community-led accelerated wash (cowash) project...being finalized in the reporting period. thus far,...

64
COMMUNITY-LED ACCELERATED WASH (COWASH) PROJECT NINE MONTHS PERFORMANCE REPORT 2007 EFY (07/07/2014-31/03/2015) MAY 2015

Upload: others

Post on 31-Aug-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: COMMUNITY-LED ACCELERATED WASH (COWASH) PROJECT...being finalized in the reporting period. Thus far, the consultant submitted all of the 18 parts of the manual and strategic framework

COMMUNITY-LED ACCELERATED WASH (COWASH)

PROJECT

NINE MONTHS PERFORMANCE REPORT

2007 EFY (07/07/2014-31/03/2015)

MAY 2015

Page 2: COMMUNITY-LED ACCELERATED WASH (COWASH) PROJECT...being finalized in the reporting period. Thus far, the consultant submitted all of the 18 parts of the manual and strategic framework

i

Table of contents

1 EXECUTIVE SUMMARY ........................................................................................................................................ 1

2 OVERALL OBJECTIVE ACHIEVEMENT.................................................................................................................... 5

3 PROJECT PURPOSE ACHIEVEMENT ...................................................................................................................... 5

4 COMPONENT 1: STRENGTHENING THE FEDERAL CAPACITY TO IMPLEMENT COMMUNITY MANAGED PROJECTS

ALONGSIDE WITH A SUPPORT TO THE ESTABLISHMENT OF THE ONE WASH NATIONAL PROGRAM .................. 7

4.1 RESULT 1 OF COMPONENT 1: COMMUNITY MANAGED PROJECT APPROACH SCALED-UP AT NATIONAL LEVEL ....... 7

4.1.1 Output 1: Manuals and Guidelines Reviewed and Developed for Standardizing the CMP Implementation

within the WaSH Implementation Framework .............................................................................................. 7

4.1.2 Output 2: Tools and Mechanisms Reviewed and Developed for Standardizing the Planning,

Implementation and Monitoring of CMPs ..................................................................................................... 8

4.1.3 Output 3: CMP Approach within the Rural WaSH Scientifically Researched ................................................. 9

4.1.4 Output 4: Information, Education and Communication (IEC) on CMP Implementation Modality Enhanced

..................................................................................................................................................................... 10

4.2 RESULT 2 OF COMPONENT 1: CMP IMPLEMENTATION CAPACITY AT THE FEDERAL AND REGIONAL LEVELS

DEVELOPED ....................................................................................................................................................... 12

4.2.1 Output 1: Capacity Building Instruments Reviewed and Developed ........................................................... 12

4.2.2 Output 2: Capable and Adequate Personnel in place for CMP Implementation at National and Regional

Levels ........................................................................................................................................................... 13

4.3 RESULT 3 OF COMPONENT 1: DEVELOPMENT AND IMPLEMENTATION OF ONE WASH NATIONAL PROGRAM

SUPPORTED ...................................................................................................................................................... 15

4.3.1 Output 1: COWASH Support Provided in Preparing One WaSH National Program ..................................... 15

4.3.2 Output 2: COWASH Support Provided in Implementation of One WaSH National Program ....................... 15

5 COMPONENT 2: ESTABLISHING AND STRENGTHENING THE CAPACITY IN REGIONS TO SCALE-UP

IMPLEMENTATION OF CMP ...............................................................................................................................17

5.1 RESULT 1 OF COMPONENT 2: TARGET REGIONS, ZONES AND WOREDAS CAPABLE TO PLAN, MANAGE, MONITOR

AND IMPLEMENT RURAL WASH INTERVENTIONS USING CMP APPROACH ....................................................... 17

5.1.1 Output 1: Regional Support Units (RSU) Established and Functional .......................................................... 17

5.1.2 Output 2: Regions, Zones and Woredas Capacitated to Implement Rural WaSH through CMP ................. 18

5.2 RESULT 2 OF COMPONENT 2: FINANCIAL AND PROCUREMENT SERVICES DELIVERED FOR CMP INTERVENTION AT

ALL LEVELS IN THE SELECTED REGIONS .............................................................................................................. 30

5.2.1 Output 1: Flow of Funds for CMPs Functional ............................................................................................. 30

5.2.2 Output 2: Linkages Created with Private Sector in the Supply of Materials, Equipment, Tools and Services

..................................................................................................................................................................... 30

5.3 RESULT 3 OF COMPONENT 2: SUSTAINABLE COMMUNITY AND INSTITUTIONAL ACCESS TO SAFE WATER,

SANITATION AND HYGIENE IN THE TARGET WOREDAS INCREASED.................................................................. 31

5.3.1 Output 1: Access to Improved Water Sources for Communities and Institutions Increased ....................... 31

5.3.2 Output 2: Access to Sanitation for Household and Institutions Increased and Hygiene Behavior Improved

..................................................................................................................................................................... 40

5.3.3 Output 3: Sustainability of Communal and Institutional Water Schemes in the Targeted Woredas

Strengthened ............................................................................................................................................... 42

5.3.4 Output 4: Potable Water Quality Ensured in Targeted Woredas ................................................................ 44

6 FINANCIAL PERFORMANCE ................................................................................................................................45

6.1 COMPONENT 1, FEDERAL LEVEL ................................................................................................................................ 45

6.1.1 Cumulative expenditures of Phase I and II .................................................................................................. 45

Page 3: COMMUNITY-LED ACCELERATED WASH (COWASH) PROJECT...being finalized in the reporting period. Thus far, the consultant submitted all of the 18 parts of the manual and strategic framework

ii

6.1.2 Comparison of the budget utilization with the first 6 - months of Phase II (October 2014-March 2015)

representing the Quarter II of 2007 Ethiopian Fiscal Year. ......................................................................... 46

6.2 COMPONENT 2 FINANCIAL PERFORMANCE ...................................................................................................... 48

6.2.1 Tigray Region ............................................................................................................................................... 48

6.2.2 SNNP REGION .............................................................................................................................................. 49

6.2.3 Oromia Region ............................................................................................................................................. 51

6.2.4 Amhara region............................................................................................................................................. 52

6.2.5 Benishangul Gumuz region .......................................................................................................................... 53

7 PROJECT COORDINATION WITH KEY STAKEHOLDERS .........................................................................................55

8 CHALLENGES ......................................................................................................................................................58

Page 4: COMMUNITY-LED ACCELERATED WASH (COWASH) PROJECT...being finalized in the reporting period. Thus far, the consultant submitted all of the 18 parts of the manual and strategic framework

iii

Abbreviation Interpretation

ACSI Amhara Credit and Saving Institution

AfDB African Development Bank

AWP Annual Work Plan

BoE Bureau of Education

BoFED Bureau of Finance and Economic Development

BoH Bureau of Health

CARE Cooperative for Assistance and Relief Everywhere

CBN Community Based Nutrition

CDF Community Development Fund

CFT Community Facilitation Team

CIDA Canadian International Development Agency

CLTSH Community-Led Total Sanitation and Hygiene

CMP Community Managed Project

COWASH Community Led Accelerated WASH in Ethiopia

CRS Catholic Relief Services

CTA Chief Technical Advisor

CWA Consolidated WaSH Account

DCSI Dedebit Credit & Saving Institution

DFID Department for International Development (UK)

EFY Ethiopian Fiscal Year

EIRR Economic Internal Rate of Return

ETB Ethiopian Birr

EU European Union

EUR Euro

EUWI European Union Water Initiative

EWA Ethiopian Water Alliance

FI Financial Intermediary

FinnWASH-BG Rural Water Supply, Sanitation and Hygiene Programme in

Benishangul-Gumuz Region

FTAT Federal Technical Assistance Team

GoE Government of Ethiopia

GoF Government of Finland

GTP Growth and Transformation Plan

HEW Health Extension Worker

HIV/AIDS Human Immunodeficiency Virus/ Acquired Immunodeficiency

Syndrome

HQ Head Quarter

HRD Human Resource Development

HSDP Health Sector Development Plan

IDC Italian Development Cooperation

IEC Information, Education and Communication

JFA Joint Financing Agreement

JICA Japan International Cooperation Agency

JMP Joint Monitoring Program

JTR Joint Monitoring Review

KWT Kebele WaSH Team

LWI Living Water International

MDG Millennium Development Goal

M&E Monitoring and Evaluation

Page 5: COMMUNITY-LED ACCELERATED WASH (COWASH) PROJECT...being finalized in the reporting period. Thus far, the consultant submitted all of the 18 parts of the manual and strategic framework

iv

Abbreviation Interpretation

METB Million Birr

MEUR Million Euros

MFA Ministry for Foreign Affairs (of Finland)

MFI Microfinance Institution

MIS Management Information System

MMS Mass Mobilization Strategy

MoE Ministry of Education

MoFED Ministry of Finance and Economic Development

MoH Ministry of Health

MoU Memorandum of Understanding

MoWE Ministry of Water & Energy

MSF Multi-Stakeholder Forum

MUS Multiple Use of Services (Water)

MUSD Million United States Dollars

MWA Millennium Water Alliance

NGO Non-Governmental Organization

NPV Net Present Value

NUWI Netherlands-UNICEF WaSH Initiative

NWCO National WaSH Coordination Office

NWI National WaSH Inventory

NWMU National WaSH Management Unit

NWSC National WaSH Steering Committee

NWTT National WaSH Technical Team

OCSSCO Oromia Credit and Saving Shareholder Company

ODF Open Defecation Free

O&M Operation and Maintenance

OMA Office Management Assistant

OMFI OMO Micro-Finance Institution

OMSU Operation and Maintenance Support Unit

ORDA Organization for Rehabilitation and Development in Amhara

PASDEP Plan for Accelerated and Sustainable Development to End Poverty

REST Relief Society of Tigray

RiPPLE Research Inspired Policy and Practice Learning in Ethiopia and the

Nile Region

RSU Regional Support Unit

RWCO Regional WaSH Coordination Office

RWSC Regional WaSH Steering Committee

RWSEP Rural Water Supply and Environment Programme

RWTT Regional WaSH Technical Team

SAP National Hygiene and Sanitation Strategic Action Plan

SNNPR Southern Nations & Nationalities Peoples Region

SNV Netherlands Development Organization

SvB Supervisory Board

SWAp Sector Wide Approach

TA Technical Assistance

TVETC Technical Vocational & Educational Training College

UAP Universal Access Plan

UK United Kingdom

UNESCO United Nations Educational, Scientific and Cultural Organization

Page 6: COMMUNITY-LED ACCELERATED WASH (COWASH) PROJECT...being finalized in the reporting period. Thus far, the consultant submitted all of the 18 parts of the manual and strategic framework

v

Abbreviation Interpretation

UNICEF United Nations Children’s Fund

WaSH Water Supply, Sanitation and Hygiene

WASHCO Water Supply, Sanitation and Hygiene Committee

WB The World Bank

WEW Water Extension Worker

WIF WaSH Implementation Framework

WMP Woreda Managed Project

WMU WaSH Management Unit

WRDB Water Resources Development Bureau

WSA Woreda Support Agent

WSG Woreda Support Group

WSP Water Safety Plan

WSP-AF Water and Sanitation Program-Africa

WSS Water Supply and Sanitation

WSSD Water Supply and Sanitation Directorate

WSSP Water Supply and Sanitation Program

WWT Woreda WaSH Team

WYCB Women, Youth and Children Bureau

Page 7: COMMUNITY-LED ACCELERATED WASH (COWASH) PROJECT...being finalized in the reporting period. Thus far, the consultant submitted all of the 18 parts of the manual and strategic framework

1

1 EXECUTIVE SUMMARY

The COWASH project has two components. Component 1 strives to strengthen the federal

level capacity for implementation of the CMP approach and to support the overall WaSH sector

development process including the establishment and implementation of One WaSH National

Program (OWNP).

Under Component 1, a number of activities were planned to be conducted by COWASH FTAT at

the federal level and in the regions in the first nine months of 2007 EFY. The main

achievements in the reporting period were the following:

Combined Rural Water Supply O&MM Manual for Rural Piped Schemes (RPS) and

Pastoralist areas and Generic O&MM Strategic Framework being completed

(95.0%): The development of the manual and strategic framework started in 2006 EFY

being finalized in the reporting period. Thus far, the consultant submitted all of the 18

parts of the manual and strategic framework (95.0%) and the task force members have

been commenting on the parts of the manual submitted by the consultant. COWASH is

strictly following and providing technical assistance for the development of the manual and

strategic framework.

GLOWS/WSP training manual translated into Amharic (100.0%): A GLOWS/WSP

training manual was developed by MetaMeta. It was found necessary to translate the

manual into the working languages of the project regions so as to ease GLOWS/WSP

trainings at the grassroots level. Cognizant of the importance of this manual for woreda

and kebele staff, COWASH hired a short term consultant for the translation and the

translation of the manual into Amharic has been completed by incorporating comments of

reviewers (Amhara RSU staff and COWASH FTAT).

1 PhD level research underway and 1 MSc level CMP Research sponsored: The

project has been carrying out the on-going PhD level research and the newly started

Master’s level research entitled “Assessment of Potable Water Access & Users’ service

satisfaction in Gonji Kolella woreda rural communities during CMP implementation”. Articles

have been produced by the PhD level researcher and draft Thesis of the MSc level research

was prepared and commented by COWASH FTAT and sent to the researcher for corrections.

1 Case Study on the Impact of CMP Water Supply in Gonji Kolella Woreda

conducted (100.0%): A case study was conducted, by a short term consultant, on the

impact of CMP water supplies on the life of Abunebla and Besanit village communities in

Gonji Kolella woreda of West Gojjam Zone of Amhara region. It was found out that the

implementation of rural water supply schemes using CMP funding mechanism created

sense of ownership and motivation to rural communities in these villages. Farmers are

looking to improve their livelihood using the excess water from the improved sources and

rope pumps.

5 Regions have received COWASH FTAT Technical Assistance in the preparation of

2007 EFY Planning: With the view to prepare the 2007 EFY regional plans timely, the

COWASH federal technical assistant team prepared draft planning formats (both physical

and financial) and estimated unit costs and distributed to Regional Support Units (RSUs).

With these templates the regions have prepared and approved their annual plans.

Human Capacity Building Assistance to Regions:

1) 125 (14.4% female) Woreda, Zone and Regional staff in Amhara, Tigray,

SNNPR and Oromia regions trained by COWASH FTAT in GIS/M&E (90.6%):

Page 8: COMMUNITY-LED ACCELERATED WASH (COWASH) PROJECT...being finalized in the reporting period. Thus far, the consultant submitted all of the 18 parts of the manual and strategic framework

2

With the view to mapping of project woredas and equipping GIS skills to woreda, zonal

and regional staff, COWASH GIS expert trained 125 regional, zonal and woreda staff of

Amhara, Tigray, Oromia and SNNP regions on Quantum GIS, Data Management and

Basic Computer skills. The training was provided in collaboration with MoWIE GIS

department staff and regional water bureau staff of the four project regions.

2) 29 (2 female) COWASH FTAT, RSU and Water Bureau Staff trained for 5 days in

GLOWS/WSP ToT Training (10.0%): MetaMeta trained a total of 29 RSU, Water

Bureau and COWASH FTAT staff on GLOWS/WSP. These trainees are expected to train

woreda and zonal staff on GLOWS/WSP so as to sustain the water points constructed at

the grassroots level. The Amharic version of the GLOWS/WSP manual was reviewed by

COWASH staff during the training.

3) 222 (29 female) Regional, Zone and Woreda staff trained in CMP Management,

Promotion, Appraisal, M&E and O&MM for 3 days(96.5%): COWASH FTAT in

collaboration with Regional Support Units (RSU) of SNNPR, Oromia and BSG have

trained 222 (96.5%) regional. Zone and woreda staff of SNNPR, Oromia and BSG

regions on CMP management, promotion, monitoring and O&MM for three days.

Moreover, 57 (7 female) of these staff were trained on CMP promotion, appraisal and

reporting by the COWASH FTAT for additional 3 days.

In all, 376 (49 female) woreda, zone and regional staff have been trained by COWASH

FTAT in various types of trainings – CMP management, promotion, appraisal, and

Operation and Maintenance (O&MM).

COWASH Project Performance Reports Prepared and distributed (100.0%): In the

reporting period, COWASH FTAT prepared and disseminated the 2006 EFY annual

performance report, the 2007 EFY First Quarter Performance Report and the 2007 EFY

Semi-annual Performance report. The reports were consolidated by incorporating the

performance of the project regions and Component 1 achievements. The quarterly reports

can be found at http://www.cmpethiopia.org/page/273.

6,500 Table Calendars printed and disseminated (100.0%): Like the previous fiscal

year, the project planned to produce CMP table calendars. Accordingly, a total of 6,500

copies of the 2007 CMP calendars (100.0%) were produced and disseminated to all the

project regions, zones, woredas and also to the stakeholders at federal level. These

calendars are believed to promote CMP in the COWASH woredas and beyond.

3 MoWIE staff Participated in Stockholm Water Week 2014 with the sponsorship

of COWASH: COWASH planned to assist MoWIE to participate in Stockholm Water Week

2014. As part of COWASH’s effort to promote CMP at the international and national levels,

the project sponsored 3 MoWIE staff to participate in Stockholm Water Week. Moreover,

the project has also sponsored the stand of MoWIE exhibition, which was successfully

carried out.

1 Training Impact Research Completed and another started: Impact research on the

CMP related trainings held in 2005 EFY in Tigray and Amhara regions has been conducted

in 2006 EFY by a private consultant called Lisan Management. The consultant has

completed the research report. Another impact assessment on the trainings conducted in

Oromia and SNNPR is launched by a private consultant contracted by COWASH.

CMP Implementation Manual using Public Finance and Procurement Management

System (PFPMS) prepared (100.0): Consultants (IRC ad Eyob Defere) financed by

UNICEF and COWASH jointly developed the CMP Implementation Manual using PFPMS with

Page 9: COMMUNITY-LED ACCELERATED WASH (COWASH) PROJECT...being finalized in the reporting period. Thus far, the consultant submitted all of the 18 parts of the manual and strategic framework

3

several stakeholder consultations. This Manual is the mitigation measure included into the

One WASH Program Operational Manual (POM) also finalized in 2006 EFY. The manual,

which is to be annexed to POM, was presented to MoFED by MoWIE for approval. However,

so far no feedback from MoFED and a number of planned activities are pending due to the

delay in the approval of the manual.

Component 1 Budget Utilization: The total COWASH Component 1 (C-1) five year

budgets is EUR 3,730,393. Of this, about 658,088 EUR (76.2% of the 2007 EFY budget,

863,718 EUR) was allocated for the first nine months of the fiscal year. Accordingly, about

574,641 EUR (87.3% of the allocated), or 66.5% of the annual budget of C-1, has been

utilized for activities planned for the reporting period.

Component 2 of the project deals with “Establishing and Strengthening the Capacity in

Regions to Scale-up Implementation of CMP”. A number of activities have been performed

under this component.

Increasing the Number of CMP Woredas (from 31 to 76): The number of woredas

implementing the CMP approach has been on the rise. In 2003 EFY, only 31 woredas (26 in

Amhara; 19 by RWSEP and 7 by UNICEF, and 5 in Benishangul-Gumuz) have been

implementing CMP. This accounts for 16% of the 166 rural woredas in Amhara Region and

24% of the 21 rural woredas in Benishangul-Gumuz region, respectively. Excluding the

UNICEF CMP woredas in Amhara, the number of CMP Woredas has increased to 76 (11.6%

of the rural woredas in the five project regions) in 2007 EFY. UNCICEF has stopped

implementing CMP approach since 2006 EFY and, hence, the UNICEF CMP woredas are not

included in the report. While the FinnWASH–BG woredas remained same (5), COWASH

woredas increased from 19 in 2003 EFY to 71 in 2007 EFY in the five project regions.

Construction of Water Points: The four regions (Amhara, Tigray, SNNPR and Oromia)

have constructed a total of 1,297 water points (1,267 communal and 30 institutional) over

the nine months. This accounts 50.7% of the plan for 2007 EFY. The 1,267 community

water points are benefiting some 270,757 rural people in the COWASH kebeles. The

institutional water points are serving 15,493 students and teachers and 21 health

extension workers and some clients of the institutions.

To date, 6,331 water points (5,148 in Amhara, 238 in Tigray, 313 in SNNPR and 632 in

Oromia) were constructed in the COWASH woredas of four regions. Of this, majority of

them (6,007 or 94.9%) were built by communities themselves and 324 by institutions (264

for schools and 60 for health institutions) with financial and technical support of COWASH.

The 6,007 communal water points are benefiting more than 1,465,151 rural people in the

COWASH/CMP kebeles of the four regions. Over 105,380 students and teachers and 12,989

staff and clients of health facilities are benefiting from the institutional water points.

Rehabilitation of Water Points: In the reporting period, only 33 community water points

(11.6% of the annual plan), benefiting more than 11,924 rural people, were rehabilitated

in three regions: Tigray, SNNPR and Oromia.

So far, a total of 348 water points (342 communal and 6 schools) have been rehabilitated

since the launching of the COWASH project. Given the large number of project woredas,

majority of them (288 or 82.8%) are in Amhara followed by SNNPR (28), Tigray (23) and

Oromia (9). Above 91,187 rural people and 2,314 students and teachers are benefiting

from these rehabilitated water points through the support of COWASH.

Institutional Latrine Construction: Effort has been exerted to improve the sanitation

situation of institutions. Over the first nine months, schools and health facilities have

Page 10: COMMUNITY-LED ACCELERATED WASH (COWASH) PROJECT...being finalized in the reporting period. Thus far, the consultant submitted all of the 18 parts of the manual and strategic framework

4

constructed 16 latrines (15.8% of the annual plan) in three regions – Amhara (7),

Tigray(8) and SNNPR(1). These latrines benefit more than 15,596 students and teachers

(48.5% female) and 282 health extension workers and clients of health facilities (46.5%

female) in the COWSH/CMP kebeles.

To date, a total of 115 institutional latrines (69 for schools and 46 for health facilities) were

constructed in the four regions -79 in Amhara, 20 in Tigray, 3 in SNNPR and 13 in Oromia.

More than 79,008 teachers and students (50.5% female) and 2,649 health staff and clients

of the facilities (50.0% female) are using these latrines.

The project regions have been receiving funds (Euro) from the Ministry for Foreign Affairs of

Finland (MFA) as per their funding agreement with Embassy of Finland. Euro 18,269,590 was

allocated by the Government of Finland for the five years implementation of the project in five

regions. Of this amount, Euro 12,162,400.28 (66.6% of the Euro allocated), or about Birr

298.92 million has been transferred to the project regions until end of the reporting period

(Table 1). Financial performance reports of the project regions reveal that over 66.0% of the

funds transferred from MFA has been utilized for the project activities in the five regions until

31 March 2015.

Table 1: Amount of Funds (in Euro) transferred from MFA to Project Regions (in Euro & Birr)

until March 31, 2015

COWASH

Project

Region

Amount of Euro

Agreed for 5

Years

Amount of Euro

Transferred from MFA

until 31st March 2015

Amount (in Birr)

Transferred from

MFA until 31st

March 2015*

Amount utilized

(in Birr) until 31st

March 2015

%

Utilized

Amhara*10,310,578 8,391,081.71 209,461,912.25 148,721,913.21 71.0

Tigray2,184,299 1,200,462.77 28,734,412.85 15,920,221.17 55.4

SNNPR1,746,084 1,087,713.00 24,370,231.50 17,479,426.41 71.7

Oromia1,766,000 1,158,347.00 28,016,347.24 17,424,409.49 62.2

BSG2,262,629 324,796.00 8,332,614.38 151,933.00 1.8

Total18,269,590.00 12,162,400.48 298,915,518.22 199,697,903.28 66.8

Note: * The ‘Amount Transferred from MFA until 31st March 2015’ to Amhara region includes Birr 4,291,860.92

transferred from RWSEP.

Page 11: COMMUNITY-LED ACCELERATED WASH (COWASH) PROJECT...being finalized in the reporting period. Thus far, the consultant submitted all of the 18 parts of the manual and strategic framework

5

2 OVERALL OBJECTIVE ACHIEVEMENT

The overall objective of COWASH is ‘to achieve universal access to WaSH in the rural

areas of Ethiopia’. The project tries to attain this objective through implementing Component

1 at the federal level and Component 2 in the regions through the adoption and application of

Community Managed Project (CMP) approach. Complete information on the contribution of the

project in improving the water supply, sanitation and hygiene situation of the project woredas

will be presented in annual report of the project.

3 PROJECT PURPOSE ACHIEVEMENT

Within the framework of the overall objective described above, the project purpose is to

“Support the acceleration of UAP-rural water and sanitation targets attainment

through the establishment of an enabling environment and the implementation of

CMP interventions in selected rural areas of Ethiopia”. Thus, COWASH strives to provide

support for the development of the enabling environment at the federal level and in the project

regions where hydro-geological conditions are suitable for its replication.

The key indicators for the verification of the achievement of the Project purpose are:

i) Percentage of Regions implementing CMP approach; ii) Percentage of Woredas of targeted

regions implementing CMP approach; iii) Percentage of Kebeles of targeted woredas

implementing CMP approach; iv) Percentage of rural people that has access to potable water

through COWASH; and v) Amount of regional budget allocated for COWASH.

The number of regions implementing CMP has increased from two regions (22.2% of the 9

administrative regions of Ethiopia, excluding the city administrations of Addis Ababa and Dire

Dawa) in 2003 EFY to five regions (55.6%) in 2007 EFY. Benishangul Gumuz region is

encompassed by COWASH in 2007 EFY as delay in the preparatory activities delayed the

implementation of activities in 2006 EFY.

The number of woredas implementing CMP approach rose from 5.5% (32 of the 583 rural

woredas) in 2003 EFY to 13.0% (76 of the 583 rural woredas) in 2007 EFY. In 2003 EFY, only

27 woredas in Amhara (19 by RWSEP and 8 by UNICEF) and 5 woredas in Benishangul-Gumuz

have been implementing CMP. This accounts for 17.6 % of the 153 rural woredas in Amhara

Region and 25 % of the 20 rural woredas in Benishangul-Gumuz region, respectively. In 2004

EFY, the approach has been implemented in 44 woredas in Amhara, Tigray, SNNPR and BSGR,

which is 13.2 % of the woredas in the four regions. In 2005 EFY, the share of CMP woredas in

the 5 regions was 9.1 % including the 8 UNICEF CMP woredas in Amhara region. In 2006 EFY,

UNICEF stopped implementing CMP approach in the 8 woredas and the approach has been

implemented in 68 (11.7%) woredas of the five regions. In the reporting period, 8 woredas (4

each in Oromia and BSG regions) were encompassed by the project and the total number of

CMP woredas increased to 76 (13.0% of the 583 rural woredas) of the five regions.

Between 2003 EFY and the current fiscal year (2007 EFY), the number of kebeles implementing

CMP approach increased from 360 (17.3%) of the 1,945 rural kebeles in COWASH,

FINNIWASH-BG and UNICEF woredas to 1,104 (58.6%) of the 1,885 rural kebeles in COWASH

and FINNWASH-BG woredas, excluding the rural kebeles of UNICEF. In 2004 EFY, the CMP

approach has been implemented in 637 kebeles (58.9% of the 1,081 rural kebeles of 44

COWASH, UNICEF and FinnWASH-BG woredas) of Amhara, Tigray, SNNP, BSG regional states.

In 2005 EFY, 703 kebeles (54.9 % of 1,280 rural kebeles) of 53 COWASH, UNICEF and

FinnWASH-BG woredas in five regions (Amhara, Tigray, SNNPR, Oromia and BSG) have been

implementing the approach. A total of 916 kebeles (662 in Amhara, 47 in Tigray, 70 in SNNPR,

Page 12: COMMUNITY-LED ACCELERATED WASH (COWASH) PROJECT...being finalized in the reporting period. Thus far, the consultant submitted all of the 18 parts of the manual and strategic framework

6

61 in Oromia, and 76 in BGR) in COWASH and FinnWaSH-BG woredas (53.6 % of the 1,709

kebeles including FinnWaSH-BG kebeles) have been implementing the CMP approach in 2006

EFY. In the reporting period, the CMP approach is being implemented in 1,104 kebeles in 76

woredas of five regions of the country. Since 2006 EFY, UNICEF has stopped using the CMP

approach in Amhara and hence UNICEF’s CMP woredas and kebeles are not included in the

COWASH reports.

Table 2: Number of Regions, Woredas and Kebeles Implementing CMP Approach

COWASH UNICEFFinnWASH-

BGTotal COWASH UNICEF

FinnWASH-

BGTotal %

Amhara 153 19 8 27 120 40 40 26.1 732

Tigray 36 0 0 0 7 7 19.4 62

SNNPR 125 0 0 0 8 8 6.4 105

Oromia 249 0 0 0 12 12 4.8 101

BSGR 20 5 5 76 4 5 9 45.0 104

Total 583 19 8 5 32 196 71 0 5 76 13.0 1,104

Region

Total No.

of Rural

Woredas

No. of CMP Woredas & Kebeles

CMP Woredas in 2007 EFYNo. of CMP

Kebeles in

2007 EFY

CMP Woredas in 2003 EFY No. of

CMP

Kebeles in

2003 EFY

Note: UNICEF CMP woredas and kebeles are not included in the table as CMP implementation by UNICEF has not been valid starting

from 2006 EFY.

With regards to water supply scheme beneficiaries, some 1.47 million rural people in 67

woredas of the four project regions of Amhara, Tigray, SNNPR and Oromia have benefited from

6,007 communal water points constructed until end of March 31, 2015. More than 105,380

students and teachers and 12,989 health staff and beneficiaries of the facilities have benefited

from the 264 school and 60 health facilities’ water points constructed with the support of the

project.

Moreover, more than 79,008 students and teachers (50.5% female) 2,649 health staff and

some beneficiaries of health institutions (50.0% female) have benefitted from the 69 school

and 46 health institutions’ latrines constructed with the support of the project until end of

March 31, 2015.

As far as allocation of funds is concerned, as indicated in the revised Project Document, the

five COWASH regions have committed to allocate more than half a billion birr (Birr 501,827,

227) for the implementation of the project activities until end of 2008 EFY (Table 2). About

5.1%, 14.0%, 27.1% and 37.4% of the committed funds have been allocated for 2004 EFY,

2005 EFY, 2006 EFY and 2007 EFY, respectively. In sum, much of the committed funds

(83.6%) has been allocated for the project for the 4 years of implementation of the project.

The GoE budget allocation in the four regions (Amhara Tigray SNNPR and Oromia) has shown

a huge growth (167.0%) from 2005 EFY to 2007 EFY.

Table 2: Budget Committed and Allocated for COWASH by Regional States

2004 EFY 2005 EFY 2006 EFY 2007 EFY

Total Allocated

(2004-

2007EFY)

Amhara 239,634,780 20,537,000 38,096,900 64,682,503 100,885,262 224,201,665

Tigray 92,838,635 2,427,352 14,127,300 30,111,071 38,688,525 85,354,248

SNNPR 77,400,262 2,559,304 7,791,305 20,553,155 30,133,464 61,037,228

Oromia 72,153,550 10,553,549 20,869,323 14,411,890 45,834,762

BSG 20,800,000 4,000,000 4,000,000

Total 502,827,227 25,523,656 70,569,054 136,216,052 188,119,141 420,427,903

Region

Budget Allocated (in Birr)Amount

Commited to be

Allocated by

Regions (in

Birr)

Page 13: COMMUNITY-LED ACCELERATED WASH (COWASH) PROJECT...being finalized in the reporting period. Thus far, the consultant submitted all of the 18 parts of the manual and strategic framework

7

4 COMPONENT 1: STRENGTHENING THE FEDERAL CAPACITY TO IMPLEMENT

COMMUNITY MANAGED PROJECTS ALONGSIDE WITH A SUPPORT TO THE

ESTABLISHMENT OF THE ONE WASH NATIONAL PROGRAM

Component 1 of the COWASH project strives to strengthen the federal level capacity for

implementation of the CMP approach and to support the overall WaSH sector development

process. It also strives to support the establishment and implementation of One WaSH

National Program. In order to scale-up the CMP approach, tools in planning, implementation

and monitoring mechanisms were developed for a wider application of the CMP approach.

Networking and coordination activities have been performed to promote CMP and generate

more funds for CMP implementations thereby accelerate the WaSH interventions in water

supply access, sanitation and hygiene.

In 2007 EFY, the project planned to widen and deepen its support in contributing for the

achievement of the GTP targets of WaSH by providing technical and financial support to NWCO

and other stakeholders of the project. The Component 1 major activities performed during the

reporting period are presented under the outputs indicated below (Component 1 detailed

activities performed in the reporting period are attached in Annex 1). It should be noted that

all the activities performed by the federal COWASH team do not automatically belong to

Component 1 but support directly Component 2 (the project regions).

4.1 RESULT 1 OF COMPONENT 1: COMMUNITY MANAGED PROJECT APPROACH

SCALED-UP AT NATIONAL LEVEL

4.1.1 Output 1: Manuals and Guidelines Reviewed and Developed for Standardizing

the CMP Implementation within the WaSH Implementation Framework

The achievement of the output is measured by the three indicators: i) number of generic CMP

implementation guidelines harmonized with WIF and incorporating crosscutting issues

developed and implemented, ii) number of tested higher technology options reviewed and

incorporated into CMP manuals and guidelines and iii) number of generic O&MM

manuals/guidelines for rural water supply developed.

A number of manuals/guidelines have been prepared in the last fiscal years. Some main

activities were planned to be executed in the reporting period: i) Participate as a member of

the Task Force in the development of Generic RPS and Pastoralist areas Water Supply O&MM

Manual and Strategic Framework; ii) Provision of technical assistance in the development of

GLOWS/Water Safety Planning Guideline for CMP point water schemes; iii) Assist in the

approval of the CMP Implementation Manual by the MoFED; and iv) Develop new CMP financial

management manual training materials using Public Financial Management System (PFMS) in

CMP Implementation.

The analysis of the status of the above and some other documents and manuals are presented

below.

4.1.1.1 Participation in the Task Force in the Development of Generic Rural Water Supply O&MM RPS and Point Water Schemes and Generic O&MM Strategic Framework

The guideline and strategic framework have been under preparation in the last fiscal year

based on the table of content prepared based on comments and suggestions of a half-day

meeting of the taskforce established to lead the assignment. The preparation of the manual

Page 14: COMMUNITY-LED ACCELERATED WASH (COWASH) PROJECT...being finalized in the reporting period. Thus far, the consultant submitted all of the 18 parts of the manual and strategic framework

8

and framework has continued in the reporting period with the overall guidance of the

taskforce. In the third quarter, all the 18 parts of the manual and generic strategic framework

are completed and many of these parts have been commented by the taskforce members. The

manual and strategic framework will be completed by incorporating comments by taskforce

members and participants of a workshop that is scheduled to be held in April 2015.

4.1.1.2 Translation of GLOWS/WSP Guideline into Amharic

COWASH planned to promote and implement GLOWS and Water Safety Planning

(GLOWS/WSP) in its project woredas. For this purpose the English version of the GLOWS/WSP

guideline prepared by MetaMeta should be translated into regional working languages:

Amharic, Oromifa and Tigrigna. The training guideline has been translated into Amharic by a

private consultant experienced in GLOWS and commented by COWASH FTAT and some

experienced Amhara RSU. The Amharic version will be translated into Oromifa and Tigrigna so

that it can be used in the trainings in Tigray and Oromia woredas.

4.1.1.3 Developing GIS based mapping trainers manual

It was planned to prepare a manual for GIS training of regional, zonal and woreda staff of

project regions. Accordingly, the GIS Expert has prepared a training manual and distributed to

trainees in digital and hardcopy during the GIS trainings in the regions. The manual will be

improved through comments from the trainees in the regions and incorporating self-learning

exercises.

4.1.1.4 Editing of the Point Source O&M Manual for rural water supply

It was planned to edit the Point Source O&M Manual completed last fiscal year to make it

suitable for training at the grassroots level. The activity has not yet been started as it was

found important to make the editing together with the RPS O&MM manual being finalized.

4.1.1.5 Approval of the CMP Implementation Manual based on Public Financial Management System

(PFMS)

The CMP Implementation Manual as per the Public Financial Management System has been

finalized by private consultants and it was submitted to MoFED for approval. The manual was

commented by MoWIE staff and a half-day workshop participants. Once it is approved, the

manual will be part of POM. However, there is not feedback yet from MoFED and a number of

important federal and regional level activities planned are pending due to the delay in the

approval of the manual by MoFED.

4.1.2 Output 2: Tools and Mechanisms Reviewed and Developed for Standardizing

the Planning, Implementation and Monitoring of CMPs

Four indicators were set to measure the achievement of the output, namely, i) number of

annual plans prepared; ii) number of quarterly reports prepared and disseminated to partners;

iii) M&E framework developed; and iv) number of federal level steering committee meetings

conducted.

As in the previous implementation years, as indicated in Annex 1, a series of activities that are

believed to contribute for the achievement of the output were planned to be carried out in the

reporting period. The status of some of the main activities are presented as follows:

Page 15: COMMUNITY-LED ACCELERATED WASH (COWASH) PROJECT...being finalized in the reporting period. Thus far, the consultant submitted all of the 18 parts of the manual and strategic framework

9

4.1.2.1 Preparation of Annual Plans

The 2007 EFY COWASH Component 1 (C-1) annual plan has been prepared and approved by

the NWSC early in the first quarter of the fiscal year. Moreover, COWASH FTAT has been

assisting in the preparation of regional plans. Planning templates (physical and financial) and

unit costs were prepared and distributed to RSUs to modify them to be suitable to their

situation and employ them in their planning exercises. Consequently, all of the project regions

have finalized their annual plans and approved by the respective RWSCs in the second quarter.

4.1.2.2 Participation in Federal WaSH Steering Committee Meetings

National and Regional WaSH Steering Committee meetings are expected to be made twice a

year. COWASH facilitates the meetings and provides technical assistance for undertaking these

meetings. Usually, quite a lot of issues and challenges hindering the implementation of the

project are raised and deliberated and important decisions are being made during these

meetings. In the reporting period, two National Wash Steering Committee (NWSC) meetings

were held. During this meeting, Component 1 performance reports of 2006 EFY, 2007 EFY

annual plan and the 2007 EFY semi-annual report have been discussed and endorsed. Issues

related to the CMP Implementation Manual based on the Public Financial Management System

(PFMS) were discussed during the 2nd NWSC meeting in 2007 EFY.

4.1.2.3 COWASH Quarterly Report Preparation

Every fiscal year, COWASH is expected to prepare four progress reports – one annual report

and three quarterly reports. In the reporting period, the 2006 EFY annual, the 2007 EFY first

quarter report and the 2007 EFY semi-annual performance report have been prepared

(100.0%). All of these reports were distributed to stakeholders. Moreover, a summarized

version of the first phase of the project’s Results-Based Report and the 2007 EFY semi- annual

report were prepared and distributed to stakeholders. On top of these, quarterly performance

reports of the Component 1 including some construction achievements of regions have been

submitted to MoWIE.

4.1.2.4 Indicator Monitoring Plan Preparation

COWASH planned to complete the indicator monitoring plan preparation of four regions.

Accordingly, the indicator monitoring plans of the four regions have been prepared based on

the baseline data collected from the regions and project woredas. The indicator monitoring

plan of BSG region will be prepared in the 4th quarter based on the baseline data collected

from the project woredas.

4.1.2.5 Production of WASH facility maps for each COWASH woreda

COWASH planned to produce 67 maps (one for each project woreda) in the fiscal year, of

which 40 were planned for the reporting period. Accordingly, the GIS expert produced 15

woreda maps (37.5%). The maps of the 25 woredas were not produced as the GIS expert has

been engaged in FINNWASH-BG project data collection and mapping and training of the

woreda staff on GIS and basic computer skills.

4.1.3 Output 3: CMP Approach within the Rural WaSH Scientifically Researched

Three indicators are set for measuring the achievement of this output. These are: i) number of

CMP researches (disaggregated by Doctoral, Masters and Bachelor levels) completed;

ii) number of published articles on CMP research results; and iii) number of CMP research

result presentations given in international conferences.

Page 16: COMMUNITY-LED ACCELERATED WASH (COWASH) PROJECT...being finalized in the reporting period. Thus far, the consultant submitted all of the 18 parts of the manual and strategic framework

10

So far, one PhD level and one MSc level researches are underway and 4 MSc level and 1 BSc

level researches on CMP were completed with the financial and technical support of COWASH.

All the completed researches are uploaded in the website www.cmpethiopia.org. Some

activities have been carried out in the reporting quarter. The main ones are indicated below:

4.1.3.1 Continuation of the PhD level research

This fiscal year, the PhD level research has continued. In this reporting period, four articles

have been prepared and some are submitted for publication in reputable journals. The status

of the four articles is indicated below.

Article I: ‘Evolution of Community Managed Water Supply Projects (CMP) from 1994 to the

2010s in Ethiopia’ planned to be published in the Journal of Public Works

Management and Policy was commented by the reviewers.

Article II: ‘Community Managed Projects and other Implementation Approaches in Rural Water

Supply of Ethiopia’ submitted for the Journal(: Waterlines) is under review.

Article III: ‘Service Failures of Rural Water Supply Systems in Ethiopia and Their Policy

Implications’ submitted to Journal of Natural Resources Forum is under review

Article IV: ‘Lessons from indigenous practices of water system management: Case of Borana

and

Konso, Ethiopia’ is targeted for the Journal of Developmental Studies and is

currently under co-authors review

4.1.3.2 New MSc level research

A new MSc level CMP research was started in Gonji Kolella woreda of Amhara region with the

financial support of COWASH. The research is entitled “Assessment of Potable Water Access &

Users’ service satisfaction in Gonji Kolella woreda rural communities during CMP

implementation”. The researcher has submitted the draft thesis report and comments were

given by COWASH FTAT.

4.1.3.3 Case study on the Impact of CMP Water Supply in Gonji Kolella Woreda

COWASH has conducted a case study on the impact of CMP water supplies on the life of rural

community in Gonji Kolella woreda of West Gojjam Zone of Amhara region. It was found out

that the implementation of rural water supply schemes using CMP funding mechanism created

sense of ownership and motivation to rural communities in Abunebla and Besanit village. Since

the introduction of this approach in the area, rural communities have understood the value and

ownership of water resources. Farmers are looking to improve their livelihood using the excess

water from the improved sources and rope pumps. All households visited stopped open

defecation and practice hand washing at critical moments. The project has also a plan to carry

out another case study on women empowerment in the upcoming quarter.

4.1.4 Output 4: Information, Education and Communication (IEC) on CMP

Implementation Modality Enhanced

The major indicators for measuring the achievement of the output are: i) Communication

strategy developed; ii) Number of major international and national events (workshops,

seminars, conferences, symposiums) where CMP awareness is raised through COWASH

participation; and iii) Number of CMP related information and education materials prepared

and published (disaggregated by types).

As indicated in Annex 1, a number of communication-related activities were planned for the

reporting period. The major ones and their status are indicated hereunder:

Page 17: COMMUNITY-LED ACCELERATED WASH (COWASH) PROJECT...being finalized in the reporting period. Thus far, the consultant submitted all of the 18 parts of the manual and strategic framework

11

4.1.4.1 Production and distribution of table calendars with CMP incorporated

COWASH produced its own table calendars in the first month of the reporting period. A total of

6,500 CMP table calendars (100.0%) were produced and disseminated to all 5 regions, zones,

woredas and also to the stakeholders at federal level. These calendars are believed to promote

CMP in the COWASH woredas and beyond.

4.1.4.2 Participation in selected International conferences, networking and forums

COWASH has been supporting participation in international conferences, networking meetings

and forums so as to promote CMP at the international and national levels. This reporting

period, it was planned to participate 3 MoWIE staff in Stockholm Water Week 2014.

Accordingly, three MoWIE staff (Abiy Girma, head of NWCO, Nuredin Muhammed, director of

WSSD and Lakech Haile, director of WCYD) participated in the conference with the sponsorship

of COWASH. The project has also sponsored the stand of MoWIE exhibition, which was

successfully carried out.

4.1.4.3 Participation in selected national events (WWD & March 8)

COWASH planned to assist the MoWIE in celebrating international events in the country.

Financial and technical support has been provided in organizing the World Water Day (WWD)

and World Women’s Day (March 8) celebrations. Moreover, a two pages article that focused on

introducing the readers with CMP and COWASH achievements was prepared and published in

WWD publication. One workshop, where COWASH participated, was held on March 20 focused

on self-supply and another workshop on March 21 focused on WWD objective and themes. On

March 22 the WWD was colorfully celebrated in MoWIE. In addition, there was also an

exhibition at MoWIE compound on “WASH as a business” where private sector and NGOs

presented their products. Besides funding the event, COWASH assisted in preparing ToR,

selection of an entertainment enterprise, preparing magazine and banner, and following-up

drama performance and facilitation of the March 8 celebration.

4.1.4.4 Water Credit Market Assessment Report Dissemination Workshop

The water credit market assessment was carried out by M2i consultants from India with the

support of Water.Org and co-operation of COWASH. On July 23, 2014, a workshop was

organized jointly with Water.org, WaterAid and COWASH. A total of 73 participants (7 female)

participated in the one-day event facilitated by COWASH CTA. In this workshop, findings and

experience of the WASH/MFI workshop held on October 2012 was presented by COWASH CTA

and experiences from Kenya, Uganda and India were also presented at the workshop.

COWASH also assisted in commenting the data collection instruments and draft report.

4.1.4.5 Updating CMP WEB page

The official CMP website (www.cmpethiopia.org) was developed in collaboration with IRC to

disseminate basic information on CMP and attract more funding for the country. In the

reporting period, the website was redesigned and updated regularly and a number of

WASH and related documents have been uploaded. This website is also assisting in

providing information on Ethiopian WASH sector through uploading major WASH related

documents. COWASH has been receiving appreciations from many international and

national organizations for availing important WASH related documents at the CMP web

page.

Page 18: COMMUNITY-LED ACCELERATED WASH (COWASH) PROJECT...being finalized in the reporting period. Thus far, the consultant submitted all of the 18 parts of the manual and strategic framework

12

4.1.4.6 Incorporating COWASH as a Case study into the Water Integrity Network (WIN) Flagship

Publication

The Water Integrity Network (WIN) and other institutional partners are working on a flagship

publication on water integrity to be released at Stockholm World Water Week 2015. WIN

proposed to include COWASH as a case study in the section of 'WRM and Access to Water and

Sanitation in Rural Areas' of the flagship publication. Accordingly, COWASH team drafted the

case study and submitted to the organizers. The draft of the case study has been published in

http://www.cmpethiopia.org/page/184.

4.1.4.7 Organizing Exhibition on Finnish Financed Projects in Ethiopia

The Minister of Development Cooperation of Finland (Ms Sirpa Paatero) paid a visit to Ethiopia

specifically to Amhara region on Jan 8-10, 2015. COWASH, together with the other five

Government of Finland financed development cooperation projects, organized an exhibition on

Jan.9, 2015 in Bahir Dar as part of the visit of the Minister. The Minister visited a COWASH-

funded water point in Yeloma Kebele of Bahir Dar Zuria woreda and visited and made

discussion with a beneficiary household in the same kebele. COWASH has prepared a set of

profiles of the project both in English and Finnish languages and a case study of one Steward

of the water point selected for the visit and disseminated to the participants of the Exhibition.

The responsibility of the practical arrangements of the visit was carried by AGRO-BIG project

in collaboration with Amhara RSU staff.

Besides, COWASH facilitated visits and provided information about the project performance to

independent reviewers of the effectiveness/results of Finland’s development cooperation in its

current form. The objective of the review, commissioned by MFA, is to present a general

indication on how effective and impactful Finland's development cooperation can be considered

and why. The reviewers (Mrs Ritva Reinikka and Mr. Jim Adams) visited Abichu-gena woreda,

a COWASH woreda in Oromia, on 8th of March 2015. The project has also facilitated the

meeting of the reviewers with the State Minister and Directors of MoWIE held on March 6,

2015.

The project facilitated the visit of a team of 16 journalists from Finland to Fogera woreda of

Amhara region. The team visited two water points (one community and one school) and paid

visit to a household in Maksegnit kebele of the same woreda.

4.1.4.8 Preparation of Comprehensive Information Package of COWASH and CMP approach

The project planned to prepare information package on COWASH and CMP approach so as to

promote the approach and through disseminating working systems and achievements.

According, information pack on CMP approach and achievements of COWASH project was

prepared and disseminated to visitors and journalists coming from Finland to visit the project.

This package includes fact sheets on COWASH at the federal level and Amhara region, a case

story and CMP cycles.

4.2 RESULT 2 OF COMPONENT 1: CMP IMPLEMENTATION CAPACITY AT THE

FEDERAL AND REGIONAL LEVELS DEVELOPED

4.2.1 Output 1: Capacity Building Instruments Reviewed and Developed

The achievement of the output is to be measured by three indicators: i) Generic CMP capacity

building strategy developed; ii) Generic woreda level capacity building package developed;

and iii) number of impact assessments made on CMP related trainings (one in each project

region).

Page 19: COMMUNITY-LED ACCELERATED WASH (COWASH) PROJECT...being finalized in the reporting period. Thus far, the consultant submitted all of the 18 parts of the manual and strategic framework

13

The project has developed generic CMP capacity building strategy and generic woreda level

capacity building package in the previous implementation years. The capacity building

strategy has been revised every year to capture new developments in the WaSH sector.

Moreover, training impact assessment on trainings conducted in 2004 EFY was completed

and an in-depth study was conducted on CMP trainings conducted in 2005 EFY in Amhara and

Tigray regions.

Some of the main activities planned for the reporting period were the completion of the

training impact research and the transfer of the impact research findings into the capacity

building strategy, conducting another training impact assessment in SNNP and Oromia

regions. Accordingly, the research report was completed by the consultant by including all

the comments and suggestions forwarded by stakeholders: development partners, MoWIE

representatives and COWASH federal and regional unit staff. The report is uploaded to the

CMP website http://www.cmpethiopia.org/page/184. The project has hired a Human Resource

Development (HRD) Specialist and the review of the impact assessment research was

completed.

Furthermore, the second training impact assessment planned to be conducted in Oromia and

SNNPR is just started. Agreement was concluded and the private consultant has submitted

inception report and questionnaire and checklists and comments have been made by

COWASH FTAT. The consultant is expected to submit the revised inception report with

questionnaires and checklists.

4.2.2 Output 2: Capable and Adequate Personnel in place for CMP Implementation at

National and Regional Levels

Number of people hired at federal and regional level (disaggregated by sex), number of

trainings given by the federal COWASH team and number of people participated in trainings

(disaggregated by sex) are the indicators set to measure the achievement of the output.

COWASH planned to carry out a number of capacity building activities in the reporting period.

The activities were planned to be conducted at the federal and regional levels. The major

activities and their achievements in the reporting period are the following.

4.2.2.1 Hiring of Staff for Phase II of COWASH

Ramboll hired all the 12 staff needed for COWASH Phase II as per the revised project

document (100%). This includes the HRDS. All of the COWASH Phase I national staff and the

GIS Specialist continued to Phase II and the 4 additional national and international staff

(Crosscutting Specialist, Communication Specialist, HRD Specialist and Junior Professional

Officer) were included. All of them have assumed their post.

Moreover, it was planned to provide technical assistance to Water Bureau of BSG region in the

hiring of 4 RSU staff. In the first quarter, the ToRs were prepared and sent and technical

assistance in recruitment process was given to the bureau. Accordingly, though it was delayed

for some time due to competing activities in the region, 4 RSU staff (Team Leader and

Capacity Building, M&E and Financial Specialists) have been hired and assumed their post in

BSG region. All the RSU staff hired, including the CMP Coordinator assigned from the regional

water bureau, and has received training on CMP management, promotion, appraisal and M&E

by COWASH FTAT. Moreover, COWASH has assigned the Cross Cutting Specialist to oversee

and assist the region in the implementation of the COWASH activities in Benishangul Gumuz

region.

Page 20: COMMUNITY-LED ACCELERATED WASH (COWASH) PROJECT...being finalized in the reporting period. Thus far, the consultant submitted all of the 18 parts of the manual and strategic framework

14

4.2.2.2 GIS/M&E Training

COWASH planned to map out its project woredas including all the facilities (community and

institutional water points and institutional latrine) constructed over the years. For this purpose,

training of regional and woreda staff in Quantum GIS, Data Management and Basic Computer

skills were planned and executed. In the reporting period, it was planned to train Tigray,

Oromia and Amhara woreda staff. Accordingly, overall, a total of 125 woreda, zone and

regional staff (18 female) in Tigray, Oromia and Amhara region have been trained in GIS,

Water Points and Institutional Latrines data management and basic computer skill for 3- 5

days. This accounts 96.0% of the planned (138 people).

In Tigray and Oromia regions, 24(5 females) and 17 (1 female) woreda, zone and regional

staff participated in this training. In Amhara, 84 (12 females), including those trained for ToT

from region and MoWIE, were trained for 5 days in five sessions. The last training in Amhara is

underway in Dessie.

Besides, the training materials and data collection tools have been updated based on the

findings in the trainings conducted in each region.

4.2.2.3 GLOWS/WSP Training

COWASH is promoting and implementing GLOWS/WSP in view of sustaining facilities it has

been supporting in the project woredas. To attain this objective, the project has started

training staff at the federal and regional levels to cascade the capacity building down the

administrative ladder of the project regions. In the first quarter, 3 COWASH FTAT were trained

by MetaMeta for 3 days on few of the GLOWS/WSP modules together with other trainees

constituted from different organizations based in Addis Ababa. Moreover, COWASH in co-

operation with MetaMeta conducted ToT training in GLOWS-Rural Water Safety Planning

(GLOWS/WSP) for 5 days. A total of 29 staff (2 female, one each from MetaMeta and

COWASH) of COWASH FTAT, RSU and Regional Water Bureaux received the training sponsored

by COWASH.

Trainees of GLOWS/WSP learnt how to facilitate rural water assessments and action plans

preparation in water safety planning. GLOWS modules 1-10 and Kebele Water Safety Plan

Guideline provided the main resources for the training. The participants learned kebele water

safety plan preparation and its concept from resource protection to the point of use of water.

They also learned to understand the participatory approach, how to facilitate the woreda staff

trainings to become more participative and how to develop support materials to be used in

participatory training. During the training, the Amharic version of the training manual was

reviewed and made ready for training in the woredas and kebeles. The English and Amharic

versions of GLOWS manual and Kebele WSP Guideline were uploaded to the CMP web page

http://www.cmpethiopia.org/page/401. The plan is to publish these Amharic documents in a

book so that they can be adequately used at woreda level.

4.2.2.1 CMP Management Training to Regions

COWASH FTAT planned to carry out CMP management, promotion, appraisal and M&E and

WASHCO CMP management ToT training to BSG and Oromia new woreda and zonal staff.

Consequently, a total of 222 woreda, zone and regional staff (19 female) have been provided

different CMP related trainings BY COWASH FTAT, in collaboration with RSU staff, for 3 days.

This accounts 96.5% of the plan for the reporting period. The disaggregation by type of

training and region is presented below.

Page 21: COMMUNITY-LED ACCELERATED WASH (COWASH) PROJECT...being finalized in the reporting period. Thus far, the consultant submitted all of the 18 parts of the manual and strategic framework

15

In BSG region, 114 (16 females) staff have been trained in the reporting period – 76(11

females) in CMP management, promotion and appraisal and 38(5 females) in WASHCO CMP

management ToT- for 3 days. A total of 86 staff (12 females) were trained in Oromia region –

60 in CMP management, promotion, appraisal and reporting and 26 (4 females) in WASHCO

CMP management ToT- for 3 days. Among these, 34 (2 females) in BSG and 57(7 females)

were trained on CMP appraisal and & M&E for 3 additional days.

Moreover, in SNNPR, 22 woreda and zone and regional staff (1 female) have been trained in

O&MM for 3 days at Hawassa.

4.3 RESULT 3 OF COMPONENT 1: DEVELOPMENT AND IMPLEMENTATION OF

ONE WaSH NATIONAL PROGRAM SUPPORTED

In the One WaSH National Program development, COWASH is accountable for the provision

of technical assistance and financial support as per the mutually agreed terms of references.

COWASH is not, however, responsible in the development and implementation of One WaSH

National Program.

4.3.1 Output 1: COWASH Support Provided in Preparing One WaSH National

Program

Number of short-term consultancy days provided by COWASH for the development and

implementation of One WaSH National Program, and amount of finance provided for the

development and implementation of One WaSH National Program are the indicators set to

measure the achievement of this output.

COWASH has been active in the development of OWNP Phase I and it will continue its support

(technical and financial) to NWCO in the preparation of the OWNP Phase II document and

review of Phase I through participation in the task force. Last fiscal year, COWASH FTAT

contributed for the successful development of the OWNP document. Much of the activities are

planned for the upcoming quarters with the view that supports are required in the third and

fourth quarters of the fiscal year. However, much support could not be provided as request has

not been presented to COWASH. Anyhow, 10 consultancy days have been provided for the

finalization of the CMP implementation manual for CWA and POM.

4.3.2 Output 2: COWASH Support Provided in Implementation of One WaSH National

Program

Number of people trained in CMP implementation in non-COWASH regions by federal

COWASH and number of federal level advisers assigned in the One WaSH National Program

management are the two indicators set for measuring the achievement of the output.

The indicators were set with the view that OWNP will be implemented and CMP will be scaled

up in the rest of the regions of the country. However, reporting as per these indicators has not

been started as the CMP approach is not yet implemented in the non-COWASH regions.

In the period under reporting, COWASH planned to participate and provide technical and

financial support in the first Joint Technical Review of the fiscal year (JTR 9 &10), organizing

MSF7, development of the national Water Safety Plan (WSP) Guideline, and strengthening the

regional, zone and woreda WASH structures. It was also planned to provide technical

assistance in the development of planning and reporting formats of OWNP upon request of the

NWCO.

Page 22: COMMUNITY-LED ACCELERATED WASH (COWASH) PROJECT...being finalized in the reporting period. Thus far, the consultant submitted all of the 18 parts of the manual and strategic framework

16

WSP Guideline Development: a ToR was prepared by the MoWIE on Climate Resilient Water

Safety Plan implementation and on establishment of Task Force. Revision of the ToR was made

based on the comments of COWASH CTA. COWASH has also provided its feedback on the

questionnaires prepared by WHO on the experience of COWASH in WSP in Amhara region. The

draft rural and Urban Water Safety strategy document was made by a consultant and COWASH

provided 10 TA days technical support through commenting and participation in Task Force

meeting to review the documents.

Joint Technical Review (JTR 9 &10) and MSF 7: The first draft ToR for JTR 9 and MSF 7

was drafted by COWASH CTA. CWA partners conducted CWA-Project review in Dec. 2014

according to POM. However, due to the busy schedule of the regions and federal ministries in

massive trainings for staff, preparations for JTR and MSF have been postponed and COWASH

could not provide its planned technical support in the reporting period. Anyhow, the second

JTR, which will be conducted by One WASH partners, is pushed to late January-early February

2015. Therefore, the 2007 EFY MSF 7 cannot be held in the third quarter.

Strengthening of the WASH structure: COWASH has been strengthening the WASH

structure through trainings, awareness raising workshops and meetings and covering some

running costs. In the reporting period, Regional WASH Steering Committee (RWSC) on

COWASH meetings of all the project regions (50.0%) have been held and many of the

members attended the meetings and decisions have been passed. Moreover, zone and woreda

WASH Team members have attended the CMP management, promotion and M&E trainings for

BSG and Oromia woredas. In these trainings, awareness on the WASH M&E-MIS and Guidance

and Governance of WASH have been given.

Support in the development of Planning and Reporting Tools: Technical support have

not been extended as there was no specific request presented to COWASH.

Page 23: COMMUNITY-LED ACCELERATED WASH (COWASH) PROJECT...being finalized in the reporting period. Thus far, the consultant submitted all of the 18 parts of the manual and strategic framework

17

5 COMPONENT 2: ESTABLISHING AND STRENGTHENING THE CAPACITY IN

REGIONS TO SCALE-UP IMPLEMENTATION OF CMP

The original document of COWASH had three components-Component 1, Component 2 and

Component 3. The two components (Component 2 and 3) are now merged into one

Component in the revised project document. This new component aims at building the capacity

of target Regions, Zones and Woredas to plan, manage, monitor and implement WaSH

interventions through the CMP approach; deliver financial and procurement services for CMP

interventions at all levels; and to increase the sustainable community and institutional access

to safe water, sanitation and hygiene in the target areas.

The major achievements of the regions during the first nine months of 2007 EFY are indicated

hereunder.

5.1 RESULT 1 OF COMPONENT 2: TARGET REGIONS, ZONES AND WOREDAS

CAPABLE TO PLAN, MANAGE, MONITOR AND IMPLEMENT RURAL WaSH

INTERVENTIONS USING CMP APPROACH

The major achievements of the regions in the reporting period in planning, managing,

monitoring and implementing WaSH interventions through CMP approach are presented in the

following output levels.

5.1.1 Output 1: Regional Support Units (RSU) Established and Functional

Number of Regional Support Unit (RSU) staff hired (disaggregated by region and sex), number

of annual COWASH work plans produced and number of COWASH quarterly and annual reports

produced as per the annual plan are set to measure the achievement of this output of

Component 2.

All project regions have hired adequate staff in previous years of implementation of the

project. What was remaining was the hiring of 4 RSU for Benishangul Gumuz region. The new

region has hired four Specialists (Coordinator, Capacity Building, M&E and Financial) in the 2nd

quarter. Process is underway to fill the Oromia Financial Specialist position, who left office in

the 2nd quarter.

All project regions were expected to prepare and approve their annual plans of the project.

Accordingly, regions have prepared the 2007 EFY plans of the project, with the participation of

woreda, zonal and regional stakeholders, and approved by the respective Regional WASH

Steering Committees. The preparation and approval of the regional plans were extended to the

2nd quarter due to one or more of the following reasons: i) delay in the announcement of

shares of the annual budget of the woredas and zones from the regional governments and

other competing activities (soil and water conservation, irrigation, etc.) in the regions.

Regions are also expected to prepare and submit four performance reports (3 quarterly and

one annual) to Embassy of Finland. In the reporting period, RSUs of the four COWASH regions

have prepared and submitted the 2006 EFY annual (physical and financial) reports and the

2007 EFY first two quarters performance reports (100.0%). The first quarter performance

reports of the regions were not formal as their plans have not been approved and there were

no many activities performed in the quarter.

Besides, unlike the previous fiscal years, the 2007 EFY first Regional WaSH Steering

Committee (RWSC) on COWASH meetings have been conducted timely. The RWSCs have

endorsed the 2007 EFY annual plans and made decisions on a range of issues of the project

Page 24: COMMUNITY-LED ACCELERATED WASH (COWASH) PROJECT...being finalized in the reporting period. Thus far, the consultant submitted all of the 18 parts of the manual and strategic framework

18

which speed up the implementation of the project. The 2nd meeting of the RWSCs on COWASH

has not been conducted in the reporting period.

5.1.2 Output 2: Regions, Zones and Woredas Capacitated to Implement Rural WaSH

through CMP

Number of training types held by region, zone and woreda (disaggregated by type of training),

number of people (disaggregated by sex and type of training) participated in trainings given by

regions, zones and woredas and number of water pints and institutional latrines built as per

plan (proxy indicator) are the indicators set to measure the achievement of the output.

The scaling-up of the CMP approach requires extensive human capacity building activities at

the regional, zonal and woreda levels. A number of trainings were expected to be carried out in

the new woredas and zones of the project regions. Some trainings which were not conducted

in the previous fiscal year and refreshment trainings should be carried out in the reporting

period. Accordingly, many trainings have been carried out in the project regions and the

human capacity building performance in the reporting period are presented hereunder.

5.1.2.1 Trainings Conducted in SNNPR in the First Nine Months of 2007 EFY

A total of 20 trainings were planned to be conducted in the reporting period. Among these, 11

types of trainings (55.0%), many of them rolled over from 2006 EFY, have been carried out as

planned. The main trainings conducted at the regional and woreda levels are: 1) O&MM ToT

training for woreda and zone staff; 2) WASHCO training in Scheme Management; 3) CLTSH

training on for kebele level experts; 4) KWT CMP management, promotion and appraisal

training; 5) WASHCO CMP management training; 6) artisans training; 7) pump attendants and

care takers training; 8) KWT gender awareness and mainstreaming training; and 9) WASHCO

training in Water Quality.

The trainings were given to a total of 2,743 (44.2% female) people with an estimated cost of

Birr 1.85 million. The number of people trained accounted about 30.0% of the people planned

to be trained in the nine months.

Page 25: COMMUNITY-LED ACCELERATED WASH (COWASH) PROJECT...being finalized in the reporting period. Thus far, the consultant submitted all of the 18 parts of the manual and strategic framework

19

Table 3: Trainings held in SNNPR in the First Nine Months of 2007 EFY

M F T M F T

1CMP Management Training for ZWT, WWT &

appraisal team

COWaSH

FTAT & RSU135 0 135 0 0 0 0 0 0

2CMP Promotion, Application, Appraisal & M&E

Training for CMP appraisal team

COWaSH

FTAT & RSU52 0 52 0 0 0 0 0 0

3 WaSHCO ToT in CMP ManagementCOWaSH

FTAT & RSU48 0 48 0 0 0 0 0 0

4 O&M ToT Training for Zonal &Woreda technical staffCOWaSH

FTAT & RSU28 28 28 27 1 28 27 1 28 3 64,208

5 ToT Training in Water Safety Planning/GLOWS RSU 52 26 52 0 0 0 0 0 0

6Financial management & Utilization training for Zonal

& Woreda technical staffBoFED 50 0 50 0 0 0 0 0 0

7 WASHCO Training in Scheme Management WWO 1,460 376 1460 0 0 0 185 124 309 3 to 4 235,342

8 Pump attendants & care takers Refreshment Training WWO 380 85 380 0 0 0 0 0 0

9 CLTSH ToT Training (for Woreda & Zone staff) BoH 86 0 86 0 0 0 0 0 0

10 CLTSH Training for Kebele Level Experts W HO 585 190 585 131 39 170 208 119 327 5 272,433

11 KWT CMP Promotion & Appraisal Training WWO 328 82 328 167 116 283 249 145 394 3 to 4 325,725

12 WASHCO CMP Management Training WWO 2692 731 1851 388 415 803 543 575 1118 4 to 5 589514

13 WASHCO CMP Management refreshment Training WWO 1030 275 1030 0 0 0 0 0 0

14 Refreshment of WASHCOs in O&M training WWO 800 402 398 0 0 0 0 0 0

15 New artisans Training WWO 114 15 14 0 0 0 9 9 18 28 49,815

16 Refreshment training for old artisans WWO 49 15 49 0 0 0 11 4 15 7 13,359

17 Pump Attendants & Caretakers Training WWO 858 280 713 0 0 0 87 57 144 4 to 5 90,698

18 Kebele strategic plan in 5 kebeles per Woreda WWO 0 0 0 0 0 0 15 10 25 4 15,000

19 WASHCOs GLOWS/WSP Training WWO 2443 380 1292 0 0 0 0 0 0

20 KWT gender awareness & mainstreaming Training WWAO 605 310 605 0 0 0 144 118 262 4 107,136

21 Training of WASHCOs in Water Quality WWO 266 103 103 0 0 0 53 50 103 4 84,964

12 ,06 1 3 ,298 9,259 71 3 571 1 ,284 1 ,531 1 ,2 1 2 2 ,743 1 ,848, 1 94

Number Trained Estimated cost

of training (in

Birr)3rd Quarter Cumlative

Annual3rd

QuarterCumulative

No. of

Days

Trained

Total

S/

NType of Training Trainer

No. of Trainees Planned

5.1.2.2 Trainings Conducted in Tigray Region in the First Nine Months of 2007 EFY

In Tigray region, 20 types of trainings were planned to be executed in the fiscal year. All of

these were planned to be executed in the reporting period. However, only half of them

(50.0%) have been conducted in the reporting period due to delay in the approval of the

annual work plan and presence of competing activities in the woredas and region. The main

trainings conducted were: i) WWT CMP management refreshment; ii) CMP promotion,

appraisal and M&E; iii) Water Schemes O&M refreshment; iv) CLTSH for kebele level experts;

v) KWT CMP promotion and appraisal; vi) WASHCO CMP management; and vii) O&M for

WASHCO members.

Overall, 2,156 people have received different trainings with an outlay of about Birr 1.18

million. This accounts about 33.7% of the planned for the reporting period. Among the trained

people, 909 (42.2%) were female.

Page 26: COMMUNITY-LED ACCELERATED WASH (COWASH) PROJECT...being finalized in the reporting period. Thus far, the consultant submitted all of the 18 parts of the manual and strategic framework

20

Table 4: Trainings held in Tigray Region in First Nine Months of 2007 EFY

M F T M F T

1 WWT CMP Management TrainingCOWASH

FTAT & RSU15 0 15 0 0

2CMP Promotion, Application, Appraisal & M&E

Training

COWASH

FTAT & RSU20 0 20 0 0

3 WASHCO ToT in CMP ManagementCOWASH

FTAT & RSU15 15 15 0 0

4 WWT CMP Management refrshemnet Training RSU 15 0 15 0 19 4 23 1 28,414

5CMP Promotion, Application, Appraisal & M&E

Refreshment TrainingRSU 20 0 20 0 19 4 23 1

6 WASHCO Refreshment TOT in CMP Management RSU 0 0 0 0 0

7 Financial training for Finanace Personel BoFP 30 0 30 0 0

8 Refreshment TOT in O&M of water schemes RSU 20 0 20 0 6 2 8 3 25,380

9 Pump Attendants & Caretakers Training BoW & RSU 738 738 738 0 0

10 CLTSH ToT Training BoH 28 28 28 0 0 0 0 0 0

11 CLTSH Training for kebelle level experts Wo H 315 0 315 0 336 151 487 5 218252

12 CLTSH Training for Woreda level experts Wo H 0 0 0 0 0

13 KWT CMP Promotion & Appraisal Training WoW 175 0 175 0 167 98 265 3 142,773

14 WASHCO CMP Management Training WoW 2040 0 2040 0 488 427 915 5 537,392

15WASHCO CMP Management Refreshment

Training WoW 0 0 0 0 0

16 Artisans Training WoW 105 105 105 0 0

17 Artisans refreshment Training WoW 0 0 0 0 0

18 WASHCO Training in scheme management WoW 0 0 0 0 0

19 Kebelle level trigering training Wo H 0 0 0 0 0

20 Instutional WASHCO training for latrine building WoW 0 0 0 0 0

21 GLOWS/WSP ToT Training BoW 20 0 20 0 12 3 15 4 59,100

22 KWT gender awareness & mainstreaming Training WoWA 280 0 280 0 52 120 172 2 76,910

23 WASHCO GLOWS/WSP Training WoW 35 0 35 0 0

24 O & M Training for WaSHCO members WoW 2190 2190 2190 0 79 76 155 2 83,743

25 School club WASH Training WoW & Wo H 280 280 280 0 69 24 93 3 3,917

26 Gender awareness & mainstreaming Training BoWA 24 24 24 0

27 WASH Training for school girls clubs and teachers BoE 34 34 34 0 0

6 ,399 3,414 6 ,399 - - - ##### 909 2 , 1 56 1 , 1 75,881 Total

S/

NType of Training Trainer

No. of Trainees Planned Number Trained Estimated cost

of training (in

Birr)3rd Quarter Cumlative

Annual3rd

QuarterCumulative

No. of

Days

Trained

Note: WoWA- Woreda Women Affairs Office; WoW – Woreda Water Office; BoH – Regional Health Bureau

5.1.2.3 Trainings Conducted in Amhara Region in the First Nine Months of 2007 EFY

In Amhara, 15 types of trainings were planned to be conducted in 2007 EFY. Majority of them

were planned to be started in the reporting period. Accordingly, over 93.0% of the planned

trainings have been conducted in the reporting period (Table 5).

Some of the main trainings conducted in the region were: i) WWT CMP Management; ii) CMP

Promotion, application, appraisal & M&E; iii) WASHCO CMP management ToT; iv) financial

management; v) O&MM of Water Schemes refreshment ToT; vi) KWT CMP promotion and

appraisal; vii) WASHCO CMP management; and viii) water quality test.

A total of 166(26.0% of those planned) woreda and zonal staff have been trained on CMP

promotion, management, appraisal and reporting training for 2 days.

Twenty woreda experts (25.0% of those planned) were given ToT training on O&MM of water

supply schemes for 2 days at the zonal level. A total of 3,253 Kebele WASH Team members

(19.0%) have been trained on CMP promotion and appraisal for 2 days by trained woreda

experts. Moreover, it was also possible to train 10,128 (41.5% female) WASHCO members on

CMP management for 3 days at the woreda level. Woredas have also trained 515 (39.4%

female) artisans for 45 days on water scheme construction. KWT members have been given

Page 27: COMMUNITY-LED ACCELERATED WASH (COWASH) PROJECT...being finalized in the reporting period. Thus far, the consultant submitted all of the 18 parts of the manual and strategic framework

21

training on gender and mainstreaming for 2 days by trained woreda staff. More than 2300

KWT members (61.0%) have been trained in the different project woredas. Overall, over

20,857 woreda, zone and regional staff (40.5% female) have been receiving different trainings

in the woredas and zones. This accounts about 82.0% of the planned for the nine months. The

estimated costs of the trainings could not be presented as the region has not been collecting

the human capacity building costs.

Table 5: Trainings held in Amhara Region in the First Nine Months of 2007 EFY

M F T M F T

1 WWT CMP Management Training ZoW & ZoH 320 0 320 219 46 265 219 46 265 2

2CMP Promotion, Application, Appraisal

and M&E TrainingZoW & ZoH 160 0 160 139 39 178 139 39 178 2

3 WASHCO CMP Management ToT Training ZoW & ZoH 160 0 160 129 37 166 129 37 166 2

4 Financial Training for Finance Personnel BoFED 108 108 108 57 39 96 57 39 96 2

5O&MM of Water Schemes Refreshment

TrainingZoW 80 80 80 19 1 20 19 1 20 2

6 Pump Attendants & Caretakers Training WoW 1,699 0 0 - -

7 CLTSH ToT Training ZoH 80 0 80 30 3 33 43 11 54 4

8 CLTSH Training for Kebele Level Experts W OH 2,000 0 2,000 957 840 1,797 957 840 1,797 4

9 KWT CMP Promotion & appraisal Training WoW & W oH 1,400 0 1,400 1,695 398 2,093 2,637 616 3,253 2

10 WASHCO CMP Management Training WoW & W oH 8,235 8,235 8,235 4,107 2,619 6,726 5,921 4,207 10,128 3

11 Artisans training WoW 422 0 422 312 203 515 312 203 515 45

12WASHCO Training in Scheme

ManagementWoW & W oH 8,335 8,335 8,335 98 147 245 98 147 245 4

13KWT Gender Awareness & Mainstreaming

TrainingWoWA 2,000 0 2,000 898 1,404 2,302 898 1,404 2,302 2

14

Institutional WASHCO training for latrine

buildingWoW 120 120 120 32 9 41 32 9 41 3

15 Water Quality Test Training WoW & W oH 2,000 0 2,000 957 840 1,797 957 840 1,797 5

27,1 19 16 ,878 25,420 9,649 6,625 16 ,274 12 ,418 8,439 20,857 - Total

Total Cost

of Training

(in Birr)S/N Type of Training

Trainer

Number Trained

Annual

No. of

Days

Trained3rd

Quarter

Cumulati

ve

3rd Quarter Cumulative

Planned No. of Trainees

5.1.2.4 Trainings Conducted in Oromia Region in the First Nine Month of 2007 EFY

A total of 22 types of trainings were planned to be given in Oromia region in the fiscal year. All

of them were planned to be started in the reporting period. Accordingly, 10 (45.5% of

planned) have been conducted in the reporting quarter. Among the five regional level trainings

planned, three of them (60.0%) have been conducted. Sixty one WWT members and other

woreda staff in Oromia woredas, zones and regional sector bureaus (48.0% of those planned)

were trained on CMP management for 3 days at Ambo town. Besides, 22 of those trained in

CMP management were also trained in CMP promotion, appraisal and reporting for additional 3

days in the same town. Seven (11.5%) and 2 (9.1%) of the participants of the WWT CMP

management and appraisal and reporting trainings, respectively, were female. The estimated

costs of the trainings were not reported by the region. At the woreda level, majority of the

WASHCO members (99.6%) and the KWT members (93.0%) have been trained for 3 days.

Moreover, 62 (71.3% of those planned) new artisans have been trained in the construction of

water supply schemes through the CMP approach. Besides, 315 (94.0% planned) received

training on gender awareness and mainstreaming for 2 days. Overall, among the 10,385

people planned to be trained in the fiscal year, some 44.0% have received different trainings

with an outlay of about Birr 1.95 million allocated from the GoF contribution.

Page 28: COMMUNITY-LED ACCELERATED WASH (COWASH) PROJECT...being finalized in the reporting period. Thus far, the consultant submitted all of the 18 parts of the manual and strategic framework

22

Table 6: Trainings held in Oromia Region in the First Nine Months of 2007 EFY

M F T M F T

1 WWT CMP Management Training FTAT/RSU 127 0 127 0 0 0 54 7 61 3 145,600 44.4 70.5

2 CMP Promotion, Application, Appraisal & M&E Training FTAT/RSU 56 0 56 0 0 0 20 2 22 3 61,351 70.6 91.2

3 WASHCO CMP Management ToT Training FTAT/RSU 68 68 68 23 3 26 23 3 26 3 82,000 43.4 72.7

4 WASHCO Refreshment ToT in CMP Management FTAT/RSU 35 35 35 0 0

5 Financial Training for Finance Personnel BoFED 32 0 32 0 0

6 ToT in O&MM of Water Schemes BoWME 32 32 32 0 0

7 Pump attendants & care takers Training BoWME 1262 474 892 49 3 52 49 3 52 3 30,208.99

8 CLTSH ToT Training BoH 34 0 34 0 0

9 CLTSH Training for Woreda Level Experts Wo H 180 0 180 128 37 165 128 37 165 5 64,521.90

10WPs design Prepn, Site selection & Sup for Woreda

staffBoWME 51 0 51 0 0

11 KWT CMP Promotion & Appraisal Training WoWME 819 819 819 557 205 762 557 205 762 3 287,214.13

12 WASHCO CMP Management Training WoWME 2194 1001 2194 1226 950 2176 1226 950 2176 3 745,190.00

13 WASHCO CMP Management Refreshment Training WoWME 194 194 194 0 0

14 Artisans Training WoWME 87 44 87 51 11 62 51 11 62 47,957.40

15 Artisans Refreshment Training WoWME 175 175 175 0 0

16 WASHCO Training in Scheme Management WoWME 4183 1472 2716 401 500 901 401 500 901 5 381,853.00

17 Train Woreda Staff on Institutional Latrine design BoWME 51 0 51 0 0

18Training on CMP Finance Mgt guideline & Audit

ComplianceBoFED 54 0 54 0 0

19 Training on School WASH WoE &

WoWME28 0 28 0 0

20 GLOWS/WSP ToT Training BoWME 39 39 39 0 0

21 KWT Gender Awareness & Mainstreaming Training WoWA 335 0 335 168 147 315 168 147 315 2 99,422.00

22 WASHCOs GLOWS/WSP Training WoWME 350 350 350 0 0

10,386 4,703 8,549 2 ,603 1 ,856 4,459 2 ,6 77 1 ,865 4,542 1 ,945,318

Pre-& Post-Test

Result(%)Pre-test

Result (%)

Post-test

Result (%)

Total

S/N Type of Training Trainer

No. of Trainees Planned Number TrainedEstimated cost of

training (in Birr)3rd Quarter Cumlative

Annual 3rd Quarter Cumulative

No. of

Days

Trained

5.1.2.5 Trainings Conducted in BSG Region in the First Nine Months of 2007 EFY

Fourteen types of trainings were planned to be undertaken in the reporting period in

Benishangul Gumuz region. Accordingly, half of them (50.0%) have been conducted in the

reporting period. The trainings conducted are: i) WWT CMP Management; ii) CMP Promotion,

appraisal and M&E; iii) WASHCO ToT in CMP Management; iv) CLTSH ToT; v) KWT CMP

Promotion and Appraisal; vi) Artisans training; and vii) CLTSH training for Kebele level experts.

COWASH FTAT in collaboration with RSU has conducted four of the trainings. A total of 81 (5

female) members of WWT and ZWT and staff of regional, zonal and woreda WASH sector

offices, including RSU staff, were trained on CMP management, promotion and monitoring for

3 days. This accounted about 111.0% of the trainees planned. Of these trainees, 34 woreda

and RSU staff (3 female), 113.3% of the trainees planned, were trained on CMP promotion,

appraisal and reporting for more 3 days at the regional capital. Moreover, COWASH FTAT

trained 61 woreda and RSU staff on WASHCO CMP management ToT for 3 days. In turn,

woreda staffs trained at the regional level have conducted four types of trainings. 140 (46

females) KWT members have received training on CMP promotion and management for 5 days

and 16 artisans have been trained for 30 days in Bambasi woreda. Besides, Benishangul

Gumuz health bureau has given ToT training on CLTSH for 18 woreda staff for 3 days and

woreda staff, in turn, trained 69(53 females) kebele level experts on the same issue for 3

days. Capacity building funds amounting to Birr 434,166 was spent for the seven trainings.

Page 29: COMMUNITY-LED ACCELERATED WASH (COWASH) PROJECT...being finalized in the reporting period. Thus far, the consultant submitted all of the 18 parts of the manual and strategic framework

23

Table 7: Trainings held in BSG Region in the First Nine Months of 2007 EFY

M F T M F T

1 WWT CMP Management TrainingCOWASH FTAT

73 0 73 0 0 0 76 5 81 3 87,022 45.3 61.8

2CMP Promotion, Application, Appraisal & M&E

Training COWASH FTAT30 0 30 0 0 0 31 3 34 3 11,790 64.5 69.1

3 WASHCO ToT in CMP ManagementCOWASH FTAT

& RSU28 28 28 49 12 61 49 12 61 3 77,660 43.0 67.0

4 ToT in O&MM of Water Schemes 16 0 0 0 0

5 CLTSH ToT Training BoH 36 36 36 18 0 18 18 0 18 3 95,508

6 KWT CMP Promotion & Appraisal Training WoW 181 181 181 94 46 140 94 46 140 5 65,702

7 WASHCO CMP Training 559 559 559 0 0

8 Artisans Training WoW 40 40 40 16 0 16 16 0 16 30 52,738

9 Artisan Refreshment Training 15 15 15 0 0

10 WASHCO Training in Scheme Management 280 0 0 0 0

11 Pump Attendants & Caretakers Training 144 0 0 0 0

12 CLTSH Training for WoH experts & other WaSH staff 36 0 0 0 0

13 KWT gender awareness & mainstreaming Training 210 210 210 0 0

14 Training of WASHCOs in Water Safety Planning 60 60 60 0 0

15Water Points Design, Site Selection & Supervision

Training14 14 14 0 0

16 GLOWS/WSP ToT Training 24 24 24

17 Traning of woreda on latrin desigin 21 21 21 0 0

18 Training of kebel level experts on CLTSH WoW 184 184 184 16 53 69 16 53 69 3 43,746

1 ,951 1 ,372 1 ,475 1 93 1 1 1 304 300 1 1 9 419 434, 166

Pre-& Post-Test

Result(%)

Pre-test

Result (%)

Post-test

Result (%)

Total

S/

NType of Training Trainer

No. of Trainees Planned Number TrainedEstimated cost

of training

(in Birr)3rd Quarter Cumlative

Annual 3rd Quarter Cumulative

No. of

Days

Trained

5.1.2.6 Workshops and Meetings held in the Regions

All regions were expected to conduct 2006 EFY annual performance review and 2007 EFY

Planning workshop in the reporting period. Accordingly, all regions, except SNNPR, have

conducted the workshop in the reporting period of the fiscal year. In these workshops, regions

have reviewed COWASH/CMP performance of 2006 EFY and prepared (physical and financial)

plans of 2007 EFY in the presence of all woredas and zones including new woredas and zones

in the regions. Quarterly Zonal level performance reviews were also planned to be conducted

in the presence of project woredas.

The Amhara review and planning workshop was held at two places in the region. One of these

workshops was held at Dangila town in the presence of Western part of 27 project woredas

and zones in the Western part of the region while the second was conducted at Dessie town in

the presence of the 13 new woreda and 4 zonal staff of Eastern woredas and zones. A total of

359 (38 female) Woreda and zonal staff participated in the workshop held for 2 days. Two

Amhara zones (Awi and Waghimra) have conducted awareness raising workshop to private

sector on the availability of market opportunities in the presence of 20 representatives (all

male) of private enterprises for 1 day. Four zones (West Gojjam, South Gondar, North Wollo,

and East Gojjam) reviewed the performance of COWASH in the presence of project woredas

for 2 days at the zonal level. Moreover, a total of 98 Whole System in the Room (WSR)

Page 30: COMMUNITY-LED ACCELERATED WASH (COWASH) PROJECT...being finalized in the reporting period. Thus far, the consultant submitted all of the 18 parts of the manual and strategic framework

24

workshops have been conducted in the woredas of two zones – West Gojjam (37) and East

Gojjam(61).

Oromia region has also conducted the 2006 EFY annual performance review and 2007 planning

workshop of Oromia region for the old 8 woredas. The workshop was conducted for 1 day with

the participation of 86 people (1 female) who are the WWT and WASH sector offices’ focal

persons from the 8 woredas, zonal WASH team members from 4 zones, and the focal persons

and experts from the regional WASH sector bureaus and RSU staff. In this workshop,

presentations of woredas’ reports based on the summarized result of the annual review

meeting conducted in the zones were presented. Together with performance reports of the

woredas and zones, the final version of the 2007 EFY plan of the zones, woredas and bureaus

drafted by the RSU staff in consultation with the respective sector offices were presented and

discussed. COWASH FTAT could not participate in the workshop due to competing activities in

other regions of the project. The new zones and woredas could not participate as the selection

of the woredas and zones was not finalized by the regional sector offices. Woreda health

offices have conducted Whole System in the Room (WSR) workshop with the participation of

522 people (156 female) for 2 days with an estimated cost of Birr 92,213. Quarterly review

meetings at the zonal level have not been conducted in the project zones.

Tigray’s workshop was conducted for 2 days with the participation of 77 (8 female) woreda

and regional sector bureaus’ staff, who were 77.0% of those invited to take part in the

workshop. Approximately Birr 143,732 was expended for the workshop held at Wukro town.

Woredas have shared their experiences over the implementation years and this will improve

the implementation of the project activities in the project woredas. Zonal level quarterly

review meetings and woreda level Whole System in the Room (WRS) workshops have not been

held in the woredas.

SNNP region conducted the 2006 EFY Performance Review and 2007 EFY Planning workshop in

for one day in the third quarter of the fiscal year. A total of 92 people (7 female) participated

in the workshop. Performance of woredas and zones were presented and the 2007 EFY plan

was discussed during the workshop. About Birr 203,587 was expended for the workshop held

at Hawassa. Esara woreda has also conducted its review and planning workshop in the

reporting period. Some 102 woreda staff (25 female) attended the workshop held for 3 days

with a total cost of about Birr 32,197. The woreda has also conducted ‘awareness raising

workshop to Private sector on the availability of market opportunities’ workshop for 5 days and

approximately Birr 7,608 was spent for the workshop.

BSG region has conducted its first annual planning workshop in the 2nd quarter of the fiscal

year. A total of 68 (3 female) people, constituted from regional sector bureaus, 2 zones and 4

woredas, participated in the 3 days workshop held at the regional capital. This accounted

97.1% of those invited for the workshop. About Birr 73,079 was expended for the workshop

After the briefing on COWASH the regional sector bureaus, zones and woredas prepared their

own 2007 EFY annual plan with the technical assistance of the COWASH FTAT.

Three SNNPR woredas health offices (Duna, Esara and Tocha) have executed Whole System in

the Room (WSR) workshop for 3-4 days with an estimated cost of Birr 99,612.

Page 31: COMMUNITY-LED ACCELERATED WASH (COWASH) PROJECT...being finalized in the reporting period. Thus far, the consultant submitted all of the 18 parts of the manual and strategic framework

25

Table 8: Workshops and Review Meetings held in the Regions in the First 9 Months of 2007 EFY

M F T M F T

1Annual Review (EFY 2006) and

Planning Workshop (EFY 2007) RWDB 410 0 410 0 321 38 359 2

2

Awareness Raising Workshop to

Private Sector on the Availability of

Market OpportunitiesZWD 120 0 120 20 0 20 20 0 20 1

3Zonal Quarterly Review Meeting with

Woredas (No. of Review Meetings)ZWD 20 0 10 2

4Whole System in the Room (WSR)

workshop (No. of Workshops)W oH 200 200 200 1

1Annual Review (EFY 2006) and

Planning Workshop (EFY 2007) BoW 124 0 124 0 0 0 85 1 86 1 163,160.27

2

Awareness Raising Workshop to

Private Sector on the Availability of

Market Opportunities

ZoW 0 0 0 0 0

3Zonal Quarterly Review Meeting with

WoredasZWT 398 100 200 0 0

4Whole System in the Room (WSR)

workshop W oH 787 0 787 366 156 522 366 156 522 2 92,213.00

1Annual Review (EFY 2006) and

Planning Workshop (EFY 2007) BoW 100 0 100 0 69 8 77 2 143,732

2COWASH Zonal Quarterly Review

Meeting with Woredas ZoW 72 0 72

3 Whole System in the Room (WSR)

workshop W oH 490 0 490 0 0

1Annual Review (EFY 2006) and

Planning Workshop (EFY 2007) BoW 117 0 117 85 7 92 85 7 92 1 203,587.0

2

Awareness Raising Workshop to

Private Sector on the Availability of

Market OpportunitiesZoW 195 0 195 12 1 13 12 1 13 5 7,608.0

3Zonal Quarterly Review Meeting with

WoredasZoW 235 0 235 0 0 0 0 0 0

4Whole System in the Room (WSR)

workshop W oH 1,371 100 1,371 95 27 122 125 47 172 3 to 4 99,612

5Annual Review and Planning Workshop

by WoredasWoW 130 0 130 41 7 48 41 7 48 3 32,197

1 Planning Workshop (EFY 2007) BoW 70 70 70 65 3 68 65 3 68 2 73,079

2

Awareness Raising Workshop to

Private Sector on the Availability of

Market OpportunitiesZoW 60 0 0

3 Zonal Quarterly Review Meeting with

WoredasZoW 168 0 0

E. BSG Region

A. Amhara Region

B. Oromia Region

C. Tigray Region

D. SNNP Region

0 4

98 98

Number Attended No. of

Workshop

Days

Total Cost of

Workhop/Mee

ting (in Birr)

S/

NType of Training Organizer

No. of Participants

Planned

3rd Quarter3rd

QuarterCumulative

CumulativeAnnual

Page 32: COMMUNITY-LED ACCELERATED WASH (COWASH) PROJECT...being finalized in the reporting period. Thus far, the consultant submitted all of the 18 parts of the manual and strategic framework

26

5.1.2.7 Procurements made in the Regions

COWASH aims at building the physical capacity of the implementing institutions so as to

implement the CMP approach in a meaningful and sustainable manner. Much of the

procurement is to be made by the new woredas as the old woredas have already procured

many of the required materials in the previous implementation years of the project. However,

much of the procurements in the new woredas and zones have not been made in the reporting

period as the preparation of the regional annual plans is delayed. Anyhow, few procurements

were made with the funds leftover from 2005 EFY. The different procurements made in the

reporting period in the regions, zones and woredas are presented below.

5.1.2.7.1 Procurements made in Oromia Region

In the reporting period, twenty types of office equipments and construction equipments were

planned to be procured in the woredas, zones and regional sector bureaus. Much of the

procurement was in the new woredas and zones. Accordingly, many of the planned items have

been procured (Table 9) and the remaining ones, like vehicle, water quality test kits,

dewatering pump, etc. are in the process of procurement. Some of the major items procured

were 22 motorbikes (100.0%), 27 desktop computers (64.3%), 2 laptop computers (100.0%),

32 printers (80.0%), 10 LCD Projectors (71.4%), and 3 photocopy machines (75.0%). The

project has spent about Birr 3.1 million for the procurement of the office and construction

equipments.

Table 9: Materials procured in Oromia region during the First Nine Months of 2007 EFY

Annual3

rd

QuarterCumulative

3rd

QuarterCumulative

1 Desktop Computer No. 42 0 42 27 27 388,690 WMEO, WHO, WEO, WoFED, WYCH

offices of 6 Project WOredas

2 Laptop Computer No. 2 0 2 2 2 30,800 WMEOs of 2 Project Woredas

3 Printer No. 40 0 40 32 32 223,308 WMEO, WHO, WEO, Wo FED, WYCH o ffices o f 7

P ro jec t WOredas

4 Photocopy Machine No. 4 0 4 3 3 91,247 WMEOs of 2 Project Woredas

5 LCD Projector No. 14 0 14 10 10 172,638 WMEOs of 10 Project Woredas

6 Scanner No. 1 0 1 0 0

7 Digital Camera No. 13 0 13 8 8 27,276 WMEOs of 6 Project Woredas

8 File cabinet No. 22 0 22 9 9 42,800 WMEOs of 5 Project Woredas

9 Motorbike No. 22 0 22 22 22 1,891,817 WMEO, WHO, WEO, WoFED, WYCH

offices of 7 Project WOredas

10 Small diameter mold No. 21 0 21 3 3 36,000 WMEOs of 1 Project Woreda

11 Chain block No. 8 0 8 2 2 5,300 WMEOs of 2 Project Woredas

12 Artisan tools Set 103 0 103 52 52 64,293 WMEOs of 7 Project Woredas

13 Vehicle No. 1 0 1 0 0

14 Spring Construction Equipment Set 10 0 10 3 3 63,309 WMEOs of 3 Project Woredas

15 Water Quality Test Kit No. 8 0 8 0 0

16 Fax Machine No. 3 0 3 2 2 19,300 WMEOs of 2 Project Woredas

17 Dewatering Pump No. 2 0 2 0 0

18 External hard disk No. 1 0 1 1 1 2,500 WMEOs of 1 Project Woreda

19 GPS No. 14 0 14 2 2 10,300 WMEOs of 2 Project Woredas

20 Stabiliser No. 50 0 50 29 29 26,510 WMEO, WHO, WEO, WoFED, WYCH

offices of 5 Project WOredas

3,096,088

Total Cost

(in Birr)Beneficiary Office(s)

Quantity Planned

S/N

Total

Material or Equipment Unit

Quantity Procured

Page 33: COMMUNITY-LED ACCELERATED WASH (COWASH) PROJECT...being finalized in the reporting period. Thus far, the consultant submitted all of the 18 parts of the manual and strategic framework

27

5.1.2.7.2 Procurements done in Amhara Region

Thirteen types of items were planned to be procured in 2007 EFY. All of them were planned to

be completed in the reporting period. Among these, 7 of them were undertaken in the nine

months. Twenty nine laptops(72.5%), 5 file cabinets (100.0%), 22 motorbikes (100.0%), 102

sets of artisan hand tools (23.7%), 9 drums of chlorine (11.3%), 1 spring construction tools

(33.3%), and 20 water quality test kits (100.0%) have been procured in the woredas, zones

and regional levels. The procurement of the 31 cars for RSU, Zones and Woredas is still on

process.

Table 10: Materials procured in Amhara region during the First Nine Months of 2007 EFY

5.1.2.7.3 Procurements done in Tigray Region

In Tigray region, 15 types of office and construction materials were planned to be procured in

2007 EFY. All of them were planned to be executed in the reporting period. However, none of

the planned items have been procured in the woredas and regional level. The procurement

process was started late and many of the items will be procured in the last quarter of the fiscal

year.

Table 11: Materials procured in Tigray region during the First Nine Months of 2007 EFY

Annual3rd

Quarter

cummu

lative

3rd

Quarter

cummul

ative

Total cost

(in Birr)

1 Desktop Computer with UPS No. 11 11 11

2 Laptop Computer No. 10 10 10

3 Printer No. 8 8 8

4 LCD Projector No. 13 13 13

5 Motorbike No. 11 11 11

6 Chain blocks No. 3 3 3

7 Artisan tools Set 105 105 105

8 Digital Camera No. 11 11 11

9 Water quality test kit Set 7 7 7

10 Spring construction tools No. 2 2 2

11 Stablizer No. 9 9 9

12 Hand held GPS No. 6 6 6

13 External Hard disk No. 3 3 3

14 Office furniture No. 2 0 1

15 Vehicle No. 2 2 2

-

Beneficiary Office(s) of the

material procuredS/N

Total

Material or Equipment Unit

Quantity ProcuredQuantity Planned

Annual3

rd

QuarterCumulative

3rd

QuarterCumulative

1 Desktop Computer No. 1 0 1 0 0

2 Laptop Computer No. 40 0 40 27 29 Woreda Water Offices

3 Printer No. 1 0 1

4 File cabinet No. 5 0 5 5 5 Woreda Water Offices

5Motorbike No. 22 0 22 22 22 Woreda Water &

Health Offices

6 Large diameter mold No. 4 0 4

7 Small diameter mold No. 17 0 17

8 Artisan tools Set 430 0 430 102 102 Woreda Water Offices

9 Vehicle No. 31 0 31

10 Chlorine Drum  80 80 80 9 9 Woreda Water Offices

11  Spring construction tools  Set 3 0 3 1 1 Woreda Water Offices

12  Water quality test kit  No. 20 0 20 0 20 Woreda Water Offices

13  Water quality test reagent  No.  10  0 10

-

Total

Cost

(in Birr)

Beneficiary Office(s)S/N

Total

Material or Equipment Unit

Quantity ProcuredQuantity Planned

Page 34: COMMUNITY-LED ACCELERATED WASH (COWASH) PROJECT...being finalized in the reporting period. Thus far, the consultant submitted all of the 18 parts of the manual and strategic framework

28

5.1.2.7.4 Procurements done in SNNP Region

Twenty four types of office and construction materials, majority of them rolled over from 2006

EFY, were planned to be procured in SNNPR in the reporting period. Accordingly, many of the

items (21 or 87.5%) have been procured and the remaining ones are in the process of

procurement. Some of the materials procured are: 6 desktop computers (37.5%), 8 laptop

computers (100.0%), 11 printers (73.3%), 5 photocopy machines (100.0%), 8 digital camera

(66.7%), 7 file cabinets (100.0%), 5 motorbikes(71.4%), 2 Larger diameter molds (50.0%),

14 small diameter molds (43.8%), 2 chain blocks (16.7%), 3 artisan tools (60.0%), and 4

hand held GPSs (50.0%). The region has effected advance payment for the procurement of the

long awaited RSU car procurement. The RWSC on COWASH has decided to complete all the

procurements until end of Jan. 2015 and an action plan has been prepared for the purpose.

Capacity building fund amounting to about Birr 4.48 million has been spent for the

procurement of the items, including the funds committed for the car procurement. The RSU

car is expected to be delivered before the end of this fiscal year.

Table 12: Materials procured in SNNP region during the First Nine Months of 2007 EFY

Annual3rd

Quarter

cummu

lative

3rd

Quarter

cummul

ative

Total cost

(in Birr)

1 Desktop Computer with UPS No. 16 5 16 3 6 82,012

Tocha WWO & WEO ; Esara WWO;

Duna WWO; Dawuro zone WO &

FO

2 Laptop Computer No. 8 0 8 4 8 121,535 RSU; Tocha, Gorche, Duna

&Arbegona WWOs; Dawuro zone

WO

3 Printer No. 14 0 14 0 10 64,695 ZFO; Tocha WWO,WEO

&WFEDO,EsaraWWO

4 Colour Printer No. 1 0 1 1 1 17,250 RSU

5 LCD Projector No. 8 1 8 2 2 30,790 Dawuro zone WO; Duna WWO

6 Photocopy Machine No. 5 0 5 2 5 141,709 Tocha, Gorche, Esara & Arbegona

WWOs; Dawuro zone WO;

7 Filing cabinet No. 7 1 7 4 7 40,947 RSU; Gcrche, Tocha and Esara

WWO

8 Motorbike No. 7 0 6 1 5 223,197 Tocha, Gorche, Esara & Esara

WWOs

9 Large diameter mold No. 4 0 4 2 2 36,800 Tocha WWO

10 Small diameter mold No. 32 0 32 12 14 156,100 Chencha & Tocha WWO

11 Chain blocks No. 12 0 12 2 2 12,000 Chencha WWO

12 Artisan tools Set 5 0 5 2 3 85,345 Tocha, Arbegona & Gorche WWo

13 Digital Camera No. 12 0 12 4 8 47,270 Tocha & Arbegona WWO & Dawuro

zone WO

14 Scanner No. 2 0 2 0 0

15 Water quality test kit Set 5 0 5 5 5 847,665 Chencha, A/Zuria, Misha, Duna &

Esara WWO

16 Spring construction tools No. 6 0 6 1 3 44,000 Chencha & Gorche WWO

17 Stablizer No. 15 0 15 5 16 16,245 Tocha, Misha WWO, WHO, WFO,

WED & Dawuro zone ZFO

18 Hand held GPS No. 8 2 8 1 4 20,720 Tocha, Arbegona, Chencha &

Misha WWO

19 Fax machine No. 1 0 1 1 1 10,971 Misha WWO

20 External Hard disk No. 2 0 2 1 1 1,782 SU

21 CDMA No. 2 0 2 0 0

22 Office furniture No. 2 0 2 2 2 9,900 RSU

23 Vehicle No. 1 1 1 1 1 2,470,000 Advance paid for the vehicle

24 Flash Disk No. 3 0 3 3 3 552 RSU

4,481,485

Beneficiary Office(s) of the

material procuredS/N

Total

Material or Equipment Unit

Quantity ProcuredQuantity Planned

5.1.2.7.5 Procurements done in BSG Region

As indicated in Table 13, twenty eight types of office and construction materials were planned

to be procured in 2007 EFY. Much of the procurement was planned to be completed in the 3rd

quarter of the reporting period. Accordingly, few materials have been procured in the third

quarter. Nine desktop computers (30.0%), 11 laptops (73.3%), 14 Printers (48.3%),

3 photocopy machines (37.5%), 1 fax machine (50.0%) and 2 flash disks (3.0%) have been

procured. More than half a million Birr (Birr 546,362), from the GoF contribution, has been

Page 35: COMMUNITY-LED ACCELERATED WASH (COWASH) PROJECT...being finalized in the reporting period. Thus far, the consultant submitted all of the 18 parts of the manual and strategic framework

29

spent for the procurement of the items. Many items are still on the process of procurement by

woreda, zone and regional beneficiary sector offices.

Table 13: Materials procured in BSG region during the First Nine Months of 2007 EFY

Annual3rd

Quarter

cummu

lative

3rd

Quarter

cummul

ative

Total cost

(in Birr)

1 Desktop Computer with UPS No. 30 30 30 9 9 125,610 Woreda & Zonal Sector Offices

2 Laptop Computer No. 15 15 15 11 11 198,068

RSU, Woreda & Zonal Sector

Offices

3 Printer No. 29 29 29 14 14 67,360

RSU, Woreda & Zonal Sector

Offices

4 LCD Projector No. 7 7 7 0 0

5 Scanner No. 1 1 1

6 Photocopy Machine No. 8 8 8 3 3 88,234 Woreda & Zonal Sector Offices

7 Filing cabinet No. 14 14 14 0 0

8 Motorbike No. 16 16 16 0 0

9 Large diameter mold No. 4 4 4 0 0

10 Small diameter mold No. 30 30 30 0 0

11 Chain blocks No. 18 18 18 0 0

12 Artisan tools Set 55 55 55 0 0

13 Digital Camera No. 13 13 13 0 0

14 Spring construction tools No. 5 5 5 0 0

15 Stablizer No. 26 26 26 0 0

16 Hand held GPS No. 12 12 12 0 0

17 Fax machine No. 2 2 2 1 1 25,500 Woreda sector offices

18 Office furniture No. 1 0 1 0 0

18.1 L-shape table No. 5 5 5

18.2 normal table (1.50cm*80*75cm No. 1 1 1

18.3 managerial chair (low back) No. 6 6 6

18.4 Gust chair with arm No. 10 10 10

18.5 Drawer chair No. 1 1 1

18.6 Gust chair without arm No. 3 3 3

19 Laptop bag No. 5 5 5

20 Doubl Cabin Toyota Pick up No. 1 0 1 0 0

21 Flash Disk No. 66 66 66 2 2 640 RSU

22 Remote sensor No. 1 1 1

23 Binding machine No. 1 1 1

24 Broadband Installation Set 1 1 1

25 Dewatering pump No. 3 3 3

26 Vehicles No. 5 5 5

27 Vehicles tyres No. 5 5 40,950 RSU

28 Generator No. 6 6 6

546,362

Beneficiary Office(s) of the

material procuredS/N

Total

Material or Equipment Unit

Quantity ProcuredQuantity Planned

Page 36: COMMUNITY-LED ACCELERATED WASH (COWASH) PROJECT...being finalized in the reporting period. Thus far, the consultant submitted all of the 18 parts of the manual and strategic framework

30

5.2 RESULT 2 OF COMPONENT 2: FINANCIAL AND PROCUREMENT SERVICES

DELIVERED FOR CMP INTERVENTION AT ALL LEVELS IN THE SELECTED

REGIONS

5.2.1 Output 1: Flow of Funds for CMPs Functional

Some indicators are set to measure the achievement of the output, viz., 1) number of fund

transfer requests done to the financier; 2) number of BoFED audit reports produced

(disaggregated by regions); 3) amount of funds transferred to WASHCOs and 4) amount of

funds settled by WASHCOs.

Opening of bank accounts in new regions, zones and woredas was among the major activities

to be accomplished during the first quarter of the reporting period. The new zones (2 in

Oromia and 2 in BSGR) and woredas (4 in Oromia and 4 in BSGR) have opened bank accounts

with the support of the RSUs staff and BoFED of the respective regions.

According to the funding agreements made between the beneficiary regional Finance Bureaus

and Embassy of Finland, a COWASH region is expected to submit four fund transfer requests

to the Embassy of Finland per year. A new region can request fund for the first and second

quarters of a fiscal year, at a time, for the first year while an old region can request only for a

quarter.

In the reporting period, all regions SNNPR have submitted fund requests to Embassy of

Finland. Oromia, Tigray and BSG regions submitted two requests at a time while Amhara and

SNNPR submitted only one fund request each. SNNP region is preparing two fund requests to

submit at the beginning of the third quarter of the fiscal year. In all, a total of 8 (40.0%) of

the fund requests have been submitted to Embassy of Finland. Many of the regions didn’t

request funds for the first quarter as they had some leftover funds from 2006 EFY to cover the

expenses in the quarter. The delay in the approval of the 2007 EFY annual plan has delayed

the timely submission of the fund requests.

The project regions are expected to audit the project fund utilization every year and prepare

audit reports. The auditing of the 2006 EFY fund utilization was expected to be conducted in all

regions in the reporting period. However, only SNNPR has conducted the auditing and

submitted to Embassy of Finland. The auditing of the SNNPR includes 4 woredas (Misha, Duna,

A/Zuria and Chencha), 2 zones (Hadiya and Gamo Gofa) and Regional Water Resources

Bureau. The other regions are expected to audit the 2006 EFY COWASH funds utilization of

beneficiary sector offices in the last quarter of the fiscal year.

Usually, it is convenient to get detailed financial data on WASHCOs fund utilization at the end

of the fiscal year. Hence, complete information on investment fund transferred to, via MFIs,

and amount settled by WASHCOs in each region will be reported in the annual report of the

project.

5.2.2 Output 2: Linkages Created with Private Sector in the Supply of Materials,

Equipment, Tools and Services

Number of new artisans trained by COWASH for WaSH facility construction in the woredas

(disaggregated by sex) and number of awareness raising workshops organized for the private

sector are set to measure the achievement of the output.

Page 37: COMMUNITY-LED ACCELERATED WASH (COWASH) PROJECT...being finalized in the reporting period. Thus far, the consultant submitted all of the 18 parts of the manual and strategic framework

31

Usually, some activities are included in the annual plans of regions and woredas to create

linkage with the private sector at the regional, zonal and woreda levels. The major ones are:

training of artisans; organizing awareness raising workshops to the private sector (pump,

spare parts and construction materials suppliers) on the availability of market opportunities;

carrying out market surveys in the Woredas; and informing communities on the prices of

construction materials, equipment, tools and services based on market surveys made in the

woredas.

Accordingly, awareness raising workshop to private sector on the availability of market

opportunities was conducted in only one zone of SNNPR. This has been planned with the view

to create linkage between the WASHCOs and the private suppliers so as to speed up the

construction activities and sustaining the facilities. The performance was low due to competing

activities in the zones of the project regions.

As indicated in the regional performances in Output 2 of Result 1, a total of 611 artisans (223

females) have been trained or refreshed in the nine months in three regions (Amhara, SNNPR,

Oromia and BSG). Some woredas are in the process of training more artisans and complete

information of artisans trained will be presented in the annual report.

5.3 RESULT 3 OF COMPONENT 2: SUSTAINABLE COMMUNITY AND

INSTITUTIONAL ACCESS TO SAFE WATER, SANITATION AND HYGIENE IN

THE TARGET WOREDAS INCREASED

5.3.1 Output 1: Access to Improved Water Sources for Communities and Institutions

Increased

Three indicators are set to measure the achievement of the output. These are, a) number of

new CMP applications submitted to WWT(disaggregated by communal and institutional);

b) number of new CMP applications approved by WWT (disaggregated by communal and

institutional); and c) number of new water schemes constructed (disaggregated by communal

and institutional).

As the first quarter of the reporting period is characterized by a rainy season and the second

quarter is mainly crop harvesting period in the majority of the project woredas, there were no

many applications submitted and construction activities carried out during the first half of the

fiscal year. Most applications are coming during the third quarter and only some construction

activities, many of them started in the previous fiscal year, have been completed in the nine

the reporting period.

In 2007 EFY, a total of 2,557 new WPs constructions (including those rolled over from 2006

EFY) were planned to be undertaken in the five project regions (Table 14). Of this, 2,236 are

for communities and the remaining 321 are for institutions- 207 for schools and 114 for health

facilities. Hence, at least 2,557 applications are expected to be submitted to and approved by

WWTs in the fiscal year by communities and institutions.

Page 38: COMMUNITY-LED ACCELERATED WASH (COWASH) PROJECT...being finalized in the reporting period. Thus far, the consultant submitted all of the 18 parts of the manual and strategic framework

32

Table 14: Number of New Water Points Planned to be Constructed in 2007 EFY

School Health Facility

Amhara 1,357 153 80 1,590

Tigray 166 22 12 200

SNNPR 401 11 4 416

Oromia 261 9 9 279

BSGR 51 12 9 72

Total 2,236 207 114 2,557

InstitutionalCommunity

Project RegionTotal

Number of Planned WPs

5.3.1.1 Water supply schemes constructed in Amhara Region

As indicated in Table 14 above, 40 Amhara woredas planned to construct 1,590 WPs – 1,357

by communities and 215 by institutions (153 schools and 80 health facilities). Consequently,

promotions have been made in the reporting period in the CMP kebeles of Amhara woredas

with the trained woreda staff in collaboration with KWT members. As a result of these

promotions, 2,861 applications (2,664 for communities and 147 for schools and 50 for health

facilities) have been submitted to WWTs of the project woredas. This accounts about 180.0%

of the planned water points in the 40 project woredas of the region. Among these, 2,754

(96.3%) were desk appraised and 2,524 of those desk appraised (91.6%) were appraised at

the field level by the woreda appraisal team, who were trained in CMP promotion and appraisal

by the Zonal experts and RSU staff. Accordingly, 2,445 (97.0%) of the field appraised projects

have been approved by the respective WWTs of the project woredas. Among the approved

proposals, 1,266 (1,145 communities’, 94 schools’ and 27 health facilities’) water points were

under construction at the end of the reporting period.

Table 15: Number of applications submitted, appraisals made and applications approved in

Amhara Region in the First Nine Months of 2007 EFY

<50% >50% Total

A. Community Water Points -

HDW with RP - - - - - - - - - HDW 896 1,904 1,805 1,656 1,608 76 274 641 915 SPD 411 690 690 633 618 52 66 154 220 - SW 48 48 48 48 48 23 3 6 9 - DW - - - - - - - RWH - - - - - - SPD-RPS 2 22 14 2 2 1 1 1 DW-RPS - Subtotal 1,357 2,664 2,557 2,339 2,276 152 343 802 1,145 -

B. Institutional Water Points

B.1 School Water Points

HDW with RP - - - - - - - - -

HDW 152 136 136 126 120 16 26 62 88 -

SPD 1 11 11 11 8 - 2 4 6 -

SW - - - - - - - - -

DW - - - - - - - - -

RWH - - - - - - - - -

SPD-RPS - DW-RPS - Subtotal 153 147 147 137 128 16 28 66 94 -

B.2 Health Institutions Water Points

HDW with RP - - - - - - - - - -

HDW 80 47 47 45 40 13 8 18 26 -

SPD - 3 3 3 1 - - 1 1 -

SW - - - - - - - - - -

DW - - - - - - - - - -

RWH - - - - - - - - - -

SPD-RPS - - DW-RPS - - Subtotal 80 50 50 48 41 13 8 19 27 -

Total 1,590 2,861 2,754 2,524 2,445 181 379 887 1,266 -

No. of WPs

Not Started

Construction

No. of WPs under

construction

No. of WPs

Abandoned

(could not

be

constructed)

Type of

Water

Point(WP)

No. of

Planned

WPs

No. of WPs

Applications

made

No. of WPs

Applications

Desk

Appraised

No. of WPs

Application

Field

Appraised

No. of WPs

Applications

Approved by

WWT

Page 39: COMMUNITY-LED ACCELERATED WASH (COWASH) PROJECT...being finalized in the reporting period. Thus far, the consultant submitted all of the 18 parts of the manual and strategic framework

33

In the reporting period, 998 (979 community, 18 schools and 1 health facility) water points,

which accounts 62.8% of the annual plan, have been completed in the Amhara woredas. A

total of 175,896 rural people of the project woredas are benefiting from the water points.

Moreover, study and design of RPSs from springs were completed and construction of 2 RPSs

from springs is underway.

Table 16: Number of new WPs constructed in Amhara Region in the First 9 Months of 2007 EFY

5.3.1.2 Water supply schemes constructed in Tigray Region

In Tigray region, a total of 200 WPs – 166 by communities and 34 by institutions (22 schools

and 12 health facilities) were planned to be constructed in the 7 woredas of the region through

the CMP approach.

Accordingly, promotions have been made in the kebeles and beneficiaries expressed their

demand to WWTs. For the planned 200 WPs, 264 (132.0% of the plan) applications have been

submitted. Of this, 261 (98.9%) were appraised at the desk level. Among the desk appraised

applications, 208 (79.7%) were appraised on the field by trained woreda staff. Consequently,

WWTs have approved 172 (82.7%) of the field appraised applications for funding. Among the

approved applications 166 are for communities and 6 for institutions – 4 each for schools and

health facilities.

3rd

QuarterCumulative Annual

3rd

QuarterCumulative

A. Community Water PointsHDW with RP

HDW 467 467 896 602 617 108,011 108,011

SPD 109 109 411 342 346 60,361 60,361

SW 16 16 48 11 16 7,524 7,524

DW

RWH

SPD-RPS 2

DW-RPS

Subtotal 592 592 1,357 955 979 175,896 175,896

B. Institutional Water Points

B.1 School Water Points

HDW with RP

HDW 152 152 152 16 16 10,346

SPD 1 1 1 2 2 882

SW

DW

RWH

SPD-RPS

DW-RPS

Subtotal 153 153 153 18 18 11,228 -

B.2 Health Institutions Water Points -

HDW with RP -

HDW 80 80 80 1 1 21

SPD

SW

DW

RWH

SPD-RPS

DW-RPS

Subtotal 80 80 80 1 1 21 -

Total 825 825 1,590 974 998

Type of Water Point(WP)

Number of WPs

Construction

Completed

Actual No

of People

Using the

Completed

WPs

No of People

having access

to the

Completed WPs

within 1.5KM

radius of the

WPs

Number of WPs planned to be

constructed

Page 40: COMMUNITY-LED ACCELERATED WASH (COWASH) PROJECT...being finalized in the reporting period. Thus far, the consultant submitted all of the 18 parts of the manual and strategic framework

34

Table 16: Number of WPs applications submitted, appraisals made and applications approved

in Tigray Region in the First Nine Months of 2007 EFY

<50% >50% Total

A. Community Water Points -

HDW with RP - - - - - - - - - HDW 90 113 113 87 79 60 19 - 19 SPD 45 84 81 71 48 11 37 37 - SW 29 59 59 42 37 37 - - DW - - - - - - - RWH - - - - - - SPD-RPS - DW-RPS 2 2 2 2 2 2 2 Subtotal 166 258 255 202 166 108 58 - 58 -

B. Institutional Water Points

B.1 School Water Points

HDW with RP - - - - - - - - -

HDW 9 2 2 2 2 2 - -

SPD - - - - - - - - -

SW 7 2 2 2 2 2 - - -

DW - - - - - - - - -

RWH 6 - - - - - - - -

SPD-RPS - DW-RPS - Subtotal 22 4 4 4 4 4 - - - -

B.2 Health Institutions Water Points

HDW with RP - - - - - - - - - -

HDW 5 - - - - - - - -

SPD 1 1 1 1 1 - - - -

SW 4 1 1 1 1 1 - - - -

DW - - - - - - - - - -

RWH 3 - - - - - - - -

SPD-RPS - - DW-RPS - - Subtotal 12 2 2 2 2 2 - - - -

Total 200 264 261 208 172 114 58 -

No. of WPs

Not Started

Construction

No. of WPs under

construction

No. of WPs

Abandoned

(could not

be

constructed)

Type of

Water

Point(WP)

No. of

Planned

WPs

No. of WPs

Applications

made

No. of WPs

Applications

Desk

Appraised

No. of WPs

Application

Field

Appraised

No. of WPs

Applications

Approved by

WWT

Tigray woredas have constructed 14 water points (12 for community and 2 for schools) in the

reporting period. Ten of these water points are hand dug wells while 6 of them are On Spot

Springs. The performance (7.0%) was very low compared with the annual target. The

communal water points completed are benefiting over 4,143 rural people in the project

woredas whereas the 2 school water points benefitted 1,953 students and teachers.

Besides, in Tigray, study and design of 2 deep wells for RPS and construction of 2 deep wells

for RPS and construction of 2 reservoirs were underway (about 50.0%) in the reporting period.

Table 17: Number of new WPs constructed in Tigray Region in the First 9 Months of 2007 EFY

3rd

Quarter

Cumulativ

eAnnual

3rd

QuarterCumulative

A. Community Water PointsHDW with RP

HDW 2 2 90 6 8 2,860 2,860

SPD 1 1 45 3 4 1,283 1,283

SW 29

DW

RWH

SPD-RPS

DW-RPS 2

Subtotal 3 3 166 9 12 4,143 4,143

B. Institutional Water Points

B.1 School Water Points

HDW with RP

HDW 1 1 9 1 2 1,953

SPD

SW 7

DW

RWH 6

SPD-RPS

DW-RPS

Subtotal 1 1 22 1 2 1,953 -

B.2 Health Institutions Water Points -

HDW with RP -

HDW 5

SPD

SW 4

DW

RWH 3

SPD-RPS

DW-RPS

Subtotal - - 12 - - - -

Total 4 4 200 10 14

Type of Water Point(WP)

Number of WPs

Construction

Completed

Actual No

of People

Using the

Completed

WPs

No of People

having access

to the

Completed WPs

within 1.5KM

radius of the

WPs

Number of WPs planned to

be constructed

Page 41: COMMUNITY-LED ACCELERATED WASH (COWASH) PROJECT...being finalized in the reporting period. Thus far, the consultant submitted all of the 18 parts of the manual and strategic framework

35

5.3.1.3 Water supply schemes constructed in SNNP Region

In SNNP region, a total of 416 WPs – 401 by communities and 15 by institutions (11 schools

and 4 health facilities) - were planned to be constructed, through the CMP approach, in the 8

project woredas of the region. The plan includes the point water supply schemes started in the

preceding fiscal year. The regional plan has been reduced from 440 to 416 due to some

changes in some woreda plans and misreporting of rolled over water points in Arbaminch Zuria

woreda.

Accordingly, 302 new applications were submitted from communities in the reporting period.

Majority of this (291 or 96.4%) were desk appraised and 255 (87.6%) of this were appraised

at the field level. WWTs have approved 207 (81.2%) of the field appraised applications. Only

10 institutions have submitted applications for water supply construction- 9 from schools and 1

from health facilities.

Table 18: Number of WPs applications submitted, appraisals made and applications approved

in SNNP Region in First Nine Months of 2007 EFY

<50% >50% Total

A. Community Water Points -

HDW with RP - - - - - - - - - HDW 23 20 19 16 16 9 3 1 4 SPD 361 278 268 235 188 34 19 10 29 - SW 5 1 1 1 - - - - - - DW - - - - - - - RWH - - - - - - SPD-RPS 12 3 3 3 3 2 1 - 1 DW-RPS - - - - - - - - - Subtotal 401 302 291 255 207 45 23 11 34 -

B. Institutional Water Points

B.1 School Water Points

HDW with RP - - - - - - - - -

HDW 10 9 7 7 7 3 2 1 3 -

SPD - - - - - - - - -

SW 1 - - - - - - - -

DW - - - - - - - - -

RWH - - - - - - - - -

SPD-RPS - DW-RPS - Subtotal 11 9 7 7 7 3 2 1 3 -

B.2 Health Institutions Water Points

HDW with RP - - - - - - - - - -

HDW 4 1 1 1 1 1 1 - 1 -

SPD - - - - - - - - - -

SW - - - - - - - - - -

DW - - - - - - - - - -

RWH - - - - - - - - - -

SPD-RPS - - DW-RPS - - Subtotal 4 1 1 1 1 1 1 - 1 -

Total 416 312 299 263 215 49 26 12 38 -

No. of WPs

Not Started

Construction

No. of WPs under

construction

No. of WPs

Abandoned

(could not

be

constructed)

Type of

Water

Point(WP)

No. of

Planned

WPs

No. of WPs

Applications

made

No. of WPs

Applications

Desk

Appraised

No. of WPs

Application

Field

Appraised

No. of WPs

Applications

Approved by

WWT

Some constructions started late in the preceding fiscal year and some new ones started in the

third quarter have been completed in some woredas of SNNP region. It was reported that 134

water points (129 for communities and 5 schools) were completed in the reporting period. This

accounts 32.2 % of the total planned water points in the region. The community water points

constructed were 4 hand dug well, 129 on spot springs and 1 RPS from a spring. Five of the

water points completed (1 hand dug well and 4 on spot springs) are for rural schools. More

than 64,435 rural people have started to benefit from the 129 community water points and

1,139 students and teachers are benefiting from the school WPs constructed with the support

of COWASH project.

Page 42: COMMUNITY-LED ACCELERATED WASH (COWASH) PROJECT...being finalized in the reporting period. Thus far, the consultant submitted all of the 18 parts of the manual and strategic framework

36

Table 19: Number of new WPs constructed in SNNP Region in the First 9 Months of 2007 EFY

5.3.1.4 Water supply schemes constructed in Oromia Region

Twelve project woredas of Oromia (8 old and 4 new) have planned to construct 279 water

points- 261 by communities and 18 by institutions (9 each for schools and health facilities).

These water points are going to be constructed with the support of investment funds from the

regional government and contributions from the beneficiary community themselves.

A total of 366 applications (346 from communities and 20 from institutions) have been

submitted in the reporting period. Among these, 316 (302 community and 14 institutions

demands), 86.3% of the applications submitted, were appraised at the desk level by the

woreda experts trained. Of the desk appraised applications, majority of them (98.4%) have

been appraised on the field by the trained woreda appraisal team. As reported by the region,

300 (96.5%) of the field appraised applications were approved by WWTs of the project

woredas.

Table 20: Number of applications submitted, appraisals made and applications approved in

Oromia Region in the First Nine Months of 2007 EFY

<50% >50% Total

A. Community Water Points -

HDW with RP - - - - - - - - - HDW 134 170 148 147 143 28 22 20 42 SPD 120 166 144 141 137 25 7 11 18 - SW 7 10 10 10 7 7 - - DW - - - - - - - RWH - - - - - - SPD-RPS - DW-RPS - Subtotal 261 346 302 298 287 60 29 31 60 -

B. Institutional Water Points

B.1 School Water Points

HDW with RP - - - - - - - - -

HDW 9 13 9 9 9 2 2 -

SPD - - - - - - - - -

SW - - - - - - - - -

DW - - - - - - - - -

RWH - - - - - - - - -

SPD-RPS - DW-RPS - Subtotal 9 13 9 9 9 - 2 - 2 -

B.2 Health Institutions Water Points

HDW with RP - - - - - - - - - -

HDW 9 7 5 4 4 2 - 1 1 -

SPD - - - - - - - - - -

SW - - - - - - - - - -

DW - - - - - - - - - -

RWH - - - - - - - - - -

SPD-RPS - - DW-RPS - - Subtotal 9 7 5 4 4 2 - 1 1 -

Total 279 366 316 311 300 62 31 32 63 -

No. of WPs

Not Started

Construction

No. of WPs under

construction

No. of WPs

Abandoned

(could not

be

constructed)

Type of

Water

Point(WP)

No. of

Planned

WPs

No. of WPs

Applications

made

No. of WPs

Applications

Desk

Appraised

No. of WPs

Application

Field

Appraised

No. of WPs

Applications

Approved by

WWT

3rd

QuarterCumulative Annual

3rd

QuarterCumulative

A. Community Water PointsHDW with RP

HDW 1 23 23 2 3 705 625

SPD 119 361 361 65 125 63,218 44,425

SW 5 5 5

DW

RWH

SPD-RPS 12 1 512 383

DW-RPS

Subtotal 125 389 401 67 129 64,435 45,433

B. Institutional Water Points

B.1 School Water Points

HDW with RP

HDW 10 10 1 1 284

SPD 2 4 855

SW 1 1 1

DW

RWH

SPD-RPS

DW-RPS

Subtotal 1 11 11 3 5 1,139 -

B.2 Health Institutions Water Points -

HDW with RP -

HDW 4 4

SPD

SW

DW

RWH

SPD-RPS

DW-RPS

Subtotal - 4 4 - - - -

Total 126 404 416 70 134

Type of Water Point(WP)

Number of WPs

Construction

Completed

Actual No

of People

Using the

Completed

WPs

No of People

having access

to the

Completed WPs

within 1.5KM

radius of the

WPs

Number of WPs planned to be

constructed

Page 43: COMMUNITY-LED ACCELERATED WASH (COWASH) PROJECT...being finalized in the reporting period. Thus far, the consultant submitted all of the 18 parts of the manual and strategic framework

37

In Oromia region, a total of 151 (147 community and 4 school) water points, accounting

41.3% of the annual plan, have been completed in the reporting period. Over 9,150 rural

people of the project woredas have benefited from the community water points and 1,173

students and teachers from the 4 school hand dug wells constructed by schools with the

support of COWASH through the CMP approach.

Table 21: Number of new WPs constructed in Oromia Region in the First 9 Months of 2007 EFY

5.3.1.5 Water supply schemes constructed in Benishangul Region (BSGR)

The four project woredas of BSGR have planned to construct 70 water points- 51 by

communities and 19 by institutions (12 for schools and 7 for health facilities each). These

water points are going to be constructed with the support of investment funds from the

regional government, government of Finland and contributions from the beneficiary community

themselves. The construction of these water points will improve the low water supply access of

the woredas.

Consequently, a total of 45 applications (34 from communities and 11 from institutions) have

been submitted in two woredas in the reporting period. Among these, 38 (27 community and

11 institutional) demands, 84.4% of the applications submitted, were appraised at the desk

and field level by the woreda experts trained. It was reported from the region that 19 (50.0%)

desk appraised applications were approved by WWTs of the project woredas.

Construction has not been started in the woredas until end of the reporting period.

3rd

QuarterCumulative Annual

3rd

QuarterCumulative

A. Community Water PointsHDW with RP

HDW 60 60 134 54 58 9,150 9,150

SPD 57 57 120 77 89 17,133 17,133

SW 3 3 7

DW

RWH

SPD-RPS

DW-RPS

Subtotal 120 120 261 131 147 26,283 26,283

B. Institutional Water Points

B.1 School Water Points

HDW with RP

HDW 9 4 4 1,173

SPD

SW

DW

RWH

SPD-RPS

DW-RPS

Subtotal - - 9 4 4 1,173 -

B.2 Health Institutions Water Points -

HDW with RP -

HDW 9

SPD

SW

DW

RWH

SPD-RPS

DW-RPS

Subtotal - - 9 - - - -

Total 120 120 279 135 151

Type of Water Point(WP)

Number of WPs

Construction

Completed

Actual No

of People

Using the

Completed

WPs

No of People

having access

to the

Completed WPs

within 1.5KM

radius of the

WPs

Number of WPs planned to be

constructed

Page 44: COMMUNITY-LED ACCELERATED WASH (COWASH) PROJECT...being finalized in the reporting period. Thus far, the consultant submitted all of the 18 parts of the manual and strategic framework

38

Table 22: Number of applications submitted, appraisals made and applications approved in

Benishangul Gumuz Region in the First Nine Months of 2007 EFY

<50% >50% Total

A. Community Water Points -

HDW with RP - - - - - - - - HDW 42 29 23 23 16 - SPD 9 5 4 4 3 - SW - - DW - - - - - - - RWH - - - - - - SPD-RPS - DW-RPS - Subtotal 51 34 27 27 19 - - - - -

B. Institutional Water Points

B.1 School Water Points

HDW with RP - - - - - - - - -

HDW 12 6 6 6 - -

SPD - - - - - - - - -

SW - - - - - - - - -

DW - - - - - - - - -

RWH - - - - - - - - -

SPD-RPS - DW-RPS - Subtotal 12 6 6 6 - - - - - -

B.2 Health Institutions Water Points

HDW with RP - - - - - - - - - -

HDW 7 5 5 5 - - - -

SPD - - - - - - - - - -

SW - - - - - - - - - -

DW - - - - - - - - - -

RWH - - - - - - - - - -

SPD-RPS - - DW-RPS - - Subtotal 7 5 5 5 - - - - - -

Total 70 45 38 38 19 - - - - -

No. of WPs

Not Started

Construction

No. of WPs under

constructionNo. of WPs

Abandoned

(could not

be

constructed)

Type of

Water

Point(WP)

No. of

Planned

WPs

No. of WPs

Applications

made

No. of WPs

Applications

Desk

Appraised

No. of WPs

Application

Field

Appraised

No. of WPs

Applications

Approved by

WWT

As reported from the regions, in the reporting period, 1,297 water points (1,267 communal

and 30 institutional – 29 schools and 1 health facility) have been completed in the reporting

period in the four regions – Amhara, Tigray, SNNPR and Oromia. Majority of the WPs are hand

dug wells (710), followed by on spot springs (571) and shallow wells (16). The communal

water points are benefiting over 270,757 rural people in the project woredas while the school

water points are serving 15,493 students and teachers. The only health facility water point

constructed in Amhara is benefiting 21 health extension workers and some clients of the

facility.

In aggregate, since the launching of COWASH in 2004 EFY, a total of 6,331 water points

(6,007 communal, 324 institutional – 264 for schools and 60 for health facilities) have been

constructed in four project regions (5,148 in Amhara, 238 in Tigray, 313 in SNNPR and 632 in

Oromia). In terms of type, majority of the water points are hand dug wells (4,352), followed

by springs (1,911), shallow wells (65) and roof water harvesting (3) for schools. A total of

1.47 million rural people of the COWASH/CMP kebeles are benefiting from the 6,007 communal

water points. The 264 school water points constructed with the support of COWASH are

benefiting 105,380 students and teachers while the 60 health facilities’ schemes are serving

more than 12,989 health extension workers and some clients of the facilities.

Page 45: COMMUNITY-LED ACCELERATED WASH (COWASH) PROJECT...being finalized in the reporting period. Thus far, the consultant submitted all of the 18 parts of the manual and strategic framework

39

Table 23: Number of new (community, school and health institution) water points constructed until end of First 9 Months of 2007 EFY (March 31, 2015)

HDW

with RPHDW SPD SW DW RWH Total

Populatio

n Served

Popn.

having

Access

within

1.5km

HDW with

RPHDW SPD SW DW RWH Total

Populatio

n Served

Popn.

having

Access

within

1.5km

HDW

with

RP

HDW SPD SW DW RWH TotalPopulation

Served

Popn.

Having

Access

within

1.5Km of

Amhara 15 3,020 864 13 0 0 3,912 998,578 988,578 0 617 346 16 0 0 979 175,896 175,896 15 3,637 1,210 29 0 0 4,891 1,174,474 1,164,474

Tigray 0 85 90 33 0 0 208 59,589 59,589 0 8 4 0 0 0 12 4,143 4,143 0 93 94 33 0 0 220 63,732 63,732

SNNPR 0 8 161 0 0 0 169 56,451 51,114 0 3 126 0 0 0 129 64,435 45,433 0 11 287 0 0 0 298 120,886 96,547

Oromia 0 252 199 0 0 0 451 79,776 73,014 0 58 89 0 0 0 147 26,283 26,283 0 310 288 0 0 0 598 106,059 99,297

BSG 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

Subtotal 15 3,365 1,314 46 0 0 4,740 1,194,394 1,172,295 0 686 565 16 0 0 1,267 270,757 251,755 15 4,051 1,879 62 0 0 6,007 1,465,151 1,424,050

Amhara 0 181 10 0 0 0 191 66,686 0 16 2 0 0 0 18 11,228 0 197 12 0 0 0 209 77,914

Tigray 0 8 1 2 0 3 14 4,113 0 2 0 0 0 0 2 1,953 0 10 1 2 0 3 16 6,066

SNNPR 0 5 3 0 0 0 8 7,109 0 1 4 0 0 0 5 1,139 0 6 7 0 0 0 13 8,248

Oromia 0 16 6 0 0 0 22 11,979 0 4 0 0 0 0 4 1,173 0 20 6 0 0 0 26 13,152

BSG 0 0 0 0 0 0 0 0 0 0 0 0 0 0

Subtotal 0 210 20 2 0 3 235 89,887 0 23 6 0 0 0 29 15,493 0 233 26 2 0 3 264 105,380

Amhara 0 44 3 0 0 0 47 8,074 0 1 0 0 0 0 1 21 0 45 3 0 0 0 48 8,095

Tigray 0 0 1 1 0 0 2 100 0 0 0 0 0 0 0 0 0 1 1 0 0 2 100

SNNPR 0 1 1 0 0 0 2 445 0 0 0 0 0 0 0 0 1 1 0 0 0 2 445

Oromia 0 7 1 0 0 0 8 4,349 0 0 0 0 0 0 0 0 7 1 0 0 0 8 4,349

BSG 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

Subtotal 0 52 6 1 0 0 59 12,968 0 1 0 0 0 0 1 21 0 53 6 1 0 0 60 12,989

Amhara 15 3,245 877 13 0 0 4,150 0 634 348 16 0 0 998 15 3879 1225 29 0 0 5,148

Tigray 0 93 92 36 0 3 224 0 10 4 0 0 0 14 0 103 96 36 0 3 238

SNNPR 0 14 165 0 0 0 179 0 4 130 0 0 0 134 0 18 295 0 0 0 313

Oromia 0 275 206 0 0 0 481 0 62 89 0 0 0 151 0 337 295 0 0 0 632

BSG 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

Grandtotal 15 3,627 1,340 49 0 3 5,034 0 710 571 16 0 0 1,297 15 4,337 1,911 65 0 3 6,331

B. School

c. Health Institution

Total Water Points (Community + School + Health Institution)

A. Community

Region

Number of Water Points Constructed in COWASH Woredas

Cumulative2004-2006 EFY 2007 EFY Q1+Q2+Q3

Note: HDW with RP - Hand dug well with Rope Pump; SW - Shallow Well

HDW - Hand dug well with Afridev pump; DW - Deep well

SPD - Spring On Spot; RWH - Roof water harvesting

Page 46: COMMUNITY-LED ACCELERATED WASH (COWASH) PROJECT...being finalized in the reporting period. Thus far, the consultant submitted all of the 18 parts of the manual and strategic framework

40

5.3.2 Output 2: Access to Sanitation for Household and Institutions Increased and

Hygiene Behavior Improved

Percentage of ODF kebeles in the COWASH intervention woredas (disaggregated by project

regions), number of new institutional latrines constructed (disaggregated by institutions) are

the indicators of measuring the achievement of the output.

The ODF status of woredas will be reported at the end of the fiscal year upon receipt of

information from the regions.

The annual plans of the regions show that the attention to sanitation and hygiene has been

improving over the fiscal years. In 2007 EFY, 101 institutional latrines (61 for schools and 40

for health institutions) were planned to be constructed in the five regions of the project.

Among these latrines, 46 are in Amhara, 20 in Tigray, 13 in SNNPR, 14 in Oromia and 8 in

BSG regions.

In the reporting period, 97 applications (64 from schools and 40 from health facilities) have

been submitted to WWTs. It was reported that 93 (95.9%) of the applications were appraised

at the desk level by the woreda appraisal team. Among the desk appraised applications,

majority of them (97.9%) were field appraised by the same team of experts trained at the

regional level and of this 88(96.7%) were approved by the respective WWTs.

Table 24: Number of Latrines applications submitted, appraisals made and applications

approved in the First Nine Months of 2007 EFY

< 50% > 50% Total

Amhara 22 23 23 23 23 14 6 20

Tigray 14 20 20 20 20 0 0 0

SNNPR 13 15 11 11 10 5 1 6

Oromia 7 3 3 2 2 0 2 2

BSG 5 3 3 3 3 0 0 0

Subtotal 61 64 60 59 58 19 9 28

Amhara 24 23 23 23 23 14 5 19

Tigray 6 4 4 4 4 0 0 0

SNNPR 0 0 0 0 0 0 0 0

Oromia 7 5 5 4 2 1 0 1

BSG 3 1 1 1 1 0 0 0

Subtotal 40 33 33 32 30 15 5 20

Total 101 97 93 91 88 34 14 48

B. Health Institutions

No. of

Latrines

Applications

Approved

by WWT

Type of

Institution/

Region

No. of

Planned

Latrines

No. of

Latrines

Applications

made

No. of

Latrines

Applications

Desk

Appraised

No. of

Latrines

Application

Field

Appraised

No. of Latrines under

construction

A. Schools

In the first nine months, some institutional latrines, including those rolled over from the

preceding fiscal year, have been completed. Regional reports show that 16 institutional latrines

(8 each for schools and health facilities), were completed in three regions – Amhara (7), Tigray

(8) and SNNPR (1). These latrines are benefiting over 14,365 students and teachers (48.5%

female) and 282 health extension workers and clients of the facilities (46.5%) in the project

kebeles.

Page 47: COMMUNITY-LED ACCELERATED WASH (COWASH) PROJECT...being finalized in the reporting period. Thus far, the consultant submitted all of the 18 parts of the manual and strategic framework

41

Table 25: Number of Institutional Latrines Constructed in the First Nine Months of 2007 EFY

Annual3rd

QuarterCumulative

3rd

QuarterCumulative Male Female Total

A. School

Amhara 22 22 22 2 3 1,634 1,655 3,289

Tigray* 14 0 14 0 4 5,970 5,494 11,464

SNNPR 13 1 9 0 1 431 412 843

Oromia 7 2 7 0 0 -

BSG 5 0 0 0 0 -

Subtotal 61 25 52 2 8 8,035 7,561 15,596

B. Health Institution

Amhara 24 24 24 4 4 136 108 244

Tigray 6 0 4 0 4 15 23 38

SNNPR 0 0 0 0 0 -

Oromia 7 3 7 0 0 -

BSG 3 0 0 0 0 -

Subtotal 40 27 35 4 8 151 131 282

Total 101 52 87 6 16 8,186 7,692 15,878

Region

No. of Latrines

Construction

Completed

Estimated No. of People

using the Completed

Latrines

No. of Latrines Planned to be

Constructed

*- Note: In Tigray, woredas have constructed 1 block each for 3 schools and 2 blocks each for 13 schools

In total, 115 latrines (69 for schools and 46 for health facilities) were constructed in the

COWASH woredas through the CMP approach since the launching of COWASH project in four

regions (Amhara, Tigray, SNNPR and Oromia). There were no latrines constructed in BSG

region due to delay in the preparatory activities to start the project in the region. A total of

more than 79,008 students and teachers and 2,649 health staff, most of them health

extension workers, and some clients of the facilities are using these latrines (Table 26).

Table 26: Number of Institutional Latrines Constructed until end of March 31, 2015

M F T M F T M F T

Amhara 45 25,082 24,117 49,199 3 1,634 1,655 3,289 48 26,716 25,772 52,488

Tigray* 9 2,914 2,963 5,877 4 5,970 5,494 11,464 13 8,884 8,457 17,341

SNNPR 2 858 787 1,645 1 431 412 843 3 1,289 1,199 2,488

Oromia 5 2,245 4,446 6,691 0 0 5 2,245 4,446 6,691

Subtotal 61 31,099 32,313 63,412 8 8,035 7,561 15,596 69 39,134 39,874 79,008

Amhara 27 228 206 434 4 136 108 244 31 364 314 678

Tigray 3 20 38 58 4 15 23 38 7 35 61 96

SNNPR 0 0 0 0 0 0 0 0 0 0

Oromia 8 925 950 1,875 0 0 8 925 950 1,875

Subtotal 38 1,173 1,194 2,367 8 151 131 282 46 1,324 1,325 2,649

Amhara 72 25,310 24,323 49,633 7 1,770 1,763 3,533 79 27,080 26,086 53,166

Tigray 12 2,934 3,001 5,935 8 5,985 5,517 11,502 20 8,919 8,518 17,437

SNNPR 2 858 787 1,645 1 431 412 843 3 1,289 1,199 2,488

Oromia 13 3,170 5,396 8,566 0 0 0 0 13 3,170 5,396 8,566

Grandtotal 99 32,272 33,507 65,779 16 8,186 7,692 15,878 115 40,458 41,199 81,657

No. of

Latrines

Population Served

2007 EFY Q1+Q2+Q3

No. of

Latrines

Population Served

2004-2006 EFY

No. of

Latrines

Population Served

Total (School + Health Institution)

Cumulative

Number of Latrines Constructed in COWASH Woredas

A. School

B. Health Institution

Region

Note *: In Tigray upgrading of school latrines have been conducted. In the first half of 2007 EFY, besides the 8 standard latrines, 1 block latrine each for 3 schools and 2 blocks latrines each for 13 schools have been constructed in some woredas.

Page 48: COMMUNITY-LED ACCELERATED WASH (COWASH) PROJECT...being finalized in the reporting period. Thus far, the consultant submitted all of the 18 parts of the manual and strategic framework

42

5.3.3 Output 3: Sustainability of Communal and Institutional Water Schemes in the

Targeted Woredas Strengthened

Three indicators are set to measure the achievement of the output. These are: i) number of

CMP schemes with trained pump attendants and caretakers (disaggregated by sex); ii) number

of water points rehabilitated (disaggregated by communal and institutional); and

iii) percentage of WASHCOs with at least 50% women members.

A number of activities were expected to be accomplished every year for the attainment of this

output. The main ones are: i) maintain or repair water schemes; ii) provide refresher trainings

for members of existing (old) WASHCOs in O&M management, environment, sanitation,

hygiene and gender; and iii) carry out refresher training for existing pump attendants and

caretakers and their replacements in Operation and Maintenance (O&M). However, only very

few of them performed in the reporting period. Data on the percentage of WASHCOs with at

least 50% or more female members and trained pump attendants and caretakers are reported

at the end of the fiscal year.

Table 27: Number of Water Points Planned to be Rehabilitated in 2007 EFY

Community Institutional Total

Amhara 105 23 128

Tigray 95 12 107

SNNPR 31 6 37

Oromia 2 0 2

BSG 8 3 11

Total 241 44 285

Project RegionNumber of WPs Planned to be Rehabilitated

A total of 285 water points (241 community and 44 institutional) were planned to be

rehabilitated in all regions in 2007 EFY (Table 28).

However, the performance of the regions in rehabilitating water points was very low in the

reporting period as woredas have been giving priority to new constructions and delay in the

approval of the plans

Anyhow, 33 communal water points (18 hand dug wells and 15 springs) have been

rehabilitated in the first nine months in Tigray, SNNPR and Oromia regions. This accounts only

11.6% of the rehabilitations planned in 2007 EFY. There were no rehabilitations completed in

Amhara and BSG woredas in the reporting period.

In total, 348 water points (342 communal and 6 school water points) were rehabilitated in

COWASH woredas since 2004 EFY– 288 in Amhara, 23 in Tigray, 28 in SNNPR and 9 in Oromia

regions (Table 28). The water points rehabilitated are benefiting more than 91,187 rural

people and 2,314 students and teachers in the project woredas.

Page 49: COMMUNITY-LED ACCELERATED WASH (COWASH) PROJECT...being finalized in the reporting period. Thus far, the consultant submitted all of the 18 parts of the manual and strategic framework

43

Table 28: Number of Water Points Rehabilitated until end of March 31, 2015

HDW

with

RP

HDW SPD SW DW RWH TotalPopulation

Served

HDW

with

RP

HDW SPD SW DW RWH TotalPopulation

Served

HDW

with

RP

HDW SPD SW DW RWH TotalPopulation

Served

Amhara 0 206 78 0 0 0 284 68,850 0 0 0 0 0 0 0 0 206 78 0 0 0 284 68,850

Tigray 0 7 5 0 0 0 12 3,000 0 11 0 0 0 0 11 2,250 0 18 5 0 0 0 23 5,250

SNNPR 0 4 4 0 0 0 8 6,855 0 6 14 0 0 0 20 9,380 0 10 18 0 0 0 28 16,235

Oromia 0 3 2 0 0 0 5 558 0 1 1 0 0 0 2 294 0 4 3 0 0 0 7 852

BSG 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

Subtotal 0 220 89 0 0 0 309 79,263 0 18 15 0 0 0 33 11,924 0 238 104 0 0 0 342 91,187

Amhara 0 4 0 0 0 0 4 1080 0 0 0 0 0 0 0 0 4 0 0 0 0 4 1,080

Tigray 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

SNNPR 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

Oromia 0 2 0 0 0 0 2 1234 0 0 0 0 0 0 0 0 2 0 0 0 0 2 1,234

BSG 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

Subtotal 0 6 0 0 0 0 6 2,314 0 0 0 0 0 0 0 0 0 6 0 0 0 0 6 2,314

Amhara 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

Tigray 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

SNNPR 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

Oromia 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

BSG 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

Subtotal 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

Amhara 0 210 78 0 0 0 288 0 0 0 0 0 0 0 0 0 210 78 0 0 0 288

Tigray 0 7 5 0 0 0 12 0 11 0 0 0 0 11 2250 0 18 5 0 0 0 23

SNNPR 0 4 4 0 0 0 8 0 6 14 0 0 0 20 9380 0 10 18 0 0 0 28

Oromia 0 5 2 0 0 0 7 0 1 1 0 0 0 2 294 0 6 3 0 0 0 9

BSG 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

Grandtotal 0 226 89 0 0 0 315 0 18 15 0 0 0 33 11,924 0 244 104 0 0 0 348

c. Health Institution

Total Rehabilitated (Community + School + Health Institution)

Cumulative

Number of Water Points Rehabilitated in COWASH Woredas

A. Community

B. School

Region2004-2006 EFY 2007 EFY Q1+Q2+Q3

Note: HDW with RP - Hand dug well with Rope Pump; SW - Shallow Well

HDW - Hand dug well with Afridev pump; DW - Deep well

SPD - Spring On Spot; RWH - Roof water harvesting

Page 50: COMMUNITY-LED ACCELERATED WASH (COWASH) PROJECT...being finalized in the reporting period. Thus far, the consultant submitted all of the 18 parts of the manual and strategic framework

44

5.3.4 Output 4: Potable Water Quality Ensured in Targeted Woredas

Number of water quality tests (post construction) made on CMP water schemes (new and

rehabilitations); number of chlorination made (post construction) on CMP water schemes (new and

rehabilitations) and number of CMP water schemes with Water Safety Plans are the indicators set to

measure the achievement of the output.

Some of the major activities to be performed to attain the output are: i) chlorination of water

schemes before taken into use; ii) carrying out testing of water quality of water schemes before

taken into use and periodically; iii) train WASHCOs in Water Safety Planning; iv) conduct periodic

water safety planning by WASHCOs; v) procure water quality testing kits for woredas; and vi) train

woreda staff on the use of water quality testing kits. These activities are planned to be

accomplished in the fiscal year.

Many of the activities related to water quality have not been undertaken in many of the project

regions in the reporting period. The practice of preparing Water Safety Plans for water points is not

common in Ethiopia. With the view to sustain the water points and maintain the quality of the

water, training of trainers on GLOWS/Water Safety Planning (WSP) was given, by WHO and

MetaMeta in collaboration with COWASH, to COWASH RSU and some regional water bureau and

MoWIE staff. Consequently, the training of regional, zonal and woreda staff will be started by the

regions and WSP plans prepared for the water points. Moreover, Water Safety Planning is being

piloted in one micro-watershed of a kebele in Yilmana Densa woreda of Amhara region with the

cooperation of an international organization called MetaMeta. This fiscal year, the planning is

scaled-up in selected woredas of the other project regions. However, many of these activities have

not been conducted.

All of the regions have planned to procure water quality tests kits for woredas. Amhara has already

procured the kits and SNNPR is finalizing the procurement. Other regions are in the process of

procuring the kits. Besides, as indicated in Output2 of Result 1, WASHCOs have been receiving

training on O&M of schemes so as to sustain their water points.

Page 51: COMMUNITY-LED ACCELERATED WASH (COWASH) PROJECT...being finalized in the reporting period. Thus far, the consultant submitted all of the 18 parts of the manual and strategic framework

45

6 FINANCIAL PERFORMANCE

In this chapter, the financial utilization performance, in the reporting period, of all the components

of the project (Component 1 and 2) are described. Each component is discussed separately and

summarized financial data by region are presented accordingly.

6.1 COMPONENT 1, FEDERAL LEVEL

The COWASH expenditures started to build-up already during 2003 Ethiopian Fiscal Year (EFY). The

financial plan and usage of C-1 for the Phase I and II until the end of the reporting period (March

2015) are presented as follows.

6.1.1 Cumulative expenditures of Phase I and II

The total C-1 five year budget is EUR 3 730 392 (Table 29). The total budget usage at the end of

March 2015 is EUR 2,579,297. This represents 69 % total usage of Component 1. The usage of the

fee component is 68 %. The usage of the reimbursable costs is 77 % and the usage of the capacity

building and sector support component is 57 %.

Table 29: Total C-1 Usage Follow-up compared to the 5 year budget (2011-2016)

Figure (a) below illustrates that the total budget utilization of C-1 lags some 65,000 EUR behind

when compared to the planned total 5 years budget.

The budget between the Fee, Reimbursable costs and Sector Support and Capacity Building was re-

adjusted for Phase II of C-1 starting from October 1, 2014.

Page 52: COMMUNITY-LED ACCELERATED WASH (COWASH) PROJECT...being finalized in the reporting period. Thus far, the consultant submitted all of the 18 parts of the manual and strategic framework

46

Figure a. Illustration of the C-1 Budget Utilization based on the 5 year budget period (2011-2016).

Ethiopian Fiscal Year (EFY) is for a period of July-June.

6.1.2 Comparison of the budget utilization with the first 6 - months of Phase II (October

2014-March 2015) representing the Quarter II of 2007 Ethiopian Fiscal Year.

The comparison of the 1st and 2nd quarter of Phase II of Component 1 (Q2 and Q3/2007 EFY)

cumulative budget and expenditures is presented in Table 30 below. The follow-up reveals that

the total 80.0% of the two quarters budget of Phase II (October 2014-March 2015) was utilized.

The Fee usage was 78.0%, reimbursable usage 83.0% and sector support usage 88.0%. The

main reason for the underutilization of the fee budget was the non-invoiced days of the HRDS

visits to Ethiopia made in January-March 2015 and late start of Training Impact Assessment

Consultancy and late execution of the RWS O&M consultancy. For these reasons, the total Fee

budget usage was below the planned. The over usage in Junior Expert budget line was caused

from the non-used annual leaves.

The reimbursable budget usage was about 83.0 %. The low budget usage was caused from the

non-executed international HRD consultant travelling costs and savings achieved in local

travelling.

The slight underuse of the sector support budget was due to the cancellation of participation in

the 7th WWF in Korea.

Page 53: COMMUNITY-LED ACCELERATED WASH (COWASH) PROJECT...being finalized in the reporting period. Thus far, the consultant submitted all of the 18 parts of the manual and strategic framework

47

Table 30: Comparison of budget and expenditures of 1st and 2nd quarters of Phase II

(Q2+Q3/2007 EFY)

The expenditure follow-up of the 2007 Ethiopian Fiscal Year which overlaps with the Phase I and

II of Component 1 by one quarter is illustrated in Table 31 below.

The total budget usage during the 9 months of 2007 EFY was about 101.0 %. Due to the

extensive GIS trainings, the sector support budget was slightly overused. International short

term consultancy use was less than planned due to the non-invoicing of the already conducted

consultancy days. The National Short term consultancy budget was slightly overused due to the

Q1 additional works for Training Impact Assessment work.

The table shows that 68 % of the planned 2007 EFY budget was used during the first three

quarters of the fiscal year. Major savings were made in the reimbursable costs and in the use of

National Short Term Consultants as explained above.

Table 31: Component 1 budget follow-up of 2007 EFY

Page 54: COMMUNITY-LED ACCELERATED WASH (COWASH) PROJECT...being finalized in the reporting period. Thus far, the consultant submitted all of the 18 parts of the manual and strategic framework

48

6.2 COMPONENT 2 FINANCIAL PERFORMANCE

The financial performances of Component 2 in the reporting period, disaggregated by project

regions, are presented hereunder.

6.2.1 Tigray Region

The funding arrangement in Tigray is governed by the funding agreement signed between the

Bureau of Plan and Finance of Tigray National Regional State and Embassy of Finland. All the

investment and some operational costs are covered by the Tigray National Regional State while the

(human and physical) capacity building fund is contributed from the Finland Government. The

investment funds and capacity building funds are being channeled in different ways. All the

investment funds from the regional government are being channeled to the communities through

Dedebit Credit and Saving Institution (DECSI) with a commission of 5% while the capacity building

fund from the Finnish Government has been channeled through the government financial structure.

An estimated amount of Birr 54.94 million (Birr 16.26 million from GoE and Birr 38.69 million from

GoF) was allocated for 2007 EFY. Some 65.1 %, 5.9 %, 11.3 %, and 17.6 % of the annual budget

was allocated for investment, physical capacity building, human capacity building and operational

cost (including RSU costs), respectively. Of this annual budget, Birr 52.61 million (95.7%) was

allocated for the first nine months of the fiscal year.

The financial performance report of the region shows that only 13.1% of the total fund allocated for

first nine months has been utilized for implementing the planned activities (Table 32). The

breakdown of budget utilization by cost categories shows that only 16.4% of the investment funds,

0.2% of the physical capacity building funds, 2.8% of the human capacity building funds, and

14.4% of the operational costs allocated for the reporting period have been utilized in the first nine

months of the fiscal year.

Table 32: Fund allocated and Utilized in Tigray region in the First Nine Months of 2007 EFY

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19

Planned

for 3rd

Quarter

Ut ilized 3rd

Quarter

(15+18 )

Planned for

3rd Quarter

Utilized 3rd

Quarter

Planned for

3rd Quarter

Utilized 3rd

Quarter

GoF GoE Total (1+2 ) GoF GoE GoF+GoE GoF GoE GoF+GoE GoF + GoE GoF + GoE

Cumulat ive

( 9 / 6 ) *10

0

This

Quarter

(11/ 10 )

*10 0

GoF GoF GoE GoE

INVESTM ENT

COST0.00 35,795,025 35,795,025 0.00 35,795,025 35,795,025 0.00 5,877,695.23 5,877,695.23 0 0.00 16.42 # DIV/0! 0.00 0.00 # DIV/0! 0 0.00 # DIV/0!

PHYSICAL

CAPACITY

BUILDING COST

3,263,750 0.00 3,263,750 3,263,750 0.00 3,263,750 116,562.21 0.00 6,723.70 0 109,838.51 0.21 # DIV/0! 0 109,838.51 # DIV/0! 0.00 0.00

HUM AN

CAPACITY

BUILDING COST

6,219,486 0.00 6,219,486 8,275,856 0.00 8,275,856 1,936,096.27 0.00 232,666.13 316,501 1,925,933.37 2.81 608.51 316,501 1,925,933.37 608.51 0.00 0.00

OPERATIONAL

COST6,772,806 2,893,500 9,666,306 4,063,572 1,212,299 5,275,871 797,340.57 397,601.40 757,331.30 1,537,285 571,545.52 14.35 37.18 645,235 224,344.12 34.77 892,050 347,201.40 38.92

TOTAL 16,256,042 38,688,525 54,944,567 15,603,178 37,007,324 52,610,502 812,386.28 6,062,030.08 6,874,416.36 1,853,786 2,607,317.40 13.07 140.65 961,736 2,260,116.00 235.00 892,050 347,201.40 38.92

Total in Euro (1

Euro = 24 Birr)677,335 1,612,022 2,289,357 650,132 1,541,972 2,192,104 33,849 252,585 286,434 77,241 108,638 40,072 94,172 37,169 14,467

Utilizat io

n (%)

( 18 / 17)

*10 0

Category

Planned(Annual) Cumulat ive Planned Cumulat ive Utilized Utilizat ion(%)Utilizat ion

(%)

( 15/ 16 ) *1

0 0

Note: All the investment fund for the fiscal year is allocated for the 2nd quarter so as to transfer the investment fund to the woredas at once

Page 55: COMMUNITY-LED ACCELERATED WASH (COWASH) PROJECT...being finalized in the reporting period. Thus far, the consultant submitted all of the 18 parts of the manual and strategic framework

49

The total funds received from sources (GoE & GoF) and transferred to and utilized by sector offices

to date in Tigray are indicated in Table 33 below.

Table 33: Funds received, transferred and utilized in Tigray until end of March 31, 2015

Received

(%)

Transferred

(%)

GoF28,734,412.85 28,102,662.29 15,920,221.17 12,814,191.68 12,182,441.12 55.4 56.7

GoE28,463,124.94 28,463,124.94 22,289,694.04 6,173,430.90 6,173,430.90 78.3 78.3

Total 57,197,537.79 56,565,787.23 38,209,915.21 18,987,622.58 18,355,872.02 66.8 67.5

Usage from Budget

Source

Received

from Source

to date

Transferred to

Beneficiaries

to date

Utilized by

Beneficiaries

to date

Balance

from

Received to

date

Balance

from

Transferred

to date

Note: From the GoF funds received so far, Birr 1,618,280.55 was exchange rate gain and the amount is not yet utilized.

Tigray region received a total of Euro 1,200,462.77 (equivalent to about Birr 28,734,412.85) from

the Finland Government (GoF). In total, the region received Birr 57.20 million from the two sources

for the implementation of COWASH project in the region - Birr 28.73 million from GoF and Birr

28.50 million from GoE. Of this amount, approximately Birr 56.57 million (Birr 28.10 million from

GoF and the entire amount received from GoE) has been transferred to beneficiaries of the project.

Until end of the reporting period (March 31, 2015), 66.8 % of the amount received (55.40 % of the

GoF and 78.3% off the GoE) or 67.6 % of the transferred (56.7 % of GoF and 78.3 % of GoE) has

been utilized for investment (construction of water supply schemes and institutional latrines),

(physical and human) capacity building and covering the operational costs of the project.

6.2.2 SNNP REGION

The funding arrangement in SNNPR is governed by the funding agreement signed between the

Bureau of Finance and Economic Development (BoFED) of Southern Nations Nationalities and

Peoples’ Regional State and Embassy of Finland (EoF). All the investment, some operational costs

and all the physical capacity building of the new woredas and zones are covered by SNNPR while

the (human and physical) capacity building fund for the old woredas, zones and regional sector

offices and all the human capacity building funds for the new woredas and zones is contributed

from the Finland Government. The investment and capacity building funds are being channeled in

different ways. All the investment funds from the regional government are being channeled to the

communities through Omo Microfinance Institute (OMFI) with a commission of 3% while the

capacity building fund from the regional state and Finnish Government has been channeled through

the government financial structure.

The project has allocated an estimated amount of Birr 47.16 million (Birr 17.02 million from GoF

and Birr 30.13 million from GoE) was allocated for 2007 EFY. Of this amount, SNNPR has allocated

an estimated amount of Birr 44.48 million (Birr 15.71 million from GoF and Birr 28.7 million from

GoE) for first nine months of 2007 EFY. This accounts 94.3% of the annual budget allocated for the

project. This annual budget includes unutilized fund rolled over from 2006 EFY. Like the other

regions, the budget allocated for reporting period was apportioned into four cost categories:

investment cost (42.0%), physical capacity building cost (30.9%), human capacity building cost

(17.3%) and operational cost (9.8%).

The financial performance of the region shows that approximately 32.1 % of the total fund

allocated for the first nine months of 2007 EFY has been utilized (Table 34). The budget utilization

Page 56: COMMUNITY-LED ACCELERATED WASH (COWASH) PROJECT...being finalized in the reporting period. Thus far, the consultant submitted all of the 18 parts of the manual and strategic framework

50

by cost category shows that 22.9 % of the investment funds, 89.3% of the physical capacity

building budget, 23.6% of the human capacity building funds and 48.1% of the operational cost

allocated for the reporting period has been utilized.

The fund utilization performance of the region was very low. The delay in the transfer of funds and

unsettled funds in the woredas have contributed for the low utilization rate of the region.

Table 34: Fund allocated and Utilized in SNNPR in the First Nine Months of 2007 EFY

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19

Planned for

this Quarter

(14 +17)

Utilized this

Quarter

(15+18 )

Planned for

this Quarter

Utilized this

Quarter

Planned for this

Quarter

Utilized this

Quarter

GoF GoE Total (1+2 ) GoF GoE GoF+GoE GoF GoE GoF+GoE GoF + GoE GoF + GoE

Cumulat i

ve

( 9 / 6 ) *

10 0

This

Quarter

(11/ 10 ) *

10 0

GoF GoF GoE GoE

INVESTM ENT

COST - 27,192,766 27,192,766 26,152,245 26,152,245 5,983,948 5,983,948 7,746,285 3,459,600 22.9 44.7 # DIV/0! 7,746,285 3,459,600 44.7

PHYSICAL

CAPACITY

BUILDING

COST

3,196,150 1,744,855 4,941,005 3,196,150 1,744,885 4,941,035 3,396,614 1,016,417 4,413,031 - 3,840,143 89.3 # DIV/0! - 3,217,213 # DIV/0! - 622,930 # DIV/0!

HUM AN

CAPACITY

BUILDING

COST

11,217,561 - 11,217,561 10,493,292 - 10,493,292 2,474,488 2,474,488 1,960,924 1,107,664 23.6 56.5 1,960,924 1,107,664 56.5 # DIV/0!

OPERATIONA

L COST 2,608,298 1,195,843 3,804,141 2,025,134 868,719 2,893,853 1,183,153 207,663 1,390,816 1,098,449 626,417 48.1 57.0 707,017 527,988 74.7 391,432 98,429 25.1

TOTAL 17,022,009 30,133,464 47,155,473 15,714,576 28,765,849 44,480,425 7,054,255 7,208,028 14,262,283 10,805,658 9,033,824 32.06 83.60 2,667,941 4,852,865 181.90 8,137,717 4,180,959 51.38

Utilizat ion (%)

( 18 / 17) *10

0

Category

Planned(Annual) Cumulat ive Planned Cumulat ive Utilized Utilizat ion(%)Utilizat i

on (%)

( 15/ 16

) *10 0

Table 35 illustrates the total funds received from sources (GoE & GoF) and transferred to and

utilized by sector offices to date in SNNPR.

Table 35: Funds received, transferred and utilized in SNNPR until end of First Nine Months of 2007

EFY (March 31, 2015)

Received

(%)

Transferred

(%)

GoF24,370,231.50 23,782,248.26 17,479,426.41 6,890,805.09 6,302,821.85 71.7 73.5

GoE35,116,139.00 32,924,593.14 16,247,888.94 18,868,250.06 16,676,704.20 46.3 49.3

Total 59,486,370.50 56,706,841.40 33,727,315.35 25,759,055.15 22,979,526.05 56.7 59.5

Usage from Budget

Source

Received from

Source to date

Transferred to

Beneficiaries

to date

Utilized by

Beneficiaries to

date

Balance from

Received to

date

Balance from

Transferred

to date

Note: Of the total Birr 24.37 million transferred from MFA, some Birr 1,376,594.80 was exchange rate gain. All of this amount has been utilized.

The SNNPR BoFED received a total of Euro 1,087,713 (equivalent to about Birr 24,370,236.80)

from the Finland Government. Until end of the reporting period, the region received about Birr

59.49 million from the two sources for the implementation of COWASH project in the region - Birr

24.37 million from GoF and Birr 35.12 million from GoE. Of this amount, approximately Birr 56.71

million (Birr 23.78 million from GoF and Birr 32.92 million from GoE) or 95.3 % of the amount

received was transferred to beneficiary offices. Until 31st March 2015, 56.7% of the amount

received (71.7 % of the GoF and 46.3 % of the GoE) or 59.5% of the transferred (73.5 % of GoF

and 49.3 % of GoE) has been utilized in SNNP region.

Page 57: COMMUNITY-LED ACCELERATED WASH (COWASH) PROJECT...being finalized in the reporting period. Thus far, the consultant submitted all of the 18 parts of the manual and strategic framework

51

6.2.3 Oromia Region

The funding arrangement in Oromia is governed by the funding agreement signed between the

Bureau of Finance and Economic Development of Oromia National Regional State and Embassy of

Finland. All the investment and some operational costs are covered by the SNNPR while all the

(human and physical) capacity building fund is contributed from the Finland Government. Funds are

being channeled in two ways: all the investment funds from the regional government are being

channeled to the communities through Oromo Credit and Saving Share Company (OCSSCo) with a

commission of 4% while the capacity building funds from the Finnish Government has been

channeled through the government financial structure.

An estimated amount of Birr 35.62 million (Birr 21.21 million from GoF and Birr 14.41 million from

GoE) was allocated for implementation of planned activities in the fiscal year at all levels: regional,

zonal and woreda. Of this, 91.4% was allocated for the first nine months of the fiscal year.

Funds allocated for Oromia region was apportioned into the four cost categories: investment costs,

physical capacity building costs, human capacity building costs and operational costs. Of the total

budget allocated for the reporting period, 40.4%, 23.5 %, 30.4%, and 5.7 % was allocated for

investment, physical capacity building, human capacity building and operational costs, respectively.

The regional report revealed that only 28.9 % of the total fund allocated for the first nine months

has been utilized (Table 36). In terms of cost category, 38.2% of the investment funds, 31.4% of

the physical capacity building, 13.0% of the human capacity building funds and 37.2% of the funds

allocated for operation have been utilized in the reporting period. The financial utilization

performance of the region was low due to delay in the approval of the annual work plan and hence

delay in the release of funds for the first two quarters of the fiscal year.

Table 36: Fund allocated and Utilized in Oromia Region in the First Nine Months of 2007 EFY

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19

Planned for

3rd Quarter

(14 +17)

Utilized 3rd

Quarter

(15+18 )

Planned for

3rd Quarter

Utilized 3rd

Quarter

Planned for

3rd Quarter

Utilized 3rd

Quarter

GoF GoE Total (1+2 ) GoF GoE GoF+GoE GoF GoE GoF+GoE GoF + GoE GoF + GoE

Cumulat ive

( 9 / 6 ) *10

0

This

Quarter

(11/ 10 ) *10

0

GoF GoF GoE GoE

INVESTM ENT

COST13,152,618 13,152,618 13,152,618 13,152,618 5,023,494 5,023,494 6,168,497 5,023,494 38.2 81.4 - 6,168,497 5,023,494

PHYSICAL

CAPACITY

BUILDING

COST

7,664,250 7,664,250 7,664,250 7,664,250 2,406,362 - 2,406,362 - 2,406,362 31.4 # DIV/0! - 2,406,362 # DIV/0!

HUM AN

CAPACITY

BUILDING

COST

12,788,460 12,788,460 9,900,102 9,900,102 1,287,650 - 1,287,650 223,366 1,287,650 13.0 576.5 223,366 1,287,650 576.5

OPERATIONAL

COST758,400 1,259,272 2,017,672 580,800 1,259,272 1,840,072 450,900 232,892 683,792 563,965 366,586 37.2 65.0 193,600 170,132 87.9 370,365 196,454.0 0.5

TOTAL 21,211,110 14,411,890 35,623,000 18,145,152 14,411,890 32,557,042 4,144,912 5,256,386 9,401,298 6,955,828 9,084,092 28.9 130.6 416,966 3,864,144 926.7 6,538,862 5,219,948 80

Ut ilizat ion (%)

( 18 / 17) *10 0

Category

Planned(Annual) Cumulat ive Planned Cumulat ive Utilized Utilizat ion(%)Utilizat ion

(%)

( 15/ 16 ) *

10 0

Page 58: COMMUNITY-LED ACCELERATED WASH (COWASH) PROJECT...being finalized in the reporting period. Thus far, the consultant submitted all of the 18 parts of the manual and strategic framework

52

Total fund received and utilized to date in Oromia region, by fund source, is indicated in Table 37.

The region has received Euro 1,158,347 (Birr 28,016,347.24) GoF contribution from Ministry of

Foreign Affairs (MFA) of Finland and Birr 33.71 million from Oromia regional government. About

93.2 % of the amount received from the two sources (99.3% of the GoF and 88.0% of the GoE)

has been transferred to beneficiary sector offices as per their annual plans approved by the

Regional WaSH Steering Committee (RWSC). Of the total amount of funds transferred to

beneficiary sector offices, 70.3% (62.6 % of the GoF and 77.5 % of the GoE) has been utilized until

end of March 31, 2015. About 65.5% (62.2 % of the GoF and 68.3 % of the GoE) of the amount

received from the sources (GoF and GoE) has been utilized by beneficiary sector offices including

RSU.

Table 37: Funds received, transferred and utilized in Oromia Region until end of March 31, 2015

Received

(%)

Transferred

(%)

GoF 28,016,347.24 27,823,787.44 17,424,409.49 10,399,377.95 10,591,937.75 62.2 62.6

GoE 33,706,573.62 29,682,115.39 23,012,354.54 6,669,760.85 10,694,219.08 68.3 77.5

Total 61,722,920.86 57,505,902.83 40,436,764.03 17,069,138.80 21,286,156.83 65.5 70.3

Usage from Budget

Source

Received from

Source to date

Transferred to

Beneficiaries

to date

Utilized by

Beneficiaries

to date

Balance from

Received to

date

Balance from

Transferred to

date

Note: Of the Birr 28.02 million received from GoF, Birr 502,942.47 was exchange rate gain. All of this exchange rate gain has been utilized.

6.2.4 Amhara region

As per the funding agreement signed between the Bureau of Finance and Economic Development of

Amhara National Regional State, all capacity building and some operational costs (including all RSU

costs) are covered from GoF contribution while all investment costs and some operational costs are

covered from GoE fund allocations. All the investment funds from GoE is being channeled to the

communities through Amhara Credit and Saving Institution (ACSI) with a commission of 3% while

the capacity building funds and operational costs from the Finnish Government has been channeled

through the government financial structure - BoFED-ZoFED/WoFED.

A total of about Birr 196.79 million (Birr 95.90 million from GoF and Birr 100.89 million from GoE)

is allocated, including BoFED Treasury contingency, for 2007 EFY. Of this amount, approximately

Birr 193.57 million (Birr 93.89 million from GoF and Birr 99.69 million from GoE), about 41.9 % of

the total allocated for the fiscal year, was allocated for the first nine months of the fiscal year.

Report of the regional performance revealed that of the total amount allocated, 25.4 % (19.2 % of

the GoF and 31.2% of the GoE) funds allocated for the nine months has been utilized by the

beneficiaries (regional, zonal and woreda sector offices and RSU). The budget utilization has been

low as the 31 vehicles planned to be procured for new woredas and zones have not been supplied

in the reporting period and settlement of shallow wells drilling costs by WASHCOs has been delayed

due to low performance of drillers.

Page 59: COMMUNITY-LED ACCELERATED WASH (COWASH) PROJECT...being finalized in the reporting period. Thus far, the consultant submitted all of the 18 parts of the manual and strategic framework

53

Table 38: Fund allocated and Utilized in Amhara Region in the First Nine Months of 2007 EFY

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19

Planned for

3r d

Quarter

(14 +17)

Utilized 3r d

Quarter

(15+18 )

Planned for

3r d

Quarter

Utilized 3r d

Quarter

Planned for

3r d

Quarter

Utilized 3r d

Quarter

GoF GoE Total (1+2 ) GoF GoE GoF+GoE GoF GoE GoF+GoE GoF + GoE GoF + GoE

Cumulat ive

( 9 / 6 ) *10

0

3r d

Quarter

(11/ 10 ) *10

0

GoF GoF GoE GoE

INVESTM ENT

COST648,223 93,336,812 93,985,035 648,223 92,136,812 92,785,035 - 30,430,130 30,430,130 33,853,398 - - 33,853,398

PHYSICAL

CAPACITY

BUILDING

COST

63,635,920 63,635,920 63,635,920 63,635,920 8,139,436 8,139,436 59,276,800 5,452,816 12.8 9.2 59,276,800 5,452,816 9.2

HUM AN

CAPACITY

BUILDING

COST

23,847,708 23,847,708 23,390,220 23,390,220 7,374,467 7,374,467 12,222,768 5,193,598 31.5 42.5 12,222,768 5,193,598 42.5

OPERATIONAL

COST 7,202,760 7,548,450 14,751,210 5,930,328 7,548,450 13,478,778 2,521,824 718,330 3,240,154 5,007,932 1,574,887 24.0 31.4 1,471,232 856,558 58.2 3,536,700 718,330 20.3

BoFED

Treasury &

Contingency

565,389 565,389 282,695 282,695 2,282 2,282 282,695 - - 282,695 - -

TOTAL 95,900,000 100,885,262 196,785,262 93,887,386 99,685,262 193,572,648 18,038,010 31,148,459 49,186,469 110,643,593 12,221,301 25.4 11.0 73,253,495 11,502,972 15.7 37,390,098 718,330 1.9

Ut ilizat ion (%)

( 18 / 17) *10

0

Category

Planned(Annual) Cumulat ive Planned Cumulat ive Utilized Utilizat ion(%)Utilizat ion

(%)

( 15/ 16 ) *

10 0

The Amhara region has received about Birr 432.82 million (8,391,081.71 Euro or about Birr 209.46

million from Government of Finland including Birr 4,291,860.92 RWSEP savings and Birr 223.36

million from Amhara Regional Bureaus) for the implementation of planned activities in the woredas,

zones and sector bureaus in the region. Of this amount, approximately Birr 416.75 million (Birr

191.83 million from GoF and 100% of the GoE contribution) has been transferred to beneficiaries.

This accounts 96.3 % of the total received from the two funding sources.

From the total funds transferred to beneficiaries, about Birr 282.76 million (67.8%) has been

utilized until end of the reporting period (Table 39). In terms of fund source, Birr 148.72 million

(76.9%) and Birr 134.04 million (60.0%) of GoF and GoE funds transferred, respectively, has been

utilized by beneficiaries of the project.

Table 39: Funds received, transferred and utilized in Amhara Region until end of March 31, 2015

Received

(%)

Transferred

(%)

GoF (including RWSEP

saving)209,461,912.25 193,388,638.34 148,721,913.21 60,739,999.04 44,666,725.13 71.0 76.9

GoE 223,357,071.61 223,357,071.61 134,039,520.84 89,317,550.77 89,317,550.77 60.0 60.0

Total 432,818,983.86 416,745,709.95 282,761,434.05 150,057,549.81 133,984,275.90 65.3 67.8

Usage from

Budget SourceReceived from

Source to date

Transferred to

Beneficiaries

to date

Utilized by

Beneficiaries

to date

Balance

from

Received

Balance

from

Transferred

Note: Of the Birr 209.46 million received from GoF (including the RWSEP savings), Birr 20,558,150.19 is exchange rate gain. All of the exchange rate gains have been added to the annual budgets and transferred to beneficiary sector offices.

6.2.5 Benishangul Gumuz region

All the investment funds from the two fund sources (GoF and GoE/Benishangul Gumuz National

Regional State) is being channeled to the communities through Benishangul Gumuz Credit and

Saving Institution (BECSI) with a commission of 5% while the capacity building fund from the

Finnish Government and operational cost from both sources have been channeled through the

government financial structure. The project fund is administered as per the funding agreement

Page 60: COMMUNITY-LED ACCELERATED WASH (COWASH) PROJECT...being finalized in the reporting period. Thus far, the consultant submitted all of the 18 parts of the manual and strategic framework

54

signed between the Benishangul Gumuz Bureau of Finance and Economic Development (BoFED)

and Embassy of Finland.

A total of about Birr 28.58 million (Birr 24.58 million from GoF and Birr 4.00 million from GoE) was

allocated for 2007 EFY. Of this amount, approximately Birr 23.0 million or 80.5% of the total

allocated for the fiscal year, was allocated for the first nine months of the fiscal year. In the

reporting period, GoF funds amounting to Birr 0.71 have been utilized for different capacity building

and operational costs. This accounts about 3.1% of the allocated for the nine months. This shows

that the fund utilization of the region was very low as much of the activities have not been started

due to delay in revision of the 2007 EFY and preparatory activities at the regional level and delay in

the implementation of the planned activities in many of woredas.

Table 40: Fund allocated and Utilized in BSG Region in the First Nine Months of 2007 EFY

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19

Planned for

3rd Quarter

(14 +17)

Utilized 3rd

Quarter

(15+18 )

Planned for

3rd Quarter

Utilized

3rd

Quarter

Planned for

3rd Quarter

Utilized

3rd

Quarter

GoF GoE Total (1+2 ) GoF GoE GoF+GoE GoF GoE GoF+GoE GoF + GoE GoF + GoE Cumulat ive

( 9 / 6 ) *10 0

3rd Quarter

(11/ 10 ) *10 0GoF GoF GoE GoE

INVESTM ENT

COST3,843,000 2,845,500 6,688,500 2,000,250 1,640,625 3,640,875 - 3,640,875 - 2,000,250 - - 1,640,625 - -

PHYSICAL

CAPACITY

BUILDING

COST

13,840,900 734,013 14,574,913 13,840,900 734,013 14,574,913 216,815 216,815 14,574,913 216,815 1.5 1.5 13,840,900 216,815 1.6 734,013 -

HUM AN

CAPACITY

BUILDING

COST

3,085,195 9,000 3,094,195 2,290,901 9,000 2,299,901 224,628 224,628 1,965,448 224,628 9.8 11.4 1,956,448 224,628 11.5 9,000 -

OPERATIONAL

COST3,809,758 411,487 4,221,245 2,225,197 219,744 2,444,941 267,783 - 267,783 2,343,701 267,783 11.0 11.4 2,123,957 267,783 12.6 219,744 - -

TOTAL 24,578,853 4,000,000 28,578,853 20,357,248 2,603,382 22,960,630 709,227 - 709,227 22,524,937 709,227 3.1 3.1 19,921,555 709,227 3.6 962,757 - -

Ut ilizat ion (%)

( 18 / 17) *10 0

Category

Planned(Annual) Cumulat ive Planned Cumulat ive Utilized Utilizat ion(%)Utilizat ion

(%)

( 15/ 16 ) *

10 0

So far, BSG region has received 324,796 Euro or Birr 8,332,614.38 from the government of

Finland. Of this amount, about Birr 440,892 has been transferred to beneficiary sector bureaus.

Funds have not been transferred to woredas and zones due to delay in the preparatory activities.

Until end of the reporting period, only Birr 709,227 from GoF contribution has been utilized. This

accounts about 8.5 % of the amount received from MFA or 9.7 % of the amount transferred to

beneficiary sector offices.

Table 41: Funds received, transferred and utilized in BSG Region until end of First Half of 2007 EFY

(March 31, 2015)

Receive

d(%)

Transferred

(%)

GoF 8,332,614.38 7,314,272.00 709,227.00 7,623,387.38 6,605,045.00 8.5 9.7

GoE 4,000,000.00 0.00 0.00 4,000,000.00 0.00 0.0 #DIV/0!

Total 12,332,614.38 7,314,272.00 709,227.00 11,623,387.38 6,605,045.00 5.8 9.7

Usage from

Budget

Source

Received

from

Source to

date

Transferred

to

Beneficiaries

to date

Utilized by

Beneficiarie

s to date

Balance

from

Received

Balance

from

Transferred

Note: Of the total Birr 8.33 million received from GoF, about Birr 212,714 was exchange rate gain. This is not yet utilized

Page 61: COMMUNITY-LED ACCELERATED WASH (COWASH) PROJECT...being finalized in the reporting period. Thus far, the consultant submitted all of the 18 parts of the manual and strategic framework

55

7 PROJECT COORDINATION WITH KEY STAKEHOLDERS

The scaling-up of the CMP approach at the national level requires having meetings and discussions

with different WaSH stakeholders thereby sharing the success of the CMP approach and raising

awareness and generating funds for investments. Cognizant of this fact, COWASH has been

participating in a number of meetings and discussions held during the reporting period at the

national level to promote and share experience on the CMP approach and to attract more funds for

CMP. The major meetings and/or discussions that COWASH has participated are presented

hereunder.

Water Sector Working Group (WSWG)

WSWG WRM-TC kick-off meeting was held on August 14, 2014. A 5-year capacity building plan

of MoWIE was prepared as per the proposal of WSWG and the group members, including

COWASH, commented on the plan. Accordingly, comments, much of which is from COWASH,

were incorporated. In January 2015, WSWG secretariat submitted the second version of the 5-

year capacity building plan for development partners’ comments. The strategic plan of WSWG

Secretariat was in a process of preparation during January. WSWG released the MoWIE Annual

review meeting proceedings. Moreover, WRM-TC meeting was conducted in February and WRM

situation in Ethiopia was discussed but no clear decisions how to operationalize WRM-TC were

made. The second version of the 5-year capacity building plan was discussed and plenty of new

Comments and concerns were addressed to WSWG secretariat. The issues did not get further as

“decision- makers” were absent of the meeting.

Local Capacity Development Facility (LCDF) Meeting

COWASH participated in a meeting on the development of Local Capacity Development Facility. It

was found out that currently SNV, PANE and RiPPLE are working together in LCDF project. The

required funding for the project is covered by SNV as donor and quality control works are being

done by SNV. COWASH is mentioned as a collaborator in the LCDF project document and hence its

grassroots level service provision experience is expected to be a springboard for the project so as

to avoid duplication of efforts in service provision. PANE tried to organize a meeting in September,

but it could not be successful as the month was not convenient for TAG.

MSF and JTR Meeting

COWASH CTA drafted the MSF 7 and JTR 9 concept paper for NWCO actions. However, the meeting

of development partners on MSF 7 and JTR 9 could not be made due to busy schedule of NWCO

staff. The MSF and JTR are postponed indefinitely.

MDG Achievement Celebration

The MoWIE Minister established a team, where COWASH CTA is a member, to prepare MDG target

achievement celebration event. The Team developed a brochure on the MDG achievement in

Ethiopia on water and sanitation and started to prepare communication strategy and event

program. Later on the MDG celebration event idea was cancelled as it was found out that the data

on the water supply access was not reliable and transparent enough to conclude the achievements

in a way that the results would be also comparable and debatable at global level. Finally, discussion

has been made with JMP to use the NWI hh data for ascertaining the attainment of MDG target (7c)

in water. The 2015 JMP for Water and Sanitation indicated that Ethiopia has met the target of 57 %

Page 62: COMMUNITY-LED ACCELERATED WASH (COWASH) PROJECT...being finalized in the reporting period. Thus far, the consultant submitted all of the 18 parts of the manual and strategic framework

56

(1990 baseline is 14% - un-served = 86%, MDG target is therefore 86/2 = 43+14 = 57%) of the

population using safe drinking water and has attained the target by halving the number of people

without access to safe water since 1990. However, Ethiopia is way off the target for sanitation

(baseline was 3%, MDG target was to reach 52%, but the achievement is 28% in 2015). Ethiopia

has therefore celebrated the Water MDG target achievement on March 23, 2015 here in Addis

Ababa at Sheraton Addis. COWASH representative participated in the celebration of the target.

National Hygiene and Environmental Health Experience Sharing Forum

CTA and JE participated in the 6th National Hygiene and Environmental Health Experience Sharing

Forum held in Dire Dawa on 26-28 Feb. 2015. COWASH CTA has facilitated almost the entire forum

and COWASH sponsored the event reporter and field day transportation. During the three-day

forum, the performance of different regions in Hygiene and Environmental Health were presented

and discussed and research papers on rural sanitation and hygiene; safe and green cities;

Institutional WASH and Health Impacts of WASH were presented. A site visit was organized to visit

a closed landfill site or the site presenting the different low cost sanitation technologies.

Discussions (formal/informal) with different national and international organizations and

experts

Several unofficial discussions were held with MoWE/WSSD/NWCO/GIS directorate on the

development of OWNP and GIS-based mapping of water points and updating of NWI data.

Moreover, COWASH FTAT participated in MoWIE 2006 EFY Annual performance and 2007

EFY annual plan review meeting in Adama and presented its three years performance

- COWASH CTA took part in the Federal Micro-and Small-Enterprise Development Agency debriefing meeting on Business Plan Model that was organized by the WSP on July 1, 2014.

- COWASH FTAT participated in the COWASH follow-up monthly meetings held in the Embassy

of Finland.

- COWASH CTA held meeting with MetaMeta to plan the future COWASH RSU staff training on

GLOWS/WSP. Accordingly, RSU staff and some regional water bureau and COWASH FTAT were trained on GLOWS/WSP by MetaMeta.

- Several meetings were held with the Consultants who are preparing the O&M manual and carrying out Training Impact Research

- COWASH CTA conducted Planning meeting with Quest consult.

- COWASH FTAT held follow-up and supervision meeting with SNNP Water Bureau Head and

relevant regional COWASH stakeholders.

- CMP promotion meeting with local NGO called WCDO and the NGO is willing to include CMP into their food security concept note for financiers.

- COWASH CTA conducted meeting with SNV on joint projects.

- COWASH FTAT held meeting with WHO consultant on WSP was held in July 2014.

- Meeting conducted on July 10, 2014 with IRC on their role in WASH in Ethiopia and on CMP in particular.

- COWASH CTA participated in a meeting with UNICEF on CMP development.

- COWASH CTA participated in the meeting with Water.org and WaterAid on WaterCredit workshop.

- COWASH FTAT participated in a meeting held on SNNP implementation at Embassy of

Finland.

Page 63: COMMUNITY-LED ACCELERATED WASH (COWASH) PROJECT...being finalized in the reporting period. Thus far, the consultant submitted all of the 18 parts of the manual and strategic framework

57

- COWASH Steering Committee meeting was conducted through the facilitation of COWASH

FTAT

- COWASH FTAT participated in a meeting conducted with South Pole on the ‘Result Based

Financing’

- A meeting was conducted on UNICEF-SNV coordination on CMP Implementation Manual

approval and finalization process

- COWASH CTA participated in the Stockholm World Water Week exhibition and assisted in

erecting MoWIE stand

- A meeting with M-Birr Ethiopia was held and the possibilities to use mobile payments in

COWASH was discussed

- COWASH CTA met the IRC auditor Mr. Bert L.M. Van Woersen and discussed the IRC

performance in Ethiopia

- COWASH CTA participated in a meeting with Oromia Water Bureau Head (Ato Motuma) with

Anu Eskonheimo on COWASH in Oromia and CTA presented Oromia progress in the last

fiscal years

- A meeting was conducted with Open University (OU) on WASH Capacity Building in Ethiopia.

OU has been contracted by World Vision in WASH +project to be responsible of the capacity

building component.

- COWASH CTA participated in Disability Inclusion round table discussion on October 7, 2014.

- COWASH CTA and GIS Expert participated in the FinnWASH-BG Board meeting on Oct. 17

in Assosa

- Oxford Policy Management consultant Lucrezia Tincani visited COWASH and discussed with

COWASH CTA on the Value for Money and focusing on the Sustainability in rural WaSH

programs.

- COWASH CTA participated in the sanitation marketing business group meeting on November

25 and workshop on latrine technology training manual held on Nov. 21 and 28; It was also

managed to participate on Sanitation Marketing Multi-stakeholder Platform Meeting

conducted on Nov.6

- COWASH FTAT participated in JMP meeting with development partners on Nov. 24 and NWI

data updating in relation to GTP II indicators was discussed

- COWASH held meeting on Nov. 5 with IRC on WASH dynamics survey; COWASH also

participated on the 5-year strategy development of WaterAid.

- COWASH CTA held extensive discussion with AGUACONSULT developing sustainability check

tools. UNICEF has drafted the TOR to recruit a consultant who will develop the sustainability

check tool for One WASH. Same time USAID has already employed a consultant to carry out

extensive WASH sustainability check in Ethiopia. COWASH also provided lots of comments

on the sustainability check tools for AGUACONSULT.

- COWASH CTA made discussion with WHO hired consultant conducting HWTS market

assessment in Ethiopia.

Page 64: COMMUNITY-LED ACCELERATED WASH (COWASH) PROJECT...being finalized in the reporting period. Thus far, the consultant submitted all of the 18 parts of the manual and strategic framework

58

8 CHALLENGES

Like the previous fiscal year, different kinds of challenges have been faced during the reporting period. The major ones that require the

attention of National WaSH Steering Committee (NWSC) and Regional WaSH Steering Committee (RWSC) are indicated as follows.

Challenges Measures taken

Delay in preparation and approval of regional annual plans: The 2007 EFY annual plans of

COWASH in the regions were expected to be prepared before the end of 2006 EFY. However, the

plans are not still approved in the regions. The delay in the approval of the regional annual plans will

also delay the implementation of some of the federal level activities. The delay in the preparation

and approval of annual plans hampers the implementation rate and budget utilization of woredas

thereby affecting the contribution of COWASH in accelerating the GTP/UAP WASH targets.

COWASH provided technical assistance to

all the regions in the preparation of their

annual plans. Planning templates and unit

costs were prepared by COWASH FTAT and

sent to regions timely.

Delay in sending quarterly reports: Quarterly performance reports are expected from regions to

prepare project performance report at the federal level and submit to the pertinent bodies timely.

However, quarterly reports from the regions are delayed and this takes much time to prepare the

performance report of the project at the federal level. Quality of the regional reports is also a

problem that is delaying the finalization of federal level reports.

The problem persists in the reporting

quarter. COWASH FTAT has been assisting

RSUs in preparing regional reports and

providing feedback on the reports sent to

COWASH FTAT.

Lack of field vehicle: Though with a delay for more than 2 years, Tigray and Oromia RSUs have

got field vehicles to provide technical assistance to the woredas and zones. However, the

procurement of SNNPR RSU car took much time and the staff could not carry out fieldworks to the

woredas and zones. Many of the woredas have no vehicle to assist WASHCOs and KWTs to carry out

CMP activities at the grassroots level. The motorbike procurements in some woredas took much time

than expected.

The agreement with the first company,

who couldn’t submit the car, was cancelled

and a new bid is floated. The procurement

is now given due emphasis and it is hoped

to receive the car soon.