(conceptual plan) forenvironmentclearance.nic.in/writereaddata/online/tor/06... · 2017. 4. 6. ·...
TRANSCRIPT
-
ENVIRONMENT CLEARANCE(Conceptual Plan)
For Integrated Exhibition cum Convention
Centre (IECC)
(Redevelopment of ITPO Complex at Pragti Maidan)
Submitted ByIndia Trade Promotion Organisation (ITPO)
-
ContentsIntroduction..................................................................................................5
General......................................................................................................5
Brief about Project Proponent....................................................................5
Project Consultant.....................................................................................6
Brief about Project.....................................................................................6
Site Surroundings and Connectivity..............................................................7
Location.....................................................................................................7
Salient features of the site...........................................................................12
Area Details................................................................................................12
Ground Coverage and FAR Details............................................................14
Population Density......................................................................................15
During Construction Phase......................................................................15
During Operational Phase........................................................................15
Land Environment......................................................................................16
Topography..............................................................................................17
Water Environment.....................................................................................17
Construction Phase..................................................................................17
Operational Phase....................................................................................17
Wastewater Details...................................................................................20
Sewage Treatment Technology..................................................................23
Technology Proposed- MBR (Membrane Bio Reactor)..............................24
Process Description...............................................................................26
MBR Module.........................................................................................28
Operation..............................................................................................28
Sewer System........................................................................................29
-
Preventive measures to Avoid Leaching.....................................................29
Rainwater Harvesting and Strom Water Drain..........................................29
Need for Rainwater Harvesting.................................................................30
Rainwater Harvesting Network.................................................................30
Efficacy of Rain Water Harvesting............................................................32
Parking Details............................................................................................33
Electrical details.........................................................................................34
Power Details...........................................................................................34
D. G. Sets Details..................................................................................34
Lighting system........................................................................................34
Lighting Control through day lighting and sensor Motion.........................35
Integrated Fire Detection System..............................................................35
Solid Waste Details......................................................................................36
During Construction Phase of the Proposed Building...............................36
C & D waste of Existing Buildings............................................................37
During Operational Phase........................................................................37
Collection and Segregation of waste.......................................................39
Treatment of Waste................................................................................39
Disposal................................................................................................40
Landscape Details.......................................................................................41
Energy Conservation Measures...................................................................43
List of the construction Material Used.........................................................44
List of Figures
-
Figure 1: Google Map Showing Site and Its Surroundings (500 mtrs)..........10Figure 2: Toposheet Map showing Site and Surroundings (5 km).................11Figure 3 : Water Balance Diagram during Dry Season.................................21Figure 4: Water Balance diagram during Monsoon Season..........................22Figure 5: Schematic Diagram of MBR Technology........................................27Figure 6: Rainwater Harvesting Structure...................................................32Figure 7: Solid Waste Management for Construction Phase.........................37Figure 8: Solid Waste Management Scheme -Domestic Waste......................41
List of TablesTable 1: Project Consultants Involved............................................................6Table 2: Geographical Co-ordinates of the site...............................................7Table 3: Site Surroundings and Connectivity.................................................8Table 4: Salient Features of the site.............................................................12Table 5: Area Details of Retained (Existing) + Proposed Building.................13Table 6: Ground Coverage and FAR details of Retained (Existing) building...14Table 7: Ground Coverage and FAR Details of Proposed Building................14Table 8: Population Details for Retained (Existing) Building.........................15Table 9: Population Details for Proposed Building.......................................15Table 10: Water Requirement during Operational Phase (Retained + Proposed) Building...................................................................................................................19Table 11: Design Parameters for Sewage Collection System.........................24Table 12: Wastewater Details.......................................................................29Table 13: Calculation for Strom Water Load for the Development of IECC....31Table 14: ECS Required...............................................................................33Table 15: Parking Proposed.........................................................................33Table 16: D.G. sets location and their description.......................................34Table 17: Calculation of Solid Waste Generation of Retained and Proposed Building 38Table 18: Landscape Area Details................................................................41Table 19: Plantation List.............................................................................43
AnnexureAnnexure 1: Land Ownership Documents..................................................17
CONCEPTUAL PLANCONCEPTUAL PLAN
file:///E:%5CDELHI%5CITPO%5CProposal%5Creconceptualplanforieccdiscussedon16_03_2017%5C01%20ITPOS-%20Conceptual%20Plan%20F2.docx#_Toc477871339file:///E:%5CDELHI%5CITPO%5CProposal%5Creconceptualplanforieccdiscussedon16_03_2017%5C01%20ITPOS-%20Conceptual%20Plan%20F2.docx#_Toc477871340file:///E:%5CDELHI%5CITPO%5CProposal%5Creconceptualplanforieccdiscussedon16_03_2017%5C01%20ITPOS-%20Conceptual%20Plan%20F2.docx#_Toc477871341file:///E:%5CDELHI%5CITPO%5CProposal%5Creconceptualplanforieccdiscussedon16_03_2017%5C01%20ITPOS-%20Conceptual%20Plan%20F2.docx#_Toc477871342file:///E:%5CDELHI%5CITPO%5CProposal%5Creconceptualplanforieccdiscussedon16_03_2017%5C01%20ITPOS-%20Conceptual%20Plan%20F2.docx#_Toc477871365
-
Introduction
General The Ministry of Environment, Forest and Climate Change has notified the
Environmental Impact Assessment (EIA) Notification, 2006 under the provisions of the
Environment (Protection) Act, 1986, which regulates development and their
expansion/modernization of 39 sectors/activities listed in the Schedule to the EIA
Notification, 2006. As per the EIA Notification 2006, all the building construction projects/Area
Development projects and Township Projects comes under schedule 8 and projects
covering an area ≥ 50 ha and/or built up area ≥1,50,000 sq .mtrs they come under
schedule 8 (b). All projects under Item 8(b) shall be appraised as Category B1. The application for environmental clearance shall comprise submission of Form 1,
Form 1A, and Conceptual Plan along with EIA/EMP Report incorporated proposed ToR
in SEIAA. The EIA/EMP shall be prepared on the basis of Approved ToR issued from
SEAC and will be submitted to the SEAC for appraisal and due recommendation and
suggestions. Following the appraisal of the project to the satisfaction of the SEAC and
SEIAA, Environmental Clearance shall be granted.Total Built up area of the proposed site is 3, 97,249.559 m2.
Brief about Project Proponent India Trade Promotion Organization (ITPO) is the nodal agency of the Government of
India under aegis of Ministry of Commerce and Industry (India) for promoting
country's external trade. ITPO is a Mini-Ratna Category-1 Central Public Sector
Enterprise (CPSE) with 100 percent shareholding of Government of India. ITPO, during its existence of more than 5 decades has played a proactive role in
catalysing trade, investment and technology transfer processes. Its promotional tools
include organising of fairs and exhibitions in India and abroad, Buyer-Seller Meets,
Contact Promotion Programmes, Product Promotion Programmes and Promotion
through Overseas Department Stores, Market Surveys and Information Dissemination.
Project ConsultantDetails regarding Project consultants involved are given below;
-
Table 1 : Project Consultants Involved
Project Team Details
Architects
Aedas Architects Unit 133, Rectangle One,D4 District Centre Saket,New Delhi, Delhi 110017Arcop Associates (P) Ltd.A-15, Pamposh Enclave, Greater Kailash - 1, New Delhi-110048 India
Environment Consultant
Envision Enviro Technologies Pvt. Ltd.A-73, Noida-201301
Landscape Architect Pravin KhotMEP Consultant Meinhardt India Pvt Ltd
A-8 , Sector 16 Noida-201301
Project Management Agency (PMA)
NBCC (India) LimitedNBCC Bhawan, Lodhi RoadNew Delhi - 110 003, India
Brief about Project
Pragati Maidan is a venue for large exhibitions and conventions in New Delhi with
65,000 m2 of existing exhibition space is now re-develop into Integrated Exhibition-
cum-Convention Centre (IECC) with Approx. 3,61,688.809 m2 of built up area having
Convention Center & Exhibition Halls building development in Phases-1 facilities like
car parking for visitors a single basement also planned. Proposed development will
become Delhi's & North India's largest exhibition centre owned and managed by India
Trade Promotion Organization (ITPO) The design comprises of an iconic convention centre& exhibition- halls. Considerations
have been made for the use of environment friendly materials to achieve Green
Building Features. Overall layout of the project includes convention centre, exhibition
halls, Restaurants, Business centre, open exhibition space with parking basement.
-
The existing buildings were constructed and also became operational prior to the
publication of EIA Notification 2006. Therefore, the existing buildings did not attract
applicability of to obtain Environmental Clearance from SEIAA/MoEFCC and no
environmental clearance was issued. Accordingly, the issuance of certified monitoring
report by Regional Director of MoEFCC is not applicable for the existing buildings. The
construction of existing buildings was done after getting approval from concerned
departments of Delhi.
Site Surroundings and Connectivity
LocationThe proposed site is connected to Delhi, Noida, and other NCR regions. It is surrounded by
places such as Supreme Court, Purana Qila and National Sports Club, Mandi House, Bappa
Nagar, Balmiki Basti and kaka Nagar within 5km of the area of the site.
Geographical co-ordinates of the site are given in Table
Table 2 : Geographical Co-ordinates of the site
Lattitude LongitudeCentre of the Plot 28°37'2.39"N 77°14'36.70"ECorner-1 28°36'47.50"N 77°14'52.64"ECorner-2 28°36'47.08"N 77°14'26.39"ECorner-3 28°37'7.91"N 77°14'25.95"ECorner-4 28°37'10.93"N 77°14'44.46"ECorner-5 28°37'25.43"N 77°14'34.90"ECorner-6 28°37'25.95"N 77°14'26.18"E
Site is well connected to transport facilities as well as surrounded by densely populated
areas. Pragati Maidan is flanked by Mathura Road to its West and Bhairon Road on the
South. To its east runs the main railway line to Central and Southern India. Pragati Maidan
is situated in Central Delhi and directly connected to India Gate and Purana Qila Road. On
the adjacent side, Pragati Maidan metro station and Pragati Maidan Bus terminal are
located.
Site surroundings and site connectivity within 15 km are shown in below table
Table 3 : Site Surroundings and Connectivity
S.No. Particulars Name Distance ‘n’
Direction 1. Nearest Railway Pragati Maidan Halt 0.3 Km in E
-
Station Tilak Bridge 0.8 Km in NW2. Nearest Airport Indira Gandhi
International Airport Safdarjung Airport
15.5 Km in SW
5 km in SW3. Nearest
Populated Area
Chandni Chowk Patparganj Government Officer
Colony
2.9 Km in N4.0 Km in E
0.5 Km in NW
4. State Boundary Delhi-UP stateBoundary
17.22 km in E
5. Nearest Highway NH-24 SH-57
2.5 km in ESE
2.45 km in N6. Nearest Road Mahatama Gandhi
Marg Mathura Road
0.57 km, E
Adjacent, W
7. Nearest Metro
station
Pragti Maidan Inderprasth
Adjacent to the site
0.6 km in NE8. Nearest School Modern School
Mater Dei School St. Coloumbia School Free School Under the
bridge
1.73 km in NW
0.69 km in SW
3.7 km in W
3.23 km in E9. Nearest Hospital Dr. Ram Manohar Lohia
Hospital Dr. Shroff Charity Eye
Hospital
4 km in WNW3.3 km
in NW
10. Place of worship Akshardham Temple Bangla Sahib
Gurudwara
3.10 km in E
3.5 km in NW
11. Water Bodies Yamuna River Old fort Lake
1.2 km in E
0.2 km in SW12. Forest Southern Ridge Forest 5.1 km in W
(Source: Google Earth Pro)
Google map and topographical map showing site and surroundings are given below.
-
Figure 1 : Google Map Showing Site and Its Surroundings (500 mtrs)
-
Salient features of the siteThe salient features of the project are as follow. The Pragati Maidan complex having Existing
building (retained) comprises of 7 Exhibition Halls (Hall No. 7 to Hall No. 13) however
proposed building is having 6 Exhibition halls. Buildings of various shapes and sizes; Eating
Figure 2 : Toposheet Map showing Site and Surroundings (5 km)
-
Outlets & Restaurants; Open Theatre and Auditorium for Performing Arts, Rock Concerts
and Cultural events;
Table 4 : Salient Features of the site
S. No. Description Proposed1. Plot Area 4,99,829.28 m2
2. Proposed Built Up Area (Retained +
Proposed)
3,97,249.559 m2
3. Maximum Height with Mumty 36.0mtrs4. Maximum No. of Floors G+55. Cost of Project6. Expected Population (Retained +
Proposed)
1, 68,676
7. Total Water Requirement 3,975 KLD 8. STP Capacity and Technology 2,200 KLD (MBR)9. No. of RWH Proposed 1010. Parking Proposed 4,806 ECS11. Solid Waste Generation 26,835.26 kg/day12. Total Power Requirement 17.51 MVA13. D.G. Set Back Up 18,740 kVA
Area DetailsThis is re development of existing exhibition space to integrated Exhibition-cum-Convention
Centre (IECC). Total area of the IECC site is Site is having plot area of 4, 99,829.28 m2 (49.98
Hectare).The retained (existing) building having 7 No. of blocks (From Hall No. 7-13) with
maximum height of G+1 (13.35 mtrs) however the proposed building is having 06 nos. of
blocks with maximum height of G+5 (36.0 mtrs).Total built up area of the site (Retained +
Proposed) Building is 3, 97,249.559 m2
Area details are given in table below.
Table 5 : Area Details of Retained (Existing) + Proposed Building
S.
No
.
Particulars Retained
(Existing)
Area (m2)
Proposed Area
(m2)
Total Area
(m2)
1. Plot Area (As per the Lease area) 4,99,829.282. Total Ground Coverage (A+B)
Permissible Ground Coverage (@40% of PA) (A) Add. G.C. for atrium (@10 % of PA)(B)
2,49,914.642
1,99,931.714
49,982.928
-
3. Total ground
coverage (Proposed)
Proposed Ground
Coverage Atrium Ground
coverage
28,654.750
-
92,357.115
3,561.524
1,24,573.389
@ 24.92 %
Plot area
4. Permissible FAR @1.2 5,99,795.1415. Proposed FAR @ 0.45
FAR of Halls (No.
7-13) FAR of Halls (No.
1-6) FAR of
Convention Hall FAR for Admin
Building Gate House
31,976.750
1,96,544.137
1,33,831.162
54,265.906
8,293.095
153.974
2,28,520.887
6. Basement area
Parking area Service area
- 1,65,144.672
1,47,392.521
17,752.151
1,65,144.672
7. Podium area 3,584 - 3,5848. Built Up Area 35,560.75 3,61,688.809 3,97,249.559
9. Open area 471,174.53 3,75,255.895 3,75,255.89510. Road and Paved area
Area under Surface Parking
1,14,066.200
5234.0211. Landscape (51.20 % of Plot Area) 2,55,955.67512. Maximum Height of
the Building (mtrs)
13.35 36.0
Ground Coverage and FAR DetailsGround coverage and floor wise details of each block (existing and proposed) blocks are givenin table.
Table 6 : Ground Coverage and FAR details of Retained (Existing) building
Block No. Storey Gr. Coverage F.A.R Height (mtrs)Hall no-07 G+1 8,495.000 9,885.000 13.35Hall no-08 G+1 460.400 1,113.400 13.00
-
Hall no-09 G+1 2,853.95 3,406.950 13.00Hall no-10 GR. FLOOR 1,818 1,818.000 13.00Hall no-11 G+1 6,682.4 7,408.400 13.00Hall no-12 GR. FLOOR 1,807 1,807.000 13.00Hall no-13 GR. FLOOR 6,538 6,538.000 13.00
Total 28,654.75 31,976.75
Table 7 : Ground Coverage and FAR Details of Proposed Building
Block No.Storey Gr. Coverage F.A.R
Height (mtrs)
Convention-hall G+4 25,898.774 54,265.906 31.500Hall-A1 G+1 9,853.919 20,621.058 29.100Hall A2 G+1 9,853.919 20,621.058 29.100Hall A3-A5 G+1 32,077.252 65,500.500 29.100Hall A6 G+1 13,136.220 27,088.546 29.100Admin building G+5 1,383.058 8,293.095 30.000Gate house Gr. Floor 153.97 153.974 4.500
Total 92,357.1151,96,544.13
7
Population Density
During Construction PhaseThe total manpower requirement during construction phase of the site will be anapproximate 250-300 person which includes workmen, labourers, supervisors, engineers,architect and Manager.
During Operational PhaseThe total population of the project (Retained building + Proposed) will be 1,68,676 personsthat include staff as well as Visitor population .The detailed population breakup includingStaff members as well as visitors is given in table below
Table 8 : Population Details for Retained (Existing) Building
S.No.
Description Floor Area(m2)
Occupant Load,Floor Area inm2/Person
TotalPopulation
1.Hall no-07
9,885.0001.5
6,590
2.Hall no-08
1,113.4001.5
742
3. Hall no-09 3,406.950 1.5 2,271
-
4.Hall no-10
1,818.0001.5
1,212
5.Hall no-11
7,408.4001.5
4,939
6.Hall no-12
1,807.0001.5
1,205
7.Hall no-13
6,538.0001.5
4,359
Total Population 21,318
Table 9 : Population Details for Proposed Building
S.No.
Description Floor Area(m2)
Occupant Load, Floor Area in m2/Person
TotalPopulatio
n
1. MAIN HALLS n ADMIN BUILDINGG-G Plenary Hall (Axial & Radial Partition) 3,246
0.6 5,410
Pre-function 3,234 0.6 5,390 Support facilities 1,662 10 166 Circulation 1,920 0.6 3,200 B-B Function Hall 5,495 0.6 9,158 Pre-function 1,280 0.6 2,133 Support facilities 1,774 10 177 Meeting spaces 15,030 0.6 25,050 Support Facilities and AmenitiesManagement Offices 147 10 15 VIP Lounges 246 10 25 Café 352 1.5 235 Reception 5,722 10 572 Business Centre 196 10 20 First aid rooms 38 10 4 Cloak rooms 60 10 6 Amphitheater Green rooms A 168
10 17
Amphitheater Green rooms B 212
10 21
Driver’s quarters 340 10 34 Additional Circulation 1,277 10 128 Security and Docks quarters
410 10 41
-
Pantry 75 10 8 Green Rooms 170 10 17 Additional room within Convention Centre 1,350
10 135
F& B 4,184 1.5 2,789 Business Centre 2,167 10 217 Amphitheatre 3,510 1.5 2,340 Admin building 8,293.095 10 829
25. EXHIBITION HALLSHalls A1-A6 1,33,831.16
21.5 89,221
Total Population (1+2) 1,47,358
Total population of Integrated Exhibition cum Convention Centre (IECC) will be 1,68,676.
Land Environment The site has been allotted to India Trade Promotion Organisation (ITPO), the premier
trade promotion agency of the Ministry of Commerce & Industry, Govt. of India for
conducting large exhibitions and conventions at Pragti Maidan, New Delhi. Perpetual lease has been made between President of India acting through Land &
Development Officer, Nirman Bhawan, New Delhi and Indian Trade Promotion
Organisation, Pragti Maidan, New Delhi.
Annexure 1 : Land Ownership Documents
Topography Physically the natural capital territory of Delhi can be divided into 3 segments - the
Yamuna flood plain, the Ridge and the Plain. The entire area of the national capital
territory of Delhi is categorized as Bangar or the plain. The land of the plain is mostly
fertile The entire area of the site is monotonously flat. The project area possesses plain terrain.
Highest elevation levels is 692 feet & the lowest levels is 685 feet
Water Environment (Requirement and Consumption)
-
Construction PhaseDuring the construction phase the water requirement (approx. 1900 ML) will be met from
Private water or treated wastewater from Nearby STP. No ground water will be extracted.
Hence, there will be no impacts on ground water environment during construction phase.
Operational Phase
Total water requirement for redevelopment of IECC Project (Existing + Proposed) is 3,975
KLD. Total domestic water requirement is approx 1,574KLD. The main sources fresh water
will be
DJB Registered tube wells within ITPO Complex.
However the secondary sources of the water are
Tanker supply (For Emergency Use only) Treated Effluent from an external centralized sewage treatment Plant
The existing source of water for the project is DJB. There are two existing metered tapings
from 450 mm diameter water pipe line, one of the connections is of 50 mm diameter and is
near gate no. 3 of ITPO while the other connection is of 150 mm diameter and is near gate
no.7. Water is supplied 24 x 7 to Pragati Maidan. There are existing 5 bore well and
additional 2 bore well will be dug to fulfill the present water demand.
Detail of water requirements for various uses is given in below table. Efficient dual flushing
fixtures will be provided for conservation of fresh water. The demand may vary depending on
the water conservation methods employed by the facility, which may include use of water
efficient fixture, use of dishwashers, water auditing and metering etc
Total quantity of wastewater generation will likely to be 2,295KLD. The generated sewage will
be collected and treated in the in-house Sewage Treatment Plant of 2,200 KLD capacity. The
treated wastewater will be re used for flushing and gardening and HVAC cooling. Water
Balance diagram during Non Rainy season and Rainy season are shown below.
Table 10 : Water Requirement during Operational Phase (Retained + Proposed) Building
S.No. Description Population/area (m2)
waterconsumption(litres/capita
Total waterrequired (KLD)
Water Requirement ForDomestic use
(KLD)
-
/day)1. Exhibition Halls (A1-13) 1,10,539 15
1,658.09 994.85
2. Main Halls0.00 0.00
G-G Plenary Hall (Axial & Radial Partition)
5,410 15 81.15 48.69
Pre-function 5,390 15 80.85 48.51Support facilities (Staff) 166 45 7.47 4.98Circulation 3,200 15 48.00 28.80B-B Function Hall 9,158 15 137.37 82.42Pre-function 2,133 15 32.00 19.20Support facilities (Staff) 177 45 7.97 5.31Meeting spaces 25,050 15 375.75 225.45Management Offices 15 45 0.68 0.45VIP Lounges 25 45 1.13 0.75Café 235 45 10.58 7.05Reception 572 45 25.74 17.16Business Centre 20 45 0.90 0.60First aid rooms 4 45 0.18 0.12Cloak rooms 6 45 0.27 0.18Amphitheatre Green rooms 38 45 1.71 1.14Other staff 363 45 16.34 10.89Business Centre 217 45 9.77 6.51F & B 2,789 15 41.84 25.10Amphitheatre visitors 2,340 15 35.10 21.06Admin Building 829 45 37.31 24.87Sub Total (1+2) 2,610.2 1,574.09
3. OTHER AREAS
Landscape (51.20 % of Plot Area)
2,55,955.6751 ltrs/day 256
HVAC** 11,445 TR 1,075 D.G. Cooling* 18,740 kVA 0.9l/kVA/hr 101Total (1+2+3) 3,975 KLD say
3.9 MLD*(D.G. sets operational hours are 6-8 hrs)
** HVAC cooling required fresh water demand during dry season in 632 KLD and 376 KLD during Monsoon.
Wastewater DetailsS.No. Details Water (KLD)
1. Fresh Water Requirement 1,574
2. Wastewater to be generated from domestic use (@80% of domestic wastewater)
1,259
-
T o ta l
W at e r
R eq u i
r em e
n t
Fresh
Water
Wastewater
T r ea t ed W at e r ( 18 36 K LD )
Flushing
T r ea t ed W at e r ( 18 36 K LD )
Hor
ti
cu
lt
ur
e
T r ea t ed W at e r ( 18 36 K LD )
HVAC
T r ea t ed W at e r ( 18 36 K LD )
D.G. Cooling
T r ea t ed W at e r ( 18 36 K LD )
Tr
ea
ted
Wa
te
r
Wastewater
T r ea t ed W at e r ( 18 36 K LD )
Flushing
T r ea t ed W at e r ( 18 36 K LD )
Hor
ti
cu
lt
ur
e
T r ea t ed W at e r ( 18 36 K LD )
HVAC
T r ea t ed W at e r ( 18 36 K LD )
D.G. Cooling
T r ea t ed W at e r ( 18 36 K LD )
3. Water Requirement for Flushing Purposes 1,036
4.Wastewater to be generated from Flushing (@100 % of Flushing Requirement) 1,036
5.Total Wastewater Generated (80% of fresh wastewater + 100% Flushing wastewater) 2,295 or say 2.2 MLD
-
Figure 3 : Water Balance Diagram during Dry Season
-
T o ta l
W at e r
R eq u i
r em e
n t
Fresh
Water
Wastewater
T r ea t ed W at e r ( 18 36 K LD )
Flushing
T r ea t ed W at e r ( 18 36 K LD )
T r ea t ed W at e r ( 18 36 K LD )
HVAC
T r ea t ed W at e r ( 18 36 K LD )
D.G. Cooling
T r ea t ed W at e r ( 18 36 K LD )
Tr
ea
ted
Wa
te
r
Wastewater
T r ea t ed W at e r ( 18 36 K LD )
Flushing
T r ea t ed W at e r ( 18 36 K LD )
T r ea t ed W at e r ( 18 36 K LD )
HVAC
T r ea t ed W at e r ( 18 36 K LD )
D.G. Cooling
T r ea t ed W at e r ( 18 36 K LD )
During Construction Phase
The quantity of sewage generation during the construction phase will be approx. approx. 11
KLD. Thus the sewage will be treated by providing small septic tanks, soak trenches and
sulabh shauchalaya type mobile toilets.
During Operational Phase
Quantity of sewage generated during operational phase shall be 2,295KLD. Thus the sewage
will be treated through sewage treatment plant of capacity 2,200 KLD. The treated sewage
will be re used for flushing (1,036 KLD) greenbelt development (256 KLD) and for HVAC (632
KLD during Non Monsoon Season and 376 KLD during Monsoon Season).
Figure 4 : Water Balance diagram during Monsoon Season
-
Sewage Treatment TechnologyThe design of sewage network shall be done in accordance with the CPHEEO guideline, NBC
guidelines and reverent Indian Standards. Sewage generation is assumed to be 100% of
flushing water and 80% of domestic water.
The following parameters/ site conditions shall be kept in mind when designing the sewage,
Sludge and storm water drainage system.
Natural slope of the area. Layout of different facility in the complex; Possibility of using complete or part of the existing sewage network; Sub-soil water table; Provision of Sewage lifting station; ( if required) Provision of venting arrangement for manholes; Construction of manholes & laying of pipes considering ground condition; Termination of vent cowl at terrace level; Provision of adequate slope for horizontal header in the under slung pipes especially
for public toilets Sewage flow starts with fractional capacity and builds up to full capacity in due
course. An operational plan to meet this demand from a low flow to full flow will be
part of the design.
A summary of board design parameters to be adopted for designing Sewage supply system is
given below.
Table 11 : Design Parameters for Sewage Collection System
Different Use Norm UsedType of Collection System Separate System Design Period -30 years for sewers and
appurtenances -15 years for pumps and electric equipment’s
Peak Factor 3 Minimum velocity 0.6 m/sec Maximum velocity 3.0 m/sec Minimum size of pipe 250 mm (ID) Minimum depth of Sewer 1.0 m from FGL (0.6 m minimum
cushion) Hydraulic Formula for calculation for design of sewer lines (As per CPHEEO manual 3.4.2.1 page no-36)
Manning’s formula V= 1/n*(R^2/3) *(S^1/2 ) V= Velocity R = Hydraulic mean depth = A/P S = Slope
Flow conditions in pipe up to 400 0.50 full
-
mm dia Flow conditions in pipe up to 300 mm dia
0.67 full
Manning’s Co-efficient ‘n’ 0.011 Shape of sewers Circular Material of sewers HDPE Manhole Sizes As per manual on sewerage and
sewerage treatment/ IS4111:1985 For depth above 0.9m & up to 1.65m
900 mm diameter
For depth 1.65m & up to 2.3m 1200 mm diameter For depth 2.3m & up to 9.0m 1500 diameter
Technology Proposed- MBR (Membrane Bio Reactor)The MBR is a suspended growth-activated sludge system that utilizes micro porous
membranes for solid/liquid separation instead of secondary clarifiers.
An external sewage network shall collect the sewage from all units, and flow by gravity to the
proposed sewage treatment plant.
Following are the benefits of providing the Sewage Treatment Plant in the present
circumstances:
Reduced net daily water requirements, source for Horticultural purposes by
utilization of the treated wastewater. This shall consequently lead to a lower
withdrawal from the underground aquifer water sources.
Reduced dependence on the public utilities for water supply and sewerage
systems.
Sludge generated from the Sewage Treatment Plant shall be rich in organic
content and an excellent fertilizer for horticultural purposes.
The STP is being proposed with state-of-the-art membrane separation technology called as
Membrane Bio-Reactor (MBR) which can produce very good quality with highest possible
bacterial reduction without adding any chemicals. MBR (Membrane Bio Reactor) is the latest
technology in wastewater treatment. MBR has many advantages such as higher quality of
treated water, smaller space for installation and easier operation compared to conventional
activated sludge process.
-
Designed to produce high quality treated water from wastewater the Membrane Bio Reactor
(MBR) is among the latest technologies in biological treatment.
The characteristic of the MBR process is the use of revolutionary submerged polymeric
hollow fibre membranes in the biological process water tank, so as to produce high quality
permeate from domestic sewage, primary and secondary waste water, cooling tower blow
down etc. The MBR is also ideal for retrofitting/augmenting capacity/quality of existing
wastewater plants.
The hollow fibers are combined into bundles and wound around a carrier cartridge, which
gives the membranes the required strength and allows for high-pressure air scour for
cleaning. The MBR can handle very high sludge concentrations in the aeration tank because
of which the size of the aeration tank reduces four to five folds. As the membrane acts as a
fine filter, it does not require any further treatment using sand filters, activated carbon
filters, etc. The MBR is available in standard and customized modules.
Process Description
Figure below shows the principle of the filtration for the flat sheet type submerged
membrane. Activated sludge in the aeration tank is clearly removed by the flat sheet type
submerged membrane. The membrane module consists of housing, aeration diffuser;
permeate water manifold and membrane elements. The membrane element consisting of flat
sheet membranes sandwiching a support panel is set up vertically. Feed water including
activated sludge is filtrated by flat sheet membranes with pore size of 0.1 micron meter. The
air bubbles supplied from the bottom of the membrane elements continuously scour off cake
of activated sludge accumulated on the membrane surface. This is continuous filtration
operation. The air bubbles are also used for the biological reaction to decompose organic
substances included in the raw sewage.
-
Figure 5 : Schematic Diagram of MBR Technology
MBR Module
The material of the membrane is PVDF (Poly vinylidene fluoride). PVDF is fluorine polymer,
which has high stability for chemicals and good physical strength. The form of membrane is
fibre reinforced flat sheet membrane. The membrane has small and uniform pore size.
Therefore, the rejection property of this membrane is excellent. Almost all particles with sizes
more than 0.1 micron meter can be removed effectively using this membrane.
Operation
Sewage from main drain line is collected through gravity pipes into a screen chamber.
This manually cleaned screen is provided to remove floating and big size particles, which
may choke the pumps and pipe lines.
Screened sewage is then passed through equalization tank to homogenize the sewage
quality and also even out flow fluctuations and feed sewage of uniform quality at constant
rate to subsequent treatment units. Air mixing is also provided to mix the contents of the
equalization tank. A coarse bubble aeration grid is provided to distribute air uniformly at
-
the base of the equalization tank.
After above treatment, raw sewage is fed into aeration basin.
In aeration tank, MLSS (mixed liquor suspended solids) in the range of 12000 to 15000
mg/l are maintained. The high amount of bacteria gives better and complete removal of
organic matter from the raw sewage in relatively small area. Oxygen required for the
bacteria is supplied through the blower. The air is used both for scouring of membranes
and supplying oxygen to bacteria.
The filtration is carried out by the suction pump directly sucking permeates water. The
permeate water produced is clear and devoid of bacteria and viruses to the minimum
levels.
As the membranes are continuously under operation, they are polluted with organic or
inorganic substances. Hence, chemical cleaning is carried out once in two to three
months for removing substances polluting and clogging the membranes. Normal cleaners
used are sodium hypo chloride and citric acid.
Sewer System
The alignment and slope of the sewer line will follow the road network, drains or natural
ground surface and will be connected to the trunk sewers. The discharge point will be a
treatment plant, a pumping station, a water course or an intercepting sewer. Pumping
stations would be provided at places where the natural slope of the terrain is insufficient to
permit gravity flow or the cost of excavation is uneconomical to do the same
Table 12 : Wastewater Details
Particulars QuantityDaily load 2,295KLDDuration of flow to STP 24 HoursTemperature 320 C
Inlet Outlet (Treated Wastewater )pH 6.0 – 9.0 7.0-8.0T.S.S. (mg/l) 300-400
-
treated wastewater pipes will be laid in conduits wherever road crossings are expected. Thus
no leaching of treated sewage into nearby water courses shall take place. Supervisors will be
employed for overall operation & maintenance of water supply, waste water treatment and
other utility services.
Rainwater Harvesting and Strom Water DrainA rainwater harvesting system comprises components of various stages -transporting
rainwater through pipes or drains, filtration, and recharging the ground water through
tanks. Percolation structures will be constructed for ground water recharge.
Runoff from the first spell of rain carries a relatively large amount of pollutants from the air
and catchments surface so the system will be provided with a filtration pit consisting of
layers of sand, gravel and pebbles of relevant sizes to remove impurities from the collected
rainwater.
Need for Rainwater HarvestingSurface water is inadequate to meet the daily demand and we have to depend on groundwater.
Due to rapid urbanization, infiltration of rain water into the sub-soil has decreaseddrastically and recharging of ground water has diminished.
Rainwater harvesting prevents the flooding of low-lying areas in the site.
Rainwater Harvesting NetworkRain water harvesting structures will be constructed all around the compound wall to collect
rain water. Excess storm water will be allowed to drain into the external storm drain.
Rain water harvesting has been catered to and designed as per the guideline of CGWA. Peak
hourly rainfall has been considered as 11 mm/hr. The recharge well of 10 mtr dia and 10
mtr depths and 4 mtrs width will be constructed for recharging the water. The bottom of the
recharge structure will be kept 5 m above this level. At the bottom of the recharge pit, a filter
media is provided to avoid choking of the recharge bore.
The pit will be filled with rounded gravel 5 to 10 mm size. The sectional detail of the
proposed rain water recharge structure is provided in below figure.
The path ways around the harvesting lines will be graded to facilitate drainage into trenches
proposed around the compound. Recharge wells/structures are envisaged along the path of
-
the storm water drains for rain water recharging & surplus water from the recharge
wells/structures shall be diverted to the storm water drainage network.
The collected storm water will be allowed to percolate to the sub-soil by suitably designed
percolation structures. The structures will be designed based on the soils percolation
capability. The subsoil water table is high in these areas and however harvesting structures
with bores will be provided.
Percolation structures of suitable numbers will be provided for recharge of ground water
potential. A total of 10 rain water harvesting structures will be constructed. The quantity of
storm water load for the proposed construction project is given below.
Table 13 : Calculation for Strom Water Load for the Development of IECC
S. No.
Type of Surface
Catchment's Area Run off Coff. [C]
Intensity of Rainfall (mm/hr)
Discharge (Run Off) [Q=10CIA] m3/hr
Total(m3/hr) [Q]
sq. m Ha.
1 Building (Terrace)
(a) Area 1,40,169.75 14.01 0.60 80 10×0.60×80×14 6,720
1,80,482.31 18.04 0.20 80 10×0.20×80×18 2,886.4
1,55,409 15.54 0.75 80 10 ×0.75×80×15 9,000
Total 18,606.4
(b) Considering 15 mins (0.25) retention period 4,651.6
(c) Volume of Rain water Storage Structure 10×4×4 160 m3
(d) Total No. of Rain water Storage Structure required 29.07Total No. of Rain water Storage Structure Proposed 10
-
Figure 6 : Rainwater Harvesting Structure
Efficacy of Rain Water HarvestingThe area of site has the water table at 3.0 M. It is not advisable to recharge aquifer by rain
water in areas with water table less than 8.0 M. In this case, following is recommended: -
Use the storm water to recharge lake next to Old Fort, subject to approval by ASI &additional cost of connectivity. This will automatically mean water harvesting throughpercolation.
Use the storm water to run chillers cooling towers after tertiary treatment during themonsoons. The treated effluent being received from DJB will not be drawn during thisperiod. The facility management team must ensure the same.
Parking DetailsAdequate provision will be made for car/vehicle parking at the project site. There shall be
adequate parking provisions for visitors so as not to disturb the traffic and allow smooth
movement at the site.
-
Proposed project will be consists of basement and open parking. The parking space criteria
and area requirement provided are summarized in the table below. Parking details are
designed as per Delhi Building Bye Laws
Table 14 : ECS Required
As Per DDAParking Required Area (m2) Total (ECS)For the Site 2 ECS/100
m2 of FAR
area
2,28,520.887/
50
2,28,520.887
4,570
Total Parking Required
(ECS)
4,570
Table 15 : Parking Proposed
Description Area
Required for
1 ECS
Area (m2) Parking
Proposed
( ECS)In Basement 1 ECS/32 m2
of area
1,47,392.5
2
4,606
In Open 1 ECS/23 m2
of area
1,649.580 72
In podium 1ECS/28 m2 3,584.440 128Total Parking Proposed
(ECS)
4,806
TWO WHEELER 1000 × 0.5 500ECSBUSES 52 × 3.5 182 ECSCARS 4,124 × 1 4,124 ECS
Electrical details
Power DetailsThe power shall be supplied by BSES Delhi. The total demand load for the project (Retained
Building + Proposed) will be 17.51 MVA. It is proposed to install 2 Electrical subs- Station
named MRS-1 and MRS-2.
-
MRS-1 shall receive 2 Nos. 33KV supplies from BSES and feed electrical power at 11KV to
Hall A1, A2, A3, A4a, A4b, A5 and A6 by providing 2 Nos. 7.5 MVA 33/11KV and it shall be
located near Hall A5
MRS-2 shall receive 1 No. 33KV supply from BSES and feed electrical power at 11KV to
Convention Center and Admin Block by providing 1 Nos. 6 MVA 33/11KV and it shall be
located near Hall A6. 2 Nos. 33kV meter room shall be located for MRS-1 (near Hall A5) and
1 No. 33KV meter room for MRS-2 shall be near Hall Admin Block at the Ground Level.
For the MRS I, 2 numbers of (7.5 MVA), 33/11 kV, oil types outdoor transformers has been
selected. For MRS II, 1 number of (6 MVA), 33/11 kV, oil types outdoor transformers has
been selected
D. G. Sets Details
In case of power failure, there are 2 Nos. 11 KV DG rooms with corresponding 2 Nos. MRS .it
provides the 100% power back up for the development. The location of DG rooms shall be
either at the ground or in Basement. D.G. sets location and their description is given below.
Table 16 : D.G. sets location and their description
S.No. Description Feed1. DG Room-1 (For Hall A1, A2, A3, A4a,
A4b, A5 and A6)
6 Nos. 2MVA & 2Nos.
2.5MVA, 11KV DG Sets2.
DG Room-2 (For Hall A6 and Admin Block)4 Nos. 2MVA, 11KV DG
Sets
Lighting systemLighting systems with green features to be used for this project are:
Solar Street Lightings. LED lights over T5 or T8 Fluorescent lightings.
Lighting Control through day lighting and sensor Motion
It is proposed to use Presence/Occupancy sensors in common areas like corridor, Lift Lobby,Toilets etc. which will result in considerable saving of energy.
Two way programmable High performance, compact presence detectors /occupancy
sensors will be used which provide automatic control for lighting loads. It detects human presence and automatically turns the lights ‘ON’. When the area is
vacated, the lights turn ‘OFF’ after a preset time period.
-
The sensor has advanced presence detection by passive infrared (PIR) technology along
with Sensitivity level adjustments. The sensor has Adjustable off delay timing 10 sec –
99 min which can be programmed & changed using a remote control. The sensor has a Passive photocell that holds lights OFF in extremely bright ambient
conditions. The occupancy cum day light sensors will be used which are used for switching off the
luminaries when the areas are unoccupied & also used for dimming the luminaries
when there is day light coming inside the building & thus help to reduce the power
consumption. This sensor is basically used in the areas along the building façade where the day
light contribution is high. Along with presence detection, this sensor has built-in
adjustable photocell which regulates the lighting level as per availability of natural
daylight in an area, thus maintaining uniform illumination.
Integrated Fire Detection SystemThis will comprise of below mentioned components.
Intelligent addressable Fire Detection system with communication, notification &
Interface capability. Manual call points for activation of fire alarm system manually. Integrated Emergency Voice Evacuation System. Interlocking with other equipments likes Elevators, Air-conditioning Units, Smoke
Extraction system etc.
Solid Waste Details
During Construction Phase of the Proposed Building
The solid waste expected to be generated during the construction phase will comprise of
excavated materials, used bags, bricks, concrete, MS rods, tiles, wood etc. The following
steps are proposed to be followed for the management solid waste:
Construction yards are proposed for storage of construction materials. The excavated material such as topsoil and stones will be stacked for reuse during
later stages of construction. Excavated top soil will be stored in temporary constructed soil bank and will be reused
for landscaping during operational phase of the project. Remaining soil shall be utilized for refilling / road work / rising of site level at
locations/ selling to outside agency for construction of roads etc.
-
Construction
n Demolition
Waste
Construction
waste,Broken
bricks,Waste
plaster
Re
filling,Raising
Site
Level
Empty
Cement
Bags
Road
Making
Excavated
Soil
Top soil
conserved
for
landscaping
and
refilling
the
site
Demolish waste
Handed over to Govt
. approved agency for fi
nal disposal
Construction waste management is shown in below figure.
Figure 7 : Solid Waste Management for Construction Phase
C & D waste of Existing Buildings
Construction and demolition waste of the site shall be keep within the premises. The waste shall be deposited at collection centre so made by the local body or
handover it to the authorized processing facilities for further process or disposal. As inert it shall be used to fill material for low -lying areas, landscaping, Road Making
etc. Finer grade can be molded into blocks and slabs with appropriate binder.
During Operational Phase
The project will adopt a systematic approach for solid waste collection and disposal. Solid
waste generated from the project will be collected properly and will be managed as per MSW
Rules, 2000 amended in 2016.
Waste shall be mainly categories in two classes. 1. Bio degradable Waste 2 Non-
biodegradable Waste. The biodegradable portion dominates the bulk of MSW. This is
mainly due to food and yard waste. These solid wastes will be collected separately by putting three types of separate bins
at the source of generation. For the biodegradable waste yellow bins will be provided,
for the recyclable waste black bins and for the non-recyclable waste red bins will be
provided. It is estimated that maximum solid waste generation would be about 26,835.26 kg/day;
Following are the solid waste generation rate has been considered as is given table.
-
Table 17 : Calculation of Solid Waste Generation of Retained and Proposed Building
S.No. Category Counts(heads)
Westegeneration(p/kg/day)
WasteGenerated(kg/day)
For the Retained and Proposed Building
1. Staff Support
Facilities343
@ 0.25kg/day
671.7541.50
ManagementOffice
1544.25
VIP Lounges 25 3.75 Café 235 6.25 Reception 572 58.75 Business Centre 20 143.00 First Aid Rooms 4 5.00 Cloak rooms 6 1.00
AmphitheatreGreen Rooms
381.50
Other staff 383 9.50 Business Centre 217 95.75 Admin Building 829 207.25
2. Visitors Exhibition Halls
(A1-A13)1,18,894
@ 0.15kg/day
26,154.60
17,834.10
G-G PlenaryHall (Axial &Radial Partition)
5,410811.50
Pre- Function 5,390 808.50
Circulation 3,200 480.00 B-B Function
Hall9,158
1,373.70
Pre- Function 2,133 319.95 Meeting Spaces 25,050 3,757.50 F& B 2,789 418.35 Amphitheatre
Visitors2,340
351.00
Total Domestic Waste (1+2)
26,826.35
11. Landscape waste(44.59 Acre)
@ 0.2 kg/acre/da
8.91
-
y
Total Wastegenerated (1-3)
26,835.26 kg/day
(Source:http://cpheeo.nic.in/WriteReadData/Cpheeo_SolidWasteManagement/chap3.pdf )
Following arrangements will be made at the site in accordance to Municipal Solid Wastes(Management and Handling) Rules, 2000 and amended Rules; 2016.
Collection and Segregation of waste
For Domestic Waste
A door to door collection system will be provided for collection of domestic waste in
colored bins from every unit. The local vendors will be hired to provide separate colored bins for dry recyclables and
Bio-Degradable waste. For waste collection, adequate number of colored bins (Green and Blue & dark grey
bins– separate for Bio-degradable and Non Bio-degradable) are proposed to be
provided at the strategic locations of the area. Litter bin will also be provided in open areas like parks etc.
Treatment of Waste
Domestic Waste
Bio degradable Waste
Bio-degradable waste will be subjected to the compost/resultant will be used as
manure. STP sludge is proposed to be used for horticultural purposes as manure. Horticultural Waste is proposed to be composted and will be used for gardening
purposes.
Recyclable Waste
The cropped grass will be spread on the green area. It will act as manure after
decomposition. Recyclable wastes like paper, plastic, metals etc. will be sold off to recyclables.
Disposal
Recyclable and non-recyclable wastes will be disposed through Govt. approved agency.
Hence, the Municipal Solid Waste Management t will be conducted as per the guidelines of
http://cpheeo.nic.in/WriteReadData/Cpheeo_SolidWasteManagement/chap3.pdf
-
Solid waste
Non Biodegradable Waste
Recyclable
Blue bins
to Govt. approved Vendor
Non-Recyclable
Dark Grey Bins
to govt. approved agency
Biodegradable Waste
Green bins
Composter
Manure
Municipal Solid Wastes (Management and Handling) Rules, 2000 and amended Rules, 2016.
Solid waste management Scheme is depicted in the following figure.
Figure 8 : Solid Waste Management Scheme -Domestic Waste
Landscape Details Total green area measures 2,55,955.675m2 (51.20 % of Plot Area) A diverse variety of indigenous evergreen and ornamental trees would be planted. As
the project site for construction consists of trees, herbs and shrubs it will require
cutting of trees for construction purpose. Total number of trees planted will be 6,713. However nos of trees retained will be 913. The plant species will be selected on the basis of Urban Standard Plantation norms
and CPCB guidelines. Landscape Details are given in below table
Table 18 : Landscape Area Details
Particulars DetailsPlot area 4,99,829.28 m2
Open area 3,75,255.895 m2
Landscape area Proposed 2,55,955.675m2 (51.20 % of Plot Area)As Per MoEF Guidelines One tree per 80 m2 of total area out of which
minimum 50 % to be in the category ofevergreen trees.
-
Trees Required 4,99,829.28/80= 6,247.866 TreesNumber Of Trees Proposed ToBe Planted
6,713 Trees (Existing Trees Retained= 913)
Energy
Conservation Measures CFC free equipment, chillers with CFC-free environmentally friendly refrigerant will be
installed to protect the ozone layer.
Table 19 : Plantation List
-
The Building envelope details has been followed as per ECBC to reduce heat intakefrom outside. Walls, roofs and glass U values will be less than the ASHRAE Standard90.1 2007 to save energy compared to baseline building energy consumption.
Lighting power densities are expected to be less than the ASHRAE Standard 90.1 2007base line to save energy compared to baseline building criteria.
Provision and space allocation for energy metering will be provided for the followingsystem loads for continuous monitoring:
Air conditioning Internal lighting External lighting Treated Effluent water pumping Landscape water pumping
Solar water supply shall be restricted to kitchens. The DG set will be ISI rated and certified by the central pollution control board (CPCB)
for emission and noise. Level controllers in water tanks will be provided to avoid overflow of water and waste of
energy All pumps will be ISI rated with a minimum 60% efficiency LED lamps will be provided in all display/exit sign boards to save energy Movement sensors for lighting control will be provided in toilets, study rooms,
staircases, cabins, corridors, garbage rooms, balconies, washing and storage areas Provision of 50% solar PV panel with LED Street lighting for the external area with
50% based on conventional LED Street lighting to be subjected to GRIHA Consultantadvice.
Provision of LED lighting over T5 fluorescent lighting.
List of the construction Material UsedList of building materials being used at site:
1. Coarse sand2. Fine sand3. Stone aggregate4. Stone for masonry work5. Cement6. Reinforcement steel7. Pipe scaffolding (cup lock system)8. Bricks9. ACC Blocks10. Crazy (white marble) in grey cement P.V.C. conduit11. MDS, MCBs12. PVC overhead water tanks13. 2 1/2'’ thick red colour paver tiles14. PPR (ISI marked)15. PVC waste water lines16. S.W. sewer line up to main sewer
-
17. PVC rain water down take18. Stainless steel sink in kitchen
IntroductionGeneralBrief about Project ProponentProject ConsultantBrief about Project
Site Surroundings and ConnectivityLocation
Salient features of the siteArea DetailsGround Coverage and FAR Details
Population DensityDuring Construction PhaseDuring Operational Phase
Land EnvironmentTopography
Water EnvironmentConstruction PhaseOperational PhaseWastewater DetailsSewage Treatment TechnologyTechnology Proposed- MBR (Membrane Bio Reactor)Process DescriptionMBR ModuleOperationSewer System
Preventive measures to Avoid LeachingRainwater Harvesting and Strom Water DrainNeed for Rainwater HarvestingRainwater Harvesting NetworkEfficacy of Rain Water Harvesting
Parking DetailsElectrical detailsPower DetailsD. G. Sets Details
Lighting systemLighting Control through day lighting and sensor MotionIntegrated Fire Detection System
Solid Waste DetailsDuring Construction Phase of the Proposed BuildingC & D waste of Existing BuildingsDuring Operational PhaseCollection and Segregation of wasteTreatment of WasteDisposal
Landscape DetailsEnergy Conservation MeasuresList of the construction Material Used