commissioning green buildings - bcxa€¦ · 18th national conference on building commissioning a...

18
Paul McCown Sr. Energy Engineer SSRCx, LLC Commissioning Green Buildings

Upload: others

Post on 29-Jul-2020

16 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Commissioning Green Buildings - BCxA€¦ · 18th National Conference on Building Commissioning A PECI EVENT Learning Objectives. 1. LEED for Existing Buildings; Retro-commissioning

Paul McCownSr. Energy EngineerSSRCx, LLC

Commissioning Green Buildings

Page 2: Commissioning Green Buildings - BCxA€¦ · 18th National Conference on Building Commissioning A PECI EVENT Learning Objectives. 1. LEED for Existing Buildings; Retro-commissioning

A PECI EVENT18th National Conference on Building Commissioning

Learning Objectives

1. LEED for Existing Buildings; Retro-commissioning process 2. Energy management best practices for existing buildings3. Examples of energy efficiency in existing buildings

AIA Quality Assurance

Page 3: Commissioning Green Buildings - BCxA€¦ · 18th National Conference on Building Commissioning A PECI EVENT Learning Objectives. 1. LEED for Existing Buildings; Retro-commissioning

A PECI EVENT18th National Conference on Building Commissioning

The Metrics

•LEED: Existing Buildings GOLD•320,000 ft2

Class A Office•12% -

immediate reduction in energy•28% -

highest monthly reduction in energy•Savings of $207,000 to date from energy•Reduced water consumption by 22%•Reduced solid waste generation by 49%

Page 4: Commissioning Green Buildings - BCxA€¦ · 18th National Conference on Building Commissioning A PECI EVENT Learning Objectives. 1. LEED for Existing Buildings; Retro-commissioning

A PECI EVENT18th National Conference on Building Commissioning

Outline

Building DescriptionLEED-EB v2.0 Retro-Cx guidelines

Project Timeline•

Performance Period•

Retro-Cx Scope

Retro-Cx Process•

Findings•

Results

Continuous Commissioning®

Process•

Findings•

Results

Page 5: Commissioning Green Buildings - BCxA€¦ · 18th National Conference on Building Commissioning A PECI EVENT Learning Objectives. 1. LEED for Existing Buildings; Retro-commissioning

A PECI EVENT18th National Conference on Building Commissioning

Building Description

Class A Office•

11 stories, 320,000 sf, 900 people, 1600 computers

Cafeteria, fitness center, parking garage, auditorium

HVAC•

2, 500 ton chillers with constant volume pumping

2 cooling towers •

13 VAV air handling units, fan powered boxes (perimeter)

Fully electric facility

Page 6: Commissioning Green Buildings - BCxA€¦ · 18th National Conference on Building Commissioning A PECI EVENT Learning Objectives. 1. LEED for Existing Buildings; Retro-commissioning

A PECI EVENT18th National Conference on Building Commissioning

Retro-Cx Implementation

Two options•

Visual observation

Data trends

Scope•

Develop a building operations plan (BOP)

Prepare a commissioning plan•

Implement the commissioning plan

Make repairs or upgrades of deficient items•

Retest items repaired (over 5 years)

Page 7: Commissioning Green Buildings - BCxA€¦ · 18th National Conference on Building Commissioning A PECI EVENT Learning Objectives. 1. LEED for Existing Buildings; Retro-commissioning

A PECI EVENT18th National Conference on Building Commissioning

Timeline

January 2008•

Preparation for RCx•

Assessment•

Maintenance

May 2008•

Performance Period Begins•

Retro-Cx begins

August 2008•

LEED-EB submission

February 2009•

LEED-EB Gold Certification

Page 8: Commissioning Green Buildings - BCxA€¦ · 18th National Conference on Building Commissioning A PECI EVENT Learning Objectives. 1. LEED for Existing Buildings; Retro-commissioning

A PECI EVENT18th National Conference on Building Commissioning

RCx FindingsChilled water

Chilled water bypass valve operation

Page 9: Commissioning Green Buildings - BCxA€¦ · 18th National Conference on Building Commissioning A PECI EVENT Learning Objectives. 1. LEED for Existing Buildings; Retro-commissioning

A PECI EVENT18th National Conference on Building Commissioning

RCx Findings

Chilled water•

Chilled water supply temperature reset based on outside air temperature○

42ºF to 50ºF based on CHW valve position located at the AHUs

Air-Side•

Test and Balance of Fan Powered Terminal Boxes

After-hours temperature setback○

Winter operation did not work at first

Supply air static pressure reset•

Supply air temperature reset

Page 10: Commissioning Green Buildings - BCxA€¦ · 18th National Conference on Building Commissioning A PECI EVENT Learning Objectives. 1. LEED for Existing Buildings; Retro-commissioning

A PECI EVENT18th National Conference on Building Commissioning

RCx Findings

Building Envelope

Chimney effect at roof column Missing insulation under first floor at parking garage.

Page 11: Commissioning Green Buildings - BCxA€¦ · 18th National Conference on Building Commissioning A PECI EVENT Learning Objectives. 1. LEED for Existing Buildings; Retro-commissioning

A PECI EVENT18th National Conference on Building Commissioning

RCx ResultsEnergy Savings

Page 12: Commissioning Green Buildings - BCxA€¦ · 18th National Conference on Building Commissioning A PECI EVENT Learning Objectives. 1. LEED for Existing Buildings; Retro-commissioning

A PECI EVENT18th National Conference on Building Commissioning

CC® Findings

Building Supply and Exhaust Air•

Exhaust “conditions”

Telecomm and Electrical rooms

Automatic F/S Dampers shutting down•

Modified Supply and Exhaust Fan schedules (7pm-7am off)

Air Terminal Boxes•

Were not coming on in winter after hours operation

Needed “main air”

from AHU•

Reprogrammed boxes to provide heat with box fan only

Savings can be seen immediately in March 2009 energy bill

Page 13: Commissioning Green Buildings - BCxA€¦ · 18th National Conference on Building Commissioning A PECI EVENT Learning Objectives. 1. LEED for Existing Buildings; Retro-commissioning

A PECI EVENT18th National Conference on Building Commissioning

CC® FindingsAfter-Hours Operation

Re-Zoning○

Several spaces require air conditioning 24/7○

Reprogrammed the terminal boxes for these areas to remain in occupied mode, while others on the AHU went to unoccupied mode.

AHU stayed on, VFD ramped to minimum○

Duct was not over-pressurized due to fan type (backward-inclined airfoil), VFD minimum, and duct configuration

Request for occupied time○

Prior to changes, many floors were scheduled to be occupied on Saturday (even for only a few people).

Zones were mapped.○

Thermostats were re-programmed to allow for over-ride○

Now, when only one person comes in after hours, their zone can be over-ridden without over-riding the whole floor.

Page 14: Commissioning Green Buildings - BCxA€¦ · 18th National Conference on Building Commissioning A PECI EVENT Learning Objectives. 1. LEED for Existing Buildings; Retro-commissioning

A PECI EVENT18th National Conference on Building Commissioning

CC® ResultsEnergy Savings

Page 15: Commissioning Green Buildings - BCxA€¦ · 18th National Conference on Building Commissioning A PECI EVENT Learning Objectives. 1. LEED for Existing Buildings; Retro-commissioning

A PECI EVENT18th National Conference on Building Commissioning

Results

Energy Star Score•

62 as of January 2008

76 as of March 2010•

23% increase

Energy Use Index (kBtu/sf/yr)•

107.5 as of January 2008

85.2 as of March 2010•

21% decrease

Page 16: Commissioning Green Buildings - BCxA€¦ · 18th National Conference on Building Commissioning A PECI EVENT Learning Objectives. 1. LEED for Existing Buildings; Retro-commissioning

A PECI EVENT18th National Conference on Building Commissioning

Results

•LEED: Existing Buildings GOLD•320,000 ft2

•12% -

immediate reduction in energy•28% -

highest monthly reduction in energy•Savings of $207,000 to date from energy•Energy Star Registered March 2010•Reduced water consumption by 22%•Reduced solid waste generation by 49%

Page 17: Commissioning Green Buildings - BCxA€¦ · 18th National Conference on Building Commissioning A PECI EVENT Learning Objectives. 1. LEED for Existing Buildings; Retro-commissioning

A PECI EVENT18th National Conference on Building Commissioning

AIA Quality Assurance

Portland Energy Conservation, Inc is a registered provider with The American Institute of Architects Continuing Education Systems. Credit earned on completion of this program will be reported to CES Records for AIA members. Certificates of Completion for non-AIA members are available on request.

This program is registered with the AIA/CES for continuing professional education. As such, it does not include content that may be deemed or construed to be an approval or endorsement by the AIA of any material of construction or any method or manner of handling, using, distributing, or dealing in any material or product. Questions related to specific materials, methods, and services will be addressed at the conclusion of this presentation.

Page 18: Commissioning Green Buildings - BCxA€¦ · 18th National Conference on Building Commissioning A PECI EVENT Learning Objectives. 1. LEED for Existing Buildings; Retro-commissioning

Thank You

Paul McCown

[email protected]