computer applications in resource levelling
TRANSCRIPT
-
8/13/2019 Computer Applications in Resource Levelling
1/30
COMPUTERAPPLICATIONS IN
RESOURCE LEVELLINGPRESENTED BY
BEHARA RAJASEKHAR
NELSON PRABHU
VISHNU UNNIKRISHNAN
-
8/13/2019 Computer Applications in Resource Levelling
2/30
Resource
An economic or productive factor required to
accomplish an activity, or as means to
undertake an enterprise and achieve desired
outcome.
-
8/13/2019 Computer Applications in Resource Levelling
3/30
Resource levelling
A project management technique used to examineunbalanced use of resources (usually people orequipment) over time, and for resolving over-
allocations or conflicts.
Leveling resources involves redistributing animbalance of allocated work. It assists project team
members by keeping them from becomingoverwhelmed, working overtime, or running intoproject burnout.
-
8/13/2019 Computer Applications in Resource Levelling
4/30
COMPUTER SOFTWARES
MICROSOFT PROJECT
PRIMAVERA
-
8/13/2019 Computer Applications in Resource Levelling
5/30
Resource Over-allocation
Searching for names of resources highlighted in red in anyresource view.
Using the Resource Allocation view to help find and reviewdetailed task and assignment information about
overallocated resources. Using the Resource Usage view, which shows the
assignments that are causing the overallocation. Thetimesheet portion of the view can show the amount of timethat the resource is overallocated within a given period of
time. Filtering any resource view to find overallocated resources.
Printing the Overallocated Resources report.
-
8/13/2019 Computer Applications in Resource Levelling
6/30
Fixing overallocation
By delaying a task until the assigned resource has
time to work on it.
By splitting a task so that part of a task is done
when planned and the rest of it is done later whenthe assigned resource has time.
-
8/13/2019 Computer Applications in Resource Levelling
7/30
-
8/13/2019 Computer Applications in Resource Levelling
8/30
Resource Levelling With Primavera P6
Resource Usage Profile
-
8/13/2019 Computer Applications in Resource Levelling
9/30
Setting Up for Resource Leveling
Project Leveling Priority
-
8/13/2019 Computer Applications in Resource Levelling
10/30
Activity Leveling Priority
-
8/13/2019 Computer Applications in Resource Levelling
11/30
Primavera P6 Resource Leveler
Usage
Level Resources
-
8/13/2019 Computer Applications in Resource Levelling
12/30
-
8/13/2019 Computer Applications in Resource Levelling
13/30
Primavera P6 Resource Leveler
running
-
8/13/2019 Computer Applications in Resource Levelling
14/30
-
8/13/2019 Computer Applications in Resource Levelling
15/30
CHECKS TO BE DONE
-
8/13/2019 Computer Applications in Resource Levelling
16/30
-
8/13/2019 Computer Applications in Resource Levelling
17/30
-
8/13/2019 Computer Applications in Resource Levelling
18/30
Resource levelling with MS
PROJECT
Primarily used in projects where resources are the
most important priority
Cost and schedule are secondary priorities
First checks each resource for overallocations
Finds tasks associated with overallocations and
identifies which ones can be delayed
-
8/13/2019 Computer Applications in Resource Levelling
19/30
Does not delay if:
A constraint of MustStart On or MustFinish Onexists
A constraint of As Late As Possible exists, if this
project is being scheduled from the start date. A constraint of AsSoon As Possible,if this project is
being scheduled from the finish date.
A priority of 1000, meaning do not level.
An actual start date exists but will split remaining workif Levelingcan create splits in remaining workcheck
box is selected
-
8/13/2019 Computer Applications in Resource Levelling
20/30
Automatic
Levels as soon as there is a change in a task or resource
Assumes Automatic Calculation is set within Options
Typically degrades MS Project performance not
recommended
Manual (Default)
Levels only when LevelNowbutton is selected Assumes Automatic Calculation mode is active
-
8/13/2019 Computer Applications in Resource Levelling
21/30
-
8/13/2019 Computer Applications in Resource Levelling
22/30
Look for overallocations on a Day by Day basis:(Default)
Established the point you want leveling to intervene
Week by Week smallest interval recommended
Time periods are based on settings within individual
resource calendars first and then max units (Calendar tab ofOptions)
Clear leveling values before leveling: (Default-Checked)
All leveling delays previously entered (automatic/manual)are cleared before the next leveling action
Clear the box if using Automatic Leveling to improveperformance
-
8/13/2019 Computer Applications in Resource Levelling
23/30
Priorities are used to restrict/focus leveling activities
Priority Range: 0 (lowest) to 1000 (highest)
Priority Default for Tasks: 500
Priorities Set to 1000:
No resources will be leveled
No splits or leveling delays will be applied
Used for critical tasks you never want to changew/leveling
Priorities Set to 100:Tasks that have more flexibility as to start/finish dates
MS Project will focus change to these tasks first
-
8/13/2019 Computer Applications in Resource Levelling
24/30
Level only within available slack (Default-not checked)
Used if you do not want to push out the project finish date
Assumes slack exists if it doesntfew changes may occur
Recommend first pass with this box checked If little effect may need to add resources, cut scope, extend timeline
Leveling can adjust individual assignments on a task (Default-checked)
Adjusts when a resource works on a task independent of others
assigned
May create problems based on the task & type/sequence of work
-
8/13/2019 Computer Applications in Resource Levelling
25/30
level without extending the end date
-
8/13/2019 Computer Applications in Resource Levelling
26/30
EFFECTIVE LEVELLING
-
8/13/2019 Computer Applications in Resource Levelling
27/30
Resource level by Id options
-
8/13/2019 Computer Applications in Resource Levelling
28/30
Resource level by Standard options
-
8/13/2019 Computer Applications in Resource Levelling
29/30
CONCLUSION
Looks for available slack and resources
Schedules Longest Duration tasks first
Then in ID order
Options allow control over leveling algorithm
Priority field can be used to override and schedule
tasks first
-
8/13/2019 Computer Applications in Resource Levelling
30/30
THANKS