(conceptual plan) forenvironmentclearance.nic.in/writereaddata/online/tor/06... · 2017. 4. 6. ·...

39
ENVIRONMENT CLEARANCE (Conceptual Plan) For Integrated Exhibition cum Convention Centre (IECC) (Redevelopment of ITPO Complex at Pragti Maidan) Submitted By India Trade Promotion Organisation (ITPO)

Upload: others

Post on 06-Feb-2021

0 views

Category:

Documents


0 download

TRANSCRIPT

  • ENVIRONMENT CLEARANCE(Conceptual Plan)

    For Integrated Exhibition cum Convention

    Centre (IECC)

    (Redevelopment of ITPO Complex at Pragti Maidan)

    Submitted ByIndia Trade Promotion Organisation (ITPO)

  • ContentsIntroduction..................................................................................................5

    General......................................................................................................5

    Brief about Project Proponent....................................................................5

    Project Consultant.....................................................................................6

    Brief about Project.....................................................................................6

    Site Surroundings and Connectivity..............................................................7

    Location.....................................................................................................7

    Salient features of the site...........................................................................12

    Area Details................................................................................................12

    Ground Coverage and FAR Details............................................................14

    Population Density......................................................................................15

    During Construction Phase......................................................................15

    During Operational Phase........................................................................15

    Land Environment......................................................................................16

    Topography..............................................................................................17

    Water Environment.....................................................................................17

    Construction Phase..................................................................................17

    Operational Phase....................................................................................17

    Wastewater Details...................................................................................20

    Sewage Treatment Technology..................................................................23

    Technology Proposed- MBR (Membrane Bio Reactor)..............................24

    Process Description...............................................................................26

    MBR Module.........................................................................................28

    Operation..............................................................................................28

    Sewer System........................................................................................29

  • Preventive measures to Avoid Leaching.....................................................29

    Rainwater Harvesting and Strom Water Drain..........................................29

    Need for Rainwater Harvesting.................................................................30

    Rainwater Harvesting Network.................................................................30

    Efficacy of Rain Water Harvesting............................................................32

    Parking Details............................................................................................33

    Electrical details.........................................................................................34

    Power Details...........................................................................................34

    D. G. Sets Details..................................................................................34

    Lighting system........................................................................................34

    Lighting Control through day lighting and sensor Motion.........................35

    Integrated Fire Detection System..............................................................35

    Solid Waste Details......................................................................................36

    During Construction Phase of the Proposed Building...............................36

    C & D waste of Existing Buildings............................................................37

    During Operational Phase........................................................................37

    Collection and Segregation of waste.......................................................39

    Treatment of Waste................................................................................39

    Disposal................................................................................................40

    Landscape Details.......................................................................................41

    Energy Conservation Measures...................................................................43

    List of the construction Material Used.........................................................44

    List of Figures

  • Figure 1: Google Map Showing Site and Its Surroundings (500 mtrs)..........10Figure 2: Toposheet Map showing Site and Surroundings (5 km).................11Figure 3 : Water Balance Diagram during Dry Season.................................21Figure 4: Water Balance diagram during Monsoon Season..........................22Figure 5: Schematic Diagram of MBR Technology........................................27Figure 6: Rainwater Harvesting Structure...................................................32Figure 7: Solid Waste Management for Construction Phase.........................37Figure 8: Solid Waste Management Scheme -Domestic Waste......................41

    List of TablesTable 1: Project Consultants Involved............................................................6Table 2: Geographical Co-ordinates of the site...............................................7Table 3: Site Surroundings and Connectivity.................................................8Table 4: Salient Features of the site.............................................................12Table 5: Area Details of Retained (Existing) + Proposed Building.................13Table 6: Ground Coverage and FAR details of Retained (Existing) building...14Table 7: Ground Coverage and FAR Details of Proposed Building................14Table 8: Population Details for Retained (Existing) Building.........................15Table 9: Population Details for Proposed Building.......................................15Table 10: Water Requirement during Operational Phase (Retained + Proposed) Building...................................................................................................................19Table 11: Design Parameters for Sewage Collection System.........................24Table 12: Wastewater Details.......................................................................29Table 13: Calculation for Strom Water Load for the Development of IECC....31Table 14: ECS Required...............................................................................33Table 15: Parking Proposed.........................................................................33Table 16: D.G. sets location and their description.......................................34Table 17: Calculation of Solid Waste Generation of Retained and Proposed Building 38Table 18: Landscape Area Details................................................................41Table 19: Plantation List.............................................................................43

    AnnexureAnnexure 1: Land Ownership Documents..................................................17

    CONCEPTUAL PLANCONCEPTUAL PLAN

    file:///E:%5CDELHI%5CITPO%5CProposal%5Creconceptualplanforieccdiscussedon16_03_2017%5C01%20ITPOS-%20Conceptual%20Plan%20F2.docx#_Toc477871339file:///E:%5CDELHI%5CITPO%5CProposal%5Creconceptualplanforieccdiscussedon16_03_2017%5C01%20ITPOS-%20Conceptual%20Plan%20F2.docx#_Toc477871340file:///E:%5CDELHI%5CITPO%5CProposal%5Creconceptualplanforieccdiscussedon16_03_2017%5C01%20ITPOS-%20Conceptual%20Plan%20F2.docx#_Toc477871341file:///E:%5CDELHI%5CITPO%5CProposal%5Creconceptualplanforieccdiscussedon16_03_2017%5C01%20ITPOS-%20Conceptual%20Plan%20F2.docx#_Toc477871342file:///E:%5CDELHI%5CITPO%5CProposal%5Creconceptualplanforieccdiscussedon16_03_2017%5C01%20ITPOS-%20Conceptual%20Plan%20F2.docx#_Toc477871365

  • Introduction

    General The Ministry of Environment, Forest and Climate Change has notified the

    Environmental Impact Assessment (EIA) Notification, 2006 under the provisions of the

    Environment (Protection) Act, 1986, which regulates development and their

    expansion/modernization of 39 sectors/activities listed in the Schedule to the EIA

    Notification, 2006. As per the EIA Notification 2006, all the building construction projects/Area

    Development projects and Township Projects comes under schedule 8 and projects

    covering an area ≥ 50 ha and/or built up area ≥1,50,000 sq .mtrs they come under

    schedule 8 (b). All projects under Item 8(b) shall be appraised as Category B1. The application for environmental clearance shall comprise submission of Form 1,

    Form 1A, and Conceptual Plan along with EIA/EMP Report incorporated proposed ToR

    in SEIAA. The EIA/EMP shall be prepared on the basis of Approved ToR issued from

    SEAC and will be submitted to the SEAC for appraisal and due recommendation and

    suggestions. Following the appraisal of the project to the satisfaction of the SEAC and

    SEIAA, Environmental Clearance shall be granted.Total Built up area of the proposed site is 3, 97,249.559 m2.

    Brief about Project Proponent India Trade Promotion Organization (ITPO) is the nodal agency of the Government of

    India under aegis of Ministry of Commerce and Industry (India) for promoting

    country's external trade. ITPO is a Mini-Ratna Category-1 Central Public Sector

    Enterprise (CPSE) with 100 percent shareholding of Government of India. ITPO, during its existence of more than 5 decades has played a proactive role in

    catalysing trade, investment and technology transfer processes. Its promotional tools

    include organising of fairs and exhibitions in India and abroad, Buyer-Seller Meets,

    Contact Promotion Programmes, Product Promotion Programmes and Promotion

    through Overseas Department Stores, Market Surveys and Information Dissemination.

    Project ConsultantDetails regarding Project consultants involved are given below;

  • Table 1 : Project Consultants Involved

    Project Team Details

    Architects

    Aedas Architects Unit 133, Rectangle One,D4 District Centre Saket,New Delhi, Delhi 110017Arcop Associates (P) Ltd.A-15, Pamposh Enclave, Greater Kailash - 1, New Delhi-110048 India

    Environment Consultant

    Envision Enviro Technologies Pvt. Ltd.A-73, Noida-201301

    Landscape Architect Pravin KhotMEP Consultant Meinhardt India Pvt Ltd

    A-8 , Sector 16 Noida-201301

    Project Management Agency (PMA)

    NBCC (India) LimitedNBCC Bhawan, Lodhi RoadNew Delhi - 110 003, India

    Brief about Project

    Pragati Maidan is a venue for large exhibitions and conventions in New Delhi with

    65,000 m2 of existing exhibition space is now re-develop into Integrated Exhibition-

    cum-Convention Centre (IECC) with Approx. 3,61,688.809 m2 of built up area having

    Convention Center & Exhibition Halls building development in Phases-1 facilities like

    car parking for visitors a single basement also planned. Proposed development will

    become Delhi's & North India's largest exhibition centre owned and managed by India

    Trade Promotion Organization (ITPO) The design comprises of an iconic convention centre& exhibition- halls. Considerations

    have been made for the use of environment friendly materials to achieve Green

    Building Features. Overall layout of the project includes convention centre, exhibition

    halls, Restaurants, Business centre, open exhibition space with parking basement.

  • The existing buildings were constructed and also became operational prior to the

    publication of EIA Notification 2006. Therefore, the existing buildings did not attract

    applicability of to obtain Environmental Clearance from SEIAA/MoEFCC and no

    environmental clearance was issued. Accordingly, the issuance of certified monitoring

    report by Regional Director of MoEFCC is not applicable for the existing buildings. The

    construction of existing buildings was done after getting approval from concerned

    departments of Delhi.

    Site Surroundings and Connectivity

    LocationThe proposed site is connected to Delhi, Noida, and other NCR regions. It is surrounded by

    places such as Supreme Court, Purana Qila and National Sports Club, Mandi House, Bappa

    Nagar, Balmiki Basti and kaka Nagar within 5km of the area of the site.

    Geographical co-ordinates of the site are given in Table

    Table 2 : Geographical Co-ordinates of the site

    Lattitude LongitudeCentre of the Plot 28°37'2.39"N 77°14'36.70"ECorner-1 28°36'47.50"N 77°14'52.64"ECorner-2 28°36'47.08"N 77°14'26.39"ECorner-3 28°37'7.91"N 77°14'25.95"ECorner-4 28°37'10.93"N 77°14'44.46"ECorner-5 28°37'25.43"N 77°14'34.90"ECorner-6 28°37'25.95"N 77°14'26.18"E

    Site is well connected to transport facilities as well as surrounded by densely populated

    areas. Pragati Maidan is flanked by Mathura Road to its West and Bhairon Road on the

    South. To its east runs the main railway line to Central and Southern India. Pragati Maidan

    is situated in Central Delhi and directly connected to India Gate and Purana Qila Road. On

    the adjacent side, Pragati Maidan metro station and Pragati Maidan Bus terminal are

    located.

    Site surroundings and site connectivity within 15 km are shown in below table

    Table 3 : Site Surroundings and Connectivity

    S.No. Particulars Name Distance ‘n’

    Direction 1. Nearest Railway Pragati Maidan Halt 0.3 Km in E

  • Station Tilak Bridge 0.8 Km in NW2. Nearest Airport Indira Gandhi

    International Airport Safdarjung Airport

    15.5 Km in SW

    5 km in SW3. Nearest

    Populated Area

    Chandni Chowk Patparganj Government Officer

    Colony

    2.9 Km in N4.0 Km in E

    0.5 Km in NW

    4. State Boundary Delhi-UP stateBoundary

    17.22 km in E

    5. Nearest Highway NH-24 SH-57

    2.5 km in ESE

    2.45 km in N6. Nearest Road Mahatama Gandhi

    Marg Mathura Road

    0.57 km, E

    Adjacent, W

    7. Nearest Metro

    station

    Pragti Maidan Inderprasth

    Adjacent to the site

    0.6 km in NE8. Nearest School Modern School

    Mater Dei School St. Coloumbia School Free School Under the

    bridge

    1.73 km in NW

    0.69 km in SW

    3.7 km in W

    3.23 km in E9. Nearest Hospital Dr. Ram Manohar Lohia

    Hospital Dr. Shroff Charity Eye

    Hospital

    4 km in WNW3.3 km

    in NW

    10. Place of worship Akshardham Temple Bangla Sahib

    Gurudwara

    3.10 km in E

    3.5 km in NW

    11. Water Bodies Yamuna River Old fort Lake

    1.2 km in E

    0.2 km in SW12. Forest Southern Ridge Forest 5.1 km in W

    (Source: Google Earth Pro)

    Google map and topographical map showing site and surroundings are given below.

  • Figure 1 : Google Map Showing Site and Its Surroundings (500 mtrs)

  • Salient features of the siteThe salient features of the project are as follow. The Pragati Maidan complex having Existing

    building (retained) comprises of 7 Exhibition Halls (Hall No. 7 to Hall No. 13) however

    proposed building is having 6 Exhibition halls. Buildings of various shapes and sizes; Eating

    Figure 2 : Toposheet Map showing Site and Surroundings (5 km)

  • Outlets & Restaurants; Open Theatre and Auditorium for Performing Arts, Rock Concerts

    and Cultural events;

    Table 4 : Salient Features of the site

    S. No. Description Proposed1. Plot Area 4,99,829.28 m2

    2. Proposed Built Up Area (Retained +

    Proposed)

    3,97,249.559 m2

    3. Maximum Height with Mumty 36.0mtrs4. Maximum No. of Floors G+55. Cost of Project6. Expected Population (Retained +

    Proposed)

    1, 68,676

    7. Total Water Requirement 3,975 KLD 8. STP Capacity and Technology 2,200 KLD (MBR)9. No. of RWH Proposed 1010. Parking Proposed 4,806 ECS11. Solid Waste Generation 26,835.26 kg/day12. Total Power Requirement 17.51 MVA13. D.G. Set Back Up 18,740 kVA

    Area DetailsThis is re development of existing exhibition space to integrated Exhibition-cum-Convention

    Centre (IECC). Total area of the IECC site is Site is having plot area of 4, 99,829.28 m2 (49.98

    Hectare).The retained (existing) building having 7 No. of blocks (From Hall No. 7-13) with

    maximum height of G+1 (13.35 mtrs) however the proposed building is having 06 nos. of

    blocks with maximum height of G+5 (36.0 mtrs).Total built up area of the site (Retained +

    Proposed) Building is 3, 97,249.559 m2

    Area details are given in table below.

    Table 5 : Area Details of Retained (Existing) + Proposed Building

    S.

    No

    .

    Particulars Retained

    (Existing)

    Area (m2)

    Proposed Area

    (m2)

    Total Area

    (m2)

    1. Plot Area (As per the Lease area) 4,99,829.282. Total Ground Coverage (A+B)

    Permissible Ground Coverage (@40% of PA) (A) Add. G.C. for atrium (@10 % of PA)(B)

    2,49,914.642

    1,99,931.714

    49,982.928

  • 3. Total ground

    coverage (Proposed)

    Proposed Ground

    Coverage Atrium Ground

    coverage

    28,654.750

    -

    92,357.115

    3,561.524

    1,24,573.389

    @ 24.92 %

    Plot area

    4. Permissible FAR @1.2 5,99,795.1415. Proposed FAR @ 0.45

    FAR of Halls (No.

    7-13) FAR of Halls (No.

    1-6) FAR of

    Convention Hall FAR for Admin

    Building Gate House

    31,976.750

    1,96,544.137

    1,33,831.162

    54,265.906

    8,293.095

    153.974

    2,28,520.887

    6. Basement area

    Parking area Service area

    - 1,65,144.672

    1,47,392.521

    17,752.151

    1,65,144.672

    7. Podium area 3,584 - 3,5848. Built Up Area 35,560.75 3,61,688.809 3,97,249.559

    9. Open area 471,174.53 3,75,255.895 3,75,255.89510. Road and Paved area

    Area under Surface Parking

    1,14,066.200

    5234.0211. Landscape (51.20 % of Plot Area) 2,55,955.67512. Maximum Height of

    the Building (mtrs)

    13.35 36.0

    Ground Coverage and FAR DetailsGround coverage and floor wise details of each block (existing and proposed) blocks are givenin table.

    Table 6 : Ground Coverage and FAR details of Retained (Existing) building

    Block No. Storey Gr. Coverage F.A.R Height (mtrs)Hall no-07 G+1 8,495.000 9,885.000 13.35Hall no-08 G+1 460.400 1,113.400 13.00

  • Hall no-09 G+1 2,853.95 3,406.950 13.00Hall no-10 GR. FLOOR 1,818 1,818.000 13.00Hall no-11 G+1 6,682.4 7,408.400 13.00Hall no-12 GR. FLOOR 1,807 1,807.000 13.00Hall no-13 GR. FLOOR 6,538 6,538.000 13.00

    Total 28,654.75 31,976.75

    Table 7 : Ground Coverage and FAR Details of Proposed Building

    Block No.Storey Gr. Coverage F.A.R

    Height (mtrs)

    Convention-hall G+4 25,898.774 54,265.906 31.500Hall-A1 G+1 9,853.919 20,621.058 29.100Hall A2 G+1 9,853.919 20,621.058 29.100Hall A3-A5 G+1 32,077.252 65,500.500 29.100Hall A6 G+1 13,136.220 27,088.546 29.100Admin building G+5 1,383.058 8,293.095 30.000Gate house Gr. Floor 153.97 153.974 4.500

    Total 92,357.1151,96,544.13

    7

    Population Density

    During Construction PhaseThe total manpower requirement during construction phase of the site will be anapproximate 250-300 person which includes workmen, labourers, supervisors, engineers,architect and Manager.

    During Operational PhaseThe total population of the project (Retained building + Proposed) will be 1,68,676 personsthat include staff as well as Visitor population .The detailed population breakup includingStaff members as well as visitors is given in table below

    Table 8 : Population Details for Retained (Existing) Building

    S.No.

    Description Floor Area(m2)

    Occupant Load,Floor Area inm2/Person

    TotalPopulation

    1.Hall no-07

    9,885.0001.5

    6,590

    2.Hall no-08

    1,113.4001.5

    742

    3. Hall no-09 3,406.950 1.5 2,271

  • 4.Hall no-10

    1,818.0001.5

    1,212

    5.Hall no-11

    7,408.4001.5

    4,939

    6.Hall no-12

    1,807.0001.5

    1,205

    7.Hall no-13

    6,538.0001.5

    4,359

    Total Population 21,318

    Table 9 : Population Details for Proposed Building

    S.No.

    Description Floor Area(m2)

    Occupant Load, Floor Area in m2/Person

    TotalPopulatio

    n

    1. MAIN HALLS n ADMIN BUILDINGG-G Plenary Hall (Axial & Radial Partition) 3,246

    0.6 5,410

    Pre-function 3,234 0.6 5,390 Support facilities 1,662 10 166 Circulation 1,920 0.6 3,200 B-B Function Hall 5,495 0.6 9,158 Pre-function 1,280 0.6 2,133 Support facilities 1,774 10 177 Meeting spaces 15,030 0.6 25,050 Support Facilities and AmenitiesManagement Offices 147 10 15 VIP Lounges 246 10 25 Café 352 1.5 235 Reception 5,722 10 572 Business Centre 196 10 20 First aid rooms 38 10 4 Cloak rooms 60 10 6 Amphitheater Green rooms A 168

    10 17

    Amphitheater Green rooms B 212

    10 21

    Driver’s quarters 340 10 34 Additional Circulation 1,277 10 128 Security and Docks quarters

    410 10 41

  • Pantry 75 10 8 Green Rooms 170 10 17 Additional room within Convention Centre 1,350

    10 135

    F& B 4,184 1.5 2,789 Business Centre 2,167 10 217 Amphitheatre 3,510 1.5 2,340 Admin building 8,293.095 10 829

    25. EXHIBITION HALLSHalls A1-A6 1,33,831.16

    21.5 89,221

    Total Population (1+2) 1,47,358

    Total population of Integrated Exhibition cum Convention Centre (IECC) will be 1,68,676.

    Land Environment The site has been allotted to India Trade Promotion Organisation (ITPO), the premier

    trade promotion agency of the Ministry of Commerce & Industry, Govt. of India for

    conducting large exhibitions and conventions at Pragti Maidan, New Delhi. Perpetual lease has been made between President of India acting through Land &

    Development Officer, Nirman Bhawan, New Delhi and Indian Trade Promotion

    Organisation, Pragti Maidan, New Delhi.

    Annexure 1 : Land Ownership Documents

    Topography Physically the natural capital territory of Delhi can be divided into 3 segments - the

    Yamuna flood plain, the Ridge and the Plain. The entire area of the national capital

    territory of Delhi is categorized as Bangar or the plain. The land of the plain is mostly

    fertile The entire area of the site is monotonously flat. The project area possesses plain terrain.

    Highest elevation levels is 692 feet & the lowest levels is 685 feet

    Water Environment (Requirement and Consumption)

  • Construction PhaseDuring the construction phase the water requirement (approx. 1900 ML) will be met from

    Private water or treated wastewater from Nearby STP. No ground water will be extracted.

    Hence, there will be no impacts on ground water environment during construction phase.

    Operational Phase

    Total water requirement for redevelopment of IECC Project (Existing + Proposed) is 3,975

    KLD. Total domestic water requirement is approx 1,574KLD. The main sources fresh water

    will be

    DJB Registered tube wells within ITPO Complex.

    However the secondary sources of the water are

    Tanker supply (For Emergency Use only) Treated Effluent from an external centralized sewage treatment Plant

    The existing source of water for the project is DJB. There are two existing metered tapings

    from 450 mm diameter water pipe line, one of the connections is of 50 mm diameter and is

    near gate no. 3 of ITPO while the other connection is of 150 mm diameter and is near gate

    no.7. Water is supplied 24 x 7 to Pragati Maidan. There are existing 5 bore well and

    additional 2 bore well will be dug to fulfill the present water demand.

    Detail of water requirements for various uses is given in below table. Efficient dual flushing

    fixtures will be provided for conservation of fresh water. The demand may vary depending on

    the water conservation methods employed by the facility, which may include use of water

    efficient fixture, use of dishwashers, water auditing and metering etc

    Total quantity of wastewater generation will likely to be 2,295KLD. The generated sewage will

    be collected and treated in the in-house Sewage Treatment Plant of 2,200 KLD capacity. The

    treated wastewater will be re used for flushing and gardening and HVAC cooling. Water

    Balance diagram during Non Rainy season and Rainy season are shown below.

    Table 10 : Water Requirement during Operational Phase (Retained + Proposed) Building

    S.No. Description Population/area (m2)

    waterconsumption(litres/capita

    Total waterrequired (KLD)

    Water Requirement ForDomestic use

    (KLD)

  • /day)1. Exhibition Halls (A1-13) 1,10,539 15

    1,658.09 994.85

    2. Main Halls0.00 0.00

    G-G Plenary Hall (Axial & Radial Partition)

    5,410 15 81.15 48.69

    Pre-function 5,390 15 80.85 48.51Support facilities (Staff) 166 45 7.47 4.98Circulation 3,200 15 48.00 28.80B-B Function Hall 9,158 15 137.37 82.42Pre-function 2,133 15 32.00 19.20Support facilities (Staff) 177 45 7.97 5.31Meeting spaces 25,050 15 375.75 225.45Management Offices 15 45 0.68 0.45VIP Lounges 25 45 1.13 0.75Café 235 45 10.58 7.05Reception 572 45 25.74 17.16Business Centre 20 45 0.90 0.60First aid rooms 4 45 0.18 0.12Cloak rooms 6 45 0.27 0.18Amphitheatre Green rooms 38 45 1.71 1.14Other staff 363 45 16.34 10.89Business Centre 217 45 9.77 6.51F & B 2,789 15 41.84 25.10Amphitheatre visitors 2,340 15 35.10 21.06Admin Building 829 45 37.31 24.87Sub Total (1+2) 2,610.2 1,574.09

    3. OTHER AREAS

    Landscape (51.20 % of Plot Area)

    2,55,955.6751 ltrs/day 256

    HVAC** 11,445 TR 1,075 D.G. Cooling* 18,740 kVA 0.9l/kVA/hr 101Total (1+2+3) 3,975 KLD say

    3.9 MLD*(D.G. sets operational hours are 6-8 hrs)

    ** HVAC cooling required fresh water demand during dry season in 632 KLD and 376 KLD during Monsoon.

    Wastewater DetailsS.No. Details Water (KLD)

    1. Fresh Water Requirement 1,574

    2. Wastewater to be generated from domestic use (@80% of domestic wastewater)

    1,259

  • T o ta l

    W at e r

    R eq u i

    r em e

    n t

    Fresh

    Water

    Wastewater

    T r ea t ed W at e r ( 18 36 K LD )

    Flushing

    T r ea t ed W at e r ( 18 36 K LD )

    Hor

    ti

    cu

    lt

    ur

    e

    T r ea t ed W at e r ( 18 36 K LD )

    HVAC

    T r ea t ed W at e r ( 18 36 K LD )

    D.G. Cooling

    T r ea t ed W at e r ( 18 36 K LD )

    Tr

    ea

    ted

    Wa

    te

    r

    Wastewater

    T r ea t ed W at e r ( 18 36 K LD )

    Flushing

    T r ea t ed W at e r ( 18 36 K LD )

    Hor

    ti

    cu

    lt

    ur

    e

    T r ea t ed W at e r ( 18 36 K LD )

    HVAC

    T r ea t ed W at e r ( 18 36 K LD )

    D.G. Cooling

    T r ea t ed W at e r ( 18 36 K LD )

    3. Water Requirement for Flushing Purposes 1,036

    4.Wastewater to be generated from Flushing (@100 % of Flushing Requirement) 1,036

    5.Total Wastewater Generated (80% of fresh wastewater + 100% Flushing wastewater) 2,295 or say 2.2 MLD

  • Figure 3 : Water Balance Diagram during Dry Season

  • T o ta l

    W at e r

    R eq u i

    r em e

    n t

    Fresh

    Water

    Wastewater

    T r ea t ed W at e r ( 18 36 K LD )

    Flushing

    T r ea t ed W at e r ( 18 36 K LD )

    T r ea t ed W at e r ( 18 36 K LD )

    HVAC

    T r ea t ed W at e r ( 18 36 K LD )

    D.G. Cooling

    T r ea t ed W at e r ( 18 36 K LD )

    Tr

    ea

    ted

    Wa

    te

    r

    Wastewater

    T r ea t ed W at e r ( 18 36 K LD )

    Flushing

    T r ea t ed W at e r ( 18 36 K LD )

    T r ea t ed W at e r ( 18 36 K LD )

    HVAC

    T r ea t ed W at e r ( 18 36 K LD )

    D.G. Cooling

    T r ea t ed W at e r ( 18 36 K LD )

    During Construction Phase

    The quantity of sewage generation during the construction phase will be approx. approx. 11

    KLD. Thus the sewage will be treated by providing small septic tanks, soak trenches and

    sulabh shauchalaya type mobile toilets.

    During Operational Phase

    Quantity of sewage generated during operational phase shall be 2,295KLD. Thus the sewage

    will be treated through sewage treatment plant of capacity 2,200 KLD. The treated sewage

    will be re used for flushing (1,036 KLD) greenbelt development (256 KLD) and for HVAC (632

    KLD during Non Monsoon Season and 376 KLD during Monsoon Season).

    Figure 4 : Water Balance diagram during Monsoon Season

  • Sewage Treatment TechnologyThe design of sewage network shall be done in accordance with the CPHEEO guideline, NBC

    guidelines and reverent Indian Standards. Sewage generation is assumed to be 100% of

    flushing water and 80% of domestic water.

    The following parameters/ site conditions shall be kept in mind when designing the sewage,

    Sludge and storm water drainage system.

    Natural slope of the area. Layout of different facility in the complex; Possibility of using complete or part of the existing sewage network; Sub-soil water table; Provision of Sewage lifting station; ( if required) Provision of venting arrangement for manholes; Construction of manholes & laying of pipes considering ground condition; Termination of vent cowl at terrace level; Provision of adequate slope for horizontal header in the under slung pipes especially

    for public toilets Sewage flow starts with fractional capacity and builds up to full capacity in due

    course. An operational plan to meet this demand from a low flow to full flow will be

    part of the design.

    A summary of board design parameters to be adopted for designing Sewage supply system is

    given below.

    Table 11 : Design Parameters for Sewage Collection System

    Different Use Norm UsedType of Collection System Separate System Design Period -30 years for sewers and

    appurtenances -15 years for pumps and electric equipment’s

    Peak Factor 3 Minimum velocity 0.6 m/sec Maximum velocity 3.0 m/sec Minimum size of pipe 250 mm (ID) Minimum depth of Sewer 1.0 m from FGL (0.6 m minimum

    cushion) Hydraulic Formula for calculation for design of sewer lines (As per CPHEEO manual 3.4.2.1 page no-36)

    Manning’s formula V= 1/n*(R^2/3) *(S^1/2 ) V= Velocity R = Hydraulic mean depth = A/P S = Slope

    Flow conditions in pipe up to 400 0.50 full

  • mm dia Flow conditions in pipe up to 300 mm dia

    0.67 full

    Manning’s Co-efficient ‘n’ 0.011 Shape of sewers Circular Material of sewers HDPE Manhole Sizes As per manual on sewerage and

    sewerage treatment/ IS4111:1985 For depth above 0.9m & up to 1.65m

    900 mm diameter

    For depth 1.65m & up to 2.3m 1200 mm diameter For depth 2.3m & up to 9.0m 1500 diameter

    Technology Proposed- MBR (Membrane Bio Reactor)The MBR is a suspended growth-activated sludge system that utilizes micro porous

    membranes for solid/liquid separation instead of secondary clarifiers.

    An external sewage network shall collect the sewage from all units, and flow by gravity to the

    proposed sewage treatment plant.

    Following are the benefits of providing the Sewage Treatment Plant in the present

    circumstances:

    Reduced net daily water requirements, source for Horticultural purposes by

    utilization of the treated wastewater. This shall consequently lead to a lower

    withdrawal from the underground aquifer water sources.

    Reduced dependence on the public utilities for water supply and sewerage

    systems.

    Sludge generated from the Sewage Treatment Plant shall be rich in organic

    content and an excellent fertilizer for horticultural purposes.

    The STP is being proposed with state-of-the-art membrane separation technology called as

    Membrane Bio-Reactor (MBR) which can produce very good quality with highest possible

    bacterial reduction without adding any chemicals. MBR (Membrane Bio Reactor) is the latest

    technology in wastewater treatment. MBR has many advantages such as higher quality of

    treated water, smaller space for installation and easier operation compared to conventional

    activated sludge process.

  • Designed to produce high quality treated water from wastewater the Membrane Bio Reactor

    (MBR) is among the latest technologies in biological treatment.

    The characteristic of the MBR process is the use of revolutionary submerged polymeric

    hollow fibre membranes in the biological process water tank, so as to produce high quality

    permeate from domestic sewage, primary and secondary waste water, cooling tower blow

    down etc. The MBR is also ideal for retrofitting/augmenting capacity/quality of existing

    wastewater plants.

    The hollow fibers are combined into bundles and wound around a carrier cartridge, which

    gives the membranes the required strength and allows for high-pressure air scour for

    cleaning. The MBR can handle very high sludge concentrations in the aeration tank because

    of which the size of the aeration tank reduces four to five folds. As the membrane acts as a

    fine filter, it does not require any further treatment using sand filters, activated carbon

    filters, etc. The MBR is available in standard and customized modules.

    Process Description

    Figure below shows the principle of the filtration for the flat sheet type submerged

    membrane. Activated sludge in the aeration tank is clearly removed by the flat sheet type

    submerged membrane. The membrane module consists of housing, aeration diffuser;

    permeate water manifold and membrane elements. The membrane element consisting of flat

    sheet membranes sandwiching a support panel is set up vertically. Feed water including

    activated sludge is filtrated by flat sheet membranes with pore size of 0.1 micron meter. The

    air bubbles supplied from the bottom of the membrane elements continuously scour off cake

    of activated sludge accumulated on the membrane surface. This is continuous filtration

    operation. The air bubbles are also used for the biological reaction to decompose organic

    substances included in the raw sewage.

  • Figure 5 : Schematic Diagram of MBR Technology

    MBR Module

    The material of the membrane is PVDF (Poly vinylidene fluoride). PVDF is fluorine polymer,

    which has high stability for chemicals and good physical strength. The form of membrane is

    fibre reinforced flat sheet membrane. The membrane has small and uniform pore size.

    Therefore, the rejection property of this membrane is excellent. Almost all particles with sizes

    more than 0.1 micron meter can be removed effectively using this membrane.

    Operation

    Sewage from main drain line is collected through gravity pipes into a screen chamber.

    This manually cleaned screen is provided to remove floating and big size particles, which

    may choke the pumps and pipe lines.

    Screened sewage is then passed through equalization tank to homogenize the sewage

    quality and also even out flow fluctuations and feed sewage of uniform quality at constant

    rate to subsequent treatment units. Air mixing is also provided to mix the contents of the

    equalization tank. A coarse bubble aeration grid is provided to distribute air uniformly at

  • the base of the equalization tank.

    After above treatment, raw sewage is fed into aeration basin.

    In aeration tank, MLSS (mixed liquor suspended solids) in the range of 12000 to 15000

    mg/l are maintained. The high amount of bacteria gives better and complete removal of

    organic matter from the raw sewage in relatively small area. Oxygen required for the

    bacteria is supplied through the blower. The air is used both for scouring of membranes

    and supplying oxygen to bacteria.

    The filtration is carried out by the suction pump directly sucking permeates water. The

    permeate water produced is clear and devoid of bacteria and viruses to the minimum

    levels.

    As the membranes are continuously under operation, they are polluted with organic or

    inorganic substances. Hence, chemical cleaning is carried out once in two to three

    months for removing substances polluting and clogging the membranes. Normal cleaners

    used are sodium hypo chloride and citric acid.

    Sewer System

    The alignment and slope of the sewer line will follow the road network, drains or natural

    ground surface and will be connected to the trunk sewers. The discharge point will be a

    treatment plant, a pumping station, a water course or an intercepting sewer. Pumping

    stations would be provided at places where the natural slope of the terrain is insufficient to

    permit gravity flow or the cost of excavation is uneconomical to do the same

    Table 12 : Wastewater Details

    Particulars QuantityDaily load 2,295KLDDuration of flow to STP 24 HoursTemperature 320 C

    Inlet Outlet (Treated Wastewater )pH 6.0 – 9.0 7.0-8.0T.S.S. (mg/l) 300-400

  • treated wastewater pipes will be laid in conduits wherever road crossings are expected. Thus

    no leaching of treated sewage into nearby water courses shall take place. Supervisors will be

    employed for overall operation & maintenance of water supply, waste water treatment and

    other utility services.

    Rainwater Harvesting and Strom Water DrainA rainwater harvesting system comprises components of various stages -transporting

    rainwater through pipes or drains, filtration, and recharging the ground water through

    tanks. Percolation structures will be constructed for ground water recharge.

    Runoff from the first spell of rain carries a relatively large amount of pollutants from the air

    and catchments surface so the system will be provided with a filtration pit consisting of

    layers of sand, gravel and pebbles of relevant sizes to remove impurities from the collected

    rainwater.

    Need for Rainwater HarvestingSurface water is inadequate to meet the daily demand and we have to depend on groundwater.

    Due to rapid urbanization, infiltration of rain water into the sub-soil has decreaseddrastically and recharging of ground water has diminished.

    Rainwater harvesting prevents the flooding of low-lying areas in the site.

    Rainwater Harvesting NetworkRain water harvesting structures will be constructed all around the compound wall to collect

    rain water. Excess storm water will be allowed to drain into the external storm drain.

    Rain water harvesting has been catered to and designed as per the guideline of CGWA. Peak

    hourly rainfall has been considered as 11 mm/hr. The recharge well of 10 mtr dia and 10

    mtr depths and 4 mtrs width will be constructed for recharging the water. The bottom of the

    recharge structure will be kept 5 m above this level. At the bottom of the recharge pit, a filter

    media is provided to avoid choking of the recharge bore.

    The pit will be filled with rounded gravel 5 to 10 mm size. The sectional detail of the

    proposed rain water recharge structure is provided in below figure.

    The path ways around the harvesting lines will be graded to facilitate drainage into trenches

    proposed around the compound. Recharge wells/structures are envisaged along the path of

  • the storm water drains for rain water recharging & surplus water from the recharge

    wells/structures shall be diverted to the storm water drainage network.

    The collected storm water will be allowed to percolate to the sub-soil by suitably designed

    percolation structures. The structures will be designed based on the soils percolation

    capability. The subsoil water table is high in these areas and however harvesting structures

    with bores will be provided.

    Percolation structures of suitable numbers will be provided for recharge of ground water

    potential. A total of 10 rain water harvesting structures will be constructed. The quantity of

    storm water load for the proposed construction project is given below.

    Table 13 : Calculation for Strom Water Load for the Development of IECC

    S. No.

    Type of Surface

    Catchment's Area Run off Coff. [C]

    Intensity of Rainfall (mm/hr)

    Discharge (Run Off) [Q=10CIA] m3/hr

    Total(m3/hr) [Q]

    sq. m Ha.

    1 Building (Terrace)

    (a) Area 1,40,169.75 14.01 0.60 80 10×0.60×80×14 6,720

    1,80,482.31 18.04 0.20 80 10×0.20×80×18 2,886.4

    1,55,409 15.54 0.75 80 10 ×0.75×80×15 9,000

    Total 18,606.4

    (b) Considering 15 mins (0.25) retention period 4,651.6

    (c) Volume of Rain water Storage Structure 10×4×4 160 m3

    (d) Total No. of Rain water Storage Structure required 29.07Total No. of Rain water Storage Structure Proposed 10

  • Figure 6 : Rainwater Harvesting Structure

    Efficacy of Rain Water HarvestingThe area of site has the water table at 3.0 M. It is not advisable to recharge aquifer by rain

    water in areas with water table less than 8.0 M. In this case, following is recommended: -

    Use the storm water to recharge lake next to Old Fort, subject to approval by ASI &additional cost of connectivity. This will automatically mean water harvesting throughpercolation.

    Use the storm water to run chillers cooling towers after tertiary treatment during themonsoons. The treated effluent being received from DJB will not be drawn during thisperiod. The facility management team must ensure the same.

    Parking DetailsAdequate provision will be made for car/vehicle parking at the project site. There shall be

    adequate parking provisions for visitors so as not to disturb the traffic and allow smooth

    movement at the site.

  • Proposed project will be consists of basement and open parking. The parking space criteria

    and area requirement provided are summarized in the table below. Parking details are

    designed as per Delhi Building Bye Laws

    Table 14 : ECS Required

    As Per DDAParking Required Area (m2) Total (ECS)For the Site 2 ECS/100

    m2 of FAR

    area

    2,28,520.887/

    50

    2,28,520.887

    4,570

    Total Parking Required

    (ECS)

    4,570

    Table 15 : Parking Proposed

    Description Area

    Required for

    1 ECS

    Area (m2) Parking

    Proposed

    ( ECS)In Basement 1 ECS/32 m2

    of area

    1,47,392.5

    2

    4,606

    In Open 1 ECS/23 m2

    of area

    1,649.580 72

    In podium 1ECS/28 m2 3,584.440 128Total Parking Proposed

    (ECS)

    4,806

    TWO WHEELER 1000 × 0.5 500ECSBUSES 52 × 3.5 182 ECSCARS 4,124 × 1 4,124 ECS

    Electrical details

    Power DetailsThe power shall be supplied by BSES Delhi. The total demand load for the project (Retained

    Building + Proposed) will be 17.51 MVA. It is proposed to install 2 Electrical subs- Station

    named MRS-1 and MRS-2.

  • MRS-1 shall receive 2 Nos. 33KV supplies from BSES and feed electrical power at 11KV to

    Hall A1, A2, A3, A4a, A4b, A5 and A6 by providing 2 Nos. 7.5 MVA 33/11KV and it shall be

    located near Hall A5

    MRS-2 shall receive 1 No. 33KV supply from BSES and feed electrical power at 11KV to

    Convention Center and Admin Block by providing 1 Nos. 6 MVA 33/11KV and it shall be

    located near Hall A6. 2 Nos. 33kV meter room shall be located for MRS-1 (near Hall A5) and

    1 No. 33KV meter room for MRS-2 shall be near Hall Admin Block at the Ground Level.

    For the MRS I, 2 numbers of (7.5 MVA), 33/11 kV, oil types outdoor transformers has been

    selected. For MRS II, 1 number of (6 MVA), 33/11 kV, oil types outdoor transformers has

    been selected

    D. G. Sets Details

    In case of power failure, there are 2 Nos. 11 KV DG rooms with corresponding 2 Nos. MRS .it

    provides the 100% power back up for the development. The location of DG rooms shall be

    either at the ground or in Basement. D.G. sets location and their description is given below.

    Table 16 : D.G. sets location and their description

    S.No. Description Feed1. DG Room-1 (For Hall A1, A2, A3, A4a,

    A4b, A5 and A6)

    6 Nos. 2MVA & 2Nos.

    2.5MVA, 11KV DG Sets2.

    DG Room-2 (For Hall A6 and Admin Block)4 Nos. 2MVA, 11KV DG

    Sets

    Lighting systemLighting systems with green features to be used for this project are:

    Solar Street Lightings. LED lights over T5 or T8 Fluorescent lightings.

    Lighting Control through day lighting and sensor Motion

    It is proposed to use Presence/Occupancy sensors in common areas like corridor, Lift Lobby,Toilets etc. which will result in considerable saving of energy.

    Two way programmable High performance, compact presence detectors /occupancy

    sensors will be used which provide automatic control for lighting loads. It detects human presence and automatically turns the lights ‘ON’. When the area is

    vacated, the lights turn ‘OFF’ after a preset time period.

  • The sensor has advanced presence detection by passive infrared (PIR) technology along

    with Sensitivity level adjustments. The sensor has Adjustable off delay timing 10 sec –

    99 min which can be programmed & changed using a remote control. The sensor has a Passive photocell that holds lights OFF in extremely bright ambient

    conditions. The occupancy cum day light sensors will be used which are used for switching off the

    luminaries when the areas are unoccupied & also used for dimming the luminaries

    when there is day light coming inside the building & thus help to reduce the power

    consumption. This sensor is basically used in the areas along the building façade where the day

    light contribution is high. Along with presence detection, this sensor has built-in

    adjustable photocell which regulates the lighting level as per availability of natural

    daylight in an area, thus maintaining uniform illumination.

    Integrated Fire Detection SystemThis will comprise of below mentioned components.

    Intelligent addressable Fire Detection system with communication, notification &

    Interface capability. Manual call points for activation of fire alarm system manually. Integrated Emergency Voice Evacuation System. Interlocking with other equipments likes Elevators, Air-conditioning Units, Smoke

    Extraction system etc.

    Solid Waste Details

    During Construction Phase of the Proposed Building

    The solid waste expected to be generated during the construction phase will comprise of

    excavated materials, used bags, bricks, concrete, MS rods, tiles, wood etc. The following

    steps are proposed to be followed for the management solid waste:

    Construction yards are proposed for storage of construction materials. The excavated material such as topsoil and stones will be stacked for reuse during

    later stages of construction. Excavated top soil will be stored in temporary constructed soil bank and will be reused

    for landscaping during operational phase of the project. Remaining soil shall be utilized for refilling / road work / rising of site level at

    locations/ selling to outside agency for construction of roads etc.

  • Construction

    n Demolition

    Waste

    Construction

    waste,Broken

    bricks,Waste

    plaster

    Re

    filling,Raising

    Site

    Level

    Empty

    Cement

    Bags

    Road

    Making

    Excavated

    Soil

    Top soil

    conserved

    for

    landscaping

    and

    refilling

    the

    site

    Demolish waste

    Handed over to Govt

    . approved agency for fi

    nal disposal

    Construction waste management is shown in below figure.

    Figure 7 : Solid Waste Management for Construction Phase

    C & D waste of Existing Buildings

    Construction and demolition waste of the site shall be keep within the premises. The waste shall be deposited at collection centre so made by the local body or

    handover it to the authorized processing facilities for further process or disposal. As inert it shall be used to fill material for low -lying areas, landscaping, Road Making

    etc. Finer grade can be molded into blocks and slabs with appropriate binder.

    During Operational Phase

    The project will adopt a systematic approach for solid waste collection and disposal. Solid

    waste generated from the project will be collected properly and will be managed as per MSW

    Rules, 2000 amended in 2016.

    Waste shall be mainly categories in two classes. 1. Bio degradable Waste 2 Non-

    biodegradable Waste. The biodegradable portion dominates the bulk of MSW. This is

    mainly due to food and yard waste. These solid wastes will be collected separately by putting three types of separate bins

    at the source of generation. For the biodegradable waste yellow bins will be provided,

    for the recyclable waste black bins and for the non-recyclable waste red bins will be

    provided. It is estimated that maximum solid waste generation would be about 26,835.26 kg/day;

    Following are the solid waste generation rate has been considered as is given table.

  • Table 17 : Calculation of Solid Waste Generation of Retained and Proposed Building

    S.No. Category Counts(heads)

    Westegeneration(p/kg/day)

    WasteGenerated(kg/day)

    For the Retained and Proposed Building

    1. Staff Support

    Facilities343

    @ 0.25kg/day

    671.7541.50

    ManagementOffice

    1544.25

    VIP Lounges 25 3.75 Café 235 6.25 Reception 572 58.75 Business Centre 20 143.00 First Aid Rooms 4 5.00 Cloak rooms 6 1.00

    AmphitheatreGreen Rooms

    381.50

    Other staff 383 9.50 Business Centre 217 95.75 Admin Building 829 207.25

    2. Visitors Exhibition Halls

    (A1-A13)1,18,894

    @ 0.15kg/day

    26,154.60

    17,834.10

    G-G PlenaryHall (Axial &Radial Partition)

    5,410811.50

    Pre- Function 5,390 808.50

    Circulation 3,200 480.00 B-B Function

    Hall9,158

    1,373.70

    Pre- Function 2,133 319.95 Meeting Spaces 25,050 3,757.50 F& B 2,789 418.35 Amphitheatre

    Visitors2,340

    351.00

    Total Domestic Waste (1+2)

    26,826.35

    11. Landscape waste(44.59 Acre)

    @ 0.2 kg/acre/da

    8.91

  • y

    Total Wastegenerated (1-3)

    26,835.26 kg/day

    (Source:http://cpheeo.nic.in/WriteReadData/Cpheeo_SolidWasteManagement/chap3.pdf )

    Following arrangements will be made at the site in accordance to Municipal Solid Wastes(Management and Handling) Rules, 2000 and amended Rules; 2016.

    Collection and Segregation of waste

    For Domestic Waste

    A door to door collection system will be provided for collection of domestic waste in

    colored bins from every unit. The local vendors will be hired to provide separate colored bins for dry recyclables and

    Bio-Degradable waste. For waste collection, adequate number of colored bins (Green and Blue & dark grey

    bins– separate for Bio-degradable and Non Bio-degradable) are proposed to be

    provided at the strategic locations of the area. Litter bin will also be provided in open areas like parks etc.

    Treatment of Waste

    Domestic Waste

    Bio degradable Waste

    Bio-degradable waste will be subjected to the compost/resultant will be used as

    manure. STP sludge is proposed to be used for horticultural purposes as manure. Horticultural Waste is proposed to be composted and will be used for gardening

    purposes.

    Recyclable Waste

    The cropped grass will be spread on the green area. It will act as manure after

    decomposition. Recyclable wastes like paper, plastic, metals etc. will be sold off to recyclables.

    Disposal

    Recyclable and non-recyclable wastes will be disposed through Govt. approved agency.

    Hence, the Municipal Solid Waste Management t will be conducted as per the guidelines of

    http://cpheeo.nic.in/WriteReadData/Cpheeo_SolidWasteManagement/chap3.pdf

  • Solid waste

    Non Biodegradable Waste

    Recyclable

    Blue bins

    to Govt. approved Vendor

    Non-Recyclable

    Dark Grey Bins

    to govt. approved agency

    Biodegradable Waste

    Green bins

    Composter

    Manure

    Municipal Solid Wastes (Management and Handling) Rules, 2000 and amended Rules, 2016.

    Solid waste management Scheme is depicted in the following figure.

    Figure 8 : Solid Waste Management Scheme -Domestic Waste

    Landscape Details Total green area measures 2,55,955.675m2 (51.20 % of Plot Area) A diverse variety of indigenous evergreen and ornamental trees would be planted. As

    the project site for construction consists of trees, herbs and shrubs it will require

    cutting of trees for construction purpose. Total number of trees planted will be 6,713. However nos of trees retained will be 913. The plant species will be selected on the basis of Urban Standard Plantation norms

    and CPCB guidelines. Landscape Details are given in below table

    Table 18 : Landscape Area Details

    Particulars DetailsPlot area 4,99,829.28 m2

    Open area 3,75,255.895 m2

    Landscape area Proposed 2,55,955.675m2 (51.20 % of Plot Area)As Per MoEF Guidelines One tree per 80 m2 of total area out of which

    minimum 50 % to be in the category ofevergreen trees.

  • Trees Required 4,99,829.28/80= 6,247.866 TreesNumber Of Trees Proposed ToBe Planted

    6,713 Trees (Existing Trees Retained= 913)

    Energy

    Conservation Measures CFC free equipment, chillers with CFC-free environmentally friendly refrigerant will be

    installed to protect the ozone layer.

    Table 19 : Plantation List

  • The Building envelope details has been followed as per ECBC to reduce heat intakefrom outside. Walls, roofs and glass U values will be less than the ASHRAE Standard90.1 2007 to save energy compared to baseline building energy consumption.

    Lighting power densities are expected to be less than the ASHRAE Standard 90.1 2007base line to save energy compared to baseline building criteria.

    Provision and space allocation for energy metering will be provided for the followingsystem loads for continuous monitoring:

    Air conditioning Internal lighting External lighting Treated Effluent water pumping Landscape water pumping

    Solar water supply shall be restricted to kitchens. The DG set will be ISI rated and certified by the central pollution control board (CPCB)

    for emission and noise. Level controllers in water tanks will be provided to avoid overflow of water and waste of

    energy All pumps will be ISI rated with a minimum 60% efficiency LED lamps will be provided in all display/exit sign boards to save energy Movement sensors for lighting control will be provided in toilets, study rooms,

    staircases, cabins, corridors, garbage rooms, balconies, washing and storage areas Provision of 50% solar PV panel with LED Street lighting for the external area with

    50% based on conventional LED Street lighting to be subjected to GRIHA Consultantadvice.

    Provision of LED lighting over T5 fluorescent lighting.

    List of the construction Material UsedList of building materials being used at site:

    1. Coarse sand2. Fine sand3. Stone aggregate4. Stone for masonry work5. Cement6. Reinforcement steel7. Pipe scaffolding (cup lock system)8. Bricks9. ACC Blocks10. Crazy (white marble) in grey cement P.V.C. conduit11. MDS, MCBs12. PVC overhead water tanks13. 2 1/2'’ thick red colour paver tiles14. PPR (ISI marked)15. PVC waste water lines16. S.W. sewer line up to main sewer

  • 17. PVC rain water down take18. Stainless steel sink in kitchen

    IntroductionGeneralBrief about Project ProponentProject ConsultantBrief about Project

    Site Surroundings and ConnectivityLocation

    Salient features of the siteArea DetailsGround Coverage and FAR Details

    Population DensityDuring Construction PhaseDuring Operational Phase

    Land EnvironmentTopography

    Water EnvironmentConstruction PhaseOperational PhaseWastewater DetailsSewage Treatment TechnologyTechnology Proposed- MBR (Membrane Bio Reactor)Process DescriptionMBR ModuleOperationSewer System

    Preventive measures to Avoid LeachingRainwater Harvesting and Strom Water DrainNeed for Rainwater HarvestingRainwater Harvesting NetworkEfficacy of Rain Water Harvesting

    Parking DetailsElectrical detailsPower DetailsD. G. Sets Details

    Lighting systemLighting Control through day lighting and sensor MotionIntegrated Fire Detection System

    Solid Waste DetailsDuring Construction Phase of the Proposed BuildingC & D waste of Existing BuildingsDuring Operational PhaseCollection and Segregation of wasteTreatment of WasteDisposal

    Landscape DetailsEnergy Conservation MeasuresList of the construction Material Used