community-led accelerated wash (cowash) project€¦ · 1 executive summary ... strengthening the...

63
COMMUNITY-LED ACCELERATED WASH (COWASH) PROJECT NINE MONTHS PERFORMANCE REPORT 2008 EFY (08/07/2015-31/03/2016) JUNE 2016

Upload: others

Post on 26-Aug-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: COMMUNITY-LED ACCELERATED WASH (COWASH) PROJECT€¦ · 1 EXECUTIVE SUMMARY ... STRENGTHENING THE FEDERAL CAPACITY TO IMPLEMENT COMMUNITY MANAGED PROJECTS ALONGSIDE WITH A SUPPORT

COMMUNITY-LED ACCELERATED WASH (COWASH)

PROJECT

NINE MONTHS PERFORMANCE REPORT

2008 EFY (08/07/2015-31/03/2016)

JUNE 2016

Page 2: COMMUNITY-LED ACCELERATED WASH (COWASH) PROJECT€¦ · 1 EXECUTIVE SUMMARY ... STRENGTHENING THE FEDERAL CAPACITY TO IMPLEMENT COMMUNITY MANAGED PROJECTS ALONGSIDE WITH A SUPPORT

i

Table of contents

1 EXECUTIVE SUMMARY ........................................................................................................................................ 1

2 OVERALL OBJECTIVE ACHIEVEMENT.................................................................................................................... 5

3 PROJECT PURPOSE ACHIEVEMENT ...................................................................................................................... 5

4 COMPONENT 1: STRENGTHENING THE FEDERAL CAPACITY TO IMPLEMENT COMMUNITY MANAGED PROJECTS

ALONGSIDE WITH A SUPPORT TO THE ESTABLISHMENT OF THE ONE WASH NATIONAL PROGRAM .................. 7

4.1 RESULT 1 OF COMPONENT 1: COMMUNITY MANAGED PROJECT APPROACH SCALED-UP AT NATIONAL LEVEL ....... 7

4.1.1 Output 1: Manuals and Guidelines Reviewed and Developed for Standardizing the CMP Implementation

within the WaSH Implementation Framework .............................................................................................. 7

4.1.2 Output 2: Tools and Mechanisms Reviewed and Developed for Standardizing the Planning,

Implementation and Monitoring of CMPs ..................................................................................................... 8

4.1.3 Output 3: CMP Approach within the Rural WaSH Scientifically Researched ............................................... 10

4.1.4 Output 4: Information, Education and Communication (IEC) on CMP Implementation Modality Enhanced

..................................................................................................................................................................... 11

4.2 RESULT 2 OF COMPONENT 1: CMP IMPLEMENTATION CAPACITY AT THE FEDERAL AND REGIONAL LEVELS

DEVELOPED ....................................................................................................................................................... 12

4.2.1 Output 1: Capacity Building Instruments Reviewed and Developed ........................................................... 12

4.2.2 Output 2: Capable and Adequate Personnel in place for CMP Implementation at National and Regional

Levels ........................................................................................................................................................... 13

4.3 RESULT 3 OF COMPONENT 1: DEVELOPMENT AND IMPLEMENTATION OF ONE WASH NATIONAL PROGRAM

SUPPORTED ...................................................................................................................................................... 14

4.3.1 Output 1: COWASH Support Provided in Preparing One WaSH National Program ..................................... 14

4.3.2 Output 2: COWASH Support Provided in Implementation of One WaSH National Program ....................... 15

5 COMPONENT 2: ESTABLISHING AND STRENGTHENING THE CAPACITY IN REGIONS TO SCALE-UP

IMPLEMENTATION OF CMP ...............................................................................................................................15

5.1 RESULT 1 OF COMPONENT 2: TARGET REGIONS, ZONES AND WOREDAS CAPABLE TO PLAN, MANAGE, MONITOR

AND IMPLEMENT RURAL WASH INTERVENTIONS USING CMP APPROACH ....................................................... 16

5.1.1 Output 1: Regional Support Units (RSU) Established and Functional .......................................................... 16

5.1.2 Output 2: Regions, Zones and Woredas Capacitated to Implement Rural WaSH through CMP ................. 16

5.2 RESULT 2 OF COMPONENT 2: FINANCIAL AND PROCUREMENT SERVICES DELIVERED FOR CMP INTERVENTION AT

ALL LEVELS IN THE SELECTED REGIONS .............................................................................................................. 28

5.2.1 Output 1: Flow of Funds for CMPs Functional ............................................................................................. 28

5.2.2 Output 2: Linkages Created with Private Sector in the Supply of Materials, Equipment, Tools and Services

..................................................................................................................................................................... 28

5.3 RESULT 3 OF COMPONENT 2: SUSTAINABLE COMMUNITY AND INSTITUTIONAL ACCESS TO SAFE WATER,

SANITATION AND HYGIENE IN THE TARGET WOREDAS INCREASED.................................................................. 29

5.3.1 Output 1: Access to Improved Water Sources for Communities and Institutions Increased ....................... 29

5.3.2 Output 2: Access to Sanitation for Household and Institutions Increased and Hygiene Behavior Improved

..................................................................................................................................................................... 38

5.3.3 Output 3: Sustainability of Communal and Institutional Water Schemes in the Targeted Woredas

Strengthened ............................................................................................................................................... 40

5.3.4 Output 4: Potable Water Quality Ensured in Targeted Woredas ................................................................ 42

6 FINANCIAL PERFORMANCE ................................................................................................................................43

6.1 COMPONENT 1, FEDERAL LEVEL ................................................................................................................................ 43

6.2 COMPONENT 2 FINANCIAL PERFORMANCE ...................................................................................................... 45

Page 3: COMMUNITY-LED ACCELERATED WASH (COWASH) PROJECT€¦ · 1 EXECUTIVE SUMMARY ... STRENGTHENING THE FEDERAL CAPACITY TO IMPLEMENT COMMUNITY MANAGED PROJECTS ALONGSIDE WITH A SUPPORT

ii

6.2.1 Tigray Region ............................................................................................................................................... 45

6.2.2 SNNP REGION .............................................................................................................................................. 46

6.2.3 Oromia Region ............................................................................................................................................. 47

6.2.4 Amhara region............................................................................................................................................. 48

6.2.5 Benishangul Gumuz region .......................................................................................................................... 50

7 PROJECT COORDINATION WITH KEY STAKEHOLDERS .........................................................................................52

8 CHALLENGES ......................................................................................................................................................53

9 PERFORMANCE OF METEKEL WOREDAS ............................................................................................................. 2

9.1 INTRODUCTION ........................................................................................................................................................ 2

9.2 CAPACITY BUILDING ................................................................................................................................................. 3

9.3 PHYSICAL CAPACITY BUILDING .................................................................................................................................... 3

9.4 ALI SPRING WATER SAFETY PLAN & REHABILITATION ..................................................................................................... 3

9.5 FINANCIAL UTILIZATION ............................................................................................................................................. 4

Page 4: COMMUNITY-LED ACCELERATED WASH (COWASH) PROJECT€¦ · 1 EXECUTIVE SUMMARY ... STRENGTHENING THE FEDERAL CAPACITY TO IMPLEMENT COMMUNITY MANAGED PROJECTS ALONGSIDE WITH A SUPPORT

iii

Abbreviation Interpretation

ACSI Amhara Credit and Saving Institution

AfDB African Development Bank

AWP Annual Work Plan

BoE Bureau of Education

BoFED Bureau of Finance and Economic Development

BoH Bureau of Health

CARE Cooperative for Assistance and Relief Everywhere

CBN Community Based Nutrition

CDF Community Development Fund

CFT Community Facilitation Team

CIDA Canadian International Development Agency

CLTSH Community-Led Total Sanitation and Hygiene

CMP Community Managed Project

COWASH Community Led Accelerated WASH in Ethiopia

CRS Catholic Relief Services

CTA Chief Technical Advisor

CWA Consolidated WaSH Account

DCSI Dedebit Credit & Saving Institution

DFID Department for International Development (UK)

EFY Ethiopian Fiscal Year

EIRR Economic Internal Rate of Return

ETB Ethiopian Birr

EU European Union

EUR Euro

EUWI European Union Water Initiative

EWA Ethiopian Water Alliance

FI Financial Intermediary

FinnWASH-BG Rural Water Supply, Sanitation and Hygiene Programme in

Benishangul-Gumuz Region

FTAT Federal Technical Assistance Team

GoE Government of Ethiopia

GoF Government of Finland

GTP Growth and Transformation Plan

HEW Health Extension Worker

HIV/AIDS Human Immunodeficiency Virus/ Acquired Immunodeficiency

Syndrome

HQ Head Quarter

HRD Human Resource Development

HSDP Health Sector Development Plan

IDC Italian Development Cooperation

IEC Information, Education and Communication

JFA Joint Financing Agreement

JICA Japan International Cooperation Agency

JMP Joint Monitoring Program

JTR Joint Monitoring Review

KWT Kebele WaSH Team

LWI Living Water International

MDG Millennium Development Goal

M&E Monitoring and Evaluation

Page 5: COMMUNITY-LED ACCELERATED WASH (COWASH) PROJECT€¦ · 1 EXECUTIVE SUMMARY ... STRENGTHENING THE FEDERAL CAPACITY TO IMPLEMENT COMMUNITY MANAGED PROJECTS ALONGSIDE WITH A SUPPORT

iv

Abbreviation Interpretation

METB Million Birr

MEUR Million Euros

MFA Ministry for Foreign Affairs (of Finland)

MFI Microfinance Institution

MIS Management Information System

MMS Mass Mobilization Strategy

MoE Ministry of Education

MoFED Ministry of Finance and Economic Development

MoH Ministry of Health

MoU Memorandum of Understanding

MoWE Ministry of Water & Energy

MSF Multi-Stakeholder Forum

MUS Multiple Use of Services (Water)

MUSD Million United States Dollars

MWA Millennium Water Alliance

NGO Non-Governmental Organization

NPV Net Present Value

NUWI Netherlands-UNICEF WaSH Initiative

NWCO National WaSH Coordination Office

NWI National WaSH Inventory

NWMU National WaSH Management Unit

NWSC National WaSH Steering Committee

NWTT National WaSH Technical Team

OCSSCO Oromia Credit and Saving Shareholder Company

ODF Open Defecation Free

O&M Operation and Maintenance

OMA Office Management Assistant

OMFI OMO Micro-Finance Institution

OMSU Operation and Maintenance Support Unit

ORDA Organization for Rehabilitation and Development in Amhara

PASDEP Plan for Accelerated and Sustainable Development to End Poverty

REST Relief Society of Tigray

RiPPLE Research Inspired Policy and Practice Learning in Ethiopia and the

Nile Region

RSU Regional Support Unit

RWCO Regional WaSH Coordination Office

RWSC Regional WaSH Steering Committee

RWSEP Rural Water Supply and Environment Programme

RWTT Regional WaSH Technical Team

SAP National Hygiene and Sanitation Strategic Action Plan

SNNPR Southern Nations & Nationalities Peoples Region

SNV Netherlands Development Organization

SvB Supervisory Board

SWAp Sector Wide Approach

TA Technical Assistance

TVETC Technical Vocational & Educational Training College

UAP Universal Access Plan

UK United Kingdom

UNESCO United Nations Educational, Scientific and Cultural Organization

Page 6: COMMUNITY-LED ACCELERATED WASH (COWASH) PROJECT€¦ · 1 EXECUTIVE SUMMARY ... STRENGTHENING THE FEDERAL CAPACITY TO IMPLEMENT COMMUNITY MANAGED PROJECTS ALONGSIDE WITH A SUPPORT

v

Abbreviation Interpretation

UNICEF United Nations Children’s Fund

WaSH Water Supply, Sanitation and Hygiene

WASHCO Water Supply, Sanitation and Hygiene Committee

WB The World Bank

WEW Water Extension Worker

WIF WaSH Implementation Framework

WMP Woreda Managed Project

WMU WaSH Management Unit

WRDB Water Resources Development Bureau

WSA Woreda Support Agent

WSG Woreda Support Group

WSP Water Safety Plan

WSP-AF Water and Sanitation Program-Africa

WSS Water Supply and Sanitation

WSSD Water Supply and Sanitation Directorate

WSSP Water Supply and Sanitation Program

WWT Woreda WaSH Team

WYCB Women, Youth and Children Bureau

Page 7: COMMUNITY-LED ACCELERATED WASH (COWASH) PROJECT€¦ · 1 EXECUTIVE SUMMARY ... STRENGTHENING THE FEDERAL CAPACITY TO IMPLEMENT COMMUNITY MANAGED PROJECTS ALONGSIDE WITH A SUPPORT

1

1 EXECUTIVE SUMMARY

The COWASH project has two components. Component 1 strives to strengthen the federal level

capacity for implementation of the CMP approach and to support the overall WaSH sector

development process including the establishment and implementation of One WaSH National

Program (OWNP).

Under Component 1, a number of activities were planned to be conducted by COWASH FTAT at

the federal level and in the regions in 2008 EFY. The main achievements in the first nine months

were the following:

Approval of CMP Implementation Manual using Public Finance and Procurement

Management System (PFPMS): Generic CMP Implementation manual using PFPMS was

developed by Consultants jointly financed by UNICEF and COWASH, in consultation with

several WASH stakeholders. This Manual is the mitigation measure included into the One

WASH Program Operational Manual (POM) prepared in 2006 EFY. The manual, which is to be

annexed to POM, was presented to MoFED by MoWIE for approval. However, there is no any

official response yet from MoFED and consequently a number of planned activities are pending

due to the delay in the approval of the manual.

Combined Rural Water Supply O&MM Manual for Rural Piped Schemes (RPS) and

Pastoralist areas and Generic O&MM Strategic Framework being completed

(98.0%): The development of the 18 components O&MM manual and strategic framework

started in 2006 EFY have been completed and submitted for MoWIE for endorsement.

Moreover, the preparation of the training guidelines based on the manuals is on progress by

the same consultant and small editing remains to complete them. COWASH is strictly

following and providing technical assistance for the development of the manual, strategic

framework, business plan and training manuals. All manuals, framework, business plan and

some training guidelines have been uploaded to CMP web site www.cmpethiopia.org

Climate and Environmental Risk Screening Trainer’s Manual, Climate Resilient Water

Safety Plan (CR-WSP) Guideline and Social Accountability Guideline developed

(100.0%): COWASH has developed 3 manuals decisive for the development of Ethiopia’s

WASH sector. The climate and environmental risk screening trainer’s manual has been

developed based on the climate screening guidelines developed by Over Seas Development

Institute (ODI) and regional and federal level staff received ToT training to incorporate the

climate screening into COWASH’s appraisal process. CR-WSP implementation guideline has

been prepared in collaboration with WHO Ethiopia country office and ToT training provided to

regional and federal level experts to launch WSP in selected kebeles in some woredas of the

COWASH project regions. Besides, with the view to sustaining the water points, draft Social

Accountability guideline was prepared by the project. COWASH decided to conduct sector-wide

workshop on Social Accountability and WASH so as to get the views of WASH stakeholders in

making the guideline serve the whole WASH sector.

1 PhD level research underway and 1 MSc level CMP Research started: The project

continued supporting the PhD level research and a new Master’s level research entitled

“Community Participation in Rural Water Supply Development and Management: The Case of Bahir Dar

Zuria Woreda, West Gojjam Administrative Zone, Amhara Region, Ethiopia” has been started. The PhD

level researcher has published one article in a reputable journal and the second and third

articles are under revision and ready for publication, respectively. The MSc level research is on

the data collection stage and analysis will start in the first month of the 4th quarter.

Climate and Environmental Risk Screening, CR-Resilient WSP, Pedagogical and

Facilitation Skill and GIS Trainings conducted (100.0%): COWASH FTAT, in

Page 8: COMMUNITY-LED ACCELERATED WASH (COWASH) PROJECT€¦ · 1 EXECUTIVE SUMMARY ... STRENGTHENING THE FEDERAL CAPACITY TO IMPLEMENT COMMUNITY MANAGED PROJECTS ALONGSIDE WITH A SUPPORT

2

collaboration with other WASH actors, trained 133 (11 females) woreda, zone, regional and

federal level experts on four trainings which enhance the development of the WASH sector.

With the view to improve the facilitation and presentation skills, a four days Pedagogical and

facilitation skill training was given to 28 (2 females) COWASH FTAT and RSU staff; A total of

30 (5 females) regional and federal experts have received a 5-day Training of Trainer (ToT)

training on Climate and Environmental Risk Screening training by Overseas Development

Institute (ODI) and Addis Ababa University staff. The risk screening systems are being

incorporated into the COWASH’s appraisal tools. Moreover, Climate Resilient Water Safety

Plan (CR-WSP) ToT training was given to 28 (4 females) regional and federal level experts,

including staff of water and agriculture bureaus, for 5 days. The project has also provided a 4-

day GIS and data management training for 47 experts drawn from woredas, zones, regional

WASH sector bureaus in BSG, Oromia and MoWIE.

Support to Regions in carrying out Trainings (96%): COWASH FTAT has been assisting

regions in conducting trainings to woreda, zone and regional level stakeholders of the project.

In the reporting period, FTAT provided support to BSG and Oromia RSU in conducting CMP

related trainings to Woreda and Zonal experts. A total of 77 (53 in Oromia and 24 in BSG)

have been trained. The support provided accounted 40% of the regions and 96% of the

trainees planned for the reporting period.

Five Regions have received COWASH FTAT Technical Assistance in the preparation of

2008 EFY Planning (100.0%): With the view preparing the 2008 EFY regional plans timely,

the COWASH federal technical assistant team prepared draft planning formats (both physical

and financial) and estimated unit costs and distributed to Regional Support Units (RSUs). With

these templates the regional detailed plans have been prepared with the technical assistance

of COWASH FTAT.

COWASH annual and quarterly performance reports prepared and disseminated

(100.0%): COWASH FTAT has prepared and disseminated to stakeholders the 2007 EFY

annual performance, the 2008 EFY First Quarter and Semi-Annual Performance reports. The

2007 EFY report shows the contribution of the project in attaining the GTP 1 WASH targets

while the 2008 EFY quarterly reports describe the accomplishments in the first half of the

fiscal year vis-à-vis the plans approved by Steering Committees. The reports can be found at

www.cmpethiopia.org

Participation in 2007 EFY Annual Performance Review and 2008 EFY Regional

Planning Workshops (100.0%): All of the five project regions (Amhara, Tigray, SNNPR and

BSG) have conducted their 2007 EFY annual performance review and 2008 EFY planning

workshop in the reporting period. COWASH FTAT participated in all of these workshops and

shared experiences of other regions and made discussions on issues that will mitigate the

challenges in the implementation of the project in the woredas of the respective regions.

5, 000 CMP Calendar Note Books printed and disseminated (100.0%): This fiscal year,

the project planned to prepare and print CMP calendar note books unlike the previous years

where CMP table calendars had been produced. Accordingly, 5,000 CMP calendar note books

were produced and distributed to stakeholders at federal, regional, zone and woreda levels

including some other WASH actors. Calendar note books were also distributed to MSF 7

participants. The distributed calendar note books are believed to raise awareness about the

CMP approach.

Participation in 3 International Conferences to promote CMP: As part of COWASH’s

effort to promote CMP at the international level, COWASH planned to assist MoWIE to

participate in the 25th Annual Stockholm Water Week 2015 (SWWW2015) and 38th WEDC

conference and COWASH FTAT in ‘Innovative Financing for WASH for West and Central African

Page 9: COMMUNITY-LED ACCELERATED WASH (COWASH) PROJECT€¦ · 1 EXECUTIVE SUMMARY ... STRENGTHENING THE FEDERAL CAPACITY TO IMPLEMENT COMMUNITY MANAGED PROJECTS ALONGSIDE WITH A SUPPORT

3

Countries’. Accordingly, COWASH managed to participate MoWIE and COWASH Junior

Professional Officer (JPO) at SWWW2015 and WEDC Conferences and CMP was promoted in

these conferences. Two COWASH staff have also participated in the ‘Innovative Financing for

WASH for West and Central African Countries’ conference held at Dakar, Senegal. The

Ethiopian experience in the use of Microfinance Institutions to scale-up community water

programmes was shared by the COWASH staff and learnt on other WASH financing

mechanisms such as capital markets, blending of funds, equity banking and others.

Technical Assistance in preparation of MSF 7 and JTR 9:

COWASH supported NWCO in preparing and undertaking JTR 9 and MSF 7. The support

includes preparation of programs/schedules, reports and proceedings and chairing and

facilitating some of the sessions in collaboration with other WASH stakeholders. The project

has also uploaded reports, presentations and undertakings on its website

www.cmpethiopia.org so that knowledge can be managed and shared.

Component 1 Budget Utilization: The total COWASH Component 1 (C-1) five year budget

is EUR 3,730,393. Of this amount, EUR 3,514,657 was allocated for the period June 2011 to

March 2016. During the same period, the C-1 expenditures have been EUR 3,503,532

accounting 99.7 % utilization rate. EUR 200,000 was allocated for the third quarter of 2008

EFY and some EUR 184,781 has been utilized. This represents about 92.4% budget utilization

rate in the third quarter. Savings were purposefully made in order to have enough funds to pay all

Phase II completion and remaining payments in the last quarter.

Component 2 of the project deals with “Establishing and Strengthening the Capacity in Regions

to Scale-up Implementation of CMP”. A number of activities have been performed under this

component.

Increasing the Number of CMP Woredas (from 31 to 76): The number of woredas

implementing the CMP approach has been on the rise. In 2003 EFY, only 31 woredas (26 in

Amhara; 19 by RWSEP and 7 by UNICEF, and 5 in Benishangul-Gumuz) have been

implementing CMP. Excluding the UNICEF CMP woredas in Amhara, the number of CMP

Woredas has increased to 76 (11.6% of the rural woredas in the five project regions) in 2008

EFY. COWASH woredas increased from 19 in 2003 EFY to 71 in 2008 EFY in the five project

regions.

Increasing the Number of CMP Kebeles (from 360 to 1,198): This fiscal year, 51 new

rural kebeles are covered by project. This has increased the number of kebeles implementing

the CMP approach from 360 (18.2%) in the base year (2003 EFY) to 1,198 (64.4% of the

1,859 rural kebeles in the project woredas) in 2008 EFY.

Construction of Water Points: A total of 2,421 water points were planned to be constructed

in the five project regions in 2008 EFY. A total of 765 water points (745 community and 20

institutional), which accounts about 31.6 % of the annual plan, have been completed in four

regions in first nine months of the fiscal year. The community water points are benefitting

over 131,560 rural people while the institutional water supply schemes are serving more than

8,168 students and teachers and 93 health extension workers and some clients of the

facilities.

On aggregate, 8,926 water supply schemes (8,457 community, 391 schools and 78 health

facilities) have been constructed in the COWASH woredas until end of 30 March 2016. Well

over 1.96 million rural people benefitted from the community water points. The water supply

schemes constructed for schools are benefitting 169,137 students, teachers and

administrative staff of the schools whereas the health facility water supply schemes are

Page 10: COMMUNITY-LED ACCELERATED WASH (COWASH) PROJECT€¦ · 1 EXECUTIVE SUMMARY ... STRENGTHENING THE FEDERAL CAPACITY TO IMPLEMENT COMMUNITY MANAGED PROJECTS ALONGSIDE WITH A SUPPORT

4

providing service to more than 14,422 health extension workers and some clients of the

health institutions.

Rehabilitation of Water Points: A total of 12 water points (10 community and 2

institutional) have been rehabilitated in the first nine months of 2008 EFY. The performance is

only 6.1% of the annual plan of the five regions. The rehabilitated water points are benefitting

more than 1,741 rural people of the project woredas. Since the launching of COWASH in

2004 EFY, 456 water points (443 community, 12 schools and 1 health facility) have been

rehabilitated in four regions of the project. The community water points rehabilitated are

benefitting more than 111,199 rural people while the rehabilitated school and health facility

water points benefit over 5,112 students and teachers and 100 health extension workers and

clients of the health facility.

Institutional Latrine Construction: 133 latrines (75 school and 58 health facility) were

planned to be constructed in 2008 EFY. It was managed to construct 15 standard institutional

latrines (12 schools and 3 health facilities) in three regions in the first 9 months of the fiscal

year. This reveals that project woredas have executed only 11.3% of the plan of 2008 EFY.

On the whole, 152 institutional latrines (87 schools and 65 health facilities) have been

constructed since COWASH is launched in 2004 EFY. The school and health facility latrines

have benefitted more than 97,112 students and teachers (51.0% females) and 3,002 health

extension workers and some clients of the institutions (56.5% females). The performance in

the construction of institutional latrine construction in particular and sanitation and hygiene in

general has been very low due to the high priority given to community water supply

constructions and competing activities in the woredas.

GoF fund utilization: According to the regional financing agreements, Government of Finland

(GoF) has allocated Euro 18,269,590 for the implementation of COWASH for five years. The

project regions have been receiving funds (Euro) from the Ministry for Foreign Affairs of Finland

(MFA) as per their funding agreement signed with Embassy of Finland. Until end of March 2016,

regions have received Euro 16,140,492.10 (88.4% of the Euro allocated). This is equivalent to

about Birr 391.59 million. Hitherto, more than 80.2 % of the amount of funds received from MFA

has been utilized by the project regions.

Table 1: Amount of Euro Agreed & Transferred from MFA to Project Regions until end of March 2016

COWASH

Project

Region

Amount of

Euro Agreed

for 5 Years

Amount of Euro

Transferred

from MFA until

30 March 2016

%

Transferred

Amount

Transferred (in

Birr) from MFA

until 30 March

2016*

Amount utilized

(in Birr) until

30 March 2016

%

Utilized

Amhara*10,310,578 10,310,577.71 100.0 252,813,114.11 210,070,288.01 83.1

Tigray2,184,299 1,419,191.77 65.0 33,812,040.14 25,407,520.62 75.1

SNNPR1,746,084 1,337,454.00 76.6 31,940,482.97 25,839,463.24 80.9

Oromia1,766,000 1,427,778.00 80.8 34,183,057.02 33,211,548.00 97.2

BSG2,262,629 1,645,490.62 72.7 38,840,844.88 19,675,319.19 50.7

Total18,269,590 16,140,492.10 88.3 391,589,539.12 314,204,139.06 80.2

Note: * The ‘Amount Transferred from MFA until 30th March 2016’ to Amhara region includes Birr 4,291,860.92 transferred from RWSEP savings.

Page 11: COMMUNITY-LED ACCELERATED WASH (COWASH) PROJECT€¦ · 1 EXECUTIVE SUMMARY ... STRENGTHENING THE FEDERAL CAPACITY TO IMPLEMENT COMMUNITY MANAGED PROJECTS ALONGSIDE WITH A SUPPORT

5

2 OVERALL OBJECTIVE ACHIEVEMENT

The overall objective of COWASH is ‘to achieve universal access to WaSH in the rural areas

of Ethiopia’. The project tries to attain this objective through implementing Component 1 at the

federal level and Component 2 in the regions through the adoption and application of Community

Managed Project (CMP) approach. Complete information on the contribution of the project in

improving the water supply, sanitation and hygiene situation of the project woredas will be

presented in annual report of the project.

3 PROJECT PURPOSE ACHIEVEMENT

Within the framework of the overall objective described above, the project purpose is to

“Support the acceleration of UAP-rural water and sanitation targets attainment through

the establishment of an enabling environment and the implementation of CMP

interventions in selected rural areas of Ethiopia”. Thus, COWASH strives to provide support

for the development of the enabling environment at the federal level and in the project regions

where hydro-geological conditions are suitable for its replication.

The key indicators for the verification of the achievement of the Project purpose are:

i) Percentage of Regions implementing CMP approach; ii) Percentage of Woredas of targeted

regions implementing CMP approach; iii) Percentage of Kebeles of targeted woredas implementing

CMP approach; iv) Percentage of rural people that has access to potable water through COWASH;

and v) Amount of regional budget allocated for COWASH.

There is no increase in the number of regions implementing CMP approach in 2008 EFY. The

number of regions implementing the CMP approach has increased from two regions (22.2% of the

9 administrative regions of Ethiopia, excluding the city administrations of Addis Ababa and Dire

Dawa) in 2003 EFY to five regions (55.6%) in 2008 EFY. Benishangul Gumuz region joined

COWASH in 2007 EFY as the delay in the preparatory activities had delayed the joining of the

region in 2006 EFY. The regions and number of woredas implementing the CMP approach are

indicated in Table 2 below.

Table 2: COWASH Regions and Number of Woredas Implementing CMP Approach

RWSEP UNICEFFinnWASH-

BGTotal COWASH*

% of the total

Rural Woredas

Amhara 153 19 8 27 40 26.1 775

Tigray 36 0 0 7 19.4 62

SNNPR 125 0 0 8 6.4 145

Oromia 249 0 0 12 4.8 101

BSGR 20 5 5 9 45.0 115

Total 583 19 8 5 32 76 13.0 1,198

No. of

COWASH

/CMP

Kebeles

in 2008

EFY

Project

Region

Total No.

of Rural

Woredas

No. of CMP Woredas

CMP Woredas in 2008 EFYCDF/CMP Woredas in 2003 EFY

Note: * As of Oct. 2015, the 5 FinnWASH-BG woredas have joined COWASH.

The number of woredas implementing CMP approach rose from 5.5% in the base year (2003 EFY)

to 13.0% in 2008 EFY. There is no new woreda joined COWASH in 2008 EFY except that the 5

FinnWASH-BG woredas have joined COWASH in Oct. 2015 due to the phase out of the FinnWASH-

BG project.

This fiscal year, 51 new rural kebeles are covered by project. This has increased the number of

kebeles implementing the CMP approach from 360(18.2%) in the base year (2003 EFY) to 1,198

(64.4% of the 1,859 rural kebeles in the project woredas) in 2008 EFY.

Page 12: COMMUNITY-LED ACCELERATED WASH (COWASH) PROJECT€¦ · 1 EXECUTIVE SUMMARY ... STRENGTHENING THE FEDERAL CAPACITY TO IMPLEMENT COMMUNITY MANAGED PROJECTS ALONGSIDE WITH A SUPPORT

6

The number of rural people benefiting from the COWASH water points and institutions having

access to water supply and latrines in the project areas have increased. The project has managed

to construct water supply schemes to 20.2% of the 9, 407,458 rural population of the 71 project

woredas in five regions of the country. Besides, 9.2% and 3.3% of the schools and health

facilities of the project woredas have got access to water supply until end of the reporting period.

Table 3: No. of Water Points Constructed and Beneficiary Population until end of March 2016

Community SchoolHealth

FacilityTotal

Actual no. of

people using the

Community WPs

Population having

access to Community

WPs within 1.5 km

radius

Amhara 40 6,737 312 60 7,109 1,505,535 1,495,535

Tigray 7 371 21 4 396 107,589 107,589

SNNPR 8 568 25 6 599 202,225 174,418

Oromia 12 763 31 8 802 140,792 131,276

BSGR 4 18 2 - 20 6,519 6,519

Total 71 8,457 391 78 8,926 1,962,660 1,915,337

No. of WPs constructed

Project

Region

Beneficiary Population

No. of

Project

Woredas

The emphasis to sanitation and hygiene has been improving over the implementation period of

the project. However, the attention was much lower than the water supply service provision in

the woredas. Thus far, a total of 152 institutions (87 schools and 65 health facilities) have got

access to improved latrine with the support of the project through the CMP approach. The

regional distribution of the latrine facilities constructed is presented in Table 4 below.

Table 4: No. of Institutional Latrines Constructed until end of March 2016

School Health Facility Total

Amhara 40 60 49 109

Tigray 7 5 10 15

SNNPR 8 12 - 12

Oromia 12 10 6 16

BSGR 4 - - -

Total 71 87 65 152

No. of Latrines Constructed

Project

Region

No. of Project

Woredas

As far as allocation of funds is concerned, the project regions committed to allocate some

Birr 501.83 million for the implementation of COWASH activities in five years. Accordingly, the

five project regions have allocated funds amounting to Birr 578.14 million (Table 5). The amount

allocated exceeds the committed as some regions (Amhara and Tigray) have allocated additional

funds above their commitments. SNNPR and Oromia regions have allocated below their

commitments.

Page 13: COMMUNITY-LED ACCELERATED WASH (COWASH) PROJECT€¦ · 1 EXECUTIVE SUMMARY ... STRENGTHENING THE FEDERAL CAPACITY TO IMPLEMENT COMMUNITY MANAGED PROJECTS ALONGSIDE WITH A SUPPORT

7

Table 5: Budget Committed and Allocated for COWASH by Project Regions

Total Allocated

(2004-2007EFY)2008 EFY

Total Allocated

(2004-2008 EFY)

Amhara 239,634,780 224,201,665 76,187,621 300,389,286 60,754,506

Tigray 92,838,635 31,217,328 32,461,725 63,679,053 (29,159,582)

SNNPR 77,400,262 35,116,139 15,227,151 50,343,290 (27,056,972)

Oromia 72,153,550 45,834,762 17,949,779 63,784,541 (8,369,009)

BSG 20,800,000 4,000,000 16,800,000 20,800,000 -

Total 502,827,227 340,369,894 158,626,276 498,996,170 (3,831,057)

Region

Amount

Commited to be

Allocated by

Regions

(in Birr)

GoE Budget Allocated (in Birr)

Allocated LESS

Committed

4 COMPONENT 1: STRENGTHENING THE FEDERAL CAPACITY TO IMPLEMENT

COMMUNITY MANAGED PROJECTS ALONGSIDE WITH A SUPPORT TO THE

ESTABLISHMENT OF THE ONE WASH NATIONAL PROGRAM

In 2008 EFY, the project planned to widen and deepen its support by providing technical and

financial support to NWCO and other stakeholders of the project. The Component 1 major

activities planned and performed during the reporting period are presented under the outputs

indicated below (Component 1 detailed activities planned and performed in the reporting period

are attached in Annex 1). It should be noted that all the activities performed by the federal

COWASH team do not automatically belong to Component 1 but support directly Component 2

(the project regions).

4.1 RESULT 1 OF COMPONENT 1: COMMUNITY MANAGED PROJECT APPROACH

SCALED-UP AT NATIONAL LEVEL

4.1.1 Output 1: Manuals and Guidelines Reviewed and Developed for Standardizing the

CMP Implementation within the WaSH Implementation Framework

The achievement of the output is measured by the three indicators: i) number of generic CMP

implementation guidelines harmonized with WIF and incorporating crosscutting issues developed

and implemented, ii) number of tested higher technology options reviewed and incorporated into

CMP manuals and guidelines and iii) number of generic O&MM manuals/guidelines for rural water

supply developed.

A number of manuals/guidelines have been prepared in the last fiscal years. The major activities

planned and accomplished in the reporting period, under this output level, are presented below.

4.1.1.1 Participation in the Task Force in the Development of Generic Rural Water Supply O&MM RPS and Point Water Schemes and Generic O&MM Strategic Framework

The project planned to finalize the O&MM, strategic framework and business plan preparation

started in 2006 EFY. This fiscal year, additional assignment was given to the consultant to

prepare trainer’s manual for the O&MM manuals developed. Accordingly, the consultant has

submitted the O&MM manual with 18 parts, strategic framework and business plan by

incorporating all the comments and suggestions. The manuals have been submitted to MoWIE for

endorsement and some editing works are remaining to complete the training manuals. Overall,

98% of the assignment has been completed until end the reporting period. However, translation

of the trainer’s manual, business plan, strategic framework and training manuals is not yet

started. The manuals are available in the project’s website www.cmpethiopia.org

Page 14: COMMUNITY-LED ACCELERATED WASH (COWASH) PROJECT€¦ · 1 EXECUTIVE SUMMARY ... STRENGTHENING THE FEDERAL CAPACITY TO IMPLEMENT COMMUNITY MANAGED PROJECTS ALONGSIDE WITH A SUPPORT

8

4.1.1.2 Preparation and Approval of the CMP Implementation Manual based on Public Financial

Management System (PFMS)

The CMP Implementation Manual as per the Public Financial Management System was finalized by

private consultants and submitted to MoFED for approval. The manual was prepared to be part of

POM. However, so far, there is no official response from MoFED and a number of important

federal and regional level activities planned are still pending.

4.1.1.3 Development and Translation of Climate Risk Screening Trainer’s Manual

Climate risks screening guidelines has been completed by ODI. This year, it is planned to prepare

trainer’s manual and translate these manuals into Amharic for providing training to regional and

woreda staff. Accordingly, COWASH has developed climate and environment risks screening

trainer’s manual in consultation with ODI experts based on the draft climate risk screening

guideline developed by the institute (100.0%). Moreover, the climate and environmental risks

screening trainer’s manual has been translated into Amharic, by a private consultant, for

providing trainings at the woreda and grassroots level (100.0%).

4.1.1.4 Development of Social Accountability Guideline

With the view to improving the service level thereby contributing for sustainability of the facilities

constructed in the project woredas, the project planned to develop and implement a Social

Accountability guideline. Consequently, the draft guideline was finalized by COWASH FTAT by

incorporating the comments and suggestions on the guideline (50.0%). Latter it was decided to

postpone the piloting of the guideline so as to get the views of WASH stakeholders in developing

a sector wide social accountability guideline. The coordination meeting between the sector

ministries has not yet been organized and the finalization of the guideline is pending. Ethiopia

Social Accountability Project (ESAP) organized the first national conference on Social

Accountability on March 31 to April 1, 2016 and COWASH participated in the conference. The

primary objective of the conference was to familiarize sector ministries on the concept, processes

and results of Social Accountability.

4.1.2 Output 2: Tools and Mechanisms Reviewed and Developed for Standardizing the

Planning, Implementation and Monitoring of CMPs

Four indicators were set to measure the achievement of the output, namely, i) number of annual

plans prepared; ii) number of quarterly reports prepared and disseminated to partners; iii) M&E

framework developed; and iv) number of federal level steering committee meetings conducted.

As indicated in Annex 1, as in the previous implementation years, a series of activities that are

believed to contribute for the achievement of the output were planned to be carried out in the

reporting period. Some of the major activities planned and their status are presented as follows:

4.1.2.1 Preparation of Annual Plans

The 2008 EFY COWASH Component 1 (C-1) annual plan has been prepared and approved by the

NWSC early in the first quarter (100.0%). Thorough discussion was made on the plan together

with the 2007 EFY project performance progress report. Moreover, COWASH FTAT has assisted

regions in preparing the 2008 EFY annual plans. Planning templates (physical and financial) and

unit costs were prepared and distributed to RSUs to modify them to be suitable to their situation

and employ them in their planning exercises.

Page 15: COMMUNITY-LED ACCELERATED WASH (COWASH) PROJECT€¦ · 1 EXECUTIVE SUMMARY ... STRENGTHENING THE FEDERAL CAPACITY TO IMPLEMENT COMMUNITY MANAGED PROJECTS ALONGSIDE WITH A SUPPORT

9

4.1.2.2 Facilitation and Participation in National WaSH Steering Committee Meetings

National and Regional WaSH Steering Committee meetings are expected to be made twice a year.

COWASH is expected to facilitate and provide technical assistance in undertaking these meetings.

In the reporting period, the National WASH Steering Committee (NWSC) on COWASH was held

early in the first quarter. The meeting was held with the facilitation of COWASH FTAT. During this

meeting, the 2007 EFY annual performance progress report and 2008 EFY Component 1 annual

plan were discussed and endorsed.

4.1.2.3 COWASH Annual Performance Report Preparation

In the reporting period, COWASH FTAT is expected to prepare two performance reports (the

performance reports of the previous fiscal year, the first quarter and semi-annual performance

reports). Consequently, the 2007 EFY annual performance report, the 2008 EFY first quarter and

semi-annual performance reports of the project have been prepared and disseminated to

stakeholders (100.0%). Moreover, a summarized report of the 2007 EFY C-1 performance report,

the 2008 EFY first and semi-annual performance reports of Component 1, including progress of

water supply scheme and institutional latrine construction achievements, have been prepare and

submitted to MoWIE.

4.1.2.4 COWASH Data Compilation Template Preparation

Project data compilation templates are planned to be developed with the aim of managing the

project data and generating reports on the performance of the project in the regions. Last fiscal

year, it was managed to develop COWASH project data management templates for SNNPR and

BSG regions. It was planned to develop 2 data compilation templates (one each for Tigray and

Oromia) in the reporting period. Accordingly, the data compilation and management templates

were developed for Tigray and Oromia regions and implementation started. On-the-job training

was given to RSU staff of the two regions and data on plans and accomplishments over the years

in the regions is being entered into the templates. The project data in the regions is expected to

reach to COWASH FTAT, as per the templates, until end of the fiscal year.

4.1.2.5 Production of WASH facility maps for COWASH woredas

This year, it is planned to produce 46 maps. All of them are planned to be developed in the

reporting period. At the end of the reporting period, the GIS specialist developed all of the

planned woreda maps (100.0%). So far, 57 woreda maps with facilities constructed have been

produced and these maps will be updated to include all the WPs and latrines constructed in the

woredas until end of 2007 EFY. The maps of all the FinnWASH-BG woredas have been produced

and submitted in hard disk, together with other data, to Embassy of Finland.

4.1.2.6 Technical Assistance in 2007 EFY Annual Review and 2008 EFY Regional Planning Workshops

COWASH has been assisting in conducting annual review and planning workshops of regions.

These workshops are learning forums for project woredas and zones for strengthening plan

preparation and mitigating the challenges in implementing project activities at all levels. In the

reporting period, it was planned to assist and participate in the 2007 EFY annual performance

review and 2008 EFY plan preparation workshops of all project regions. Accordingly, COWASH

FTAT participated in 2007 EFY performance review and 2008 EFY annual plan preparation

workshops of the five project regions (Amhara, Tigray, SNNPR, Oromia and BSG). In these

workshops, besides preparing 2008 EFY plans, woredas and zones have shared their experiences

in implementing CMP approach and experiences of other regions have been shared by COWASH

FTAT.

Page 16: COMMUNITY-LED ACCELERATED WASH (COWASH) PROJECT€¦ · 1 EXECUTIVE SUMMARY ... STRENGTHENING THE FEDERAL CAPACITY TO IMPLEMENT COMMUNITY MANAGED PROJECTS ALONGSIDE WITH A SUPPORT

10

4.1.2.7 Participation in Regional WASH Steering Committee (RWSC) meetings

COWASH is being implemented in the regions with the overall guidance and governance of

Regional WASH Steering Committee (RWSC) in which Embassy of Finland is a member. RWSCs

are expected to meet twice in a fiscal year with the facilitation of COWASH FTAT. In the reporting

period, each RWSC has made one meeting and these meetings deliberated mainly on the 2007

EFY annual performance report and the 2008 EFY annual plan. Accordingly, all of the meetings

have endorsed both the 2007 EFY performance report and the 2008 EFY annual plans of the

regions. Tigray and SNNPR RWSC meetings were delayed until late the 2nd quarter due to

different reasons. Tigray’s meeting was delayed due to busy schedule of the RWSC members

while the SNNPR meeting had been delayed as the preparation of the annual plans could not be

finalized due to delay in the transfer of the committed funds from zones and woredas.

4.1.3 Output 3: CMP Approach within the Rural WaSH Scientifically Researched

Three indicators are set for measuring the achievement of this output. These are: i) number of

CMP researches (disaggregated by Doctoral, Masters and Bachelor levels) completed; ii)

number of published articles on CMP research results; and iii) number of CMP research result

presentations given in international conferences.

So far, one PhD level and one MSc level researches are underway and 4 MSc level and 1 BSc level

researches on CMP were completed with the financial and technical support of COWASH. All the

completed researches are uploaded in the website www.cmpethiopia.org. This fiscal year, the PhD

level research has continued and one MSc level research started. The status of these activities is

presented below.

4.1.3.1 Continuation of the PhD level research

So far, four articles have been prepared and all of them were submitted for publication in

reputable journals (Public Works Management & Policy, Waterlines and SAGE Open). Accordingly,

one of the articles was published in Public Works Management and Policy Journal and three of

them are at different stages. One of these articles is accepted and two of them are waiting

decision. The published article can be found in

http://pwm.sagepub.com/content/20/4/379.full.pdf?ijkey=7eTVbxtzzpmIOVs&keytype=finite.

Moreover, write up of the Dissertation is underway.

4.1.3.2 New MSc level research started

Last fiscal year, an MSc level CMP research entitled “Assessment of Potable Water Access & Users’

service satisfaction in Gonji Kolella woreda rural communities during CMP implementation” has

been on-going in Gonji Kolela woreda of Amhara region with the financial support of COWASH.

The draft thesis of the MSc level research was prepared and commented by COWASH FTAT and

sent to the researcher for corrections. However, so far, the final version of the thesis is not

submitted to COWASH. This year, another CMP research is started with technical and financial

support of COWASH. The new research is entitled “Community Participation in Rural Water Supply

Development and Management: The Case of Bahir Dar Zuria Woreda, West Gojjam Administrative

Zone, Amhara Region, Ethiopia”. The researcher is now collecting data in the target woreda and

analysis will be started at the beginning of the 4th quarter.

4.1.3.3 Case study on Women Empowerment through CMP

The case study intends to assess how women can be empowered through active (leadership)

roles in community managed projects. The study tries to compare women and men-led WASHCOs

Page 17: COMMUNITY-LED ACCELERATED WASH (COWASH) PROJECT€¦ · 1 EXECUTIVE SUMMARY ... STRENGTHENING THE FEDERAL CAPACITY TO IMPLEMENT COMMUNITY MANAGED PROJECTS ALONGSIDE WITH A SUPPORT

11

in relation to COWASH project performance. COWASH FTAT collected primary data from members

of WASHCOs in some kebeles of Fogera and Farta woredas of Amhara region. The data collected

was analysed and discussion was made with Women’s Affairs Directorate of MoWIE on the

preliminary results. It was decided to collect additional data from Tigray, SNNPR and Oromia

regions to get more insight into the issue of women empowerment. Consequently, additional data

was collected from some kebeles in SNNPR and Oromia and the data collection in Tigray is

schedule to be conducted in the first month of the upcoming quarter.

4.1.4 Output 4: Information, Education and Communication (IEC) on CMP

Implementation Modality Enhanced

The major indicators for measuring the achievement of the output are: i) Communication strategy

developed; ii) Number of major international and national events (workshops, seminars,

conferences, symposiums) where CMP awareness is raised through COWASH participation; and

iii) Number of CMP related information and education materials prepared and published

(disaggregated by types).

As indicated in Annex 1, a number of communication-related activities were planned for the

reporting period. The major ones and their status are indicated hereunder:

4.1.4.1 Production and distribution of CMP Calendar Notebooks

This fiscal year, the project planned to prepare and print CMP calendar notebooks unlike the

previous years where CMP table calendars had been produced. Accordingly, 5,000 CMP calendar

note books were produced and distributed (100.0%) to stakeholders at federal, regional, zone

and woreda levels including some other WASH actors. The calendar notebooks are believed to

raise awareness about the CMP approach at all levels.

4.1.4.2 Participation in selected International conferences, networking and forums

COWASH has been supporting participation in international conferences, networking meetings and

forums so as to promote CMP at the international and national levels. This reporting period, it was

planned to participate in Stockholm Water Week 2015 (SWWW 2015) and WEDC 2015. The

experience of COWASH in promoting and implementing CMP approach has been promoted in both

events. In the SWWW 2015, the Junior Professional Expert presented the CMP approach in two

sessions. The CMP approach was also promoted to visitors of the MFA’s stand at the exhibition.

The case study on development and scaling-up of CMP was presented at the 38th International

WEDC Conference held in Loughborough University in England. While three MoWIE staff (State

Minister, Women Affairs Director and Change Management Director and junior professional officer

of COWASH) participated in the SWWW2015, two persons (NWCO coordinator and COWASH

junior professional officer) took part in the WEDC 2015.

4.1.4.3 Developing Video Films and Clips on CMP Implementation

With the view to promoting CMP implementation, it was planned to prepare 1 documentary film

and two video clips that focus on the implementation process of CMP approach. So far, the

documentary film and one video clip (67.0%) were prepared and shared on CMP Youtube account

and Facebook page. The preparation of one of the video clips is postponed to the upcoming

quarter due to come competing activities on the Communication Specialist.

4.1.4.4 Developing Case Studies on CMP Implementation

This fiscal year it was planned to conduct two case studies, one in Bambasi woreda in BSG reigon

and the other in Bahir Dar Zuria woreda of Amhara region. As a result, the case study that

focuses on the lack of access to water, sanitation and hygiene (WASH) service showcasing Nebar

Page 18: COMMUNITY-LED ACCELERATED WASH (COWASH) PROJECT€¦ · 1 EXECUTIVE SUMMARY ... STRENGTHENING THE FEDERAL CAPACITY TO IMPLEMENT COMMUNITY MANAGED PROJECTS ALONGSIDE WITH A SUPPORT

12

keshmando kebele in Bambasi woreda was prepared. In addition, the other case story that

focuses on the provision of safe water supply in Yeloma kebele of Bahir Dar Zuria Woreda was

also prepared (100.0%). However, these case stories could not be published in different national

newspapers due to shortage of budget.

4.1.4.5 Updating CMP WEB page

The official CMP website (www.cmpethiopia.org) was developed in collaboration with IRC to

disseminate basic information on CMP and attract more funding for the country. In the reporting

period, the website has been updated regularly. News about various events were prepared and

published on the website. In an attempt to call the attention of concerned bodies to these

updates, efforts were made to share the links of those updates. Some more updates have been

made on the website to provide information on CMP implementation. Moreover, the CMP facebook

and the youtube account are also updated regularly to provide information about CMP to the

larger audience.

4.1.4.6 Assistance and Participation in National Events

The project has been assisting (financially and technically) in executing major national events:

International Women’s Day and World Water Day celebrations. The assistance includes both

financial and technical. Accordingly, COWASH financed and supported technically the celebration

of Women's International Day. Besides, COWASH FTAT participated in the celebration of World

Water Day. The support of COWASH in the preparation and celebration of Women’s Day was

appreciated by the Women’s Affairs Directorate.

4.2 RESULT 2 OF COMPONENT 1: CMP IMPLEMENTATION CAPACITY AT THE

FEDERAL AND REGIONAL LEVELS DEVELOPED

4.2.1 Output 1: Capacity Building Instruments Reviewed and Developed

The achievement of the output is to be measured by three indicators: i) Generic CMP capacity

building strategy developed; ii) Generic woreda level capacity building package developed; and

iii) number of impact assessments made on CMP related trainings (one in each project region).

The project has developed generic CMP capacity building strategy and generic woreda level

capacity building package in the previous implementation years. The capacity building strategy

has been revised every year to capture new developments in the WaSH sector. Moreover,

training impact assessments have been completed.

Some of the main activities planned for the reporting period and their progress are presented

below.

4.2.1.1 Updating of COWASH Capacity Building Strategy

This year it was planned to update the capacity building strategy of the project. Accordingly, the

capacity building strategy has been updated (100.0%) by the Human Resources Development

Specialist (HRDS). Trainings supported by the project have been conducted following the

updated strategy.

4.2.1.2 Evaluation of the COWASH training approaches

It was planned to assess the existing COWASH training materials, tools, approaches, methods,

number of trainees per session, etc. and make some suggestions. Accordingly, assessment on

the training methodologies and materials has been done by an independent consultant and

recommendations made (100.0%). Following the recommendations, COWASH’s HRDS has

Page 19: COMMUNITY-LED ACCELERATED WASH (COWASH) PROJECT€¦ · 1 EXECUTIVE SUMMARY ... STRENGTHENING THE FEDERAL CAPACITY TO IMPLEMENT COMMUNITY MANAGED PROJECTS ALONGSIDE WITH A SUPPORT

13

conducted training of trainer’s for COWASH FTAT and regional support units (RSUs) to improve

pedagogical skills in conducting trainings, facilitation and training design. WASHCO handbook in

CMP will be developed to be used during WASHCO training and retained by WASHCOs for

reference.

4.2.2 Output 2: Capable and Adequate Personnel in place for CMP Implementation at

National and Regional Levels

Number of people hired at federal and regional level (disaggregated by sex), number of trainings

given by the federal COWASH team and number of people participated in trainings (disaggregated

by sex) are the indicators set to measure the achievement of the output.

A number of capacity building activities, which are decisive for the sustainability of the water

supply schemes are planned to be conducted in the fiscal year. The main ones are trainings on

climate risk screening and WSP, pedagogical skills and knowledge, O&M, etc. The four major

trainings and some refreshment trainings assisted by COWASH FTAT and their progresses in the

reporting period are indicated hereunder.

4.2.2.1 ToT Training on Climate Resilient Water Safety Planning (CR-WSP)

COWASH planned to provide ToT training on CR-WSP with the view to sustain the water supply

services in the project regions. Accordingly, CR-WSP ToT was provided to regional selected and

pertinent WASH sector experts drawn mainly from COWASH FTAT, RSU, Water bureau, Health

bureau and Agriculture Bureau (BoA). A total of 28 experts (4 Female) have received the ToT

training held for 5 days in Bishoftu town. This accounts about 75.7% of the planned trainees. A

one day field visit was made in Adaa Woreda of Oromia region and trainees have developed their

own WSP plan based on the field visit. The training was provided by a team of experts constituted

from MoWIE, Hydrology & Water Quality Directorate and WHO Country Office.

4.2.2.2 ToT Training on Climate and Environmental Risk Screening

COWASH has also planned to undertake ToT training on climate and environmental risk screening

to regional sector office staff and COWASH FTAT. Consequently, the ToT training was given to

regional WASH sector experts drawn mainly from COWASH FTAT, RSU, Water bureau, and

Agriculture bureau. A total of 30 experts (5 Female), which is 111.1% of the plan, have received

the training conducted for 5 days at Bahir Dar town. The trainees have spent two and half days

on the field in a kebele in Farta woreda of Amhara region and discussed their observations and

experiences about the site visited. The training was given by experts drawn from Oversees

Development Institute (ODI) and Addis Ababa University.

4.2.2.3 ToT Training on Pedagogical and Facilitation Skills and Knowledge Training

Another important ToT training planned to be conducted in the reporting period was Pedagogical

skill training. This was designed to improve the training, facilitation and presentation skills of the

regional and federal level experts participating in different trainings at different levels. It was

managed to provide the training to 28 (2 females) regional and COWASH FTAT experts for 4 days

at Hawassa town. The training was given by the COWASH Human Resources Development

Specialist (HRDS).

4.2.2.4 ToT Training on GIS and Data Management

Last fiscal year COWASH had trained many of the regional, zonal and woreda level experts on GIS

and data management. This fiscal year it was planned to train 34 staff of region, zones and

woredas in BSG, Oromia and SNNPR. Accordingly, 47 staff of woreda, zone and regional sector

Page 20: COMMUNITY-LED ACCELERATED WASH (COWASH) PROJECT€¦ · 1 EXECUTIVE SUMMARY ... STRENGTHENING THE FEDERAL CAPACITY TO IMPLEMENT COMMUNITY MANAGED PROJECTS ALONGSIDE WITH A SUPPORT

14

offices in Oromia and BSG and MoWIE staff 138.0%) have been trained on GIS and data

management for four days. The training was given by the COWASH GIS expert in collaboration

with other COWASH FTAT and MoWIE staff. COWASH has now made available two GIS trained

people in each of the 76 project woredas and more than three experts in each region.

The trainees gained skills and experience in managing their water points and latrines data and

producing maps.

4.2.2.5 Refreshment trainings assisted by COWASH FTAT

Like the previous fiscal years, COWASH FTAT planned to assist RSUs in carrying out refreshment

trainings based on demand. It was planned to refresh 88 woreda and zonal experts in CMP

management, appraisal and WASHCO CMP management. Until end of the reporting period, 77 (3

female) woreda and zonal experts in Oromia and BSG regions have been refreshed with the

technical support of the COWASH FTAT. This accounts about 96.0% of the planned trainees.

Overall, 118 (10 females) COWASH FTAT, MoWIE, regional, zonal and woreda level staff have

been trained on different issues for 4 to 5 days. This accounts about 106.0% of the trainees

planned to be trained in the reporting period. The achievement exceeded the plan due to the

inclusion of MoWIE staff in the GIS and data management training.

Moreover, COWASH FTAT assisted in refreshing 77 (3 female) woreda and zonal experts in

Oromia and BSG regions as per the request of the RSUs.

4.3 RESULT 3 OF COMPONENT 1: DEVELOPMENT AND IMPLEMENTATION OF ONE

WaSH NATIONAL PROGRAM SUPPORTED

In the One WaSH National Program development, COWASH is accountable for the provision of

technical assistance and financial support as per the mutually agreed terms of references.

COWASH is not, however, responsible in the development and implementation of One WaSH

National Program.

4.3.1 Output 1: COWASH Support Provided in Preparing One WaSH National Program

Number of short-term consultancy days provided by COWASH for the development and

implementation of One WaSH National Program, and amount of finance provided for the

development and implementation of One WaSH National Program are the indicators set to

measure the achievement of this output.

The major activities planned for the reporting period are: i) support the OWNP Phase II Program

Document Preparation; and ii) participate in the One WASH National Program Task Force

meetings for the Phase I review.

However, COWASH couldn’t contribute much in the reporting period as the activities planned have

not been started by the NWCO. Anyhow, the following has been accomplished in the reporting

period:

- besides sponsoring the reporter and proceeding of MSF 7, COWASH together with

NWCO proposed OWNP Phase II Program Document Preparation to be part of the MSF

7 undertakings and finally approved

- technical assistance provided in drafting ToR for OWNP review and Phase II document

preparation

- the task force for the review of OWNP Phase I and the Preparation of the Phase II has

not yet been established and COWASH is assisting and calling for the establishment of

this task force.

Page 21: COMMUNITY-LED ACCELERATED WASH (COWASH) PROJECT€¦ · 1 EXECUTIVE SUMMARY ... STRENGTHENING THE FEDERAL CAPACITY TO IMPLEMENT COMMUNITY MANAGED PROJECTS ALONGSIDE WITH A SUPPORT

15

- COWASH is assisting NWCO in planning and implementing different preparatory

activities that enhance the successful implementation of the WASH activities in the

country.

4.3.2 Output 2: COWASH Support Provided in Implementation of One WaSH National

Program

Number of people trained in CMP implementation in non-COWASH regions by federal COWASH

and number of federal level advisers assigned in the One WaSH National Program management

are the two indicators set for measuring the achievement of the output.

The indicators were set with the view that OWNP will be implemented and CMP will be scaled-up

in the rest of the regions of the country. However, reporting as per these indicators has not been

started as the CMP approach is not yet implemented in the non-COWASH regions. Other activities

which assist the implementation of the OWNP were planned by the project.

In the period under reporting, COWASH planned to participate in JTR 9, assist in undertaking

MSF, providing technical assistance to the OWNP M&E system development team, and

participating in different task forces and technical committees. Accordingly, all of the planned

activities have been undertaken as planned. The detailed activities performed are indicated

hereunder:

- COWASH FTAT participated in JTR 9 and preparation of report on the review. The findings

of the review were presented at the MSF 7.

- COWASH has actively participated in the preparation and undertaking of MSF 7. The CTA

of COWASH has contributed a lot in selecting topics of presentations, shaping the

presentations, preparing schedule of the forum, facilitating and chairing presentations and

preparing undertakings of the forum.

- COWASH FTAT is working closely with the M&E development team and providing technical

assistance in workshops organized and providing enriching comments on reports produced

by the team. The project staff provided detailed comments on Diagnostic Analysis,

Inception report and WASH M&E MIS assessment reports produced by the team.

- COWASH has also contributed a lot in the development of the WASH sector through

participating in a number of task forces’ meetings and events such as Urban-WASH Sub-

Group meetings, Rural-WASH Sub-Group meetings, WASH-SG meeting, and Self-supply

sub-group meetings. COWASH could not participate in some other task force meetings due

to overlapping of schedules.

- Contributed in the Sanitation Marketing Occupational Standard and SME development and

CR-WSP development through participating in committee meetings.

5 COMPONENT 2: ESTABLISHING AND STRENGTHENING THE CAPACITY IN

REGIONS TO SCALE-UP IMPLEMENTATION OF CMP

Component 2 aims at building the capacity of target Regions, Zones and Woredas to plan,

manage, monitor and implement WaSH interventions through the CMP approach; deliver financial

and procurement services for CMP interventions at all levels; and to increase the sustainable

community and institutional access to safe water, sanitation and hygiene in the target areas.

The major achievements of the regions during the first nine months of 2008 EFY are indicated

hereunder.

Page 22: COMMUNITY-LED ACCELERATED WASH (COWASH) PROJECT€¦ · 1 EXECUTIVE SUMMARY ... STRENGTHENING THE FEDERAL CAPACITY TO IMPLEMENT COMMUNITY MANAGED PROJECTS ALONGSIDE WITH A SUPPORT

16

5.1 RESULT 1 OF COMPONENT 2: TARGET REGIONS, ZONES AND WOREDAS

CAPABLE TO PLAN, MANAGE, MONITOR AND IMPLEMENT RURAL WaSH

INTERVENTIONS USING CMP APPROACH

The major achievements of the regions in the reporting period in planning, managing, monitoring

and implementing WaSH interventions through CMP approach are presented in the following

output levels.

5.1.1 Output 1: Regional Support Units (RSU) Established and Functional

Number of Regional Support Unit (RSU) staff hired (disaggregated by region and sex), number of

annual COWASH work plans produced and number of COWASH quarterly and annual reports

produced as per the annual plan are set to measure the achievement of this output of Component

2.

All project regions have hired adequate staff in previous years of implementation of the project.

In the reporting period, it was planned to fill the Oromia Financial Specialist and SNNPR Capacity

Building and M&E Specialist posts. Consequently, the Oromia Financial Specialist was filled. The

SNNPR post could not be filled due to complaint raised on the recruitment process.

Every year, all project regions are expected to prepare and approve their annual plans of the

project. Accordingly, regions have prepared the 2008 EFY plans of the project, with the

participation of woreda, zonal and regional stakeholders, and approved by the respective Regional

WASH Steering Committees. The preparation and approval of the regional plans were extended to

the 2nd quarter due to delay in the announcement of shares of annual budget of the woredas and

zones and busy schedule of steering committee members.

Regions are also expected to prepare and submit four performance reports (3 quarterly and one

annual) to Embassy of Finland as per their funding agreement. In the reporting period, RSUs of

the four COWASH regions have prepared and submitted the 2007 EFY annual (physical and

financial) reports and the 2008 EFY first and 2nd quarter performance reports (100.0%). The first

quarter performance reports of the regions were not formal as their plans were not approved and

there were no many activities performed in the quarter.

Besides, unlike the previous fiscal years, Regional WaSH Steering Committee (RWSC) on

COWASH meetings were conducted timely. In these meetings, the RWSCs have endorsed the

2008 EFY annual plans and made decisions on a range of issues of the project which speed up the

implementation of the project in their respective region.

5.1.2 Output 2: Regions, Zones and Woredas Capacitated to Implement Rural WaSH

through CMP

Number of trainings types held by region (disaggregated by type of training), number of people

(disaggregated by sex and type of training) participated in trainings given by regions, zones and

woredas and number of water points and institutional latrines built as per plan (proxy indicator)

are the indicators set to measure the achievement of the output.

The scaling-up of the CMP approach requires extensive human capacity building activities at the

regional, zonal and woreda levels. A number of trainings, including refreshments, are planned to

be conducted in the regions. Accordingly, some trainings have been conducted in the reporting

period. The performances of the regions in human capacity building in the first half of the fiscal

year are presented hereunder.

Page 23: COMMUNITY-LED ACCELERATED WASH (COWASH) PROJECT€¦ · 1 EXECUTIVE SUMMARY ... STRENGTHENING THE FEDERAL CAPACITY TO IMPLEMENT COMMUNITY MANAGED PROJECTS ALONGSIDE WITH A SUPPORT

17

5.1.2.1 Trainings Conducted in SNNPR in the First Nine months of 2008 EFY

In SNNPR, a total of 26 trainings (new and refresher) were planned for 2008 EFY. Among these,

10 were planned to be undertaken in the reporting period.

Accordingly, project woredas have managed to undertake 8 of the 26 types of trainings planned

for the fiscal year (30.8%).

In aggregate, 2,631 people (woreda staff, members of KWT & WASHCO, artisans, members of

Women Associations, etc) have been trained on different issues for 3 to 40 days by woreda

experts trained at the regional level. This accounts about 30.0% of the people planned to be

trained in the fiscal year. Among the people trained in the reporting period, 865 (33.0%) were

female and 45 (2 females) were artisans engaged in the construction of water supply schemes

and institutional latrines.

The types of trainings conducted in the reporting period include, i) KWT CMP management,

ii) artisans training (new and refreshment), iii) WASHCO CMP management and O&MM training,

iv) pump attendants and caretakers training, v) CLTSH training for kebele and woreda level

experts, and vi) KWT gender awareness and mainstreaming training. These trainings were

conducted with an outlay of Birr 1.98 million capacity building funds (Table 6).

Page 24: COMMUNITY-LED ACCELERATED WASH (COWASH) PROJECT€¦ · 1 EXECUTIVE SUMMARY ... STRENGTHENING THE FEDERAL CAPACITY TO IMPLEMENT COMMUNITY MANAGED PROJECTS ALONGSIDE WITH A SUPPORT

18

Table 6: Trainings held in SNNPR in First Nine months of 2008 EFY

M F T M F T

1WWT & ZWT CMP management & Social Accountability Training

(Refresher)

RSU & COWASH

FTAT135 135 135 - - - - - -

2CMP application preparation, appraisal and M&E Training for Woreda CMP

appraisal team( Refresher).

RSU & COWASH

FTAT52 52 52 - - - - - -

3 WASHCO CMP management & Implementation ToT Training (Refresher)RSU & COWASH

FTAT48 48 48 - - - - - -

4 CR-WSP ToT for Zonal & Woreda staff (selected woreda) RSU & COWASH

FTAT52 52 52 - - - - - -

5Woreda& Zonewater office staff Training on RWSO&MM based on thenew

manual

RSU & COWASH

FTAT- - 28 - - - - - -

6 Environmental Assessment & Climate Risk Screening TrainingRSU & COWASH

FTAT- - 28 - - - - - -

7 Woreda & Zone staff Training on the use of Water Quality Test Kits WRB - - 60 - - - - - -

8Regional, zonal and woreda CMP focal persons Training in communication

skills, photographing and videoing

RSU & COWASH

FTAT- - 32 - - - - - -

12 Zonal and Woreda Health Office technical Staff Training in ODF Verification BoH & RSU 92 92 92 - - - - - -

13Zonal & Woreda health office experts Training in the improved household

sanitation technology and sanitation marketingBoH & RSU 30 30 30 - - - - - -

14

Woreda & Zone finance officeaccountants Financial Managemetn Training in

CMP management using the public Finance and Procurement Management

System ( if manual approved by MoFEC)

BoFED & RSU 25 25 25 - - - - - -

15KWT training in CMP promotion, application preparation, appraisal & M&E&

social accountability at the woreda level WoW 181 181 328 126 36 162 215 97 312 3 231,805

16 Training of new artisans in hand dug well & spring construction WoW - 63 120 - - - 30 - 30 40 141,206

17 Refreshment training for previously trained (old) artisans WoW 15 15 375 13 2 15 13 2 15 15 67,300

18 WASHCO training in CMP implementation & social accountability WoW - - 1,010 185 169 354 366 328 694 4 526,673

19Training of WASHCO members of new WPs in O&M management,

environmental S&H and gender mainstreaming (new)WoW - - 1,041 66 44 110 308 224 532 3 378,811

20

Training for EXISTING (OLD) WASHCO members of WPs in O&M

management and environmental S&H and Gender Mainstreaming

(refresher)

WoW - - 2,195 - - - - - -

21Training of Kebele Climate Resiliant WSP Team (CR-WSPT) in selected kebele

in CR-WSP/GLWOS WoW - - 775 - - - - - -

22 Training of newpump attendants and caretakers of WPs (new) WoW - - 364 90 - 90 389 61 450 3 314,911

23 Training for EXISTING pump attendants and caretakers of WPs (refresher) WoW - - 1,060 - - - - - -

24 Training for selecetd scheme specific CR-WSP team WoW - - 110 - - - - - -

25 Training of Woreda and Kebele Level Experts in CLTSH Wo H - - 400 106 71 177 352 109 461 4 242,738

26Training on gender awareness and mainstreaming to Kebele WaSH Team

(KWT) membersWWAO - - 400 38 12 50 93 44 137 3 77,519

Total 630 693 8,760 624 334 958 1,766 865 2,631 1,980,963

S/N Type of Training Trainer

Planned No. of Trainees

3rd

QuarterAnnualCumulative

Number Trained

3rd Quarter Cumulative

No. of

Days

Trained

Total Cost of

Training (in Birr)

5.1.2.2 Trainings Conducted in Tigray Region in the First Nine Months of 2008 EFY

In Tigray region, 15 types of trainings were planned to be executed in the fiscal year (Table 7).

All of these trainings were planned to be completed in the reporting period. Consequently, nine of

the trainings (60.0%) have been conducted in the first nine months and the remaining human

capacity building activities are scheduled to be started in the final quarter of the fiscal year. The

delay in the approval of the annual workplan has contributed for the low performance in building

the capacity of implementers and other stakeholders of the project. Some of the major trainings

conducted are: i) WASHCO CMP management, ii) KWT CMP Promotion and Appraisal, iii) CLTSH

for Kebele level experts, iv) Climate risk screening training; v) GLOWS/WSP ToT training; and

vi) WASHCO CMP management training.

Page 25: COMMUNITY-LED ACCELERATED WASH (COWASH) PROJECT€¦ · 1 EXECUTIVE SUMMARY ... STRENGTHENING THE FEDERAL CAPACITY TO IMPLEMENT COMMUNITY MANAGED PROJECTS ALONGSIDE WITH A SUPPORT

19

The regional performance report shows that a total of 895 (404 female) kebele, woreda and

regional level people, including members of WASHCO and KWT, have been trained for 2 to 5 days

at different levels. This accounts about 41.7% of the annual plan. The region has spent about Birr

0.68 million for the trainigns conducted in the reporting period.

Table 7: Trainings held in Tigray Region in First Nine Months of 2008 EFY

M F T M F T

1 WWT CMP Management TrainingCOWASH

FTAT & RSU30 30 30 34 3 37 34 3 37 26,944

2CMP Promotion, Application, Appraisal & M&E

Training

COWASH

FTAT & RSU30 30 30 34 3 37 34 3 37 26,994

3 WASHCO ToT in CMP ManagementCOWASH

FTAT & RSU27 27 27 - -

4 Financial training for Finanace Personel RSU 42 42 42 - -

5 Refreshment TOT in O&M of water schems RSU 25 25 25 - -

6 Pump Attendants & Caretakers Training BoW & RSU 384 - - - -

7 CLTSH Training for kebelle level experts Wo H 315 315 315 - 10 4 14 5 6,138

8 KWT CMP Promotion & Appraisal Training WoW 140 140 - 59 21 80 3 72,680

9 WASHCO CMP Management Training WoW 1152 1152 99 83 182 303 280 583 4 399,897

10 Artisans Training WoW 40 40 - -

11 WASHCO Training in scheme management WoW 1152 - - - -

12 GLOWS/WSP ToT Training BoW 20 20 15 3 18 15 3 18 4 47,808

13 KWT gender awareness & mainstreaming Training WoWA 280 280 - 24 24 - 83 83 2 29,718

14Training woreda experts and town water

committee on RPS O&MBoW 25 25 20 7 27 20 7 27 3 19,155

15 Climare Risk Screening Training WoW 20 20 0 - 16 0 16 3 48,648

3,682 469 2,146 202 123 325 491 404 895 677,982 Total

Estimated cost

of training (in

Birr)Annual3rd

QuarterCumulative

3rd Quarter CumlativeS/

NType of Training Trainer

No. of Trainees Planned Number Trained No. of

Days

Trained

Note: WoWA- Woreda Women Affairs Office; WoW – Woreda Water Office; BoH – Regional Health Bureau

5.1.2.3 Trainings Conducted in Amhara Region in the First Nine Months of 2008 EFY

In Amhara, 19 types of trainings were planned to be conducted in 2008 EFY. Majority of the

trainings were planned to be conducted in the reporting period. So far, 12 of the 19 trainings

have been conducted (63.0%) and the remaining trainings will be completed in the upcoming

quarter of the fiscal year. Many of the planned trainings started late because of the delay in the

approval of the annual plan and the fund transfer.

As indicated in the regional performance report, a total of 14,257 kebele, woreda, zonal and

regional level (78.5% of the planned) have attended the trainings provided for 2 to 45 days.

Females constituted some 35.2% of the trainees (Table 8). Among the trainees, 99 are artisans

traine for 45 days by the Woreda Water Offices experts. Unlike the other project regions, Amhara

has not been collecting and reporting estimated costs of trainings and items procured with the

support of the project.

Page 26: COMMUNITY-LED ACCELERATED WASH (COWASH) PROJECT€¦ · 1 EXECUTIVE SUMMARY ... STRENGTHENING THE FEDERAL CAPACITY TO IMPLEMENT COMMUNITY MANAGED PROJECTS ALONGSIDE WITH A SUPPORT

20

Table 8: Trainings held in Amhara Region in the First Nine Months of 2008 EFY

M F T M F T

1 WWT CMP Management Training ZoW & ZoH 360 360 188 20 208 241 28 269 2

2

CMP Promotion, Application, Appraisal

and M&E TrainingZoW & ZoH 160 160 145 30 175 195 38 233 2

3 WASHCO CMP Management ToT Training ZoW & ZoH 160 160 145 30 175 195 38 233 2

4 Financial Training for Finance Personnel BoFED 108 108 15 4 19 15 4 19 2

5 ToT training in O&MM of Water Schemes ZoW 120 120 120 71 26 97 71 26 97 2

6 Pump Attendants & Caretakers Training WoW 1,266 - -

7 CLTSH ToT Training ZoH 80 80 -

8 CLTSH Training for Kebele Level Experts W OH 800 800 800 549 480 1,029 549 480 1,029 4

9 KWT CMP Promotion & appraisal Training WoW & W oH 2,000 2,000 757 188 945 2,220 698 2,918 2

10 WASHCO CMP Management Training WoW & W oH 5,980 5,980 1,879 1,326 3,205 4,792 3,229 8,021 3

11 Artisans training WoW 15 15 - 39 60 99 45

12WASHCO Training in Scheme

ManagementWoW & W oH 5,980 5,980 5,980 - -

13

Institutional WASHCO training in Latrine

ConstructionWoW 80 80 39 12 51 62 24 86 3

14 ToT in CR-WSP BoW 10 10 7 3 10 7 3 10 5

15WASHCO CR-WSP team training on CR-

WSPWoW 18 18 18 13 2 15 13 2 15 2

16 Schools Sanitation Clubs training Wo H 800 800 800 817 392 1,209 817 392 1,209 2

17Woreda staff environmental assessment

and climate risk screening trainingWoW 120 120 - -

18Woreda education office experts training

on School Sanitation ProgrammeWo H 80 80 16 3 19 16 3 19 2

19ToT in Environmental Climate Risk

AssessmentWoW 30 30 - -

18,167 7,718 16,901 4,641 2,516 7,157 9,232 5,025 14,257Total

Total Cost

of Training

(in Birr)

S/N Type of Training Trainer

Number Trained

Annual

No. of

Days

Trained3rd

Quarter

Cumula

tive

3rd Quarter Cumulative

Planned No. of Trainees

5.1.2.4 Trainings Conducted in Oromia Region in the First Nine Months of 2008 EFY

A total of 25 types of trainings were planned to be given in Oromia region in 2008 EFY. All of

them were planned to be started in the reporting period. Consequently, 10 types of trainings

(40.0%) were conducted at the regional, zonal and woreda levels in the first nine months. The

major trainings conducted were: i) CMP appraisal & M&E; ii) WASHCO CMP management ToT

training; iii) Financial management training on the management of GoF fund;

iv) Environmental Assessment and Climate Risk Screening; v) CLTSH ToT Training;

vi) WASHCO CMP management and social accountability; vii) KWT CMP management training;

viii) Artisan training; and ix) Pump attendant and caretaker training. Over 3,986 regional, zonal,

woreda and kebele level people (37.0% females) have been trained on these trainings for 3 to 5

days with an outlay of about Birr 3.21 million allocated from GoF capacity building fund. The

number of people trained in the reporting period accounts about 40.0% of the planned for 2008

EFY (Table 9).

Page 27: COMMUNITY-LED ACCELERATED WASH (COWASH) PROJECT€¦ · 1 EXECUTIVE SUMMARY ... STRENGTHENING THE FEDERAL CAPACITY TO IMPLEMENT COMMUNITY MANAGED PROJECTS ALONGSIDE WITH A SUPPORT

21

Table 9: Trainings held in Oromia Region in the First Nine months of 2008 EFY

M F T M F T

1 WWT & ZWT CMP Management Training RSU 194 194 - -

2 CMP Promotion, Application, Appraisal & M&E Training RSU 78 78 0 50 3 53 3 225,823

3 WASHCO CMP Management ToT Training RSU 78 78 0 50 3 53 3 184,765

4 CR-WSP/GLOWS ToT Training BoWME 30 30 - - - - - -

5 Environmental Assessment and Climate Risk Screening

TrainingBoWME 51 51 43 3 46 43 3 46 5 358,840

6 Woreda and Zonal experts Water Quality testing Training BoWME 21 21 - - - - - -

7Regional, Zonal and Woreda Staff training on M&E, Data

Management and ReportingRSU 109 109 - - - - - -

8ToT on Sentisization of Influential Leaders on Sanitation &

HygieneBoH 65 65 - - - - - -

9 CLTSH ToT Training BoH 116 116 95 10 105 95 10 105 5 433,233

10 Woreda and Zonal experts on school led TSH BoE 82 82 - - - - - -

11GoF fund management Training for Woreda and Zonal

Finance personnelBoFED 29 29 - - - 20 7 27 3 85,792

12KWT CMP Promotion & Appraisal & Social Accountability

TrainingWoWME 798 798 633 208 841 633 208 841 3 425,942

13WASHCO CMP Management & Social Accountability

TrainingWoWME 2,556 1,283 2,556 808 577 1,385 808 577 1,385 3 676,410

14 Artisans Training WoWME 69 25 69 - - - - -

15 Artisans Refreshment Training WoWME 196 196 196 28 154 182 28 154 182 5 128,623

16 WASHCO Training in Scheme Management WoWME 2,651 537 2,651 686 496 1,182 686 496 1,182 5 579,362

17Trainin on Sensitization of Influential persons on Sanitation

and HygieneWo H 1,404 1,404 1,404 - - - -

18 Kebele and Sheme Specific CR-WSP Team training WoWME 80 80 80 - - - - - -

19 Pump attendants and care takers training WoWME 658 0 658 104 8 112 104 8 112 5 109,266

20 Scheme specific CR-WSP Training Wo h 450 0 450 - - - - - -

21 Triggering of Kebles Wo H 60 24 24 - - - - - -

22 Follow-up and Post triggering of kebeles Wo H 264 132 132 - - - - - -

23 CR-WSP/GLOWS ToT Training BoWME 80 80 80 - - - - - -

24 Radio Spot/Advocacy using local media Wo H 12 12 12 - - - - - -

25 School WASH clubs training WoE 120 120 120 - - - - - -

10,251 3,893 10,083 2,397 1,456 3,853 2,517 1,469 3,986 3,208,056

Number Trained Estimated cost

of training (in

Birr)

3rd Quarter CumlativeAnnual

3rd

QuarterCumulative

No. of

Days

Trained

Total

S/

NType of Training Trainer

No. of Trainees Planned

5.1.2.5 Trainings Conducted in BSG Region in the First Nine Months of 2008 EFY

In BSG, the implementing sectors planned to train some 4,510 people in 41 trainings in the fiscal

year. Thirty five of the trainings (85.4%) were planned to be started in the reporting period.

Accordingly, 19 of them (54.3%) have been conducted in the first nine months of the fiscal year.

Among the 4,510 planned number of people, 2,758 (61.2%) have received different trainings in

the reporting period. The trainees constituted WASHCO & KWT members, pump attendants and

care takers, artisans, etc. More than 32.0% of the people trained were females. The trainings

costed some Birr 2.24 million allocated from the Governemnt of Finland contribution. All the

trainings were conducted with an estimated capacity building fund of Birr 2.24 million. The major

trainings conducted in the reporting period were:1) pump attendants and care takers training,

2)CLTSH for kebele level experts, 3) O&MM training for woreda staff, 4) KWT and WASHCO CMP

management trainings, 5) Artisan trainings (for new and old artisans), 6) School WASH clubs on

School WASH, 7) KWT gender awareness and mainstreaming training. The trainings have been

conducted for 3 to 35 days (Table 10).

Page 28: COMMUNITY-LED ACCELERATED WASH (COWASH) PROJECT€¦ · 1 EXECUTIVE SUMMARY ... STRENGTHENING THE FEDERAL CAPACITY TO IMPLEMENT COMMUNITY MANAGED PROJECTS ALONGSIDE WITH A SUPPORT

22

Table 10: Trainings held in BSG Region in the First Nine months of 2008 EFY

M F T M F T

1 WWT CMP Management Training (Refreshment) BoW 0 74 74 0 0 0 0

2 CMP Promotion, Application, Appraisal & M&E Training (Refreshment) BoW 0 38 38 0 0 0 0

3 ToT in CR-WSP for Zonal Woreda experts BoW 34 34 34 20 4 24 20 4 24 4 56,181

4 WASHCO CMP Management ToT (Refreshment) BoW 77 77 77 72 5 77 72 5 77 4 123,712

5 Training on RWS O&MM BoW 24 24 24 0 0 0 0

6 Financial Training for Finance Personnel BoFED 0 42 42 19 11 30 19 11 30 4 36,280

7 Training on gender in WASH and Water Supply Protection WYCAB 0 30 30 0 0 0 0

8 Training for Women Association members on WASH and integration WYCAB 30 30 30 22 38 60 22 38 60 3 45,746

9 Training on Gender Mainstreaming in WASH WYCAB 0 100 100 0 0 0 0

10 ToT in O&MM of Water Schemes (Refreshment) BoW 0 42 0 0 0 0

11 Pump attendants & care takers Training(new) WoW 0 0 254 0 0 0 0

12 Pump attendants & care takers Training(old) WoW 0 44 44 0 0 0 36 0 36 5 24,066

13 Training of CR-WSP Team. WoW 83 83 83 0 0 0 0

14 WASHCO training on concrete slab production WoW 0 20 20 0 0 0 0

15 CLTSH Training for Kebele Level Experts WoH 0 240 240 29 23 52 147 64 211 5 160,108

16 CLTSH Training for Regional, Woreda& zonal experts BoH 0 44 44 48 0 48 48 48 29,748

17 Training on Improved Household sanitation technology & marketing BoH 0 60 60 0 0 0 0

18 Media/communication officers training on sanitation and hygiene promotion BoH 0 10 10 0 0 0 0

19 Training on school WASH BoE 0 30 30 124 1 125 124 1 125 1 80,175

20 School Improvement (SIP) domains training BoE 0 30 30 124 1 125 124 1 125 1 201,125

21 RWS O&MM training for Woredas ZoW 0 40 40 0 0 0 18 12 30 7 32,348

22 CLTSH training for woredas staff at zonal level ZoH 0 85 85 75 21 96 75 21 96 4 104,678

23 Water quality test training for woredas at zonal leve ZoH 0 60 60 0 0 0 0

24 KWT CMP Promotion & Appraisal Training WoW 0 599 599 8 23 31 210 52 262 4 253,281

25 WASHCO CMP Management Training New WoW 0 876 876 303 276 579 422 388 810 5 471,730

26 WASHco training for rehabilitation of water points WOW 0 48 48 0 0 0 48 32 80 3 39,630

27 Artisans Training(New) WoW 0 51 51 35 0 35 48 0 48 35 172,129

28 Artisans Refreshment Training WoW 0 23 23 9 0 9 29 0 29 4 25,889

29 Training of WASHCO members on O&MM, environment & gender (new) WoW 0 0 466 0 0 0 0

30Training of WASHCO members on O&MM, environment & gender

(Refreshment)

WoW0 237 237 90 60 150 90 60 150 7 114,289

31 Training of Kebele CR-WSP Team on GLOWS/WSP WoW 15 15 15 0 0 0 0

32 Training of School WASH clubs on WASH WoE 0 225 225 41 12 53 142 55 197 5 104,630

33 GLOWS/WSP ToT Training FTAT 0 0 24 0 0 0 0

34 KWT Gender Awareness & Mainstreaming Training WWYCA 0 294 294 18 21 39 182 138 320 5 164,353.00

35 Training on Environmental Impact Assessment & Climate Risk Screening BoW 0 0 40 0 0 0 0

36 Water Quality test kit training BoW 0 22 22 0 0 0 0

37CMP focal persons training on communication skills, photographing and

videoing

BoW 0 40 40 0 00 0

38 Public audit ToT Training FTAT 0 7 7 0 0 0 0

39 Bio-Sand Filter & Solar pump ToT training FTAT 10 0 10 0 0 0 0

40 Basic computer skill training BoW 30 0 30 0 0 0 0

41 SS system & Manual drilling ToT training FTAT 12 12 12 0 0 0 0

315 3,644 4,510 1,037 496 1,533 1,876 882 2,758 2,240,098

Number Trained Estimated cost

of training (in

Birr)

3rd Quarter Cumlative3rd Quarter Cumulative Annual

No. of

Days

Trained

Total

S/N Type of Training Trainer

No. of Trainees Planned

Page 29: COMMUNITY-LED ACCELERATED WASH (COWASH) PROJECT€¦ · 1 EXECUTIVE SUMMARY ... STRENGTHENING THE FEDERAL CAPACITY TO IMPLEMENT COMMUNITY MANAGED PROJECTS ALONGSIDE WITH A SUPPORT

23

5.1.2.6 Workshops and Meetings held in the Regions

Review and planning workshops and other meetings have been planned so as to increase and

cement the awareness on CMP at all levels in the project regions. The achievements of the

regions in the first nine months of the fiscal year are indicated hereunder.

All regions have successfully completed the 2007 EFY annual performance review and 2008 EFY

planning workshop. In these workshops, regions have reviewed COWASH/CMP performance of

2007 EFY and prepared (physical and financial) plans of 2008 EFY in the presence of over 781 (76

females) woreda, zonal and regional level stakeholders of the project. These workshops are

serving as experience sharing platforms for woredas and zones.

Some other workshops have also been conducted in the reporting period. Some woredas of

Amhara and SNNP regions have carried out Whole System in the Room (WSR) workshop for 1 to

5 days. A total of 2,799 (43.6% females) woreda and kebele level people took part in the

workshop held at woreda and kebele levels.

More than 4,119 (50.0% of the annual plan) have participated different types of workshops held

at different levels of the regions. Some 33.0% of the attendees were female.

However, workshops related to linking WASHCOs to the private sector and zonal level quarterly

review meetings have not been conducted as planned due to different reasons.

Page 30: COMMUNITY-LED ACCELERATED WASH (COWASH) PROJECT€¦ · 1 EXECUTIVE SUMMARY ... STRENGTHENING THE FEDERAL CAPACITY TO IMPLEMENT COMMUNITY MANAGED PROJECTS ALONGSIDE WITH A SUPPORT

24

Table 11: Workshops and Review Meetings held in the Regions in the 9 months of 2008 EFY

M F T M F T

1Annual Review (EFY 2007) and

Planning Workshop (EFY 2008) RWDB 438 0 438 0 0 0 285 44 329 2

2

Awareness Raising Workshop to

Private Sector on the Availability of

Market OpportunitiesZWD 250 250 86 9 95 86 9 95 1

3Zonal Quarterly Review Meeting with

WoredasZWD 720 360 360 251 23 274 251 23 274 2

4Whole System in the Room (WSR)

workshop W oH 4000 1173 910 2083 1299 1077 2376 1

1Annual Review (EFY 2007) and

Planning Workshop (EFY 2008) BoW 136 136 0 152 8 160 2 518,020

2Performance Review meeting on

Sanitation and HygieneBoH 102 51 0 0

3Zonal Quarterly Review Meeting with

WoredasZWT 201 201 201 0 0

1Annual Review (EFY 2007) and

Planning Workshop (EFY 2008) BoW 100 100 0 0 0 62 12 74 2 154,653

2Whole System in the Room (WSR)

workshop W oH 350 0 0 0 0

1Annual Review (EFY 2007) and

Planning Workshop (EFY 2008) BoW 138 138 0 122 2 124 1

2

Awareness Raising Workshop to

Private Sector on the Availability of

Market OpportunitiesZoW 145 0 145 0 0

3COWASH Zonal Quarterly Review

Meeting with WoredasZoW 272 68 136 15 4 19 15 4 19 3 54,740

4Whole System in the Room (WSR)

workshop W oH 880 37 65 102 279 144 423 5 308,214

5Briefing to Woreda Cabinet on 2008

EFY COWASH planW oH 160 80 160 13 2 15 57 8 65 1 5,180

1Awareness raising workshop on

WASH/CMP at the zonal level

Zonal

Offices170 170 17 0 17 101 10 111 2 to 5 104,485

2

Awareness Raising Workshop to

Private Sector on the Availability of

Market OpportunitiesZoW 60 60 21 10 31 21 10 31 2 1,884

3 Zonal Quarterly Review Meeting with

WoredasZoW 72 36 0 35 3 38 37,587

4Bi-Annual Performance Review

Meeting with Zones & WoredasB oH 90 0 0 0 0

Total 8,284 709 2,381 1,613 1,023 2,636 2,765 1,354 4,119

E. BSG Region

A. Amhara Region

B. Oromia Region

C. Tigray Region

D. SNNP Region

Number AttendedNo. of

Workshop

Days

Total Cost of

Workhop/Mee

ting (in Birr)

S/

NType of Training Organizer

No. of Participants

Planned

3rd Quarter3rd

QuarterCumulative

CumulativeAnnual

5.1.2.7 Procurements made in the Regions

COWASH also aims to building the physical capacity of the implementing institutions so as to

implement the CMP approach in a meaningful and sustainable manner. Much of the procurement

has been made in the previous fiscal years and only a few procurements were planned in this

budget year. Anyhow, some procurement activities were undertaken in the first nine months and

the different procurements made in the regions, zones and woredas are presented below.

Page 31: COMMUNITY-LED ACCELERATED WASH (COWASH) PROJECT€¦ · 1 EXECUTIVE SUMMARY ... STRENGTHENING THE FEDERAL CAPACITY TO IMPLEMENT COMMUNITY MANAGED PROJECTS ALONGSIDE WITH A SUPPORT

25

5.1.2.7.1 Procurements done in Oromia Region

This fiscal year, sixteen types of items, many of them rolled over from the previous fiscal year,

were planned to be procured in Oromia region. All of these items were planned to be procured in

the reporting period. Accordingly, many of the items (field vehicle, office equipments and

construction materials, etc.) have been procured in the reporting period. Among the planned

items de-watering pump, water quality test kits and small diameter molds were not procured as

planned. These items will be procured in the last quarter of the fiscal year together with other

procurements of regional sector bureaus. Capacity building funds amounting to Birr 2.19 million

was spent for the procurement of the 13 types of items (Table 12). Much of this cost (88.5%)

was spent for the procurement of field vehicle for RSU staff.

Table 12: Materials procured in Oromia region during First Nine Months of 2008 EFY

5.1.2.7.2 Procurements done in Amhara Region

Only 8 types of items were planned to be procured in Amhara region in 2008 EFY. This is mainly

due to the fact that procurements had been completed in the previous fiscal years. The regional

performance report shows that only 5 of the 8 items planned (63.0%) have been procured in the

reporting period. It was reported that only 20-50% of the planned quantities of these items have

been procured in the first nine months of the fiscal year. The items procured are desktop

computers (20.0%), file cabinet (26.0%), 40 drums of chlorine (20%), 4 spring construction tools

(29%) and 2 electric generators (50%). The remaining items are expected to be procured in the

final quarter of COWASH Phase II.

Table 13: Materials procured in Amhara region during the First 9 Months of 2008 EFY

Annual3rd

QuarterCumulative

3rd

QuarterCumulative

1 Desktop Computer with UPS No. 2 2 1 1 12,000 RSU staff

2 Laptop Computer No. 4 4 4 4 62,681 Woreda Water Offices

3 Printer No. 1 1 1 1 6,697 Health Bureau

4 Photocopy Machine No. 1 1 1 1 34,000

Horro Woreda Water

Office

5 LCD Projector No. 2 2 2 2 31,081 Woreda Water Offices

6 Scanner No. 1 1 1 9,500 RSU staff

7 File cabinet No. 13 13 5 5 19,200 Woreda Water Offices

8 Small diameter mold No. 6 6 - -

9 Chain block No. 2 2 1 1 17,000

Dire Inchini Woreda

Water Office

10 Artisan tools Set 50 50 25 25 28,798 Woreda Water Offices

11 Vehicle No. 1 1 1 1,935,000

Water, Mines and

Energy Bureau

12 Spring Construction Equipment Set 2 2 - -

13 Water Quality Test Kit with reagentsNo. 8 8 - -

14 Dewatering Pump No. 7 7 - -

15 Hand held GPS No. 4 4 1 1 5,200

Horro Woreda Water

Office

16 Furniture Set 1 1 1 1 24,000 RSU staff

2,185,157

Total Cost

(in Birr)

Beneficiary

Office(s)

Quantity Planned

S/N

Total

Material or Equipment Unit

Quantity Procured

Annual3rd

QuarterCumulative

3rd

QuarterCumulative

1 Laptop Computer No. 10 10 10 2 2 Woreda Water Offices

2 File Cabinet No. 27 27 4 7 Woreda Water Offices

3 Motorbike No. 54 54 Woreda Sector offices

4 Chlorine Drum  40 40 8 8 Woreda Water Offices

5  Spring construction tools  Set 14 14 4 4 Woreda Water Offices

6  Water quality test reagent No. 11 11

7 Electric generator No. 4 4 2 2 Woreda Water Offices

8 Handheld GPS No. 40 40

-

Total

Cost

(in Birr)

Beneficiary Office(s)S/N

Total

Material or Equipment Unit

Quantity ProcuredQuantity Planned

Page 32: COMMUNITY-LED ACCELERATED WASH (COWASH) PROJECT€¦ · 1 EXECUTIVE SUMMARY ... STRENGTHENING THE FEDERAL CAPACITY TO IMPLEMENT COMMUNITY MANAGED PROJECTS ALONGSIDE WITH A SUPPORT

26

5.1.2.7.3 Procurements done in Tigray Region

Only few items (8) were planned to be procured in Tigray region in 2008 EFY. This is due to the

fact that many of the items required for the implementation of the project activities had been

procured in the previous fiscal years. Nonetheless, only 2 vehicles were procured in the reporting

period. The two vehicles were procured with an estimated cost of Birr 3.96 million. The planned

items will be procured in the last quarter of the fiscal year as purchase requests have been

submitted to finance offices responsible for procurement of items.

Table 14: Materials procured in Tigray region during the First 9 Months of 2008 EFY

Annual3rd

Quarter

cummu

lative

3rd

Quarter

cummul

ative

Total cost

(in Birr)

1 Desktop Computer with UPS No. 2 2

2 Laptop Computer No. 7 7

3 Printer No. 1 1

4 LCD Projector No. 2 2

5 Motorbike No. 18 18 18

6 Digital Camera No. 1 1

7 Water quality test kit No. 7 7

8 Vehicle No. 2 2 2 2 3,956,000

3,956,000

Beneficiary Office(s) of the

material procuredS/N

Total

Material or Equipment Unit

Quantity ProcuredQuantity Planned

5.1.2.7.4 Procurements done in SNNP Region

Nine types of office equipments, vehicle and construction materials were planned to be procured

in 2008 EFY. Very few number of items were planned to be procured as many of the sector offices

had procured much of the materials required for implementation of the project activities in the

previous implementation years. All of the procurements were planned to be undertaken in the

reporting period. Nonetheless, only three of the items planned (50.0%) have been procured in

the reporting period. The items procured are laptops (50.0%), photocopy machine (100.0%), and

field vehicle (50.0%). The procurement of the other items is expected to be completed in the last

quarter of the fiscal year.

Table 15: Materials procured in SNNP region during the First 9 Months of 2008 EFY

Annual3rd

Quarter

cummu

lative

3rd

Quarter

cummul

ative

Total cost

(in Birr)

1 Desktop Computer with UPS No. 4 4 4

2 Laptop Computer No. 6 6 6 3 3 46,332 Woreda and Zone Water Offices

3 Printer No. 2 2 2

4 Photocopy Machine No. 1 1 1 1 1 21,299 Hadiya Zone Water Office

5 Motorbike No. 1 1 1

6 File Cabinet No. 4 4 4

7 Water quality test kit Set 4 4 4

8 Spring construction tools No. 1 1 1

9 Field Vehicle No. 1 1 1

67,631

Beneficiary Office(s) of the

material procuredS/N

Total

Material or Equipment Unit

Quantity ProcuredQuantity Planned

5.1.2.7.5 Procurements done in BSG Region

Quite a lot of office equipments, construction materials and transportation facilities (43 types of

items) were planned in 2008 EFY. Many of the planned items were rolled over from the previous

fiscal year. All of the items were planned to be procured in the first six months of the fiscal year

so as to accelerate the construction process in the third quarter. As a result of the concerted

efforts exerted at all levels, majority of the items planned (88.4%) have been procured in the

reporting period with an outlay of Birr 22.64 million allocated from the GoF contribution. Among

the different items procured are 15 motorbikes(83.3%), 5 field vehicles(100.0%), 4 water quality

Page 33: COMMUNITY-LED ACCELERATED WASH (COWASH) PROJECT€¦ · 1 EXECUTIVE SUMMARY ... STRENGTHENING THE FEDERAL CAPACITY TO IMPLEMENT COMMUNITY MANAGED PROJECTS ALONGSIDE WITH A SUPPORT

27

test kits(100.0%), 13 large diameter molds(65.0%), 10 small diameter molds(48.0%), 11 chain

blocks(55.0%), 71 sets of artisan hand tools(92.0%) and communication materials (wireless

mikes, IT toolkits, TV, etc.). The motorbikes, vehicles and water quality test kits were procured

with a total cost of Birr 1.73 million, Birr 5.99 million and 1.34 million, respectively. The items

procured especially the transportation facilities are believed to mitigate the transportation

problems of the project woredas and zones thereby speeding up the slow process of project

implementation in the region.

Table 16: Materials procured in BSG region during the First 9 Months of 2008 EFY

Annual3rd

Quarter

cummu

lative

3rd

Quarter

cumm

ulativ

e

Total cost

(in Birr)

1 Desktop Computer with UPS No. 13 13 6 9 99,531 Zone & Woreda Offices

2 External Hard Disk No 4 - 4 2 7 20,880 RSU&BOWR

3 Flash disk No 20 20 11 25 28,797 Woreda Water Offices

4 Motorbike No 18 18 - 15 1,725,000 Four Woredas

5 Laptop Computer No. 7 7 8 11 246,044 Zone &Regional sector offices &

RSU

6 Laptop bag No 9 9 2 11 6,279 Woreda and Zone Water Offices

7 Printer No. 8 8 8 9 77,134 Zone & Regional Sector offices

8 Photocopy Machine No. 8 8 1 1 32,700 RSU

9 Fax machine No. 4 4 1 3 67,148 Zonal sector offices

10 E-VDO No. 5 - 5 - 5 6,950 RSU& Coordinator

11 LCD Projector No. 4 4 3 4 56,119 Woreda & Zone sector offices &RSU

12 Scanner No. 3 - 3 3 4 41,113 Zone & Regional Sector offices

13 Digital Camera without video No. 15 15 6 9 27,938 Regional & Zone sector offices &

RSU14 Digital Camera with video No. 1 1 - -

15 Giant Stapler No. 4 - 4 1 540 Assosa ZOW

16 Small stapler No. 5 - 5 1 127 Assosa ZOW

17 Remote sensor for LCD No. 2 2 1 1 -

18 WiFI procurement and installationNo. 1 1 - - -

19 Binding Machine No. 8 - 8 3 7 25,836 RSU & Zone Sector Offices

20White board and rolled sheet

for LCDNo. 1 1 - - -

21 Safety shoes No. 5 5 - - -

22 Vehicle tyre No. 5

23 File cabinet No. 12 12 3 3 34,554 Zone & Woreda Offices

24 Chair and table No 7 - 7 9 12 13,939 Assosa Zone sector offices

25 Water quality test kit with reagentNo. 4 - 4 4 13,406,367 Woreda Water Offices

26 Office furniture LS 18 18 13 13 83,480 BoE & Kamashi zone sector offices

27 Stabilizer & UPS No. 21 21 6 14 18,336 Woreda & Zone sector offics & RSU

28 Hand held GPS No 9 9 5 7 28,416 Zone sector offices & RSU

29 Large diameter mould No. 20 20 7 13 187,130 Bambassi & Belo Woreda Water

Offices30 Small diameter mould No. 21 21 6 10 122,280 Bambassi & Belo Woreda Water

Offices

31 Chain blocks No. 20 20 6 11 66,752Three woredas water offices

(Bambasi, Belo & Oda)

32 Artisan tools Set 77 77 46 71 84,448 Four woredas water offices

33Equipment for spring

development Set

5 5 2 3 25,547Four woredas water offices

34 Hand glove for experts No. 9 9 - - -

35 Submersible pump &

GeneratorNo. 2 2 - - -

36Generator for running

computer when power off No. 1 1 1 1 39,000 Oda Water Office

37 Vehicle rolled from 2007EFY No. 5 5 5 5,991,697 RSU& 4 Woredas

38 Wireless phone No. 2 2 - 1 1,198 RSU

39 Wireless Mike with stand & tripodNo. 1 1 1 1 42,000 Bureau of Water

40 IT Tool Kit & Camera AccessoriesNo 1 1 1 1 20,505 Bureau of Water

41 32'' Flat Screen TV No 1 1 8,800 Bureau of Water

42 Paper perforator No. 2 2 - 2 340 RSU

43 Barrel and Mouth No. - - - 8 8 7,285 Agalometi Woreda Water Office

22,644,210

Beneficiary Office(s) of the

material procuredS/N

Total

Material or Equipment Unit

Quantity ProcuredQuantity Planned

In all, the procurement of planned construction materials and office equipments in the regions

was delayed due to delay in the approval of 2008 EFY annual plans by Regional WaSH Steering

Committee (RWSC) in the respective regions of the project. The low procurement performance

shows that much effort needs to be exerted in the third quarter to procure many of the planned

materials before the end of COWASH Phase II.

Page 34: COMMUNITY-LED ACCELERATED WASH (COWASH) PROJECT€¦ · 1 EXECUTIVE SUMMARY ... STRENGTHENING THE FEDERAL CAPACITY TO IMPLEMENT COMMUNITY MANAGED PROJECTS ALONGSIDE WITH A SUPPORT

28

5.2 RESULT 2 OF COMPONENT 2: FINANCIAL AND PROCUREMENT SERVICES

DELIVERED FOR CMP INTERVENTION AT ALL LEVELS IN THE SELECTED

REGIONS

5.2.1 Output 1: Flow of Funds for CMPs Functional

Some indicators are set to measure the achievement of the output, viz., 1) number of fund

transfer requests done to the financier; 2) number of BoFED audit reports produced

(disaggregated by regions); 3) amount of funds transferred to WASHCOs and 4) amount of funds

settled by WASHCOs.

A number of activities were planned in the regions to achieve this output. According to the

funding agreements made between the beneficiary regional Finance Bureaus and Embassy of

Finland, a COWASH region is expected to submit four fund transfer requests to the Embassy of

Finland per year. Each project region was expected to submit three fund transfer requests in the

first nine months of the fiscal year. Consequently, six fund transfer requests have been submitted

to Embassy of Finland in the first nine months. This accounts 40.0% of the transfer requests

expected in the reporting period. All regions except SNNPR have requested only once whereas

SNNPR requested twice in the reporting period. All of the regions didn’t request funds for the first

quarter as they had some leftover funds from 2007 EFY to cover the expenses in the quarter. The

delay in the approval of the 2008 EFY annual plan has delayed the timely submission of fund

requests.

Project regions are expected to audit the project fund utilization every year and prepare audit

reports. The auditing of the 2007 EFY fund utilization was expected to be conducted in all regions

in the reporting period. However, no region has submitted audit report of 2007 EFY to the

Embassy of Finland. The auditing of 2007 EFY fund utilization is underway in the regions and

many of them are expected to submit their audit reports to Embassy of Finland in the last quarter

of the fiscal year.

The data on investment fund transfer and utilization by WASHCOs is difficult to report within the

fiscal year where activities are on-going. Complete information on investment fund transferred to,

via MFIs, and amount settled by WASHCOs in each region will be reported in the annual report of

the project.

5.2.2 Output 2: Linkages Created with Private Sector in the Supply of Materials,

Equipment, Tools and Services

Number of new artisans trained by COWASH for WASH facility construction in the woredas

(disaggregated by sex) and number of awareness raising workshops organized for the private

sector are set to measure the achievement of the output.

Usually, some activities are included in the annual plans of regions and woredas to create linkage

with the private sector at the regional, zonal and woreda levels. The major ones are: training of

artisans; organizing awareness raising workshops to the private sector (pump, spare parts and

construction materials suppliers) on the availability of market opportunities; carrying out market

surveys in the Woredas; and informing communities on the prices of construction materials,

equipment, tools and services based on market surveys made in the woredas.

However, while some artisan trainings have been undertaken in some woredas, regional reports

reveal that no workshop has been conducted at all levels of the project regions. In fact, this

Page 35: COMMUNITY-LED ACCELERATED WASH (COWASH) PROJECT€¦ · 1 EXECUTIVE SUMMARY ... STRENGTHENING THE FEDERAL CAPACITY TO IMPLEMENT COMMUNITY MANAGED PROJECTS ALONGSIDE WITH A SUPPORT

29

activity has not been implemented effectively in almost all of the project regions over the

implementation periods of the project.

5.3 RESULT 3 OF COMPONENT 2: SUSTAINABLE COMMUNITY AND

INSTITUTIONAL ACCESS TO SAFE WATER, SANITATION AND HYGIENE IN

THE TARGET WOREDAS INCREASED

5.3.1 Output 1: Access to Improved Water Sources for Communities and Institutions

Increased

Three indicators are set to measure the achievement of the output. These are, a) number of new

CMP applications submitted to WWT(disaggregated by communal and institutional); b) number of

new CMP applications approved by WWT (disaggregated by communal and institutional); and c)

number of new water schemes constructed (disaggregated by communal and institutional).

In 2008 EFY, a total of 2,421 new WPs constructions (including those rolled over from 2007 EFY)

were planned to be undertaken in the five project regions. Of these, 2,049 are for communities

and the remaining 372 are for institutions (227 for schools and 145 for health facilities). Hence,

at least 2,421 applications are expected to be submitted by communities and institutions and

approved by WWTs in the fiscal year.

Table 17: Number of New Water Points Planned and Constructed in 2008 EFY

Community Institutional Total Community Institutional Total

Amhara 1,261 225 1,486 642 10 652 43.9 106,592

Tigray 194 34 228 0 0 0 0.0 -

SNNPR 225 20 245 72 8 80 32.7 20,015

Oromia 289 42 331 13 0 13 3.9 2,060

BSGR 80 51 131 18 2 20 15.3 6,519

Total 2,049 372 2,421 745 20 765 31.6 135,186

No. of WPs Planned to be

Constructed in 2008 EFYProject

Region

No. of WPs Constructed in

9 Months) Achieve

ment

(%)

Actual No. of

People Using

the Community

WPs

Constructed

Cognizant of the fact that the first six months are characterized by a rainy season and harvesting

season in majority of the project woredas, there were no many applications submitted and

construction activities carried out during the first half of the reporting period. The delay in the

preparation and approval of the 2008 EFY has also delayed the promotions and construction of

facilities in the project kebeles. Anyhow, the performance of regions in generating demand for

water supply and constructions completed in the first nine months presented below.

The five project regions managed to construct 765 water points (745 community, 17 school and 3

health facility) in the first nine months of the fiscal year. This accounts about 31.6% of the annual

plan. The performance is very low compared with the previous fiscal years and much needs to be

done in the remaining quarter of the fiscal year. The community water pints are benefitting more

than 135, 186 rural people of the project woredas. Over 8,168 students and teachers and 93

health staff and some clients of the health facilities are benefitting from the institutional water

points constructed with the support of COWASH through the CMP approach.

Page 36: COMMUNITY-LED ACCELERATED WASH (COWASH) PROJECT€¦ · 1 EXECUTIVE SUMMARY ... STRENGTHENING THE FEDERAL CAPACITY TO IMPLEMENT COMMUNITY MANAGED PROJECTS ALONGSIDE WITH A SUPPORT

30

Fig.1 Number of WPs Planned and Constructed in the 9 Months of 2008 EFY

1,486

228 245331

131

652

080

13 2043.90.0 32.7 3.9 15.3

0

200

400

600

800

1,000

1,200

1,400

Amhara Tigray SNNPR Oromia BSGR

Project Region

Planned (2008 EFY)

Constructed (9 Months)

% Constructed

The performances of the five regions in the first 9 months of the fiscal year are presented below.

5.3.1.1 Water supply schemes planned and constructed in Amhara Region

As indicated in Table 17 above, the 40 Amhara woredas planned to construct 1,486 WPs – 1,261

by communities and 225 by institutions (141 schools and 84 health facilities). As the country is

now starting the 2nd growth and transformation plan (GTP II), the construction of these water

points are believed to contribute for the attainment of GTP II/WASH targets of the project

woredas.

Consequently, promotions have been made in the reporting period in the CMP kebeles of Amhara

woredas with the trained woreda staff. As a result of the promotions made, more applications

(2,525) than planned (1,486) have been submitted to WWTs (Table 18). Of this applications,

2,464 (97.6%) were appraised on the desk by the trained woreda appraisal team. Field level

appraisal has been made on 2,360 (96.0%) of the desk appraised applications. Accordingly, some

1,909 (81.0%) of the field appraised were approved by WWTs.

Table 18: Applications submitted, appraisals made and applications approved in Amhara Region in

the First 9 Months of 2008 EFY

<50% >50% Total

A. Community Water Points -

HDW with RP - - - - - - - - - HDW 860 1,751 1,709 1,616 1,303 482 621 200 821 SPD 379 570 558 552 427 255 132 40 172 - SW 14 14 14 14 14 5 8 1 9 - DW - - - - - - - - - - RWH - - - - - - - - - RPS from SPD 8 28 28 28 28 9 12 7 19 - RPS from DW - - - - - - - - - - Subtotal 1,261 2,363 2,309 2,210 1,772 751 773 248 1,021 -

B. Institutional Water Points

B.1 School Water Points

HDW with RP - - - - - - - - -

HDW 116 104 97 92 82 19 40 23 63 -

SPD 18 21 21 21 18 4 9 5 14 -

SW - - - - - - - - -

DW - - - - - - - - -

RWH - - - - - - - - -

RPS from SPD 7 5 5 5 5 2 3 - 3 RPS from DW - - - - - - - - - Subtotal 141 130 123 118 105 25 52 28 80 -

B.2 Health Institutions Water Points

HDW with RP - - - - - - - - - -

HDW 68 28 28 28 28 5 16 8 24 -

SPD 10 3 3 3 3 - 3 - 3 -

SW - - - - - - - - - -

DW - - - - - - - - - -

RWH - - - - - - - - - -

RPS from SPD 6 1 1 1 1 - 1 - 1 RPS from DW - - - - - - - - - Subtotal 84 32 32 32 32 5 20 8 28 -

Total 1,486 2,525 2,464 2,360 1,909 781 845 284 1,129 -

No. of WPs

Not Started

Construction

No. of WPs under

construction

No. of WPs

Abandoned

(could not

be

constructed)

Type of Water

Point(WP)

No. of

Planned

WPs

No. of WPs

Applications

made

No. of WPs

Applications

Desk

Appraised

No. of WPs

Application

Field

Appraised

No. of WPs

Applications

Approved by

WWT

Page 37: COMMUNITY-LED ACCELERATED WASH (COWASH) PROJECT€¦ · 1 EXECUTIVE SUMMARY ... STRENGTHENING THE FEDERAL CAPACITY TO IMPLEMENT COMMUNITY MANAGED PROJECTS ALONGSIDE WITH A SUPPORT

31

Unlike the previous fiscal years, less than half of the planned water supply schemes (43.8%) have

been completed in the reporting period. It was managed to construct only 652 water supply

schemes (642 community and 10 institutional) in the project woredas in the reporting period.

More than 106,592 rural people, 3,359 students and teachers and 33 health staff and some

clients of the health facilities have benefitted from the water supply schemes constructed through

the CMP approach with the support of the project.

Table 19: New Water Points Constructed in Amhara Region in the First 9 Months of 2008 EFY

5.3.1.2 Water supply schemes planned and constructed in Tigray Region

In Tigray region, a total of 228 WPs (194 by communities and 34 by institutions-23 schools and

11 health facilities) are planned to be constructed, through the CMP approach, in the 7 woredas of

the region. The construction of these water points will contribute highly to attainment of the GTP

II/WASH targets of the woredas.

Demand creation promotions were conducted in the kebeles in the first half of the fiscal year. As

a result, 207 applications (189 for communities and 15 for schools and 3 for health facilities),

accounting 91.0% of the annual plan, were submitted to WWTs of the project woredas. Among

these, 182 (87.9%) were desk appraised and 118 of those desk appraised (64.8%) were

appraised at the field level by the woreda appraisal team. Nonetheless, only 39 (33.1%) of the

projects appraised at the field level have been approved in the reporting period. This shows that

much has not been done in the approval process and construction of water points planned for the

fiscal year. The very low performance of the region necessitates extra effort to attain the annual

targets in the last quarter of the fiscal year.

3rd

QuarterCumulative Annual

3rd

QuarterCumulative

A. Community Water PointsHDW with RP - - - - - - -

HDW 347 352 860 430 434 67,722 67,722

SPD 149 151 379 196 198 36,472 36,472

SW 14 17 14 - 3 1,683 1,683

DW - - - - - - -

RWH - - - - - - -

SPD-RPS 3 3 8 7 7 715 715

DW-RPS - - - - - - -

Subtotal 513 523 1,261 633 642 106,592 106,592

B. Institutional Water Points

B.1 School Water Points

HDW with RP - - - - - -

HDW 67 67 116 5 5 2,185

SPD 10 10 18 2 2 480

SW - - - - - -

DW - - - - - -

RWH - - - - - -

SPD-RPS 7 7 7 2 2 694

DW-RPS - - - - - -

Subtotal 84 84 141 9 9 3,359 -

B.2 Health Institutions Water Points -

HDW with RP - - - - - -

HDW 47 47 68 1 1 33

SPD 5 5 10 - - -

SW - - - - - -

DW - - - - - -

RWH - - - - - -

SPD-RPS 4 4 6 - - -

DW-RPS - - - - - -

Subtotal 56 56 84 1 1 33 -

Total 653 663 1,486 643 652

Type of Water Point(WP)

Number of WPs

Construction

Completed

Actual No

of People

Using the

Completed

WPs

No of People

having access

to the

Completed WPs

within 1.5KM

radius of the

WPs

Number of WPs planned to be

constructed

Page 38: COMMUNITY-LED ACCELERATED WASH (COWASH) PROJECT€¦ · 1 EXECUTIVE SUMMARY ... STRENGTHENING THE FEDERAL CAPACITY TO IMPLEMENT COMMUNITY MANAGED PROJECTS ALONGSIDE WITH A SUPPORT

32

Table 20: Applications submitted, appraisals made and applications approved in Tigray Region in

the First 9 Months of 2008 EFY

<50% >50% Total

A. Community Water Points -

HDW with RP - - - - - - - - - HDW 82 67 62 54 14 - - - - SPD 50 59 55 51 25 - - - SW 56 62 47 8 - - - - DW 4 1 1 - - - - - RWH - - - - - - - - RPS from SPD - - - - - - - - RPS from DW 2 - - - - - - - - Subtotal 194 189 165 113 39 - - - - -

B. Institutional Water Points

B.1 School Water Points

HDW with RP - - - - - - - - HDW 4 3 2 2 - - - SPD 1 2 2 2 - - - - SW 11 10 10 - - - - - DW - - - - - - - - RWH 7 - - - - - - - RPS from SPD - - - - - - - - - RPS from DW - - - - - - - Subtotal 23 15 14 4 - - - - -

B.2 Health Institutions Water Points

HDW with RP - - - - - - - - - HDW 4 1 1 1 - - - - - SPD 2 - - - - - - - - SW 5 2 2 - - - - - - DW - - - - - - - - - RWH - - - - - - - - - RPS from SPD - - - - - - - - RPS from DW - - - - - - Subtotal 11 3 3 1 - - - - - -

Total 228 207 182 118 39 - - -

No. of WPs

Not Started

Construction

No. of WPs under

construction

No. of WPs

Abandoned

(could not

be

constructed)

Type of Water

Point(WP)

No. of

Planned

WPs

No. of WPs

Applications

made

No. of WPs

Applications

Desk

Appraised

No. of WPs

Application

Field

Appraised

No. of WPs

Applications

Approved by

WWT

There has not been water point construction completed in Tigray in the reporting period. Anyhow,

the construction of 95 water points and 2 RPSs from borehole (Aliasa and Edagaberhe) is on

progress. The two RPSs benefit 7 communities, 2 schools and 1 health center each. While

Edagaberhe RPS is near completion (95.0%), some 34.7% of the construction of Aliasa RPSs has

been completed until end of the reporting period.

Table 21: New Water Points Constructed in Tigray Region in the First 9 Months of 2008 EFY

3rd

QuarterCumulative Annual

3rd

QuarterCumulative

A. Community Water PointsHDW with RP - - - - - - - HDW 60 60 82 - - - -

SPD 50 50 50 - - - -

SW 30 30 56 - - - -

DW 2 2 4 - - - -

RWH - - - - - - -

RPS from SPD - - - - - - -

RPS from DW 1 1 2 - - - -

Subtotal 143 143 194 - - - -

B. Institutional Water Points

B.1 School Water Points

HDW with RP - - - - -

HDW 4 4 4 - - -

SPD 1 1 1 - - -

SW 5 5 11 - - -

DW - - - - - -

RWH 7 7 7 - - -

RPS from SPD - - - - - -

RPS from DW - - - - - -

Subtotal 17 17 23 - - - -

B.2 Health Institutions Water Points -

HDW with RP - - - - - -

HDW 4 4 4 - - - 0

SPD 2 2 2 - - -

SW 3 3 5 - - -

DW - - - - - -

RWH - - - - - -

SPD-RPS - - - - - -

DW-RPS - - - - - -

Subtotal 9 9 11 - - - -

Total 169 169 228 - -

Type of Water Point(WP)

Number of WPs

Construction

Completed

Actual No

of People

Using the

Completed

WPs

No of People

having access

to the

Completed WPs

within 1.5KM

radius of the

WPs

Number of WPs planned to be

constructed

Page 39: COMMUNITY-LED ACCELERATED WASH (COWASH) PROJECT€¦ · 1 EXECUTIVE SUMMARY ... STRENGTHENING THE FEDERAL CAPACITY TO IMPLEMENT COMMUNITY MANAGED PROJECTS ALONGSIDE WITH A SUPPORT

33

5.3.1.3 Water supply schemes planned and constructed in SNNP Region

In SNNP region, a total of 245 WPs – 225 by communities and 20 by institutions (12 schools and

8 health facilities)- were planned to be constructed, through the CMP approach, in the 8 project

woredas of the region. The plan includes the point water supply schemes started in the preceding

fiscal year.

Trained woreda staff have been promoting CMP approach in the project kebeles. Following the

promotions, 93 applications (84 community and 9 institutional) 74 have been submitted to WWTs

of the project woredas. All of the applications have been appraised at the desk and field levels by

group of woreda staff trained on appraisal of projects. Majority of the appraised applications

(99.0%) were approved and financing agreements signed between WWTs and WASHCOs.

Table 22: Applications submitted, appraisals made and applications approved in SNNP Region in

First 9 Months of 2008 EFY

<50% >50% Total

A. Community Water Points -

HDW with RP - - - - - - - - - HDW 9 4 4 4 4 4 - - - 1 SPD 194 60 60 60 60 60 1 1 2 - SW 12 12 12 12 12 12 - 4 4 1 DW - - - - - - - RWH - - - - - - RPS from SPD 8 8 8 8 8 2 3 3 6 RPS from DW - - - - - - - - - Subtotal 223 84 84 84 84 78 4 8 12 2

B. Institutional Water Points

B.1 School Water Points

HDW with RP - - - - - - - - -

HDW 7 1 1 1 1 1 - 1 1 -

SPD - - - - - - - - -

SW 7 7 7 7 7 7 - - -

DW - - - - - - - - -

RWH - - - - - - - - -

RPS from SPD - RPS from DW - Subtotal 14 8 8 8 8 8 - 1 1 -

B.2 Health Institutions Water Points

HDW with RP - - - - - - - - - -

HDW 8 1 1 1 - - - - - -

SPD - - - - - - - - - -

SW - - - - - - - - - -

DW - - - - - - - - - -

RWH - - - - - - - - - -

RPS from SPD - - RPS from DW - - Subtotal 8 1 1 1 - - - - - -

Total 245 93 93 93 92 86 4 9 13 2

No. of WPs

Not Started

Construction

No. of WPs under

construction

No. of WPs

Abandoned

(could not

be

constructed)

Type of Water

Point(WP)

No. of

Planned

WPs

No. of WPs

Applications

made

No. of WPs

Applications

Desk

Appraised

No. of WPs

Application

Field

Appraised

No. of WPs

Applications

Approved by

WWT

Though the approval of the 2008 EFY plan had been delayed until end of the 2nd quarter, some

constructions started late in the preceding fiscal year have been undertaken in some SNNPR

project woredas. It was managed to construct 80 water points (72 communities, 6 schools and 2

health facilities) in the nine months of the fiscal year. Over 16,380 rural people started to benefit

from the 72 community water points. The school and health facility water points are benefitting

more than 3,809 students and teachers and 60 health staff and some clients of the institutions,

respectively.

Page 40: COMMUNITY-LED ACCELERATED WASH (COWASH) PROJECT€¦ · 1 EXECUTIVE SUMMARY ... STRENGTHENING THE FEDERAL CAPACITY TO IMPLEMENT COMMUNITY MANAGED PROJECTS ALONGSIDE WITH A SUPPORT

34

Table 23: New Water Points Constructed in SNNP Region in the First 9 Months of 2008 EFY

5.3.1.4 Water supply schemes planned and constructed in Oromia Region

The 12 project woredas of Oromia region planned to construct 331 water points (289 by

communities, 21 each by schools and health facilities) in the fiscal year.

Following the series of promotions made in the kebeles, communities, schools and health facilities

submitted a total of 379 applications (337 by rural communities, schools and health facilities 21

each) for WWTs for approval (Table 24). The demands of the community, schools and health

facilities exceeded the number of planned water points. Majority of the applications (89.7%) has

been appraised on the desk, and many of these desk appraised applications (95.6%) were

appraised at the field level and submitted to WWTs for approval. Consequently, 291 (90.0%) of

the field appraised projects were approved by WWTs and contractual agreement between

WASHCOs and WWTs have been signed.

Table 24: Applications submitted, appraisals made and applications approved in Oromia Region in

the First 9 Months of 2008 EFY

<50% >50% Total

A. Community Water Points -

HDW with RP - - - - - - - - - HDW 116 165 154 142 133 25 53 38 91 - SPD 139 126 115 112 92 46 13 10 23 - SW 28 41 30 30 27 16 5 7 12 - DW - - - - - - - - - - RWH - - - - - - - - - -

RPS from SPD - - - - - - - - - -

RPS from DW

Expansion 6 5 5 5 5 5 - - - -

Subtotal 289 337 304 289 257 92 71 55 126 -

B. Institutional Water Points

B.1 School Water Points

HDW with RP - - - - - - - - - -

HDW 14 12 11 11 10 3 4 2 6 -

SPD 3 2 2 2 2 1 1 - 1 -

SW 4 7 5 5 5 3 1 1 2 -

DW - - - - - - - - - -

RWH - - - - - - - - - -

RPS from SPD - - - - - - - - - RPS from DW - - - - - - - - - Subtotal 21 21 18 18 17 7 6 3 9 -

B.2 Health Institutions Water Points

HDW with RP - - - - - - - - - -

HDW 14 12 11 11 10 3 4 2 6 -

SPD 3 2 2 2 2 1 1 - 1 -

SW 4 7 5 5 5 3 1 1 2 -

DW - - - - - - - - - -

RWH - - - - - - - - - -

RPS from SPD - - - - - - - - -

RPS from DW - - - - - - - - -

Subtotal 21 21 18 18 17 7 6 3 9 -

Total 331 379 340 325 291 106 83 61 144 -

No. of WPs

Not Started

Construction

No. of WPs under

construction

No. of WPs

Abandoned

(could not

be

constructed)

Type of Water

Point(WP)

No. of

Planned

WPs

No. of WPs

Applications

made

No. of WPs

Applications

Desk

Appraised

No. of WPs

Application

Field

Appraised

No. of WPs

Applications

Approved by

WWT

3rd

QuarterCumulative Annual

3rd

QuarterCumulative

A. Community Water PointsHDW with RP - - - - - - -

HDW 7 9 9 - - - -

SPD 79 123 194 43 61 14,217 11,453

SW 10 14 14 - 4 1,370 1,151

DW - - - - - - -

RWH - - - - - - -

SPD-RPS 2 6 8 7 7 4,428 3,776

DW-RPS - - - - - - -

Subtotal 98 152 225 50 72 20,015 16,380

B. Institutional Water Points

B.1 School Water Points

HDW with RP - - - - - -

HDW 3 7 7 - 2 432

SPD - - - 1 3 2,208

SW 5 5 5 - 1 1,169

DW - - - - - -

RWH - - - - - -

SPD-RPS - - - - - -

DW-RPS - - - - - -

Subtotal 8 12 12 1 6 3,809 -

B.2 Health Institutions Water Points -

HDW with RP - - - - - -

HDW 5 8 8 1 2 60

SPD - - - - - -

SW - - - - - -

DW - - - - - -

RWH - - - - - -

SPD-RPS - - - - - -

DW-RPS - - - - - -

Subtotal 5 8 8 1 2 60 -

Total 111 172 245 52 80

Type of Water Point(WP)

Number of WPs

Construction

Completed

Actual No

of People

Using the

Completed

WPs

No of People

having access

to the

Completed WPs

within 1.5KM

radius of the

WPs

Number of WPs planned to be

constructed

Page 41: COMMUNITY-LED ACCELERATED WASH (COWASH) PROJECT€¦ · 1 EXECUTIVE SUMMARY ... STRENGTHENING THE FEDERAL CAPACITY TO IMPLEMENT COMMUNITY MANAGED PROJECTS ALONGSIDE WITH A SUPPORT

35

As indicated in Table 25 below, only 13 community water points (7 handdug wells and 6 on spot

springs) have been completed in the reporting period. This accounts 4.0% of the annual plan,

which is much lower than the performance of the region in the previous fiscal years. The newly

constructed water points are benefiting over 2,060 rural people of the project woredas.

Table 25: New Water Points Constructed in Oromia Region in the First 9 Months of 2008 EFY

5.3.1.5 Water supply schemes planned and constructed in BSG Region

COWASH started implementing CMP approach in 4 woredas of BSG region in 2007 EFY. There was

no construction completed last fiscal year. In 2008 EFY, the four project woredas planned to

construct a total of 131 water points – 80 for communities and 50 for institutions (29 for schools

and 21 for health facilities) in the woredas.

Thus, woreda appraisal teams have created demand for water supply in the project kebeles.

Following the promotions made in the project kebeles, applications equal to the annual plan have

been submitted to WWTs for approval. Accordingly, all of the applications submitted have been

appraised (at office and field levels) and approved for construction. All WASH Cos have signed

financial agreement with WWTs and many of them have concluded service agreements with

artisans to start construction of their water points.

Table 26: Applications submitted, appraisals made and applications approved in BSG Region in

the First 9 Months of 2008 EFY

<50% >50% Total

A. Community Water Points -

HDW with RP - - - - - - - - - HDW 69 69 69 69 69 24 43 2 45 - SPD 9 9 9 9 9 8 1 - 1 - SW 2 2 2 2 2 2 - - - - DW - - - - - - - - - - RWH - - - - - - - - - - RPS from SPD - - - - - - - - - - RPS from DW - - - - - - - - - - Subtotal 80 80 80 80 80 34 44 2 46 -

B. Institutional Water Points

B.1 School Water Points

HDW with RP - - - - - - - - - -

HDW 29 29 29 29 29 12 15 2 17 -

SPD - - - - - - - - - -

SW 1 1 1 1 1 1 - - - -

DW - - - - - - - - - -

RWH - - - - - - - - - -

SPD-RPS - - - - - - - - - DW-RPS - - - - - - - - - Subtotal 30 30 30 30 30 13 15 2 17 -

B.2 Health Institutions Water Points

HDW with RP - - - - - - - - - -

HDW 20 20 20 20 20 16 4 - 4 -

SPD - - - - - - - - - -

SW 1 1 1 1 1 1 - - - -

DW - - - - - - - - - -

RWH - - - - - - - - - -

SPD-RPS - - - - - - - - -

DW-RPS - - - - - - - - -

Subtotal 21 21 21 21 21 17 4 - 4 -

Total 131 131 131 131 131 64 63 4 67 -

No. of WPs

Not Started

Construction

No. of WPs under

construction

No. of WPs

Abandoned

(could not

be

constructed)

Type of Water

Point(WP)

No. of

Planned

WPs

No. of WPs

Applications

made

No. of WPs

Applications

Desk

Appraised

No. of WPs

Application

Field

Appraised

No. of WPs

Applications

Approved by

WWT

3rd

QuarterCumulative Annual

3rd

QuarterCumulative

A. Community Water PointsHDW with RP - - - - - - - HDW 7 14 116 7 7 1,004 1,004

SPD 66 71 139 6 6 1,056 1,056

SW 14 14 28 - - - -

DW - - - - - - -

RWH - - - - - -

RPS from SP - - - - - -

RPS from DW

Expansion 6 6 6 - - - -

Subtotal 93 105 289 13 13 2,060 2,060

B. Institutional Water Points

B.1 School Water Points

HDW with RP - - - - - -

HDW 7 7 14 - - -

SPD 1 1 3 - - -

SW 2 2 4 - - -

DW - - - - - -

RWH - - - - - -

RPS from SP - - - - - -

RPS from DW - - - - - -

Subtotal 10 10 21 - - - -

B.2 Health Institutions Water Points -

HDW with RP - - - - - -

HDW 7 7 14 - - -

SPD 1 1 3 - - -

SW 2 2 4 - - -

DW - - - - - -

RWH - - - - - -

RPS from SP - - - - - - 0

RPS from DW - - - - - -

Subtotal 10 10 21 - - - -

Total 113 125 331 13 13

Type of Water Point(WP)

Number of WPs

Construction

Completed

Actual No

of People

Using the

Completed

WPs

No of People

having access

to the

Completed WPs

within 1.5KM

radius of the

WPs

Number of WPs planned to be

constructed

Page 42: COMMUNITY-LED ACCELERATED WASH (COWASH) PROJECT€¦ · 1 EXECUTIVE SUMMARY ... STRENGTHENING THE FEDERAL CAPACITY TO IMPLEMENT COMMUNITY MANAGED PROJECTS ALONGSIDE WITH A SUPPORT

36

As shown in Table 27 below, there were 20 water points (18 community and 2 schools) were

completed in the reporting period in BSG region with the support of COWASH through the CMP

approach. The number of water points completed accounts only 15.3% of the annual plan of the

four woredas of BSG. Over 6,518 rural people of the woredas started benefitting from the 18

community water points. The low performance of the woredas shows that extra effort is required

to attain the annual targets of water supply construction in the woredas in the final quarter of

COWASH Phase II.

Table 27: New Water Points Constructed in BSG Region in the First 9 Months of 2008 EFY

Cumulative Number of Water Supply Schemes Constructed to Date:

Between 2004 EFY and end of 3rd quarter of 2008 EFY, on aggregate 8,926 water points have

been completed in the five regions with the support of COWASH through the CMP approach.

Majority of the water points (8,457) are for rural communities while the remaining is for schools

(391) and health facilities (78). In terms of geographic location, 7,109 were constructed in

Amhara, 396 in Tigray, 599 in SNNPR, 802 in Oromia and 20 in BSG region.

The community water points are benefitting over 1.96 million rural people in the project woredas

of the five project regions. The school and health facility water pints completed are benefitting

more than 0.17 million students, teachers and administrative staff and 14,400 health staff and

clients of the health facilities (Table 28).

3rd

QuarterCumulative Annual

3rd

QuarterCumulative

A. Community Water PointsHDW with RP - - - - - - - HDW 69 69 69 2 15 5,203 5,203

SPD 9 9 9 - 3 1,315 1,315

SW 2 2 2 - - - -

DW - - - - - - -

RWH - - - - - -

RPS from SP - - - - - -

RPS from DW - - - - - -

Subtotal 80 80 80 2 18 6,518 6,518

B. Institutional Water Points

B.1 School Water Points

HDW with RP - - - - - -

HDW 29 29 29 2 2 1,000

SPD - - - - - -

SW 1 1 1 - - -

DW - - - - - -

RWH - - - - - -

SPD-RPS - - - - - -

DW-RPS - - - - - -

Subtotal 30 30 30 2 2 1,000 -

B.2 Health Institutions Water Points -

HDW with RP - - - - - -

HDW 20 20 20 - - -

SPD - - - - - -

SW 1 1 1 - - -

DW - - - - - -

RWH - - - - - -

SPD-RPS - - - - - - 0

DW-RPS - - - - - -

Subtotal 21 21 21 - - - -

Total 131 131 131 4 20

Type of Water Point(WP)

Number of WPs

Construction

Completed

Actual No

of People

Using the

Completed

WPs

No of People

having access

to the

Completed WPs

within 1.5KM

radius of the

WPs

Number of WPs planned to be

constructed

Page 43: COMMUNITY-LED ACCELERATED WASH (COWASH) PROJECT€¦ · 1 EXECUTIVE SUMMARY ... STRENGTHENING THE FEDERAL CAPACITY TO IMPLEMENT COMMUNITY MANAGED PROJECTS ALONGSIDE WITH A SUPPORT

37

Table 28: Number of new (community, school and health institution) water points constructed until end of March 2016

HDW

with RPHDW SPD SW DW RWH

R P S

fro m

SP

R P S

fro m D WTotal

Population

Served

Popn.

having

Access

within

1.5km

HDW

with RPHDW SPD SW DW RWH

R P S

fro m SP

R P S

fro m D WTotal

Population

Served

Popn.

having

Access

within

1.5km

HDW

with

RP

HDW SPD SW DW RWHR P S

fro m

SP

R P S

fro m

D W

TotalPopulatio

n Served

Popn.

Having

Access

within

1.5Km of

Amhara 18 4,524 1,503 42 0 0 8 0 6,095 1,398,943 1,388,943 0 434 198 3 0 0 7 0 642 106,592 106,592 18 4,958 1,701 45 0 0 15 0 6,737 1,505,535 1,495,535

Tigray 0 172 131 68 0 0 0 0 371 107,589 107,589 0 0 0 0 0 0 0 0 0 0 0 0 172 131 68 0 0 0 0 371 107,589 107,589

SNNPR 0 13 481 0 0 0 2 0 496 182,210 158,029 0 0 61 4 0 0 7 0 72 20,015 16,389 0 13 542 4 0 0 9 0 568 202,225 174,418

Oromia 0 390 357 3 0 0 0 0 750 138,527 129,216 0 7 6 0 0 0 0 0 13 2,060 2,060 0 397 363 3 0 0 0 0 763 140,587 131,276

BSG 0 0 0 0 0 0 0 0 0 0 0 0 15 3 0 0 0 0 0 18 6,519 6,519 0 15 3 0 0 0 0 0 18 6,519 6,519

Subtotal 18 5,099 2,472 113 0 0 10 0 7,712 1,827,269 1,783,777 0 456 268 7 0 0 14 0 745 135,186 131,560 18 5,555 2,740 120 0 0 24 0 8,457 1,962,455 1,915,337

Amhara 0 285 18 0 0 0 0 0 303 126,383 0 5 2 0 0 0 2 0 9 3,359 0 290 20 0 0 0 2 0 312 129,742

Tigray 0 11 3 3 0 4 0 0 21 8,386 0 0 0 0 0 0 0 0 0 0 0 11 3 3 0 4 0 0 21 8,386

SNNPR 0 9 10 0 0 0 0 0 19 9,571 0 2 3 1 0 0 0 0 6 3,809 0 11 13 1 0 0 0 0 25 13,380

Oromia 0 23 6 0 0 0 2 0 31 16,629 0 0 0 0 0 0 0 0 0 0 0 23 6 0 0 0 2 0 31 16,629

BSG 0 0 0 0 0 0 0 0 0 0 0 2 0 0 0 0 0 0 2 1,000 0 2 0 0 0 0 0 0 2 1,000

Subtotal 0 328 37 3 0 4 2 0 374 160,969 0 9 5 1 0 0 2 0 17 8,168 0 337 42 4 0 4 4 0 391 169,137

Amhara 0 55 4 0 0 0 0 0 59 9,342 0 1 0 0 0 0 0 0 1 33 0 56 4 0 0 0 0 0 60 9,375

Tigray 0 1 2 1 0 0 0 0 4 125 0 0 0 0 0 0 0 0 0 0 0 1 2 1 0 0 0 0 4 125

SNNPR 0 3 1 0 0 0 0 0 4 513 0 2 0 0 0 0 0 0 2 60 0 5 1 0 0 0 0 0 6 573

Oromia 0 7 1 0 0 0 0 0 8 4,349 0 0 0 0 0 0 0 0 0 0 0 7 1 0 0 0 0 0 8 4,349

BSG 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

Subtotal 0 66 8 1 0 0 0 0 75 14,329 0 3 0 0 0 0 0 0 3 93 0 69 8 1 0 0 0 0 78 14,422

Amhara 18 4,864 1,525 42 0 0 8 0 6,457 0 440 200 3 0 0 9 0 652 18 5304 1725 45 0 0 17 0 7,109

Tigray 0 184 136 72 0 4 0 0 396 0 0 0 0 0 0 0 0 0 0 184 136 72 0 4 0 0 396

SNNPR 0 25 492 0 0 0 2 0 519 0 4 64 5 0 0 7 0 80 0 29 556 5 0 0 9 0 599

Oromia 0 420 364 3 0 0 2 0 789 0 7 6 0 0 0 0 0 13 0 427 370 3 0 0 2 0 802

BSG 0 0 0 0 0 0 0 0 0 0 17 3 0 0 0 0 0 20 0 17 3 0 0 0 0 0 20

Grandtotal 18 5,493 2,517 117 0 4 12 0 8,161 0 468 273 8 0 0 16 0 765 18 5,961 2,790 125 0 4 28 0 8,926

Cumulative

A. Community

B. School

c. Health Institution

Total Water Points (Community + School + Health Institution)

Region

Number of Water Points Constructed in COWASH Woredas

2004-2007 EFY 2008 EFY Q1+Q2+Q3

Note: HDW with RP - Hand dug well with Rope Pump; SW - Shallow Well

HDW - Hand dug well with Afridev pump; DW - Deep well

SPD - Spring On Spot; RWH - Roof water harvesting

Page 44: COMMUNITY-LED ACCELERATED WASH (COWASH) PROJECT€¦ · 1 EXECUTIVE SUMMARY ... STRENGTHENING THE FEDERAL CAPACITY TO IMPLEMENT COMMUNITY MANAGED PROJECTS ALONGSIDE WITH A SUPPORT

38

5.3.2 Output 2: Access to Sanitation for Household and Institutions Increased and

Hygiene Behavior Improved

Percentage of ODF kebeles in the COWASH intervention woredas (disaggregated by project

regions), number of new institutional latrines constructed (disaggregated by institutions) are

the indicators of measuring the achievement of the output.

With regards to freeing kebeles from open defecation, the five regions planned to make 431

rural kebeles ODF in 2008 EFY with the assistance of other WASH actors in the project

woredas. However, the performance cannot be known before the end of the fiscal year as the

process of ODF continues until end of the fiscal year. Hence, the ODF status of woredas is

being reported at the end of the fiscal year upon receipt of information from the regions.

The regional plans show that the attention to sanitation and hygiene has been improving over

the fiscal years. In 2008 EFY, 133 institutional latrines (75 for schools and 58 for health

institutions) were planned to be constructed in the five regions of the project. Among these, 30

were planned in Amhara, 14 in Tigray, 17 in SNNPR, 12 in Oromia and 60 in BSG region.

Consequently, after a series of promotions made in the kebeles, a total of 88 applications

(66.2% of the annual plan) have been submitted to Woreda WASH Teams. All of these

applications have been appraised both at the desk and field level. Accordingly, majority of the

field appraised applications (99.0%) were approved by WWTs.

Table 29: Number of Latrines applications submitted, appraisals made and applications

approved in the First 9 Months of 2008 EFY

< 50% > 5%

Amhara 16 16 16 16 16 13 0

Tigray 9 9 9 9 9 0 0

SNNPR 17 15 15 15 15 4 4

Oromia 8 8 8 8 8 0 0

BSG 25 7 7 7 7 1 0

Subtotal 75 55 55 55 55 18 4

Amhara 14 14 14 14 14 13 0

Tigray 5 5 5 5 4 0 0

SNNPR 0 0 0 0 0 0 0

Oromia 4 4 4 4 4 0 0

BSG 35 10 10 10 10 0 2

Subtotal 58 33 33 33 32 13 2

Total 133 88 88 88 87 31 6

A. Schools

B. Health Institutions

No. of

Latrines

Applications

Approved by

WWT

Type of

Institution/Region

No. of

Planned

Latrines

No. of

Latrines

Applications

made

No. of Latrines

Applications

Desk

Appraised

No. of

Latrines

Application

Field

Appraised

No. of Latrines

under

construction

Woredas have completed construction of 15 institutional latrines (12 for schools and 3 for

health facilities) in the first nine months of the fiscal year. In terms of region, majority of the

latrines were constructed in SNNPR (8) followed by Amhara (4) and Oromia region (3). These

school and health facility latrines are benefitting more than 10,104 students and teachers

(4,481 females) and 855 health staff and clients of the facilities (504 females), respectively.

Moreover, 37 latrines were under construction at the end of the reporting period in different

woredas of the project regions.

Page 45: COMMUNITY-LED ACCELERATED WASH (COWASH) PROJECT€¦ · 1 EXECUTIVE SUMMARY ... STRENGTHENING THE FEDERAL CAPACITY TO IMPLEMENT COMMUNITY MANAGED PROJECTS ALONGSIDE WITH A SUPPORT

39

Table 30: Number of Institutional Latrines Constructed in the First 9 Months of 2008 EFY

Annual3rd

QuarterCumulative

3rd

QuarterCumulative Male Female Total

A. School

Amhara 16 8 16 2 2 688 655 1,343

Tigray 9 9 9 - - - - -

SNNPR 17 12 12 1 8 3,858 3,132 6,990

Oromia 8 8 8 - 2 1,077 694 1,771

BSG 25 25 25 - - - - -

Subtotal 75 62 70 3 12 5,623 4,481 10,104

B. Health Institution

Amhara 14 8 14 2 2 43 40 83

Tigray 5 5 5 - - - - -

SNNPR - - - - - - - -

Oromia 4 4 4 - 1 308 464 772

BSG 35 35 35 - - - - -

Subtotal 58 52 58 2 3 351 504 855

Total 133 114 128 5 15 5,974 4,985 10,959

Region

No. of Latrines

Construction

Completed

Estimated No. of People

using the Completed

Latrines

No. of Latrines Planned to be

Constructed

On aggregate, 152 institutional latrines (87 for schools and 65 for health facilities) have been

built in the COWASH woredas through the CMP approach since the launching of COWASH

project in 2004 EFY. The facilities are benefitting more than 97,112 students and teachers and

3,002 health extension workers and some clients of the institutions (Table 31).

Table 31: Number of Institutional Latrines Constructed until end of March 30, 2016

M F T M F T M F T

Amhara 58 32,931 33,973 66,904 2 688 655 1,343 60 33,619 34,628 68,247

Tigray* 5 1,485 1,215 2,700 0 0 0 0 5 1,485 1,215 2,700

SNNPR 4 1,883 1,607 3,490 8 3,858 3,132 6,990 12 5,741 4,739 10,480

Oromia 8 5,785 8,129 13,914 2 1,077 694 1,771 10 6,862 8,823 15,685

BSG 0 0 0 0 0 0 0 0 0 0 0 0

Subtotal 75 42,084 44,924 87,008 12 5,623 4,481 10,104 87 47,707 49,405 97,112

Amhara 47 639 591 1,230 2 43 40 83 49 682 631 1,313

Tigray 10 51 85 136 0 0 0 0 10 51 85 136

SNNPR 0 0 0 0 0 0 0 0 0 0 0 0

Oromia 5 265 516 781 1 308 464 772 6 573 980 1,553

BSG 0 0 0 0 0 0 0 0 0 0 0 0

Subtotal 62 955 1,192 2,147 3 351 504 855 65 1,306 1,696 3,002

Amhara 105 33,570 34,564 68,134 4 731 695 1,426 109 34,301 35,259 69,560

Tigray 15 1,536 1,300 2,836 0 0 0 0 15 1,536 1,300 2,836

SNNPR 4 1,883 1,607 3,490 8 3,858 3,132 6,990 12 5,741 4,739 10,480

Oromia 13 6,050 8,645 14,695 3 1,385 1,158 2,543 16 7,435 9,803 17,238

BSG 0 0 0 0 0 0 0 0 0 0 0 0

Grandtotal 137 43,039 46,116 89,155 15 5,974 4,985 10,959 152 49,013 51,101 100,114

A. School

B. Health Institution

Total (School + Health Institution)

Number of Latrines Constructed in COWASH Woredas

2008 EFY Q1 +Q2+Q3 Cumulative

No. of

Latrines

Population Served No. of

Latrines

Population Served

2004-2007 EFY Region

No. of

Latrines

Population Served

Note: The school latrine construction in Tigray was not based on the standard (of 3 blocks) for a school. The regional performance report shows that the 20 school latrines completed in 2007 EFY are 1 block each for 3 schools, 2 blocks each for 13 schools and 3 blocks each for 4 schools.

Page 46: COMMUNITY-LED ACCELERATED WASH (COWASH) PROJECT€¦ · 1 EXECUTIVE SUMMARY ... STRENGTHENING THE FEDERAL CAPACITY TO IMPLEMENT COMMUNITY MANAGED PROJECTS ALONGSIDE WITH A SUPPORT

40

5.3.3 Output 3: Sustainability of Communal and Institutional Water Schemes in the

Targeted Woredas Strengthened

Three indicators are set to measure the achievement of the output. These are: i) number of

CMP schemes with trained pump attendants and caretakers (disaggregated by sex); ii) number

of water points rehabilitated (disaggregated by communal and institutional); and

iii) percentage of WASHCOs with more than 50% women members.

A number of activities were planned in the regions to attain the output. The data on schemes

with trained pump attendants and caretakers and WASHCOs with at least 50% female

members are reported at the end of the fiscal year. The progress of regions in rehabilitating

non-functional water points is presented as follows.

In this fiscal year, all the five project regions planned to rehabilitate community and

institutional non-functional water supply schemes. A total of 196 water points (119 community

and 77 institutional) were planned to be rehabilitated in 2008 EFY (Table 32).

Table 32: Water Points Planned and Rehabilitated in the first 9 Months of 2008 EFY

Community Institutional Total Community Institutional Total

Amhara 70 48 118 5 2 7 5.9 728

Tigray 7 5 12 0 0 0 0.0

SNNPR 6 3 9 3 0 3 33.3 661

Oromia 10 1 11 2 0 2 18.2 352

BSG 26 20 46 0 0 0 0.0

Total 119 77 196 10 2 12 6.1 1,741

Project

Region

No. of WPs Planned to be

Rehabilitated in 2008 EFY

No. of WPs Rehabilitated

in 9 Months Achieve

ment(%)

Actual No. of

People Using the

Community

Rehabilitated

WPs

The performance of the woredas in the rehabilitation of water points was very low in the

reporting period. In total, only 12 water points have been rehabilitated in the first nine months

of the fiscal year. This accounts only 6.1% of the annual plan. The rehabilitation activities were

made in some Amhara, SNNPR and Oromia woredas. The 10 rehabilitated community water

points are benefitting over 1,741 rural people of the woredas while the institutional water

points rehabilitated benefit more than 1,484 students and teachers and some 100 health

extension workers and clients of the health facilities.

On aggregate, 458 water points (445 community and 13 school) have been rehabilitated in the

project woredas since the launching of COWASH in 2004 EFY (Table 33). Majority of the

rehabilitated water points were in Amhara followed by SNNPR, Tigray and Oromia. There were

no water points rehabilitated in BSG.

Page 47: COMMUNITY-LED ACCELERATED WASH (COWASH) PROJECT€¦ · 1 EXECUTIVE SUMMARY ... STRENGTHENING THE FEDERAL CAPACITY TO IMPLEMENT COMMUNITY MANAGED PROJECTS ALONGSIDE WITH A SUPPORT

41

Table 33: Number of Water Points Rehabilitated until end of March 30, 2016

HDW

with

RP

HDW SPD SW DW RWH TotalPopulation

Served

HDW

with

RP

HDW SPD SW DW RWH TotalPopulatio

n Served

HDW

with

RP

HDW SPD SW DW RWH TotalPopulation

Served

Amhara 0 280 96 0 0 0 376 90,161 0 5 0 0 0 0 5 728 0 285 96 0 0 0 381 90,889

Tigray 0 18 5 0 0 0 23 5,250 0 0 0 0 0 0 0 0 18 5 0 0 0 23 5,250

SNNPR 0 10 22 0 0 0 32 13,195 0 0 3 0 0 0 3 661 0 10 22 0 0 0 32 13,856

Oromia 0 4 3 0 0 0 7 852 0 2 0 0 0 0 2 352 0 4 3 0 0 0 7 1,204

BSG 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

Subtotal 0 312 126 0 0 0 438 109,458 0 7 3 0 0 0 10 1,741 0 317 126 0 0 0 443 111,199

Amhara 0 8 1 0 0 0 9 2,394 0 1 0 0 0 0 1 1,484 0 9 1 0 0 0 10 3,878

Tigray 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

SNNPR 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

Oromia 0 2 0 0 0 0 2 1,234 0 0 0 0 0 0 0 0 2 0 0 0 0 2 1,234

BSG 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

Subtotal 0 10 1 0 0 0 11 3,628 0 1 0 0 0 0 1 1,484 0 11 1 0 0 0 12 5,112

Amhara 0 0 0 0 0 0 0 0 0 1 0 0 0 0 1 100 0 1 0 0 0 0 1 100

Tigray 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

SNNPR 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

Oromia 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

BSG 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

Subtotal 0 0 0 0 0 0 0 0 0 1 0 0 0 0 1 100 0 1 0 0 0 0 1 100

Amhara 0 288 97 0 0 0 385 0 7 0 0 0 0 7 0 295 97 0 0 0 392

Tigray 0 18 5 0 0 0 23 0 0 0 0 0 0 0 0 18 5 0 0 0 23

SNNPR 0 10 22 0 0 0 32 0 0 3 0 0 0 3 0 10 22 0 0 0 32

Oromia 0 6 3 0 0 0 9 0 2 0 0 0 0 2 0 6 3 0 0 0 9

BSG 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

Grandtotal 0 322 127 0 0 0 449 0 9 3 0 0 0 12 0 329 127 0 0 0 456

A. Community

B. School

c. Health Institution

Total Rehabilitated (Community + School + Health Institution)

2004-2007 EFY

Region

Number of Water Points Rehabilitated in COWASH Woredas

2008 EFY Q1 +Q2+Q3 Cumulative (2004 - 2008 EFY Q3)

Note: HDW with RP - Hand dug well with Rope Pump; SW - Shallow Well

HDW - Hand dug well with Afridev pump; DW - Deep well

SPD - Spring On Spot; RWH - Roof water harvesting

Page 48: COMMUNITY-LED ACCELERATED WASH (COWASH) PROJECT€¦ · 1 EXECUTIVE SUMMARY ... STRENGTHENING THE FEDERAL CAPACITY TO IMPLEMENT COMMUNITY MANAGED PROJECTS ALONGSIDE WITH A SUPPORT

42

5.3.4 Output 4: Potable Water Quality Ensured in Targeted Woredas

Number of water quality tests (post construction) made on CMP water schemes (new and

rehabilitations); number of chlorination made (post construction) on CMP water schemes (new and

rehabilitations) and number of CMP water schemes with Water Safety Plans are the indicators set to

measure the achievement of the output.

Numerous activities have been planned to attain this output. Though the project has been

attempting to build the capacity of the implementers and beneficiaries, the performance in this

regard is not encouraging and performances have not been reported in many of the project

woredas. This is mainly due to the lack of system in O&MM and lack of human and materials

capacity in many of the woredas.

COWASH has been trying its best in establishing systems and building the capacity of the woredas,

WASHCOs and kebele administrative structure to mitigate the problem of O&MM, water safety and

environmental protection. The project has procured Water Quality Test Kits for many of the

woredas in Amhara and SNNPR, O&MM manuals and Strategic Framework are being finalized, and

scheme management training provided to WASHCOs and woreda staff. Moreover, climate-risk

screening is made part of the field appraisal and Water Safety Planning (WSP) has been introduced

in some of the project woredas. Available data on water quality tests and chlorination are reported

at the end of every fiscal year.

Page 49: COMMUNITY-LED ACCELERATED WASH (COWASH) PROJECT€¦ · 1 EXECUTIVE SUMMARY ... STRENGTHENING THE FEDERAL CAPACITY TO IMPLEMENT COMMUNITY MANAGED PROJECTS ALONGSIDE WITH A SUPPORT

43

6 FINANCIAL PERFORMANCE

In this chapter, the financial utilization performance, in the reporting period of Component 1 (C-1)

and Component 2 (C-2) are elaborated.

6.1 COMPONENT 1, FEDERAL LEVEL

The COWASH expenditures started to build-up already during 2003 Ethiopian Fiscal Year (June

2011). The financial plan and usage of C-1 until the end of the reporting period (March 2016) are

presented as follows.

The total budget of Component 1 from the beginning of the COWASH (June 2011) to the end of

March 2016 was EUR 3,514,657. During the same period the C-1 expenditures have been EUR

3,503,532. This represents 99,7 % utilization rate. The quarter 3 budget of 2008 EFY was EUR

200,000 and the utilization in the same quarter was EUR 184,781. Accordingly the 2008 EFY 3rd

quarter utilization rate was 92,4 %. The savings were purposefully made in order to have enough

funds to pay all Phase II completion and remaining payments in the last quarter.

When compared the budget utilization to the COWASH Phase II budget the situation is as follows:

Component 1 budget of COWASH Phase II is EUR 1,513,547 (October 2015-June 2016)

Same budget used by March 2016 is EUR 1,286,686 (90 %) and the time used is also 90 %

The figure 2 below illustrates the total cumulative COWASH Component 1 budget and use from the

Beginning of COWASH to the end of December 2015.

Figure 2. Illustration of the C-1 Budget Utilization based on the 5 year budget period (2011-2016).

Ethiopian Fiscal Year (EFY) is for a period of July-June.

The Table 35a below provides more detailed information on the COWASH Component 1 budget

use. As can be seen from the table the total 5-year budget usage at the end of March 2016 is

94 %. The time spent from the 5 year project period is 95 %. Therefore the total 5 year budget

usage is in line.

-

1 000 000,00

2 000 000,00

3 000 000,00

4 000 000,00

EUR

O

COWASH Component 1 budget plan 2011-2016 Utilization May 2011-March 2016

Actual, Phase I Planned, Phase II Actual Phase II

End of Mar 2016 used 11,000 EUR less than planned (cumulative from

Page 50: COMMUNITY-LED ACCELERATED WASH (COWASH) PROJECT€¦ · 1 EXECUTIVE SUMMARY ... STRENGTHENING THE FEDERAL CAPACITY TO IMPLEMENT COMMUNITY MANAGED PROJECTS ALONGSIDE WITH A SUPPORT

44

The Phase II budget was revised as some budget lines were re-allocated without changing the

approved fee and total budget figures. The budget usage compared to revised Phase II budget

is as follows:

Fee component: 87 %

Reimbursable component: 81 %

Sector support component: 86 %

Total Phase II budget use 85 %

The time usage of Phase II is 86 %. According to this analysis the budget usage is in line

without major exceptions.

Table 35a: COWASH Component 1 budget follow-up

As a conclusion the total Component 1 budget will be used nearly 100 % by the end of Phase II

(June 30, 2016). Due to the shortage of Sector support budget COWASH sector support during

the last 3 months of the project has already been fixed and will be very limited. If savings can

be made in reimbursable and fee budget components, more sector support can then be then

provided or there is also a possibility to extent Phase II so that there would be no gap between

Phase II and III.

The use of Technical assistance in Component I of Phase II is illustrated in the table 35b below.

Table 35b: technical Assistance use in COWASH Component 1

This table clearly illustrates that the technical assistance use is in balance with the project

implementation. Six days out of the allocated 4 days for HRD Specialist will not be used in

Phase II and can therefore contribute for the possible extension of Phase II if needed.

Page 51: COMMUNITY-LED ACCELERATED WASH (COWASH) PROJECT€¦ · 1 EXECUTIVE SUMMARY ... STRENGTHENING THE FEDERAL CAPACITY TO IMPLEMENT COMMUNITY MANAGED PROJECTS ALONGSIDE WITH A SUPPORT

45

6.2 COMPONENT 2 FINANCIAL PERFORMANCE

The financial performance of Component 2 in the reporting period, disaggregated by project

regions, is presented hereunder.

6.2.1 Tigray Region

The funding arrangement in Tigray is governed by the funding agreement signed between the

Bureau of Plan and Finance of Tigray National Regional State and Embassy of Finland. All the

investment and some operational costs are covered by the Tigray National Regional State while the

(human and physical) capacity building fund is contributed from the Finnish Government (GoF). The

investment funds and capacity building funds are being channeled in different ways. All the

investment funds from the regional government are being channeled to the communities through

Dedebit Credit and Saving Institution (DECSI) with a commission of 5% while the capacity building

fund from the Finnish Government (GoF contribution) has been channeled through the government

financial structure as per the agreement.

An estimated amount of Birr 47.01 million (Birr 14.55 million from GoF and Birr 32.46 million from

GoE and) was allocated for 2008 EFY. Out of this, Birr 42.5 million (90.4%) was allocated for the

activities planned to be executed in the first nine months of the fiscal year.

Accordingly, some Birr 11.46 million (Birr 6.38 million from GoF and Birr 5.08 million from GoE) has

been utilized in the first nine months of the fiscal year (Table 36). This shows that only 27.0% of

the fund allocated for the reporting period has been utilized by all the beneficiaries of the project.

The low budget utilization is attributable to several factors. The main ones are: delay in the

approval of the annual plan, presence of competing activities in the woredas and low priority to

WASH activities.

Table 36: Fund allocated and Utilized in Tigray region in the First 9 Months of 2008 EFY

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19

Planned for

3rd Quarter

(14+17)

Utilized 3rd

Quarter

(15+18)

Planned for

3rd Quarter

Utilized 3rd

Quarter

Planned for 3rd

Quarter

Utilized 3rd

Quarter

GoF GoE Total (1+2) GoF GoE GoF+GoE GoF GoE GoF+GoE GoF + GoE GoF + GoE

Cumula

tive

(9/6)*

100

This

Quarter

(11/10

)*100

GoF GoF GoE GoE

INVESTM ENT

COST0 29,289,750 29,289,750 - 29,289,750.00 29,289,750 4,773,943.36 4,773,943.36 - - 16.3 #DIV/0! - - - -

PHYSICAL

CAPACITY

BUILDING COST7,843,000 0 7,843,000 7,843,000 - 7,843,000 3,987,600.01 - 3,987,600.01 - - 50.8 #DIV/0! - - - - -

HUM AN

CAPACITY

BUILDING COST3,958,111 0 3,958,111 3,308,860 3,308,860 1,201,561.53 - 1,201,561.53 1,455,159 976,514.52 36.3 67.1 1,455,159 976,514.52 67.1 - - -

OPERATIONAL

COST2,751,152 3,171,975 5,923,127 859,388 1,192,193 2,051,581 1,196,926.07 301,307.55 1,498,233.62 1,452,318 624,520.28 73.0 43.0 438,877 323,212.73 73.6 1,013,441 301,308 29.7

TOTAL 14,552,263 32,461,725 47,013,988 12,011,248 30,481,943 42,493,191 6,386,088 5,075,251 11,461,338.52 2,907,477 1,601,035 27.0 55.1 1,894,036 1,299,727.25 68.6 1,013,441 301,308 29.7

Total in Euro (1

Euro = 22 Birr) 661,466.50 1,475,532.95 2,136,999 545,965.82 1,385,542.86 1,931,508.68 290,276.71 230,693.22 520,969.93 132,158.03 72,774.31 27.0 55.1 86,092.53 59,078.51 68.6 46,065.50 13,695.8 29.7

Utilizatio

n (%)

(15/14)

*100

Utilization

(%)

(18/17)

*100

Category

Planned(Annual) Cumulative Planned Cumulative Utilized Utilization(%)

Cumulative funds received from sources (GoE & GoF) and transferred to and utilized by sector

offices to date in Tigray region are shown in Table 37 below.

Page 52: COMMUNITY-LED ACCELERATED WASH (COWASH) PROJECT€¦ · 1 EXECUTIVE SUMMARY ... STRENGTHENING THE FEDERAL CAPACITY TO IMPLEMENT COMMUNITY MANAGED PROJECTS ALONGSIDE WITH A SUPPORT

46

Table 37: Funds received, transferred and utilized in Tigray until end of March 30, 2016

Received

(%)

Transferred

(%)

GoF33,812,040.14 30,883,988.32 25,407,520.62 8,404,519.52 5,476,467.70 75.1 82.3

GoE50,789,264.91 50,789,264.91 35,906,388.57 14,882,876.34 14,882,876.34 70.7 70.7

Total 84,601,305.05 81,673,253.23 61,313,909.19 23,287,395.86 20,359,344.04 72.5 75.1

Usage from Budget

Source

Received

from Source

to date

Transferred to

Beneficiaries

to date

Utilized by

Beneficiaries

to date

Balance

from

Received

to date

Balance

from

Transferred

to date

As shown in Table 35 above, up until end of March 2016, Tigray region Bureau of Finance and Plan

(BoFP) received a total of Euro 1,419,191.77 (equivalent to about Birr 33,812,040.14) from the

Finland Government (GoF) and Birr 50,789,264.91 from the regional government for the

implementation of COWASH activities in the region. Out of this amount received, Birr 81.67 million

(96.5%) has been transferred to beneficiary sector offices until 30th March 2016. As a result,

72.5% of the amount transferred from Ministry of Foreign Affairs of Finland (MFA) or 75.1% of the

amount transferred to beneficiaries have been utilized for the project activities undertaken at all

levels in the region. The regional financial report shows that Euro 765,107.29 is left at MFA out of

the amount agreed for five years.

6.2.2 SNNP REGION

The funding arrangement in SNNPR is governed by the funding agreement signed between the

Bureau of Finance and Economic Development (BoFED) of Southern Nations Nationalities and

Peoples’ Regional State and Embassy of Finland (EoF). All the investment, some operational costs

and all the physical capacity building of the new woredas and zones and are covered by the SNNPR

while the (human and physical) capacity building fund for the old woredas, zones and regional

sector offices and all the human capacity building funds for the new woredas and zones is

contributed from the Finland Government. The investment and capacity building funds are being

channeled in different ways. All the investment funds from the regional government are being

channeled to the communities through Omo Microfinance Institute (OMFI) with a commission of 3%

while the capacity building fund from the regional state and Finnish Government has been

channeled through the government financial structure as per the funding agreement.

The project has allocated an estimated amount of Birr 27.57 million (Birr 12.35 million from GoF

and Birr 15.23 million from GoE) was allocated for 2008 EFY planned activities in SNNPR. Of this

amount, an estimated amount of Birr 25.6 million (Birr 11.25 million from GoF and Birr 14.35

million from GoE) was allocated for the first nine months of the fiscal year. This accounts about

92.8% of the annual budget of the project in the region.

The regional performance report shows that some 43.7% of the budget allocated for the reporting

period has been utilized. As shown in Table 38 below, about 41.0% of the GoF and 45.9% of the

GoE funds allocated for the reporting period have been utilized. The delay in the approval of the

2008 EFY budget and presence of competing activities in the woredas were cited as the main

reasons for the low fund utilization performance of the region.

Page 53: COMMUNITY-LED ACCELERATED WASH (COWASH) PROJECT€¦ · 1 EXECUTIVE SUMMARY ... STRENGTHENING THE FEDERAL CAPACITY TO IMPLEMENT COMMUNITY MANAGED PROJECTS ALONGSIDE WITH A SUPPORT

47

Table 38: Fund allocated and Utilized in SNNPR in the First 9 Months of 2008 EFY

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19

Planned for

3rd Quarter

(14 +17)

Utilized 3rd

Quarter

(15+18 )

Planned for

3rd Quarter

Utilized 3rd

Quarter

Planned for

3rd Quarter

Utilized 3rd

Quarter

GoF GoE Total (1+2 ) GoF GoE GoF+GoE GoF GoE GoF+GoE GoF + GoE GoF + GoE

Cumulat i

ve

( 9 / 6 ) *

10 0

1st

Quarter

(11/ 10 ) *

10 0

GoF GoF GoE GoE

INVESTM E

NT COST - 13,888,551 13,888,551 - 13,300,581 13,300,581 6,345,447 6,345,447 6,723,515 2,536,587 47.7 37.7 # DIV/0! 6,723,515 2,536,587 37.7

PHYSICAL

CAPACITY

BUILDING

COST

1,012,000 15,000 1,027,000 1,062,000 15,000 1,077,000 238,668 - 238,668 - 75,128 22.2 # DIV/0! - 75,128 # DIV/0! - - # DIV/0!

HUM AN

CAPACITY

BUILDING

COST

8,756,848 - 8,756,848 8,183,398 - 8,183,398 2,858,188 2,858,188 2,936,857 1,171,759 34.9 39.9 2,936,857 1,171,759 39.9 - # DIV/0!

OPERATIO

NAL COST 2,578,252 1,323,600 3,901,852 1,999,708 1,033,878 3,033,586 1,508,095 232,812 1,740,907 1,031,883 749,878 57.4 72.7 659,363 613,905 93.1 372,520 135,973 36.5

TOTAL 12,347,100 15,227,151 27,574,251 11,245,106 14,349,459 25,594,565 4,604,951 6,578,259 11,183,210 10,692,255 4,533,352 43.69 42.40 3,596,220 1,860,792 51.74 7,096,035 2,672,560 37.66

Total in

Euro (1 Euro

= 22 Birr)

561,232 692,143 1,253,375 511,141 652,248 1,163,389 209,316 299,012 508,328 486,012 206,061 43.694 42.398 163,465 84,581 51.743 322,547 121,480 37.66

Utilizat ion (%)

( 18 / 17) *10

0

Category

Planned(Annual) Cumulat ive Planned Cumulat ive Utilized Utilizat ion(%)Utilizat io

n (%)

( 15/ 16 )

*10 0

Table 39 below presents total funds received from sources (GoE & GoF) and transferred to and

utilized by sector offices to date in SNNPR.

Table 39: Funds received, transferred and utilized in SNNPR until end of March 2016

Received

(%)

Transferred

(%)

GoF31,940,482.97 31,907,947.26 25,839,463.24 6,101,019.73 6,068,484.02 80.9 81.0

GoE48,231,139.00 47,663,610.14 31,389,910.19 16,841,228.81 16,273,699.95 65.1 65.9

Total 80,171,621.97 79,571,557.40 57,229,373.43 22,942,248.54 22,342,183.97 71.4 71.9

Usage from Budget

Source

Received from

Source to date

Transferred to

Beneficiaries

to date

Utilized by

Beneficiaries to

date

Balance from

Received to

date

Balance from

Transferred

to date

Until end of March 2016, SNNPR BoFED received a total of Euro 1,337,454 (equivalent to about Birr

31,940,482.97) from the Finnish Government and Birr 48, 231,139 from the regional government,

project zones and woredas. Out of this, approximately Birr 79.57 million (Birr 31.91 million from

GoF and Birr 47.66 million from GoE) or 99.3 % of the amount received has been transferred to

beneficiary offices. Consequently, 71.4% of the received or 72.0% of the transferred has been

utilized until 30th March 2016. A total of Euro 408,630 is left from the GoF funds agreed for 5 years.

6.2.3 Oromia Region

The funding arrangement in Oromia is governed by the funding agreement signed between the

Bureau of Finance and Economic Development of Oromia National Regional State and Embassy of

Finland. All the investment and some operational costs are covered by Oromia region while all the

(human and physical) capacity building fund is contributed from the Finnish Government. Funds are

being channeled in two ways: all the investment funds from the regional government are being

channeled to the communities through Oromo Credit and Saving Share Company (OCSSCo) with a

commission of 4% while the capacity building funds from the Finnish Government has been

channeled through the government financial structure in line with the funding agreement.

An estimated amount of Birr 36.81 million (Birr 18.86 million from GoF and Birr 17.95 million from

GoE) was allocated for implementation of planned activities in Oromia region in 2008 EFY. About

Page 54: COMMUNITY-LED ACCELERATED WASH (COWASH) PROJECT€¦ · 1 EXECUTIVE SUMMARY ... STRENGTHENING THE FEDERAL CAPACITY TO IMPLEMENT COMMUNITY MANAGED PROJECTS ALONGSIDE WITH A SUPPORT

48

43.1%, 13.0%, 34.0% and 9.9% of the annual budget is allocated for investment, physical capacity

building, human capacity building and operational costs.

About 94.3% of the annual budget (Birr 34.7 million) was allocated for the first nine months of the

fiscal year. According to the regional performance report, some Birr 21.59 million (Birr 13.0 million

from GoF and Birr 8.6 million from GoE), or about 62.2% of the 9-month budget, has been utilized

in the reporting period (Table 40). The fund utilization by cost category shows that 47.9% of the

investment funds, 58.0% of the physical capacity building, 85.6% of the human capacity building

and 56.2% of the operational costs planned for the 9 months have been utilized for the planned

activities.

Table 40: Fund allocated and Utilized in Oromia Region in the First 9 Months of 2008 EFY

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19

Planned for 3rd

Quarter (14 +17)

Utilized 3rd

Quarter (15+18 )

Planned for 3rd

QuarterUtilized 3rd Quarter

Planned for 3rd

QuarterUtilized 3rd Quarter

GoF GoE Total (1+2 ) GoF GoE GoF+GoE GoF GoE GoF+GoE GoF + GoE GoF + GoE Cumulat ive

( 9 / 6 ) *10 0

This

Quarter

(11/ 10 ) *1

0 0

GoF GoF GoE GoE

INVESTM ENT

COST15,874,742 15,874,742 15,874,742 15,874,742 7,602,622 7,602,622 7,736,085 7,015,860 47.9 90.7 7,736,085 7,015,860 90.7

PHYSICAL

CAPACITY

BUILDING COST

4,768,078 4,768,078 4,768,078 - 4,768,078 2,765,485 2,765,485 4,768,078 820,760 58.0 17.2 4,768,078 820,760 17.2

HUM AN

CAPACITY

BUILDING COST

12,520,938 12,520,938 11,286,755 - 11,286,755 9,659,296 - 9,659,296 4,096,221 8,635,434 85.6 210.8 4,096,221 8,635,434 210.8

OPERATIONAL

COST1,568,174 2,075,037 3,643,211 977,231 1,796,244 2,773,475 571,592 987,934 1,559,526 1,159,866 1,164,374 56.2 100.4 325,744 198,830 61.0 834,122.00 965,544.00 115.8

TOTAL 18 ,8 57,19 0 .0 17,9 4 9 ,779 .0 3 6 ,8 0 6 ,9 6 9 .0 17,0 3 2 ,0 6 4 17,6 70 ,9 8 6 3 4 ,70 3 ,0 50 12 ,9 9 6 ,3 73 8 ,59 0 ,556 2 1,58 6 ,9 2 9 17,76 0 ,2 50 17,6 3 6 ,4 2 8 6 2 .2 9 9 .3 9 ,19 0 ,0 4 3 9 ,6 55,0 2 4 .0 0 10 5.0 6 8 ,570 ,2 0 7.0 0 7,9 8 1,4 0 4 .0 0 9 3 .1

Euro 857,145.0 815,899.0 1,673,044.0 774,184.7 803,226.6 1,577,411.4 590,744.2 390,479.8 981,224.1 772,185 766,801 62.2 99.3 417,729 438,865 105 389,555 362,791 93.1

Utilizat ion (%)

( 18 / 17) *10

0

Category

Planned(Annual) Cumulat ive Planned Cumulat ive Utilized Utilizat ion(%)Utilizat ion

(%)

( 15/ 16 ) *1

0 0

Total fund received by Oromia BoFED and utilized to date in Oromia region, by fund source, is

indicated in Table 41 below. The region has received Euro 1,427,778 (equivalent to

Birr 34,183,057) GoF contribution from Ministry of Foreign Affairs (MFA) of Finland and Birr

48,561,573.62 from the regional government (GoE). Accordingly, the entire amount received from

the two sources has been transferred to beneficiary sector offices as per their annual plans

approved by the Regional WaSH Steering Committee (RWSC). Much of the funds transferred

(90.0%) has been utilized by beneficiary sector offices including RSU, until end of March 2016.

Table 41: Funds received, transferred and utilized in Oromia Region until end of March 30, 2016

Received

(%)

Transferred

(%)

GoF 34,183,057.02 34,183,057.02 33,211,548.60 971,508.42 971,508.42 97.2 97.2

GoE 48,561,573.62 48,561,573.62 41,277,387.50 7,284,186.12 7,284,186.12 85.0 85.0

Total 82,744,630.64 82,744,630.64 74,488,936.10 8,255,694.54 8,255,694.54 90.0 90.0

Usage from Budget

Source

Received from

Source to date

Transferred to

Beneficiaries

to date

Utilized by

Beneficiaries

to date

Balance from

Received to

date

Balance from

Transferred to

date

6.2.4 Amhara region

As per the funding agreement signed between the Bureau of Finance and Economic Development of

Amhara National Regional State, all capacity building and some operational costs (including RSU

costs) are covered from GoF contribution while all investment costs and some operational costs are

covered from GoE fund allocations. All the investment funds from GoE is being channeled to the

Page 55: COMMUNITY-LED ACCELERATED WASH (COWASH) PROJECT€¦ · 1 EXECUTIVE SUMMARY ... STRENGTHENING THE FEDERAL CAPACITY TO IMPLEMENT COMMUNITY MANAGED PROJECTS ALONGSIDE WITH A SUPPORT

49

communities through Amhara Credit and Saving Institution (ACSI) with a commission of 3% while

the capacity building funds and operational costs from the Finnish Government has been channeled

through the government financial structure as per the funding agreement signed by the two

parties.

A total of about Birr 135.06 million (Birr 44.87 million from GoF and Birr 90.19 million from GoE)

was budgeted, including BoFED Treasury & contingency, for 2008 EFY. This amount includes the

additional budget Birr 17.54 million (14.97 million from GoE and Birr 2.55 million from GoF)

transferred for 36 project woredas. Of the total annual budget, about Birr 131.87 million (Birr 41.68

million from GoF and Birr 90.19 million from GoE) was allocated for the first nine months of the

fiscal year. This accounts about 97.6 % of the total allocated for 2008 EFY.

The regional financial performance report shows that only 30.6% of the budget allocated (24.5% of

the GoF and 33.5% of the GoE) for the reporting period has been utilized. The main reason for the

low fund utilization is the delay in the approval of the 2008 EFY and slow settlement of funs in the

project woredas. Detail of the fund utilization by cost category is presented in Table 42 below.

Page 56: COMMUNITY-LED ACCELERATED WASH (COWASH) PROJECT€¦ · 1 EXECUTIVE SUMMARY ... STRENGTHENING THE FEDERAL CAPACITY TO IMPLEMENT COMMUNITY MANAGED PROJECTS ALONGSIDE WITH A SUPPORT

50

Table 42: Fund allocated and Utilized in Amhara Region in the First 9 Months of 2008 EFY

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19

Planned for

3rd Quarter

(14 +17)

Utilized 3rd

Quarter

(15+18 )

Planned for

3rd Quarter

Utilized 3rd

Quarter

Planned for

3rd Quarter

Utilized 3rd

Quarter

GoF GoE Total (1+2 ) GoF GoE GoF+GoE GoF GoE GoF+GoE GoF + GoE GoF + GoE

Cumulat ive

( 9 / 6 ) *10

0

3rd Quarter

(11/ 10 ) *10

0

GoF GoF GoE GoE

INVESTM ENT

COST471,145 83,826,089 84,297,234 471,145 83,826,089 84,297,234 30,187,757 30,187,757 42,948,344 30,187,757 50.9 70.3 - 42,948,344 30,187,757 70.3

PHYSICAL

CAPACITY

BUILDING COST

9,434,000 9,434,000 9,434,000 9,434,000 156,565 156,565 8,720,000 156,565 1.7 1.8 8,720,000 156,565 1.8

HUM AN

CAPACITY

BUILDING COST

25,008,229 25,008,229 25,008,229 25,008,229 7,500,232 7,500,232 6,323,406 7,500,232 30.0 118.6 6,323,406 7,500,232 118.6

OPERATIONAL

COST 7,983,421 6,359,655 14,343,076 4,799,436 6,359,655 11,159,091 2,531,864 2,531,864 2,970,954 2,531,864 22.7 85.2 1,300,779 2,531,864 194.6 1,670,175

BoFED Treasury &

Contingency1,971,164 1,971,164 1,971,164 1,971,164 - 1,971,164 - - 1,971,164 -

TOTAL 44,867,959 90,185,744 135,053,703 41,683,974 90,185,744 131,869,718 10,188,660 30,187,757 40,376,417 62,933,868 40,376,417 30.6 64.2 18,315,349 10,188,660 55.6 44,618,519 30,187,757 -

Total in Euro

(1Euro=22 Birr) 2,039,452.67 4,099,352.01 6,138,804.68 1,894,726.09 4,099,352.01 5,994,078.10 463,120.92 1,372,170.76 1,835,291.68 2,860,630.35 1,835,291.68 832,515.85 463,120.92 2,028,114.50 1,372,170.76

Utilizat ion (%)

( 18 / 17) *10

0

Category

Planned(Annual) Cumulat ive Planned Cumulat ive Utilized Utilizat ion(%)Utilizat ion

(%)

( 15/ 16 ) *

10 0

BoFED of Amhara region has received about Birr 511.98 million (Euro 10,310,577.71 or about Birr

252,813,114.41 from Government of Finland including Birr 4,291,860.92 RWSEP savings and

Birr 300,389,286.24 from Amhara Regional Bureaus) for the implementation of COWASH activities.

The region has received all the Euro agreed for COWASH Phase I and II. More than 98.6% of the

amount received has been transferred to beneficiary sector offices until end of the reporting period.

About 76.3% of the transferred (85.7% of the GoF and 68.6% of the GoE transferred) has been

utilized until end of the reporting period (Table 43). As much of the construction activities are

underway in the last quarter, the region will utilize all the funds allocated for COWASH Phase II.

Table 43: Funds received, transferred and utilized in Amhara Region until end of March 30, 2016

Received

(%)

Transferred

(%)

GoF (including RWSEP

saving)252,813,114.11 245,198,480.66 210,070,288.01 42,742,826.10 35,128,192.65 83.1 85.7

GoE 300,389,286.24 300,389,286.24 206,192,384.35 94,196,901.89 94,196,901.89 68.6 68.6

Total 553,202,400.35 545,587,766.90 416,262,672.36 136,939,727.99 129,325,094.54 75.2 76.3

Usage from

Budget SourceReceived from

Source to date

Transferred to

Beneficiaries

to date

Utilized by

Beneficiaries

to date

Balance from

Received

Balance from

Transferred

Note: Exchange rate gain received and utilized to date:

Total exchange rate gains received (in Birr) to date: Birr 21,688,537

Total amount of exchange rate utilized (in Birr) to date: the region was using the exchange rate gain from the previous year by re planning to the next budget year.

6.2.5 Benishangul Gumuz region

All the investment funds from the two fund sources (GoF and GoE/Benishangul Gumuz National

Regional State) is being channeled to the communities through Benishangul Gumuz Credit and

Saving Institution (BECSI) with a commission of 5% while the capacity building fund from the

Finnish Government and operational cost from both sources have been channeled through the

Page 57: COMMUNITY-LED ACCELERATED WASH (COWASH) PROJECT€¦ · 1 EXECUTIVE SUMMARY ... STRENGTHENING THE FEDERAL CAPACITY TO IMPLEMENT COMMUNITY MANAGED PROJECTS ALONGSIDE WITH A SUPPORT

51

government financial structure. The project fund is administered as per the funding agreement

signed between the Benishangul Gumuz Bureau of Finance and Economic Development (BoFED)

and Embassy of Finland.

A total of about Birr 45.32 million (Birr 28.52 million from GoF and Birr 16.80 million from GoE)

was allocated for 2008 EFY. More than Birr 42.85 million (94.5% of the annual budget) was

allocated for the first nine months of 2008 EFY. Close to 74.0% of the funds allocated for the

reporting period (Birr 15.53 million of the fund allocated for the nine months) or 34.3% of the

annual budget of the project has been utilized. Much of the funds utilized was paid for the

procurement of 15 motorbikes and 5 vehicles rolled over from 2007 EFY.

Table 44: Fund allocated and Utilized in BSG Region in the First 9 Months of 2008 EFY

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19

Planned for

3rd Quarter

(14+17)

Utilized 3rd

Quarter

(15+18)

Planned for

3rd Quarter

Utilized 3rd

Quarter

Planned for

3rd Quarter

Utilize

d 3rd

Quart

er

GoF GoE Total (1+2) GoF GoE GoF+GoE GoF GoE GoF+GoE GoF + GoE GoF + GoE

Cumula

tive

(9/6)*

100

This

Quarter

(11/10)

*100

GoF GoF GoE GoE

INVESTMEN

T COST7,568,400 14,669,550 22,237,950 756,840 14,669,550 15,426,390 - - 12,968,550 - 0.0 0.0 5,218,500 - 0.0 7,750,050.00 - -

PHYSICAL

CAPACITY

BUILDING

COST

10,762,356 19,500 10,781,856 10,762,354 19,500 10,781,854 10,775,138.90 - 10,775,138.90 45,000 1,554,137.42 99.9 3453.6 45,000 1,554,137.42 3453.6 - -

HUMAN

CAPACITY

BUILDING

COST

6,232,000 367,456 6,599,456 5,320,695 285,916 5,606,611 1,649,935.05 - 1,649,935.05 609,343 765,377.87 29.4 125.6 564,343 765,377.87 135.6 45,000.00 - -

OPERATION

AL COST3,957,244 1,743,494 5,700,738 2,976,107 1,243,766 4,219,873 3,108,714.51 - 3,108,714.51 1,511,924 1,249,147.54 73.7 82.6 988,135 1,249,147.54 126.4 523,789.00 - -

TOTAL 28,520,000 16,800,000 45,320,000 19,815,996 16,218,732 36,034,728 15,533,788.46 - 15,533,788.46 15,134,817 3 ,568,662.83 43.11 23.58 6 ,815,978 3 ,568,662.83 52.36 8 ,318,839.00 - 0 .00

Utilization

(%)

(15/16)

*100

Utilizatio

n (%)

(18/17)

*100

Category

Planned(Annual) Cumulative Planned Cumulative Utilized Utilization(%)

As shown in Table 45 below, Benishangul Gumuz BoFED has received Birr 43.97 million (Birr 38.84

million equivalent to Euro 1,645,490.62 from GoF and only Birr 5.13 million from GoE) until end of

March 2016. Of this amount, about Birr 30.73 million (Birr 25.73 million from GoF and Birr 5.00

million from GoE) has been transferred to beneficiary sector offices in the same period. Till end of

the reporting period, close to 45.1% of the received or 64.5% of the transferred to beneficiaries

has been utilized.

Table 45: Funds received, transferred and utilized in BSG Region until end of March 30, 2016

Receive

d(%)

Transferred

(%)

GoF 38,840,844.88 25,732,738.00 19,675,319.19 19,165,525.69 6,057,418.81 50.7 76.5

GoE 5,125,000.00 5,000,000.00 150,000.00 4,975,000.00 4,850,000.00 2.9 3.0

Total 43,965,844.88 30,732,738 19,825,319.19 24,140,525.69 10,907,418.81 45.1 64.5

Usage from

Budget

Source

Received from

Source to date

Transferred to

Beneficiaries

to date

Utilized by

Beneficiaries

to date

Balance from

Received

Balance from

Transferred

Page 58: COMMUNITY-LED ACCELERATED WASH (COWASH) PROJECT€¦ · 1 EXECUTIVE SUMMARY ... STRENGTHENING THE FEDERAL CAPACITY TO IMPLEMENT COMMUNITY MANAGED PROJECTS ALONGSIDE WITH A SUPPORT

52

7 PROJECT COORDINATION WITH KEY STAKEHOLDERS

The scaling-up of the CMP approach at the national level requires having meetings and discussions

with different WASH stakeholders thereby sharing the success of the CMP approach and raising

awareness and generating funds for investments. Cognizant of this fact, COWASH has been

participating in a number of meetings and discussions held in the fiscal year at the national level to

promote and share experience on the CMP approach and to attract more funds for CMP. The major

meetings and/or discussions that COWASH has participated are presented hereunder.

Water Sector Working Group (WSWG)

The WSWG Secretarial together with UNICEF is in a process to recruit an international expert to the

Secretariat. WASH technical Committee meeting (now called WASH-Sub-Group) was convened on

July 8, 2015, Nov. 25, 2015 and Oct. 30, 2015 and COWASH participated this meeting. During this

meetings, activity plan of 2008 EFY was developed, annual work plan for UWASH-TC, RWASH-TC,

EWASH-TC, action plans of Rural and Urban WASH Technical Committes under WASH-SG and

progress of Integrated Urban Sanitation & Hygiene Strategy preparation were presented and

discussed. In addition, the 2015 JMP report’s major findings in Ethiopia were presented and the

Water Sector Capacity Building 5-year plan was further discussed. CTA also participated in the

WATSAM project closing seminar, which is EU funded urban water utility capacity building project in

Arba Minch.

Self Supply Working Group (SSWG)

Self-Supply Sub Working Group (SSSWG) meeting was held in July 3, 2015 and COWASH’s Junior

Professional Expert (JE) participated in the meeting. It was informed that the name ‘Self-Supply

Sub-Working group’ is changed to Self-Supply Task Force, SNNPR water bureau procured 10,000

rope pumps, standardization of rope pump proposal will be distributed to the standardization

agency, the implementation approaches of Self Supply between partners vary; IDE is demanding

Birr 700 contribution wheras JICA requests Birr 1,500 from the beneficiary household.

MoWIE Annual Review Meeting

COWASH FTAT took part in the 2007 EFY annual performance and GTP 1 performance review held

at Adama town. Besides the performance in 2007 EFY, GTP 2 plans were discussed during the

meeting.

Page 59: COMMUNITY-LED ACCELERATED WASH (COWASH) PROJECT€¦ · 1 EXECUTIVE SUMMARY ... STRENGTHENING THE FEDERAL CAPACITY TO IMPLEMENT COMMUNITY MANAGED PROJECTS ALONGSIDE WITH A SUPPORT

53

8 CHALLENGES

Like the previous fiscal year, different kinds of challenges have been faced during the reporting period. The major ones that require the

attention of National WaSH Steering Committee (NWSC) and Regional WaSH Steering Committee (RWSC) are indicated as follows.

Challenges Measures taken

Delay in the approval of Generic CMP Implementation Manual by MoFEC: CMP

Implementation Manual using Public Finance and Procurement Management System (PFPMS) was

developed and presented to MoFEC for approval. However, the Ministry has not yet given any official

response and a number of planned activities are still pending.

.

Embassy of Finland and COWASH CTA

have been communicating and reminding

the concerned officials in MoFEC. The

COWSH evaluation and Phase III

document preparation team has also made

discussion with the concerned officials.

Delay in preparation and approval of regional annual plans: The 2008 EFY annual plans of

COWASH in the regions were expected to be prepared before the end of 2007 EFY. However, the

preparation and approval of the plans were delayed in the regions. The delay in the preparation and

approval of annual plans hampers implementation and budget utilization of woredas.

COWASH provided technical assistance to

all the regions in the preparation of their

annual plans. Planning templates and unit

costs were prepared by COWASH FTAT and

sent to regions timely and reminders have

been sent to start the process timely.

Delay in sending quarterly reports: Quarterly performance reports are expected from regions to

prepare project performance reports at the federal level and disseminate to stakeholders and for

requesting fund transfers timely. However, the 2007 EFY annual report and the first quarter

performance report of the regions were delayed and this takes much time to prepare the

performance report of the project at the federal level. Quality of the regional reports has been

contributing for the delay in the preparation of the project level report.

Quarterly report preparation outlines and

reporting templates have been sent timely.

Moreover, COWASH FTAT has been

assisting RSUs in preparing regional

reports and providing feedbacks on the

reports sent to COWASH FTAT.

Page 60: COMMUNITY-LED ACCELERATED WASH (COWASH) PROJECT€¦ · 1 EXECUTIVE SUMMARY ... STRENGTHENING THE FEDERAL CAPACITY TO IMPLEMENT COMMUNITY MANAGED PROJECTS ALONGSIDE WITH A SUPPORT

i

FinnWASH-BG Project Woredas

2008 EFY Nine Months Performance Report

(08/07/2015 – 30/03/2016)

June 2016

Page 61: COMMUNITY-LED ACCELERATED WASH (COWASH) PROJECT€¦ · 1 EXECUTIVE SUMMARY ... STRENGTHENING THE FEDERAL CAPACITY TO IMPLEMENT COMMUNITY MANAGED PROJECTS ALONGSIDE WITH A SUPPORT

2

9 PERFORMANCE OF METEKEL WOREDAS

9.1 INTRODUCTION

The Community Development Fund approach was developed in Amhara Region through the RWSEP

programme over a period of 17 years in 1995-2012. It was found to be a functional platform for

sustainable, community-led Water Supply and Sanitation development. Finn WASH-BG was the first

programme to replicate, test, develop and apply this approach in Benishangul Gumuz region. The

CDF approach is currently known as CMP (Community Managed Project) in the sector wide policy

documentation in Ethiopia.

In 2011, the Ethiopian Government launched COWASH at federal level to scale-up the CMP

approach across all the Regions of Ethiopia. The CMP approach has also been officially adopted as a

financing strategy by the WASH sector Ministries at the CDF summit in Bahir Dar in February 2010.

The Finn WASH Programme is due to end in June 2013, however, the main targets of reaching 98%

UAP (Universal Access Plan) and 100% sanitation coverage as stated in the Programme Document

(PD) of 2008 could not be met by that date and the project was extended for more year. This is due

to the challenging nature of the remote, culturally diverse and geologically challenging region. Since

the Planning Phase of FinnWASH-BG, it has been evident that Benishangul Gumuz Region will

require various technologies to achieve the UAP goal of 98% water supply and 100% sanitation

coverage. To respond to this challenge, the Finn WASH-BG Programme has introduced innovative

and ambitious approaches to solving especially water supply challenges, while adopting the CDF

mechanism to medium and larger mechanized and gravity schemes. While these solutions have

brought valuable experience of how to solve WASH developments through a community-led

approach, it also requires more time to test and develop the solutions and ensure sustainable

operations.

The Ali Spring gravity water supply scheme rehabilitation and management structure is an

ambitious component of the Finn WASH-BG, launched in 2011. To ensure technical, financial and

social sustainability of this scheme, more time is required. While the physical construction of several

medium size schemes will be achieved by June 2013, the establishment of management systems

will likewise require time for adequate testing and institutionalization.

Since its inception in 2008, the Finn WASH-BG Program has achieved impressive results through the

CDF approach in five Woredas of Pawe, Mandura, Dibate, Bullen and Wombera in Metekel Zone of

Benishangul Gumuz region. The community water supply access coverage has increased from 15%

to 81.3% at the end of 2007 EFY. As a result of the project’s interventions, the water supply

coverage in schools and health facilities reached to 52% and 55%, respectively. The VIP latrine

coverage in schools and health facilities has increased to 45% and 54%, respectively. Besides,

awareness about the CDF/CMP approach and sanitation and hygiene issues has raised in all

communities where the project has intervened.

Since Oct. 2015 the project activities have been annexed to COWASH upon the phase out of the

project. The activities performed in the six months (Oct. –March 2016) in the project woredas, zone

and regional level are presented below.

Page 62: COMMUNITY-LED ACCELERATED WASH (COWASH) PROJECT€¦ · 1 EXECUTIVE SUMMARY ... STRENGTHENING THE FEDERAL CAPACITY TO IMPLEMENT COMMUNITY MANAGED PROJECTS ALONGSIDE WITH A SUPPORT

3

9.2 CAPACITY BUILDING

9.2.1 Human Capacity Building

The capacity building activities have continued in the zone and woredas so as to sustain the project

outputs. Some trainings were planned in the first half of 2008 EFY. It was also planned to conduct

review workshop on supply chain system at woreda level in the presence of woreda executive

bodies and kebele administrators of 59 kebeles of three woredas (Bullen, Pawe and Mandura). The

workshop was conducted for 3 days with the participation of 391 people (99 females) with an

estimated cost of Birr 345,000. Moreover, refreshment training was given to 26 people (15 females)

woreda staff on financial management, procurement, property administration for 3 days at a cost of

Birr 37,250. Moreover, 86 kebele and woreda people (21 females) have received a refresher

training on O&M and scheme management training for 3 days at a cost of Birr 58,000. Overall, 503

people (26.8% female) have been trained in the reporting period at a cost of Birr 440,250. This

accounts 62.0% of the annual plan.

Table 46. Trainings planned and achieved in the First 9 Months of 2008 EFY

M F T M F T

1Review workshop at woreda level for WASHCO of Supply

Chain SystemWoW 484 484 484 - 292 99 391 3 345,000

2

Refreshment training on Financial management, procurement

& property administration at woreda level for executive &

techinical staff of WWUA.

WoW 55 55 55 - 11 15 26 3 37,250

3 Refreshment training on Scheme Management and O&M WoW 262 262 262 65 21 86 65 21 86 3 58,000

801 801 801 65 21 86 368 135 503 440,250 Total

S/

NType of Training Trainer

No. of Trainees Planned Number Trained Estimated cost

of training (in

Birr)

3rd Quarter CumlativeAnnual

3rd

QuarterCumulative

No. of

Days

Trained

9.3 PHYSICAL CAPACITY BUILDING

In 2008 EFY, it was planned to procure a boat for Ali Spring rehabilitation. There were no other

material procurements planned in the fiscal year. Consequently, one old boat was procured from

Lake Tana Transport Enterprise.

9.4 ALI SPRING WATER SAFETY PLAN & REHABILITATION

In 2008 EFY, Ali Spring rehabilitation and establishment of the management system constitutes a

sub-project within the Project. A contractor was hired for the rehabilitation and the field advisor

together with the Pawe Woreda Officials have been following up the rehabilitation of the Spring. The

major accomplishments in Ali Spring rehabilitation are the following:

Construction of two fences with 74 meter long has been completed (98.7%). The fencing

was executed to stop animal entry into the water.

Fencing of some 1,150 meter gully erosion area was completed.

Repair of 150 meter fence around Ali Spring, removal of fallen tree branches and fixing holes

were executed.

Construction of 30 m3 long Gabion erosion protection was completed

Page 63: COMMUNITY-LED ACCELERATED WASH (COWASH) PROJECT€¦ · 1 EXECUTIVE SUMMARY ... STRENGTHENING THE FEDERAL CAPACITY TO IMPLEMENT COMMUNITY MANAGED PROJECTS ALONGSIDE WITH A SUPPORT

4

9.5 FINANCIAL UTILIZATION

FinnWASH BG Project is jointly financed by regional government of B/G/R/S (GoE) and Government

of Finland (GoF). And it is implemented by Water, Mine & Energy Resource Development Bureau

(BoW) in Five woredas of Pawe Mandura, Dibate, Bullen and Wombera in collaboration with sector

Bureaus like Health Bureau, Education Bureau, Finance and Economic Development Bureau &

Women, youth & children.

As it is shown in Table 47 below, from the overall annual budget of Birr 9,372,000, about Birr

6,841,566.70 (73.0%) was utilized for the implementation of planned activities in the reporting

period. Some Birr 2.53 million is left for the last quarter of 2008 EFY.

Table 47: Budget Plan and Expenditure of FinnWASH

S/n Beneficiary Sector

offices

2008 EFY

Planned

Budget

Expenditure

(Oct. 2015 – March

2106

Balance

1 Pawi Woreda 860,640 602,470 258,169.71

2 Mandura Woreda 891,700 549,234 342,465.70

3 Bullen Woreda 809,373 633,016 176,356.77

4 Wombera Woreda 865,440 169,398 696,042.00

5 Dibate Woreda 756,640 331,627 425,013.00

6 Metekel Zone sectors 1,760,927 1,730,980 29,947.10

7 WMERDB 3,289,280 2,686,840 602,440.40

8 BoFED 61,200 61,200 -

10 Health Bureau 25,600 25,600 -

11 Education Bureau 25,600 25,600 -

12 Women, Children & Youth

Bureau 25,600

25,600 -

Total 9,372,000

6,841,565.7 2,530,435

The major challenges in the FinnWASH BG Woredas in the reporting period were the following:

- Repair of FinnWASH BG field vehicle was delayed for more than 2 months and this had affected

supervisions to the woredas;

- Budget for retention of water points in Wonbera Woreda was wrongly put in BoFED account and it is

taking much time to transfer the retention budget to the woreda

- Retention budget for Senkora Deep Well and 25 Hand Dug Wells in Wombera Woreda was not deducted

and deposited at the Woreda level. Some Birr 286, 000 is required for retention of Senkora deep well and

25 Hand Dug Wells in this woreda. The woreda needs Birr 216, 000 for Senkora Deep Well and Birr 70,000

for 25 Hand Dug Wells.