67
Grievance Process
CONSTANCIA PRESENTATION l 68
Closed case
92%
Closed/ Permanent monitoring
3%
Processing
5%
Grievance Management Count of status (percentage)
Grand Total: 337
76
52 209
Risk of Harm Number of complaints and grievances
With Cusco Regional Government and Provincial Municipality of Chumbivilcas
To finance the new Hospital of Chumbivilcas’ feasibility studies
With District of Chamaca
To finance three projects approved as a conclusion of the Dialogue &
Development Roundtable
With District of Velille
To support the project “Sierra Productiva” (agricultural sector)
With District of Livitaca
To co - finance the improvement and expansion of the service of basic sanitation,
together with the district municipality and the community of Chilloroya, as well as
to equip the Technologic Institute of Livitaca
Agreements: Local & Regional Governments
CONSTANCIA PRESENTATION l 69
Ministry of Development & Social Inclusion, and Cusco Regional Government
To fully finance the “Development of Competences for Young People in Chumbivilcas” project, to support
them to improve their capacities in the transition stage between secondary education and insertion into
the productive world
Ministry of Energy & Mines
To support the delivery of kitchens that use liquefied petroleum gas, and to support the distribution and
installation of photovoltaic systems -solar panels- in our area of influence
Ministry of Labor
To cooperate in training, bonding and employability of the vulnerable population in our area of influence, in
order to extend the coverage of the State on employment, employability and entrepreneurship
Ministry of Agriculture
To develop the program of agricultural development in Chumbivilcas, seeking sustainable development
promoting and boosting the economy of its inhabitants through the use of modernized irrigation systems,
cultivation of pastures, breeding of livestock (cattle and sheep), and implementation of dairy plants
Agreements with National Government
CONSTANCIA PRESENTATION l 70
Asociación Vida Peru
To manage donations of medicines, medical equipment, educational materials and other goods, and
to finance all the logistics that is necessary for the distribution of these goods among the poorest
health centers and communities of our area of influence
Universidad Nacional San Antonio Abad del Cusco (UNSAAC)
To jointly develop projects for education and training in cultural and productive research in the area
of influence of Constancia, and implement the Hudbay scholarship, the “classroom Hudbay", and
the International Centre for the mining production and regional development
Universidad Nacional San Agustín de Arequipa” (UNSA)
To develop joint education and training projects with the participation and resources that both
institutions have to promote professional development, infrastructure improvement, and knowledge
exchange, and implement the Hudbay scholarship and the “classroom Hudbay"
Others
In addition to the above mentioned agreements, periodically we carry out medical campaigns and
solid waste collection campaigns for the benefit of the population of adjacent districts and
communities
Agreements with Other Institutions
CONSTANCIA PRESENTATION l 71
6 Exploration
CONSTANCIA PRESENTATION l 72
Prolific Belt Provides Opportunities
CONSTANCIA PRESENTATION l 73
Aeromagnetic Survey Map
• Total Cost: $ 582,194
• Time: 26 days
• Area-Km2: 3,197.50
• Line-Km: 7,219.20
CONSTANCIA PRESENTATION l 74
Appendix
CONSTANCIA PRESENTATION l 75
Current Schedule
Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4
Permitting
Front End Engineering Design
Construction Camp
Procurement
Community Agreements
Board Approval
Power Line
TMF and WRF
Plant
Commissioning and Ramp Up
2011 2012 2013 2014 2015
Mine Permit
Commercial
Production Q2 2015
CONSTANCIA PRESENTATION l 76
Access Road Map
CONSTANCIA PRESENTATION l 77
Hudbay access road
Las Bambas access road
Peru Reserves Overview
Constancia Mineral Reserves
Category Ore (M tonnes) Cu (%) Mo (g/t) Au (g/t) Ag (g/t)
Proven 483 0.32 93 0.040 3.04
Probable 94 0.22 61 0.036 2.77
Pampacancha Mineral Reserves
Category Ore (M tonnes) Cu (%) Mo (g/t) Au (g/t) Ag (g/t)
Proven 23 0.52 142 0.298 4.28
Probable 20 0.44 159 0.252 3.74
As at January 1, 2014
Total Mineral Reserves
Category Ore (M tonnes) Cu (%) Mo (g/t) Au (g/t) Ag (g/t)
Total Proven 506 0.33 95 0.052 3.09
Total Probable 114 0.26 78 0.074 2.94
Total Reserves 620 0.32 92 0.056 3.07
Note: totals may not add up correctly due to rounding
CONSTANCIA PRESENTATION l 78
Peru Resources Overview
Constancia Mineral Resources
Category M (tonnes) Cu (%) Mo (g/t) Au (g/t) Ag (g/t)
Measured 68 0.22 59 0.036 2.17
Indicated 293 0.20 58 0.033 1.96
Inferred 200 0.19 51 0.031 1.86
Pampacancha Mineral Resources
Category M (tonnes) Cu (%) Mo (g/t) Au (g/t) Ag (g/t)
Measured 5 0.41 69 0.243 5.46
Indicated 6 0.34 98 0.211 4.68
Total Mineral Resources
Category M (tonnes) Cu (%) Mo (g/t) Au (g/t) Ag (g/t)
Measured + Indicated 372 0.20 59 0.039 2.09
Inferred 200 0.19 51 0.031 1.86
As at September 30, 2013
Note: totals may not add up correctly due to rounding
CONSTANCIA PRESENTATION l 79
Peru Reserves and Resources Information
For additional details relating to the estimates of mineral reserves and resources at the Constancia project, including data verification and
quality assurance/quality control processes refer to “The Constancia Project, National Instrument 43-101 Technical Report” as filed on
SEDAR by Hudbay on November 6, 2012.
The Constancia and Pampacancha mineral reserves are based on a Peruvian Sole: US Dollar exchange rate of 2.85:1 and the following long
term metals prices: copper price of US$3.00 per pound; silver price of US$25.00 per ounce; gold price of US$1,250.00 per ounce; and
molybdenum price of US$13.50 per pound.
The Constancia and Pampacancha mineral resources correspond to a resources pit shell. A pit optimization to delimit the portion of the block
model having reasonable prospects for economic extraction was performed.
The Constancia resource pit consists of a non-operational pit of Measured, Indicated and Inferred resources diluted to a 10x10x15m full
block size using a 0.12% copper cut-off based on a copper price of US$2.88 per pound and a molybdenum price of US$16.00 per pound,
copper recovery of 89%, molybdenum recovery of 60%, processing costs of US$5.50 per tonne and mining costs of US$1.30 per tonne.
The Pampacancha resource pit consists of a non-operational pit of Measured, Indicated and Inferred resources diluted to a 10x10x15m full
block size using a 0.1% copper cut-off based on a copper price of US$3.00 per pound, a molybdenum price of US$13.50 per pound, silver
price of US$25.00 per ounce, gold price of US$1,250 per ounce, copper recovery of 85%, molybdenum recovery of 40%, gold and silver
recovery of 65%; processing costs of US$4.72 per tonne and mining costs of US$1.90 per tonne.
The primary consideration to accommodate the increased Constancia mineral reserve in the Constancia life of mine plan (“LOM”) was the
confirmation through pre-feasibility investigation to increase the tailings dam height to accommodate this extra tonnage and the waste rock
facility configuration. The resulting LOM has increased to 22 years from 16 years. In this process some of the major cost components have
been updated to reflect some known actual costs such as energy, fuel, concentrate transport and port charges. The resulting change is an
average cost of US$0.72 per pound of copper produced net of by product credits from a previously disclosed US$0.66 per pound of copper
in the first full five years of production. Contained copper metal in concentrate is expected to average 116,000 tonnes per year over the first
five full years versus 118,000 tonnes as previously disclosed. Over the remaining years, the cost per pound of copper net of by product
credits has increased to US$1.14 per pound from US$1.11 per pound; and the contained copper metal in concentrate is expected to average
67,000 tonnes per year versus 77,000 tonnes per year as previously disclosed. The cost per pound of copper net of by product credits does
not include the impact of the precious metals streaming transactions.
Measured and indicated mineral resources were estimated in house. The process includes determination of the integrity and validation of the
data collected, including confirmation of specific gravity, assay results and methods of data recording. The process also includes determining
the appropriate geological model, selection of data and the application of statistical models including probability plots to establish continuity
and model validation.
CONSTANCIA PRESENTATION l 80
Precious Metals Stream Overview
US$750 million in upfront deposit payments from Silver Wheaton for delivery of:
100% of payable gold and silver from 777 mine until the end of 2016;
and 50% of payable gold and 100% of payable silver thereafter for the remainder of
life of mine
100% of payable silver from Constancia project
Along with upfront payments, Hudbay will receive US$400 per ounce for gold and
US$5.90 per ounce of silver1
Additional US$135 million deposit payment from Silver Wheaton against
delivery of:
50% of payable gold from the Constancia project
In addition to the deposit payment, Hudbay will receive the lesser of the market
price and US$400 per ounce for gold delivered to Silver Wheaton2
Precious metals stream transaction preserves precious metals upside potential
for Hudbay shareholders
Precious metals production from Lalor excluded
Excludes land package outside of Constancia and Pampacancha, including
Chilloroya
1Subject to 1% annual escalation starting 2015 2 Subject to 1% annual escalation starting 2016
CONSTANCIA PRESENTATION l 81
ACCORDING TO PLAN
CONSTANCIA MINE SITE VISIT
September 2014