    COMPUTERAPPLICATIONS IN

    RESOURCE LEVELLINGPRESENTED BY

    BEHARA RAJASEKHAR

    NELSON PRABHU

    VISHNU UNNIKRISHNAN

  • 8/13/2019 Computer Applications in Resource Levelling

    2/30

    Resource

    An economic or productive factor required to

    accomplish an activity, or as means to

    undertake an enterprise and achieve desired

    outcome.

  • 8/13/2019 Computer Applications in Resource Levelling

    3/30

    Resource levelling

    A project management technique used to examineunbalanced use of resources (usually people orequipment) over time, and for resolving over-

    allocations or conflicts.

    Leveling resources involves redistributing animbalance of allocated work. It assists project team

    members by keeping them from becomingoverwhelmed, working overtime, or running intoproject burnout.

  • 8/13/2019 Computer Applications in Resource Levelling

    4/30

    COMPUTER SOFTWARES

    MICROSOFT PROJECT

    PRIMAVERA

  • 8/13/2019 Computer Applications in Resource Levelling

    5/30

    Resource Over-allocation

    Searching for names of resources highlighted in red in anyresource view.

    Using the Resource Allocation view to help find and reviewdetailed task and assignment information about

    overallocated resources. Using the Resource Usage view, which shows the

    assignments that are causing the overallocation. Thetimesheet portion of the view can show the amount of timethat the resource is overallocated within a given period of

    time. Filtering any resource view to find overallocated resources.

    Printing the Overallocated Resources report.

  • 8/13/2019 Computer Applications in Resource Levelling

    6/30

    Fixing overallocation

    By delaying a task until the assigned resource has

    time to work on it.

    By splitting a task so that part of a task is done

    when planned and the rest of it is done later whenthe assigned resource has time.

  • 8/13/2019 Computer Applications in Resource Levelling

    7/30

  • 8/13/2019 Computer Applications in Resource Levelling

    8/30

    Resource Levelling With Primavera P6

    Resource Usage Profile

  • 8/13/2019 Computer Applications in Resource Levelling

    9/30

    Setting Up for Resource Leveling

    Project Leveling Priority

  • 8/13/2019 Computer Applications in Resource Levelling

    10/30

    Activity Leveling Priority

  • 8/13/2019 Computer Applications in Resource Levelling

    11/30

    Primavera P6 Resource Leveler

    Usage

    Level Resources

  • 8/13/2019 Computer Applications in Resource Levelling

    12/30

  • 8/13/2019 Computer Applications in Resource Levelling

    13/30

    Primavera P6 Resource Leveler

    running

  • 8/13/2019 Computer Applications in Resource Levelling

    14/30

  • 8/13/2019 Computer Applications in Resource Levelling

    15/30

    CHECKS TO BE DONE

  • 8/13/2019 Computer Applications in Resource Levelling

    16/30

  • 8/13/2019 Computer Applications in Resource Levelling

    17/30

  • 8/13/2019 Computer Applications in Resource Levelling

    18/30

    Resource levelling with MS

    PROJECT

    Primarily used in projects where resources are the

    most important priority

    Cost and schedule are secondary priorities

    First checks each resource for overallocations

    Finds tasks associated with overallocations and

    identifies which ones can be delayed

  • 8/13/2019 Computer Applications in Resource Levelling

    19/30

    Does not delay if:

    A constraint of MustStart On or MustFinish Onexists

    A constraint of As Late As Possible exists, if this

    project is being scheduled from the start date. A constraint of AsSoon As Possible,if this project is

    being scheduled from the finish date.

    A priority of 1000, meaning do not level.

    An actual start date exists but will split remaining workif Levelingcan create splits in remaining workcheck

    box is selected

  • 8/13/2019 Computer Applications in Resource Levelling

    20/30

    Automatic

    Levels as soon as there is a change in a task or resource

    Assumes Automatic Calculation is set within Options

    Typically degrades MS Project performance not

    recommended

    Manual (Default)

    Levels only when LevelNowbutton is selected Assumes Automatic Calculation mode is active

  • 8/13/2019 Computer Applications in Resource Levelling

    21/30

  • 8/13/2019 Computer Applications in Resource Levelling

    22/30

    Look for overallocations on a Day by Day basis:(Default)

    Established the point you want leveling to intervene

    Week by Week smallest interval recommended

    Time periods are based on settings within individual

    resource calendars first and then max units (Calendar tab ofOptions)

    Clear leveling values before leveling: (Default-Checked)

    All leveling delays previously entered (automatic/manual)are cleared before the next leveling action

    Clear the box if using Automatic Leveling to improveperformance

  • 8/13/2019 Computer Applications in Resource Levelling

    23/30

    Priorities are used to restrict/focus leveling activities

    Priority Range: 0 (lowest) to 1000 (highest)

    Priority Default for Tasks: 500

    Priorities Set to 1000:

    No resources will be leveled

    No splits or leveling delays will be applied

    Used for critical tasks you never want to changew/leveling

    Priorities Set to 100:Tasks that have more flexibility as to start/finish dates

    MS Project will focus change to these tasks first

  • 8/13/2019 Computer Applications in Resource Levelling

    24/30

    Level only within available slack (Default-not checked)

    Used if you do not want to push out the project finish date

    Assumes slack exists if it doesntfew changes may occur

    Recommend first pass with this box checked If little effect may need to add resources, cut scope, extend timeline

    Leveling can adjust individual assignments on a task (Default-checked)

    Adjusts when a resource works on a task independent of others

    assigned

    May create problems based on the task & type/sequence of work

  • 8/13/2019 Computer Applications in Resource Levelling

    25/30

    level without extending the end date

  • 8/13/2019 Computer Applications in Resource Levelling

    26/30

    EFFECTIVE LEVELLING

  • 8/13/2019 Computer Applications in Resource Levelling

    27/30

    Resource level by Id options

  • 8/13/2019 Computer Applications in Resource Levelling

    28/30

    Resource level by Standard options

  • 8/13/2019 Computer Applications in Resource Levelling

    29/30

    CONCLUSION

    Looks for available slack and resources

    Schedules Longest Duration tasks first

    Then in ID order

    Options allow control over leveling algorithm

    Priority field can be used to override and schedule

    tasks first

  • 8/13/2019 Computer Applications in Resource Levelling

    30/30