Compendium of Instructions related to Inspections and Competency Certificates in Engineering Department Compendium of Instructions related to Inspections and Competency Certificates in Engineering Department October 2015 October 2015 Indian Railways Institute of Civil Engineering Pune 411001 Indian Railways Institute of Civil Engineering Pune 411001

Upload: others

Post on 25-Mar-2020

42 views

Category:

Documents


2 download

TRANSCRIPT

Page 1: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

Compendium ofInstructions related to Inspections

andCompetency Certificates in

Engineering Department

Compendium ofInstructions related to Inspections

andCompetency Certificates in

Engineering Department

October 2015October 2015

Indian Railways Institute of Civil EngineeringPune 411001

Indian Railways Institute of Civil EngineeringPune 411001

Page 2: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

Price < 60/-

First Edition : October 2015

Page 3: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

i

Compendium of

Instructions Related to Inspections

and

Competency Certificates in

Engineering Department

Compendium of

Instructions Related to Inspections

and

Competency Certificates in

Engineering Department

Indian Railways Institute of Civil Engineering,

Pune 411001

October 2015

Page 4: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

ii

Page 5: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

iii

Foreword

Inspections are an integral part of the various safety measures

undertaken by the Railways to make train-mode transport safe,

comfortable, efficient and punctual. Inspections in general means

visits to various work centres to carefully examine the working of

the system; find out the defects and to see that rules and

instructions are implemented according to their spirit. It is both

educative and corrective in nature.

The Civil Engineering assets comprise important part in Railway

system and its upkeep is very important from safety and comfort point

of view. This handbook containing compendium of instructions

related to inspection of civil engineering assets would be of great

help to all the inspecting officials. An attempt has been made in

formulating certain frame work which will be of help in facilitating

focussed and in-depth inspections of civil engineering asset.

The information presented in this book is in no way intended to

supersede or negate any existing rules, regulations, or instructions

contained in various codes and manual. Further, it is not intended to

conflict with any currently effective operating and maintenance

instructions and/or specifications. It also cannot be taken as

exhaustive. It should, however, always be kept in mind that

inspections are not merely fault finding. It is one of the most

effective tools that can be intelligently used to run the system

smoothly and safely.

It is hoped that all Engg officials will make use of present book

during their inspections in improving quality of inspections and

thereby bringing overall improvement in productivity and

performance enhancement of Civil Engg. assets in particular and Rly

system in general.

(Vishwesh Chaubey)

Director/IRICEN

Page 6: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

iv

Page 7: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

v

S.N. Title Page

1 Inspection schedule of Engineering Officials

A. Sr.DEN/DEN 1

B. ADENS 4

C. SSE/SE/JE (P.Way) 9

D. SSE (Works) 14

E. Bridge Organization 18

F. Track Machine Organization 20

2 List of Functionaries Authorise to issue Competency

Certificate for various track activities 23

3 Check List for different Registers for Track Maintenance 41

4 Check list for Inspection of Open Line Organization

A. Track 65

B. SSE (P.Way) Office/Store 82

C. USFD testing 83

D. AT Welding 91

E. Level Crossing 107

F. Tamping Machine 116

G. Ballast Cleaning Machine 131

H. Check List of Concrete Sleeper Plant 150

I. Bridges & Tunnels 157

J. Passenger Amenities 169

K. Colony And Other Buildings 187

CONTENTS

Page 8: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

vi

L. Land matters 192

M. Steel Structures in Work Shops, Running Sheds &

P/F Covers 197

N. Steel Water Tank, Staging and Flood Light Towers 198

O. Water Supply Installation 200

P. Rain Water Harvesting System 203

5 Check List for New Construction Site

A. Worksite 204

B. Work in/near Electrified Area 206

C. Precautions within Station Premises 207

D. Track Ballast 207

E. Formwork in Concrete Work 210

F. Box Pushing Work 210

S.N. Title Page

Page 9: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

1

CHAPTER - 1

INSPECTION SCHEDULES OF ENGINEERING OFFICIALSG

A. Inspection Schedules of Sr. DENs /DENs

S. Type of Schedule of Reference

N. Inspection Inspection

1. Push Trolley Once in four month.

Inspection Unimportant branch line

having less than 2 GMT

traffic – Once in 6 month

2. Foot Plate/ Brake Once in three month to

Van/Rear Window cover his entire section

either by footplate, rear-

window, TRC or OMS.

3. Points & Crossings At least one Point & Cross-

ing on passenger running

line as often as possible

4. Level Crossing Minimum one Level

Crossing per PWI every

three month

5. LWR/SEJs During routine motor

trolley/push trolley or

foot inspection

6 Hot Weather As and when required

Patrolling

RB No.

2013/CE-11/

CS/1 dated

20.06.2013

Page 10: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

2

7. Curves Minimum one curve in

each ADEN’s section every

four month

8 Inspection of As much as possible

ongoing works of during Foot Plate/Trolley

construction and inspections to check quality

other organization and safety

e.g. RVNL etc

9. Land boundary During trolley inspection at

verification vulnerable locations

10. Track renewal/ As much as possible during

Deep Screening site Trolley inspection

11. AT welding site As much as possible during

Trolley inspection

12. Private sidings When referred

13. Review of Routine checking during

inspection by trolley inspection

subordinate

14. Bridge:

• Important Bridge • Once in a year

• On reference by • On reference

ADEN

• Bridge with • Once in a year Para 1104

Overall Rating of IRBM

number (ORN)

1,2,3

S. Type of Schedule of Reference

N. Inspection Inspection

RB No.

2013/CE-

II/CS/1 dated

20.06. 2013

Page 11: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

3

15. Tunnel on on reference

reference

from ADEN

16. Inspection of Track

machines working

in the section

• CSM, BCM, FRM, • Once a two month when

P&C Tamper, DTS working in section

• T-28, PQRS • At least once in a month

• UT, UNO, DUO, • As per need

BRM

17. Night/surprise Minimum once in three

Inspection month. More intensive

during monsoon

18. Monsoon Patrolling Minimum once in two

month to evaluate

adequacy of safety

19. Gang Inspection Minimum one gang per .

SSE every three month

20. Railway Affecting Peruse the inspection

Works/ Tanks report of revenue /PWD

and forward, with name

of Tank (so marked) for

inspection by ADEN to

report upon.

21. TRC/OMS run Accompany each TRC run RB No. 2013/CE-

and alternate OMS run II/CS/1 dated

20.06.2013

S. Type of Schedule of Reference

N. Inspection Inspection

Para 1104

of IRBM

RB No. 2013/

CE- II/CS/1

dated

20.06.2013

Para 726 of

IRPWM

Page 12: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

4

22 Inspection of Once a year IRPWM Para

waterworks 554 (d)

S. Type of Schedule of Reference

N. Inspection Inspection

S. Type of Schedule of Reference

N. Inspection Inspection

1. Push Trolley Entire section Main Line

Inspection – Once in 2 month

Unimportant branch Lines

having GMT < 2

– once in 3 month

2. Fast train Entire sub-division either Para 107 (2) of

inspection by engine / rear window IRPWM

of a fast train or by TRC/ (C.S. No. 132)

OMS - Once a month

3. Points & All Points & Crossings on

Crossings passenger lines once a year

& 10% of Points &

Crossings on other lines

4. Level Crossing All manned Level crossings Para 107(3) of

- Once in six month IRPWM (C.S. No.

132)

5. LWR Once in six month Para 8.1.5(ii) of

(Preferably in hottest and LWR Manual

coldest month)

6. Curves One curve each SSE Para 107(4) of

jurisdiction every quarter IRPWM

B. Inspection Schedule of ADEN

Para 107 (1) of

IRPWM

(C.S. No. 132)

Para 107(5) of

IRPWM

Page 13: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

5

7. Bridge Once in a year after Para 102(a) of

monsoon IRBM

8 Inspection of Side Once in a year before

drains, Catch water on set of rains

drains and Water

ways of bridges &

culvert

9 Inspection of Once in a year before Para 1011 of

Cutting onset of rain IRBM C.S. NO.28

10. Tunnel Once in a year before Para 1004 of

Monsoon IRBM

11 Inspection of Track

machines working

in the section

• CSM, BCM, FRM, • Once a month when

P&C Tamper, DTS working in section

• T-28, PQRS, TRT • At least once in fortnight

& RGM

• UT, UNO, DUO, • At least once in a period

BRM of working in their section

12. Night foot plate Once in a month between Para 107 of

Inspection 0.0 – 4.00 hrs. IRPWM

13. AT Welding AT welding each site as Para 107 (11) of

much as possible but at IRPWM

least once in a month C S NO. 132.

S. Type of Schedule of Reference

N. Inspection Inspection

Para 223(C) of

IRPWM

CS no. 132

C.S. No.14 of

IRTMM

Para 5.3.3

Page 14: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

6

14. Test check of USFD USFD checking few hours Para 4.3 of USFD

Inspection each month (min. two manual 2012

hours) during regular

Trolley Inspection.

15. Monsoon At night once in a month Para 107 (6) of

Patrolling either by train, push IRPWM

trolley, Motor trolley. (C.S. No. 132)

16. Private Sidings Min. once in a year S. NO.1.4

Inspection

Manual Rly.Bd.

17. Gang Inspection Min. one Gang each SSE Para 107 (1) of

every quarter IRPWM

(C.S. No. 132)

18. RAW/RAT Min. once in a year before Para 726 of

inspection monsoon IRPWM

19. Inspection of Sand Min. once in a year -

Humps

20. Inspection of Steel Once in 12 month Para 273(b)(7) of

Channel Sleepers alternately with SSE IRPWM

(P way) (C.S.No. 128)

21. TRC/OMS Run Every Run Para 111 of

IRPWM

S. Type of Schedule of Reference

N. Inspection Inspection

Page 15: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

7

22. Inspection of

Steel Structures

• Structure such as work- • One fifth every year

shops, running sheds, on a programmed

platform covers and basis

foot over bridges

• Cast iron, wrought • As required

iron or pressed

steel plate water

tanks and

staging’s whether of

steel section or rails

• Structures with roof • 10-20% test check

trusses inspection of struc-

ture under each

group

• Other structures in • 10-20% test check

which timber, rail or inspection of

steel work is used to structure under

support any part of the each group

structure

• Tie rods of arched roof • 10-20% test check

excluding jack inspection of

structure under

each group

• Wrought iron or mild • 10-20% test check

steel tanks or sleeper inspection of

cribs at temporary structure under

watering kilometerage. each group

S. Type of Schedule of Reference

N. Inspection Inspection

Para 228(a)

of IRWM

Page 16: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

8

23. Inspection of staff As many buildings

quarters & service (particularly those

buildings required heavy repairs)

24. Inspection of water Once in 3 month Para 554(c)

supply installations (i) of IRWM

25. Inspection of Land Once a year Para 813 of

boundary and IRWM

Encroachment

26. Inspection of colony Once in 2 month Para 225(b)

by care committee (iii) of IRWM

28. Inspection of colony by Once in 2 month Para 225(a)

Services Improvement of IRWM

Group (SIG)

29. Inspection and checking Minimum once a year Para 115 of

of stores and office of IRPWM

SSE

30. Small Track Machines Once in 6 month each Para 115(b)

PWI of IRPWM

31. Inspection of Canal and Joint inspection with Para 1103 of

Irrigation crossing state government IRBM

officers wherever

necessary

32 Inspection of washable Once in 6 month Railway Board

apron Lr.No.2010

CE-II/TK/11

dt.8.11.2010

S. Type of Schedule of Reference

N. Inspection Inspection

Para 224 (d)

of IRWM

Page 17: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

9

C. Inspection Schedule of SSE/SE /JE (P.Way)

(Over all in-charge/Sectional)

S. Type of Schedule of Reference

N. Inspection Inspection

33 Joint Inspection for Annually

identifying trees which

are likely to endanger

safety of track along

with Junior scale

officers of S&T and

Electrical Department.

34 Inspection of station As prescribe and Para 302 of

and Colony by nominated by GM IRWM

sanitation committee.

S. Type of Schedule of Reference

N. Inspection Inspection

1 Foot Inspection

C.S. No. 132

of IRPWM

Over all in charge

– As much as possible

on pro-rata basis so as

to cover entire section

at least once a year

Not Over all in charge

– Once in a six month

in a systematic

manner (Every month

on pro rata basis so

as to cover entire

length of running

track)

Para 715 (c)

of IRWM

Page 18: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

10

Over all in-charge

– Entire section by Push/

Motor Trolley – Once in a

month

Not Overall in charge

- Entire section by Push

trolley – Once in a

fortnight

SSE/JE –

Once in a month

Over all in charge – Night

Foot plate once in a

month between 00 to

4.00 hrs

Not over all in charge –

Once in a month

Over all in-charge – One

inspection every month by

train and inspection by

trolley – As per the schedule

laid down by the

administration

Not over all in charge – One

inspection every fortnight by

train and inspection by

trolley - As per the schedule

laid down by the

administration

2 Inspection of

Gangs / Trolley

Inspection

Para 124 of

IRPWM (C.S.

No. 132)

Para 139 of

IRPWM

(CS No.132)

3 Loco / Break van /

Rear window

Para 123 &

139 (6) of C.S.

132, IRPWM

5 Night Inspection Para 139 (8) of

IRPWM CS

no.132

6 Monsoon

Patrolling

Para 126 of

IRPWM

4 Night Foot plate

InspectionPara 124 & 139

of IRPWM

C.S. No. 132

S. Type of Schedule of Reference

N. Inspection Inspection

Page 19: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

11

S. Type of Schedule of Reference

N. Inspection Inspection

Passenger & running line

– Once in three month by

rotation with JE / P. way.

Other lines & yards lines –

Once in a six month by

rotation with JE / P. way.

Once in a month by

rotation with JE / P. way

Once in fort night during

two coldest and two

hottest month otherwise

once in two month by

rotation with JE

Once in six month by

rotation with JE

Over all in charge - Once

in a year in prescribed

month before monsoon

Once in a year after

monsoon

Over all in charge - Once

in a year in Prior to

monsoon

Not Over all in charge -

Once in a year in the month

of April prior to monsoon

7 Points & Crossings

Para 126 of

IRPWM

8 Level Crossing

Para 8.1.5 of

LWR Manual

and Para 144

of IRPWM

9 LWR

Para 124 &

139 of IRPWM

(CS No. 132)

10 Curves

Para 1101 of

IRBM

11 Bridge

Para 1001 of

IRBM

12 Tunnel

Para 223 of

IRPWM

(CS no. 132)

13 Inspection of Side

drains, Catch

water drains and

Water ways of

bridges & culvert

Page 20: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

12

SSE/JE - Once in a year

immediately after

Monsoon

Over all in charge –

Once at the time of taming.

Not Over all in charge –

Once at the time of pre

tamping, during tamping

and post tamping.

Over all in charge – As

much as possible but at

least once in a month

Not Over all in charge –At

least two inspections in a

month

SSE/JE - Once in three

month

Over all in charge -Once in

a year by rotation with

ADEN

SSE – Each run

JE - Alternate run

S. Type of Schedule of Reference

N. Inspection Inspection

14 Cutting Para 1011 of

IRBM

(C.S.No.28)

C.S. No.14 of

IRTMM

Para 5.3.3

15 Inspection of pre

tamping, during

tamping and post

tamping

operations during

working of track

machines

Para 127 (3)

and 139 (9) of

IRPWM

(CS No. 132)

16 Inspection of AT

Welding site

Manual of

Inspection

Schedule for

Engg. official

17 Private Sidings

Para 273(b)(7)

of IRPWM

(C.S. No. 128)

18 Inspection of Steel

Channel Sleepers

Para 139 (7)

of IRPWM

19 Accompany TRC/

OMS Run

Page 21: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

13

S. Type of Schedule of Reference

N. Inspection Inspection

Over all in charge -

Once a year

SSE in charge - Once in 3

month

SSE/JE - As much as

possible during foot plate

and trolley inspection

Once in 3 month on

rotation basis by SSE/P.

Way (overall in charge) &

JE/P. Way (not in overall

in charge)

Once in 3 month with

Section Engineer (S&T) if

not done by sectional J.E.

Once in 6 month with

Section Engineer (S&T) if

not done sectional J.E.

20 Inspection of Land

boundary and

Encroachment

Para 813 of

IRWM

Para 1.5 of

IRSTM (CS No.2)

21 Small Track

Machines

Para 127 (4)

and 139 (10)

of IRPWM

(CS No.132)

22 Ongoing work of

construction and

other organization

e.g. RVNL etc.

Railway Board

Lr.No.2010/CE-

II/TK/11

dt.8.11.2010

23 Inspection of

Washable Apron

24 Joint Inspection of

Points & Crossings

Interlocked points

on passenger run-

ning lines

25 Joint Inspection of

Points & Crossings

Interlocked points

on other than

passenger running

lines.

Page 22: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

14

S. Type of Schedule of Reference

N. Inspection Inspection

Once in three month

Once a year

Every year

26 Inspection of

Encroachment

Para 814 (d) of

IRWM

Para 813(c) of

IRWM

27 Inspection of Land

boundary

verification at

between stations

and unimportant

stations

Para 720 of

IRWM

28 Survey of

Surviving trees

S. Type of Schedule of Reference

N. Inspection Inspection

• Once a year during the

prescribed month.

1 Inspection of Steel

Structures

• Structure such

as workshops,

running sheds,

platform covers

and foot over

bridges

• Cast iron,

wrought iron or

D. Inspection Schedules of SSE/Works

• Once a year on a

Programmer basis.

Para 228 (a)

of IRWM

Page 23: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

15

S. Type of Schedule of Reference

N. Inspection Inspection

pressed steel

plate water

tanks and

staging’s

whether of steel

section or rails

• Structures with

roof trusses

• Other structures in

which timber, rail

or steel work is

used to support

any part of the

structure

• Tie rods of arched

roof excluding jack

• Wrought iron or

mild steel tanks

or sleeper cribs at

temporary

watering

kilometerage

• Once a year during the

prescribed month.

• Once a year during the

prescribed month

• Once a year during

the prescribed month

• Once a year during

the prescribed

month

Para 224 (e)

of IRWM

2 All the buildings, water

supply installations,

sewerage installations

and drainage

arrangements once a

year.

Inspection of

Buildings

Para 228 (a)

of IRWM

Page 24: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

16

S. Type of Schedule of Reference

N. Inspection Inspection

Para 552 (a)

of IRWM

3 FrequentlyInspection of all

water supply

installations & Pipe

lines

Inspection of Land

boundary

verification at

important stations

and staff colonies

Inspection of

Encroachment

Inspection of colony

by care committee

Inspection of colony

by Services

Improvement

Group (SIG)

Testing of yield of

tube well and other

source of water

Petty repair/

Complaint book

Joint Inspection of

Pumping machinery

along with staff of

Para 813 (c)

of IRWM

4 Once a year

Para 814 (d) of

IRWM

5 Once in three month

Para 225 (b)

(iii) of IRWM

6 Once in 2 month

Para 225 (e)

of IRWM

7 As prescribed

Para 119 (c )

of IRWM

8 Once a year in

coordination with

Electrical staff at the

time when the subsoil

water is at the lowest.

225 (a & b (i))

of IRWM

9 Frequently

554 c (i) of

IRWM

10 Once a year

Page 25: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

17

S. Type of Schedule of Reference

N. Inspection Inspection

Mechanical/

Electrical

Department

Survey of Surviving

trees

Storage-tanks for

drinking water and

for flushing

purposes over

offices, bungalows

and quarters

Inspection of leaky

roofs.

Inspection of

bridges minor ,

major and

important including

ROB/RUB/FOB

(except track and

approaches)

(as per practice of

railways)

Detail inspection of

steel girder less

than 12.2 m clear

span ( as per

practice of railway)

Para 813 (c)

of IRWM

11 Every year

Para 552 (b) of

IRWM

12 Frequently

Annexure 2.7,

Para 5 of

IRWM

13 Preferably be done

during rainy season

Para 117 and

1101 of IRBM

14 Once a year prior to

monsoon

Para 1101 (a)

iv of IRBM

15 Once in five years

- 20% per year.

Page 26: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

18

S. Type of Schedule of Reference

N. Inspection Inspection

Inspection of tunnel

(structural part

only)

Para 1001 of

IRBM

16 Once a year during the

prescribe month after

the monsoon season

S. Type of Schedule of Reference

N. Inspection Inspection

Steel work of

Bridges

Steel work of

Bridges

Para 1106 (2a)

of IRBM

1 Called for his inspection

after scrutiny of register

by DEN(Br) /AEN(Br)

As directed by CBE

E. Inspection Schedules of Bridge Organization

Inspection Schedules of Dy. CE (Bridge)

Para 1106 (2a)

of IRBM

1

2 Para 1106 (2b)

of IRBM

Inspection Schedules of Assistant (Bridge)

Engineer/Divisional Bridge Engineer

S. Type of Schedule of Reference

N. Inspection Inspection

Bridges Para 105 (2) of

IRBM

1 All overstressed girders

where camber loss is

noted and such bridges

which have been

referred to him by BRI

1

Page 27: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

19

S. Type of Schedule of Reference

N. Inspection Inspection

Bridges Para 105 (2) of

IRBM

3

Called for his inspection

based on scrutiny of the

Bridge Inspector’s

registers.

10% test check of the

Bridges inspected by

Bridge Inspectors every

year.

All such steel structures

as ordered by the Chief

Engineer at specified

intervals.

Bridges Para 105 (2) of

IRBM

2

Bridges Para 105 (2) of

IRBM

4

Inspection Schedules of Bridge Inspector

S. Type of Schedule of Reference

N. Inspection Inspection

All welded, RCC,

PSC and composite

girders and their

bearings.

Girders kept under

observation

Floor system of

early steel girders

Para 107(1a)

of IRBM

1 Within one year of

Installation.

Para 107(1b)

of IRBM

2 Once a year or at intervals

specified by the CBE

Para 107(1c)

of IRBM

3 Once a year

Page 28: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

20

S. Type of Schedule of Reference

N. Inspection Inspection

Superstructure

including bearings

of all steel girders

of span 12.2m and

above, RCC,PSC and

composite girder

bridges.

Other nominated

steel structures,

being maintained

by Bridge Inspector

Para 107 (1d)

of IRBM

4 Once in five years on

planned basis.

Para 107 (1e)

of IRBM

5 Once in five years.

F. Inspection Schedules of Track Machine Organization

Inspection Schedules of Dy.CE and Senior Engineer

In-charge of Track Machines

S. Type of Schedule of Reference

N. Inspection Inspection

Inspection of

Machines

Para 1.1 of

IRTMM

1 Frequently especially

where a group of

machines such as

tamping, ballast cleaning

machines are deployed.

Page 29: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

21

Inspection Schedules of Assistant Engineer

(Track machine)

S. Type of Schedule of Reference

N. Inspection Inspection

Inspection of

Machines

• CSM

• Unimat

• BCM

• BRM

• SBCM

• DTS

• UNO

• DUO

• T-28

• PQRS

• TRT

1

Para 5.3.2 (ii)

of IRTMM

• Monthly

• Monthly

• Fortnightly

• Once in two month

• Monthly

• Once in two month

• Monthly

• Monthly

• Monthly

• Monthly

• Weekly

Page 30: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

22

Inspection Schedules of SSE/Track Machine

S. Type of Schedule of Reference

N. Inspection Inspection

Inspection of

Machines

• CSM

• Unimat

• BCM

• BRM

• SBCM

• DTS

• UNO

• DUO

• T-28

• PQRS

• TRT

1

Para 5.3.2(ii)

of IRTMM

• Fortnightly

• Fortnightly

• Weekly

• Monthly

• Fortnightly

• Monthly

• Fortnightly

• Fortnightly

• Fortnightly

• Fortnightly

• Daily

Every Officer should ensure inspections as per 'Inspection

Schedules'.

Quality of inspection is as important as an inspection.

� � �

Page 31: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

CH

AP

TE

R -

2

LIS

T O

F F

UN

CT

ION

AR

IES

AU

TH

OR

ISE

TO

IS

SU

E C

OM

PE

TE

NC

Y

CE

RT

IFIC

AT

E F

OR

VA

RIO

US T

RA

CK

AC

TIV

ITIE

S.

S.

N.

Au

tho

rity

&

Re

fere

nce

fro

m M

an

ua

l/

Cir

cula

r/

G&

SR

Au

tho

rise

le

ve

l

of

Su

pe

rvis

ion

/

De

sig

na

tio

n

Fun

ctio

na

rie

s

au

tho

rise

to

issu

e

com

pe

ten

cy /

pe

rmis

sio

n f

or

wo

rk.

Na

ture

of

Act

ivit

y /

Wo

rk

Lift

ing

/Lo

we

rin

g o

f tr

ack

in

LW

R t

err

ito

ry

(Be

yon

d t

ha

t is

do

ne

in

no

rma

l

ma

inte

na

nce

of

tra

ck)

1A

NN

VI

Ite

m

1(C

) ii L

WR

Ma

nu

al

19

96

du

ly u

p d

ate

d

in C

S N

O.

14

Co

mp

ete

ncy

cert

ific

ate

sho

uld

be

issu

ed

by C

TE

PW

M

De

ep

Scr

ee

nin

g i

n L

WR

te

rrit

ory

2A

NN

VI

Ite

m

1(C

) ii L

WR

Ma

nu

al

19

96

du

ly u

p d

ate

d

in C

S N

O.

14

Co

mp

ete

ncy

cert

ific

ate

sho

uld

be

issu

ed

by C

TE

PW

M

23

Page 32: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

24

S.

N.

Au

tho

rity

&

Re

fere

nce

fro

m M

an

ua

l/

Cir

cula

r/

G&

SR

Au

tho

rise

le

ve

l

of

Su

pe

rvis

ion

/

De

sig

na

tio

n

Fun

ctio

na

rie

s

au

tho

rise

to

issu

e

com

pe

ten

cy /

pe

rmis

sio

n f

or

wo

rk.

Na

ture

of

Act

ivit

y /

Wo

rk

3To

ca

rry

ou

t M

ain

ten

an

ce w

ork

un

de

r

the

ir p

ers

on

al

Su

pe

rvis

ion

in

LW

R/C

WR

.

Pe

rmit

ted

on

ly f

oll

ow

ing

wo

rk

1.

Ma

inte

na

nce

op

era

tio

n -

Lif

tin

g /

Low

eri

ng

of

tra

ck

2.

Ra

ils,

sle

ep

ers

an

d f

ast

en

ing

s

(a)

Ca

sua

l re

ne

wa

l if

sle

ep

ers

an

d

fast

en

ing

ove

r lo

ng

s

tre

tch

es

(b)

Re

ne

wa

l o

f d

efe

ctiv

e r

ail

s

3.

Min

or

rea

lig

nm

en

t o

f cu

rve

s

4.

Tem

po

rary

re

pa

irs

to r

ail

fra

ctu

re

Pa

ra 9

.1.3

(i),

9.2

.2 a

nd

9.2

.3 o

f LW

R

Ma

nu

al1

99

6

Co

mp

ete

ncy

cert

ific

ate

Issu

ed

by

Zo

na

l o

r

Div

isio

na

l

Tra

inin

g

ce

ntr

e t

o

wo

rk o

n

LWR

/CW

R

(va

lid

fo

r 3

yea

rs)

(W

ork

pre

scri

be

d i

n

AN

N V

I o

nly

)

PW

M

Page 33: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

25

S.

N.

Au

tho

rity

&

Re

fere

nce

fro

m M

an

ua

l/

Cir

cula

r/

G&

SR

Au

tho

rise

le

ve

l

of

Su

pe

rvis

ion

/

De

sig

na

tio

n

Fun

ctio

na

rie

s

au

tho

rise

to

issu

e

com

pe

ten

cy /

pe

rmis

sio

n f

or

wo

rk.

Na

ture

of

Act

ivit

y /

Wo

rk

To c

arr

y o

ut

Ma

inte

na

nce

wo

rk u

nd

er

the

ir p

ers

on

al

sup

erv

isio

n i

n L

WR

/CW

R.

Pe

rmit

ted

on

ly f

ollo

win

g w

ork

s

1.

(a)

En

suri

ng

th

at

all

cre

ep

an

cho

rs

bu

tt a

ga

inst

sle

ep

ers

du

rin

g d

aily

rou

nd

s.

(b)

Re

ne

wa

l o

f fa

ste

nin

gs

no

t

req

uir

ing

lif

tin

g.

2.

Em

erg

en

cy r

ep

air

s to

Ra

il fr

act

ure

3.

Insp

ect

ion

an

d C

he

ckin

g o

f SE

J, o

ilin

g

an

d g

rea

sin

g a

nd

re

-tig

hte

nin

g /

ren

ew

al

of

fitt

ings

on

ce a

fo

rtn

igh

t.

(Po

stin

g o

f K

ey

me

n a

fte

r ge

ttin

g

valid

co

mp

ete

ncy

ce

rtif

ica

te b

y

Zo

na

l/ D

ivis

ion

al

tra

inin

g c

en

tre

wh

ich

will

be

va

lid f

or

thre

e y

ea

rs

fro

m t

he

da

te o

f is

sue

.)

4LW

R m

an

ua

l

19

96

Pa

ra

9.2

.2 a

nd

Pa

ra 9

.2.3

an

d A

NN

VI

Zo

na

l /

Div

isio

na

l

Tra

inin

g

cen

tre

.

(Va

lid f

or

3

yea

rs f

rom

th

e

da

te o

f is

sue

)

Ke

y m

an

Page 34: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

26

S.

N.

Au

tho

rity

&

Re

fere

nce

fro

m M

an

ua

l/

Cir

cula

r/

G&

SR

Au

tho

rise

le

ve

l

of

Su

pe

rvis

ion

/

De

sig

na

tio

n

Fun

ctio

na

rie

s

au

tho

rise

to

issu

e

com

pe

ten

cy /

pe

rmis

sio

n f

or

wo

rk.

Na

ture

of

Act

ivit

y /

Wo

rk

a.

Ho

t w

ea

the

r p

atr

ollin

g a

s p

er

IRP

WM

an

d L

WR

ma

nu

al

b.

Co

ld w

ea

the

r p

atr

olli

ng

c.P

rote

ctio

n o

f tr

ack

an

d s

ecu

re s

afe

ty

of

tra

ins

in c

ase

of

bu

ckli

ng

, ra

il

fra

ctu

res,

or

an

y a

bn

orm

al

be

havi

ou

r o

f tr

ack

5P

ara

10

08

of

IRP

WM

an

d

AN

N V

I (p

ara

5 &

6)

of

LWR

Ma

nu

al

19

96

.

SSE

/P.

wa

y

(Exp

eri

en

ced

an

d t

rust

wo

rth

y m

en

fro

m t

he

Pe

rma

ne

nt

Ga

ng

to

wo

rk

as

pa

tro

lme

n/

Wa

tch

me

n.

Als

o b

e v

eri

fie

d

for

visi

on

te

st &

sha

ll n

ot

em

plo

yed

as

Pa

tro

lme

n

un

less

pa

sse

d

req

uis

ite

me

dic

al

test

.)

a.H

ot

We

ath

er

Pa

tro

lme

n

b.C

old

We

ath

er

Pa

tro

lme

n

c.P

atr

olm

an

/

Tra

ck

ma

n/

Ga

ng

Ma

te

Page 35: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

27

S.

N.

Au

tho

rity

&

Re

fere

nce

fro

m M

an

ua

l/

Cir

cula

r/

G&

SR

Au

tho

rise

le

ve

l

of

Su

pe

rvis

ion

/

De

sig

na

tio

n

Fun

ctio

na

rie

s

au

tho

rise

to

issu

e

com

pe

ten

cy /

pe

rmis

sio

n f

or

wo

rk.

Na

ture

of

Act

ivit

y /

Wo

rk

Au

tho

rise

le

vel

of

sup

erv

isio

n a

s p

er

LWR

Ma

nu

al

(1)

Me

cha

nis

ed

Ma

inte

na

nce

incl

ud

ing

Lif

tin

g,

alig

nin

g,

pa

ckin

g e

tc

in c

ase

of

em

erg

en

cie

s a

t

tem

pe

ratu

res

hig

he

r th

an

th

ose

pe

rmit

ted

. W

eld

ing

of

rail

join

t a

t

site

.

(2)

Re

ple

nis

hm

en

t o

f b

alla

st &

ch

eck

ing

balla

st

se

ctio

n

be

fore

on

set

of

sum

me

r.

(3)

Ma

jor

rea

lign

me

nt

of

curv

es

un

de

r

spe

cia

l in

stru

ctio

ns

fro

m

AE

N

(4)

Org

an

isin

g h

ot

we

ath

er

pa

tro

llin

g

du

rin

g s

um

me

r m

on

ths.

6C

ha

pte

r X

V o

f

IRP

WM

an

d

AN

N V

I o

f

LWR

Ma

nu

al

Su

bje

ct t

o

vari

ou

s in

itia

l

/re

fre

she

r/

Pro

mo

tio

na

l

cou

rse

at

ZR

TI

PW

I

(JE

/SS

E-

P. W

ay

)

Page 36: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

28

S.

N.

Au

tho

rity

&

Re

fere

nce

fro

m M

an

ua

l/

Cir

cula

r/

G&

SR

Au

tho

rise

le

ve

l

of

Su

pe

rvis

ion

/

De

sig

na

tio

n

Fun

ctio

na

rie

s

au

tho

rise

to

issu

e

com

pe

ten

cy /

pe

rmis

sio

n f

or

wo

rk.

Na

ture

of

Act

ivit

y /

Wo

rk

(5)

Insp

ect

ion

in

su

mm

er

mo

nth

s a

nd

che

ckin

g o

n t

he

wo

rkin

g o

f h

ot

we

ath

er

pa

tro

ls

(6)

All o

pe

rati

on

s re

ga

rdin

g d

istr

ess

ing

(7)

Pe

rma

ne

nt

rep

air

s to

Ra

il fr

act

ure

(8)

Bu

ckli

ng

(

a) E

me

rge

ncy

re

pai

rs

(

b)

Pe

rman

en

t re

pai

rs

(9)

Act

ion

in

ca

se o

f d

am

age

to

tra

ck

foll

ow

ing

De

rail

me

nts

, b

rea

che

s e

tc.

(10

)In

spe

ctio

n &

Ch

eck

ing o

f SE

J

Pe

rmit

ted

to

use

tro

lley/L

orr

y /

do

lly7

As

pe

r

IRP

WM

Pa

ra

11

03

& 1

10

4

an

d G

& S

R

Ch

ap

XV

SR

15

.18

.3

Min

. JA

gra

de

off

ice

r fr

om

en

gin

ee

rin

g

de

pa

rtm

en

t.

(Va

lid

fo

r o

ne

yea

r)

Ga

ng

ma

te/

Se

ctio

n

Ma

tes

Ch

ap

ter

XV

of

IRP

WM

an

d

AN

N V

I o

f

LWR

Ma

nu

al

Su

bje

ct t

o

vari

ou

s in

itia

l

/re

fre

she

r/

Pro

mo

tio

na

l

cou

rse

at

ZR

TI

PW

I

(JE

/SS

E-

P. W

ay

)

Page 37: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

29

S.

N.

Au

tho

rity

&

Re

fere

nce

fro

m M

an

ua

l/

Cir

cula

r/

G&

SR

Au

tho

rise

le

ve

l

of

Su

pe

rvis

ion

/

De

sig

na

tio

n

Fun

ctio

na

rie

s

au

tho

rise

to

issu

e

com

pe

ten

cy /

pe

rmis

sio

n f

or

wo

rk.

Na

ture

of

Act

ivit

y /

Wo

rk

Re

spo

nsi

bil

ity

of

ke

ep

ing

le

ng

th o

f

lin

e s

afe

fo

r p

ass

ag

e o

f tr

ain

s a

nd

sig

na

l su

pp

lie

d a

re t

o b

e k

ep

t in

pro

pe

r o

rde

r a

nd

re

ad

y f

or

use

.

Co

rre

ct k

no

wle

dg

e o

f h

an

d s

ign

al

an

d d

eto

na

tin

g s

ign

als

an

d o

the

r

too

ls o

r im

ple

me

nts

as

ma

y b

e

pre

scri

be

d b

y s

pe

cia

l in

stru

cti

on

s.

Use

of

pri

va

te t

roll

ey

Pe

rmit

ted

ON

LY

in s

idin

g

Ce

rtif

ica

te o

f co

mp

ete

ncy

to

pe

rmit

use

of

Mo

tor

tro

lle

y

8G

en

era

l R

ule

15

.14

Insp

ect

or

of

P. W

ay

or

Wo

rks

Ga

ng

ma

te

Ge

ne

ral

Ru

le

15

.12

Insp

ect

or

of

P. W

ay

or

Wo

rks

Ga

ng

ma

n9

G&

SR

Ch

. X

V

Pa

ra S

R P

ara

15

.18

.(1

3)

On

ly b

y C

E,

CSO

& D

RM

No

n R

ly O

ffic

ial

(By

nam

e)

(use

of

pri

va

te t

roll

ey)

10

G&

SR

Ch

ap

ter

SR

15

.18

.3 a

nd

IRP

WM

11

03

an

d 1

10

4

Min

imu

m J

A

Gra

de

off

ice

r

of

Eng.

dep

t C

E,

CTE

, CB

E, D

RM

Mo

tor

tro

lle

y d

rive

r

11

Page 38: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

30

S.

N.

Au

tho

rity

&

Re

fere

nce

fro

m M

an

ua

l/

Cir

cula

r/

G&

SR

Au

tho

rise

le

ve

l

of

Su

pe

rvis

ion

/

De

sig

na

tio

n

Fun

ctio

na

rie

s

au

tho

rise

to

issu

e

com

pe

ten

cy /

pe

rmis

sio

n f

or

wo

rk.

Na

ture

of

Act

ivit

y /

Wo

rk

Co

mp

ete

ncy

ce

rtif

ica

te t

o G

ate

ma

n

Ce

rtif

ica

te o

f co

mp

ete

ncy

to

pe

rmit

usa

ge

of

tro

lley/M

T/Lo

rrie

s.

12

Pa

ra 9

12

of

IRP

WM

SR

16

.01

.1

Co

mp

ete

ncy

cert

ific

ate

issu

ed

by P

WI

&

Co

un

ters

ign

ed

by A

DE

N o

r b

y

Div

l Tr

ain

ing

Ce

ntr

e

(on

ly

tho

se p

ass

ed

A3

me

dic

al

exa

min

ati

on

)

Ga

tem

an

13

He

ad

tro

lley

ma

n

Min

imu

m J

A

Gra

de

off

ice

r o

f

en

gin

ee

rin

g

de

pa

rtm

en

t.

(Pe

rmit

sh

all b

e

valid

fo

r o

ne

As

pe

r G

&S

R

Ch

ap

ter

XV

SR

15

.18

.1n

d

IRP

WM

11

03

an

d

11

04

Page 39: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

31

S.

N.

Au

tho

rity

&

Re

fere

nce

fro

m M

an

ua

l/

Cir

cula

r/

G&

SR

Au

tho

rise

le

ve

l

of

Su

pe

rvis

ion

/

De

sig

na

tio

n

Fun

ctio

na

rie

s

au

tho

rise

to

issu

e

com

pe

ten

cy /

pe

rmis

sio

n f

or

wo

rk.

Na

ture

of

Act

ivit

y /

Wo

rk

yea

r fr

om

th

e

da

te o

f is

sue

an

d R

en

ew

al

eve

ry y

ea

r.)

Ce

rtif

ica

te o

f co

mp

ete

ncy

to

pe

rmit

usa

ge

of

tro

lley/M

T/Lo

rrie

s.

14

As

pe

r G

&S

R

Ch

ap

ter

XV

SR

15

.18

.1 a

nd

IRP

WM

11

03

an

d 1

10

4

Min

imu

m J

A

Gra

de

off

ice

r,

DR

M,

CB

E,

CT

E.

(Pe

rmit

sh

all

be

va

lid

fo

r o

ne

yea

r fr

om

the

da

te o

f

issu

e a

nd

Re

ne

wa

l e

very

yea

r)

PW

I (S

SE

/

SE

/JE

) P.

Wa

y

Page 40: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

32

S.

N.

Au

tho

rity

&

Re

fere

nce

fro

m M

an

ua

l/

Cir

cula

r/

G&

SR

Au

tho

rise

le

ve

l

of

Su

pe

rvis

ion

/

De

sig

na

tio

n

Fun

ctio

na

rie

s

au

tho

rise

to

issu

e

com

pe

ten

cy /

pe

rmis

sio

n f

or

wo

rk.

Na

ture

of

Act

ivit

y /

Wo

rk

Su

pe

rvis

ion

of

wo

rk s

ite

of

ha

nd

he

ld

off

tra

ck t

am

pe

rs

Op

era

tio

n o

f O

n T

rack

Ma

chin

e

SS

E/S

E/J

E (

P.W

ay

) su

pe

rvis

ing

de

pa

rtm

en

tal

AT

we

ldin

g.

(aft

er

succ

ess

ful

com

ple

tio

n o

f tr

ain

ing

cou

rse

)

15

No

min

ate

d

by

AD

EN

JE/P

.Wa

y

16

Pa

ra 1

.4.1

&

4.2

.1

an

d 4

.3

of

IRT

MM

Issu

ed b

y D

y.C

E/

TM o

f th

e zo

nal

Ra

ilw

ay

* (V

alid

for

3

years

an

d s

hall

be

kep

t in

Pe

rso

na

l cu

sto

dy

of

the

op

erat

or)

Tra

ck M

ach

ine

Op

era

tor

17

Pa

ra 4

.1.2

.3&

an

ne

x .

I o

fM

an

ua

l fo

rF

us

ion

we

ldin

g o

fR

ail

s b

y t

he

Alu

min

o –

Th

erm

icP

roc

es

s

Issu

ed

by

TP

P/L

uck

no

w

or

TW

C/

Vij

aya

wa

da

De

pa

rtm

en

tal

AT

We

ldin

g

Su

pe

rvis

or

IRS

TM

pa

ra

8.1

.3.1

(ii

i)

Page 41: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

33

S.

N.

Au

tho

rity

&

Re

fere

nce

fro

m M

an

ua

l/

Cir

cula

r/

G&

SR

Au

tho

rise

le

ve

l

of

Su

pe

rvis

ion

/

De

sig

na

tio

n

Fun

ctio

na

rie

s

au

tho

rise

to

issu

e

com

pe

ten

cy /

pe

rmis

sio

n f

or

wo

rk.

Na

ture

of

Act

ivit

y /

Wo

rk

We

lde

r fo

r d

ep

art

me

nta

l A

T w

eld

ing

(Pro

vis

ion

al

Ce

rtif

ica

te)

(Aft

er

sati

sfa

cto

ry c

om

ple

tio

n o

f

TW

1 c

ou

rse

at

TP

P/L

uck

no

w o

r T

WC

/

Vij

ay

aw

ad

a w

ith

va

lid

ity

up

to

fo

r

exe

cuti

ng

10

0 j

oin

t o

r 6

mo

nth

s

wh

ich

ev

er

is e

arl

ier)

Re

gu

lar

Co

mp

ete

ncy

Ce

rtif

ica

te f

or

de

pa

rtm

en

tal

we

ldin

g.

(aft

er

sati

sfa

cto

ry c

om

ple

tio

n o

f

TW

2 c

ou

rse

wit

h v

ali

dit

y u

p t

o 2

ye

ars

an

d a

fte

r tw

o y

ea

r

rea

sse

ssm

en

t v

ali

d f

or

5 y

ea

r.)

18

Par

a 4

.1.2

.3 &

An

nex

I o

f

Man

ual

fo

r

Fusi

on

we

ldin

g

of

Rai

ls b

y th

e

Alu

min

o –

Th

erm

ic

Pro

cess

Issu

ed

by

TP

P/L

uck

no

w

or

TW

C/

Vij

aya

wa

da

De

par

tme

nta

l

AT

We

lde

r

19

Par

a 4

.1.2

.3 &

An

nex

I o

f

Man

ual

fo

r

Fusi

on

we

ldin

g

of

Rai

ls b

y th

e

Alu

min

o –

Th

erm

ic

Pro

cess

Issu

ed

by

TP

P/L

uck

no

w

or

TW

C/

Vij

aya

wa

da

De

par

tme

nta

l

AT

We

lde

r

Page 42: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

34

S.

N.

Au

tho

rity

&

Re

fere

nce

fro

m M

an

ua

l/

Cir

cula

r/

G&

SR

Au

tho

rise

le

ve

l

of

Su

pe

rvis

ion

/

De

sig

na

tio

n

Fun

ctio

na

rie

s

au

tho

rise

to

issu

e

com

pe

ten

cy /

pe

rmis

sio

n f

or

wo

rk.

Na

ture

of

Act

ivit

y /

Wo

rk

Pro

vis

ion

al

Co

mp

ete

nc

y

ce

rtif

ica

te

for

we

ldin

g s

up

erv

iso

r a

nd

we

lde

r o

f

firm

.

(Iss

ue

d s

ep

ara

tely

fo

r w

eld

ing

of

52

kg

/

60

kg

wit

h s

tan

da

rd g

ap

, w

ith

wid

e g

ap

,

or

we

ldin

g o

f H

H/1

10

UT

S r

ail

s.)

Re

gu

lar

Co

mp

ete

nc

y c

ert

ific

ate

fo

r

we

ldin

g s

up

erv

iso

r a

nd

we

lde

r o

f fi

rm.

(Aft

er

2 y

ea

rs f

rom

iss

ue

of

Pro

vis

ion

al

Co

mp

ete

nc

y c

ert

ific

ate

fo

r w

eld

ing

sup

erv

iso

r a

nd

we

lde

r o

f fi

rm s

ha

ll b

e

rea

sse

sse

d b

y R

DS

O a

nd

D

G(M

&C

)

RD

SO

ext

en

de

d

va

lid

ity

fo

r 5

ye

ars

(Th

is c

ert

ific

ate

iss

ue

d s

ep

ara

tely

fo

r

we

ldin

g o

f 5

2kg

/60

kg

wit

h s

tan

da

rd g

ap

, w

ith

wid

e g

ap

, o

r w

eld

ing

of

HH

/11

0

UT

S r

ail

s.)

20

As

pe

r IR

ST-

19

/20

12

Pa

ra

16

.2 a

nd

16

.6

DG

(M&

C),

RD

SO

(va

lid

fo

r 2

yea

rs)

Co

ntr

act

or

AT

we

ldin

g

sup

erv

iso

r/

We

lde

r

21

As

pe

r IR

ST-

19

/20

12

Pa

ra

16

.2 a

nd

16

.6

DG

(M

&C

),

RD

SO

Co

ntr

ac

tor

AT

we

ldin

g

sup

erv

iso

r/

We

lde

r

Page 43: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

35

S.

N.

Au

tho

rity

&

Re

fere

nce

fro

m M

an

ua

l/

Cir

cula

r/

G&

SR

Au

tho

rise

le

ve

l

of

Su

pe

rvis

ion

/

De

sig

na

tio

n

Fun

ctio

na

rie

s

au

tho

rise

to

issu

e

com

pe

ten

cy /

pe

rmis

sio

n f

or

wo

rk.

Na

ture

of

Act

ivit

y /

Wo

rk

Superv

isio

n o

f FB w

eld

ing

(Min

dip

lom

a in m

ech

/ele

ct e

ngg o

rBSc

duly

pass

ing t

est

as

per

manual

pro

vis

ion)

Weld

er

for

FB w

eld

ing

(Min

cla

ss X

or

equiv

ale

nt

duly

pass

ing t

est

as

per

manual

pro

vis

ion)

22

Pa

ra 1

3.1

an

d

13

.2 o

f

Ma

nu

al

for

Fla

sh b

utt

we

ldin

g o

f

rail

s re

vise

d

Jan

ua

ry 2

01

2.

Zo

na

l R

ailw

ay

CT

E /

CE

(co

n)

(wit

ho

ut

exa

min

ati

on

if

qu

ality

of

we

ld i

s o

k)

De

par

tme

nta

l

FB

we

ldin

g

sup

erv

iso

r

23

Pa

ra 1

3.1

an

d

13

.2 o

f

Ma

nu

al

for

Fla

sh b

utt

we

ldin

g o

f

rail

s re

vise

d

Jan

ua

ry 2

01

2.

Zo

na

l R

ailw

ay

CT

E /

CE

(co

n)

(wit

ho

ut

exa

min

ati

on

if

qu

ality

of

we

ld i

s o

k)

De

par

tme

nta

l

FB

we

lde

rs

Page 44: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

36

S.

N.

Au

tho

rity

&

Re

fere

nce

fro

m M

an

ua

l/

Cir

cula

r/

G&

SR

Au

tho

rise

le

ve

l

of

Su

pe

rvis

ion

/

De

sig

na

tio

n

Fun

ctio

na

rie

s

au

tho

rise

to

issu

e

com

pe

ten

cy /

pe

rmis

sio

n f

or

wo

rk.

Na

ture

of

Act

ivit

y /

Wo

rk

USFD

op

era

tor

of

de

pa

rtm

en

tal

US

FD

ma

chin

es

(In

itia

l ce

rtif

ica

tio

n)

(Du

ly t

rain

ed

by R

DS

O i

n t

he

te

chn

iqu

e o

f

US

FD

te

stin

g.

Init

iall

y v

ali

d f

or

3 y

ea

rs)

US

FD

op

era

tor

of

de

pa

rtm

en

tal

US

FD

ma

chin

es

(ext

en

de

d v

alid

ity a

fte

r in

itia

l

cert

ific

ati

on

).

(Ext

en

de

d v

alid

ity f

or

5 y

ea

rs a

fte

r

sati

sfa

cto

ry c

om

ple

tio

n o

f re

fre

she

r

cou

rse

.)

USFD

op

era

tor

of

con

tra

cte

d U

SFD

ma

chin

es

(Pro

visi

on

al

cert

ific

ate

)

(iss

ue

d i

n t

hre

e c

ate

go

rie

s w

hic

h R

ail

Test

ing

, W

eld

Te

stin

g a

nd

Ra

il a

nd

We

ld

test

ing

bo

th.

Pro

visi

on

al

cert

ific

ate

iss

ue

d

by R

DS

O v

alid

fo

r 6

mo

nth

s.)

24

Pa

ra 3

ma

nu

al

for

Ult

raso

nic

Ra

il T

est

ing

of

rails

& w

eld

s.

DG

(M

&C

),

RD

SO

De

pa

rtm

en

t

US

FD

Op

era

tor

Pa

ra 3

ma

nu

al

for

Ult

raso

nic

Ra

il T

est

ing

of

rails

& w

eld

s.

DG

(M

&C

),

RD

SO

De

pa

rtm

en

t

US

FD

Op

era

tor

25

Pa

ra 3

.1 a

nd

3.3

of

Pro

ced

ure

ord

er

issu

ed

by R

DSO

con

veye

d b

y

DG

(M

&C

),

RD

SO

US

FD

Test

ing

by

con

tra

cto

r

op

era

tor

26

Page 45: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

37

S.

N.

Au

tho

rity

&

Re

fere

nce

fro

m M

an

ua

l/

Cir

cula

r/

G&

SR

Au

tho

rise

le

ve

l

of

Su

pe

rvis

ion

/

De

sig

na

tio

n

Fun

ctio

na

rie

s

au

tho

rise

to

issu

e

com

pe

ten

cy /

pe

rmis

sio

n f

or

wo

rk.

Na

ture

of

Act

ivit

y /

Wo

rk

Ra

ilw

ayB

oa

rd

L.N

o.T

rack

/21

/

20

04/

09

02

/7

Vo

l –

II D

t.2

4/

10

/20

14

USFD

op

era

tor

of

con

tra

cte

d U

SFD

ma

chin

es

(Re

gu

lar

Ce

rtif

ica

te)

(Iss

ue

d i

n t

hre

e c

ate

go

rie

s w

hic

h R

ail

Test

ing

, W

eld

Te

stin

g a

nd

Ra

il a

nd

We

ld

test

ing

bo

th.

Re

gu

lar

com

pe

ten

cy c

ert

ific

ate

aft

er

veri

fyin

g e

xpe

rie

nce

of

op

era

tor

in U

SF

D

test

ing

10

0 n

o’s

we

ld j

oin

ts o

r 1

00

km

tra

ck (

20

0 K

m r

ails)

RD

SO

iss

ue

com

pe

ten

cy h

avi

ng

va

lid

ity o

f 3

ye

ars

.)

27

Pa

ra 3

.1 a

nd

3.3

of

Pro

ced

ure

ord

er

issu

ed

by R

DSO

con

veye

d b

y

Bo

ard

L.N

o.T

rack

/

21

/20

04/

09

02

/7 V

ol

–II

Dt.

24/

10

/

20

14

DG

(M&

C),

RD

SO

US

FD

Test

ing

by

con

tra

cto

r

op

era

tor

Page 46: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

38

S.

N.

Au

tho

rity

&

Re

fere

nce

fro

m M

an

ua

l/

Cir

cula

r/

G&

SR

Au

tho

rise

le

ve

l

of

Su

pe

rvis

ion

/

De

sig

na

tio

n

Fun

ctio

na

rie

s

au

tho

rise

to

issu

e

com

pe

ten

cy /

pe

rmis

sio

n f

or

wo

rk.

Na

ture

of

Act

ivit

y /

Wo

rk

Qu

ality

Co

ntr

ol

of

Co

ntr

act

USFD

(Co

ntr

act

or

sup

erv

iso

r h

avi

ng

min

imu

m

aca

de

mic

qu

alifi

cati

on

of

BS

c o

r

eq

uiv

ale

nt

wit

h p

hys

ics

as

on

e o

f th

e

sub

ject

or

Dip

lom

a/D

eg

ree

in

En

gin

ee

rin

g f

rom

an

y N

ati

on

al/

Inte

rna

tio

na

l U

niv

ers

ity.

He

sh

all

po

sse

ss r

eq

uis

ite

qu

alifi

cati

on

in

ND

T-

Test

ing

as

pe

r P

ara

7 o

f sp

eci

fica

tio

n.)

28

Pa

ra 3

.1 a

nd

3.3

of

Pro

ced

ure

ord

er

issu

ed

by R

DSO

con

veye

d b

y

Bo

ard

L.N

o.T

rack

/21

/ 2

00

4 /

09

02

/ 7

Vo

l –

II D

t.2

4 /

10

/

20

14

DG

(M

&C

),

RD

SO

Qu

ali

ty

con

tro

l U

SFD

sup

erv

iso

r

by

con

tra

cto

r

Pe

rio

d o

f h

ot

we

ath

er

pa

tro

llin

g

(PW

I/P

WM

sh

all b

e v

igila

nt

& s

ha

ll a

lso

intr

od

uce

d p

atr

ollin

g w

he

n t

em

pe

ratu

re

rise

s a

bo

ve t

d +

20

0C

or

as

pe

r A

NN

X A

of

LWR

Ma

nu

al)

29

Pa

ra 9

.1.2

(i)

& A

NN

X A

LWR

Ma

nu

al

Ch

ief

en

gin

ee

r

Pe

rio

d o

f

Ho

t w

ea

the

r

Pa

tro

llin

g

Page 47: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

39

S.

N.

Au

tho

rity

&

Re

fere

nce

fro

m M

an

ua

l/

Cir

cula

r/

G&

SR

Au

tho

rise

le

ve

l

of

Su

pe

rvis

ion

/

De

sig

na

tio

n

Fun

ctio

na

rie

s

au

tho

rise

to

issu

e

com

pe

ten

cy /

pe

rmis

sio

n f

or

wo

rk.

Na

ture

of

Act

ivit

y /

Wo

rk

Co

ld W

ea

the

r P

atr

ollin

g (

Pe

rio

d a

nd

sect

ion

)

Op

era

tio

n &

ro

uti

ne

ma

ite

na

nce

of

sma

ll t

rac

k m

ac

hin

e

Sk

ille

d q

ua

lifi

ed

we

lde

rs,

fitt

ers

ap

pro

ve

d i

nd

ivid

ua

lly

by

M&

C

dir

ecto

r, R

DS

O,

(Ap

pro

val

& t

est

ing

of

we

lde

r sh

all b

e

tra

ine

d i

n a

cco

rda

nce

wit

h I

S 8

17

sub

ject

to

qu

alify

ing

te

st s

pe

cifi

ed

in

IS

73

10

(p

art

-1

)

30

Pa

ra 9

.1.2

(ii)

& A

NN

X B

LWR

Ma

nu

al

Ch

ief

en

gin

ee

r

Pe

rio

d o

f

CW

P

31

Sm

all t

rack

ma

chin

e

ma

nu

al

Pa

ra

1.3

.2 d

uly

up

da

ted

in

CS

no

.4

Div

l Tr

ain

ing

Ce

ntr

e/

Div

isio

na

l sm

all

tra

ck m

ach

ine

ma

inte

na

nce

cen

tre

Tra

ck

ma

inte

na

r

32

Pa

ra 2

0 o

f

Ind

ian

Ra

ilw

ays

sta

nd

ard

co

de

of

pra

ctis

e f

or

me

tal

arc

M&

C

dir

ect

ora

te

RD

SO

We

lde

r,

fitt

er

for

Bri

dg

e w

ork

sho

p

Page 48: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

Init

ial

cou

rse

at

Ce

ntr

alise

d t

rain

ing

sch

oo

l o

f zo

na

l ra

ilwa

ys a

lon

g w

ith

pra

ctic

al

tra

inin

g i

n f

ield

33

Pa

ra 1

30

3

an

d 1

30

4 o

f

Bri

dg

e

Ma

nu

al

19

98

Ce

ntr

alise

d

tra

inin

g

inst

itu

te o

f

zon

al

railw

ays

Tra

inin

g f

or

Bri

dg

e K

ha

lasi

/Art

isa

ns

/

Bri

dg

e M

istr

y/

Bri

dg

e

Insp

ec

tors

we

ldin

g i

n

Str

uct

ura

l st

ee

l

bri

dg

e c

od

e.

S.

N.

Au

tho

rity

&

Re

fere

nce

fro

m M

an

ua

l/

Cir

cula

r/

G&

SR

Au

tho

rise

le

ve

l

of

Su

pe

rvis

ion

/

De

sig

na

tio

n

Fun

ctio

na

rie

s

au

tho

rise

to

issu

e

com

pe

ten

cy /

pe

rmis

sio

n f

or

wo

rk.

Na

ture

of

Act

ivit

y /

Wo

rk

� � �

40

Page 49: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

41

CHAPTER - 3

ENGINEERING DEPARTMENT REGISTERS

(PHYSICAL/TMS)

1. Points & Crossing Register-Physical: This register is maintained by Senior Section Engineer / Section

Engineer (Permanent Way) [SSE/SE (P.Way)] of the section and it is kept in

his office. Detailed inspections of points & crossings and compliance are

recorded in this register.

TMS: Same register can be accessed through TMS.

Physical Register

S. Item Check Reference

N.

1 Whether chart for inspection is Yes/No Para 236(5) of

prepared in register? IRPWM

2 Whether compliance of each point Yes/No -

is recorded?

3 Whether yard diagram showing Yes/No -

Point No. and details prepared?

4 Whether proper entry has been Yes/No Ann 2/6 & 2/6

done in each column of point and (A) of IRPWM

crossing register?

Page 50: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

42

1 Check Inspection Planning Report. Go to Report >

Inspection > 3. Inspection Planning. Choose PWI and

year, press GO. The asset number color indicates the

position of inspection.

Inspection planned Inspection planned

and done in in the month but

same month. inspection done in

later month.

Inspection planned Inspection planned

in the month and and not done so

month is not over. far

Note down the points and crossings to

be inspected during sample month.

2 Check whether planned inspections done by the

official or not. Go to Report > Inspection > 4. Inspection

Register > select ‘feature type’, ‘from date’, ‘to date’

and click on ‘Click here to see Inspections of individual

assets’ from the list choose same P&C no. and check

details of inspection done during the month or not.

3 Whether compliance of inspection note against

each point is recorded?

TMS

2. Curve Register

This register is maintained by SSE/SE (P.Way) of the section and it is kept

in his office. Versines, Super Elevation and Gauge in the curve are recorded

in the register along with compliance chart of inspections carried out by

Junior Engineer/Senior Section Engineer (Permanent Way) [JE/SSE (P.Way)]

and Assistant Divisional Engineer/Divisional Engineer (ADEN/DEN).

Yes/No

Yes/No

Yes/No

Page 51: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

43

Physical Register

S. Item Check Reference

N.

1 Whether summary of inspections is Yes/No Annexure 4 / 5

mentioned in the register? of IRPWM

2 Whether inspection is being done Yes/No Para 420(2)

in each quarter? of IRPWM

3 Whether proper entry has Yes/No

been done in each column?

4 Whether compliance of each Yes/No

point is recorded?

1 Check Inspection Planning Report. Go to Report >

Inspection > 3. Inspection Planning. Choose PWI and

year, press GO. The asset number color indicates the

position of inspection.

Inspection planned Inspection planned

and done in in the month but

same month. inspection done in

later month.

Inspection planned Inspection planned

in the month and and not done so

month is not over. far

Note down the points and crossings to be

inspected during sample month.

TMS

Annexure 4 / 5

of IRPWM

Yes/No

Page 52: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

44

2 Check whether planned inspections done by the

official or not. Go to Report > Inspection > 4. Inspection

Register > select ‘feature type’, ‘from date’, ‘to date’

and click on ‘Click here to see Inspections of individual

assets’ from the list choose same P&C no. and check

details of inspection done during the month or not.

3 Whether compliance of inspection note against each

point is recorded?

3. Long Welded Rail (LWR) - Continuous Welded Rail (CWR)

RegisterThis register is maintained by SSE/SE (P.Way) of the section and it is

kept in his office. Details of inspections are recorded in the register.

It includes a detailed drawing of Switch Expansion Joint (SEJ) assembly,

Line diagram of LWR mentioning position of SEJs and other special

features viz. Level Crossings, Glued joints, Bridges, Curves, Gradients

etc. of each LWR/CWR

Physical Register

S. Item Check Reference

N.

1 Whether summary of inspections is Yes/No Para 8.2 and

mentioned in the register? Annexure-XI,

XII, XIII A,

and XIII B of

LWR manual

2 Whether inspections are up to Yes/No -

date?

3 Whether line diagram of LWR Yes/No -

is prepared?

Yes/No

Yes/No

Page 53: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

45

1 Check Inspection Planning Report. Go to Report >

Inspection > 3. Inspection Planning. Choose PWI and

year, press GO. The asset number color indicates the

position of inspection.

Inspection planned Inspection planned

and done in in the month but

same month. inspection done in

later month.

Inspection planned Inspection planned

in the month and and not done so

month is not over. far

Note down the points and crossings to be

inspected during sample month.

2 Check whether planned inspections done by the

official or not. Go to Report > Inspection > 4. Inspection

Register > select ‘feature type’, ‘from date’, ‘to date’

and click on ‘Click here to see Inspections of individual

assets’ from the list choose same LWR no. and check

details of inspection done during the month or not.

3 Whether compliance of inspection note against

each point is recorded?

TMS

4 Whether action taken / compliance Yes/No Annexure- XIII

is recorded with date? A and XIII B of

LWR manual

S. Item Check Reference

N.

Yes/No

Yes/No

Yes/No

Page 54: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

46

4. Level Crossing RegisterThis register is maintained by SSE/SE (P.Way) of the section and it is kept in

his office. It contains permanent features of a level crossing.

Physical Register

1 Check Inspection Planning Report. Go to Report >

Inspection > 3. Inspection Planning. Choose PWI and

year, press GO. The asset number color indicates the

position of inspection.

Inspection planned Inspection planned

and done in in the month but

same month. inspection done in

later month.

TMS

S. Item Check Reference

N.

1 Whether register is up dated? Yes/No Para 915 with

Ann 9/4 of

IRPWM

2 Whether length of check rail Yes/No Item 3 of Ann

is mentioned? 9/4 Para 904 of

IRPWM

3 Whether details of track Yes/No Item 16 of Ann

structure mentioned? 9/4 of IRPWM

4 Whether a detail of Train Vehicle Yes/No Para 919 &

Units (TVU) along with date is Item 15 of Ann

mentioned? 9/4 of IRPWM

Yes/No

Page 55: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

47

Inspection planned Inspection planned

in the month and and not done so

month is not over. far

Note down the points and crossings to be

inspected during sample month.

2 Check whether planned inspections done by the

official or not. Go to Report > Inspection > 4. Inspection

Register > select ‘feature type’, ‘from date’, ‘to date’

and click on ‘Click here to see Inspections of individual

assets’ from the list choose same LC no. and check

details of inspection done during the month or not.

3 Whether compliance of inspection note against

each point is recorded?

5. Track Recording Car RegisterThis register is maintained by SSE/SE (P.Way) of the section and it is kept in

his office. It contains results of Track Recording Car (TRC) / Track Recording

Cum Research Car (TRRC) running in the section. One page is given for

each kilometer of track.

Physical Register

S. Item Check Reference

N.

1 Whether register is up dated? Yes/No Para 122, 210 of

IRPWM

2 Whether one page is allotted Yes/No Para 122, 210 of

to each kilometer IRPWM

3 Whether register is checked Yes/No Para 122, 210 of

by Engineering Officers? IRPWM

Yes/No

Yes/No

Page 56: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

48

6. Section RegisterThis register is maintained by SSE/SE (P.Way) of the section and it is kept in

his office. It contains all important information including a brief history of

the section. A few pages for major unusual occurrences are also included.

Physical Register

S. Item Check Reference

N.

1 Whether register is up dated? Yes/No Para 210 of

IRPWM

2 Whether brief history of the Yes/No Para 210 of

section is mentioned? IRPWM

3 Whether all unusual Yes/No Para 210 of

occurrences are recorded IRPWM

with date?

4 Whether register is checked Yes/No Para 210 of

by Engineering Officers? IRPWM

1 Whether latest TRC report is uploaded on TMS. Go to Yes/No

‘Reports(M-Z)>TRC>TRC Report> select all Parameters

and check the date of latest run from drop down

menu

2 Check on locations needing attention based on TRC Yes/No

from ‘Reports (A-L)>Locations Needing Attention>

select indirect>TRC

TMS

Page 57: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

49

1 Check for latest entry by going to ‘Reports(M-Z)>Misc Yes/No

Registers

TMS

7. Encroachment RegisterThis register is maintained by SSE/SE (P.Way) of the section and it is kept in

his office. In the register, one page is allotted to each encroachment, so

that about 15 years record is available at a glance regarding efforts made

in the removal of the encroachments.

Physical Register

1 Check on entries on encroachment from ‘Reports Yes/No

(A-L) > Land Management

TMS

S. Item Check Reference

N.

1 Whether register is up dated? Yes/No

2 Whether a separate page is allotted Yes/No

for each encroachment?

3 Whether action taken / follow up Yes/No

action is recorded?

4 Whether any encroachment once Yes/No

mentioned is deleted?

Para 814(e)

Para 814 (e)

Ann 8/2 of

IRPWM

Page 58: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

50

8. Land Boundary Verification RegisterThis register is maintained by SSE/SE (P.Way) of the section and it is kept in

his office. One page is allotted to record availability and location of boundary

stones in each kilometer. About 10 years record is available at a glance

about attentiveness exercised in maintenance and fixation of the land

boundary stones.

Physical Register

S. Item Check Reference

N.

1 Whether register is up dated? Yes/No

2 Whether a separate page is allotted Yes/No ANNEXURE

for each encroachment? 8.1(a)

3 Whether land boundary diagram is Yes/No (Para 813

prepared? (d) of IRWM

4 Whether missing boundary stones Yes/No

recorded?

5 Whether missing stones are Yes/No

replaced?

1 Check on land offset file in excel and verify sample Yes/No

boundary pillars at site from ‘Reports(A-L)>Land

Management>Land Offset File (Excel file)

2 Whether land boundary diagram is prepared? Yes/No

3 Whether missing boundary stones recorded? Yes/No

4 Whether missing stones are replaced? Yes/No

TMS

Page 59: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

51

9. Creep RegisterThis register is maintained by SSE/SE (P.Way) of the section and it is kept in

his office. A separate page is allotted for each kilometer of track to record

creep in fish plated/SWR Track.

Physical Register

S. Item Check Reference

N.

1 Whether register is up dated? Yes/No

2 Whether a separate page is allotted Yes/No Ann 2/7

for each kilometer? Para 242

3 Whether proper entries are made Yes/Noof IRPWM

in each column?

4 Whether excessive creep is Yes/No

adjusted and recorded with date?

1 Check from ‘Inspection Register’> choose LWR Yes/No

on type of asset

2 Whether excessive creep is adjusted and Yes/No

recorded with date?

TMS

10. Gap Survey Register This register is maintained by SSE/SE (P.Way) of the section and it is kept in

his office. Record of Gap survey done in Short Welded Rail (SWR) track is

maintained in the register.

Page 60: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

52

11. Sand Hump RegisterMaintained by SSE/SE (P.Way) of the section and kept in his office, details

of various Parameters of sand humps are recorded in this register.

Physical Register

S. Item Check Reference

N.

1 Whether register is up dated? Yes/No Ann 5/2 Para

510 of IRPWM

2 Whether gap survey is done in the Yes/No Ann 5/2 Para

month of February regularly? 510 of IRPWM

3 Whether gaps requiring gap Yes/No Ann 5/2 Para

adjustments are adjusted? 510 of IRPWM

4 Whether gap survey is done in Yes/No Ann 5/2 Para

rising trend of temperature? 510 of IRPWM

1 Check from ‘Reports(M-Z)> Misc Register> Gap Survey Yes/No

2 Whether gap survey is done in the month of February Yes/No

regularly?

3 Whether gaps requiring gap adjustments are Yes/No

adjusted?

4 Whether gap survey is done in rising trend of Yes/No

temperature?

TMS

Page 61: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

53

Physical Register

S. Item Check Reference

N.

1 Whether register is up dated? Yes/No -

2 Whether adequate loose sand is Yes/No -

available in sand hump?

3 Whether depth of sand above Yes/No -

rail level is mentioned?

4 Whether any deficiency noted Yes/No -

is complied?

1 Check from ‘Inspection Register’> Select Yes/No

feature type – Sand Hump

2 Whether adequate loose sand is available Yes/No

in sand hump?

3 Whether depth of sand above rail Yes/No

level is mentioned?

4 Whether any deficiency noted is complied? Yes/No

TMS

12. Casual Renewal RegisterThis register is maintained by SSE/SE (P.Way) of the section and it is kept in

his office. Record of piece-meal renewals is maintained allotting a separate

page for each kilometer of track.

Page 62: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

54

TMS

13. Corroded Rail Register: This register is maintained by SSE/SE(P.Way) of the section and it is kept in his office. One page is allottedfor each kilometer of track or each running line in yard to check extentof corrosion in rail flange and web.

Physical Register

S. Item Check Reference

N.

1 Whether register is up dated? Yes/No

2 Whether a separate page is Yes/No

allotted for each kilometer?

3 Whether corroded rails are being Yes/No

replaced regularly?

4 Whether action taken is recorded Yes/No

and checked by officers?

S. Item Check Reference

N.

1 Whether register is up dated? Yes/No

2 Whether reason for replacement Yes/No

is mentioned?

3 Whether complete detail of Yes/No

whole section is recorded?

1 Check from ‘Report(A-L)’>Asset Register Yes/No

2 Check from wire book whether all blocks taken

for rail renewal has been entered in TMS?

Physical Register

Para 205, 209,

210(xi) of

IRPWM

Yes/No

Ann 2/20,

Para 250(2)

of IRPWM

Page 63: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

55

TMS --- This register is not available in TMS

14. Permanent Way DiagramRecord is kept in the office of SSE/SE (P.Way). A bar chart containing

complete details of the section of SSE In-charge is prepared by the

division/Sub division and a copy of the same is made available to each

SSE/P.Way, who keeps it duly updated.

Physical Register

S. Item Check Reference

N.

1 Whether Permanent Way Yes/No Ann 2/4, Para

diagram is up dated? 211 of IRPWM

1 Check from ‘Report(M-Z) Track Diagram Yes/No

TMS

S. Item Check Reference

N.

1 Whether register is up dated? Yes/No

2 Whether proper entries have Yes/No

been done in each column?

3 Whether register is scrutinized Yes/No

by ADEN regularly?

15. Welding RegisterThis register is maintained by SSE/SE (P.Way) of the section and it is

kept in his office. All Alumino Thermit Welding (ATW) done in the section

is recorded in this register.

Physical Register

Ann 5 of

AT welding

manual

Page 64: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

56

1 Check from ‘Report(A-L)’>Asset Register>AT Weld Yes/No

TMS

S. Item Check Reference

N.

1 Whether register is up dated? Yes/No Para 5.1.3 and

Ann V,VI,VII &

VIII of USFD

Manual

2 Whether USFD testing in the Yes/No Para 6.6.1.1

section is being done regularly of USFD Manual

as per frequency ?

3 Whether this register is Yes/No -

scrutinized by higher officers?

4 Whether action taken is Yes/No -

recorded with date?

16. Ultrasonic Flaw Detection (USFD) Testing Register:This register is maintained by SSE/SE (P.Way) of the section and it is

kept in his office. Results of USFD testing and action taken there upon

is recorded in this register.

Physical Register

1 Check from ‘Report(M-Z)>USFD>USFD due/Overdue Yes/No

2 Check monthly progress Yes/No

3 Check defect list Yes/No

TMS

Page 65: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

57

S. Item Check Reference

N.

1 Whether register is up dated? Yes/No Ann V,VI & VII of

USFD manual

2 Whether date of last USFD Yes/No and Para

testing against each case is 210(X) of

recorded? IRPWM

3 Whether month-wise statement Yes/No

showing detail of rail/weld

fractures is recorded?

4 Whether USFD classification Yes/No

is recorded?

17. Rail / Weld Fracture Register:This register is maintained by SSE/SE (P.Way) of the section and it is

kept in his office. It contains records of Rail/Weld Fractures in his

section. A statement showing details of Rail/Weld fracture occurred

during the current and preceding years are also attached to have a

clear assessment of fracture prone areas and to have special watch

over those kilometers

Physical Register

1 Check from ‘Report(A-L)>Fracture>Fracture Yes/No

Analysis

2 Check whether all fracture reports have remarks Yes/No

of USFD PWI

3 Check whether all reports have photos Yes/No

TMS

Page 66: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

58

S. Item Check Reference

N.

1 Whether register is up dated? Yes/No -

2 Whether a separate page is Yes/No -

allotted for each glued joint?

3 Whether annual record of Yes/No -

performance is mentioned?

4 Whether track structure Yes/No -

mentioned along with ballast

cushion?

18. Glued Joints RegisterRegister is maintained by the sectional JE/P. Way and it is kept in the

office of SSE/SE (P.Way), in which details of glued insulated joints and

annual record of its maintenance and performance is kept. A separate

page is used for each Glued Joint.

Physical Register

1 Check from ‘Report(A-L)’>Asset Register> select Yes/No

feature type – Glued Joint

TMS

19. Tie Tamping Machine (TTM) Register:

This register is maintained by SSE/SE (P.Way) of the section and it

is kept in his office. Tamping record along with record of track

Parameters i.e. cross level and alignment before and after tamping is

maintained in the register.

Page 67: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

59

20. PCDO Register: PCDO register is maintained as per the latest

instructions of division/Hd.Qr. from time to time.

Physical Register

TMS - This register is available from Sr.DEN (Cordination)

and above logins.

S. Item Check Reference

N.

1 Whether register is up dated? Yes/No -

2 Whether assistance required is Yes/No -

highlighted?

3 Whether vacancy position is Yes/No -

highlighted?

S. Item Check Reference

N.

1 Whether register is up dated? Yes/No -

2 Whether track Parameters are Yes/No Para 3.1.2 (i)

recorded before tamping of IRTMM

3 Whether track Parameters are Yes/No Para 3.1.4 (iv)

recorded after tamping? of IRTMM

4 Whether quality of work is Yes/No -

assessed and mentioned?

TMS

Physical Register

1 Check from ‘Report(M-Z)>Track Machine Yes/No

Page 68: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

60

S. Item Check Reference

N.

1 Whether register is up dated? Yes/No -

2 Whether action taken is Yes/No -

recorded against each item?

3 Whether timely action is taken? Yes/No -

4 Whether items pertaining to Yes/No -

higher officials brought to their

notice?

21. Inspection Notes of Higher Officials :

This register is maintained by SSE/SE (P.Way) of the section and it

is kept in his office. Inspection notes of higher officials and their

compliance is recorded in this register.

Physical Register

1 Check from ‘Miscellaneous’>Inspection Notes Yes/No

2 Whether action taken is recorded against each

item? Yes/No

3 Whether timely action is taken? Yes/No

4 Whether items pertaining to higher officials Yes/No

brought to their notice?

TMS

22. Rainfall Register:

Maintained by SSE/SE (P.Way) of the section, kept in his office,

extent of rainfall is recorded in this register.

Page 69: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

61

S. Item Check Reference

N.

1 Whether register is up dated? Yes/No Para 210(c-i)

of IRPWM

2 Whether time and date of rain Yes/No -

fall is properly mentioned?

1 Check from ‘Report (M-Z)>Miscellaneous Yes/No

Register>5. Rainfall Register

2 Whether date wise rainfall for all measuring Yes/No

stations is entered for previous month?

TMS

S. Item Check Reference

N.1 Whether summary of inspection Yes/No -

is recorded in register?

2 Whether compliance of each Yes/No -

shortcoming noticed is recorded?

3 Whether inspection is being Yes/No -

done in each quarter?

4 Whether proper entry has been Yes/No -

done in each column?

23. Points & Crossing Joint Inspection Register of SSE/P.Way and SSE/

Signal and Telecommunication (S&T):

This register is maintained jointly by SSE/SE (P.Way) and SSE/SE(S&T) of

the section and it is kept in SS office/Power Cabin. A proper record of joint

inspections carried out along with compliances is maintained in this register.

Physical Register

Physical Register

Page 70: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

62

1 Check from Report (A-L) > Inspection > 4.

Inspection Register > Choose Point & Crossing

(Joint) in drop down menu for type of register. Fill

all the relevant information.

TMS

2 Whether inspection is being done in each

quarter?

3 Whether proper entry has been done in each

column?

4 Whether compliance of each shortcoming

noticed is recorded?

Yes/No

Yes/No

Yes/No

Yes/No

24. Material Under Trial Register:

This register is maintained by SSE/SE (P.Way) of the section and it

is kept in his office. Complete and proper record of material which is

under trial (if any) in the section is maintained in this register.

Physical Register

S. Item Check Reference

N.

1 Whether any material is under Yes/No Para 212(iii)

trial in the section? of IRPWM

2 Whether proper entries are Yes/No

made in corresponding columns?

3 Whether register is brought Yes/No

up-to-date?

Page 71: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

63

1 Check from ‘Register (M-Z)>Material Under Trial Yes/No

2 Whether any material is under trial in the Yes/No

section?

3 Whether proper entries are made in Yes/No

corresponding columns?

4 Whether register is brought up-to-date? Yes/No

TMS

1 Check from ‘Register (M-Z)>Miscellaneous Yes/No

Register> 7. Temperature Register

2 Whether register is up dated? Yes/No

3 Whether proper entries are made in Yes/No

corresponding columns?

TMS

S. Item Check Reference

N.

1 Whether register is up dated? Yes/No Para 505 (iii)

of IRPWM

2 Whether proper entries are Yes/No

made in corresponding columns?

25. Annual Temperature Record Register:

This register is maintained by SSE/SE (P. Way) of the section and it

is kept in his office.

Physical Register

Page 72: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

64

S. Item Check Reference

N.

1 Whether assurance of having Yes/No Para 826 of

read all rules & guidelines has IRPWM

been recorded?

26. Assurance Register

Physical Register

1 Check from ‘Register (M-Z)>Miscellaneous Yes/No

Register> 10. Circular Viewed

TMS

� � �

Page 73: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

65

CHAPTER - 4

CIVIL ENGINEERING INSPECTIONS

A PERMANENT WAY (TRACK)

1. Inspection of Track

S. Item to be inspected Remarks Reference

N.

1. Whether condition of Rail is good?

a) Vertical wear of rail is within

13/8 mm (60/52 kg)

b) Lateral wear of rail is within

i) 6/8 mm (A&B / C,D,E routes on Yes/No

straight track)

ii) 8/10 mm (A&B / C,D,E routes

on curved track)

2. Whether condition of Sleepers Yes/No

specially under rail seat is good

and their spacing is correct? (60/65

cm c/c for 1660/1540 sleeper

density)

3. Whether all track fittings are Yes/No

complete and tightened?

4. Whether ballast available is Yes/No IRLWRM

sufficient and properly boxed? para 4.2

IRPWM

Para 302

(iii) & (iv)

Page 74: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

66

S. Item to be inspected Remarks Reference

N.

5. Whether oiling and greasing of Yes/No IRPWM

fishplate joints is being done as per Para 241(3)

annual schedule? (once in 12 month)

6. Whether there is any blowing/ Yes/No

pumping joint?

7. Whether knowledge of staff regarding Yes/No

safety of track is up to the mark?

8. Whether proper protection is resorted Yes/No IRPWM Para

to at track work site as per prescribed 806,807,808

norms?

9. Whether P.Way material is properly Yes/No

stacked and is away from running

track and marked wherever required?

10. Is the Machine tamping overdue Yes/No

(in Mechanised maintained track)?

11. Whether “Location needing Yes/No

Inspection” are being regulated by

field official?

12. Whether all field officials are entering Yes/No

their irregularities in Track

Management System (TMS)?

13. Whether resources/work planning Yes/No

has been done with respect to

“Location needing attention” as per

TMS?

Page 75: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

67

2. Gang Inspection

1. Whether gang is working under proper Yes/No IRPWM Para

track protection? 806, 807,

808

2. Whether all the Trackmen are in Yes/No

uniform?

3. Whether Gang charts, Mates diary, Yes/No IRPWM Para

attendance sheet are available with 232(1)

gang?

4. Whether all equipments i.e. Gang

tools, first aid box, Safety equipments

are available and in working

condition? (In good condition /Not in

good condition)

4.1 Powrah (Spade) Yes/No

4.2 Crowbar Yes/No

4.3 Pan mortar Yes/No

4.4 Pick Beater Yes/No

4.5 Pick Axe Yes/No

4.6 Shovel Yes/No

4.7 Ballast Rake Yes/No

S. Item to be inspected Remarks Reference

N.

IRPWM

Para

232(2)(c)

Page 76: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

68

S. Item to be inspected Remarks Reference

N.

4.8 Bar Straightening Yes/No

4.9 Bar Claw Yes/No

4.10 Tommy Bar Yes/No

4.11 Wire Claw Yes/No

4.12 Punches Yes/No

4.13 Wire Basket Yes/No

4.14 Spanners Yes/No

4.15 Hammer Yes/No

4.16 Rail drilling Ratchet Yes/No

4.17 Track Bond Drill/ Drill Twist Yes/No

4.18 Chisel Yes/No

4.19 Rail hole chamfering kit Yes/No

4.20 Tools for Lubrication of ERCs Yes/No

4.21 ERC Extractor / Applicator Yes/No

4.22 Rail Tongues Yes/No

4.23 Rail Shunt-Cable (Jumper) Yes/No

4.24 Cutting Blowpipe Yes/No

4.25 De-stressing Roller Yes/No

4.26 Rail Roller Yes/No

IRPWM

Para

232(2)(c)

Page 77: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

69

S. Item to be inspected Remarks Reference

N.

4.27 Rammer Yes/No

4.28 Ballast Profile Template Yes/No

4.29 Hump Cord Yes/No

4.30 Wooden Mallet Yes/No

4.31 Hand Signal Flag Yes/No

4.32 Staff suitable for exhibition of red

lamp or red flag Yes/No

4.33 Detonators Yes/No

4.34 Whistle thunderer Yes/No

4.35 Battery operated LED based Torch

Light-cum Hand-Signal Lamp Yes/No

4.36 Safety Helmet Yes/No

4.37 Safety Jacket Yes/No

4.38 Safety Gloves Yes/No

4.39 Shoes Yes/No

4.40 First aid box Yes/No

4.41 Safety goggle Yes/No

5. Whether previous day work is as Yes/No IRPWM

per data entered in Gang chart/ Para 232(1)

diary? Is it as per expected quality?

IRPWM

Para

232(2)(c)

Page 78: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

70

S. Item to be inspected Remarks Reference

N.

6. Knowledge of Mate and Gang Yes/No IRPWM

regarding safety and quantity of Para 232 (3)

work is adequate?

7. Whether PME of Mate, Keyman and Yes/No IRMM Vol I

Trackman is being done regularly as Para 514(B)

per norms? (On attaining the age

of 45 years and thereafter at the

termination of every period of

five years)

8. Whether compliance of various Yes/No

points noted during last inspection

have been made?

9. Whether Gang Progress/work is Yes/No

being entered in TMS?

3. Checklists for Curve

1. Whether curve board is properly

provided at both ends of curve with

adequate details of Degree, Radius,

Super Elevation (SE) etc.?

2. Whether marking of cant & stations

no. and versines is indicated on rail

and is legible? (10 m apart on inside

of web of inner/outer rail)

S. Item to be inspected Remarks Reference

N.

Yes/No

Yes/NoYes/No

IRPWM

Para 409(1)

IRPWM

Para

409(3)

Page 79: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

71

3. Shoulder width on outer rail on LWR

track.

(350/500 mm shoulder ballast on

straight and inside of curve/ outside

of curve)

4. Whether rail posts are available at

Transition Tangent Point (TTP) and

Common Tangent Point (CTP)?

5. Whether extra clearance for curves

have been provided?

1.On platforms -

Inner side of curve – 27330/R + 5L/4 –

51 mm

Outside of curve – 29600/R – 25 mm

2. Adjacent Track–27330/R+29600

R+2L/4 mm Where R is radius of curve

in meter and L is Lean

6. Whether compliance of various

points noted during last inspection

have been made?

7. Whether the inspection of curve has

been done as per schedule by ADEN

SSE(P.Way)/JE(P.Way)?

(one curve every quarter in each SSE/

JE (P.Way)

jurisdiction for ADEN/ once in 6

months by rotation for SSE/JE(P.Way) )

S. Item to be inspected Remarks Reference

N.

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

LWR Manual

Para 4.2

IRPWM Para

409(2)

IRPWM

Para 417 &

Appendix of

SOD

Yes/No

IRPWM

Para 122(l)

IRPWM

Para 107(4),

124 (4)

Page 80: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

72

S. Item to be inspected Remarks Reference

N.

8. Whether Curve Inspections are

being entered by SSE/P.Way in TMS

9. Does the curve require local

complete realignment? (20% or

more stations are having versines

variations beyond limits as per

speed band)

<140 - ≥110 kmph :- 10 mm (15mm

for 110kmph) or 20% of average

versines whichever is more ;

<110 - ≥50 kmph :- 20 mm or 20% of

avg. versines whichever is more ;

< 50 kmph :- 40 mm or 20% of avg.

versines whichever is more;

10. Permissible Gauge on curve -

radius ≥ 440 m :- -6 to +15 mm

radius < 440 m :- upto +20 mm

Yes/No

Yes/No

Yes/No

IRPWM

Para 421(2)

IRPWM

Para

224(2)(e)(v)

4. Points & Crossings

1. Whether entries are recorded in

Points & Crossing's register by SSE/JE

as per their inspection schedule?

(once in 3 months on running lines

and once in 6 months on non-running

lines by rotation)

S. Item to be inspected Remarks Reference

N.

Yes/No

IRPWM Para

124(3)

Page 81: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

73

2. Whether condition of stock rail and

tongue rail of switch is damaged or

worn out?

a. Tongue rail is chipped/crack within

200 mm length in 1000 mm from ATS

b. Vertical wear of Tongue rail is

within 8/5 mm at 13 mm head width

and level point (60/52 kg)

c. Lateral wear of tongue rail at Q

point and Level point is within 8/6

mm(60/52 kg)

d. Vertical wear of Stock rail is within

13/8 mm (60/52 kg)

e. Lateral wear of Stock rail is within

i. 6/8 mm (A&B / C,D,E routes on

straight track)

ii. 8/10 mm (A&B / C,D,E routes on

curved track)

3. Whether tongue rails are out of

square?

4. Whether tongue rail houses properly

against stock rail?

5. Whether throw of switch is within

tolerance limit? (Straight switch-

95mm, Curved switch-115mm, Thick

web switch-160mm)

Yes/No

IRPWM

Para 237(2)

& 302

S. Item to be inspected Remarks Reference

N.

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No SOD Ch.2

Item 16

Page 82: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

74

Yes/No IRPWM Para

237(1)(g)

S. Item to be inspected Remarks Reference

N.

6. Whether correct gauge and cross

level is maintained at toe of switch

in both the settings i.e., Normal and

Reverse? (nominal gauge + 6 mm for

T/out having SEA> 0020’00” & nominal

gauge for T/out having SEA ≤0020’00”)

7. Whether all tongue rail fittings are

intact and effective?

8. Whether correct gauge and cross

level is maintained in lead portion?

9. Wear at Actual Nose of Crossing

(ANC) is within the Permissible

limits? (Rajdhani/Shatabdi route-

Built Up Xing: 6mm, CMS Xing:8mm;

Other routes all xings:- 10mm).

10. Whether proper clearance between

vee and wing rail at nose of crossing

is maintained properly? (44-48 mm

in B/Up xings)

11. Whether correct clearance of check

rail opposite the crossing is

maintained? ( 41-45 mm for Fan

shaped T/out; 44-48 mm for other T/

outs)

12. Whether correct gauge and crosslevel is maintained at nose ofcrossing?

Yes/No

Yes/No IRPWM Para

237(8)

Yes/No IRPWM Para

237(3)

Yes/No SOD Ch.2

Item 14 &

15

Yes/No SOD Ch.2

Item 12 &

13

Yes/No IRPWM Para

237(8)

Page 83: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

75

S. Item to be inspected Remarks Reference

N.

13. Whether proper packing is given in

switch and crossing portion?

14. Whether length of turnout is standard

or not? (28613 mm for 1 in 8.5 &

39975 mm for 1 in 12 Fan shaped T/

out)

15. Whether compliance of various

points noted during last inspection

have been made?

16. Is Machine tamping overdue?

17. Whether inspections are entered

regularly in TMS as per laid down

schedule?

Yes/No IRPWM Para

237(1)

Yes/No RDSO Drg.

No.-4865,

4218&

4732

Yes/No

Yes/No

Yes/No

5. Insulated Joints (Conventional), Glued Joints and Rail Joints

1. Whether condition of rails, sleepers

and packing of Insulated Joints/Glued

Joints is satisfactory?

2. Whether there is metal flow on the

Insulated/Glued Joint rail ends?

3. Whether rails at joint are battered/

hogged?

S. Item to be inspected Remarks Reference

N.

Yes/No IRPWM Para

280 & 281

Yes/No

Yes/No

Page 84: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

76

4. Whether drainage is good on the

Insulated/Glued Joints?

5. Whether inspections are entered

regularly in TMS?

S. Item to be inspected Remarks Reference

N.

Yes/No

Yes/No

1. Whether work is being done under

competent supervisor? (JE/P.Way or PWS

now a days, redesignated subject to

competency certificate issued by CTE)

2. Whether stipulated speed

restrictions are imposed at work site?

3. Whether level pegs are provided for

initial/final rail level restoration? (At

every 30 M)

4. Whether screened muck is thrown

away from running track?

5. Whether proper wooden blocks and

other packing are used for passing the

trains?

6. Whether cess is cross-sloped and

repaired?

7. Whether Deep screening is being

entered in TMS?

6. Deep Screening

S. Item to be inspected Remarks Reference

N.

Yes/No C.S. 128 of

IRPWM

Yes/No IRPWM Para

238(2)(f)

Yes/No IRPWM Para

238(2)

Yes/No IRPWM Para

238(2)(e)

Yes/No IRPWM Para

238(2)(e)

Yes/No IRPWM Para

238(2)(e)

Yes/No

Page 85: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

77

1. Whether all drains were cleaned

before monsoon and its silt was

taken away from track?

8. Drainage in Station Yards/Block Sections

S. Item to be inspected Remarks Reference

N.

Yes/No IRPWM

Para 239 &

240

1. Whether SE/P.Way is present at the

site of lifting of track?

2. Whether proper speed restrictions

are imposed at site?

3. Whether track protection is done at

site?

4. Whether level pegs are provided for

finalising the required level? (At every

30M)

5. Whether lifting is being done from

down-hill end?

6. Lifting of track should not more than

75mm at a time. Whether these

instruction followed?

7. Whether work done is being entered

in TMS?

7. Lifting of Track.

S. Item to be inspected Remarks Reference

N.

Yes/No C.S. 128 of

IRPWM

Yes/No IRPWM Para

233(3)

Yes/No IRPWM Para

806,807,808

Yes/No IRPWM Para

233 & 234

Yes/No IRPWM Para

233(4)

Yes/No IRPWM Para

233(3)

Page 86: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

78

1. Whether adequate leveled spacious

ground is available at specific ballast

depot?

2. Whether all testing equipments are

available and in working order at

depot laboratory?

3. Whether all records including

registers, challans are updated and

intact?

4. Whether all qualitative and

quantitative measures are being

followed?

5. Whether adequate space is available

between the stacks?

9. Ballast Depot

S. Item to be inspected Remarks Reference

N.

Yes/No IRPWM Para

266(2)

Yes/No

Yes/No IRS-GE-1

2004

Yes/No

Yes/No

S. Item to be inspected Remarks Reference

N.

Yes/No

Yes/No

IRPWM Para

239 & 240

2. Whether cleaning of shoulder ballast,

and removal of vegetation/weeds has

been ensured before monsoon?

3. Whether all side drains, catch water

drains are intact and desilted before

monsoon?

4. Whether work done has been

entered in TMS?

IRPWM Para

239 & 240

Yes/No

Page 87: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

79

1. Whether all inspections are done by

SSE/JE as per laid down stipulations

and properly recorded in LWR

register? (Fortnightly in 2 hottest & 2

coldest months individually by SSE/JE ;

once in 2 months by rotation by SSE/JE

in other months)

2. Whether gaps of SEJ are within

permissible limits? (should be within

10 mm from specified value as per

Annexure V of LWR Manual)

3. Whether conditions of SEJ i.e. tongue

rail, stock rail, sleepers & fittings are

good?

4. Whether speed restriction imposed

as per condition of track?

5. Whether destressing is done at

stipulated periods, date and

temperature are recorded on LWR

board?

10. Long Welded Rails (LWR)

S. Item to be inspected Remarks Reference

N.

Yes/No

Para 5.6

LWR Manual

Yes/No

Yes/No

C.S. 15, LWR

Manual

Yes/No Annexure III

LWR Manual

Yes/No LWR Manual

Para 8.2.2

S. Item to be inspected Remarks Reference

N.

Yes/No6. Whether unloading facilities are

adequate?

Page 88: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

80

6. Whether staff is aware about rules?

7. Whether Hot/Cold Weather Patrolling

is being practiced at prescribed

temperatures?

td + 25 for HWP on LWR with PSC

sleeper & density 1540 or more

td + 20 for LWR in other cases for HWP

td - 30 for Cold weather patrolling

8. Whether Hot Weather Patrolmen is

equipped with all stipulated tools

mentioned in LWR Manual?

9. Whether the condition of sleepers is O.K?

10. Whether all fittings are available and

tight?

11. Whether reference posts are

available?

12. Whether temperature record is being

maintained on daily basis in SSE/

P.Way office?

13. Whether LWR needs destressing?

14. Whether all inspections, work done

and changes are being entered in TMS?

15. Whether cold/Hot weather patrolling

introduced?

S. Item to be inspected Remarks Reference

N.

Yes/No LWR Manual

Para 8.1.3,

Yes/No Annexure

X-A, LWR

Manual

Yes/No Annexure X-

A & X-B of

LWR Manual

Yes/No

Yes/No

Yes/No Para 5.2,

LWR

Manual

Yes/No Para 6.4.1,

LWR Manual

Yes/No Para 1.17

LWR Manual

Yes/No

Para 5.9 of

LWR Manual

Yes/No

Page 89: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

81

1. Whether work is being done as per

approved plan, estimate, tender

conditions, and location section?

2. Whether Railway Supervisor is

available at site of work?

3. Whether SR is imposed at the

worksite?

4. Whether track is adequately

protected?

5. Whether all material is kept ready

before commencement of traffic block?

6. Whether inventory of released

material is being ensured?

7. Whether all track-parameters within

permissible limits work at the end of

the day?

8. Whether there is any infringement of

new/released material with running

track?

9. Whether quality of laying is as per

stipulated rules?

10. Whether a thermit welding done in

situ is joggle fish platted with two

clamps till tested as good by USFD?

11. Complete Track Renewal (CTR) Work

S. Item to be inspected Remarks Reference

N.

Yes/No

IRPWM Para

826

Yes/No

Yes/No

IRPWM Para

309 A

Yes/No

IRPWM Para

308

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No Para 8.10 of

USFD

Manual

IRPWM Para

806,807,808

IRPWM Para

316(2)

Yes/No

Page 90: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

82

11. Whether all work is being entered in

TMS?

S. Item to be inspected Remarks Reference

N.

Yes/No

1. Whether all entries made in TMS?

2. Whether all codes, manuals,

circulars, inspections notes are

available?

3. Whether Store and Office is neatly

maintained?

4. Whether all Consumable and

Perishable (C&P), Tools and Plants

(T&P) are recorded in ledgers?

5. Whether disposal of scrap, including

proper weighment is being ensured?

6. Whether submission of Material At

Site (MAS), revenue returns, test

check of stores being complied by

SSE?

7. Whether Periodical Medical

Examination (PME) of all Safety

category staff/Supervisors are

ensured by SSE?

B. SSE (P.Way) Office/Store

S. Item to be inspected Remarks Reference

N.

Yes/No

Yes/No

Yes/No IRPWM Para

119

Yes/No

Yes/No

Yes/No

Yes/No IRPWM Para

133(1)

Page 91: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

83

8. Whether all service records, leave

staff are neatly maintained?

9. Whether all C&P and T&P available

as per scale?

10. Whether proper water supply,

electric supply and toilet facilities

are available?

S. Item to be inspected Remarks Reference

N.

Yes/No

Yes/No

Yes/No

C. Check list for USFD testing

(Issued by RDSO. Vide Letter no. CT/Welding/Policy dt.28.10.14)Date of Inspection: …………..

S E C T I O N . . . . . . . . . . . . . . . . . . . . . . . . D I V I S I O N . . . . . . . . . . . . . . . . . . . . . . . . K M /

TP........................LINE.......................

Machine used for testing: Single Rail Tester / Double Rail Tester

Machine make and number:

Track Structure on test location:

Whether Stretch is having D-Marked Rails: Yes / No

S. Item of Works Observation/

N. Values Recorded

A. USFD Team

1. Operator (s)

(a) Name

(b) Competency Certificate Details

(c) Competency Certificate valid Yes / No

Page 92: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

84

2. Adequate staff for handling /

lifting of machines Yes / No

B. USFD Machines & Condition

1. Machine used is RDSO approved Yes / No

2. Availability of requisite tools & plants

i Sensitivity block Yes / No

i i IIW block for calibration Yes / No

iii Standard Rail test piece Yes / No

3. Visual Condition of electronic unit Proper / Not proper

4. Visual condition of Trolley Proper / Not proper

5. Condition of Probes & shoes

a Right Hand Side

i 0 degree Proper / Not proper

i i 70 degree (F) Proper / Not proper

iii 70 degree (B) Proper / Not proper

b Left Hand Side

i 0 degree Proper / Not proper

i i 70 degree (F) Proper / Not proper

iii 70 degree (B) Proper / Not proper

S. Item of Works Observation/

N. Values Recorded

Page 93: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

85

S. Item of Works Observation/

N. Values Recorded

c For Flange testing

i 70 degree 2 MHz Proper / Not proper

i i 70 degree 2 MHz (Side looking probe) Proper / Not proper

iii 45 degree 2 MHz Proper / Not proper

d Alignment probes & Lifting System

with respect to centre line Central / eccentric

6. Check on Characteristics of Machine

a Date of Check

b Whether due or not (Monthly check) Due / Not Due

7. Condition of Battery Charged/Not Charged

8. Condition of Audio Alarm Sounding /

Not Sounding

9. All Controls of electronic unit i.e.

depth range, gain, reject etc.

properly functioning Yes / No

10. Whether watering arrangement for

Probes is functional Yes / No

11. Availability of spares

i 00, 4 MHz Double crystal Probes : 8No. Yes / No

i i 00, 2 MHz Double crystal Probes : 8 No. Yes / No

Iii 700 (F&B) probes, 2 MHz Single

crystal : 8 No. Yes / No

Page 94: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

86

iv 450, 2 MHz Single crystal Probes : 2 No. Yes / No

v 700, 2 MHz Single crystal Probes : Yes / No

4 No.

vi 700, 2 MHz Single Crystal Probes Yes / No

(SLP) : 2 No

vii 00, 2/2.5 MHz Single crystal Yes / No

Probes : 2 No.

viii Connecting Cable (Flaw detector Yes / No

with junction box.) : 6 No

ix BNC Connector : 6 No. Yes / No

x IIW Block (as per IS : 1408) :2 Yes / No

xi 60x50x50 mm steel block (as per steel Yes / No

grade 45 C8 to IS : 1875-1992) : 1 No.

xii Battery Charger : 1 No. Yes / No

xiii Fuse : 12 No. Yes / No

xiv Step gauge : 1 No. Yes / No

C Check on sensitivity settings and calibration

1. Calibration Check

a Calibration for 300/200 mm longitudinal Proper /

wave using 00, Double crystal Probe Not Proper

b 165 mm Direct shear wave Proper /

calibration for 700, 2 MHz Single Not Proper

crystal Probe

S. Item of Works Observation/

N. Values Recorded

Page 95: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

87

S. Item of Works Observation/

N. Values Recorded

2. Sensitivity setting of equipment

and probes with help of standard Proper / Not Proper

rail piece

a Whether gain is locked after setting Yes / No

3. Check on function & sensitivity

of probes

a Normal Probe

(Back wall echo adjusted to full Proper / Not Proper

screen height)

b Angle probe 700 (Centre forward &

backward) (Amplitude of 12 mm dia. Proper / Not Proper

hole to be set to 3 div. i.e. 60% of

full screen height)

c Gauge face & Non gauge face

corner probe 700 (Forward &

Backward) Proper / Not Proper

(Signal amplitude from 5 mm FBH

to be set 60% of full height)

d 450 probe Proper / Not Proper

4. Whether adjustment in sensitivity

setting was done for variation in Proper / Not Proper

rail temperature

5. Whether gain has been increased Yes / No

by 10 db. for D Marked rails

Page 96: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

88

S. Item of Works Observation/

N. Values Recorded

6. Check on equipment characteristic

a Linearity of time base of flaw Proper / Not Proper

detector

b Linearity of Amplification of flaw

detector Proper / Not Proper

c Penetrative Power Proper / Not Proper

d Resolving Power Proper / Not Proper

e Probe index Proper / Not Proper

f Burn angle Proper / Not Proper

7. Whether scheduled maintenance Yes / No

of USFD machine was done

D. Check on Work

1. Whether equipment is in proper Yes / No

working order duly calibrated

a Battery is fully charged Yes / No

b All controls of electronic unit Yes / No

properly functioning

c Calibration & sensitivity setting Yes / No

done

d Whether the gap between probing

face and probe shoe is proper Yes / No

(0.2 mm)

Page 97: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

89

S. Item of Works Observation/

N. Values Recorded

e Whether alignment of probes is Yes / No

proper

f Adequate supply of water for

coupling for all the probes is Yes / No

ensured

2. Check on previous day’s work

(i) Date of testing

(ii) Location of testing (From Km to Km)

(iii) Rail testing

a Whether all IMR defects confirmed Yes / No

b If No, number of additional defects

1. Over Reported

2. Under Reported

(c) Whether preventive action taken Yes / No

on all defects

(d) Whether all OBS defects confirmed Yes / No

(e) If No, number of additional defects

1. Over Reported

2. Under Reported

(f) Whether preventive action taken Yes / No

on all defects

Page 98: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

90

S. Item of Works Observation/

N. Values Recorded

(iv) Weld testing

(a) Type of Welds

(b) Whether all defects confirmed

(c) If No, number of additional defects

1. Over Reported

2. Under Reported

(d) Whether preventive action taken Yes / No

on all defects

(v) Whether the A-scans of all defects Yes / No

preserved in machine

3. Check on day's work

(a) Type of Testing Rail / weld

(b) The A-Scans of all defects being

preserved Yes / No

(c) The defects details are properly Yes / No

logged in machine

(d) Defects are properly entered in Yes / No

Register

E. Schedule of USFD testing and adherence

1. Date of last USFD Testing of

Inspected Stretch

(a) Rail testing

Page 99: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

91

(b) Weld testing

2. Stipulated frequency of section

(a) Rail testing

(b) Weld testing

3. Whether testing is done as per Yes / No

Schedule

4. Proper up keep of defects register Yes / No

has been done

S. Item of Works Observation/

N. Values Recorded

D. Check list for Inspection of AT Welding

(Issued by RDSO. Vide Letter No. CT/Welding/Policy dt.28.10.14)Date of Inspection:

S E C T I O N . . . . . . . . . . . . . . . . . . . . . . . . D I V I S I O N . . . . . . . . . . . . . . . . . . . . . . . . K M /

TP........................LINE.......................

Brief of Welding Technique

(Rail Section/UTS/Heating Technique/Mould/Tapping)

S. Item of Works Observation/

N. Values Recorded

A. Storage of Welding Material at Store

1. AT Welding Portion

(a) Secured Building Yes / No

(b) Ventilation Good / Poor

(c) Dampness Yes / No

Page 100: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

92

S. Item of Works Observation/

N. Values Recorded

(d) Properly Packed Yes / No

2. Igniters

(a) Storage different from portion Yes / No

(b) Stored in locked steel cupboard Yes / No

3. Prefabricated Moulds

(a) Dampness Yes / No

(b) Properly Packed / Neatly stacked Yes / No

B. Preparatory Arrangements at Site

1. Availability of complete T & P and

consumables at site

(A) Preheating Equipment

A-1 Air-Petrol Heating

1. Pressure Tank with Pressure Yes / No

gauges : 1 No.

2. Vaporizers ( Burner ) complete : 1 No. Yes / No

3. Nozzle Pricker : 2 Nos. Yes / No

4. Nozzle Keys : 1 No. Yes / No

5. Vaporizer stand : 1 No. Yes / No

6. Goose neck attachment to Yes / No

vaporizers : 2 No.

A - 2 Compressed Air - Petrol Pre-Heating

Page 101: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

93

S. Item of Works Observation/

N. Values Recorded

1. Compressor system with Pressure Yes / No

gauge : 1 No.

2. Torch ( Burner ) complete :2No. Yes / No

3. Torch ( Burner ) Keys : 1 No. Yes / No

4. Torch ( Burner ) Stand : 2 No. Yes / No

5. Goose neck attachment to Yes / No

vaporizers : 2 No.

A - 3 Oxy - LPG Pre-Heating

1. Oxy - LPG Torch ( Burner ) : 1 No. Yes / No

2. Oxygen Cylinder with Pressure Yes / No

gauge : 1 No.

3. LPG Cylinder with Pressure Yes / No

gauge : 1 No.

4. Torch ( Burner ) Stand : 1 No. Yes / No

5. Connecting Hose Pipe : 2 No. Yes / No

B. Sufficient quantity of fuel

(Petrol / LPG-Oxygen as required Yes / No

from authorized sources )

(Indicate Source) →

C. Crucible and accessories :

1. Crucible Complete : 1 No.

(a) Crucible shell Yes / No

Page 102: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

94

S. Item of Works Observation/

N. Values Recorded

(b) Crucible Lining (Availability of

Magnesite powder & sodium

silicate )

2. Crucible cap : 1 No. Yes / No

3. Crucible forks : 1 No. Yes / No

4. Crucible stands : 1 No. Yes / No

5. Crucible rings : 1 No.

D. Mould fixing arrangement

1. Mould Pressure ( Clamp ) : 1 set Yes / No

2. Mould Shoes : 2 Pairs Yes / No

E. Weld Trimmer with power pack: 1 No.

( From Approved source ) Yes / No

Indicate Source →

F. Rail profile weld grinder: 1 No.

( From Approved source ) Yes / No

Indicate Source →

G. Measuring Tools :

1. Straight Edge 1m long : 1 No. Yes / No

2. Straight Edge 10 cm long : 1 No. Yes / No

3. Gap gauge & Height Gauge : 1 No. Yes / No

4. Filler gauge : 1 No. Yes / No

Page 103: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

95

S. Item of Works Observation/

N. Values Recorded

5. Pyrometer / Thermal chalk for Pyrometer /

measurement of Rail Temperature Thermal Chalk

: 1 No.

6. Stop watch : 1 No. Yes / No

H. Other tools / Equipments

1. Cleaning rod round : 1 No. Yes / No

2. Tapping rod : 1 No. Yes / No

3. Aluminum / steel rod for thermal

plugging : 1 No, Yes / No

4. Leather washers for pump : 2 No. Yes / No

5. Tool for punch marking : 1 set Yes / No

6. Mirror 150 X 100mm with Yes / No

handle : 1 No.

7. Wooden wedges for rail Yes / No

alignment : 12 No.

I. Tool box Containing following :

1. Hot Sets (Chisels): 2 No. Yes / No

( For Emergency use only )

2. Rail file 350 X 40-6 mm: 2 No. Yes / No

( For Emergency use only )

3. Funnel tin for pouring petrol : 1 No. Yes / No

4. Adjustable spanner : 1 No. Yes / No

Page 104: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

96

5. Hammer 1 kg : 1 No. Yes / No

6. Sledge hammer double panel 5 kg : 2 No. Yes / No

7. Steel wire brush : 1 No. Yes / No

8. Blue goggles : 2 pairs Yes / No

9. Paint brush 50 mm : 1 No. Yes / No

10. Slag container (bowl) : 1 No. Yes / No

11. Asbestos gloves : 2 pairs Yes / No

12. Hose clips : 4 No. Yes / No

13. Pliers : 1 No. Yes / No

J. Insulation hood for control cooling Yes / No

(for HH rail, 110 UTS rail welding ) Required /

Not Required

2. Welding Technique used is proper Yes / No

as per extant provisions

(Compressed Air/Oxy-LPG Heating,

3 piece mould & Auto Tapping

Thimble for 52 kg 90 UTS rails and

above)

(Indicate Technique being used) →

2.1 Technique is approved for the firm Yes / No

3. Welding Portion & consumable

(a) Portion as per Rail section /UTS to Yes / No

be welded & of proper technique

S. Item of Works Observation/

N. Values Recorded

Page 105: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

97

1. Supplier / Firm

2. Batch No.

3. Portion No.

4. IC No.

5. Date of Manufacture

6. Results of Reaction test, if the Required / Not

portion is 2 years old Required

Nature of Reaction Normal / Boiling

7. Condition of Packing

(b) Three piece Mould

1. Condition of Mould Damp / Dry Cracked

/ Intact

2. Condition of vents in mould Blocked / Clear

(c) Proper quality looting sand,

ignition etc. are properly inspected Yes / No

(d) Other consumables Indicate Material &

Condition

4. Welding Team

(a) Whether full contingent of welding

team is available at site

(i) Welder : 1 No. Yes / No

(ii) Skilled Artisan : 2 No. Yes / No

S. Item of Works Observation/

N. Values Recorded

Page 106: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

98

(iii) Helper Khalasi / Khalasi : 5 No. Yes / No

(iv) Track Man: As required for site Yes / No

protection.

Name of Welder

Details of competency certificate

(b) (certificate no. & validity )

Whether competency is for Yes / No

technique to be used & is valid

Name of supervisor

Details of competency certificate

(c) (certificate no. & validity )

Whether competency is for Yes / No

technique to be used & is valid

(d) Welding of Rails being welded

5. Details of Rails being welded

(a) Section / UTS

(b) Old or new

(c) In case old Rails,

1. Anticipated balance service life

2. Rail is free from corrosion or Yes / No

excess wear.

3. Result of USFD testing.

S. Item of Works Observation/

N. Values Recorded

Page 107: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

99

4. General Condition of rails

6. General Condition of Rail ends

1. Condition of Rail Ends Hogged / Battered

Straight

2. Battering / Hogging in mm

3. End Bends of the rails in mm Vertical :

( Vertical : +0.5mm/ -0.0 mm Lateral :

Lateral : 0.5 mm )

4. End cuts are truly vertical Yes / No

5. Ends are cleaned by K-oil & wire

brush Yes / No

6. Fish bolt holes have been

eliminated Yes/No

If no. distance of fish bolt holes

from rail end being welded

C. Execution of Welds

1. Traffic Block Time

2. Gap between rail in mm

(25mm + 1for normal welds

50 + 1 and 75 + 1 for wide gap welds)

3. Alignment of rail with 1m straight

edge

S. Item of Works Observation/

N. Values Recorded

Page 108: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

100

a Lateral

(+0.5mm)

b Vertical

(The joint shall be kept higher by :

3 to 4 mm for 72UTS and 2 to

2.4 mm for higher UTS)

4. Whether proper clear working

space of 250 mm is available and Yes / No

fastening of 5 adjacent sleepers

removed

5. Proper Fixing of Prefabricated

Mould

(a) Mould aligned Centrally Yes / No

(b) The gap between mould and rail Yes / No

packed firmly with luting sand

6. Proper Fixing of Mould shoes : Yes / No

perfectly vertical, not skew

7. Pressure in Preheating

arrangement

(a) Air Petrol : Compressor tank

Pressure (7+0.7 Kg/cm2)

(b) Compressed Air Petrol : Air Pressure

(0.2 to 0.3 Kg/cm2)

(c) Oxy - LPG Pre heating :

S. Item of Works Observation/

N. Values Recorded

Page 109: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

101

(i) Pressure for Oxygen Cylinder

(7 to 8 Kg/cm2)

Pressure for LPG Cylinder

(2 to 2.5 Kg/cm2)

8. Whether pre heating torch is Yes / No

properly placed

9. Proper fixing of crucible

9(a) Whether the crucible has been

repaired properly with no loose Yes / No

sand particles

10. Specific check on AT welding Dry / Wet

portion before pouring in crucible

11. Preheating time (in minutes)

(a) Air Petrol Heating (10 to 12 minutes)

(b) Compressed air petrol (4 to 4.5

minutes)

(c) Oxy - LPG preheating (2 to 2.5

minutes)

12. Reaction of AT welding portion on Normal / Boiling

ignition violent

13. Tapping time in seconds

(Manual Tapping: (20+3) sec,

Auto Tapping L As per approval)

(a) Tapping done at time

S. Item of Works Observation/

N. Values Recorded

Page 110: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

102

14. Mould waiting time

(4-6 minutes for 25 mm weld

12 minutes for 75 mm welds)

(a) Mould Removed at time

15. Trimming of weld done by weld Yes / No

trimmer with alignment wedges

in position

a . Wedges was removed fastening Yes / No

re-fixed and sleeper spacing

corrected

b. Wedges removed at time

16. All the removed fastening

re-fixed and sleeper spacing Yes / No

corrected

17. Provision of wooden block

below the weld for support Yes / No

before passing first train

18. Removal of Risers & Runners

(a) Whether weld has completely Yes / No

cooled

(b) Removed by knocking towards Yes / No

the rail

19. First train was passed after 30

min of pouring weld metal and Yes / No

completion of weld trimming

S. Item of Works Observation/

N. Values Recorded

Page 111: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

103

(a) First Train passed at time

(b) First train passed with speed

restriction of

20. Grinding of Weld

Whether Grinding done with Profile Grinder /

profile grinder or manually Manual

Grinding was done after how

much time

Grinding of location as required Yes / No

D. Inspection of Weld

1. Visual Inspection Satisfactory /

Not satisfactory

2. Tolerances of finished weld

(a) Vertical (with 1m straight edge)

(Variation not more than +1mm/

-0.0 mm)

(b) Lateral (with 1m straight edge)

(Variation not more than +0.5mm)

(c) Finished of top surface at the

end of 10cm straight edge

(+0.4 mm /-0.0mm)

(d) Finished on sides of rail head at

the centre of 10cm straight

edge (+0.3mm)

S. Item of Works Observation/

N. Values Recorded

Page 112: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

104

3. Numbering of Weld

(a) Serial number of Weld

(b) Marking on weld done on NGF Yes / No

side as per provisions

4. Whether USFD testing of weld was Yes / No

done

(a) If yes, result of USFD testing

Action Plan for Re-welding in case

the weld found defective

(b) If no, necessary precautions taken

at site

(Protection of weld by joggled

fish plates)

5. Whether painting of thermit weld Yes / No

done or not

6. Whether the details of weld was Yes / No

properly entered in weld Register

E. Miscellaneous Items

1. Whether sample test joint are due

to be made for testing. (One out of

100 joints to be tested for Load

deflection, Hardness & porosity

tests)

(a) If, yes Indicate details viz. Joint

No. etc.

S. Item of Works Observation/

N. Values Recorded

Page 113: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

105

(b) Action Taken for testing of sample

joints

2. In case of contractual welding

2.1 Contract Details

(a) Name of firm

(b) CA No.

(c) Validity of contract

2.2 Total number of welds done so far

2.3 Details of USFD Testing

(a) Total no. of weld found defective in

USFD Testing

(b) Total no. of welds failed in service

during guarantee period

(c) Total Percentage of defective Welds

(d) The % of defective weld is within

the permissible range

2.4 Load Deflection Test, Hardness &

Porosity test

(a) Total No. of samples Required to

be tested @ 1 sample per 100 welds

(b) No. of test weld tested in Load

deflection, hardness & porosity test

S. Item of Works Observation/

N. Values Recorded

Page 114: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

106

S. Item of Works Observation/

N. Values Recorded

(c) Test Weld Samples results Yes / No

satisfactory

(d) Action taken in case of

unsatisfactory results

3. Proper Maintenance of Weld Yes / No

Register

Page 115: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

107

1. Is the number of the Level Crossing (LC)

mentioned at the LC Gate?

2 Is class of the gate mentioned on the

gate?

3 Whether Traffic/Engineering is written

on the gate?

4 Whether no. of G.K. sanctioned is

written on the gate?

5 Whether lifting barrier is provided or

not?

6 Whether the focusing of gate lamps is

all right, when observed from an

adequate distance from the middle of

the road?

7 Whether sufficient quantity of

kerosene oil, wicks and match boxes

are available at the gate?

8 Whether the gateman is on duty as per

duty roster or not?

9 Whether height gauge is provided at

the level crossing (in electrified

sections)?

E. Level Crossing.

1. Manned Level Crossing.

S. Item to be inspected Remarks Reference

N.

IRPWM PARA

909

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

IRPWM

Annexure 9/1

IRPWM

Annexure

9/1

IRPWM Para

910

IRPWM Para

910(4)

Page 116: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

108

S. Item to be inspected Remarks Reference

N.

10 Whether the knowledge of gate man

is up to the mark?

11 Whether in the electrified section, the

clearance between the height gauge

and the road surface is as per

stipulation? (4.67 meter)

12 Whether the condition of gate and its

locking arrangements are all right?

13 Whether cross levels/gauge are in

order?

14 Whether adequate ballast cushion is

available at the gate?

15 Whether interlocking as per Train

Vehicle Units (TVU) criteria arecarried

out or not? (Spl., A and B1 class)

16 Are the whistle boards corroded?

17 Whether the condition of the

drainage is all right at the gate?

18 Whether the station working rule

book is available in Hindi?

19 Whether a ramp has been provided at

both ends of the road?

20 Whether the gate man has undergone

medical checkup? (At the termination

of every period of four years,

IRPWM Para

914

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

IRPWM

Annexure 9/1

IRMM Vol I

Para 514(A)

Yes/No

Page 117: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

109

S. Item to be inspected Remarks Reference

N.

calculated from the date of

appointment, until they attain the age

of 45 years, and then every two years

until the age of 55 years and then there

after annually, until the conclusion of

their service.)

21 Whether safety banners and other

related items have been displayed at

the gate?

22 Has the gate man undergone the

refresher course as per

periodicity?(Every 5 years)

23 Is the condition of the approach road

good?

24 Does the gate man have extra chains

in case of failure of the gate barrier for

immediate and prompt action?

25 Whether gate working Rules are

available at Gate?

26 Whether gate working rules are as per

provision of Station working rules?

27 Are Safety equipments such as hand

signal lamp, hand signal detonators,

pad locks and safety chains available

at LC gate as per equipment list

provided on the gate?

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

IRPWM

Annexure

9/1

CS No. 113 of

IRPWM

IRPWM

Annexure 9/1

IRPWM

910.(1)(e)

IRPWM

Annexure9/1

Page 118: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

110

S. Item to be inspected Remarks Reference

N.

28 Is the gate man fully acquainted with

the use of the equipments?

29 Whether overhauling of the gate has

been done and is not overdue? (Once

in 2 years on PSC sleepers. Every year

for other than PSC sleepers)

30 Whether night inspections are being

carried out regularly?

31 Whether the TVU data is updated as

per three years schedule?

32 Whether the speed breakers are

provided on both sides of the road? (20

m from gate post)

33 Is the revolving unit of the lifting

barrier in working order?

34 Is the communication to the gate

proper by means of telephone?

35 Whether Station Master is responding

to rings from the gate?

36 Whether private number are being

recorded correctly at gate?

37 Has a hand pump for drinking water

provided at the site?

38 Whether fencing has been provided

along the track, at the level crossing

gate? (15 Meters)

Yes/No

Yes/No IRPWM Para

914(1)(b)

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

IRPWM Para

914(1) (d)

IRPWM

Annexure

9/1

IRPWM

Annexure 9/1

IRPWM

Annexure 9/1

IRPWM

Para 919

Page 119: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

111

S. Item to be inspected Remarks Reference

N.

39 Has the cleaning of the check rails being

done properly at the gate?

40 Whether Check rail clearance is in

order? (Clearance 51–57mm Clear

depth-38mm )

41 Are the road signs on the approaches

properly maintained?

42 Whether the protection diagram has

been exhibited at gate?

43 Whether detonators are available at

LC Gate in adequate numbers with

valid date? (Validity 5 years and

extended up to 8 years).

44 Whether competency certificate of the

gate man is current and valid?

(Once in 3 years)

45 Whether condition of check rail, check

rail blocks proper or not?

46 Whether adequate ballast cushion is

available below sleeper or not?

47 Whether proper bend/flair in check

rails end portion has been provided?

48 Whether extra shoulder ballast has

been provided in the approaches of

level crossing track to arrest the extra

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

SOD Ch. I

item 5 & 6

IRPWM

Annexure 9/1

G&SR CS. No

30

Page 120: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

112

S. Item to be inspected Remarks Reference

N.

stress in rails during extreme hot

weather?

49 Whether painting and fitting of rails

and check rails has been done? (Along

with over hauling)

50 Whether adequate longitudinal slope

has been given in the approach road of

level crossing?

51 Whether adequate width has been

provided on the road in the

approaches, as well as on the track

portion i.e. as per class of road?

52 Are the W/L boards provided at

adequate distance? (600 m)

53 Is the gate lodge as per standard of the

type plan?

54 Whether the wall clock in working

condition?

55 Have the Safety posters been

displayed?

56 Whether the train time tables have

been displayed at the gate lodge?

Yes/No

57 Whether the inspection book of level

crossings is available at the gate?

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

IRPWM

Annexure 9/1

IRPWM

Annexure 9/1

IRPWM

916/1

Page 121: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

113

S. Item to be inspected Remarks Reference

N.

58 Whether the complaint book is

available at the gate?

59 Whether level crossing registers are

available at the gate?

60 Whether the gate booms/gate leaves

are properly functioning?

61 Whether the gate man is aware of the

safety rules in case of emergency?

Yes/No

IRPWM

Para 915

Yes/No

Yes/No

Yes/No

2. UNMANNED LEVEL CROSSINGS

S. Item to be inspected Remarks Reference

N.

1 Is the number of LC mentioned at LC

Gate?

2 Is the type of gate mentioned on the

gate?

3 Whether the road surface is well

maintained between gate posts and

approaches as regards level &

gradient?

(The uneven or broken surface of

road should be leveled as early as

possible. And patch work should be

done immediately, so that the road

surface can be made leveled and

Yes/No

IRPWM

Annexure 9/1

Yes/No

Yes/No

Page 122: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

114

S. Item to be inspected Remarks Reference

N.

smooth. Hexagonal concrete blocks may

be provided, which are durable against

wear and tear in gauge conversion and

new construction. It has been proved

more useful and durable for maintaining

the road surface. Secondly it gives better

appearance to the road surface and

having high resisting power during

monsoon season. It should be provided

in between the two gates. Outside the

gate road surface can be maintained by

black top road. Hence it is easy to

maintain and easy to prepare a smooth

road surface quickly. Road surface is

made smooth in such a way that vehicles

are not struck to the track)

4 Are the road signs on the approaches

properly maintained?

(Generally indicators and warning

boards get faded with time when

ordinary paint is used. Hence as for as

possible luminous paints / luminous

strips should be used. As far as

luminous strip and luminous paint are

concerned, for speed breakers sign

boards, whistle boards and stop boards

etc. the luminous strip are more

effective rather than luminous paint as

it is just a like a pre-cast concrete which

cannot be deteriorated immediately.)

IRPWM

Annexure

9/1

Yes/No

Page 123: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

115

S. Item to be inspected Remarks Reference

N.

5 Whether check rail clearance is in

order? (Clearance 51-57 mm Clear

depth 38 mm )

6 Whether track gauge and Cross-Level

are in order?

7 Whether W/L board provided on both

sides of the gate at a proper location,

at a distance of 600 m from level

crossings on either side of the road?

8 Whether the condition of the approach

track of level crossings is in good

condition?

9 Whether visibility requirement for

road users of 600 m along the track from

5 m from nearest track center.

10 Whether road users are taking

precautions of stopping on the whistle

of the train?

11 Whether stop board is provided on the

both ends of the road approaching in

case of unmanned gate? (5 m from

center line of nearest track)

12 Whether speed breakers are provided

on both sides of the road? 20 m from

gate post

SOD Ch. I

item 5 & 6Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

IRPWM Para

916(1)

IRPWM

Annexure 9/1

IRPWM Para

917

IRPWM

916(2)

CS No. 128 of

IRPWM

Page 124: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

116

F. Inspection for Tamping Site

(3X/CSM/Duomatic/UNIMAT)

S. Item to be inspected Obser- Reference

N. vation

1 a) Machine Type

(CSM/Duomatic/Unimat)

b) Machine No. & Make

c) Base station/Division

d) Manufacturer

e) Year of manufacturing

f) Last major Maintenance schedule

(POH/IOH) undertaken

g) Next POH/IOH due on

h) Month/year of last POH/IOH

i) Depot of last POH/IOH

POH/

IOH

S. Item to be inspected Remarks Reference

N.

13 Whether warning boards have been

provided at the proper location?

14 Is the census being carried out

regularly after three years?

Yes/No IRPWM

Annexure 9/1

Yes/No IRPWM Para

919

POH____

IOH___

Railway

Board

Letter

No.98/

Track-III/Tk/

27-Pt

dated 20-

05-2003

Page 125: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

117

S. Item to be inspected Remarks Reference

N.

j) Rated output of the machine

(No. of Sleepers/Hour)

k) Name of SSE/TM/In-charge

l) Name/designation of the operator

2 Is there any tamping tool(s) missing

or worn-out?

(Wear to be < 20% of cross sectional

area)

3 Is the Condition of tamping tools

satisfactory and fitting tight?

4 Is the condition and adjustment of

track lifting rollers satisfactory?

5 Is the condition of lifting hooks

(UNIMAT) satisfactory?

6 Availability of Camping coach

7 Is the condition of the Camping

Coach satisfactory?

8 Are all safety equipment as per list

annexed available?

9 Has it been ensured that stabling

siding for machine’s coaches is having

adequate water supply, power supply

& resting facility?

Yes/No

Checklist iss-

ued by RDSO

Yes/No

Yes/No

Yes/No Para 3.1.1(i)

(IRTMM)

Checklist

issued by

RDSO

Para 7.2 (i)

IRTMM

Para 3.1.3

(V)

(IRTMM)

Yes/No Para 3.1.3

(V) (IRTMM)

Yes/No

Yes/No/

NA

Checklist iss-

ued by RDSO

Yes/No

Page 126: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

118

S. Item to be inspected Remarks Reference

N.

10 Pre-tamping Inspection

i) Location of inspection

KM.

Line

Blocksection

Route

Division

ii) Availability of

a) Clean Cushion (minimum 150 mm)

b) Adequate ballast for min. 20 mm

lift in shoulder / crib

iii) Month & Year of Last Deep

Screening

iv) Is the condition of track drainage

satisfactory, pumping locations

attended & rounded ballast replaced

with clean angular ballast?

v) Is the condition of cess satisfactory

and low cess made-up?

vi) Is the speacing of sleeper’s

uniform?

vii) Are fittings in good Condition and

tightened?

Para 3.1.1(iv)

(IRTMM)

Yes/No

Yes/No

Para 3.1.2

(vi)

(IRTMM)

Yes/No Para 3.1.2(v)

(IRTMM)

Yes/No Para 3.1.2

(vi)

(IRTMM)

Yes/No

Yes/No Para 3.1.2(iv)

(IRTMM)

Page 127: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

119

viii) Has all missing/broken fittings

been replaced?

ix) Is the condition of sleepers

satisfactory?

x) Has all damaged/broken sleepers

been replaced?

xi) Are all the sleepers square?

xii) Has attention to hogged/battered

joints been given?

xiii) Was Pre-tamping survey done as

per guidelines (IRTMM/Anne. 5.3) for

design mode working?

xiv) Is the solutions for Realignment

of curves with interpolation of slews

for feeding (with correction values, as

applicable) available? (as per

Annexure 5.3of IRTMM)

xv) Are the beginning and end of

circular and transitions of curves

marked on sleepers?

xvi) Is the plotting of existing profile

after pre-survey done and working

sheet for slew & lift values and

interpolation for feeding (with

correction values, as applicable)

prepared? (as per Annex. 5.3 of IRTMM)

S. Item to be inspected Remarks Reference

N.

Yes/No Para 3.1.2

(vii) (IRTMM)

Yes/No Para 3.1.2

(viii) (IRTMM)

Yes/No Para 3.1.2

(ix)(IRTMM)

Yes/No/

NA

Para 3.1.2

(iv) (IRTMM)

Yes/No Para 3.1.2 (i)

(IRTMM)

Yes/No/

NA

Para 3.1.2(i)

(IRTMM)

Yes/No/

NA

Para 3.1.2(ii)

(IRTMM)

Yes/No Para 3.1.2 (i)

(IRTMM)

Yes/No Para 3.1.2

(ix) (IRTMM)

Page 128: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

120

xvii) Are the reference markings

along the track available?

xviii) Has slew values, lift values and

SE values written on sleepers?

xix) Is ballast heaped in tamping

zone?

xx) Are the level crossing road

surface opened for tamping?

xxi) Are the check rails on level

crossings removed for tamping?

xxii) Are the guard rails on bridge

approaches removed?

xxiii) Is the Removal/marking of

obstructions such as rail lubricators,

signal rods, cable pipes, glued joints

etc. done?

xxiv) Are the marking of OHE bonds/

removal done? (in electrified

sections)

xxv) Are the joggled fishplates,

wooden blocks etc. removed?

xxvi) Is the sufficient lighting at work

site arranged for working during

night?

xxvii) Has the availability of OHE and

S. Item to be inspected Remarks Reference

N.

Yes/No/

NA

Para 3.2.1

(xi) (IRTMM)

Yes/No/

NA

Para 3.2.1

(xi) (IRTMM)

Yes/No Para

3.2.2(xii)

(IRTMM)

Yes/No/

NA

Para

3.2.2(xiv)

(IRTMM)

Para 3.1.2

(vii)

(IRTMM)

Yes/No Para 3.1.2 (i)

(IRTMM)

Yes/No Para 3.1.2 (ii)

(IRTMM)

Yes/No/

NA

Para 3.1.2

(IRTMM)

Yes/No Para 3.2.2

(xiii) (IRTMM)

Yes/No/

NA

Yes/No Para 3.1.2

(iii) (IRTMM)

Page 129: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

121

S. Item to be inspected Remarks Reference

N.

S&T staff been ensured, as required?

xxviii) Has adjustment of gaps in

joints / creep adjustment been

done?

xxix) UNIMAT working

a) Turnout No.

b) Station

c) Angle of crossing

d) LH/RH

e) When was it last Tamped?

(Month/ Year )

f) Is the layout including spacing of

sleepers as per relevant drawings?

g) Is the battered or worn Crossing

attended? (Reconditioning/

Replacement)

h) Are the S&T gears likely to infringe

during tamping cleared?

LWR

i) Destressing temperature of LWR

ii) Last destressing date

Yes/No/

NA

Para 3.2.2 (v)

of IRTMM

Yes/No/

NA

Para 3.1.2 (x)of IRTMM

Yes/No Para 3.2.1 (i)

(IRTMM)

Yes/No Para 3.2.1 (ii)

(IRTMM)

Yes/No Para 3.2.2 (v)

(IRTMM)

Page 130: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

122

iii) Is the temporary de-stressing

done at higher/lower temperature?

iv) Likelihood of temperature

exceeding td+20°C

9 Section of work

i) Division

ii) ADEN

iii) SSE Section

10 Section of work / Traffic block

i) Block section and lines blocked

ii) Timing and total Duration (minutes)

iii) Travel time to work spot (minutes)

iv) Actual working time (minutes)

v) Travel time to clear block (minutes)

vi) Total ineffective time (minutes)

(Max ineffective time = 0.45 Hrs.)

(27 minutes)

S. Item to be inspected Remarks Reference

N.

Yes/No

Temp

td= °C

Yes/No

Para 3.1.2(x)

(IRTMM)

Para 6.2.1 (i)

(a) (LWR

Manual)

Railway

Board

Letter

No.98/

Track-III/Tk/

27-Pt dated

20-05-2003

Page 131: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

123

S. Item to be inspected Remarks Reference

N.

11 Operations During Tamping

i) Has the protection of the site of

work and adjoining track done as per

G&SR?

ii) Working alignment .

(Straight/curve)

iii) Degree & Length of curve

iv) Is there any Points & Crossings

present in planned stretch for

tamping?

v) Are there points and crossing

being tamped in same block?

vi) Is the Lining being done in Design

mode?

vii) Lining Working Method adopted

viii) Is the Levelling being done in

Precision mode?

ix) Has the Setting of tamping depth

been done as per track structure?

The gap between top edge of the

tamping blade and the bottom edge

of the sleeper in closed position of

the tamping tool should be adjusted

Para 4.2.2

(IRTMM)Yes/No

Degree=

Length=

in meter

Yes/No

Yes/No

Yes/No

3 Point

4 Point

Yes/No

Para 3.1.3 (i)

(IRTMM)Yes/No

Page 132: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

124

S. Item to be inspected Remarks Reference

N.

depending upon the type of rail and

sleepers.

(For Metal sleeper: 22-25 mm, for

Flat bottom sleeper : 10-12 mm)

x) Is the Squeezing pressure of

tamping unit correctly set?

a) PSC sleepers (110-120 kg/cm2),

b) ST, Wooden sleepers (100-110 kg/

cm2),

c) CST-9 sleepers (90-100 kg/cm2)

xi) Minimum Slew Value (mm)

xii) Maximum Slew Value (mm) ( Not

more than 50 mm)

xiii) Maximum lift value (mm) ( Not

more than 50 mm)

xiv) Has it been ensured that a

minimum 15-20 mm general lift is

given at high point?

xv) Is no. of insertion commensurate

with lift?

(up to 30mm lift – single insertion,

30mm to 50mm – two insertions for

PSC sleeper track)

mm

Yes/No

Yes/No

Para 3.1.3

(iii) (IRTMM)Yes/No

mm

mm

Para 3.1.1

(i) (IRTMM)

Para 3.1.3

(iii) (d)

(IRTMM)

Para 3.1.3

(viii) (IRTMM)

Para 3.1.3

(viii) (IRTMM)

Page 133: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

125

S. Item to be inspected Remarks Reference

N.

xvi) Is the squeezing time set

correctly? (0.4 to 0.6 sec)

xvii) Are the feeding of correction

values on transitions of curves (Vm/

F) being done? (In 4 point system of

lining only)

xviii) Is the feeding of SE values done

as per feeding location?

xix) Is the correction for new SE, (K)

being done?

xx) Is the feeding of ‘X’ correction for

vertical curve being done?

xxi) Is the ramping of 1 in 1000

given before closing the day's work

and obligatory points being done?

(The next day's work shall begin from

the point of commencement of

previous day's ramp)

xxii) Are the parameters of tamped

track checked after tamping?

xxiii) UNIMAT working

a) Length of approaches covered

along with turnout (m)

b) Direction of tamping

(Switch → Crossing)

Yes/No

Yes/No

Yes/No

Yes/No

Para 3.2.3

(iv) (IRTMM)

Yes/No/

NA

Annexure

2.1

(IRTMM)

Yes/No/

NA

Track Machine

Documentation

Track Machine

DocumentationYes/No/

NA

Track Machine

DocumentationYes/No/

NA

Para 3.1.3

(vi) (IRTMM)

Para 3.1.3

(ix) (IRTMM)

Para 3.2

IRTMM------m

Page 134: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

126

c) Is the Sequence of tamping is first

on main line then on turnout side?

(ML → LL)

d) Is the turnout side rail supported

after lifting on mainline; till it is

tamped

e) Has the Squeezing pressure been

set correctly?

(i) ST/wooden sleepers : 110-115 kg/

cm2

(ii) PSC sleepers: 135-140 kg/cm2

f) Has it been ensured that a

minimum of 10 mm general lift is

given at high points in the turnout?

g) Has the turn in curve been tamped

along with turnout?

12 Post Tamping Operations

i) Location of inspection :-

KM:-

Line:-

Block section:-

Route:-

Division:-

Yes/No

Yes/No/

NA

Yes/No

Yes/No/

NA

Para 3.2.2

(i)

(IRTMM)

Para 3.2.2

(i)

(IRTMM)

Para 3.2.2

(iii)(IRTMM)

Para 3.2

(IRTMM)

Yes/No Para 3.2.1

(iii) (IRTMM)

S. Item to be inspected Remarks ReferenceN.

Page 135: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

127

ii) Has all loose fittings been

tightensd?

iii) Has all broken fittings been

replaced?

iv) Has the ballast been dressed

neatly?

v) Has the ballast between the

sleepers and on shoulders been

consolidated?

vi) Has all track parameters been

recorded with the help of recorders

provided in the tamping machine?

vii) Whether Value of Track Parameter

recorded satisfies IRTMM provisions?

Alignment

a) Not more than 10 peaks exceeding

+/- 4 mm.

b) Any peak not more than +/- 6 mm.

Cross level Not more than 10 peaks

exceeding +/- 6 mm.

Unevenness

a) Not more than 10 peaks exceeding

6 mm.

b) Any peak not more than 10 mm.

viii) Has all check rails/guard rails

been re-fixed?

Yes/No

Para3.1.4

(iii) IRTMM

Yes/No Para3.1.4 (i)

IRTMM

Yes/No Para3.1.4 (ii)

IRTMM

Yes/No

Para 3.1.4

(iv) IRTMMYes/No

Para 3.1.4

(iv) IRTMMYes/No

Para 3.1.4

(iv) IRTMMYes/No

Para 3.1.4

(vi) IRTMM

Yes/NoPara 3.1.4

(iv) IRTMM

Yes/No

S. Item to be inspected Remarks ReferenceN.

Page 136: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

128

ix) UNIMAT working – Has all S&T/

Electrical connections been

restored?

13 Has it been ensured that adequate

ballast is trained out for complete

ballast profile as per IRPWM and

profiling done?

14 Is the actual Output of the machine

matches with rated Progress of the

Machine?

Duomatic -

CSM - 1.2 Km/effective block hour

T EX - 1.6 Km/effective block hour

UNIMAT - 75/90 min for each turnout

15 Any other specific Observation (not

covered above):

Para 3.2.3

(IRTMM)Yes/No

Para 263

(IRPWMYes/No

Railway

Board Letter

No.98/Track-

III/Tk/27-Pt

dated 20-05-

2003

Yes/No

S. Item to be inspected Remarks ReferenceN.

Page 137: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

129

1 Detonators in a tin case 1 Box

2 H.S. flag red 2 Nos.

3 H.S. flag green 1 Nos.

4 H.S. Tri colour lamps (LED) 2 Nos.

5 Chain & Padlock 1 Set

6 Clamp with Padlock 2 Nos.

7 10 t jack ( CSM / UNIMAT ) 1 No.

8 20 t jack ( Tamping Express ) 1 No.

9 Crow bars 4 Nos.

10 Wooden blocks off sizes 8 Nos.

11 Gauge cum level 1 No.

12 Rail thermometer (dial type) 1 No.

13 Banner flag 2 Nos.

14 Portable Control Phone 1 No.

15 Walky Talky 2 Nos.

16 First Aid Box 1 No.

17 Skids 2 Nos.

Safety Equipment

S. Description Quantity

N.

Page 138: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

130

S. Description Quantity

N.

18 Working time table of section where machine

working

19 G&SR book with upto date amendment slips 1 Copy

20 4 Cell Flasher Light / LED Torch, 6 Watt 1 No.

21 LED Petromax / Led Lamps 1 No.

22 Safety Helmets Machine

Staff

23 Protective Clothing, Safety Shoes and Safety Machine

Gloves Staff

24 Track Machine Manual (with updated C.S) 1 No.

25 Accident Manual (with updated C.S) 1 No.

26 Fire Extinguisher 1 No.

27 Hooter (Manual / Remote) 2 Nos.

28 Hydraulic Hand Pump 1 No.

29 Emergency pneumatic/Hydraulic hose of

sizes suiting to different machines(complete 1 No.

with end fittings)

1 Copy

Page 139: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

131

G. Inspection for Ballast Screening Site (BCM Working)

1 a) Machine Type (BCM)

b) Machine No.

c) Base station/Division

d) Manufacturer

e) Year of manufacturing

f) Last major Maintenance schedule

(POH/IOH)

g) Month/Year of last IOH/POH

h) Rated output of the machine (m/

Hour)

i) Name of SSE/TM/In-charge

j) Name/designation of the operator

2 Availability of Camping coach?

3 Is condition of the Camping Coach

satisfactory?

4 Has it been ensured that stabling

siding for machine’s coaches is having

adequate water supply, power supply

& resting facilities?

5 Has it been ensured that OHE Block is

taken or OHE is disconnected for

maintenance of BCM in stabling

siding?

S. Narration

N.

Observa-

tionsReference

POH/IOH

Yes/No

Yes/No

Yes/No Para 7.2 (i)

(IRTMM)

Yes/No Para 7.2 (vi)

(IRTMM)

RB’s

Leeter No:

98/track/

III/TK/27-

Pt.

dated.20/

05/2003.-

Page 140: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

132

S. Narration

N.

Observa-

tionsReference

6 Has it been ensured that the gas cutting

equipments is available on the machine?

7 Are all safety equipment as per list

annexed available?

Preliminary Works

8 Location of inspection

9 Availability of cushion (Total cushion

shall not be less than 250 mm)

Clean cushion =

10 i) Month & Year of Last Deep Screening

ii) GMT passed after last deepscreening

11 Has all preliminary works including

survey for marking of the longitudinal

levels for lifting and proper cross fall

to avoid formation of water traps etc.

been ensured?

12 Has the final longitudinal levels as per

redesigned profile been worked out &

marked on the pegs/OHE mast

alongside the track?

13 Has it been ensured that adequate

ballast is available on track for requisite

cushion and to avoid ballast deficiency

immediately after screening?

14 Has it been ensured that adequate

ballast is available on cess/depot for

Yes/No Para 3.3.2

(xi) (IRTMM)

Yes/No Para 3.3.2

(i) & (ii)

(IRTMM)

Yes/No

Yes/No

Yes/No Checklist iss-

ued by RDSO

IRPWM Para

238 (5)-

Para 3.3.2

(iii)

(IRTMM)

Yes/No

mm

Page 141: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

133

S. Narration

N.

Observa-

tionsReference

supplementing the ballast for

complete profile as per IRPWM?

15 Are Sleeper fittings in good Condition

and tightened?

16 Has all missing/broken fittings and

Damaged/broken sleepers been

replaced?

17 Has it been ensured that entire ballast

beyond the reach of cutter chain is

transferred in its cutting width?

18 Has it been ensured that a trench of

300mm depth & 1 meter width is

prepared lowering of cutter bar in

advance?

In case of screening of turnout,

whether requisite trench for

installation of extension pieces on right

side is prepared?

19 Has it been ensured that proper

lighting arrangement are made for

night working on machine and/or OHE

Mast?

20 Has it been ensured that there is no

obstruction (including LWR pegs, creep

post, signal rodding/cables etc.) in the

width of 4100mm to avoid

infringement to cutter chain?

Para 5.3.5

(viii)

(IRTMM)

Yes/No

Para 3.3.2

(v) & (vii)

(IRTMM)

Yes/No

Yes/No Para 3.3.1

(iv) (IRTMM)

Yes/No Para 3.3.2

(x) (IRTMM)

Yes/No

Yes/No Para 3.3.2

(iv) (IRTMM)

Yes/No

Para 3.3.2

(xiii)

(IRTMM)

Para 3.3.2

(x) (IRTMM)

Yes/No

Page 142: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

134

S. Narration

N.

Observa-

tionsReference

21 Has it been ensured that L-Xing should

be opened in advance so as to enable

machine to work?

22 Has it been ensured that in OHE

section distance of mast foundation

from track centre is accurately

measured and checked for free

movement of cutting chain?

23 Has it been ensured that approaches

to bridges which cannot be screened

by the machine screened manually in

advance of the machine working?

24 Has it been ensured that all the

obstruction i.e., rail pegs, broken PRCs,

foundation etc. are removed in advance?

25 Has it been ensured that Tamping

machine & DGS is available while

doing deep screening by BCM?

26 LWR

i) Destressing temperature of LWR

ii) Last distressing date

iii Is the temporary de-stressing done

at higher/lower temperature?Temp td=

iv) Likelihood of temperature

exceeding td + 20°C

Yes/No

Yes/No

Para 3.3.2

(viii)

(IRTMM)

Yes/No

Para 3.3.2

(v)

(IRTMM)

Yes/No

Para 3.3.2

(ix)

(IRTMM)

Para 3.3.2

(vi)

(IRTMM)

Yes/No

Yes/No

°CPara 3.1.2(x)

(IRTMM)

Yes/No Para 6.2.1 (i)

(a) (LWR

Manual)

Page 143: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

135

S. Item to be inspected Remarks Reference

N.

During Working of BCM

27 Location of work

i) Division

ii) ADEN

iii) SSE Section

28 Traffic block

i) Block section and lines blocked

ii) Timing and total Duration (minutes)

iii) Travel time to work spot (minutes)

iv) Actual working time (minutes)

v) Travel time to clear block (minutes)

vi) Total ineffective time (minutes)

(Max ineffective time = 60 minutes)

29 i) Has it been ensured that proper

protection of worksite done with

banner flag & detonators during block

to follow the lookout caution on

adjacent line?

ii) Whether speed restriction on

adjacent track has been imposed

while block working?

Rly. Bd.

Letter

No.98/

Track-iii/Tk/

27-pt dated

20-05-2003

Yes/No

Yes/No

Para 4.6.1

(IRTMM)

Page 144: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

136

S. Item to be inspected Remarks Reference

N.

30 Has it been ensured that hooter in

working condition is available at the

BCM site and everybody is sensitized

to ensure safety?

31 Has it been ensured that a person on

either side of BCM/SBCM is nominated

and available to watch for any

obstruction & stop machine

immediately?

32 Has all staff working with machine

provided with helmets and masks?

33 Has it been ensured that cutter chain is not

cutting/disturbing the formation and

necessary lifting of track done as required?

(If total cushion, less than 250 mm)

34 Are the S&T gears likely to infringe

cleared in case of Turnouts?

35 Is the availability of S&T / Electrical

Staff ensured? (If required)

36 Is the Ramping of 1 in 1000 given

before closing the day's work and

obligatory points being done?

37 Has it been ensured that vertical and

lateral clearances of OHE, signal post

& any other structure is checked and

adjusted before clearing BCM block?

Yes/No

Yes/No

Para 4.6.8 (i)

(IRTMM)

Yes/No

Para 3.3.3 (ii)

(IRTMM)

Para 3.3.3

(vi) (IRTMM)

Yes/No

Yes/No

Para 3.3.1

(i) (IRTMM)

Para 3.3.2(v)

(IRTMM)

Yes/No Para 3.1.3(vi)

(IRTMM)

Yes/No

NA

Para 3.3.2 (v)

Para 7.2 (vi)

(IRTMM)

Yes/No Para 3.1.4(ii)

(IRTMM)

Page 145: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

137

S. Item to be inspected Remarks Reference

N.

38 Has it been ensured that a round of

tamping with DTS is carried out

immediately after deepscreening to

resume trafficat aspeed of 40 Kmph?

Post BCM Working

39 Has all loose fittings been tightened?

40 Has all broken fittings been replaced?

41 Has all check rails/guard rails been re-

fixed?

42 Has it been ensured that adequate

ballast is trained out for complete

ballast profile as per IRPWM and

profiling done?

43 BCM working – Has all S&T/OHE

connections restored?

44 Is the actual Output of the machine

matches with rated Progress of the

Machine?

(BCM - 0.2 Km/effective hour of working)

45 Has it been ensured that watchman is

posted after the block or round the clock

at the location while cutter bar & chain

are left at site?

46 Any other specific observation (not

covered above):

Yes/No

Yes/No Para 3.3.4(v)

(IRTMM)

Para 3.1.4 (i)

(IRTMM)

Yes/No

Para 3.1.4

(ii) (IRTMM)

Para 3.3.4

(iii) (IRTMM)

Yes/No Para 3.2.3

(IRTMM)

Railway Board

Letter No.98/

Track-iii/Tk/27-

Pt dated 20-

05-2003

Yes/No

Yes/NoPara 3.3.4

(iv) (IRTMM)

Page 146: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

138

Safety Equipment

S. Description Quantity

N.

1 Detonators in a tin case

2 H.S. flag red

3 H.S. flag green

4 H.S. Tri colour lamps (LED)

5 Chain & Padlock

6 Clamp with Padlock

7 10 T jack

8 Crow bars

9 Wooden blocks off sizes

10 Gauge cum level

11 Rail thermometer (dial type)

12 Banner flag

13 Portable Control Phone

14 Walky Talky

15 First Aid Box

16 Skids

1 Box

2 Nos.

1 Nos.

2 Nos.

1 Set

2 Nos.

1 No.

4 Nos.

8 Nos.

1 No.

1 No.

2 Nos.

1 No.

2 Nos.

1 No.

2 Nos.

Page 147: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

139

17 Working time table of section where

machine working

18 G&SR book with upto date

amendment slips

19 4 Cell Flasher Light / LED Torch, 6 Watt

20 LED Petromax / Led Lamps

21 Safety Helmets

22 Protective Clothing, Safety Shoes and

Safety Gloves

23 Track Machine Manual (with updated C.S)

24 Accident Manual (with updated C.S)

25 Fire Extinguisher

26 Hooter (Manual / Remote)

27 Hydraulic Hand Pump

28 Emergency pneumatic/Hydraulic hose

of sizes suiting to different machines

(complete with end fittings)

1 Copy

1 Copy

1 No.

1 No.

Machine Staff

Machine Staff

1 No.

1 No.

1 No.

2 Nos.

1 No.

1 No.

S. Description Quantity

N.

Page 148: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

140

S. Item

N.

Check Reference

A. Personal

1 Is valid Track Machine competency

certificate issued by Dy.CE/Machine

available with operator?

2 4 Are all safety equipment as

indicated in IRTMM available?

3 Is Operator Carrying Extra pair of

spactacles, if wearing?

4. Are all safety equipment as indicated

in IRTMM available?

5 Is Operator conversant with the

system of working and having route

learning of the section?

6 Is the machine staff self-declared that

liquor / intoxication not taken by him

prior to reporting ON Duty? -

7 Is the machine equipped with

prescribed head & tail light, LV board,

marker light and flasher light?

8 Is the machine equipped with

prescribed equipment in working

condition as per IRTMM?

Yes/No

Yes/No

Yes/No

NA

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Para 4.3.2

(IRTMM)

Para 4.3.1

(IRTMM)

Para 4.4.1

(IRTMM)

GR

3.78

Para 4.4.2

(IRTMM)

Para 4.4.3

(IRTMM)

Para 4.3

(IRTMM)

Checklist for Machine Operator for Safe Operation of Track Machine

Page 149: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

141

S. Item to be inspected Remarks Reference

N.

B. Yard

1 Is Track Machine stabled clear of

fouling mark, sand traps and not

obstructing adjacent line(s)?

2 Are necessary precaution taken

against rolling down such as pinning

down hand brakes, chaining and

provision of skids and temporary

buffers?

3 Are concerned points set against the

line on which track machine(s) is

stabled and such points are secured

with clamps or cotter bolts and

padlocks?

4 Is brake feel test conducted before

proceeding from siding?

5 Is the shunting order issued by on duty

SM to move the machine in running line

to/from the siding/stabling line?

6 Is shunting staff with proper shunting

order available during shunting?

7 Is track machine having proper

authority to proceed?

8 Is special caution order issued by SM

duly signed by JE/SE (P.Way) and

Operator?

Yes/No Para 4.6.5

(IRTMM)

Yes/No

Yes/No

Para 4.5.1(i)

(IRTMM)

Para 4.6.6

(IRTMM)

Yes/No GR 4.31

Yes/No Para 4.5.1

(ii)(IRTMM)

Yes/No GR 5.13

Yes/No Para 4.5.1

(iii)(IRTMM)

Yes/No Para 4.5.1

(IRTMM)

Page 150: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

142

S. Item to be inspected Remarks Reference

N.

9 Is authority issued to work all

machines working in convoy as per

Subsidiary Rule of Railway?

10 Is facing point locked by clamp for

movement of machines?

C. Block Section Working.

1 Is proper line block taken for working

the Track Machine indicating number

of machines to work duly endorsed by

SM with special instruction to proceed,

work and return via right or wrong

direction?

2 Is the adjacent line also blocked (and

permitted by control and SM) in case of

some BRM, T-28 etc. likely to foul

adjacent line(s).

3 Is SE (P.Way) available on machine for

working in block section?

4 Are all restriction followed as detail

given in caution order?

5 Is continuous whistling being done

approaching to L-Xing?

6 Is safe distance of 120m between the

machines moving in convoy

maintained?

Yes/No GR0 4.65

Yes/No Para 4.6.6

(IRTMM)

Yes/No Para 4.5.1

(IRTMM)

Para 4.6.2

(IRTMM)

Yes/No Para 4.2.2

(IRTMM)

Yes/No GR 4.09

Yes/No Para 4.6.4

(IRTMM)

Para 4.6.4

(IRTMM)

Yes/No

Yes/No

Page 151: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

143

S. Item to be inspected Remarks Reference

N.

7 Is the machine moving cautiously at

very low speed which shall under no

circumstances exceed 10 kmph in foggy

weather / poor visibility/dust storm

etc.?

8 Is minimum 120 meter distance kept

machine to machine while travelling &

50 meter while working?

9. Is protection of work site in block

section and also for adjoining track(s),

in case of infringement, carried out by

SE/JE (P.Way)?

10 Is temporary whistle board is provided

by SE/JE/P.Way on adjoining track at

Track Machine work site?

11 Are hooter available with the track

machine deployed at site?

12 Are all trains passing adjoining track

issued a caution order to "OBSERVE

HAND SIGNAL, WHISTLE FREELY AND

STOP IF REQUIRED"

13 Is PTW issued by OHE supervisor for

working of machine in electrified area?

14 Are all physical locking of working unit

of machines checked after availing

block?

Yes/No GR 9.07(5)

Yes/No Para 4.6.4

(IRTMM)

Yes/No Para 4.6.1

& 4.6.2

(IRTMM)

Yes/No Para 4.6.8

(ii)(IRTMM)

Yes/No Para 4.6.8

(i)(IRTMM)

Yes/No Para 4.6.8

(iii)(IRTMM)

Yes/No Para 3.6.2

(IRTMM)

Yes/No As per

RDSO’s

inspection

checklist

Page 152: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

144

S. Item to be inspected Remarks Reference

N.

15 Has it been ensured that the

clearances (vertical and lateral) for

OHE, Signal Post and any other

structure are checked and there is no

infringement to SOD before clearing the

block?

16 Is the track certified fit and cleared for

normal train operations subject to

observation of speed restrictions?

17 Did JE/SE (P.Way) travel on last machine

in work & proceed mode & first

machine in work & return mode?

18 Sanction of CRS for working of the track

machine

NOTE:-

Yes/No Para 4.6.8

(iv)

(IRTMM)

Yes/No Para 4.5.2

(IRTMM)

Yes/No Para 4.5.2

& Para

4.5.3

(IRTMM)

Yes/No Para 3.1.1

(ii) (IRTMM)

1 Please refer to GR 4.65, and subsidiary rules thereunder for

working of Track Maintenance Machines

2 Any other safety rule not covered above, shall also be followed

by the machine operator in letter and spirit.

Page 153: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

145

Maintenance Instructions & Guidelines for

Different On-Track Machines.

Report is also available at: http://www.rdso.indianrailways.gov.in/

view_section.jsp?lang=0&id=0,2,465,610,1073

S.

N.

1 Ballast

Cleaning

Machine

(BCM-RM-80)

2 Ballast

Regulating

Machine

(BRM-

Kershaw)

3 Ballast

Regulating

Machine (PBR-

400R)

4 Continuous

Tamping

Machine (CSM

09-32)

Name of

Machine

Document Issue

Date

Report

No.

Inspection Check List

Maintenance

Schedule

Trouble-Shooting

Manual

Inspection Check List

Maintenance

Schedule

Trouble-Shooting

Manual (English)

Trouble-Shooting

Manual(Hindi)

Inspection Check List

Maintenance

Schedule

Inspection Check List

Maintenance

Schedule (English)

Maintenance

Schedule (Hindi)

Nov.2004

Jan.2005

Jan.2002

Feb.2006

Jun.2005

Jul.2004

Jul.2004

Feb.2011

Dec.2010

Oct-14

Jul.2004

Jul.2004

TM-73

TM-77

TM-42

TM-96

TM-87

TM-70

TM-70

TM-156

TM-153

TM-74 Rev.-1

TM-69

TM-69

Page 154: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

146

S.

N.

Name of

Machine

Document Issue

Date

Report

No.

5 Dynamic

Track

Stabilizer(DGS-

Plasser-62N)

6 Shoulder

Ballast

Cleaning

Machine(FRM-

80)

7 Shoulder

Ballast

Cleaning

Machine

(FRM-85F)

8 Multipurpose

Track Tamping

Machine

(UNIMAT

Compact-M)

Trouble-Shooting

Manual

List of Critical Spare

Parts(Rev.01)

Inspection Check List

Maintenance

Schedule

Trouble-Shooting

Manual

List of Critical Spare

Parts

Inspection Check List

Maintenance

Schedule

Critical Spare Part

list of Shoulder

Ballast Cleaning

Machine (FRM-80)

Inspection Check List

Maintenance

Schedule

Inspection Check List

Maintenance

Schedule

List of Critical Spare Parts

Mar.2004

Jul.2012

Oct.2005

Aug.2005

Sept.2010

Aug.2004

Sept.2005

Feb.2005

Dec. 2014

Dec.2009

Nov.2008

Dec.2006

Jun.2006

Aug.2004

TM-62

CSP

TM-92

TM-90

TM-148

CSP

TM-91

TM-79

CSP

TM-136

TM-125

TM-105

TM-100

CSP

Page 155: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

147

S.

N.

Name of

Machine

Document Issue

Date

Report

No.

Inspection Check List

Maintenance

Schedule

Trouble-Shooting

Manual

List of Critical Spare

Parts

Inspection Check List

Maintenance

Schedule

Trouble-Shooting

Manual

List of Critical Spare

Parts

Inspection Check List

Maintenance

Schedule

List of Critical Spare

Parts (Rev.01)

Inspection Check List

Maintenance

Schedule

Trouble-Shooting

Manual

Inspection Check List

Maintenance

Schedule

Mar.2015

Mar.2015

Feb.2009

Aug.2004

Sept.2006

Aug.2006

Mar.2007

Aug.2004

Dec. 2014

May.2005

Jul.2012

Jul.2011

Jul.2011

Feb.2009

Feb.2007

Oct.2006

TM-108 Rev.-1

TM-101

Revision-1

TM-128

CSP

TM-103

TM-102

TM-110

CSP

TM-106Rev.-1

TM-85

CSP

TM-160

TM-159

TM-128

TM-107

TM-104

9 Plasser Quick

Relaying

System

(PQRS)

10 Point And

Crossing

Changing

Machine

(AMECA T-28)

11 Tamping

Express

(09-3X)

12 Track

Relaying

Equipment

(TLE-SIMPLEX)

13 Track

Relaying

Train (TRT)

Page 156: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

148

S.

N.

Name of

Machine

Document Issue

Date

Report

No.

14 Point &

Crossing

Tamping

Machine

(UNIMAT)

15 Unomatic Tie

Tamping

Machine

16 Utility Track

Vehicle

(Phooltas

Make)

17 Worksite

Tamping

Machine

(METEX Make)

18 Worksite

Tamping

Machine

(8049

Critical Spares Parts

list of Track Relaying

Train

Inspection Check List

Maintenance

Schedule

Trouble-Shooting

Manual

List of Critical Spare

Parts

Inspection Check List

Maintenance

Schedule

Trouble-Shooting

Manual

Inspection Check List

Maintenance

Schedule

Critical Spares Parts

Inspection Check List

Maintenance

Schedule

Inspection Check List

Maintenance

Schedule

Dec. 2014

Sept.2004

Jun.2013

Mar.2006

Aug.2004

Dec.2004

May.2005

Jul.2005

Jun.2009

Jun.2008

Jul.2014

Aug.2010

Jun.2010

Mar.2009

Mar.2009

CSP

TM-71

TM-175

TM-99

CSP

TM-76

TM-83

TM-88

TM-132

TM-121

CSP

TM-144

TM-141

TM-129

TM-130

Page 157: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

149

Onwards)

19 UNIMAT-4S

20 Rail Grinding

Machine

21 Ballast

Cleaning

Machine

(BCM-RM-80-

92U)

22 Worksite

Tamping

MachineVPR-

02M

(Kalugaputmash

Make)

23 Inspection

Check List

Trouble-Shooting

Manual

List of Critical Spare

Parts

Maintenance

Schedule

Inspection Check List

Critical Spares Part

list of Unimat-4S

Maintenance

Schedule

Maintenance

Schedule

List of Critical Spare

Parts

Inspection Check List

Inspection Check List

Maintenance

Schedule

INSPECTION OF

UNIMAT-SPLIT HEAD

MFI

Feb.2008

2013-14

May-12

Dec. 2014

Apr-15

Jan. 2014

Feb. 2014

Nov.2013

Mar- 2015

Mar-15

Mar-15

Aug-15

TM-117

CSP

TM-168

TM-169Rev.1

CSP

TM-180

TM -178

CSP

TM-186

TM-183

TM-187

TM-184

S.

N.

Name of

Machine

Document Issue

Date

Report

No.

Page 158: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

150

H. Check list for Inspection of Concrete Sleeper Plant:

Ref: IRS-T-39 August 2011, IRS-T-45- 1996 and Schedule of Technical

Requirement (STR) issued by Rly. Bd. Vide letter no. 2010/Track-II/22/

11/4 (STR) dtd 27-5-2011

A About Plant

1 Whether plant is approved for production?

2 Whether plant is approved for production of 1 in 8.5

T/out sleepers?

3 Whether plant is approved for production of 1 in 12

T/out sleepers?

4 Whether plant is approved for production of any

other type of sleepers?

B Quality Assurance Plan & ISO Certification

5 Whether QAP is approved by RDSO?

6 Whether Plant is having ISO: 9001-2008?

C About Organisation

7 Whether plant is having at least one Graduate Civil

Engineer?

8 Whether plant is having at least one Diploma Civil

Engineer for each shift per casting shed?

9 Whether plant is having one Mechanical/Electrical

diploma Engineer for maintenance of equipments?

S. Item Remark

N.

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Page 159: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

151

S. Item Remark

N.

D Layout Requirement

10 Whether Cement godown capacity is as per STR?

(Minimum covered area 576 Sqm.)

11 Whether HTS storage capacity is as per STR?

(Minimum covered area 100 Sqm.)

12 Whether Insert godown capacity is as per STR?

(Minimum covered area 100 Sqm)

13 Whether Steam curing chambers numbers and

capacity are as per STR?

14 Whether Submerged water curing tank numbers and

capacity are as per STR?

15 Whether Stacking area for finished sleepers is as per

STR?

16 Is Area of Laboratory is as per STR? (General- 40 Sqm.

& sleeper testing-30 Sqm.)

17 Whether Lab is climate controlled?

18 For inspection of turnout sleeper set- Whether

minimum two platforms of 70 x 6m with gantry

arrangements for handling of inspection of two sets

at a time is available?

19 Minimum requirements of Plant and Machinery as

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Page 160: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

152

S. Item Remark

N.

Yes/Noper STR for production line are available or not?

20 Whether Laboratory equipments are available as

per STR?

E Raw Material Details :

E1 Cement

21 Whether current cement source is approved by

RDSO?

Name of Supplier:___________________.

22 Whether stacking of cement is as per IS code?

23 Whether placards are displaying week number,

name of manufacturer?

24 Whether cement is being used on “first in first out”

basis?

25 Whether manufacture’s test certificate is available?

E2 HTS Wire

26 Whether HTS wire is procured from BIS approved

source?

27 Whether HTS wire is inspected by railway’s

inspecting Authority?

28 Whether HTS wire coils are wrapped in Jute/plastic

cloths?

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Page 161: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

153

S. Item Remark

N.

Yes/No29 Whether Manufacture’s tag & seal of Inspecting

Authority available on coils?

30 Whether HTS wire coils are stacked in covered

godown?

E3 Aggregates (CA1 & CA2)

31 Whether source is approved by RDSO?

E4 Inserts

32 Whether Inserts are being procured from RDSO

approved source?

33 Whether Inserts are inspected by RITES with lead seal

on every bag?

34 Whether dimensional checking of each & every

inserts is done before use in Plant?

35 Whether Inserts are stacked in covered godown /

heat no wise& supplier wise?

E5 PVC Dowel

36 Whether PVC Dowels are procured from RDSO

approved source?

37 Whether PVC Dowels are inspected by RDSO?

F Production Shed

38 Whether regular cleaning of mould’s by cup wired

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Page 162: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

154

S. Item Remark

N.

Yes/Nobrush is being done before use?

39 Filling of black putty for sealing the gap between end

plates & mould is being done properly or not?

40 Whether Greasing for inserts pockets in moulds is

done?

41 Whether labours are doing hand pulling of HTS wire

for removal of sag before tensioning?

42 Is Calibration of tensioning m/c as per schedule being

done?

43 Whether Tensioning m/c is equipped with auto cut-

off?

44 Whether tensioning supervisor is measuring the

elongation of HTS wire of each & every bench and

entering it in register regularly?

45 Whether Calibration of bottom vibrators as per

schedule is done?

46 Whether Calibration of automatic batching plant as

per schedule is done?

47 Whether Pouring of cement in mixture is through

screw conveyor?

48 Whether calibration of thermometers of steam

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Page 163: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

155

chambers as per schedule being carried out?

49 Whether Keeping & maintaining half hourly record

of temperature of each & every chambers by

supervisor, as per steam cycle?

50 De-tensioning of benches after required release

strength is done or not?

51 Whether Paint marking of batch no and date of

casting on every demoulded sleeper is done?

52 Whether end painting of every demoulded sleeper

before submerged for curing is done?

53 Whether casted sleeper in submerged water curing

tanks are kept in layer wise just after demoulding?

54 Whether stacking of sleepers is batch wise & type

wise (not more than 25 layers in each stack) in

stacking yard?

55 2nd coat end painting of sleepers after submerged

water curing

56 Is Critical dimensional checking of sleepers done

completely? (100 %)

57 Is 10% General dimensional checking of sleepers

done?

S. Item Remark

N.

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Page 164: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

156

58 FTC checking of sleepers done or not?

G Record Keeping & Documentation

59 Whether Lab tests of raw materials are being done?

60 Whether Production registers maintained properly?

61 Whether Inspection certificates of raw materials

available?

62 Whether Steam curing records available?

63 Whether Dimensional checking register of sleepers

updated?

64 Whether Dimensional checking of moulds & benches.

Its repair register is maintained properly?

65 Whether Calibration of Machines, pressure gauges

& Proving rings is done?

66 SBT testing of sleepers, 15days water cured cubes

and released cubes register is maintained upto date?

67 Whether Statistical analysis report register is

available?

S. Item Remark

N.

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Page 165: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

157

1 Whether the bridge is Minor

(Individual span < 12 m & Total Linear

Waterway < 18 m)? Span=………m

2 Whether the bridge is Major

(Individual span >12 m or Total Linear

Waterway > 18 m)?

Span=………m

3 Whether the bridge is Important

bridge (Total Linear waterway 300 m

OR Total Waterway 1000 m2 OR those

classified as "IMPORTANT BY CE/CBE")?

Span=………m

4 Whether the date of Inspection is

indicated on the bridge?

If so, what is Last date of Inspection?

Date=…………

5 Whether the date of Painting is

indicated on the bridge? If so, what

is Last date of Painting? Date→

6 Whether the date of Cleaning &

Greasing is indicated on the bridge?

If so, what is Last date of Cleaning &

Greasing? Date→

I. CHECK LIST FOR BRIDGE & TUNNEL:

S. Description Remarks Reference

N.

Yes/No IRBM-1103

(3) (c)

IRBM-1103

(3) (b)

IRBM-1103

(3) (a)

IRBM-203 (1)

IRBM-203 (1)

IRBM-1107

(4) (v)

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Page 166: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

158

S. Description Remarks Reference

N.

Yes/No

Yes/No

7 Whether the date of lubrication of

bearing is indicated on the bridge?

If so, Last date of lubrication done?

Date=…………

8 Whether bridge / FOB is over railway track,

whether clearances are as per SOD?

If so, what is the vertical clearance

(5870 mm / 6350 mm)?

Vertical clearance=……………………

9 What is the clear horizontal distance

between respective centre of track and

any other structure (limiting value

2135 mm)?

10 Whether Trolley refuge is provided?

If so, Nos. required ______________ and

Nos. provided ____________.

11 Whether creep of bridge girder is

notice?

12 Whether condition of the footpath is

good?

13 Whether condition of drainage

arrangement is good?

14 Whether the Camber has been

recorded at the time of Inspection?

IRBM-1107

(4) (v)

SOD CH-

1(10) (iii)

IRBM-1107

(14) (a) (ii)

SOD CH-1 (8)

IRBM- 1107

(8)

------

IRBM-1107

(9)

IRBM-210

(2)

IRBM-212

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Page 167: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

159

S. Description Remarks Reference

N.

.....mm

If so, What is the method of recording

Camber?

What is the Camber

a) As per Drawing?

b) As per time of Last inspection?

c) At the time of Present Inspection?

15 Whether the bridge is to be inspected

at increased frequency?

If so, What is the frequency?

16 Whether the entries are made in

Bridge history Book?

17 Whether the Steel members are free

from distortion?

18 Whether the Steel members are free

from Corrosion?

19 Percentage of Defective, Broken,

Loose, Corroded & Badly Driven rivets

a) Boom Flanges

b) Web

c) Main Joints

d) Cross Girders

IRBM-1107

(15) (b)

IRBM-107

(1)

IRBM-107

(2)

IRBM-1107

(5)(c)

IRBM-216

.....mm

.....mm

Yes/No

Yes/No

Yes/No

Yes/No

.....%

.....%

.....%

.....%

Page 168: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

160

S. Description Remarks Reference

N.

Yes/No

e) Stringers

f) Bracing& Foot Path

g) Base Plate

20 Whether any member of steel girder

is overstressed? (As advised by CBE)

21 Whether steel members are free from

cracks?

22 Whether Early steel girder floor

system is inspected once in a year?

If so, what is the Last inspection

date? →

23 Whether Welded girder is inspected

once in a three years?

If so,what is the last inspection date?→

24 Whether proper scraping done

wherever required?

25 Whether there is any local or uniform

corrosion over large area?

26 Whether some pitting/corrosion is

formed?

If so, Location of Pitting/ corrosion?

27 Whether the average thickness of

paint film is as per following

IRBM-215

(3)

IRBM-212

(a)

IRBM-213

(1)

IRBM-107

(1) (c),

1102-(1) (e)

IRBM-1102-

(1) b

IRBM-217-

(1) b

IRBM-216-

(3) (i)

IRBM-216-

(3) (ii),

1107 (5) (f)

(xvii)

IRBM-218-

(1) (ii) (b)

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

.....%

.....%

.....%

Page 169: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

161

S. Description Remarks Reference

N.

Yes/No

requirement?

a) Metalising (150 Micron)

b) Epoxy Painting (200 Micron)

28 Whether the Painting has been done

as per schedule (1 to 6 years)?

If so, What is the last date of Painting?

29 Whether all Holding Down (HD) Bolts

are intact?

What is the percentage of intact bolts

per bearing?

30 Whether locking strips and guide strips

are in good condition?

31 Whether bearing strip butts with

locking strip?

32 Whether schedule of greasing (once in

3 years) of bearings has been carried

out?

Date of greasing…………….

33 Whether there are any cracks in

Knuckle slab, Saddle Plate and Roller?

34 Whether bearing is centralized?

35 Whether replacement of oil in oil bath

bearing is done? (once in 5 yrs)

IRBM-218-

(2) (ii)

IRBM-217-

(5)

IRBM-1107-

(4)(ii)

------

------

IRBM-222-

(2) (a)

BS-102-

(3.2.3.1)

------

IRBM-222-

(2) (f)

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

-----------

------%

Page 170: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

162

S. Description Remarks Reference

N.

Yes/No

Yes/No

Date of oil replacement…………….

36 Whether connection of saddle plate

with bottom boom is intact?

37 Whether condition of elastomeric

bearing is examined?

If so, than

a) Is shear deformation more than

50% of height of pads?

b) Is compression more than 5% of the

height of Pads?

c) While in rotation any loss of contact

between bearing and girder?

38 Whether any tilting/settlement is

reflected in cracks in substructure?

39 Whether there is any unusual scour

around the piers?

40 Whether water way is free from

obstruction?

41 Whether flooring, drop wall & curtain

wall are provided?

What is the condition of componenet?

42 Whether (for foundation perennially

underwater) underwater inspection

------

BS-102-

(3.5.3)

IRBM-1107

(1) (a) (ii)

IRBM-

1107(1) (a) (i)

IRBM-117(1)

(f) IRBM-

1107(3)(ii)

IRBM-

1107(1) (b)

IRBM-

1107(2) (d)

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Page 171: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

163

S. Description Remarks Reference

N.

Yes/No

done?

Date of inspection--_______________

43 Whether the Pitching of Guide bund/

groins is intact?

44 Whether there is any erosion of bank

in the vicinity of abutment?

45 Whether there is any displaced / crack

in bed block?

46 Whether any bed block is shaken?

47 Whether there is any crushing mark

under bed plate?

48 Whether any inspection platform is

available?

49 Whether there is any crack in masonry?

50 If yes, whether the crack is progressive?

51 Whether there is any weathering and

leaching of mortar?

52 Whether there is any vegetation

growth in masonry?

53 Whether there is any crack in

abutment face?

IRBM-809 (4)

(a)IRBM-

1107(3) (a)

IRBM-1107

(1)(a)

IRBM-(221)

(514)

IRBM-1107

(4/a/iii)

IRBM-

1107(1) (a)

IRBM-1107-

(2) (a)

IRBM-1107-

(2)

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Page 172: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

164

54 Whether backfill materials are intact

in case of horizontal crack on abutment

face?

55 Whether any bulging/tilting is noticed

in ballast wall on abutment?

56 Whether there is Highest Flood Level

(HFL) with year & Danger Level (D L)

marking in abutments and gauge

marking on shore piers on important

bridges?

57 Whether bridge tablet is showing

direction of flow, Bridge Number, span

arrangement, Rail level etc. has been

provided?

58 Whether ballast retainer is leaning?

59 Whether cracks in Arch Barrel with

special reference to its direction of

propagation & length of the crack

observed?

60 Whether any cracks in the intrados are

observed to be propagating in

transverse direction i.e. direction

perpendicular to traffic?

61 Whether immediate rehabilitation

measures for repair of cracks in the

intrados planned & such cracks have

been kept under close observation?

S. Description Remarks Reference

N.

IRBM-1107-

(2)

IRBM-1107-

(10) & 203

(2 & 3)

IRBM-

1107(10) d,

f, h & 203 (2

to 9)

------

IRBM-208-

(1) (i)

IRBM-

1107(2) (e)

IRBM-208-

(1) (ii)

IRBM-

1107(2) (e)

IRBM-209

IRBM-

1107(2) (e)

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Page 173: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

165

62 Whether crushing of masonry of Arch,

loosening of Key stone etc. noticed?

63 Whether any leaning of Parapet wall

noticed and weep holes in Parapet wall

are cleared?

64 Whether any tell-tale marks of repairs

earlier conducted?

65 Whether there are any loose boulders

at tunnel approaches & cutting and

major discontinuities?

66 Whether any weep holes are choked

in retaining walls and side drains?

67 Whether any tree is precariously

standing on the top of approach cutting

and slopes?

68 Are catch water drains on the

approaches and on the top of tunnel

cleaned?

69 Whether any portal has cracks in the

masonry or has shaken bulging

masonry?

S. Description Remarks Reference

N.

IRBM-208-

(1), (iv).IRBM-

1107(2) (e)

(viii)

IRBM-208-

(3)

IRBM-1107

(2) (e) (xi)

IRBM-1107

(2) (c)

IRBM-1007

(2)

IRBM-1012

IRBM-1008

(1.4)

IRBM-1012

IRBM-1007

(2) & para

1012 (5)

IRBM-1007

(2)

IRBM-1007

(2)

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Page 174: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

166

70 Whether there are any loose boulders

in tunnel wall and roofing?

71 Whether there is any seepage inside

tunnel through rock joints in tunnel

wall and roof noticed?

72 Whether side drain and drainage inside

the tunnel is clean?

Whether ventilation shafts and adits,

are free from vegetation?

Whether there is any water logged area

near heavy seepage zone of tunnel?

73 Whether all fittings of steel sleepers

and rails particularly in heavy seepage

zone are intact?

74 Whether any infringements in moving

dimension are noticed?

75 Whether tablets on top of tunnel at

entrance indicating length, year of

construction and other information

are available?

76 Are water-ways clear at the bridge?

77 Whether SWR is continued over bridge

(span< 13.1 m), what is actual span?

78 Is any fish plate joint is on bridge or

within 6 M. of abutment? (None

allowed)

S. Description Remarks Reference

N.

IRBM-1007

(4, 2)

IRBM-1007

(4)

IRBM-1007

(5, 6, 7)

IRBM-1007

(9)

IRBM-1007

(3)

IRBM-1003

IRPWM-723 (2)

IRPWM Para

272 (4)

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Page 175: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

167

79 For 26 m long rolled rails, whether 1 m

long fish plates with 6 bolts are

provided.

80 Whether permissible gaps at joints (as

per Zone and temperature range) are

given?

81 Is there any creep at joints noticed? If

yes,

LH side

RH side

82 Whether at approach two well

anchored standard rail lengths are

provided?

83 Whether LWR is continuing on the

bridge (span ≤ 20 m, 20 m to 43 m, >43

m), what is actual span?

84 a) Whether rail free fastenings are

provided from pier to pier with SEJ?

b) Whether SEJ is provided at the far

end of the bridge?

85 Whether all the provisions of LWR

manual were followed in continuing

LWR on the bridge?

S. Description Remarks Reference

N.

C/slip No.

125 & Para

272(4/a) of

IRPWM

IRPWM Para

510(3)

IRPWM Para

No.272 (6)

Para No.

272 (6) of

IRPWM

Para No.

272 (5) of

IRPWM

.....mm

Yes/No

Yes/No

.....mm

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Page 176: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

168

86 C/C spacing between sleepers (450

mm), what is actual value?

87 Clear spacing between sleepers.

88 Whether guard rail are provided on

girder bridges?

89 Clearance between guard rail and

running rail?

(250+50/ 250-50 mm)

90 Straight length of guard rail beyond the

span L1 (1875 mm)?

91 Length of flared portion of guard rail L2

(4875 mm)?

92 How much below is the top table of

guard rail from top of running rail (< 25

mm)?

93 Whether the ends of guard rails are

vertically bent and buried and block of

timber is provided

94 Whether pathway has been provided

at the centre of the track with

chequered plates?

95 Whether all AT welds on bridge as well

as on approaches of 100 M of both ends

S. Description Remarks Reference

N.

C/slip No.

102 & para

273 (B/iii) of

IRPWM

IRPWM Para

no.275

IRPWM Para

no.275/2

IRPWM C/

slip No. 102

C/slip No.

131 of

IRPWM

Yes/No

......mm

Yes/No

Yes/No

Yes/No

Yes/No

-----mm

-----mm

-----mm

-----mm

Page 177: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

169

are provided with joggled fish plates

and clamps or with fish bolts at two far

end bolts?

96 Whether trolley refuses are provided?

(at every 100 m or on every pier)

97 Whether track Parameters like gauge,

cross level, cant, versines are within limits?

98 Whether condition of track fittings and

their tightness, particularly rubber

pads in case of steel channel sleeper

are good?

99 Whether guard rail are bent down in

the ballast at approach?

100 Whether tightness and correct osition

of lips of hook bolts checked by actually

touching with hand?

101 Whether steps are provided for

inspection of bridge?

102 Whether anti sabotage/theft fittings

are provided on the bridge?

103 Whether zero toe load track fastening

(rail free fastening) of LWR on bridge

and box anchoring of 2 to 4 sleepers in

the Centre of girders are provided as

per LWR manual?

104 Whether arrow mark of hook bolts is

aiming towards c/l of track?Percentage of hook bolts not holding

flange of girder--_______ .

S. Description Remarks Reference

N.

CS No. 119 of

IRPWM

IRBM-1107-

(7) (g) (i)

------

IRBM-1107-

(e) iii

IRBM-1107-

(c)

------

------

------

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Page 178: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

170

J. ITEMS PERTAINIG TO PASSAENGERS AMMINITIES

A. ADARSH STATION.

Ref: Commercial circular no 50 of 2013 circulated vide Rly Bd.’s Letter

no. 2009/TG-IV/10/PA/Adarsh Stns dated. 13-08-2013.

1. FACILITIES AT ADARSH STATIONS (‘A1, A, B & C’ CATEGORY)

1 Whether improvements in facade of station building

are done?

2 Whether retiring room available? (Except ‘C’

category, for ‘B’ category GM can sanction based on

need & demand)

3 Whether waiting room (with bathing facility)

available for upper class with TV? ( Except ‘B’ & ‘C’

category)

4 Whether waiting room (with bathing facility)

available for other classes with TV? ( Except ‘C’

category)

5 Whether separate ladies waiting room (with bathing

facility) available? (Except ‘B & C’ category)

6 Whether cloak room available? (Except ‘C’ category,

for ‘B’ category GM can sanction based on need &

demand)

7 Whether computer based public address system is

available?

S. Item to be Inspected REMARK

N.

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Page 179: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

171

S. Item to be Inspected REMARK

N.

8 Whether circulating area is available with

necessary lighting?

(refer Table at Pg. no.186,187 for required

illumination level)

9 Whether landscaping and circulating area is

available? (If space is available)(Except ‘C’ category)

10 Whether earmarked parking is available?

11 Whether prepaid taxi/radio taxi booth available?

(Except ‘B & C’ category)

12 Whether electronic train indicator board/ plasma

TV train indicator system is available?

13 Whether lifts/escalator (if feasible) is available?

(Except ‘B’ & for ‘C’ category, GM can sanction based

on need & demand)

14 Whether standard signage are available?

15 Whether ‘Pay & Use’ toilets are available in

circulating area/ concourse area? (If not feasible,

departmental toilets are to be provided)

16 Whether ‘High level’ platforms are available?

17 Whether air conditioned VIP lounge is available?

(Only for ‘A1’ category)

18 Whether coach indicator board is available? (Only

for ‘A1’ & ‘A’ category)

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Page 180: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

172

19 Whether FOB is available? (For ‘C’ category – Wider FOB)

20 Whether ‘water coolers’ are available?

21 Whether ‘PRS’ is available? ( Except ‘C’ category)

22 Whether ‘UTS’ is available?

23 Whether energy efficient, adequate lighting is

available on platform. FOB, circulating and

concourse etc.? (Refer table at Pg. no.186,187 for

required illumination level)

24 Whether ‘Battery car’ is available? (Only for ‘A1’

category)

25 Whether ramp at entry to station for PH and Sr.

citizens is available?

26 Whether separate parking for disabled person is

available?

27 Whether ‘Non slippery’ walkway from parking lot to

station building is available?

28 Whether toilet for PH is available?

29 Whether ‘May I help you’ booth is available?

30 Whether trolley path/end pathway for inter platform

movement of wheel chair for PH is available?

31 Whether ‘Wheel chair’ is available?

32 Whether mobile charging points are available? (If

electric power is available).

S. Item to be Inspected REMARK

N.

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Page 181: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

173

2. FACILITIES AT ADARSH STATIONS (‘D & E’ CATEGORY)

1 Whether suitable face lift given to station building?

2 Whether waiting room for other than upper classes

(without bathing facility) is available? (For ‘D’

category only and for ‘E’ category seating cluster/

enclosure on main platform)

3 Whether computer based public address system is

available? (For ‘D’ category only)

4 Whether circulating area is available with necessary

lighting? (For ‘D’ category only)

(refer Table at Pg. no.186,187 for required

illumination level)

5 Whether landscaping and circulating area is

available? (If space is available)

6 Whether earmarked parking is available? (For ‘D’

category only)

7 Whether standard signage are available?

8 Whether ‘Pay & Use’ toilets are available in

circulating area/ concourse area? (If not feasible,

deptt. toilets are to be provided)

9 Whether high level for category ‘D’ and medium level

for category ‘E’ platforms are available?

10 Whether FOB is available?

S. Item to be Inspected REMARK

N.

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Page 182: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

174

S. Item to be Inspected REMARK

N.

11 Whether ‘water coolers’ are available?

12 Whether ‘UTS cum PRS’ is available?

(for category ‘E’ GM can sanction based on need &

demand)

13 Whether energy efficient, adequate lighting is

available on platform. FOB, circulating and

concourse etc.? (Refer table at Pg. no.186,187 for

required illumination level)

14 Whether ramp at entry to station for PH and

Sr.citizens is available?

15 Whether separate parking for disabled person is

available?(For ‘D’ category only)

16 Whether ‘Non slippery’ walkway from parking lot to

station building is available? (For ‘D’ category only)

17 Whether trolley path/end pathway for inter platform

movement of wheel chair for PH is available?

18 Whether ‘Wheel chair’ is available?

19 Whether mobile charging points are available?

(If electric power is available).

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Page 183: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

175

B. FACILITIES AT STATION NOMINATED AS MODEL STATION

1. For categories ‘A1, A & B’

Ref: Comprehensive instructions issued by Rly. Board vide letter no.

2012/LM (PA)/3/5 dated 11-09-2012.

1 Whether Retiring Rooms are provided?

2 Whether Waiting Rooms with bathing facilities are

provided?

a . Upper class (Except ‘B’ category)

b. 2nd Class

c. Separate For ladies (Combined upper & 2nd Class)

(Except ‘B’ category)

3 Whether Cloak Room is provided?

4 Whether enquiry & computer based announcement

is provided?

5 Whether National Trains Enquiry System (NTES) is

provided? (Except ‘B’ category)

6 Whether Interactive Voice Response System (IVRS)

is provided?

7 Whether Public Address System is provided?

8 Whether Book Stalls / other stalls of essential goods

are provided?

9 Whether Refreshment Room is provided?

S. Item to be Inspected REMARK

N.

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Page 184: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

176

S. Item to be Inspected REMARK

N.

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

10 Whether Parking / Circulatory Area is provided?

(High mast with light is to be provided if feasible)

11 Whether washable apron with jet cleaning machines

are provided?

12 Whether electronic train indicator boards are

provided?

13 Whether touch screen enquiry system is provided?

14 Whether watering vending machines are provided?

(Optional for category ‘A & B’)

15 Whether FOB is provided?

16 Whether escalator is provided? (Except category ‘B’)

17 Whether travellator is provided?

(Except category ‘B’)

(Subject to space available and feasibility)

18 Whether standardized signage are provided?

19 Whether modular catering stalls are provided?

20 Whether automatic vending machines are provided?

(Optional for category ‘A & B’)

21 Whether pay & use toilets are provided on platforms

and circulating area?

22 Whether cyber cafes are provided?

(Except category ‘A & B’, subject to space available

and feasibility)

Yes/No

Yes/No

Page 185: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

177

S. Item to be Inspected REMARK

N.

23 Whether ATMs, preferably with ticketing facilities

have been provided?

24 Whether at least one AC VIP/Executive lounge is

provided? (Except category ‘A & B’)

25 Whether Food Plaza is provided? (Except category ‘A

& B’)

26 Whether train coach indication system is provided?

(Except category ‘A & B’)

27 Whether Close Circuit Television (CCTV) for

announcement and security purpose is provided?

(Except category ‘A & B’)

28 Whether coin operated ticket vending machines are

provided?

29 Whether pre-paid taxi service facility is provided?

(Only at category ‘A1’ with GM’s approval)

30 Whether high level platforms available?

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Page 186: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

178

C. MINIMUM ESSENTIAL AMENITIES AT STATIONS OF

DIFFERENT CATEGORIES.

Ref: Comprehensive instructions issued by Rly. Board vide letter no.

2012/LM (PA)/3/5 dated 11-09-2012.

1. MINIMUM ESSENTIAL AMENITIES AT ‘A-I & A’ CATEGORY STATION

1 Booking facility

(No. of counters)

(To operate round the

clock except if there

is no night working)

2 UTS

3 Drinking water (on

each platform)

4 Waiting Hall

(marginally lower up

to 5 Sqm allowed)

5 Seating arrangement

(No. of seats per

platform)

6 Platform shelter :

on each platform

Urinals

Yes/NoAs per norms

20 taps

250 Sqm. 125 Sqm.

150 125

500 Sqm. 400 Sqm.

15 10 Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

S.

N.

Facilities As per Norms Facilities

providedA 1 A

Page 187: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

179

7 Urinals

i. includes provision in waiting rooms/hall

ii. 1/3rd to be reserved for ladies. In case of 2 toilets

existing, one each should be earmarked for ladies

and gents

iii. Includes ‘Pay & Use’ toilets also.

8 Latrines

i. includes provision in waiting rooms/hall

ii. 1/3rd to be reserved for ladies. In case of 2 toilets

existing, one each should be earmarked for ladies

and gents

iii. Includes ‘Pay & Use’ toilets also.

12 nos 10 nos

12 nos 10 nos

9 Foot Over Bridge

(with cover, new FOB-

minimum width 6m)

10 Water Cooler

11 Signage

12 Platform

Minimum one FOB

per station

Two on each platform

As per standard (Refer

Railway Board’s circular No.

97/TG II/39/11/signage dated

11.03.99)

All platforms should be of

high level

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

S.

N.

Facilities As per Norms Facilities

providedA 1 A

Page 188: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

180

14 Fans

15 Time Table Display

16 Clock

17 Public address

system/ Computer

based announcements

18 Parking cum

circulatory area ,

with lights

19 Electronic train

indicator board

20 Public phone booth

One row of fans/Bay of COP

for 6 to 9 m wide shed.

Two rows of fans/Bay of COP

for shed wider than 9 m.

Yes/No

As per extent instructions Yes/No

Yes/No

As decided by Zonal Rlys.

Yes/No

As per extent instructions

Yes/No

As per extent instructions

At station entrance/

concourse, on foot over

bridge (At landing location)

and on platform at suitable

locations.

As per extent instructions

Yes/No

Yes/No

As per extent instructions

Refer Rly Bd.’s letter no.

2004/Elec (G)/109/1 dated

18-05-2007 – Extract at Pg.

no.186,187

Yes/No13 Ligting

Yes/No

S.

N.

Facilities As per Norms Facilities

providedA 1 A

Page 189: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

181

2. MINIMUM ESSENTIAL AMENITIES AT ‘B, C & D’ CATEGORY

STATION

S.

N.

1 Booking facility -

(No. of Counters)

(To operate round the

clock except if there

is no night working)

2 UTS

3 Drinking water (taps

on each platform)

4 Waiting Hall

(marginally lower up

to 5 Sqm allowed)

5 Seating arrangement

(seats per platform)

6 Platform shelter (on

each platform)

7 Urinals

Yes/No

Facilities As per Norms Facilities

providedB C D

6 4 4

As per norms Yes/No

20 nos 06 nos 08 nos Yes/No

75 Sqm NIL 30 Sqm.

100 10 50

200 Sqm 200 Sqm 50 Sqm

6 nos 4 nos 4 nos

Yes/No

Yes/No

Yes/No

Yes/No

i. includes provision in waiting rooms / hall

ii. 1/3rd to be reserved for ladies. In case of 2 toilets

existing, one each should be earmarked for

ladies and gents

iii. Includes ‘Pay & Use’ toilets also.

8 Ltrines(Nos) 6 2 4 Yes/No

Page 190: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

182

Yes/No

02

i. includes provision in waiting rooms / hall

ii. 1/3rd to be reserved for ladies. In case of 2 toilets

existing, one each should be earmarked for

ladies and gents

iii. Includes ‘Pay & Use’ toilets also.

9 Foot Over Bridge Minimum one FOB

per station

1. New FOB-minimum width 6m.

2. For ‘D’ category FOB to be provided during

doubling/Gauge conversion for crossing

stations.

10 Water Cooler - on

each platform.

Ref: Rly Bd.’s letter

no. 69/Elect (g)/730/8

dt.30-03-1971.

11 Signage (Refer

Railway Board’s

circular No. 97/TG II/

39/11/signage dated

11.03.99)

12 Platform (Level)

13 Lighting

02 01 Yes/No

As per standerd

(Expect ‘C & D’ category)

Yes/No

Medium High Medium Yes/No

Ref: Rly Bd.’s letter no. 2004/

Elect(G)/109/1 dated 18-05-

2007 , extract at page no.

186,187

Yes/No

S.

N.

Facilities As per Norms Facilities

providedB C D

Page 191: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

183

S.

N.

Facilities As per Norms Facilities

providedB C D

14 Fans

15 Time Table Display

16 Clock

17 Public address

system/ Computer

based

announcements

One row of fans/Bay of COP

for 6 to 9 m wide shed.

Two rows of fans/Bay of COP

for shed wider than 9 m.

As per extent instructions

As decided by Zonal Rlys.

As per extent instructions

(Except ‘C & D’ category)

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

3. MINIMUM ESSENTIAL AMENITIES AT ‘E & F’ CATEGORY

STATION

As per Norms Facilities

providedFacilitiesS.

N.

1 Booking facility – (No.

of counters)02 01

To operate round the clock except if there is no night

working.

2 UTS

3 Drinking water- nos of

taps on each platform

As per norms NIL Yes/No

If piped water is not available separate

arrangement of potable water as approved by GM,

to be made.

02 Appropriate

facility

4 Waiting Hall 15 Sqm 10 Sqm

Yes/No

Yes/No

Yes/No

Page 192: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

184

7 Urinals

10

Yes/No

NIL

50 Sqm (Min.) Shady trees

1 no. NIL

i. includes provision in waiting rooms / hall

ii 1/3rd to be reserved for ladies. In case of 2 toilets

existing, one each should be earmarked for ladies

and gents

iii Includes ‘Pay & Use’ toilets also.

8 Latrines Yes/No1 Number NIL

i. includes provision in waiting rooms / hall

ii 1/3rd to be reserved for ladies. In case of 2 toilets

existing, one each should be earmarked for ladies

and gents

iii Includes ‘Pay & Use’ toilets also.

9 Platform

10 Lighting

11 Fans

Rail level Yes/No

Ref: Rly Bd.’s letter no. 2004/

Elec (G)/109/1 dated 18-05-

2007, extract at Pg. no.186,187

One row of fans/

Bay of COP for 6

to 9 m wide

shed.

Two rows of

fans/Bay of COP

for shed wider

than 9 m.

NIL

Yes/No

Yes/No

NIL Yes/No

Yes/No

Yes/No

5 Seating

arrangement (No of

seats per platform)

6 Platform shelter

S.

N.

Facilities As per Norms Facilities

providedB C D

Page 193: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

185

12 Time Table Display As per extent instructions Yes/No

13 Clock As Decided by Zonal Rlys. Yes/No

1 Concourse

2 Circulating area

3 Waiting Hall

4 Retiring Room

5 Platform

a. Open

b. Covered

6 Enquiry cum Reservation office

a . General

b. Counter

7 Covered Passage way

a . Corridors

b. FOB

c. Stairs

Extract of Rly Bd.’s letter no. 2004/Elec (G)/109/1 dated

18-05-2007: Lighting arrangement at different areas:-

S.

N

Lux

level

Location

100

30

100

100

30

100

100

150

50

50

50

S.

N.

Facilities As per Norms Facilities

providedB C D

Page 194: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

186

S.

N.

Facilities As per Norms Facilities

providedB C D

8 Parcel/luggage office

a . General

b. Counter

9 Time table- using task lighting

10 Outdoor car parking

11 Restaurant area

a . Kitchen

b. Stores

c. Dining Hall

12 Other service buildings at station

13 Cloak Room

a. General

b. Counter- using task lighting

14 Public Utility Services - Toilet/ Bathroom

100

150

200

30

150

100

150

200

100

150

75

Page 195: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

187

K. ITEMS PERTAINIG TO COLONY AND OTHER BUILDINGS

Ref: Rly Bd.’s letter no. 2014/LMB-II/1/1 dated 25-07-

2014 and 2014/LMB-II/1/1 (A) dated 25-07-2014.

(A) COLONY INSPECTION BY ‘COLONY INSPECTION GROUP

(CIG)’

1. General:

S.

N.

1 Whether ‘CIG’ formulated as per latest

instructions?

2 Whether ‘CIG’ inspection & meetings are held

regularly once in THREE months?

3 Artisans training: Initial and refresher arranged

regularly?

4 Whether modern tools & equipment are available

with artisans?

5 Whether standard ‘Tool kit ’ is available with

artisans?

6 Whether ‘Valve’ operation is automised?

7 Whether old quarters, planned for replacement has

been inspected thoroughly and it has been ensured

that repair is not economical?

Yes/No

Particular Remarks

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

2. Items to be inspected by ‘COLONY INSPECTION GROUP (CIG)’:

S.

N.

1 Whether Cleanliness of colony is upto mark? Yes/No

Particular Remarks

Page 196: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

188

2 Whether quarters are maintained in sound

condition having structural integrity?

3 Whether leaky roofs are attended properly?

4 Whether outside door & windows are maintained

properly?

5 Whether water supply is maintained properly?

6 Whether sanitation and drainage arrangements

are maintained properly?

7 Whether repair to floors is done properly?

8 Whether repairs to pathways is done properly?

9 Whether repairs to fencing and other items is done

properly?

10 Whether improvement of substandard quarters

done?

11 Whether disposal of waste from colony is arranged

properly?

12 Whether encroachment is prevented properly?

13 Whether cattle nuisance is prevented properly?

14 Whether subletting of quarters is checked &

prevented properly?

15 Whether security arrangements for colony are

proper?

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

S.

N.

Particular Remarks

Page 197: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

189

(B) MAINTENANCE SCHEDULE FOR STAFF QTRS. AND COLONY:

1. Schedule for finishing items: For type II to V Qtrs.

S.

N.

1 Whether exterior colour washing & Interior white

washing including ceiling done once in a year?

2 Whether white washing of Kitchen & pantry done

once in a year?

3 Whether painting with plaster paint, synthetic

enamel, Oil bound distemper, acrylic paint and

acrylic distemper done once in TWO years?

4 Whether polishing/painting of interior wood work

and painting of steel work done once in THREE years?

5 Whether premix, semi dense carpeting of roads

done once in FIVE years?

6 Whether collection of water samples and analysis

done for:

a . Physical & bacteriological test – Every month.

b. For chemical test – Six monthly.

Yes/No

Particular Remarks

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

2. Schedule for sanitation items: For residential buildings

and colonies:

S.

N.

1 Whether cleaning and disinfection of water

storage/distribution tanks & water mains done

once in SIX months?

Yes/No

Particular Remarks

Page 198: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

190

2 Whether cleaning of manholes/gully chambers/

inspection chambers and flushing of building

sewers done once in a YEAR before monsoon?

3 Whether cleaning of storm water drains done once

in a YEAR before monsoon?

4 Whether cleaning of wet drains meant to serve as

quarter drains done at least once in a FORTNIGHT?

5 Whether clearing of rank vegetation done at least

once in a MONTH during monsoon?

6 Whether clearing of rank vegetation done as per

requirement in period other than monsoon?

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

(C) CHECKLIST FOR TAKING OVER BUILDING / QUARTER AFTER

CONSTRUCTION:

S.

N.GENERAL ITEMS

1 Whether proper drains and drain pipes has been

provided for the disposal of water.

2 Whether the surrounding area cleared off, of unused

materials and construction debris/waste etc. ?

3 Whether plinth protection has been provided for

the building?

INSIDE BUILDING ITEMS

WALLS

1 Are there any cracks in walls?

2 Are there any signs of dampness/leakage on walls?

3 Whether finishing of wall surface is smooth and proper?

Yes/No

Description of item Remarks

Yes/No

Yes/No

Yes/No

S.N.

Particular Remarks

Page 199: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

191

FLOORS

1 Are there any cracks in floors, skirting and dado?

2 Are the floors laid to proper slopes?

3 Is there a stagnation of water in WC, bath and verandahs?

4 Whether finishing of floor surface is smooth and proper?

ROOFS

1 Are there any leakages in roofs?

2 Whether ‘Golas’ are properly made?

3 Is the slope of roof proper?

4 Are the traps and rain water pipes proper to drain

water without ponding?

DOORS, WINDOWS AND VENTILATORS

1 Are all the fittings viz. locking arrangement, tower

bolts, pull bolts, door stoppers, hooks, stays and

hinges etc. are provided & functioning properly?

2 Whether quality of wood is as per specification?

3 Whether surface of frame and shutter is smooth?

FINISHING

1 Is the plastering of walls and ceiling satisfactory,

smooth and free from cracks and other defects?

2 Is the painting of walls / doors and windows proper?

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

S.N.

Particular Remarks

Yes/No

Page 200: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

192

WATER SUPPLY AND SANITATION

1 Is there any leakage in the sewer lines, drainage

pipes etc.?

2 Are flushing cisterns, wash basins etc. correctly

fitted and working properly?

3 Are the covers of manholes, gully traps and floor

traps etc. provided?

4 Is the slope of sanitary pipes proper?

5 Is the condition of water overhead tank proper

including float valve & cleaning of tank?

6 Any other deficiency noticed in the building

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

L. ITEMS PERTAINING TO LAND MATTER.

S.

N.

1. Whether village-wise

land records i.e.

Jamabandi, Shajra, and

mutation documents

available?

2 Whether land plans are

authenticated?

3 Whether authenticated

land plans are available

and micro filming done.

Yes/No

Item to be inspected ReferenceRemarks

Yes/No

Yes/No

Para 806 (a) to (c) of

IRWM for Land record

and for micro filming

Para 806 (d)

S.N.

Particular Remarks

Page 201: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

193

S.

N.

Yes/No

Item to be inspected ReferenceRemarks

4 Whether land boundary

post is being provided

at 50 m on either side?

5 Whether within the

boundary, the

demarcation of offsets

is done at change point?

6 Whether land boundary

post is visible?

7 Whether land boundary

post/boundary wall is

missing/damaged?

8 Whether periodical

verification of land

boundary is being done?

9 Whether land boundary

verification registers

are available?

10 Whether there is any

encroachment of

jhuggies /permanent

structures?

11 Is the encroachment

register maintained?

12 Whether any

encroachment has been

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Para 808 (v) of IRWM

Para 809 (b) of IRWM

Para 813 (a to e) of

IRWM

Para 814 (C) of IRWM.

Yes/No Para 814 (e & f) of IRWM

& Ann 8.2

Page 202: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

194

S.

N.

Yes/No

Item to be inspected ReferenceRemarks

dealt under Public

Premises (Eviction of

Unauthorized

occupants) Act (PPE

Act)?

13 Whether any action is

being taken for removal

of encroachment?

14 Whether there is any

case registered in the

Court regarding

encroachments?

15 Whether there is any

unauthorized Religious

structure in the

premises?

16 Whether Religious

structure register is

maintained?

17 Whether track crossing

register is maintained?

18 Whether there is any

unauthorized track

crossing?

19 Whether realization of

way leaves charges

done?

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Para 818 of IRWM

-

-

Para 1033 of ENGG

CODE.

Page 203: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

195

S.

N.

Yes/No

Item to be inspected ReferenceRemarks

20 Whether validity period

of any track crossing

expired?

21 Whether agreements

are available for track

crossing?

22 Is there any private

siding?

23 Are there any

commercial plots?

24 Are there any Shops/

Tehbazari?

25 Whether license fee has

been updated for the

current year?

26 Whether license fee has

been updated on the

basis of market value of

land after 5 years?

27 Whether land is licensed

to Railway Staff for Grow

More Food (GMF)

purposes?

Yes/No

Yes/No

Yes/No

Yes/No

Para 1830 and 1139 of

Engg. Code. OR refer

liberalized siding

policy vide boards

various letters.

Yes/No

Yes/No

Yes/NoYes/No

Para 821 (c) of IRWM.

Para 821 (f) of IRWM.

Refer Rly Bd updated

policy.

No. 2009/LML/16/3

dated 16/07/2010

Para 1033 of

Engg. Code

Page 204: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

196

S.

N.

Yes/No

Item to be inspected ReferenceRemarks

28 Whether any land is

licensed to Container

Corporation of India /

International Container

Depot (CONCOR)?

29 Whether execution of

land license agreement

has been done for all

cases?

30 Whether validity of any

agreement has expired?

31 Whether any tree is

infringing signal / OHE /

track?

32 Whether matured trees

are being processed for

sale?

33 Whether tree register is

maintained?

34 Whether any action has

been initiated for de

notification of protected

forest?

35 Whether master data

entry in land module has

been done or not?

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Refer Rly Bd updated

policy.

Para 715 of IRWM

Para 721 of IRWM.

Para 720 of IRWM

Para 721 (2) of IRWM.

N0.2014/LML-II/2/3

dated 28/07/2014

Page 205: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

197

1. Whether truss/column is in sound condition?

2. If not, whether any remedial action is being taken?

3. Whether the timber is decaying?

3(a) If so, whether any remedial action is being taken?

4. Whether bed blocks or pedestals are in sound

condition?

4(a) If not, whether any remedial action is being taken?

5. Whether all fixtures are intact in bed blocks or

pedestals?

5(a) If not, whether any remedial action is being taken?

6. Whether the condition of paint is in good condition?

6(a) If not, whether any remedial action is being taken?

7. Whether date of painting is mentioned on the

structure?

8. Whether corrosion of steel is taking place?

8(a) If so, whether any remedial action is being taken?

9. In the case of steel work built into masonry, such as

tie rods of arched buildings, whether any corrosion

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

M. STEEL STRUCTURES IN WORKSHOPS, RUNNING SHEDS AND

PLATFORMCOVERS IN WHICH ROOF TRUSSES ARE FIXED

TO BUILT UP STANCHIONS

Ref: Para229 IRWM

Item to be inspected RemarksS.

N.

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/NoYes/No

Yes/No

Yes/No

Yes/No

Page 206: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

198

Yes/No

Yes/No

Yes/No

Item to be inspected RemarksS.

N.

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

is apparent near the masonry?

9(a) If so, whether any remedial action is being taken?

10 Whether the condition of rivets, bolts and tie rods

particularly of water storage tanks are in sound

condition?

10(a) If not, whether any remedial action is being taken?

11. Whether any crack have developed in cast iron tank

plates?

11(a) If so, whether any remedial action is being taken?

12. Whether any deformation of the structure has

occurred?

12(a) If so, whether any remedial action is being taken?

13. Whether anchor-bolts are tightly fastened to

foundations & bearings?

13(a) If not, whether any remedial action is being taken?

1. Whether any crack has developed in CI/WI/Pressed

up steel/tank plates?Yes/No

N. CI/WI/PRESSED UP STEEL WATER TANK & STAGING & FLOOD

LIGHTTOWERS

Ref: Para229 IRWM

Item to be inspected RemarksS.

N.

Page 207: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

199

Yes/No

Yes/No

Yes/No

Yes/No

Item to be inspected RemarksS.

N.

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

Yes/No

1(a) If so, whether any remedial action is being taken?

2. Whether corrosion in steel is taking place?

2(a) If so, whether any remedial action is being taken?

3 In the case of steel-work built into masonry, such

as tie rods of arched buildings and roof trusses,

whether any corrosion is apparent near the

masonry?

3(a) If so, whether any remedial action is being taken?

4 Whether the condition of rivets, bolts and tie rods

particularly of water storage tanks are in sound

condition?

4(a) If not, whether any remedial action is being taken?

5 Whether bed blocks or pedestals are in sound

conditions?

5(a) If not, whether any remedial action is being taken?

6 Whether all fixtures are intact in bed blocks or

pedestals?

6(a) If not, whether any remedial action is being taken?

7 Whether the condition of paint is good?

7(a) If not, whether any remedial action is being taken?

8 Whether date of painting is mentioned on the

structure?

Yes/No

Yes/No

Yes/No

Page 208: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

200

Yes/No

Yes/No

Yes/No

Item to be inspected RemarksS.

N.

Yes/No

Yes/No

Yes/No

9 Whether anchor-bolts are tightly fastened to

foundations & bearings?

9(a) If not, whether any remedial action is being taken?

10 Whether any deformation of the structure has

occurred?

10(a) If so, whether any remedial action is being taken?

11 Whether decay in timber is taking place in case of

wooden staging?

11(a) If so, whether any remedial action is being taken?

12 Whether any sign of leakage has been detected in

water tank?

12(a) If so, whether any remedial action is being taken?

Yes/No

Yes/No

1 Are inspections of the various water supply

installations being done as per IRWM i.e. Once

in THREE months by ADEN and joint inspection

once in a year by SSE/W with MECH/ELE dept.?

2 Are records of inspections of the various water

supply installations being maintained properly

in registers?

Yes/No

O. WATER SUPPLY INSTALLATION

1. List of Check Points on Quality of Water supply – General:

Item to be inspectedS.

N.

Remarks

IRWM

Para

554/c/i

Yes/No IRWM

Para

554/e

Ref.

Page 209: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

201

Yes/No

Yes/No

Yes/No

Item to be inspected RemarksS.

N.

Yes/No

Yes/No

Yes/No

Yes/No

3 Whether storage tank (Underground & elevated)

is clean and date of cleaning is mentioned?

4 Whether tube well is protected against

contamination from surface water?

5 Whether water samples tested from filtration

plant every MONTH?

6 Whether water samples tested for chemical

examination SIX MONTHLY (or once before & after

monsoon)?

7 Whether samples collected as per specified

manner?

8 Whether collected samples sent to medical

department or lab duly leveled, sealed without

delay?

9 Whether leakage detection test conducted?

1 Whether chlorination plant is in good working

condition?

2 Whether records like log book, and plant failure

register of the chlorination plant properly

maintained and up to date?

Yes/No

2. Inspection of Chlorination Plant

Item to be inspected RemarksS.

N.

Ref.

IRWM

Para 537

IRWM

Para 554/a

Yes/No

IRWM

Para 554/a

IRWM

Para 532

IRWM

Para

532/e

IRWM

Para 546

Page 210: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

202

Yes/No

Yes/No

Yes/No

Item to be inspected RemarksS.

N.

Yes/No

Yes/No

Yes/No

Yes/No

3 If the plant is maintained and operated through

contract, are all records of operation and

maintenance properly maintained?

4 Are plant failures promptly attended?

5 If the plant is maintained and operated

departmentally, are spares of all critical

components in stock?

6 Whether chlorine demand of the raw/untreated

water is being regularly tested?

7 Whether equipment/disinfectant chemicals in

chlorination plant are stored properly in safe

condition?

8 Whether proper record of date of receipt, date of

testing and date of consumption of the hypochlorite

solution maintained?

9 Are all components of chlorination plant

functioning properly including proportionate dozing

system (if provided)?

10 Whether contact period of 30 to 60 minutes is

maintioned?

11 Whether residual chlorine of 0.2 ppm is available

in normal condition?

Yes/No

Yes/No

Page 211: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

203

P. RAIN WATER HARVESTING SYSTEM (RWH)

Yes/No

Yes/No

Yes/No

Item to be inspected RemarksS.

N.

Yes/No

Yes/No

Yes/No

Yes/No

1 Whether new buildings which are being provided

with suitable RWH structures as per local bye laws?

2 Whether recharged water is silt free and properly

maintained?

3 Whether well/trench used for RWH is being cleaned

periodically?

4 Whether the recharge shafts for RWH are being

constructed 10-15 m away from the building for the

safety of building?

5 Whether there is an approved plan for RWH

installation?

6 Has the RWH system been checked before

monsoon?

7 Has the RWH system been checked after monsoon?

� � �

Page 212: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

204

CHAPTER NO – 5

Inspection at New construction Site

A. CHECK LIST FOR WORK SITES

Infringement to Running Line by Construction Machinery Vehicles

1 Vehicle to ply minimum generally 6m

clear from center line of track, if

required, upto 3.5 m only with the

permission of Engineer – in – charge.

Has this been done?

2 If required to work within less than 3.5

m clearance from the center line of

track, whether the presence of

authorized Railway Inspector is

ensured?

3 Whether proper barricading or 150

mm thick line (of lime) marking at a

distance of 3.5m from the centre of

track has been provided or not?

4 Is nominated vehicl is plying between

sunrise & sunset?

Para 826

of IRPWM,

For

dimensional

details

refer ann-

ii of PCE/

ECR

circular

no. 16 /

2010/

Track

Yes/No

S. Items to be checked Remarks Reference

N.

Yes/No

Yes/No

Yes/No

Page 213: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

205

S. Items to be checked Remarks Reference

N.

5 Whether trained drivers are being

utilized and the presence of at least

one flag man and one supervisor

certified for such work?

6 If night working is done, whether it has

been permitted by AEN/XEN in writing

any by deputing one inspector?

7 Whether walkie talkie sets or mobile

phones have been provided at the

site of work?

8 Whether S & T and electrical staff

have been informed before starting

of work along the track?

9 Whether vehicle / tractor drivers

trained by the Railway Officers/

Supervisors to work along the track

as per safety guide lines?

10 For night working whether sufficient

light has been provided?

Yes/No

Para 826

of IRPWM,

For

dimensional

details

refer ann-

ii of PCE/

ECR

circular

no. 16/

2010/

Track

Yes/No

Page 214: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

206

S. Items to be checked Remarks Reference

N.

1 Whether work is being done in

presence of authorized Over Head

equipments (OHE) staff with proper

power block & permit to work?

2 If track bonds, feeder connection etc.

have been disturbed, whether they

have been re-connected properly

after completion of work?

3 Whether mast foundation is exposed

and track level raised/slewed beyond

permissible limits?

4 Whether a minimum distance of 2

met. has been maintained between

live OHE wire and body parts of the

worker or tools or metallic supports,

etc.?

B. Work in /near Electrified Territory :

Yes/No

Para 283

(2)of

IRPWM

Yes/No

Yes/No

Yes/No

Page 215: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

207

D. Check list for Track Ballast:

S. Items to be checked Remarks Reference

N.

1 Whether the track ballast is hard, well

graded machine crushed and angular

in shape.

2 Physical properties of the ballast

a . Is the abrasion value of the track

ballast done is less than 30%

Yes/No

Yes/No

Specification

of ballast as

per IRS GE-

1, June

2004

corrected

upto CS no 3

dtd 05-1-

09GCC

S. Items to be checked Remarks Reference

N.

1 Whether contractor has ensured

proper barricading and protection at

the site of work?

2 Whether sufficient free space for

movement of passenger traffic

provided, to avoid any untoward

incidents for all works done within

station premises, especially on

passenger platform?

3 Whether proper signage has been

provided?

C. Precautions within station Premises

Yes/No

Yes/No

Yes/No

Para 34(3)

& 34(4) of

GCC

Page 216: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

208

b. Is the impact value of the ballast is

less than 20%

c. Is Water absorption in less than 1%

(In exceptional cases on technical and

economic ground, can be relaxed up to

35% and 25% respectively by CTE in

open line and CAO/C for construction

projects.)

Size and gradation:

Is the ballast satisfy the following size

and gradation:

a . Retained on 65 mm Sq. mesh sieve

5% Maximum

b. Retained on 40 mm Sq. mesh sieves

40% - 60%

c. Retained on 20 mm Sq. mesh sieve

Not less than 98% for machine

crushed. Not less than 95% for hand

broken.

Oversize Ballast:

a . In case retention on 65 mm square

mesh sieve exceeds 10%, the stack

shall be rejected.

b. In case retention on 40 mm square

mesh sieve exceeds 70%, the stack

shall be rejected.

Yes/No

Yes/No

Specification

of ballast

as per IRS

GE-1, June

2004

corrected

upto CS no

3 dtd 05-1-

09GCC

Yes/No

Yes/No

Yes/No

Yes/No

3

Page 217: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

209

Under size Ballast:

The ballast shall be treated as under

size and shall be rejected if:-

a. Retention on 40 mm sq. mesh sieve

is less than 40%

b. Retention on 20 mm sq. mesh sieve

is less than 98%

(For machine crushed) or 95% (for hand

broken.) Has this been done?

Stack measurement

Stacking if done on a neat, plain and firm

ground with good drainage. The height

of stack is not less than 1 m except in

hilly area where it may be 0.5 mm.

Cubical content of each stack should

normally be not less than 30 cum in plain

area and 15 cum in hill area.

The screen for sieving the ballast shall

be of square mesh. If Mesh in not less

100 X 70 X 10 cm (LXBXH). The following

tolerances in the size of the hole for 65,

40 and 20mm nominal size shall be

permitted.

Specification

of ballast

as per IRS

GE-1, June

2004

corrected

upto CS no

3 dtd 05-1-

09GCC

Yes/No

4

Yes/No

Page 218: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

210

Specification

of ballast

as per IRS

GE-1, June

2004

corrected

upto CS no

3 dtd 05-1-

09GCC

a. 65 mm sq. mesh plus/minus 1.5 mm

b. 40mm sq. mesh plus/minus1.5 mm

c. 20mm sq. mesh plus/minus 1.0 mm

E. Form Work in Concreting Work :

S.N. Items to be checked Remarks

1 Whether proper temporary support e.g.

shoring, timbering and strutting has been

checked before concreting works?

2 Whether stability and safety of all structures,

excavation and works has been ensured?

3 Whether form work is water tight?

4 Whether dimensions are checked and found

correct?

Yes/No

Yes/No

Yes/No

Yes/No

F. Box Pushing Work. :

S.N. Items to be checked Remarks

1 Whether box pushing work is to be done in parts

of 10 to 20 cm to minimize disturbance to track?

2 Are trains permitted to pass during actual box

pushing operation?

Yes/No

Yes/No

Page 219: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

211

Yes/No

Yes/No

3 Whether track parameter has been checked

and recorded before the passing of first train?

4 After close of box pushing work whether the

speed of first train passed at speed of stop

dead and 10 kmph and subsequent trains were

upto 30 kmph?

5 Whether track parameter has been checked

after each round of box pushing by the

supervisor In-charge before leaving site?

6 Whether posting of proper look out Man with

banner flags and other protection equipments

has been ensured when box pushing is not in

progress?

Yes/No

Yes/No

� � �

Page 220: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

212

Notes

Page 221: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

213

Notes

Page 222: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

214

Notes

Page 223: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

215

Notes

Page 224: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

216

Notes

Page 225: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

217

Notes

Page 226: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

218

Notes

Page 227: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

This book is compilation of updated instructions on different subjects, kindly also refer to latest correction slips, if any. Although due care has been taken while preparing this compilation. In case of any doubt/discrepancies, users are advised to kindly refer to original document/correction-slips, as indicated therein. The same may be brought to the notice of IRICEN, Pune at e-mail id: [email protected]

Page 228: Compendium of Instructions related to Inspections and ...iricen.gov.in/iricen/books_jquery/Inspection Checklist final.pdf · C. USFD testing 83 D. AT Welding 91 ... H. Check List

Published by :

Indian Railways Institute of Civil Engineering, Pune 11-A, South Main Road, Koregaon Park, Pune - 411001.

Price < 60/-

Design by :HUMA Adds, Pune.

Printed by :Kalyani Corporation, Sadashiv Peth, Pune - 30.