confined masonry training pakistan

Upload: abedinz

Post on 29-May-2018

232 views

Category:

Documents


1 download

TRANSCRIPT

  • 8/9/2019 Confined Masonry Training Pakistan

    1/31

    13 August 2006 1

    SDC

    Confined masonry

    Confined masonrySDC

    Lesson prepared by the Swiss Agency for Development and Cooperation for thetrainings at the Housing Reconstruction Centres Ballakot and Battagram

    13 August 2006 2

    SDC

    Confined masonry

    DefinitionConfined Masonry is a construction system

    where the walls are built first, and the

    columns and beams are poured inafterwards to enclose (confine) the wall.

  • 8/9/2019 Confined Masonry Training Pakistan

    2/31

    13 August 2006 3

    SDC

    Confined masonry

    Concept

    The walls are tieddown to the foundation.

    The ties work like a string around a parcel.

    13 August 2006 4

    SDC

    Confined masonry

    Difference with RC frames

    Confined Masonry

    Walls first

    Concrete later

    Reinforced Concrete Frame

    Concrete first

    Walls later

  • 8/9/2019 Confined Masonry Training Pakistan

    3/31

    13 August 2006 5

    SDC

    Confined masonry

    Difference with RC frames

    Confined Masonry

    Walls ensure rigidity

    Reinforced Concrete Frame

    Column beam connectionsensure rigidity

    Straightforwardtransmission of efforts

    Complicatedtransmission of efforts

    13 August 2006 6

    SDC

    Confined masonry

    Difference with RC frames

    Confined Masonry

    Walls are anchored to theframes through indentation.

    (Additional re-bars willimprove anchoring)

    Reinforced Concrete Frame

    Walls are usually notanchored to the frames and

    will fall out.

    Later anchoring of walls canbe difficult

  • 8/9/2019 Confined Masonry Training Pakistan

    4/31

    13 August 2006 7

    SDC

    Confined masonry

    Difference with RC frames

    Confined Masonry Reinforced Concrete Frame

    All efforts go through thebeam-column connection.

    If they are badly done,they break.

    Concrete goes intothe indentation of

    the brick wall

    13 August 2006 8

    SDC

    Confined masonry

    Summing up

    Confined Masonry

    Its the walls that do the work.

    Thats why they are calledload bearing walls.

    Reinforced Concrete Frame

    Its the columns and beams that

    do the work.

    Walls are only infills.

    From here on well talk about

    load bearing walls made withthe confined masonry system.

  • 8/9/2019 Confined Masonry Training Pakistan

    5/31

    13 August 2006 9

    SDC

    Confined masonry

    (the walls shown here are not confined)

    Walls

    13 August 2006 10

    SDC

    Confined masonry

    Walls: why do we need them

    A building needs walls for

    1. Protection against climate, view, intruders, etc.

    +When we talk about load bearing walls, they will

    2. Carry the roof and/or upper floor (vertical loads)

    +

    When we talk about earthquakes, they will also3. Carry the lateral pushes (horizontal loads)

  • 8/9/2019 Confined Masonry Training Pakistan

    6/31

    13 August 2006 11

    SDC

    Confined masonry

    Load bearing walls

    They can be made out of:

    Bricks Stone

    Cement blocks

    Most importantly, they must be strong. Water the bricks or blocks before use

    Fill all joints (horizontal and vertical with mortar) Use the right mixture for the mortar (1 bucket of

    cement for 5 buckets of clean and rough sand)

    + cement or cement/lime mortar

    + reinforced concrete confinements

    13 August 2006 12

    SDC

    Confined masonry

    Load bearing walls

    All load bearing walls must be confined.

    or

    All confined walls are load bearing.

  • 8/9/2019 Confined Masonry Training Pakistan

    7/31

    13 August 2006 13

    SDC

    Confined masonry

    Earthquake resistance

    When we talk earthquake resistance, we areparticularly interested in the capacity of a wall towithstand horizontal loads.

    Confined walls work also for horizontal loads.

    Horizontal load

    Horizontal load

    13 August 2006 14

    SDC

    Confined masonry

    Horizontal loads

    In an earthquake the groundmoves sideward. Thats likepushing the roof. The walls musthelp to resist this horizontal load.

    A serious earthquake (0.35 g) hasthe same effect on a house astilting it at an angle of 20.5degrees. Thats why walls mustbe strong.

    20.5

  • 8/9/2019 Confined Masonry Training Pakistan

    8/31

    13 August 2006 15

    SDC

    Confined masonry

    Distribution of wallsThe earthquake resistance of ahouse is much better, if least two

    strong walls without openings(called shear walls) are placed ineach direction.

    These shear wallsmust beplaced as far away from each

    other as possible.

    Special casewith walls inthe centre

    13 August 2006 16

    SDC

    Confined masonry

    Distribution of walls

    The shear wallsmust be placed

    symmetrically and as far awayfrom each other as possible toavoid rotation.

  • 8/9/2019 Confined Masonry Training Pakistan

    9/31

    13 August 2006 17

    SDC

    Confined masonry

    Shear walls

    Shear walls cannot have any openings and no slits forpipes!

    Shear walls should ideally be as long as they are high.

    Minimum length should be 2/3 of their height.

    13 August 2006 18

    SDC

    Confined masonry

    Shear walls

    Shear walls should not be higher than 8 feet.

    If the wall is higher, an intermediate bond beam must beintroduced at 8 feet.

  • 8/9/2019 Confined Masonry Training Pakistan

    10/31

    13 August 2006 19

    SDC

    Confined masonry

    Shear walls

    The total surface on the ground of

    all shear walls (L x B) in the samedirection must be between 1.0%and 1.4% of the roof surface (with2 floors, add up each floor),according to the soil.

    Example:

    If you roof surface is 400 sqft, thetotal shear wall surface touchingthe ground must be 4 to 5.6 sqft(i.e. all shear walls added up)

    1.4%Loose sandsoft clay

    Soft of loose

    1.2%Hard clayishsand

    Intermediate

    1.0%RockGravel

    Hard

    Min. wallsurface onground

    DescriptionType of soil

    Blondet 2005

    13 August 2006 20

    SDC

    Confined masonry

    Shear wallsExample: Total surface of shear walls on the ground =

    1.0 to 1.4% of roof surface in this direction.

    The same calculation must be repeated for the otherdirection.

    Blondet 2005

  • 8/9/2019 Confined Masonry Training Pakistan

    11/31

    13 August 2006 21

    SDC

    Confined masonry

    Construction details

    Foundation

    Plinth beam

    Walls

    Columns

    Bond beam

    Roof slab

    13 August 2006 22

    SDC

    Confined masonry

    Construction details

    Step by step 1. Column reinforcements

    2. Foundations

    3. Plinth beam4. Walls

    5. Doors and windows

    6. Bond beam

    7. Roof slab8. Extensions

  • 8/9/2019 Confined Masonry Training Pakistan

    12/31

    13 August 2006 23

    SDC

    Confined masonry

    Column reinforcements

    General rules

    1

    3

    Alternateposition of hooks

    Bend hooks at45 degrees

    All rebars must becovered by at least1 inch of concrete

    Always use steel barswith ridges (smoothrebars may only beused for stirrups)

    13 August 2006 24

    SDC

    Confined masonry

    ColumnreinforcementsPrepare columns

    reinforcements:

    Through plinth and bondbeams place stirrups at 4intervals.

    Keep this interval for 2

    feet in the lower and upperpart of the column.

  • 8/9/2019 Confined Masonry Training Pakistan

    13/31

  • 8/9/2019 Confined Masonry Training Pakistan

    14/31

    13 August 2006 27

    SDC

    Confined masonry

    Plinth beam

    Prepare the reinforcement of the plinth beam

    Dont forget:stirrup ends bentat 45 degrees!

    13 August 2006 28

    SDC

    Confined masonry

    1 1

    1

    1 Distance blocks(height 1 )

    Plinth beamPlace plinth beam reinforcementon foundation using distanceblocks or spacers.

    The distance blocks must also beput on both sides to keep thedistance to the formwork.

  • 8/9/2019 Confined Masonry Training Pakistan

    15/31

    13 August 2006 29

    SDC

    Confined masonry

    Plinth beamConnect beams to columns usingstraight rebars and pins

    Overlapping 50 cm

    13 August 2006 30

    SDC

    Confined masonry

    Brick wallsUse only bricks with frogs orvertical holes

    Water the bricks before use

  • 8/9/2019 Confined Masonry Training Pakistan

    16/31

    13 August 2006 31

    SDC

    Confined masonry

    Brick wallsUse the Flamish rather than the English bond. It has an equalnumber of joints in each layer, thus ensures more regular mortar

    joints (i.e. all of the same thickness).

    Flamish Bond English Bond

    6 joints

    3 joints

    6 joints

    3 joints

    13 August 2006 32

    SDC

    Confined masonry

    Brick wallsEnd walls in zig-zag towardscolumns

    Avoid continuous joints

  • 8/9/2019 Confined Masonry Training Pakistan

    17/31

    13 August 2006 33

    SDC

    Confined masonry

    Brick wallsAll joints (horizontal and vertical)must be between 3/8 and .

    Join walls carefully by alternatingbrick connection.

    1st layer

    2nd layer

    13 August 2006 34

    SDC

    Confined masonry

    Brick wallsDont build higher than 4 feet perday!

    Protect fresh walls in hot climatesagainst drying out.

  • 8/9/2019 Confined Masonry Training Pakistan

    18/31

    13 August 2006 35

    SDC

    Confined masonry

    Improved wall anchoringTo improve connection betweencolumns and walls, use stitches

    made of rebar anchors ( 1/3 or8mm).

    Place anchors every 1 foot.

    Place the anchor bars in a bed ofconcrete the height of a brick layer.

    Anchors must end with a hook.

    Link anchors with small stirrups.Stitches

    13 August 2006 36

    SDC

    Confined masonry

    Improved wall anchoring Add horizontal through bands at sill and lintel level, even if youdont have a window. These bands will secure the wall against beingknocked out during an earthquake.

    Seismic bandat lintel level

    Seismic bandat sill level

    Seismic bandrebars 3/8,

    h = brick course

    Stitches

  • 8/9/2019 Confined Masonry Training Pakistan

    19/31

  • 8/9/2019 Confined Masonry Training Pakistan

    20/31

    13 August 2006 39

    SDC

    Confined masonry

    Bond beam

    Prepare the reinforcement of the bond beam

    Dont forget:stirrup ends bentat 45 degrees!

    13 August 2006 40

    SDC

    Confined masonry

    Bond beam

    Connect bond beams to columns with straight rebars andpins.

  • 8/9/2019 Confined Masonry Training Pakistan

    21/31

    13 August 2006 41

    SDC

    Confined masonry

    Roof slab

    For spans up to 11 feet

    @ 10

    3/8 @ 8 3/8 @ 8

    6

    2

    Distanceblocks 1

    13 August 2006 42

    SDC

    Confined masonry

    Roof slab

    Example of reinforcement bar distribution for a span of 11 feet.

  • 8/9/2019 Confined Masonry Training Pakistan

    22/31

    13 August 2006 43

    SDC

    Confined masonry

    Roof slab

    A roof pulled over the wall

    edge is another good method(protects the walls againstrain).

    But you still have to place abond beam over the walls asshown on the previouspicture.

    Make sure that the slabrebars go correctly throughthe bond beam.

    13 August 2006 44

    SDC

    Confined masonry

    Roof slab

    Water the slab and keep it wet for one week.

  • 8/9/2019 Confined Masonry Training Pakistan

    23/31

    13 August 2006 45

    SDC

    Confined masonry

    Column roof slab connection

    If you want the column rebarsto stick out of your roof for

    future extensions, they mustbe:

    Long enough (at least 2feet).

    Cast in concrete (toensure correctanchoring).

    Otherwise its better to bendthem into the bond beambefore casting the slab!

    13 August 2006 46

    SDC

    Confined masonry

    Roof terrace

    If you want to make a roof terrace, theterrace walls must be anchored like allother walls.

  • 8/9/2019 Confined Masonry Training Pakistan

    24/31

    13 August 2006 47

    SDC

    Confined masonry

    Roof terrace

    Avoid putting your terrace wall on acantilevered cornice, as it will fall onyour head during an earthquake.

    13 August 2006 48

    SDC

    Confined masonry

    Slope roof

    You can use the column reinforcement bars sticking out of the roofslab to anchor the beams of a slope roof.

  • 8/9/2019 Confined Masonry Training Pakistan

    25/31

    13 August 2006 49

    SDC

    Confined masonry

    Retaining walls

    If you build against aslope, you must makeretaining walls at least2.5 feet away from thebuilding.

    Retaining walls keepaway the pressure of theslope and of the water.

    If you make retainingwalls in dry stonemasonry or situ theymust have an inclinationof 1 to 5.

    The walls of your house must not be in direct contact with the ground!

    13 August 2006 50

    SDC

    Confined masonry

    Retaining walls

    To lead away rain water(including all water thathas rained on the slopeabove your house), makea drainage canal aroundthe house.

  • 8/9/2019 Confined Masonry Training Pakistan

    26/31

    13 August 2006 51

    SDC

    Confined masonry

    Gaps between buildingsTo avoid damage among twobuildings, or an extension to the

    original building, a gap of 1/100thof the height is compulsory.

    This gap must be absolutelyempty and clean (no mortarrests).

    Example: Height of the building

    12 feet (3.6m), the gap must be1 (36mm).

    Take into account any futuresecond floor!

    13 August 2006 52

    SDC

    Confined masonry

    They will brake away during anearthquake, thats all.

    Gaps between buildingsClose gaps with bricks placed infront of them.

  • 8/9/2019 Confined Masonry Training Pakistan

    27/31

    13 August 2006 53

    SDC

    Confined masonry

    Find the error

    No distance blocks

    or spacers in theroof slab.

    These rebarsexposed on thesurface will rustquickly andbecome

    ineffective.

    13 August 2006 54

    SDC

    Confined masonry

    Find the error

    Stirrups are notbent at a 45

    degree angle.

  • 8/9/2019 Confined Masonry Training Pakistan

    28/31

    13 August 2006 55

    SDC

    Confined masonry

    Find the error

    The overlapping

    length isinsufficient

    13 August 2006 56

    SDC

    Confined masonry

    Find the error

    Bond beam mustbe cast together

    with the roof slab.

  • 8/9/2019 Confined Masonry Training Pakistan

    29/31

    13 August 2006 57

    SDC

    Confined masonry

    Find the error

    Bond beam must

    be cast togetherwith the roof slab.

    Depending on thedirection (i.e. in thedirection of theshorter span), thehorizontal

    reinforcement barsmust end in ahook.

    13 August 2006 58

    SDC

    Confined masonry

    Find the error

    Slab is castagainst another

    house. There is nomovement joint toprotect your houseagainst thehammering of yourneighbours houseduring a quake.

  • 8/9/2019 Confined Masonry Training Pakistan

    30/31

    13 August 2006 59

    SDC

    Confined masonry

    Find the error

    These distance blocks orspacers dont have a wire toattach them to the rebars. Theycan move while pouring theconcrete.

    You should prepare them asshown below, each block with awire:

    13 August 2006 60

    SDC

    Confined masonry

    Find the error

    Concrete has not been vibratedcorrectly to fill every gap.

    You should use a vibrator when

    casting concrete, or at leasthammer against formwork tomake sure that the concrete fillsevery hole.

    Dont add more water to theconcrete to make it more fluent.It will become weaker.

  • 8/9/2019 Confined Masonry Training Pakistan

    31/31

    13 August 2006 61

    SDC

    Confined masonry

    Find the error

    Wall is to highwithoutintermediateseismic band.

    An opportunityhas been missed:for little moremoney a muchstronger wallcould have been

    made.

    SDC

    Confined masonry

    Further reading Blondet M. (2005), Construction and Maintenance of Masonry Houses, Pontifica

    Universidad Catolica del Peru, Lima,www.eeri.org/lfe/clearinghouse/kashmir/resources.html

    City (year n/a), Confined Masonry Construction, City University London,

    www.staff.city.ac.uk/earthquakes/MasonryBrick/ConfinedBrickMasonryP.htm Earthquake Hazard Centre, Newsletter, Victoria University of Wellington, New

    Zealand, www.vuw.ac.nz/architecture/research/ehc/

    AIS 2001), Manual de construccion, evaluacion y rehabilitacion sismoresistente en viviendas e mamposteria, Asociation Colombiana de IngenieriaSismica, www.desenredando.org/public/libros/2001/cersrvm/index.html

    NICEE (2004), Guidelines for Earthquake Resistant Non-EngineeredConstruction, Chapter IV: Buildings in Fired-Brick and other Masonry Units,National Information Centre of Earthquake Engineering, IIT Kanput,www.iitk.ac.in/nicee/iaee_english/Chapter4.pdf

    IITK-BMTPC, Earthquake tips 1-24, Indian Institute of Technology Kanpur (IITK) andB ildi M t i l d T h l P ti C il (BMTPC)