civil engineering construction - binaan kejuruteraan · pdf filecivil engineering construction...
TRANSCRIPT
7/15/2012
1
Civil Engineering ConstructionChapter 4
Introduction to Formwork
Dr Mohamad Syazli Fathi
Department of Civil EngineeringUTM RAZAK School of Engineering & Advanced Technology
UTM International Campus
July 15, 2012
DDA 2132 Timber/Formwork Design
Introduction to Formwork
DDA2132 - Timber/Formwork Design
2
7/15/2012
2
Temporary Structures (TS)
• Definition– Any means or methods which provide
temporary support (TS), access, enhancement, or otherwise facilitate the construction of permanent structures.
• Necessity
DDA2132 - Timber/Formwork Design
3
– TS form the interface of design and construction. Most permanent structures simply could not be built without TS.
Temporary Structures (continued)
• Impact on Schedule, Cost, and Quality– Losses in time and money will occur if the TS are not
planned and coordinated with the same degree of thoroughness as the permanent structures.
• Safety
DDA2132 - Timber/Formwork Design
4
– Failure of TS have been responsible for hundreds of deaths on construction sites. Safety should be the overriding priority of contractors and designers responsible for implementing TS.
7/15/2012
3
Categorizing Temporary Structures
• Several common types of work which• Several common types of work which occur on construction sites are:– Formwork– Falsework– Rigging
DDA2132 - Timber/Formwork Design
5
– Scaffolding– Excavation support– Miscellaneous (site specific)
Responsibility
• The norm in construction industry is to place the responsibility for TS solely on the general contractor. However, architects and engineers must at least have formulated their own method of construction.
DDA2132 - Timber/Formwork Design
6
• Coordinating the design of permanent structure with the TS that will be required can lead to more efficient and cost effective construction.
7/15/2012
4
Design Consideration
• Safetyi l h fi i i f OS A– Designers must place the first priority on safety. OSHA
codes, as well as other codes in the industry, provide stringent performance specifications (how the system should work) regarding TS.
• Cost– TS can be the most expensive part of some construction
j t D i i t ff ti l ti t TS
DDA2132 - Timber/Formwork Design
7
projects. Designing cost-effective solutions to TS problems could easily be the competitive advantage of a contractor over others. The designer must have a thorough knowledge of all the options which will sufficiently solve the TS problem.
Design Consideration (continued)
• Unique Design Challenges– TS are subject to unique loading conditions which do not
apply to a permanent structure (fluctuating or dynamic loads, impact loads, loads which change position).
– Working within spatial constraints- Cramped sites require the most efficient TS so that workers still have room to maneuver safely.
DDA2132 - Timber/Formwork Design
– Uncertainty of soil conditions- It is always possible that an unforeseen condition could arise during an excavation. Designers must include an appropriate factor of safety in their calculations or they may consider contingency plans for changing soil conditions.
7/15/2012
5
Concrete Formwork (FW)
• Forms are TS that provide containment for the freshForms are TS that provide containment for the fresh concrete and support it until it can support itself.
• Forms must be designed to support loads of the fresh concrete, equipment, workers, impact of various kinds, or sometimes wind without collapse or excessive deflection.
DDA2132 - Timber/Formwork Design
9
• The cost of FW is between 40% to 60% of the cost of concrete structure. Design of a good forming system could both expedite a project as well as reduce costs.
Formwork Requirements - 1
• Safety – FW must be:• Safety FW must be:– Strong ( to carry the full load and side pressure
from freshly placed concrete, together with construction traffic and equipment).
– Sound (made of good quality, durable materials).
DDA2132 - Timber/Formwork Design
10
7/15/2012
6
Formwork Requirements - 2
• Quality – FW must be:A ( i hi ifi d l f f– Accurate (within specified tolerances for form dimension)
– Rigid (adequately braced and tied to prevent movement, bulging, or sagging during construction).
– Tight Jointed (to prevent cement paste leakage which disfigures the surface of concrete)
DDA2132 - Timber/Formwork Design
11
disfigures the surface of concrete).– Properly Finished (to provide a concrete surface of
good appearance).
Formwork Requirements - 3
• Economy – FW must be:• Economy FW must be:– Simple (simple to erect and dismantle)– Easily handled (the sizes of units should not be
too heavy to handle)– Standardized (ease of assembly and possibility
of reuse)
DDA2132 - Timber/Formwork Design
12
)
7/15/2012
7
Causes of Failures
• Improper stripping and shore removal• Improper stripping and shore removal• Inadequate bracing• Vibration• Unstable soil under mudsill, shoring not plumb• Inadequate control of concrete placement.
DDA2132 - Timber/Formwork Design
13
• Lack of attention to FW details• When FW is not at fault
DDA2132 - Timber/Formwork Design
14
7/15/2012
8
DDA2132 - Timber/Formwork Design
15
DDA2132 - Timber/Formwork Design
16
7/15/2012
9
DDA2132 - Timber/Formwork Design
17
Planning for Formwork
• The contractor should plan FW at the time ofThe contractor should plan FW at the time of making bid considering the following factors:– Placing schedule and stripping time requirements– Capacity of equipment available to handle form sections and
materials– Capacity of mixing and placing equipment– Construction joints
Re se of forms as affected b stripping time
DDA2132 - Timber/Formwork Design
18
– Reuse of forms as affected by stripping time– Relative merits of job-built, shop-built and ready-made forms.– Weather (protection requirements and stripping time)
• Compare alternative methods to determine the most efficient plan.
7/15/2012
10
Key area of Cost Reduction - 1
• Planning for maximum reuse• Planning for maximum reuse– A form designed for max reuse is stronger and more expensive, but
it can save on the total form cost.
• Economical form construction– Shop-built (greatest efficiency in working conditions and in the
purchase and use of materials and tools)– Shop area on the site (form sections too large or transportation cost
DDA2132 - Timber/Formwork Design
19
Shop area on the site (form sections too large or transportation cost too high)
– Job-built (for small jobs, or where forms must be fitted to terrain)
Key areas of Cost Reduction - 2
– Buying prefabricated forms(large number of reuses)R i f b f (b fl ibili i l i– Renting prefab forms(better flexibility in regulating volume of work)
• Setting and stripping– Repetition of the same functions to increase the crew
efficiency as the job progresses
20
– Use of metal clamp or special wedge pin connections that are secure, yet easy to assemble and dismantle
– Add extra features that make handling, erection, and stripping easier (handles, lifting eyes)
7/15/2012
11
Other costs affected by FW - 1
• Cranes and Hoists• Cranes and Hoists– Size of form sections should be limited to the capacity of the
largest crane planned for the job.– Stair towers may be completed early in the schedule to be used for
moving men and materials.– Leave one bay open to permit mobile crane and concrete truck
movement.
DDA2132 - Timber/Formwork Design
21
• Bar Setting– Form design can permit the rebar to be pre assembled before
installation (more favorable condition)
Other Costs affected by FW - 2
• Concrete Placement• Concrete Placement– High lifts in wall construction make placing and vibration difficult.– Placing rate is limited by form design.
• Other Trades– The plan should permit other trades to perform their work
DDA2132 - Timber/Formwork Design
22
efficiently and minimize interruptions in placing.
7/15/2012
12
DDA2132 - Timber/Formwork Design
23
DDA2132 - Timber/Formwork Design
24
7/15/2012
13
DDA2132 - Timber/Formwork Design
25
DDA2132 - Timber/Formwork Design
26