For further information Call 0800 170 7270 Visit 77clarendonroad.com Email [email protected] LOCAL NEWSLETTER SEPTEMBER 2018 / WELCOME Welcome to the seventh issue of the TJX Europe local newsletter which will keep you up to date as we prepare to build our new headquarters on Clarendon Road. TJX Europe operates the TK Maxx and Homesense retail chains in Europe and has had its corporate headquarters in Watford for over 20 years. / Site from Clarendon Road, 6 September / REGULAR UPDATES We will issue a regular newsletter to keep you informed of planned activities and our site progress. In the meantime if you want to be kept updated with our latest progress and receive our email updates, please contact: W: 77clarendonroad.com E: feedback@ 77clarendonroad.com T: 0800 170 7270 / SITE OPERATION HOURS The site will be operating on: Monday – Friday: 8am – 6pm Saturday: 8am – 1pm / CONTACTS CAREYS John Kearney, Project Manager Mobile 07525 600 572 / CONCRETE POURING FOR FOUNDATIONS AND WALLS TO START Excavation works are continuing and will be complete by the end of October. As this work draws to a close, you should see a noticeable reduction in the number of wagons entering and exiting the site. In the meantime, traffic marshals will remain in place at the entry and exit gates on Verulam Passage and Clarendon Road. In our previous newsletter, we advised that the council had allowed us to move vehicles from our site from 7.00am to support the bulk excavation work. This is now complete, and site operating hours will revert to 8.00am from 19th September. As we enter the next section of works, we will start pouring the concrete for the basement floor level foundations, and for the columns and walls. These works will commence in the coming weeks on the basement level. They may occasionally involve some late running works in order to finish the concrete, but we will endeavour to keep these to a minimum. The second tower crane on site is due to be erected on Saturday 29th and Sunday 30th September 2018. To ensure the safety of pedestrians and drivers, we have arranged for lane and footway closures along Clarendon Road until the installation is complete.

Upload: others

Post on 05-Jul-2020

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: CONCRETE POURING FOR FOUNDATIONS AND WALLS TO START77clarendonroad.com/wp-content/uploads/2019/01/TJX... · floor level foundations, and for the columns and walls. These works will

For further information

Call 0800 170 7270 Visit 77clarendonroad.com Email [email protected]

LOCAL NEWSLETTER SEPTEMBER 2018

/ WELCOMEWelcome to the seventh issue of the TJX Europe local newsletter which will keep you up to date as we prepare to build our new headquarters on Clarendon Road. TJX Europe operates the TK Maxx and Homesense retail chains in Europe and has had its corporate headquarters in Watford for over 20 years.

/ Site from Clarendon Road, 6 September

/ REGULAR UPDATES

We will issue a regular newsletter to keep you informed of planned activities and our site progress. In the meantime if you want to be kept updated with our latest progress and receive our email updates, please contact:W: 77clarendonroad.comE: feedback@ 77clarendonroad.comT: 0800 170 7270

/ SITE OPERATION HOURS

The site will be operating on:Monday – Friday: 8am – 6pmSaturday: 8am – 1pm

/ CONTACTSCAREYS John Kearney, Project ManagerMobile 07525 600 572

/ CONCRETE POURING FOR FOUNDATIONS AND WALLS TO START

Excavation works are continuing and will be complete by the end of October. As this work draws to a close, you should see a noticeable reduction in the number of wagons entering and exiting the site. In the meantime, traffic marshals will remain in place at the entry and exit gates on Verulam Passage and Clarendon Road. In our previous newsletter, we advised that the council had allowed us to move vehicles from our site from 7.00am to support the bulk excavation work. This is now complete, and site operating hours will revert to 8.00am from 19th September.

As we enter the next section of works, we will start pouring the concrete for the basement floor level foundations, and for the columns and walls. These works will commence in the coming weeks on the basement level. They may occasionally involve some late running works in order to finish the concrete, but we will endeavour to keep these to a minimum.

The second tower crane on site is due to be erected on Saturday 29th and Sunday 30th September 2018. To ensure the safety of pedestrians and drivers, we have arranged for lane and footway closures along Clarendon Road until the installation is complete.