S O C E T C I V I L 1 1. About SOCET Silver Oak College of Engineering and Technology (SOCET) is established in June 2009 and is located near Bhavik Publication, Gota Cross road, S.G. Highway, Ahmedabad. This is a Degree Engineering College, leading to Bachelor’s Degree in Engineering. The College is approved by AICTE, Govt. Of India, and is affiliated with Gujarat Technological University. This College also runs IGNOU Courses. Silver Oak College of Engineering and Technology Front View

Upload: kp-ahm

Post on 25-May-2015

6.142 views

Category:

Education


5 download

TRANSCRIPT

Page 1: Concrete Road

S O C E T C I V I L 1

1. About SOCET

� Silver Oak College of Engineering and Technology (SOCET) is established in June 2009 and is

located near Bhavik Publication, Gota Cross road, S.G. Highway, Ahmedabad.

� This is a Degree Engineering College, leading to Bachelor’s Degree in Engineering.

� The College is approved by AICTE, Govt. Of India, and is affiliated with Gujarat Technological

University.

� This College also runs IGNOU Courses.

Silver Oak College of Engineering and Technology

Front View

Page 2: Concrete Road

S O C E T C I V I L 2

2. Location of Site/Address

352,353 A , Nr. Bhavik Publications,

Opp. Bhagwat Vidyapith,

Near Gota Cross Road,

Ahmedabad- 382481.

Phone: +91-79-30180000/1/2/3

Fax: +91-79-30180005

Email: [email protected]

Web: www.socet.edu.in

Key Plan

Page 3: Concrete Road

S O C E T C I V I L 3

3. Background of Contractor

� Contractor Name : Mr. Bharat Patel

� Phone : +91-9904599666

� Qualification : 12th (Comm.) Pass

� Native Place : Amreli, Gujarat, India

� Mr. Bharat Patel has 8 years of experience in Construction Technology (Civil Field).

� He has 5 years of experience in making Cement Concrete Road & R.C.C. Road.

� Mr. Bharat Patel has own consultancy named “Patel Developers”.

� This consultancy located at;

B/104, Akshar Residency,

Nr. Itihas Bunglow,

Nikol-Naroda Road,

Ahmedabad-382350

� This consultancy includes R.C.C., Asphalt Road & Power Block Contractor type of civil

engineering works.

Page 4: Concrete Road

S O C E T C I V I L 4

4. Description of Concrete Road Construction

Layout Plan of Concrete Road

Page 5: Concrete Road

S O C E T C I V I L 5

5. Materials Used

Cement

Ordinary Portland cement (OPC)

� This should comply with the requirements of IS 269-1976 “Specification for Ordinary and Low-

Heat Portland Cement (Third Revision)”, or of IS 8112 -1976 “Specification or High Strength

Ordinary Portland Cement.”

� Ordinary Portland cement and High Strength Ordinary Portland Cement are most widely used for

concrete pavements.

Rapid hardening Portland cement

� This should comply with the requirement of IS: 8041E-l976 “Emergency Specification for Rapid

Hardening Portland Cement.”

� In general, this cement would be used only where time is a critical factor and the road is required

to be opened to traffic at an earlier date than would be possible if Ordinary Portland Cement or

High Strength Ordinary Portland Cement is used.

Aggregates

� In general, Aggregates should comply with IS : 383-1970 “Specification for Coarse and Fine

Aggregates from Natural Sources for Concrete (Second Revision)” with special reference to the

additional requirements stipulated for use in road works excepting in the case of Los Angeles

Abrasion Test limit.

� The Los Angeles Abrasion Test limits shall be not more than 35 % and 50 % for concrete wearing

course and sub-base course respectively.

� Maximum size of aggregate should not exceed 1/4th of the pavement slab thickness.

� In case of pavements having reinforcement, Maximum size of aggregate should not exceed 1/4th

of minimum clear spacing between reinforcing bars.

Water

� Water used in mixing or curing of concrete shall be clean and free from injurious amounts of oil,

salt, acid, vegetable matter or other substances harmful to the finished concrete.

� It shall meet the requirements stipulated in clause 4.3. Of IS: 456-1978 “Code of Practice for Plain

and Reinforced Concrete (Second Revision)”.

� Potable waters are generally considered satisfactory for mixing or curing.

Page 6: Concrete Road

S O C E T C I V I L 6

Reinforcement

Steel wire fabric

� This shall conform to the requirements of IS: 1566-1967 “Specification for Hard-drawn Steel Wire

Fabric for Concrete Reinforcement.”

Bar mats

� The steel in bar mats shall conform to the requirement of IS: 432-1966 “Specification for Mild

Steel and Medium Tensile Steel Bars and Hard-drawn Steel Wire for Concrete Reinforcement.”

� The bars shall be of the size and spacing shown on the plans.

� All junctions of longitudinal and transverse bars shall be securely tied or welded together.

Dowel & Tie Bars

� Dowel and tie bars shall be plain round steel bars conforming to the requirements of IS: 432-1966.

Pre-Moulded Joint Filler

� Pre-Moulded joint filler shall be of the thickness shown on the drawings within a tolerance of ±1.5

mm.

� It shall be 25 mm less in depth than the thickness of the slab, within a tolerance of ±3 mm and of

the full width between road forms.

� Holes to accommodate dowel bars shall be accurately bored or punched out.

� The joint filler shall comply with the requirements of IS: 1838-1961 “Specification for Preformed

Fillers for Expansion Joint in Concrete, Non-extruding and Resilient Type (Bitumen-impregnated

Fiber).”

Joint Sealing Compound

� The sealing compound shall comply with the requirements of the IS: 1834-1961 “Specification for

Hot Applied Sealing Compounds for Joints in Concrete.”

Page 7: Concrete Road

S O C E T C I V I L 7

Cross section of Road

Cross section of Road

Concrete Road Cross section

Page 8: Concrete Road

S O C E T C I V I L 8

6. Leveling Detail For Concrete Road

Leveling Detail For Road

7. Cost Analysis

� The total road constructed is divided into 17 blocks.

� In 1 block, the quantity is used includes the materials such as Cement, Sand, Aggregates, Metal

Aggregates, R.C.C., etc. is estimated up to 6467.17 m³.

� For 17 blocks, total quantity is about 6467.17 m³ x 17.

� Total estimated amount of cement road construction is about Rs. 1, 24,652.00 (INR).

Page 9: Concrete Road

S O C E T C I V I L 9

8. List of Equipment

� A list of tools, equipment and appliances required for the different phases of concrete road

construction is given below.

� This list pertains to semi-mechanized type of construction only, as practiced most in this country.

Sub-grade and Sub-base Compaction

� Compaction equipment - Three wheeled or tandem roller, pneumatic roller, vibratory roller or

sheep-foot roller

� Watering devices - Water Lorries, bhisties/water carriers or watering cans

Preparation of Sub-base for Concreting and Formwork

� Scratch templates or strike boards

� Bulk-heads

� Pick axes, shovels and spades

� Formwork and iron stakes

Concrete Manufacture

� Shovels and spades

� Sieving screens

� Weigh batcher

� Aggregate measuring boxes (only where volume batching of aggregates is permitted as a special

case)

� Water pump

� Water measures

� Concrete mixer

Transportation, Laying and Compaction of Concrete

� Wheel barrows/iron pans

� Wooden bridges

� Spades

� Concrete vibrators (both internal and screed board types)

� Wooden hand tampers

Page 10: Concrete Road

S O C E T C I V I L 10

Finishing Operations - Surface and Joints

� Wooden bridges

� Floats (longitudinal and long-handled wooden floats)

� Templates

� Three-meter long straight edges including one master straight edge

� Graduated wedge gauges

� Mild steel sections and blocks for making joint grooves

� Edging tools including double-edging tools

� Canvas belts

� Long handled brooms

� Diamond cutter (when making saw-cut joints)

� Grinder (for grinding local high spots)

Curing

� Hessian cloth burlap or polyethylene sheeting

� Watering devices (for ponding operation)

Cleaning and Sealing of Joints

� Iron raker

� Coir brush

� Cycle pump/pneumatic air blower

� Kerosene stove

� Thermometer

� Transferring pot

� Painter’s brush

� Pouring kettle

� Scraper

Page 11: Concrete Road

S O C E T C I V I L 11

9. Site Preparation

� Before construction begins, the construction site must be carefully prepared.

� This includes preparing the grade, establishing control mechanisms (the string line), and placing

dowel baskets.

Preparing the grade, or roadbed

� The majority of concrete pavement failures are not caused by failure of the concrete slab but by

problems with the materials beneath the slab.

� These problems can include poor drainage, unstable or no uniform materials, or poor compaction.

� Adequate preparation of the roadbed the sub grade, sub-base, and base is essential for a strong,

durable concrete pavement system.

Sub grade

� Earth has been graded to the desired elevation. (In county and municipal paving projects with low

traffic volumes, concrete is often placed directly on the prepared earth sub grade.)

Sub base

� A course of material is placed on the sub grade to provide drainage and stability.

Three kinds of sub bases may be used based on the need to balance drain ability and stability:

� Granular sub base is the most drainable sub base.

� It is a mixture of granular material that is uniformly shaped and minimally compacted. It does not

provide significant structural support; no construction traffic is allowed on a granular sub base.

� Modified sub base is moderately drainable.

� It contains a greater percentage of crushed particles and a denser gradation than granular sub base,

providing more stability.

� Special backfill provides more stability and support but is the least drainable. It is generally a uniform

mixture of crushed concrete or crushed limestone, or a mixture of gravel, sand, and soil, with or

without crushed stone.

� Special backfill or modified sub base is often used under pavement in urban areas to support

Page 12: Concrete Road

S O C E T C I V I L 12

construction traffic.

Base

� A course of fairly rigid material, sometimes cement- or asphalt-treated, that is placed on the sub base

to provide a stable platform for the concrete pavement slab.

Grading

� First the site is graded to cut high points and fill low areas to the desired roadway profile elevations.

� Generally, cut material can be used as embankment fill.

� However, peat, organic silt, or soil with high organic content should not be used; borrow material

should be used instead.

Stabilization

� Stable soils are generally defined as those that can support loads. Loam or clay loam of glacial till

origin or clean sand is typically desirable.

� Just as important as the soil’s quality, however, is its uniformity. During excavation, localized pockets

of various kinds of soil may be encountered where water absorption rates, densities, and expansion

and contraction rates may vary.

� These pockets lead to different levels of support.

� To stabilize the sub grade so that it will provide uniform support to the rest of the pavement structure,

localized pockets of undesirable material should be removed and replaced with the dominant soil

type or with select backfill, or the soil should be treated with additives.

� Typical stabilizing materials are select soils or back-fill—loam or clay loam, clean sand, or other

stable soil material excavated from road cuts or borrow sites.

Page 13: Concrete Road

S O C E T C I V I L 13

10. Proportioning of Concrete Mixed

Proportioning on the Basis of Strength

� As the stresses induced in concrete pavements are mainly flexural, it is desirable that their design

is based on the flexural strength of concrete.

� For economical design, the design value adopted for flexural strength of pavement concrete shall

not be less than 40 kg/sq. cm at 28 days.

� The mix shall be so designed as to ensure the minimum structural strength in the field with the

desired tolerance level.

� The paving concrete mix should preferably be designed in the laboratory and controlled in the

field on the basis of its flexural strength.

� Where this is not possible, correlation between flexural and compressive strengths should first be

established on the basis of actual tests on additional samples made for the purpose at the time of

designing the mix in the laboratory and quality control then exercised on the basis of compressive

strength, so long as the materials and mix proportions remain substantially unaltered.

Approximate Proportions

� The approximate proportions by weight (or by volume, only in unavoidable cases) necessary to

produce concrete satisfying the above conditions using aggregates from the sources designated

may be furnished in the tender documents, for guidance only, it being expressly understood that

this information is only for the convenience of the bidder.

Field Mix

� After the award of the contract, the proportions, that is, the field mix, determined by the laboratory

for the particular aggregates approved by the engineer shall govern.

� These proportions will be corrected and adjusted by the engineer to compensate for moisture

content in the aggregates or fluctuations in the grading of coarse and fine aggregates at the time of

use.

� Where fine aggregate is permitted to be measured volumetrically, due allowance should be made

for its bulking.

Water Content & Workability

� The water content per batch of concrete should be maintained constantly except for suitable

allowances to be made for free moisture and absorption by aggregates determined from time to

time during construction.

Page 14: Concrete Road

S O C E T C I V I L 14

� Adjustments for workability shall be made by variations in the ratio of the course to fine aggregate

or improving upon their grading without change in cement content or water cement ratio.

� The slump of the concrete mix for pavements compacted by vibration should not be more than 25

mm, preferably between 0 and 12 mm, and that by manual compaction not more than 50 mm.

� No price adjustment would be permissible for variations in the gradations of the aggregates or in

the ratio of course to fine aggregates necessitated from adjustment at site.

11. Construction Process

Storage of Concrete

� Cement shall not be stored for a long time and should be used normally within six months of its

date of receipt.

� Even during this period of storage it is essential that cement shall be protected from moisture by

storing it in suitable sheds.

� A storage shed with a concrete floor laid on a well-drained foundation may be satisfactory.

� Cement in bags shall be stored on boards raised above the floor level for the purpose of

ventilation, and the bags shall not touch the walls of the shed.

Handling of Concrete

� Aggregates from different sources and/or of different grading shall not be stacked together.

� Each separate size of coarse aggregate shall be stacked separately.

� If aggregates are stored in conical stacks, segregation will be increased by the rolling of the

coarser particles down the sides of the stacks.

� To avoid this, stacks should be built up in approximately horizontal layers.

� Dry fine aggregate segregates and gets blown away easily; it may be helpful to moisten it.

� The aggregates shall be handled from the stacks and fed into the mixer in such a manner as to

secure the stipulated grading of the material.

� Aggregates that have become mixed with earth or other foreign material shall not be used. They

shall be washed clean before use.

Page 15: Concrete Road

S O C E T C I V I L 15

Forms

Steel Form Used

Steel Forms

� The steel forms shall be mild steel channel sections of depth equal to the thickness of the

pavement.

� The sections shall have a length of at least 3 m except on curves of less than 45 m radius, where

shorter sections may be used.

� When set to grade and staked in place, the maximum deviation of the top surface of any section

from a straight line shall not exceed 3 mm in the vertical plane and 5 mm in the horizontal plane.

� The method of connection between sections shall be such that the joint formed shall be free from

difference in level, play or movement in any direction.

� The use of bent, twisted or worn-out forms will not be permitted. At least three stake pockets for

bracing pins or stakes shall be provided for each 3 m of form and the bracing and support must be

ample to prevent springing of the forms under the pressure of concrete or the weight or thrust of

machinery operating on the forms.

� The supply of forms shall be sufficient to permit their remaining in place for 12 hours after the

concrete has been placed, or longer if necessary in the opinion of the Engineer-in-charge.

Page 16: Concrete Road

S O C E T C I V I L 16

Setting of Forms

� The forms shall be jointed neatly and shall be set with exactness to the required grade and

alignment. Both before and after the forms are placed and set, the sub-grade or sub-base under the

forms shall be thoroughly tamped in an approved manner.

� Sufficient rigidity shall be obtained to support the forms in such a position that during the entire

operation of compacting and finishing of concrete they shall not at any time deviate more than 3

mm from a straight edge 3 m in length.

� Forms which show a variation from the required rigidity or alignment and levels shown in the

drawing, shall he reset or removed, as directed.

� The length and number of stakes shall be such as to maintain the forms at the correct line and

grade.

� All forms shall be cleaned and oiled each time before they are used.

� Forms shall be set for about 200 m ahead of the actual placing of concrete.

Page 17: Concrete Road

S O C E T C I V I L 17

12. Transporting & Placing of Concrete

Slip Formworks

Page 18: Concrete Road

S O C E T C I V I L 18

� The concrete shall be mixed in quantities required for immediate use and shall be deposited on the

sub-grade/sub-base to the required depth and width of the pavement section, in successive batches

and in continuous operation without the use of intermediate forms or bulk-heads between joints.

� Care shall be taken to see that no segregation of materials results whilst the concrete is being

transported from the mixer to the place where it is deposited.

� The usual method of transport of concrete in India is in pans as head loads or in small wheel

barrows.

� The spreading shall be as uniform as possible to avoid rehandling of the concrete. Where,

however, a certain amount of re-distribution is necessary, it shall be done with shovels and not

with rakes.

� While being placed, the concrete shall be rodded with suitable tools for slab thicknesses of 12.5

cm and less, so that formation of voids or honeycomb pockets is prevented.

� The concrete shall be particularly well placed and tapped against the forms and along all joints.

� For higher thicknesses an internal vibrator shall be employed in lieu of rodding of the concrete.

� To effect adequate compaction, the concrete shall be placed with appropriate surcharge over the

final slab thickness.

� The amount of surcharge will depend on the mode of placement of concrete and shall be

determined by trial.

� In general, the required surcharge is about 20 per cent of the required slab thickness.

� Any portion of the batch of concrete that becomes segregated white depositing it on sub-grade

shall be thoroughly mixed with the main body of the batch during the process of spreading.

� In case of unavoidable interruption, a full depth transverse joint shall be made at the point of

stoppage of work provided the section on which the work has been suspended is about 2 to 3 m

tong.

� In placing of concrete for two course construction, necessitated by either positioning of the

reinforcement, a richer mix for the wearing surface, or when thickness of the concrete is beyond

20 cm, the bottom layer of concrete shall be struck off to the required levels by a vibrating screed

working on the side forms with notches corresponding to the depth of the top course of concrete.

� The vibrating screed should have a vibrating unit mounted on it similar to that of the screed used

for compaction of the final surface of concrete. The time lag between lying of the two courses

shall not exceed the initial setting time of cement.

Page 19: Concrete Road

S O C E T C I V I L 19

13. Types of Joints in Concrete Road

There are three main types of joints.

1. Contraction Joints

2. Construction Joints

3. Isolation Joints

� There are three basic joint types used in concrete pavement: contraction, construction and

isolation.

� Specific design requirements for each type depend upon the joint's orientation to the direction of

the roadway (transverse or longitudinal). Another important factor is load transfer.

� Except for some isolation joints, all joints provide a means to mechanically connect slabs. The

connection helps to spread a load applied on one slab onto slabs along its perimeter.

� This decreases the stress within the concrete and increases the longevity of the joint and slab(s).

The efficiency of the mechanical connection is expressed as load transfer efficiency.

1. Construction Joints

� Contraction joints are necessary to control natural cracking from stresses caused by concrete

shrinkage, thermal contraction, and moisture or thermal gradients within the concrete.

� Typically transverse contraction joints are cut at a right angle to the pavement centerline and

edges.

Page 20: Concrete Road

S O C E T C I V I L 20

� However, some agencies skew transverse contraction joints to decrease dynamic loading across

the joints by eliminating the simultaneous crossing of each wheel on a vehicle’s axle.

� Contraction joints are usually sawed into the concrete, but they might be formed or tooled on

smaller projects.

� The details below show the different types of contraction joints and their dimensions.

2. Construction Joints

� Construction joints join concrete that is paved at different times.

� Transverse construction joints are necessary at the end of a paving segment or at a placement

interruption for a driveway, cross road or bridge.

� Longitudinal construction joints join lanes that are paved at different times, or join through-lanes

to curb and gutter or auxiliary lanes. The details below show the different types of construction

joints and their dimensions.

Page 21: Concrete Road

S O C E T C I V I L 21

3. Isolation Joints

� Isolation joints separate the pavement from objects or structures, and allow independent

movement of the pavement, object or structure without any connection that could cause damage.

� Isolation joints are used where a pavement abuts certain manholes, drainage fixtures, sidewalks

and buildings, and intersects other pavements or bridges.

� The details below show the different types of isolation joints and their dimensions.

Page 22: Concrete Road

S O C E T C I V I L 22

Load Transfer Devices- DOWELS

Cross Section of Dowel Joints

� Transverse expansion joints shall be equipped with dowels of the dimension and at the spacing

and location indicated on the drawing.

� They shall be firmly supported in place, accurately aligned parallel to the sub-grade/sub-base,

parallel to each other and parallel to the centre line of the pavement, by means of appropriate

dowel supports.

� The dowel supports shall ensure that the dowels are not displaced during construction.

� One-half of each dowel shall be painted with a thin film of bitumen and equipped with a tight

fitting metal sleeve of the dimensions shown on the drawing to provide space for the dowel when

pavement expands and the joint closes.

� This sleeve shall be partly filled with cotton waste to prevent it being pushed too far on the dowel

during construction.

� These sleeves are not required on dowels, if used, in dummy contraction or construction joints.

� Dowel bars transfer heavy loads across joints in the pavement, preventing faulting at the joint that

can lead to pavement damage.

� Practices vary from state to state, but dowel bars are typically required in eight-inch or thicker

pavements.

� Dowels must be positioned and aligned perfectly so that, as joints open in winter and close in

summer with contraction and expansion of the concrete, the pavement on either side of the joints

can move in a straight line along the smooth dowels.

� If a dowel bar is not aligned truly across the joint, the pavement can’t move and a stress results.

The stress can crack the pavement.

Page 23: Concrete Road

S O C E T C I V I L 23

� Without dowels, the slab on either side of a joint tends to move up and down; that is, there is little

“load transfer” at the joint.

� Dowels help provide load transfer at the joint.

Page 24: Concrete Road

S O C E T C I V I L 24

Basket placement

� After the sub base has been properly trimmed and inspected, dowel baskets are set on the road bed,

perpendicular to the pavement edge or at a slight skew.

� The bars should be located at the mid-depth of the slab and carefully aligned, horizontally and

vertically.

� As mentioned above, location and alignment of the bars is critical. If they are too close to the edge,

the paving equipment will snag them.

� When the bars are correctly aligned, the baskets must be secured with stakes. Practices vary from

state to state, but a minimum of eight stakes (for 12- or 14-foot lane widths) are placed on the leave

side of the basket wire to secure the basket against movement.

� The location of dowel centers is then marked on both sides of the roadbed, either by setting pins or

painting marks. The markers indicate where joints should be sawed, ensuring that they will be sawed

across the center of the dowel assembly.

Final check

� Dowel positions should be checked from three perspectives:

� Sight down the grade to make sure all dowels is parallel to center line.

� Sight across the dowel baskets to make sure all dowels is level. The basket assemblies should be

parallel to and aligned with each other.

� Sight across the basket, imagining a line from the pin or mark on one side to the pin or mark on the

other side. Make sure the middle of the dowels falls exactly along that line.

� After dowels have been placed, an inspector should check basket spacing, alignment, and skew.

Page 25: Concrete Road

S O C E T C I V I L 25

14. Compaction and Finishing of the top Surface

� Since PCC is an open-graded mix design, finishing takes on a different meaning than standard

concrete pavement.

� Finishing and compaction are the most crucial steps to producing a durable pavement. Properly

finishing PCC provides a uniform and level surface that prevents surface raveling of the aggregate,

while remaining aethstetically pleasing to the public.

� Dry, poorly finished slabs can ravel and appear to have failed even though they are structurally

sound. Properly finished PCC provides a surface suitable for wheelchair and rollerblade use and

an ideal surface for recreational trails.

� Many methods exist to finish and compact PCC and they range from those that strictly are for

finishing, to those that only provide compaction, but most operations provide some degree of both.

� Historically, PCC is struck off ¾ in. to 1 in. above the forms using a shim and vibratory screen as

shown in Figure.

� Then the shims are removed and the pavement is compacted to final grade using a weighted roller

as in Figure.

Strike off with a vibratory screed

Page 26: Concrete Road

S O C E T C I V I L 26

Compacting using a weight roller

� Most recently, roller screeds have been used to finish many PCC pavements.

� Roller screeds have been used for many years on traditional concrete, and provide a rapid method

to produce smooth PCC pavements.

� Roller screeds are hydraulically driven, stainless steel tubes that rotate against the direction of

placement. Small width slabs (<15 ft.) can easily be finished with a manual roller screed such as

the screed used to finish the pervious test slab at the Road facility.

Finishing using a manual roller screed, finished surface

Page 27: Concrete Road

S O C E T C I V I L 27

Finishing using a power screed

� Figure shows striking a slab off ¾ in. above the final thickness using a hand-held vibrating screed.

� The shims were then removed and compaction was achieved using a plate compactor on top of a sheet of plywood.

� The entire sidewalk at the hospital site was finished using this method and has weathered its first winter without any raveling.

Striking off using a vibrating screed

Page 28: Concrete Road

S O C E T C I V I L 28

Compaction using plywood and a plate compactor

Compaction using plywood and a plate compactor

� PCC edge raveling can be minimized by using a standard edging tool around the forms.

� The edging also adds to the aesthetics of the finished PCC.

� Figure shows use of an edging tool at the Road placement.

Page 29: Concrete Road

S O C E T C I V I L 29

15. Making Grooves

Avoid too much water

� The right amount of water is carefully measured at the plant. Extra water weakens the mix. More

water makes it easier to work with right away, but will lead to a weaker slab.

� If you're mixing your own concrete, do this test: Plow a groove in a mound of concrete with a

shovel or hoe.

� The groove should be fairly smooth and hold its shape. If it's rough and chunky, add a smidgen of

water. If it caves in, add more dry concrete.

Don't delay floating

Bull float in action: Use a bull float to flatten large areas immediately after placing the concrete.

Page 30: Concrete Road

S O C E T C I V I L 30

Close up of Groove

Purpose: Used to tool control joints in plastic concrete (as an alternative to saw cutting).

Close-up of groove: A groove has a blade (typically 1-in.) on the underside that cuts the groove

� Grooves are usually made of bronze or stainless steel and have a V-shaped bit that cuts the groove.

Like edger’s, they come with wood or comfort-grip handles.

� The most common groove size is 6 inches long and 4 1/2 inches wide, but many other sizes are

available, ranging from 2 to 8 inches wide and 3 to 10 inches long.

� However, more important is the dimension of the bit, which can be anywhere from 1/2 inch to 2

inches deep and 1/8 to 1 inch wide. Bi-directional grooves are also available and have double-end

bits that give you the flexibility to cut forward or backward.

Page 31: Concrete Road

S O C E T C I V I L 31

Finish with a broom

Broom the finish: A stiff broom creates a slightly roughened concrete surface

� A smooth, steel trowel finish is too slippery for outdoor concrete.

� Instead, drag a broom over the concrete. You'll get a nonslip texture and hide imperfections left by floating or troweling.

� You can use a plain old push broom, but a special concrete broom cuts finer lines.

� The sooner you start, the rougher the finish. Make your first pass about 15 minutes after floating. If the texture is too rough, smooth it over with a mag float and try again in 15 minutes.

� Drag the broom over the concrete in parallel, slightly overlapping strokes. You may have to rinse off the broom occasionally to avoid a too-rough finish.

Page 32: Concrete Road

S O C E T C I V I L 32

16. Curing of Concrete

� Immediately after the finishing operations have been completed, the entire surface of the newly

laid concrete shall be covered against rapid drying, and cured.

� Failure to provide sufficient cover material of the stipulated type, or inadequate supplies of water

for curing shall be adequate cause for immediate.

1. Initial Curing

� After completion of the finishing operations, the surface of the pavement shall be entirely covered

with wet hessian cloth, burlap or jute mats.

� The coverings used shall be of such length (or width) that when laid wilt extend at least 500 mm

beyond the edges of the slab, shall be so placed that the entire surface and both the edges of the

stab are completely covered.

� They shall be placed as soon as the concrete has set sufficiently to prevent marring of the surface.

� Prior to their being placed, the coverings shall be thoroughly wetted with water and placed with

the wettest side down.

� They shall be so weighed down as to cause them to remain in intimate contact with the surface

covered.

� They shall be maintained fully wetted and in position for 24 hours after the concrete has been

placed, or until the concrete is sufficiently hard to be walked upon without suffering any damage.

� To maintain the coverings wet, water shall be gently sprayed so as to avoid damage to the fresh

concrete.

� If it becomes necessary to remove the coverings for any reason, the concrete stab shall not be kept

exposed for a period of more than half an hour.

� Worn coverings or coverings with holes shall not be permitted.

� Coverings reclaimed from previous use other than curing concrete shall be thoroughly washed

prior to use for curing purposes.

� If the covering is furnished in strips, the strips shall be laid to overlap at least 150 mm.

Page 33: Concrete Road

S O C E T C I V I L 33

2. Final Curing

� Upon the removal of the covering the slab shall be thoroughly wetted and then cured by one of the

following methods of final curing:

Curing with wet earth

� Exposed edges of the slab shall be banked with a substantial berm of earth.

� Upon the slab shall then be laid a system of transverse and longitudinal dykes of clay about 50

mm high, covered with a blanket of sandy soil free from stones to prevent the drying up and

cracking of clay.

� The rest of the slab shall then be covered with sufficient sandy soil so as to produce a blanket of

earth not less than 40 mm depths after wetting.

� The earth covering shall be thoroughly wetted white it is being placed on the surface and against

the sides of the slab and kept thoroughly saturated with water for 14 days and thoroughly wetted

down during the morning of the 15th day and shall thereafter remain in place until the concrete has

attained the required strength and permission is given to open the pavement to traffic.

� When such permission is granted, the covering shall be removed and the pavement swept clean.

� If the earth covering becomes displaced during the curing period, it shall be replaced to the

original depth and re-saturated.

3. Impervious membrane method

� The membrane shall consist of a practically colorless impervious liquid of a type approved by the

Engineer-in-charge.

� The use of any membrane material which would impart a slippery surface to the pavement or alter

its natural color will not be permitted.

� Liquid shall be applied under pressure with a spray nozzle in such a manner as to cover the entire

surface with a uniform film, and shall be of such character that it will harden within 30 minutes

after application.

� The amount of liquid applied shall be ample to seal the surface of the pavement thoroughly.

� The liquid shall be applied immediately after the finishing of the surface and before the cement

has set, or, if the pavement is first covered with burlap or hessian cloth or the like, it may be

applied upon their removal.

� The impervious coating used for membrane curing shall be such that when applied to the surface

of test slabs made of cement sand mortar in the manner prescribed for the use of the materials in

Page 34: Concrete Road

S O C E T C I V I L 34

the field, the mortar shall retain at least 90 per cent of the mixing water when exposed for 144

hours to temperatures between 32 to 38°C at a relative humidity of 30 % to 50 %.

Insulating

� If air temperatures drop quickly during the first night after placement, the concrete surface will cool

quickly com-pared to the rest of the concrete.

� Such extreme temperature variations in the slab can cause concrete to change volume at different

rates (differential thermal contraction), which in turn can cause tensile stress and random cracking in

the slab.

� Covering the new concrete can help reduce extreme variations in temperature throughout the depth

of the slab.

Removing of Forms

� Forms shall not be removed from freshly placed concrete until it has set, or at least 12 hours,

whichever is later.

� They shall be carefully removed in such a manner that no damage is done to the edges of the

pavement.

� After the forms have been removed, time slab edges shall be cleaned and any limited honey-

combed areas pointed up with 1:2 cement sand mortar, after which the sides of the slab shall be

covered with earth to the level of the top of the stab for final curing.

� Slabs with excessive honey-combing as a result of inadequate compaction shall be removed

between nearest transverse joints.

Page 35: Concrete Road

S O C E T C I V I L 35

17. Protection of Concrete

1. Protection against drying out

� The quality of hardened concrete, and in particular, the durability of the surface, depends directly on

the protection of the fresh concrete against drying out.

� It is detrimental both to the strength and to the shrinkage (risk of cracks forming) and also to the

durability when the fresh concrete loses water.

� As a result of their large exposed areas, pavements are greatly subjected to drying out.

� E.g. at an ambient temperature of 20°C, a relative humidity of 60 %, a temperature of the concrete of

25°C and a wind speed of 25 km/h, 1litre of water will evaporate every hour from every m2 of

pavement surface.

� Note that the upper surface layer (a few cm thick) of the concrete only contains about 4 liters of water

per m2.

� A curing compound is usually used to protect road concrete against drying out.

� In case of an exposed aggregate finish, the setting retarder must also have the property that it protects

the concrete against drying out.

� If not, the concrete must be covered with a plastic sheet as soon as the setting retarder is applied.

� As stated above, subsequent to the removal of the skin of concrete mortar, the concrete is protected

against drying out a second time by spraying a curing compound or by covering the surface with a

plastic sheet.

� The latter method is particularly used in urban areas on colored exposed aggregate concrete.

Page 36: Concrete Road

S O C E T C I V I L 36

2. Protection against rain

� Concreting is stopped if it rains. Furthermore, the necessary measures have to be taken to prevent that the

concrete surface is washed out by rain.

� This applies both to freshly spread concrete that has not been compacted yet and to smoothed concrete.

� Plastic sheets or mobile shelters are suitable means of protection.

3. Protection against frost

Page 37: Concrete Road

S O C E T C I V I L 37

� When concrete is placed in cold weather the pavement surface has to be effectively protected against

frost in such a way that the temperature at the surface of the concrete does not drop below + 1 ºC for

72 hours after placement.

� This protection can consist of, for example, non-woven geotextile or polystyrene foam plates with

ballast.

4. Protection against mechanical influences (traffic signposting)

� Every necessary measure shall be taken to protect the fresh concrete from damage due to all kinds of

mechanical influences (Car, Bicycle, Pedestrian, Animals, Bikes, etc.)

Page 38: Concrete Road

S O C E T C I V I L 38

18. Advantages of Concrete Road

Durability and maintenance free life:

Concrete roads have a long service life of forty years, whereas asphalt roads last for ten years. Moreover,

during this service life concrete road do not require frequent repair or patching work like asphalt roads.

Vehicles consume less fuel:

A vehicle, when run over a concrete road, consumes 15-20% less fuel than that on asphalt roads. This is

because of the fact that a concrete road does not get deflected under the wheels of loaded trucks.

Resistant to automobile fuel spillage and extreme weather:

Unlike asphalt roads, concrete roads do not get damaged by the leaking oils from the vehicles or by the

extreme weather conditions like excess rain or extreme heat.

Greener process:

Asphalt (bitumen) produces lots of highly polluting gases at the time of melting it for paving. Also, less fuel

consumption by the vehicle running on a concrete road means less pollution.

Saving of natural resources:

Asphalt (bitumen) is produced from imported petroleum, the reserve of which is becoming reduced

drastically. On the other hand, concrete (cement) is produced from abundantly available limestone.

Page 39: Concrete Road

S O C E T C I V I L 39

19. Special Measures of Concrete

1. Workability period

� It must always be ensured that the concrete is processed as quickly as possible, certainly within 2 hours

after batching including the surface treatment and the protection measures.

� In hot, dry weather an even shorter workability time has to be observed (maximum 90 minutes).

Unless special precautions are taken that have been approved by the manager of the works, concrete can

only be laid if the air temperature at 1.5 m above ground under thermometer shelter does not exceed

25°C.

� Furthermore, all necessary measures shall be taken to keep the water content of the concrete as

constant as possible from the time of batching until completion of the placement.

2. Paving interruptions

� Whenever the supply of concrete is interrupted, the driver of the paving machine shall immediately

take the necessary measures to lower the speed of the paving train and to ensure that the machine

stops as little possible.

� For a short interruption, the machine should be stopped before the deposited concrete in the vibrating

chamber has dropped to such a level that the vibrators become visible. If the supply is interrupted for

more than 60 minutes (45 min. in hot weather), a construction joint has to be made.

� Upon a long-lasting defect of the paving equipment, the supply of fresh concrete has to be stopped

immediately and an attempt must be made to complete the current paving phase.

� If the circumstances and the elapsed workability time no longer make a proper completion

possible, the concrete, that has been deposited but not yet finished, has to be removed.

� To achieve a continuous profile, particular care is taken of the execution of the construction

joints, both at the end of the day and every time work is resumed.

� The concrete is compacted preferably with a separate vibrating needle before the paving machine is

passing in order to obtain properly compacted concrete on both sides of the joint.

Page 40: Concrete Road

S O C E T C I V I L 40

3. Placement of concrete on a slope

� When placing concrete on a slope of less than 4 % it is recommended to work uphill, in order to

prevent tension cracks at the surface.

� Furthermore, the consistency of the concrete and the working speed of the paver have to be adapted to

the working conditions.

� However, if the longitudinal slope is more than 4 %, unevenness can occur as concrete falls back when

the machines have passed. In that case, a suitable composition of the concrete mix has to be realized and

it is recommended to work downhill.

� It must be ensured that enough concrete is deposited in front of the paving machine to prevent the

concrete from sliding down.

� Concrete pavements have been successfully executed on slopes of 10 to 12 %. At one time the slope

was even 18%.

Page 41: Concrete Road

S O C E T C I V I L 41

20. Weather Consideration

1. Hot, dry weather paving

Definition

� Temperatures generally above 90°F (32°C), low relative humidity, high wind speed, sunny conditions

Challenges

� Concrete loses moisture more rapidly during hauling and placing.

� Aggregate stockpiles dry out, affecting moisture consistency between batches.

� The pavement sub base dries out before the mixture is placed, then absorbs water from the mixture.

� Rapid water evaporation at the pavement surface can result in shrinkage cracks.

� It’s more difficult to entrain air when temperatures are high. Entrained air is important for pavement

Durability.

� Concrete sets rapidly, perhaps twice as fast, making finishing more difficult.

� Sawing operations must proceed more rapidly. Additional saws may be required.

� Once heat-related problems develop, it may be too late to fix them.

Precautions

� If possible, do not pave in very hot, dry weather.

� Pave in the morning, evening, or night when air temperatures are cooler.

� Maintain uniform moisture in stockpiles.

� Use retarders in the mixture to slow hydration.

� Use fly ash and slag in the mixture.

� Keep sub base, forms, and equipment damp and cool.

� Apply curing compound as soon as possible. Additional compound may be required.

Page 42: Concrete Road

S O C E T C I V I L 42

2. Cold weather paving

Definition

� Air temperature of 50°F or less (10°C) for more than half of any 24-hour period, or when the

average daily air temperature is less than 40°F (5°C) for three consecutive days.

Challenges

� During cold weather, hydration slows, slowing strength development.

� Concrete cools faster at the surface than inside the slab, causing stress in the slab.

� If the stress is severe enough, the slab will crack randomly.

Precautions

� Do not pave on frozen sub grade.

� Do not use aggregates with frozen lumps.

� Heat materials to raise concrete temperature and promote hydration.

� Minimize use of fly ash and slag.

� Do not pave if the concrete cannot reach adequate strength before it freezes.

� For the first two to three days, protect concrete from freezing with insulating material.

3. Rain

Challenges

� Before final set, rain can damage the new pavement surface by leaving imprints or washing away

paste at the surface.

� After final set, rain can induce rapid cooling at the surface, leading to rapid development of thermal

restraint stresses and possibly early-age, uncontrolled cracking.

Precautions

� If it starts to rain during operations, take the following actions:

� Stop batching and placing operations and cover the fresh concrete immediately with protective

coverings like polyethylene sheeting or burlap. (Do not try to remove extra surface water first. Do not

add dry cement to the surface.)

Page 43: Concrete Road

S O C E T C I V I L 43

� As soon as the surface has dried, apply curing membrane.

� After the curing period, diamond grinding may be required to remove surface blemishes and provide

texture to any surface exposed to rain where damage has occurred.