co prod costing part 2

55
1 07/21/11

Upload: subbutnj

Post on 09-Mar-2015

211 views

Category:

Documents


19 download

TRANSCRIPT

Page 1: CO Prod Costing Part 2

107/21/11

Page 2: CO Prod Costing Part 2

Goals

2

• To understand the SAP functionality of product costing along with the corresponding configuration settings. (This is part 2 of a series of multiple sessions planned)

• To discuss real issues reported in production system, analyze the root cause of the issue and identify potential solution approaches

• To identify potential areas of improvement to the design currently in place at ConAgra

Page 3: CO Prod Costing Part 2

Agenda for this Session

3

SAP functionality overview on Product Cost Planning: Process Order Costing Overheads Application Period End: WIP/Variances/Settlement FI Entries for Process Order Steps and PE Closing Actual Activity Price Calculation and Cost Center absorption

CAG Production issues on the above topic if any brought up

Page 4: CO Prod Costing Part 2

4

Product Cost Controlling Components

Page 5: CO Prod Costing Part 2

Process Order Process Chain

5

Page 6: CO Prod Costing Part 2

Order Data

6

Page 7: CO Prod Costing Part 2

Preliminary Costing

7

The quantity structure master data (BOM and routing) in Logistics gets copied onto the cost objects e.g. Process order

Preliminary costing costs the Process order using this quantity structure

The planned costs are used for comparing with actuals

Order Data:Variance Key, Costing Variants, Profit Center, Settlement Rule, RA Key, Apportionment Structure etc.

Page 8: CO Prod Costing Part 2

Preliminary Costing

8

Page 9: CO Prod Costing Part 2

Preliminary Costing

9

• The system valuates the planned quantities of the material components using the materials list.

• The system determines the planned activity quantities using the master recipe.

• To valuate the planned material components, activities, and business processes, the system uses the planned valuation variant specified in the default values for the order type and plant. The overhead expenses are calculated using the costing sheet specified in the planned valuation variant. If template allocation is being used, the template is selected through the costing sheet and the overhead key.

• The planned costs are updated to the manufacturing order.

Page 10: CO Prod Costing Part 2

Phase and Operations in Recipe

10

• Master recipe contains operations and phases. An operation is performed on a primary resource. Operations are divided into phases. A phase is a self-contained work step that describes one part of the production process in detail. It uses the primary resource of the operation. Operations and phases can use secondary resources in addition to the primary resource.

• For each operation or phase, one or more materials that are required for the execution of that step can be defined

• In process manufacturing only the phases are costed, not the operations. A phase contains standard values for activities. These standard values are used to determine dates, capacity requirements, and costs. The relevant to costing indicator in the phase must be selected.

• If the materials list contains co-products, you can add additional co-products. You cannot, however, delete co-products from the materials list. To check whether a material component is relevant to costing, go from the materials list to the detail screen for the material.

• If no co-products are being used, the costs are updated to the order header.

Page 11: CO Prod Costing Part 2

Phase and Operations in Recipe

11

Phases contain “Standard Values”;

Operations do not

Page 12: CO Prod Costing Part 2

Results of Preliminary Costing

12

Page 13: CO Prod Costing Part 2

Results of Preliminary Costing

13

• A preliminary cost estimate is generated for the process order when it is saved or released, in accordance with the Customizing settings in the default values for the order type and plant.

• The order costs are calculated for the order header and distributed to the co-products on the basis of equivalence numbers. The equivalence numbers are entered in an apportionment structure.

When a process order is created, the system automatically generates the following:

• On the basis of the apportionment structure, the system generates a settlement rule that distributes the total order cost to the co-products (the order items). The costs are distributed to the order items both in the preliminary cost estimate and in the actual data.

• The system generates a settlement rule for each item, in accordance with the default rule. These settlement rules control the settlement of the distributed costs to materials.

Page 14: CO Prod Costing Part 2

Process Order

14

Page 15: CO Prod Costing Part 2

15

• Process orders are orders of order type 40 (process order).

• Process orders are usually analyzed by lot. That is, the variances are not determined until the order has the status delivered or technically completed. For orders that are analyzed by lot, SAP supplied default rule PP1 (Production Material Full Settlement) is assigned in the order type. This ensures that settlement type FUL (full settlement) is specified in the settlement rule for process orders of the relevant order type.

• A results analysis key must be specified in all manufacturing orders for which WIP needs to be calculated

• For preliminary costing and simultaneous costing, costing variant and valuation variant are defined in the order type. This defines the valuation procedure for materials, internal activities, external activities, and business processes. It also determines which overhead structure is used to calculate overhead.

Process Order

Page 16: CO Prod Costing Part 2

16

Process Order Process Chain

Page 17: CO Prod Costing Part 2

17

Process Order Simultaneous Costing

Page 18: CO Prod Costing Part 2

18

Process Order Simultaneous Costing

• Process orders are charged with actual costs through confirmations in Logistics.

• Charged with primary costs through material withdrawals (material back flushes, goods issues) that are generated automatically when the confirmation is entered.

• Charged with secondary costs through internal activity allocations that are executed automatically when the confirmation is entered.

• In addition, the goods receipt can be posted automatically when the confirmation is entered.

• Actual costs are charged to the order header as they are incurred. When a goods receipt for a co-product is posted, the order item is credited accordingly.

• To be able to see the actual costs for each co-product, it is required to perform the Preliminary Settlement for Co-Products, Rework function in the period-end closing process.

• Milestone operations (specified in Control key) must be confirmed specifically; Operations that are not milestones are automatically confirmed when the milestone is confirmed.

Page 19: CO Prod Costing Part 2

19

Process Order Process Chain

Page 20: CO Prod Costing Part 2

20

Preliminary Settlement of Process Order

Page 21: CO Prod Costing Part 2

21

Period End Closing Steps

Functions in the period-end closing of Product Cost by Order:

• Template allocation

• Revaluation of activity types and business processes at actual prices

• Calculation of overhead expenses

• Preliminary settlement of co-products, rework

• Calculation of work in process: In Product Cost by Order, the work in process is valuated at actual cost.

• Variance calculation

• Settlement

- Work in process is settled to Financial Accounting (FI)

- Order balance is settled to FI, Actual Costing/Material Ledger (CO-PC-ACT)

- Variance categories are settled to Profitability Analysis (CO-PA).

Page 22: CO Prod Costing Part 2

22

Process Order Costing

Work in processScrap

Variances

Settlement

Final CostingPeriod-End Closing

Preliminary Costing,Simultaneous Costing

Cost Object Controlling

Plan

Material $Labor $Overhead $Process $Total ...

Actual

Material $Labor $Total ...

Order Plan Actual WIP Target Variance Sett

Material

Labor

Overhead

Process

Debit

Credit

Stock Change

Periodic/ closing

activities

Order ReleaseGoods Issue, Confirmation, Goods Receipt

Overhead CalculationWIP Calculation

Variance Calculation

#

# Settlement

Page 23: CO Prod Costing Part 2

23

Sequence

Settlement

Work in Process

Overhead

Process Costs

Revaluation

Periodic Costs

Analyzing Costs

FI/CO -Posting

Scrap, Variances,Target Costs

Distribution for Co-Products

Page 24: CO Prod Costing Part 2

24

Preliminary Settlement of Process Order

• At the end of the period, the actual costs on the order header are distributed to the order items. This charges each co-product with its share of the actual costs. When it distributes the actual costs, the system uses the equivalence numbers defined in the apportionment structure.

• Preliminary settlement for co-products is carried out after period costs have been allocated to the header of the process order

• Actual costs must be distributed to the order items before you can calculate WIP and variances

• If an apportionment structure has not been specified in the material master record or in the production version, equivalence numbers should be entered for distribution in the settlement rule of the order header

Page 25: CO Prod Costing Part 2

25

Preliminary Settlement of Process Order

Reporting Before Distribution Reporting After Distribution

Page 26: CO Prod Costing Part 2

26

WIP Calculation

Page 27: CO Prod Costing Part 2

27

WIP Calculation

Work in process for co-products is always valuated at actual cost. The WIP is valuated using the actual costs posted to the order item less the credits from goods receipts.

Valuating WIP at actual cost requires that the order item have a settlement rule with settlement type FUL (full settlement). Settlement type FUL is derived from default rule PP1 (Production Material Full Settlement) which is specified in the order type. If a manufacturing order for co-products uses settlement type PER (default rule PP2), no work in process can be determined for it

The calculation of work in process depends on the status of the manufacturing order. The system continues to calculate work in process for the co-products until the header of the manufacturing order has the status DLV (delivered) or TECO (technically completed).

The manufacturing order only receives the status DLV when all order items have been delivered (Final Del Indicator is set). When the order has the status DLV and TECO, the WIP calculation function cancels any WIP from the previous period.

Page 28: CO Prod Costing Part 2

28

Process Order Process Chain

Page 29: CO Prod Costing Part 2

29

Variance Calculation

Page 30: CO Prod Costing Part 2

30

Variance Calculation

In the case of manufacturing orders that have co-products and whose order item has settlement type FUL, variances can only be calculated when all order items have been delivered (that is, when the delivery completed indicator is set for all order items and the status DLV is set for the order). For manufacturing orders without co-products that have the settlement type FUL, variances can only be calculated after the status DLV has been set for the order.

For manufacturing orders that have co-products for whose order item the settlement type is PER, the order balance is always interpreted as a variance (regardless of the status). No work in process is calculated for these manufacturing orders. For manufacturing orders without co-products that have the settlement type PER, variances and work in process are determined using the target cost calculation.

No scrap variances can be calculated for co-products. Therefore use a variance key for which the Scrap indicator is not selected.

Page 31: CO Prod Costing Part 2

31

Target Cost Concepts

Target Costs are the costs that should have been incurred to achieve a given “actual” output i.e. the benchmark cost for a given output.

The bench mark could be:

- Standard Cost Estimate of the material produced adjusted for the actual output. i.e. if the standard cost is $1000 for 100 units and in a process order only 40 units are produced then target cost is 40% of $1000 = $400

- Planned Cost (Preliminary Cost Estimate) of the Process Order

Target Cost Version 0 considers the “Standard Cost” as the benchmark cost and calculates the variance between “Adjusted Standard Cost” and “Actual Cost”

Target Cost Version 1 considers the “Planned Cost” as the benchmark cost and calculates the variance between “Adjusted Planned Cost” and “Actual Cost”

Target Cost is calculated ONLY if there is a receipt of finished product on a process order

Page 32: CO Prod Costing Part 2

32

Target Cost Concepts

Standard Cost based on year

beginning Recipe

Planned Cost of Order based on Current Recipe

Actual Cost of based on actual

consumption

Target Cost Version 0

Target Cost Version 1

• Shop-floor execution is held responsible/accountable for variances reported under Target Cost version 1

• Process Engineering Improvement department is held accountable for variances reported under Target Cost version 0

The above are very analogous to “Standard price”, “PO Price” and “Vendor Invoice Price” in a Purchase Cycle

Page 33: CO Prod Costing Part 2

33

Variance Categories: Overview

Variance Categories

Input Variance

Input Price Variance

Input Quantity Variance

Scrap Variance

Resource-Usage Variance

Output Variance

Lot size Variance

Output Price Variance

Mixed Price Variance

Remaining Variance

Remaining Input Variance

Page 34: CO Prod Costing Part 2

34

Variance Categories: Overview

Page 35: CO Prod Costing Part 2

35

Variance Postings

Stock Stock change

Price Difference

FINANCIAL ACCOUNTING

Productgroup

Region

Plant

PROFITABILITY ANALYSIS

Variances viaSettlement

Material 4,000 4,600

Labor 2,500 2,800

Overhead 1,500 1,600

Process 1,000 1,500

Glass 1,500 1,800

Total Costs 9,000 10,500

Cost ObjectCost Items Plan Actual

Delivery Value 9,000

Order Balance 1,500

Plug 2,000 2,200

Cable 500 600

FI:ONE Price DifferenceAccount per valuation class determined viaaccount assignment

Maximum Detail in CO-PA:One value field

per combinationvariance category

& cost element grouppossible

Page 36: CO Prod Costing Part 2

36

WIP / Variance relevance and valuation in

order based costing

Page 37: CO Prod Costing Part 2

37

Status Relevance

Order Status

Pre-Released or Released Partially Delivered Finally Delivered or Technically Completed

Variances

DeliveryValue

Actual Costs

WIPat Actual

=

Actual Costs

WIPat Actual

=

-Delivery

Value

Actual Costs

=

-

Page 38: CO Prod Costing Part 2

38

WIP Calculation

WIP at Actual Costs950

Material 4,000 600

Labor 2,500 200

Overhead 1,500 100

Process 1,000 50

Glas 1,500 150

Total Costs 9,000 950

Cost ObjectCost Items Plan Actual

Plug 2,000 300Cable 500 50

Page 39: CO Prod Costing Part 2

39

WIP at Actual Costs1,300

Material 4,000 2,300

Labor 2,500 1,400

Overhead 1,500 855

Process 1,000 745

Glas 1,500 900

Total Costs 9,000 5,300

Cost ObjectCost Items Plan Actual

Delivery Value 4,000

Order Balance 1,300

Plug 2,000 1,100Cable 500 300

WIP Calculation

Page 40: CO Prod Costing Part 2

40

WIP and Variance Calculation

Material 4,000 4,600

Labor 2,500 2,800

Overhead 1,500 1,600

Process 1,000 1,500

Glas 1,500 1,800

Total Costs 9,000 10,500

Cost ObjectCost Items Plan Actual

Delivery Value 9,000

Order Balance 1,500

Plug 2,000 2,200Cable 500 600

WIP at Actual CostsZero

Variances1,500

Page 41: CO Prod Costing Part 2

41

WIP Posting and Reversal

950

1,350

0

950

400

-1,350

FI

EC-PCA

FI

EC-PCA

FI

EC-PCA

Status Period WIP +/-

Page 42: CO Prod Costing Part 2

42

Accounting Entries

Page 43: CO Prod Costing Part 2

43

Goods Issue to Process Order

Expense Stock change

CustomersSales

Revenue

CreditStock

FI

Planned CostsRAW 10 $ACTIVITY 40 $BURDEN 60 $

Actual CostsRAW 12 $

PP Order HBL2810

PP Components issue to production order

Dr. 511230 Consumption a/c (Cost object = process order)

Cr. 116003 Raw Material Stock a/c(Standard Cost * Actual quantity issued)

Back flush: Quantity issued = Qty planned for actual production

Page 44: CO Prod Costing Part 2

44

Labor / Machine Costs (on Activity Confirmations)

Planned CostsRAW 10 $ACTIVITY 40 $BURDEN 60 $

Actual CostsRAW 12 $ACTIVITY 50 $

PP Order HBL2810

PP Labor or M/c hours issue to production

Dr. Process OrderCr. Cost Center (Secondary Cost Element)

(Std Activity price * Actual hours)

No FI entry. Only a statistical posting to Cost Center.

CO

Page 45: CO Prod Costing Part 2

45

Overheads Application

Planned CostsRAW 10 $ACTIVITY 40 $BURDEN 60 $

Actual CostsRAW 12 $ACTIVITY 50 $BURDEN 70 $

PP Order HBL2810

PPApply Overheads

Dr. Process OrderCr. Cost Center

(Std OH rate * Actual hours)

No FI entry. Only a statistical posting to Cost Center.

CO

Page 46: CO Prod Costing Part 2

46

Goods Receipt

Expense Stock change

CustomersSales

Revenue

CreditStock

FI

Planned CostsRAW 10 $ACTIVITY 40 $BURDEN 60 $

Actual CostsRAW 12 $ACTIVITY 50 $BURDEN 70 $

PP Order HBL2810

PP Receive Finished Product

Dr. 116013 FG Inventory a/cCr. 511315 Manufacturing output a/c (Cost object = process order)

(Std cost of finished product * qty received)

Factory output – 110 $

Process Order status is set to “Delivered”

Page 47: CO Prod Costing Part 2

47

Variance Calculation

Planned CostsRAW 10 $ACTIVITY 40 $BURDEN 60 $

Actual CostsRAW 12 $ACTIVITY 50 $BURDEN 70 $

PP Order HBL2810

PP Calculate Variance

No FI entry.Target cost and Variance are just

calculated and stored.

Factory output – 110 $

Variance - 22 $

Page 48: CO Prod Costing Part 2

48

Settlement

Expense Stock change

CustomersSales

Revenue

CreditProd Variance

FI

Planned CostsRAW 10 $ACTIVITY 40 $BURDEN 60 $

Actual CostsRAW 12 $ACTIVITY 50 $BURDEN 70 $

PP Order HBL2810

PP Settle production order

Dr. 511250 Production Variance a/cCr. 511315 Manufacturing output a/c (Cost object = process order)

Factory output – 110 $

Variance - 22 $

Balance in process order = zero

Page 49: CO Prod Costing Part 2

49

Activity Price Calculation (KSII)

Page 50: CO Prod Costing Part 2

50

Actual Activity Price Calculation

• Actual prices can be determined for activity types based on actual dollar costs spent on the cost centers and the actual absorption hours consumed during the month.

• The cost object is charged with the difference between the actual price and the price originally allocated to it.

Benefit: Cost center variances (Under/Over absorption can be allocated to materials produced and to analyzed by product lines)

Page 51: CO Prod Costing Part 2

51

Revaluation of allocated

activity types at actual prices

• Internal Orders•Sales Order line item•Other Cost Objects

Actual Activity Price Calculation

Page 52: CO Prod Costing Part 2

52

Actual Activity Price Calculation

Page 53: CO Prod Costing Part 2

53

Push Cost Center Variances to Product Lines

Transaction Cost Element

Production Cost center

Plant PC

Production Order

Product Line Profit center

Wages and other Exps Primary 100,000 100,000

Labor absorption Secondary (78,000) (78,000) 78,000 78,000

Material Consumption Primary 60,000 60,000

Finished Goods Std Cost Primary (132,000) (132,000)

Result

Under/(Over) Absorption 22,000 22,000

Production Variance 6,000 6,000

Costs get transferred from cost center (admin profit center) to product lines through process order

22000 2200028000 28000

0 0

Page 54: CO Prod Costing Part 2

Useful Transaction Codes

54

KSII: Activity Price CalculationCOR1,2,3: Process Order

For a Single Order:MFN1: Revalue Activity CostsCO8B: Preliminary SettlementKGI2: Overheads applicationKKS2 : Variance CalculationKKAX: WIP CalculationKKAY: Display WIPKO88: Settlement

S_ALR_87013611 – Cost center ReportS_ALR_87013167, Z3167 – Process Order Cost ReportS_ALR_87013161 – Report for multiple orders

For the entire plant:CON2: Revalue Activity CostsCO8A: Preliminary SettlementCO43: Overheads applicationKKS1 : Variance CalculationKKAO: WIP CalculationKKAQ: Display WIPCO88: Settlement

COGI: Material Movement ErrorsCOFC: Confirmation Errors

Confirmations:CORK: Enter, CORT : DisplayCORS : Cancel

Page 55: CO Prod Costing Part 2

55