COMISIÓN FEDERAL DE ELECTRICIDAD

Bidding on the Largest Wind Project in México

Ing. Eduardo H. Buendía D. Ing. R. Aracely Acosta T.August 30, 2006

2

1. Background

2. Wind Potential in Mexico

3. “La Venta II” and “La Venta III” Projects

4. Future Projects

5. Conclusions

AGENDA

Background

4

National Electric System (Dec-2005)

Conventional27,79%

Dual4,51%

Combined Cycle10,76%

Gas Turbine5,59%

Hydroelectric22,64%

Coal5,59%

Nuclear2,93%

IPP17,73%

Geo & Wind2,07%

Diesel0,39%

Power PlantType MW

192 Power Plants, with 637 Power Units

Conventional 12 934

Dual 2 100

Combined Cycle 5 005

Gas Turbine 2 599

Diesel 182

Hydroelectric 10 536

Coal 2 600

Nuclear 1 365

Geo & Wind 962

IPP 8 251

TOTAL 46 534

The national electric system has 46,534 MW installed capacity, 864 MW belong to L&FC and 45,670 MW to CFE including IPP’s.

5

Free5758 MW

Wind & Geothermal705 MW

Gas Turbine504 MW

Coal648MW

Hydroelectric2244 MW

Combined Cycle11730 MW

0 2000 4000 6000 8000 10000 12000 14000

POW

ER P

LAN

T TY

PE

NET CAPACITY(MW)

º

Power Plants: 59Total Capacity: 21,587 MW

(116 MW GEO and 589 MW WIND)

Capacity Requirements Program (2005-2014)

Wind Potential in Mexico

7

WIND POTENTIAL IN MEXICO

ESTIMATED CAPACITY: > 5000 MW

SOUTH TEHUANTEPEC ISTHMUS(*) 2000 MW – 3000 MW

BAJA CALIFORNIA SUR PENINSULA(*) 1500 MW – 2500 MW

YUCATÁN PENINSULA 1000 MW – 2000 MW

CENTRAL ZACATECAS 800 MW – 1500 MW

PACIFIC OCEAN COASTLINE 1000 MW - 1500 MW

GOLF OF MÉXICO COASTLINE 1000 MW – 1500 MW

(*) CFE has complete studies on these sites.

Wind potential in Mexico

8

Wind projects in Mexico

PRESENT INSTALLED CAPACITY

PROJECT Capacity MW

La Venta Oaxaca (7 x 225 KW) 1.575

Guerrero Negro Baja California Sur 0.6

TOTAL 2.125Rest of the Country 4.7

EXPECTED INSTALLED CAPACITY IN 2013

PROJECT CapacityMW

Comisión Federal de Electricidad 589

Private Projects 661

TOTAL 1250

9

Open Season for grid-project

To allow for self suppliers of energy in the Isthmus of Tehuantepec, CFE and CRE called for an open season for reserve capacity of energy transmission.

The network associated to the private wind farm projects consists of an interconnection point, and it will be interconnected with the network of the national electrical system.

The project will be bid by CFE next year under the Financed Public Work (OPF) scheme, with the guarantee of the private self suppliers of energy to pay for the investment.

10

Cancún

Cozumel

Istmo de Tehuantepec

VeracruzMazatlán

Hidalgo

Zacatecas

Guerrero Negro

López Mateos

San Quintín

La Rumorosa

La Venta

Sites with wind potencial

Installed wind projects

Wind potential in Mexico

11

MEAN ANNUAL WIND VELOCITIES (m/sec.)LA

VENTA 1994 1995 1996 1997 1998 1999 2000 AVRG.

1 10.07 8.91 9.45 10.41 9.16 9.45 9.30 9.53

3 8.93 8.86 8.78 9.79 8.69 8.02 7.90 8.71

4 9.30 8.93 9.38 10.05 7.26 8.37 8.23 8.78

5 9.60 9.38 9.86 10.61 9.03 9.03 8.63 9.44

AVERAGE 9.47 9.02 9.36 10.21 8.53 8.71 8.51 9.12

AVERAGE WIND VELOCITIES IN “LA VENTA OAXACA”

Pv = ½ ρA3CpVv

Pv = Power due to wind [watts]

ρ = Wind Density (1,225 kg/m3) typical value

A = Swept area [m2].

Cp = Aerodynamic efficiency Coefficient 0.435 for 3.5 ≤ V ≤ 26 m/s.

Vv = Average wind speed [m/s].

Wind potential in Mexico

“La Venta II” Project

13

The Project is located in La VentaVillage, state of Oaxaca.

Freeway

Panamericana km 15 between La Ventosa-Tapanatepec.

Project Localization

14

Economic-Financial Aspects

The Project was authorized, in the 2004 Federal Budget.

The useful life of the Project (20 years).

The Contractor will finance every aspect of the Work

during the period of Construction.

Mexican Content must be at least 17%.

CFE will pay the Price of the Contract on the Scheduled Date of Provisional Acceptance of the Power Plant (Commercial Operation).

The Project is a Financed Public Work (OPF). Winning bidder is responsible for the construction and financial costs during construction.

“La Venta II” Project

15

FEATURE

TECHNICAL FEATURES OF THE “CE LA VENTA II” CONTRACT WITH GAMESA EÓLICA

VALUE

95 %Guaranteed Availability Factor

60 HzFrequency

230 kVInterconnection Tension

98Number of wind turbine generators

83.30 MWInstalled capacity

“La Venta II” Project

The Scheduled Date of Provisional Acceptance (Commercial Operation) of the Wind Power Plant is

on November 1st, 2006.

16

Land Agreement

• Agreement: Right to Use the Land.

• Duration: 20 years.

• Payments: Yearly Payments to each land owner whose plat lies within the influence area of the project.

• Total yearly payments: equivalent to a little over 1% of the value of the energy produced.

• Payment Distribution: A fixed amount per hectare of land plus anadditional quantity for those land owners whose land is used for the installation of a turbine mast or an access road.

• Number of Contracts: 180 approximately.

• Negotiation Period: 1 year.

CFE negotiated the following agreements:

Future Projects

18

PROJECT CONTRACT TYPE RANGE(MW)

TOTAL CAPACITY

(MW)YEAR

LA VENTA II FPW 0.85

1.0-2.5 1

1.0-2.5 1

1.5-2.5 1

83.3 2006

LA VENTA III IPP 101 2008

OAXACA I IPP 101 2009

OAXACA I, III y IV IPP 304 2010

TOTAL 589

FUTURE CAPACITY PERIOD 2006 – 2014

Wind potential in Mexico

1) Whatever upper range in available and proven for at least one year

19

IPP WIND PROJECTS

CFE will provide

•an optional site through a 20 year land lease,

•site and environmental assessment (MIA),

•risk studies,

•Rights of way,

•An interconnection point.

The producer constructs, finances and operates a power plant under certain standards and commits himself to deliver a contractual amount of energy to CFE.

Wind Projects

20

The World Bank will give a donation for the project of 20 million dollars, as incentive to the tariff, during the

first 5 years of operation of the plant.

The negotiations between the World Bank and the government of Mexico concluded satisfactorily in July 2006,

thus, a Grant Agreement, a Project Agreement and the Standard Conditions documents will be signed.

“La Venta III” Project

21

“La Venta III” Project

1

2

3

4

5

6

7

8

9 Commercial Operation Date December 30, 2008

Contract Signature April 24, 2007

Scheduled Start Date October 05, 2007

Technical Veredict and Price Bid Openning March 20, 2007

Veredict March 30, 2007

Second Q&A Meeting January 18, 2007

Bid Openning Date February 28, 2007

Bid Publication November 16, 2006

First Q&A Meeting December 05, 2006

EVENT DATE

PRELIMINARY SCHEDULE

Conclusions

23

1. According to the Projects and Investment Program (POISE 2005-2014), the growth of the Country, will require an increment of the installed Capacity of 21 587 MW.

2. CFE’s 10 year capacity increase plan includes 3.26% of renewable energy.

3. CFE’s Independent Power Producer program include 589 MW of wind power plant.

Conclusions

24

4. The “La Venta II” FPW project established the foundations for continued efforts in renewable energy, using the wind potential of Oaxaca.

5. The “La Venta III” IPP project, will be the pioneer of the wind farm projects in Mexico.

6. By means of technological diversification and a reliable energetic strategy of supply based on different sources, CFE can guarantee the Electric Public Service.

Conclusions

25

Una empresade clase mundial