King Abdullah Bin Abdulaziz
Technical & Vocational Training Center
BOQ Ground, First, Second and Third Floors works
King Abdullah Bin Abdulaziz Technical Vocational Training Center
Civil Works
Bill No. 1 Excavation and Earth Works
Item No
Description Unit QTY Price/
Unit Total
The Contractor shall when pricing the rates of this bill, take into consideration including and allow for the cost or expenses of all requirements stipulated in the preambles, drawings, and technical specifications. The words engineer below means owner's engineer. The rate include the following:
The contractor has to supply a Mesh Survey plan 5mX5m for the site from approved engineering surveyor before and after the works for quantities measurements .
The Contractor should present a soil investigation report from an approved laboratory as per engineering association equipments and standards on his own expenses.
Excavation and backfilling for Working Space will not be measured .
In case and after the soil investigation report is done it was required to do more excavations, all excavations work will be carried over the bid unit price, the Contractor has no right for any kind of claims or any unit price change .
1.1
Cut in any kind of soil, concrete or stone walls to reduce level for site leveling and to reach the desired level(Below basecoarse layer) according to drawings and site instructions .The price should include using and laying the approved fill material from site and or from outsite to reduce level and all test required to use the approved cut material for filling and watering ,compacting 100% each layer 20 cm and removing the unapproved excavated materials from the site to an approved dump location.
m3 5800
1.2
Ditto but excavation for footings , ground beams, neck wall and tie beams, the price should include soil Investigation total boreholes depth 36m after site leveling from approval laboratory and as shown on drawings and specifications and engineer instructions.
m3 400
1.3
Supply and Lay selected & approved base coarse filling First class at 20cm layer to the required level ,watering and compacting 100% and where directed by the Engineer.
m2 400
Total of Bill No. 1
1 of 25
King Abdullah Bin Abdulaziz Technical Vocational Training Center
Civil Works
Item No Description Unit QTY Price / Unit Total
2 Concrete Works
The contractor shall, when pricing the rates of this bill, take into consideration including and allow for the costs or expenses of all requirements stipulated in the preambles, drawings and technical specification of the tender.
Each concrete pouring on site will be tested, pouring less than 6m3 will be tested, pouring more than 6m3 will also be tested on 6m3 portions i.e. each concrete truck on site will be tested, all done by an approved testing institute on contractors expense
The price should include cleaning all the foundation excavations, checking the sizes according to drawings, resizing if needed, cleaning, and installing wooden frame to marked the footings as instructed and approved by the site engineer
In case and after the soil investigation report is done, concrete quantities may vary,any Additional or less in bid quantities will be carried over the bid unit price, the Contractor has no right for any kind of claims or any unit price change .
2.1 PLAIN IN-SITU CONCRETE B200[200 Kg / CM2]
Supply & install Concrete B200 of 28 days cube crushing strength 200kg/cm2. Price shall include cleaning, compaction, shuttering and making good of ground surface before casting of concrete. Price shall include all nails, forms and equipments needed.
2.1.1- Blinding under footing, ground beams and raft foundation
m3 40
Bill No. 2 Concrete Works
2 of 25
King Abdullah Bin Abdulaziz Technical Vocational Training Center
Civil Works
Item No Description Unit QTY Price / Unit Total
Bill No. 2 Concrete Works
2.2 REINFORCED IN-SITU / READY MIXED CONCRETE
B300/ 300 Kg / CM2]
Supply & install concrete B300 of 28 days cube crushing strength 300kg/cm2. Price shall include the following:1. Cleaning and making good of surfaces before casting of concrete2. Steel reinforcement workmanship as per drawings.3. Form-work of any type or shape .4. Any materials such as nails, wires , 6mm steel for shuttering or any other material or workmanship needed for a best completion of the works .5. Installation of 2 cm thick. high density polystyrene on expansion joints.6. All steel reinforcement of any diameter and shape of high yield stress steel.7. Cube test 10x10x10cm and slump test before pouring any concrete on site, and vibration the concrete during casting . 8. Supply and install Polystyrene Blocks for Ribbed slabs as per Drawings and Structural notes. 9- isolation all buried parts using approved butimunies layer (hot or cold ) as per site engineer instructions and approval.
The measurement for slabs from the middle of the walls , and include all drop and inverted beams and any part casted with slab, also deduction any opining in the slab(engineering measurements ) .
2.2.1Foundation of any shape, depth and size including column foundations, ground beams and strip footings , when pricing the contractor has to take the followings
A- Check and report to the site engineer the situation of the excavation by an approved surveyorB- Clean the foundations excavations, and making good of any excavation if needed
m3 135
C- Resize the excavations to suit the design if there was any mistake in the excavation processD- Lay a wooden Works Frame Reference around the building to be referenced by an approved surveyor and approved by the site engineer
2.2.2
Tie Beams and Neck wall of any shape, depth and size including column foundations, and tie beams, when pricing the contractor has to take the followings into considerationA- Check and report to the site engineer the situation of the excavation by an approved surveyorB- Clean the foundations excavations, and making good of any excavation if needed
m3 75
C- Resize the excavations to suit the design if there was any mistake in the excavation processD- Lay a wooden Works Frame Reference around the building to be referenced by an approved surveyor and approved by the site engineer
3 of 25
King Abdullah Bin Abdulaziz
Technical Vocational Training Center
Civil Works
Item No Description Unit QTY Price / Unit Total
Bill No. 2 Concrete Works
2.2.3
For concrete columns and column necks B-300,
maximum size of aggregate 20mm as shown on
drawings.
m3 120
2.2.4Ditto but columns concrete B-400 as shown on
drawings.m3 30
2.2.5
For bearing walls, bearing walls necks, retaining walls
and bracing beams where needed as per site engineer
instructions the price include the steel and concrete
columns and formwork inside the bearing wall and as
shown on drawings .
m3 220
2.2.6
For 12cm Thick slab on grade with Ф10mm 20x20cm
steel mesh reinforcement. The price includes 500
micron thick polyethylene membrane.
m2 175
2.2.7
Ditto but fair face for slab on grade(Parking Area) using
machine helicopter, the price include expansion joint
thick 2cm each block 4X4m and filling the joint with
rode diameter 2cm and sika flex depth 2cm and
instructed by the engineer .
m2 235
2.2.8.aFor Reinforced Ribbed slab Thickness 36cm as shown
on drawings and instructed by the site engineer, m2 1360
2.2.9For well reinforced Solid slab Thickness 25cm as
shown on drawings and instructed by the site engineerm2 35
2.2.10
For stairs ,flights and landings of different
thicknesses,Rate will includes all connections
scaffoldings and steel reinforcement as shown on
drawings (measurements will be for the horizontal
projection of flight and stairs ).
m2 100
2.2.11
Supply and install concrete B-200 for inclined 1.0% roof
screed , the minimum thick 5 cm at rain pipe, marks
should be approved prior to commencement,
mechanically finish all as instructed by the site engineer
m2 360
Total of Bill No. 2
4 of 25
King Abdullah Bin Abdulaziz Technical Vocational Training Center
Civil Works
Item No
Description Unit QTY Price / Unit Total
3 Stone Works
3.1 STONE BUILDING AND POINTING
The contractor shall, when pricing the rates of this bill, take into consideration including and allow for the costs and expenses of all requirements stipulated in the preambles, drawings and technical specification of the contract. The price includes the following:
All stone should be from Hebron area dark colour class A-A, بند ارضي, with the following specifications:
- Absorption by weight should not exceed 0.9% using ASTM test method C97
- Density (Kg/m3) should not be less than 2700Kg/m3 using ATSM test method C97
- Compressive strength should not be less than 56MPa using ATSM test method C170
- Modulus of rupture should not be less than 6.9MPa using ATSM test method C99
- Abrasion resistance (hardness) should not be less than 10 using ATSM test method C241 - stone should be clear, free from all veins, cracks and salt holes from both sides
1. Steel anchors as specified.2. Flush pointing works composed of white cement and sand (1: 2) with approved additives for better workability, tightness and water proofing. 3. Ф8mm 20X20cm steel mesh reinforcement to be used for all stone concrete backing.4. Stone built shall be measured only " Net Measurements "
Bill No. 3 Stone works
5 of 25
King Abdullah Bin Abdulaziz Technical Vocational Training Center
Civil Works
Item No
Description Unit QTY Price / Unit Total
Bill No. 3 Stone works
5. Each building stone must have at least two galvanized anchors from the top and to be fixed to the 3mm steel mesh.6. Acceptance of delivered stones should be carried by comparing every stone delivered on the truck to the sample built on site. All stones will be picked up and chosen by a specialist person (dresser) paid by the Contractor before using the stone.7. Rate includes any kind of stone dressing.8. Copping stones to be Mutabbeh finish for the horizontal surface and Taltish finish for the vertical sides. 9- Price should include supply and install extruded polystyrene 30 mm thick as per drawings and site engineer instructions and approval .
3.1.1
Supply and install 5 cm thick 25cm height TALTEESH stone courses the price including all special pieces i.e. jams, lintels, sills and stone corners (at least 15cm deep), as shown on drawings. The price includes B200 concrete backing with varies thickness according to drawings, anchors and steel reinforcement,glans plastering layer on concrete backing and extruded polystyrene sheet of 30 mm thick all as shown on drawings, instructed and approved by the site engineer
m2 730
3.1.2Supply and build 5cm Thick stone copping width in any location as shown on drawings
m2 60
3.2.3Supply and build 5cm Thick stone sills width 15cm for windows to be build from outside as shown on drawings
m.r. 80
6 of 25
King Abdullah Bin Abdulaziz Technical Vocational Training Center
Civil Works
Item No
Description Unit QTY Price / Unit Total
Bill No. 3 Stone works
3.2 Stone Cladding
Supply, install stones cladding of excellent quality grade A-A " بند ارضي " with different thickness dressed Mulatash free from cracks. Rate for stone cladding shall include for:
All stone should be from Hebron Area dark colour class A-A, بند ارضي, with the following specifications:
- Absorption by weight should not exceed 0.9% using ASTM test method C97 - Density (Kg/m3) should not be less than 2700Kg/m3 using ATSM test method C97 - Compressive strength should not be less than 56MPa using ATSM test method C170 - Modulus of rupture should not be less than 6.9MPa using ATSM test method C99 - Abrasion resistance (hardness) should not be less than 10 using ATSM test method C241 - stone should be clear, free from all veins, cracks and salt holes from both sides
1. Work for all classification in any location.2. Stone shall have a minimum thickness of 5cm after dressing with a rough back preferably.3. Stone built shall be measured only " Net Measurements "4. Stone sills and lintels of any kind shall be measured within the stone building and not separately
7 of 25
King Abdullah Bin Abdulaziz Technical Vocational Training Center
Civil Works
Item No
Description Unit QTY Price / Unit Total
Bill No. 3 Stone works
5. Corner and jambs stone of any kind shall be measured within the stone building and not separately6. Key stone and any other particular stone shall be measured within the stone building and not separately7. Price shall include concrete backing and Ф6 mm @ 20cm welded steel mesh and steel reinforcement for lintel beams.8. Stones with quality grade A-A (بند ارضي) shall be used only.9. Acceptance of delivered stones should be carried by comparing every stone delivered on the truck to the sample built on site. All stones will be picked up and chosen by a specialist person (dresser) paid by the owner before using the stone.10. Flush pointing works composed of white cement and sand (1: 2) with approved additives for better workability, tightness and water proofing.
3.2.1
Supply and install 5 cm thick 25cm high, stoneTaltish courses of first quality the price (دقة ناعمة بدون زملة)including all special pieces i .e. jams and lintels and stone corners, of depth not less than 25cm. The price includes 7-10cm thick B200 concrete backing,steel mesh and galvanized wire to tie the stone to the steel mesh as shown on drawings.The rate includes for walls and around columns and all special pieces
m2 730
Total of Bill No. 3
8 of 25
King Abdullah Bin Abdulaziz Technical Vocational Training Center
Civil Works Bill No. 4 Block Works
Item No
Description Unit QTY Price / Unit Total
4 BLOCK WORK BUILDING
The contractor shall, when pricing the rates of thisbill, take into consideration including and allow forthe costs or expenses of all requirementsstipulated in the preambles, drawings andtechnical specification of the contract.
The price include lintel concrete beam andscaffolding above all blocks with height 20cm withsteel 4Ф12mm and stirrups Ф8mm/20cm
For the double Block wall Price should includesupply and install expanded polystyrene sheetthick 3 cm between walls as per drawings.
Precast Concrete hollow nonloading bearingblocks built in cement sand mortar (1:3) mix asspecified. All opening to be closed with blocks aremeasured in m2 of correspondent thickness.
Engineering measurement all openings must bededuction . The measurement engineeringdeduction all opening
4.1 7 cm thick hollow blocks. m2 450
4.2 10 cm thick hollow blocks. m2 1200
4.3 15 cm thick hollow blocks. m2 60
Total of Bill No. 4
9 of 25
King Abdullah Bin Abdulaziz Technical Vocational Training Center
Civil Works
Bill No. 5 Plastering Works
Item No
Description Unit QTY Price / Unit Total
WALL AND CEILING PLASTERING
5 Internal Plaster
The contractor shall, when pricing the rates of this bill, take into consideration including and allow for the costs or expenses of all requirements stipulated in the preambles, drawings and technical specification of the contract.
Prepare surfaces, apply a rendering coat (رشة مسمار),apply in two coats of rough and fine finish withordinary Portland cement , sand and lime asspecified. The price includes angle beads andmovement beads.
The measurement engineering , deduction allopening .
5.1
On walls and ceiling 13mm thick plaster includingpatching works for any mechanical, electrical or civilworks. Price should include supply and install steel wiremesh 200 mm wide , cloth mesh and galvanized steelor aluminum angel 2 m length where required, All asper site engineer instructions .
m2 4800
5.2 Ditto but for external plastering mixing with Begebond. m2 120
Total of Bill No. 5
10 of 25
King Abdullah Bin Abdulaziz
Technical Vocational Training Center
Civil Works
Item
NoDescription Unit QTY Price / Unit Total
6 Tiling Works
The Contractor shall when pricing the rates of this
bill, take into consideration including and allow for
the cost or expenses of all requirements stipulated
in the preambles, drawings, and technical
specifications.
Unit rate shall includes all designs and cutting as
per drawings with no allowance for wasted tiles.
Net engineering measurements on site for square
meter will be considered.
Unit rates for tiling works shall include the
completion of works according to all details shown
on drawings. The rate includes the pointing or
grouting as specified, the crystal polish of terrazzo
tiles.
Tiling should be done using WHITE CEMENT only,
even if not specified in the item
6.1 Ceramic or Porcelain Tiles
6.1.1
Supply and Install Ceramic or porcelain for floor & wall
Tiles in patterns first choice and free from all defects.
with 5mm spacing and to be pointing with a water
resistant grout like Mapei and cleaning on site. Price
to include the mortar (White Cement) (1:3). The type,
colour and size shall be approved by Engineer the price
include, transportation, tiles cutting galvanized angle for
corners and as shown on drawings
m2 430
6.2 Terrazzo Tiles
Supply and install the following class A terrazzo local
tiles size30X30X3cm Chips number 4 with a pattern
as per drawings. All bedded in , or backed with white
cement and sand mortar (1:3) . The price shall
include the supply and spreading of a layer of sand and
Portland cement dry mixture under tiles and
grouting with white cement thick 3mm (grouting colour
will be given by owner) the price also include supply
and install skirting the same as terrazzo tiles high 7cm
6.2.1 To Floors m2 1100
Bill No. 6 Flooring
11 of 25
King Abdullah Bin Abdulaziz Technical Vocational Training Center
Civil Works
Item No
Description Unit QTY Price / Unit Total
Bill No. 6 Flooring
6.3 Stone Tiling1- All as per stone samples on site for colour, quality and shape.2- All stone tiles shall be free from cracks with quality grade A-A (بند ارضي) .3- Rates for tiles shall include for straight and curved cutting, waste, grouting and pointing to execute the works to the satisfaction of the Engineer.4- All stone tiles will be picked up and chosen by a specialist person (dresser) paid by the owner before using the stone. - Absorption by weight should not exceed 0.9% using ASTM test method C97 - Density (Kg/m3) should not be less than 2700Kg/m3 using ATSM test method C97 - Compressive strength should not be less than 56MPa using ATSM test method C170 - Modulus of rupture should not be less than 6.9MPa using ATSM test method C99 - Abrasion resistance (hardness) should not be less than 10 using ATSM test method C241 - stone should be clear, free from all veins, cracks and salt holes from both sides
6.3.1
Supply and install approved natural stone polished for stair flight thick 3cm for tread and 2cm for riser the price include cement mortar under the stone and filling cement:sand 1:1 below the tiles the price include stone panels and skirting for water resist and as shown on drawings .
m.r. 210
6.3.2
Supply and install approved natural stone polished for stair landing thick 3cm size 60x30 the price include cement mortar under the stone and filling cement:sand 1:1 below the tiles the price include skirting30x7 thick 1cm and grouting with white cement and as shown on drawings .
m2 50
6.3.3 Ditto but stone door thresholds, 3cm thick m2 10
6.3.4
Supply and install approved natural stone tiles for top roof thick 5cm size 60x30 the price include cement mortar under the stone and filling cement:sand 1:1 below the tiles the price include skirting30x7 thick 1cm and grouting with white cement and as shown on drawings .
m2 60
Total of Bill No. 6
12 of 25
King Abdullah Bin Abdulaziz Technical Vocational Training Center
Civil Works
Bill No. 7 Water Proofing
Item No
Description Unit QTY Price / Unit Total
7 Water Proofing
The contractor shall, when pricing the rates of this bill, take into consideration including and allow for the costs or expenses of all requirements stipulated in the preambles, drawings and technical specification of the contract.
7.1
Supply and install 4 mm thick layers for top roof and agricultural path of modified bituminous membrane like Pazkar SBS 5/250 laid above two primer coats of GS474 at a rate of .25 kg /m2 or equivalent approved by the engineer on a clean surface of the roof tiling and around the parapets. The price includes supply and install sealant cover at groove" Sikaflex-pro 2HP or equivalent" . The price includes also supply and install 15*15cm angle fillet as shown in the drawings and painting the joints with "Silver PAZ". The application should be carried out in conformity with the manufacturers’ specifications and using propane torch welding only. The measurement horizontal dimension .
m2 550
7.2
Supply and install 4 mm thick layers for walls under natural ground of modified bituminous membrane like Pazkar SBS 5/250 laid above two primer coats of GS474 at a rate of .25 kg /m2 or equivalent approved by the engineer the price include make glanz layer cement:sand (1:1) on concrete wall on a clean surface and the price include also protection the insulation layer with polystyrene sheet 2cm and supply and install block 7cm and as shown on drawings . The measurement horizontal dimension .
m2 500
7.3
Supply and apply two coat of Sika Top Seal 107 or equivalent on a clean surface for the wet areas. The price includes 5*5cm angle fillet with smooth sand cement mortar (1:3) surface layer before applying the water proofing materials. The application should be carried out according to details and in conformity with the manufacturers’ specifications price include testing as instructed by the site engineer. The measurement horizontal dimension .
m2 260
Total of Bill No. 7
13 of 25
King Abdullah Bin Abdulaziz Technical Vocational Training Center
Civil Works
Item No Description Unit QTY Price / Unit Total 8 Metal Works
The contractor shall, when pricing the rates of this bill, take into consideration including and allow for the costs or expenses of all requirements stipulated in the preambles, drawings and technical specification of the contract.
The rate for steel works includes the following:
A. The submittal of shop drawings for the satisfaction of the Engineer prior to fabricating the units.B. The fabrication and installation of full scale model for part of metal works for inspection and approval of the Engineer before commencement of work.
8.1 ALUMINUM WORKS
Supply and install the following colored (powder coated, Migor'an) Dark gray Metallic color as per sample on site, Aluminum Mifromal Profile as made by NABCO , as shown on drawings ( All hinges and handles have to be powder coated same color as aluminum
Price shall include laminated glass 4/9/4mm , Ironmongery, fixing accessories original from Mifromal or Arpal such as rails, hinges, locks, brushes, rubber EPDM and angles must be original corresponding to each profile.Filling all sides and under the threshold and sills with SIKA FLEX 2H Pro color as of the aluminum color from out side and all exposed joints and MASTIC (NIRLAT made) from inside colored as the aluminum color All as instructed by the site engineer
Supply and install the followings ALUMINUM 7700 combinations NAPCO doors and windows, as per drawings and specifications, all as instructed by the site engineer
8.1.1AW01 with overall dimensions of (1.76x1.20m) As per drawings and Details.
No. 12
8.1.2AW02 with overall dimensions of (1.50x0.90m) As per drawings and Details.
No. 8
8.1.3AW03 with overall dimensions of (1.60mx1.50) As per drawings and Details.
No. 1
8.1.4AW04 with overall dimensions of (2.0x1.50m) As per drawings and Details.
No. 1
8.1.5AW05 with overall dimensions of (1.50x0.50m) As per drawings and Details.
No. 12
Bill No. 8 Metal Works
14 of 25
King Abdullah Bin Abdulaziz Technical Vocational Training Center
Civil Works
Item No Description Unit QTY Price / Unit Total
Bill No. 8 Metal Works
8.1.6AW06 with overall dimensions of (2.02x2.00m) As per drawings and Details.
No. 10
8.1.7AW07 with overall dimensions of (2.02x0.90m) As per drawings and Details.
No. 2
8.1.8AW08 with overall dimensions of (2.02x1.80m) As per drawings and Details.
No. 2
8.1.9AW09 with overall dimensions of (2.02x1.60m) As per drawings and Details.
No. 1
8.1.10AW11 with overall dimensions of (2.02x1.90m) As per drawings and Details.
No. 7
8.1.11GD01 with overall dimensions of (1.80X2.71m) As per drawings and Details.
No. 1
8.1.12GD02 with overall dimensions of (2.00x2.86m) As per drawings and Details.
No. 2
8.1.13GD03 with overall dimensions of (3.20x2.86m) As per drawings and Details.
No. 1
8.1.14GD06 with overall dimensions of (3.00X2.71m) As per drawings and Details.
No. 1
8.1.15GD07 with overall dimensions of (2.00x2.71m) As per drawings and Details.
No. 1
8.1.16GD08 with overall dimensions of (0.80x2.00m) As per drawings and Details.
No. 1
8.1.17 Solar wall as per drawings and details. m2 30
8.1.18 solar chimney as per drawings and details m2 20
8.1.19 Window elevation in entrance size 2.60X3.55 No. 1
15 of 25
King Abdullah Bin Abdulaziz Technical Vocational Training Center
Civil Works
Item No Description Unit QTY Price / Unit Total
Bill No. 8 Metal Works
8.2 Steel Works
The rate for steel works includes the following:
A. The submittal of shop drawings for the satisfaction of the Engineer prior to fabricating the units.
B. The fabrication and installation of full scale model for part of metal works for inspection and approval of the Engineer before commencement of work.
C. cleaning of all steel profiles prior to commencement with painting layers as specified and shown in drawings.
D. Supply all kinds of material and apply two coats of APC primer (ORANGE COLOR) Product Code: , drying period 3 days between each product
E. Supply all kinds of material and apply painting for steel, the price should include applying two coats of HAMMERITE paint with HAMMERITE dissolvent all as approved and instructed by the site engineer. The application should be carried out according to details and in conformity with the manufacturers’ specifications.
Supply and install the following steel doors, price to include cylinder, lock as made by WALLY, or approved eq., as a complete job,as shown on drawings.
8.2.1SD01 with overall dimensions of (1.20x2.71m) as shown on drawings
No. 1
8.2.2SD02 with overall dimensions of (2.27x3.38m) Louvers door as shown on drawings
No. 1
8.2.3SD03 with overall dimensions of (0.90x2.03m) as shown on drawings
No. 5
8.2.4
SD00 Garage galvanized Door 2mm from both side insulation with Foam with overall dimensions of (4.00x2.60m)the price include main steel frame 100X100X3.25mm to be fixed in the wall and z to be welding in the main frame and from the inside 100X50X3.25mm as shown on drawings
No. 1
8.2.5
Supply and install steel hand rails and stair rails, price to include all sections and stainless steel brushed 45mm diameter handle as shown on detailed drawings, instructed and approved by the site engineer
mr 55
8.2.6supply and install metal protection bars for windows and as shown on drawings .
m2 18
Total of Bill No. 8
16 of 25
King Abdullah Bin Abdulaziz Technical Vocational Training Center
Civil Works
Item No
Description Unit QTY Price /
Unit Total
Carpentry Works
The Contractor shall when pricing the rates of this bill, take into consideration including and allowing for the cost or expenses of all requirements stipulated in the preambles, drawings, and technical specifications.Wooden works shall include the following:
The contractor shall consider that all materials, woods, accessories, paint and the final work as whole to withstand the hard weather and humidity and counteract corrosion as much as possible.
In case that any specification stated below is not compatible with the above requirements the contractor will be fully responsible for the work.
1. Submittal of shop drawings prior to fabricating the units.2. The fabrication and installation of full scale model for part of wooden works for inspection and approval of the Engineer before commencement of work knowing that the sample is not part of the works and will not be paid for.
3. Veneers to be 6mm PLY wood
4. All external natural wood ( as per drawings and site engineer instructions) should be colored with water base color SIRCA made to be chosen by client, 2 coats of sealer with sanding between each layer, then one coat of
laquare paint SIRCA made. 5. All internal wood should be colored with alcohol based color , to be chosen by client ( the contractor should supply painting samples ) 3 coats of sillar base paint, and 2 coats of varnish ( Sirka type ) semi gloss, as per manufacturer's instructions.
5. All solid wood to be made of red OAK wood to be excellent quality American hard wood.
6. Solid wood is to be dry wood with humidity ratio not more than 9%. Humidity ratio in different samples chosen by the engineer to be tested by a renowned testing institute on the contractor expense.7. The contractor shall use screws ( Nail not accepted) in fixing mongery. The used glue should be Super sticky 99.
Bill No.9 Carpentary Works
17 of 25
King Abdullah Bin Abdulaziz Technical Vocational Training Center
Civil Works
Item No
Description Unit QTY Price /
Unit Total
Bill No.9 Carpentary Works
8- All wooden accessories and iron mongery to be Nerosta color ( Brushed stainless steel), Samples to be approved by Architect
9- The contractor shall use sealant material all around wooden frames (such as but not limited to;Sikaflex-Pro 2HP ) during installation, and make good after and coloring and painting wall
9.1 Wooden doors & windows
Supply and install the following wooden doors, windows and frames complete with all necessary fixing accessories, glazing, hardware and iron mongery. All as shown in detailed drawings. The rate shall include the the supply and install of the following:-
1- Supply and install heavy duty hinge, 3 hinges for each door leaf Domicile 220 C 4*3.52- Supply and install locks for doors WALLY original type. Including cylinder, Master key system, Hyraychi should be approved by the owner prior to fabrication
3- Supply and install upper and lower lockers for each door Domicile AGB No. 320 - 400
4- Supply and install door handles type Domicil Type RO 11 - RY (Brushed Nikel Color)
5- supply and install special lock with for all upper keep windows. And two hinges for each leaf Domicile CEAM No. 2010.
6- All exposed edges, louvers and door frames are excellent quality hard American red OAK wood.
7- Glazing should be according to drawings
8- All doors' leaves to have stoppers from Domicile ref. DH003, All widows' leaves to have stoppers from Domicile ref. DH011.
WOODEN DOORS
Supply and install the following 45mm thick PLY wood doors, price to include PINE wood door frame and all iron accessories as instructed and approved by the site engineerPrice to include painting (Door & Frame)oil paint primer, 2 layers of PUTTY APC, 2 coats of under coat as made by APC or an approved eq. and 3 coats of APC ARAMAT as instructed and approved by the site engineer
9.1.1WD01, Double door with and overall dimensions of 1.2X2.00m as shown in drawings .
No. 4
18 of 25
King Abdullah Bin Abdulaziz
Technical Vocational Training Center
Civil Works
Item
NoDescription Unit QTY
Price /
Unit Total
Bill No.9 Carpentary Works
9.1.2WD02, with and overall dimensions of 0.80x2.00m
as shown in drawings. No. 21
9.1.3WD03, with and overall dimensions of 0.70*2.00m
as shown in drawings. No. 12
9.1.4WD04, with and overall dimensions of 0.90x2.00m
as shown in drawings.No. 1
9.2 Kitchen Cabinets
Supply and install kitchen upper and lower
cabinets with the following specifications:
1- All handles are as made by TIRADOR 2012/14
Length of handle 96/160 mm, Color is NIROSTA
MATT.
2- All hinges are as made by BLUM
3- All Ply wood used is 17mm ARRAD made or
equivalent that should be approved by the site
engineer.
4- Price should include counter top granite as
made by CAESAR color No. 7100 or approved
equivalent
9.2.1
Supply and install lower kitchen cabinets, as per
the detailed drawings and instructed by the site
engineer. Price to include granite counter top
mr 3
9.2.2
Supply and install Upper kitchen cabinets, as per
the detailed drawings and instructed by the site
engineer.
mr 2
9.2.3
Supply and install electromechanical cabinets,
price to include casement with 17mm thick
casement with solid 17x17mm RED OAK wood
frame and , installations as shown on drawings,
price to include hinges as made by BLUM, finishing
and painting as instructed and approved by the site
engineer
m2 12
9.3
Supply and install wooden PERGOLA with all
Accessories according to the attached drawings,
price should include painting a natural varnish
colour finishing 5 coats (two coat primer and 1coat
undercoat and 2 coats finishing ), the contractor is
responsible for executing the job as it is in the
drawings and according to site Engineer
instructions .( provisional )
m2 45
Total Item No. 9
19 of 25
King Abdullah Bin Abdulaziz Technical Vocational Training Center
Civil Works
Item No Description Unit QTY Price / Unit Total
The contractor shall, when pricing the rates of this bill, take into consideration including and allow for the costs or expenses of all requirements stipulated in the preambles, drawings and technical specification of the contract.
10.1
Supply and install ORBOND water proofing (GREEN) gypsum board for false ceilings and on vertical walls of 12.5 mm thick gypsum panels with studs at every 40cm in both directions including decorations, forms, trims with all connections supports , fixing, putty sealer , wire mesh and special angles for edge of boards and all necessary accessories needed for the best completion of works . The contractor shall provide a shop drawing for architect approval.
The contractor should install paper corner and joints beads on all joints, corners, connections between walls and boards using putty (GOLD BOND BRAND), laying one layer of putty over the joints and corners and another one layer over all gypsum boards, sanding with sand paper and finishing all as approved by the site engineer
10.1.1On horizontal and vertical surfaces, as instructed and approved by the architect. m2 80
10.1.2
Supply and install service opening in the gypsum boards false ceiling where indicated on drawings or instructed by the site engineer, the price should include making the opening, making good of the gypsum edges, supply & install the pine wood frame and the ply wood, applying one coat of putty all as shown on detailed drawings and instructed by the site engineer
60x60cm service openingNo. 10
Total for False Ceiling works
Bill No.10 False Ceiling & Gypsum Works
20 of 25
King Abdullah Bin Abdulaziz Technical Vocational Training Center
Civil Works
Item No Description Unit QTY Price / Unit Total
The contractor shall, when pricing the rates of this bill, take into consideration including and allow for the costs or expenses of all requirements stipulated in the preambles, drawings and technical specification of the contract.
The contractor should allow in his pricing that the engineer will use as many different colours or combination of colours to meet an approved colour scheme. ( Company ready mix original)No hand made color mix is allowed.
The contractor has to prepare a color sample 1*1m on site for each color asked by the site engineer
All paint works should conform to Tambour instruction regarding number of coats , rate of application or drying time.
All protection and care should be taken against paint drips, drops, droplets, and brushing.
The contractor should study well the project, walls, ceilings, gypsum boards, and all finished surfaces before applying the paint, so that if he discovers any mistake or additional needed works, he shall inform the engineer so as to adjust and agreed upon additional items before signing of the contractor. Otherwise the contractor will be responsible and take no extra money for any change of order.
Bill No.11 Painting Works
21 of 25
King Abdullah Bin Abdulaziz Technical Vocational Training Center
Civil Works
Item No Description Unit QTY Price / Unit Total
Bill No.11 Painting Works
11 On Walls & Ceiling
Supply all kinds of raw material and apply paint for lobby and staircase walls to height 1.5 m , and wherever needed or instructed by the site engineer, the price should include preparing surface, clean, remove dust and foreign matter, sanding with well with sand paper, checking the walls with putty,laying two coats of putty (APC brand or an approved equivalent), applying one coat of APC SUPER BOND ROLL and applying Tow coats of APC Oil Painting or an approved equivalent Product, all as instructed and approved by the site engineer
m2 550
11.2
Supply all kinds of raw material and apply paint Emulsion for walls area ,and wherever needed or instructed by the site engineer, the price should include preparing surface, clean, remove dust and foreign matter, sanding with well with sand paper, checking the walls with putty, laying two coats of putty (APC brand or an approved equivalent), applying one coat of APC SUPER BOND ROLL and applying Four coats of APC Painting or equivalent Product, all as instructed and approved by the site engineer.
m2 2000
11.3
Supply and apply Four coats of APC FILL Aracid Product ceilings over plastering, electrical, mechanical shafts, elevator shaft and wherever needed or instructed by the site engineer.
m2 1500
Total of Bill No. 11
11.1
22 of 25
King Abdullah Bin Abdulaziz Technical Vocational Training Center
Civil Works
Item No
Description Unit QTY Total
Electrical lift works :simplex A No. of Units 1B Code: En 81.1 & and Palastinian standardsC Capacity 480 Kg, 6 Passengers D Velocity 1 m/sE Drive VVVF F Leveling Accuracy +/- 5 mmG Motion Control SimplexH Controller MicroprocessorI Stops 5J Doors NO. 5 in line K Floor Numbering 0,1,2,3,4M Shaft -Size W x D ( 1800 x1800 )mmN Overhead 4000mmO Pit Depth 1400 mm under slab on grade level .
Drive :1 Meconic-MX-GC-Gearless motor
1.1 Electronically controllled microprocessor regulated drive system
1.2180 starts/hours,AC-VVVF regulated,closed loop , power supply 3phase AC 400/230V,50Hz.stopping accuacy of (+/-5 mm)
1.3 Roping ____ with Special metel cables2 Control :
2.1 Microprocessor2.2 Overload function2.3 Fire emergency return control 2.4 Car light and fan auto on/off2.5 Re-leveling 2.6 Phase failure and phase reversal protection2.7 Over heat protection2.8 Full load bypass2.9 Automatic return to main floor2.10 Power control with sequential starting (power generator by owner)2.11 Independent operation2.12 Horn in car2.13 Anti nuisance (false calls cancellation)2.14 Nudging operation
2.15Emergency evacuation system in case of power failure to reach thenearest landing equiped with stand by battaries
2.16The elevator call system should be controlled with a Magnatic CardReader on each door.
3 Car Finish :3.1 Elephant skin stainless steel on all sides
3.2 Ceiling suspended with indirect lighting with stainless steel mirror finish
3.3Removable ceiling for maintinance task, enough space for maintinaceman
3.4 Emergency exit 500 x 600 mm3.5 Brushed Stanless Steel handrail at front elevation of the room3.6 Floor finish (red stone or Granite) To be supplied by the owner.4 Car operating panel
4.1One COP, full height colored steel Anthracite Ral _____ at side wallpanel
4.2 Micro touch push Buttons for landing (floor designations)4.3 Alarm button 4.4 Door open, button4.5 Door close button 4.6 Digital position indicator dot matrix 4.7 Direction arrows.
Bill No.12 Electrical Lift (Elevator) Works
23 of 25
King Abdullah Bin Abdulaziz Technical Vocational Training Center
Civil Works
Item No
Description Unit QTY Total
Bill No.12 Electrical Lift (Elevator) Works
4.8 Intercom system 2 terminals (car, supervision room),4.9 Overload protection device with audible and visible signal,4.10 Emergency bell and light
5 CAR DIMENSIONS:5.1 Width * Depth * Height:1600x1500x23006 CAR DOORS:
6.1 Car door: Fully automatic 2 panels, heavy duty.6.2 Car door drive: is regulated with AC-VVVF 6.3 Opening: Telescopic opening 2 doors panels 6.4 Door sill : Elephant Skin Stainless Steel. 6.5 Panels finish : Elephant Skin Stainless Steel. 6.6 Shoulders finish for car: Elephant Skin Stainless Steel. 6.7 Door safety device type : light curtain.6.8 Door open/close time is adjustable.6.9 Pre-opening at landings 7 LANDING DOORS:
7.1 Door (width X height):1200X2000 mm7.2 Door panels finish : painted steel finish at all floors7.3 Door frame: narrow in painted steel finish at all floors
7.4Fire resistance class F-60. (landing doors are 60 minutes fireresistance)
7.5 Landing operation and indication panels on all floors7.6 Position indicator dot matrix type, direction arrows. Wall mounted.
7.7Push Buttons: square type micro touch, with mirror stainless steel plate at all floors
8 Fireman Function:8.1 Fireman Key switch at MAIN FLOOR.
9 NO-MACHINE ROOM :Machine Room Less (MRL)
10 SAFETY GEAR :For Car
11 BUFFERS: buffers for car and counter weight
12 COUNTER WEIGHT : Cast Iron enclose in steel framework
Notes : -
aEach company should submit its own specifications andrequirments .
bAny scaffolding works should be done by the company and on itsexpense .
cAll steel beams needed for doors , or any where else , to besupplied and installed by the company .
Job 1
Total of Bill No. 12
24 of 25
King Abdullah Bin Abdulaziz Technical Vocational Training Center
Civil Works
Bill No. Description Total
Excavation & Earth Works
Concrete Works
Stone Works
Block Works
Plastering Works
Tiling Works
Water Proofing Works
Metal Works
Wooden Works
False Ceiling Works
Painting Works
Electrical lift
Total of Civil Works -including provisional items (Not Including Value Added Tax )
Currency of Bid (NIS or USD) : ________________
5
6
7
12
8
9
10
11
Summary of Civil Works Bills 1 - 12
1
2
3
4
25 of 25
King Abdullah Bin Abdulaziz
Technical & Vocational Training Center
BOQ Mechanical Works
King Abdullah Bin Abdulaziz Technical Vocational Training Center
Mechanical Works
No. Description Unit Qty Unit Rate Total
1 Waste and drainage systemThe Contractor shall, when pricing the rates of this bill,take into consideration including and allow for the costsor expenses of all requirements stipulated in thepreambles, drawings.
The following notes should be considered when pricing:
1- The price shall include all required digging orexcavation backfilling,coring and cement covering asspecified.
2- The price shall include all connections to exsistingdrainage pipes and manholes if needed.includdedcutting in tile & asphalt ,retiling,repair the asphalts
3- The contractor must consider keeping the systemrunning where needed during the whole constructionperiod.
1.1
Supply and Install (S&I) U.P.V.C HULIOT pipes andfittings for waste & rain water, and sanitary water stand pipes, running exposed along partitions, walls, shafts,under tiles, laid in walls. Price include all type ofsupports, hooks, and all excavation, sand embedment,back filling and concrete coring by hilti for creatingopenings, all types of fittings as but not limited to; wye, tee, reducer tee, 45 degree elbow, end caps,expansion joints, .laying at least 8cm concrete aroundthe under ground pipes
1.1.1 6" pipe suspended to ceiling L.m 30
1.1.2 4" pipe L.m 220
1.1.3 3" pipe L.m 20
1.1.4 2" pipe L.m 90
1.1.5 11/4" pipe condensate fan coil L.m 35
1.2
S & I 4"/2 Floor trap or box trab as by lipski includingstainless steel cover 15x15cm floor drain cover. Therate shall include for all connections with drain pipes2"pipes, 4"/2 extending box and nipple. and all neededfittings for proper installations.
No 11
1.3
S & I 4"/4 Floor trap Huliot including stainless steel15x15cm floor drain cover. The rate shall include forall connections with drain pipes2" pipes, 4/2" extendingbox and nipple lipski. and all needed fittings forproper installations.
No 16
1.4S & I 4" clean out openings including stainless steel15x15cm floor drain cover. The rate shall include forall connections with drain pipes .
No 11
1.5 S & I 4" P.V.C vent caps for all vent pipes at roof No 4
1 of 12
King Abdullah Bin Abdulaziz Technical Vocational Training Center
Mechanical Works
No. Description Unit Qty Unit Rate Total
1.6
S & I 20x20cm Rain water Floor trap box ready typeincluding . The rate shall include for all connectionswith rain pipes 4" extending nipple. and all neededfittings for proper installations.
No 8
1.7
Supply and install rain water trench size 100x20x12cm type ready,as shown in the drawingscomplete with 4" floor trap ready type16mm stainlesssteel rods at the top and 5cm apart and all necessarayaccessories.a slope towards the outlets of the draintrench shoud be made.perforated basket .price includedigging,excavation and all necessaray work tocomplete the job
No 6
Ditto but 30 x20cm trunch for the parking M.R 4
1.8
Supply and install of supmersible pump complete withfloat valve, to be install in the manhole under the liftroom, to collect all the rain water outside as shown inthe drawing,price include supply and install of manhole60x60cm with steel cover above the manhole with16mm steel rods and 3cm apart, price also include the40mm H.D.P as shown in drawings and all ellectricalconnection.type dab or eq pump head,1mh-7m3/h
job 1
1.9
Supply and install of 4" perforated pipe to be installaccorrding to Drawing price include all necessarayfitting to connect the perforated pipe to the rain waterpipe,with all requird fitting to complete the jobaccorrding engineer request
L.m 70
Total of waste and rain water systems
2 of 12
King Abdullah Bin Abdulaziz Technical Vocational Training Center
Mechanical Works
No. Description Unit Qty Unit Rate Total
2 External Drainage collection systemThe Contractor, when pricing the rates of this bill, shalltake into consideration including and allowing for thecosts or expenses of all requirements stipulated in thepreambles, drawings and technical specification of thecontract.
The following notes should be considered when pricing:
1- The price shall include all required digging orexcavation, backfilling and cement covering asspecified.
2- The price shall include all connections to existingdrainage pipes and manholes if needed.includdedcutting in tile & asphalt ,retiling,repair the asphalts
2.1 Excavation
Supply and install 6" UPVC pipes HOLUIOT Taken tothe exsisting manhole including digging forpipes,gutting,opening in walls an in manhole,supplywith all necessary fittings such aselbow,tee,Y,….etc,for sewage disposal and vent pipe,the price allso include fordigging,supports,hanggers,and laying at least 8cmconcreate arround the pipes,approve manufacture forpipes and fittings: ( red blassim)
L.m 50
2.2 Manholes :
Supply and install of 60cm (internal diameter) readymade concrete circular manhole of depth notexceeding 100cm measured from ground level at thetop of the manhole cover to the top level of themanhole base. internal epoxy coating, benching.Special connection pieces should be used for fixing thepipes with the manhole. The price is to includenecessary excavations, backfilling, and protection andas directed by the Engineer. Supply and Installation ofcast iron cover of 25ton Kurdieh type or eq. shall beinclude in the rate of the manhole
No. 4
2.3Ditto but 80cm internal diameter exceeding 1m depthwith cast iron cover 8 ton type kurdieh or eq. allaccorrding to engineer instructions
No. 2
Total of External drainge systems
3 of 12
King Abdullah Bin Abdulaziz Technical Vocational Training Center
Mechanical Works
No. Description Unit Qty Unit Rate Total
3 Sanitary fixture and their accessories
The Contractor shall, when pricing the rates of this bill,take into consideration including and allow for the costsor expenses of all requirements in the drawings
The following notes should be considered when pricing:
1- The price shall include all required digging orexcavation backfilling,coring and cement covering asspecified.
3.1
Supply and install wall mounted water closet creavittype SL or eq. pergamone colour.complete withreccesd plasson or shwaab nicara ,heavy duty seatcover,complete with crome plated screw,outlet soilfitting with cleanout,1/2"x3/8" angle valve nile type oreq.,connection to soil pipe,connection to watersupply.includding paper holder chrome platted.
No. 12
Supply and install handicap water closet suite creavittype BD3041 or eg. with porcelain nicara pergamonecolour floor standing type,complete with crome platedscrew,outlet soil fitting with cleanout,1/2"x1/2" anglevalve type nil or eq.,1/2" flexible white colourplastichose,heavy duty seat cover of the same type,,connection to soil pipe,connection to watersupply.includding paper holder chrome platted,PriceInclude supply and install two support arms stainlesssteel Dia 32mm one fixed, one movement type creavitTB200,TB110 or approved equal accorrding engineerruquest
No. 1
3.2
Supply and install porcelain wall hang wash basinpergamone colour, with half leg creavit type
SL6026 or eq..price shall include hot and coldwater mixing faucet hamat type 300-140 oreq,two 1/2" x 3/8" angle valve nil type oreq.,11/2"P-Trap,connection to supplypiping,connection to drainge pipe.
No. 1
4 of 12
King Abdullah Bin Abdulaziz Technical Vocational Training Center
Mechanical Works
No. Description Unit Qty Unit Rate Total
3.3 Ditto but under counter wash basin No. 11
Supply and install for handicap porcelain wall hang wash basin pergamone colour, creavit type BD060 or eq.price shall include hot and cold water mixing faucet hamat type or eq.,two 1/2" x 3/8" angle valve type nil or eq,11/2"P-Trap,connection to supply piping,connection to drainge pipe. Supply install one support arms stainless steel Dia 32mm movement type accorrding engineer ruquest
1
3.4
Supply and install stainless steel kitchen sink, singlebowl according to drawings with shelf as by *Roca oreq. , Hamt mixer type 300-153 or approved includingsiphon and complete with angle valves. 1/2x3/8" nile typeor approved accorrding engineer ruquest
No. 1
Total of Sanitary fixture
5 of 12
King Abdullah Bin Abdulaziz Technical Vocational Training Center
Mechanical Works
No. Description Unit Qty Unit Rate Total
4 Domestic water system
The Contractor shall, when pricing the rates of this bill,take into consideration including and allow for the costsor expenses of all requirements stipulated in thepreambles, drawings .the contractor shall consider keeping the interruptionfor the system to a minimum.Testing all pipes at 8bar for 24 hour
4.1
Supply and install and test galvanized steel pipe sch.40 for cold and hot& soft water supply with all necessaryfittings such as elbow,tee,reducer,union,valves,sshown in the drawings.the price shall include forhangers, supports,openings in wall by hilti,sleeves,painting and rolling of asphalted canves mesh for theunder ground pipes, Also insulatuon the hot waterpipes by 13mm ruber foam insulation(anavid) wrappedwithcolared self adhesiveP.V.C tape.shown
4.1.1 1/2" LM 50
4.1.2 3/4"ditto. LM 60
4.1.3 1" ditto LM 70
4.1.4 11/4" ditto LM 35
4.1.5 11/2" ditto. LM 20
4.1.6 2" ditto. LM 20
4.2Supply and install PVC plastic pipe(jolani) or approvedequal for sanitary fixture with all necessary fittings.16/25mm pipes,1/2" wall elbow type N.T.M
LM 400
4.3 Ditto but 25/32mm LM 50
4.4 Ditto but 32/40mm LM 50
4.5
Supply and install Gaccomini* or eq.type copper watercollectors complete with plugs, washers, brackets, draincocks,vents, isolating ball valves with T-handle on eachoutlet. The unit price shall include supply and install of 2mm steel cabinet painted in oven bymanufacturer.Number of outlets are as shown ondrawings size of cabinet according collecter size
collecter-1: 13eye cold(11/4"),7 eye hot (1") NO 1
collecter-2: 9 eye cold(11/4"),7 eye hot (1") NO 2
collecter-3: 7 eye cold(1"),3 eye hot (3/4") NO 2
collecter-4: 7 eye cold(1"),6 eye hot (3/4") NO 1
6 of 12
King Abdullah Bin Abdulaziz Technical Vocational Training Center
Mechanical Works
No. Description Unit Qty Unit Rate Total
collecter-5: soft 3 eye (3/4") NO 1
4.6 Supply and install 1/2" tap for irrigation italy type NO 5
4.7
Supply and install electrical water heater of typeoriginal or approved of capacity 60L the price includeall necessaray fitting needed to complete the work,therate also include all wirring,cables, needed to operatethe boiler
NO 2
Ditto but 30L capacity NO 3
4.8
Supply, install and connect copper gas pipes type wicofor the different fixtures and as shown on drawings,complete with all necessary fittings, accessories,regulator, shut-off valves, etc..price include pvcsleeves of bigger diameter, ,covering the pipe byconcrete for safty,price also include all excavation,coring by hilti for installation the pipes and all worksneeded to complete the work.coated gaz pipe dia16mm
LM 30
Ditto but 8mm gaz pipe LM 80
Supply and install 1/2" gaz collecter including shut offvalves SAGIV type at main and sub mainbranches,complete with hangers,and accessoriesneeded to complete the work.accorrding engineerrequest,7eyes The unit price shall include supply andinstall of 2 mm steel cabinet painted in oven bymanufacturer.Number of outlets are as shown ondrawings size of cabinet according collecter size
Job 1
Total of Domestic Water System
7 of 12
King Abdullah Bin Abdulaziz Technical Vocational Training Center
Mechanical Works
No. Description Unit Qty Unit Rate Total
5 Ventelation system
5.1
Sypply and install in line exhaust fan for toiletsroom,of type vortice or eg,price include all necessarayfitting to connect the fan to exhaust grill on bath roomabove false ceiling,also price include coring in wall byhilti for the duct and exhaust grill ,and all wirring andcables needed to operate the exhaust fan with timmerfan 300 cfm
NO 1
5.2 Ditto fan 200cfm NO 1
5.3 Ditto but wall type ex.fan 100cfm NO 1
5.4
Sypply and install roof top centrifugal exhaust fan forhood,of type vortice or eg.complete with galvanizedmetal sheet elbow and bird mesh at the dischargesection ,price include all necessaray fitting to connectthe duct to exhaust fan on roof,also price includeconcrete base for the fan and rubber under the fan forvibration also supply and install all electricalwirring,cables,switch,to operate the fan 2500cfm,1.2"sp
NO 1
5.5Supply and install 6" and 4" flexible tubes including allnecessary fittings such as elbow, Y, hangers, supports,etc. Approved manufacturer of tubes (Dec)
L.M 40
5.6
Supply and install rectangular not insulated duct ofthickness 0.7mm for the exhaust air duct for toilet room,and for solar chimney which running in walls andpartions accorrding archicets drawings Complete withhangers, supports, bolts, nuts, etc.
Sq.m. 30
5.7Supply and install aluminum exhaust grille as per"Metalpress*"
5.8 Sypply and install exhaust grill circular 6"x6" NO 1
5.9 Sypply and install exhaust grill circular 6" NO 6
Total of Ventelation system
8 of 12
King Abdullah Bin Abdulaziz Technical Vocational Training Center
Mechanical Works
No. Description Unit Qty Unit Rate Total
6 Fire Fighting System
The Contractor shall, when pricing the rates of this bill,take into consideration including and allow for the costsor expenses of all requirements stipulated in thepreambles, drawings .
Testing all pipes at 8bar for 24 hour
6.1
Supply and install fire cabinets of sufficient size topermit for installation of necessary equipment asshown on drawings . The cabinet shall include thefollowing: Fire hose 3/4" in diameter, 25 meter long,light weight, made of red rubber with working pressureof 150 psi. Hose reel of the swinging type, up to 180degrees full swing complete with guide arm. Chromeplated 3/4" in diameter nozzle capable of completeshut-off. Gate valve 1" in diameter. Fire hose 2" indiameter, 15 meter long, light weight, made of linen.Chrome plated 2" in diameter nozzle capable ofcomplete shut-off. Angle valve 2" in diameter of bestquality . Hose adapter 2" in diameter 3 Kgs. Chemicalfire extinguisher with spray hose and nozzle.
Unit 6
6.2
Supply and istall galvanized steel pipes to ASTM-A53grade "A" schedule-40 for fire fighting systempipework, inside building. The unit price shall includevalves, fittings, and all accessories and works requiredto complete the work and as per preambles,specifications, and the supervision of engineer'srequirements. The unit price shall also include theconnection to existing system in boiler room completewith cutting, taking branch, etc..
2" diameter pipe Mr 80
1" diameter pipe Mr 20
Total of Fire Fighting System
9 of 12
King Abdullah Bin Abdulaziz Technical Vocational Training Center
Mechanical Works
No. Description Unit Qty Unit Rate Total
7 PUMP ROOM&ROOF
The Contractor shall, when pricing the rates of this bill,take into consideration including and allow for the costsor expenses of all requirements stipulated in thepreambles, drawings .Testing all pipes at 8bar for 24 hour
7.1
supply and install cold&fire water pressure pumpgrandfoss or Eq. vertical multi stage type ,completewith all nessesary fittings such as ,press gage,pressure reducing valve,press stat danfoss type,andall necessaray fitting such as valves,strainer,flexsiblejoint,check valve, to complete the job Price include forelectrical,wirring,and connection to operate. pump5M3/H,50MH
NO 1
7.2 Ditto for all fitting but jokey pump 2M3/H,60MH NO 1
Ditto but for soft water 2M3/H-50MH NO 1
7.3
Supply and install pressure tank elbi type or approvedequal, as shown on drawings complete with all fittingssuch as automatic air vent, pressure reducing valve,gate valve, T, union, etc. Price includes pipinginstallation for water from main cold water pipe.Maximum pressure of tank is 6 atm. 100 lit. capacity.
No. 2
7.4
Supply and install 2" H.D.P pipe,price include theflange,with the valve needed for the water tank (well )with all necesaray fitting and pipe needed to reach topump room,all pipe inside the parking to the pumproom well be install under the slab concrete accorrdingdrawing
MR 15
7.5
Supply and install of o.5 mm galvanize sheet matelduct to gladding all the exposed pipe on roof priceinclude all necessaray fittings,such astee,elbow,valves,for all diminssion of pipes to 2"
MR 30
7.6
Supply and install softner type permo or approvedequal complete with all necessaray fitting to connectthe softner with the pressure pump and the sulttank,the rate include all the electrical wirring ,cables tocomplete the work permo type data -7 -2m3/h,orapproved equal accorrding engineer ruquest
NO 1
10 of 12
King Abdullah Bin Abdulaziz Technical Vocational Training Center
Mechanical Works
No. Description Unit Qty Unit Rate Total
7.7
Supply and install three solar panels of original type
approved equal,9 section each one and of size 90*190 cm. Complete with 180l hot water storagetank. the tank shall be painted by epoxy from insideand shall be equiped with electric heating elementof capacity 2500w, price include all necessarayfittings,also the price include metal base febricatedof steel angle 40x40x5cm,and electricalconnection,necessaray fittings needed to finish thework accorrding to engineer instructions
set 2
7.8
Supply and install PVC water tank of capacity 1500lit with steel base 1m for the soft water , the price shall include fittings such as ,1/2" floater,3/4" drain pipe with valve,and all necessary fittings for pipe ,such as ,elbow,T,union,valves, all accorrding engineer request
No. 1
Total of pump work
11 of 12
King Abdullah Bin Abdulaziz Technical Vocational Training Center
Mechanical Works
Bill No. Description Total
Total of waste and rain water systems
Total of External drainge systems
Total of Sanitary fixture
Total of Domestic Water System
Total of Ventelation system
Fire System
Total of pump work
Total of Mechanical Works-including provisional items (Not Including Value Added Tax )
Currency of Bid (NIS or USD) : ________________
Summary of Mechanical Works Bills
1
2
3
6
7
4
5
12 of 12
King Abdullah Bin Abdulaziz
Technical & Vocational Training Center
BOQ Electrical Works
King Abdullah Bin Abdulaziz Technical Vocational Training Center
Electrical Works
Item Description Unit QTY Unit Rate Total
Electrical and Communication Works
The contractor shall, when pricing the rates of the
following electrical bills take into consideration including
and allow for the cost expenses of all requirements
stipulated in the preambles, drawings and technical
specifications of the tender.
All Supplied Materials Should be class A , new , not used
and Free From any Defects, Having the Supervisor
approval Certificate .
The contractor's total price for works shall include for the
supply, execution, completion and testing of the whole of
electrical installation works and related systems in
accordance with the drawings, bill of quantities and
specifications.
The contractor shall coordinate his works with the
decoration works, furniture, changes in the positioning of
ceiling light fixtures due to partitioning changes and any
other changes which require design changes on the
tender drawings.
The contractor must consider all these changes in the
shop drawings which must be submitted and approved
before commencement of works.
Plates, labels and tags for the identification of plant,
equipment, cables, switches ,sockets and the like.
Forming or cutting holes, chases, channels etc. in
reinforced concrete structures and block works.
The contractor's rate must include the supply and install
internal sea sand plastering for the electrical conduits on
wall . composed of two coats base coat ,finish coat . The
rate includes all necessary patching works ,expanded
metal latch mesh , plastering layers must be applied to
meet plastering thickness
The contractor shall submit all samples needed for all
electrical and low voltage points, fittings , accessories
and fixtures and to take the approval from the
supervision engineer before starting works.
All electrical conduits under tiles, floor, wall should be
protected by cement mortar or concrete layer and all
electrical excavation works should be removed from site
as specified in the technical specification and drawings.
1 of 15
King Abdullah Bin Abdulaziz Technical Vocational Training Center
Electrical Works
Item Description Unit QTY Unit Rate Total
The above mentioned shop drawings, electrical
switchboards shop drawings, as built drawings and all
other required detailed drawings are to be included in
the rates for no additional cost.
1 Main Feeder
1.1.1Feeding the building with the 3*125 A electrical amperes
needed . ( Estimated by the Municipality of Hebron)L.S. 1
1.2 Main Line Excavation for main power cable
1.2.1
Supply all labor and materials to make an excavation of
80cm (deep) x 60cm (wide). The excavations for trenches
80cm width x 100cm depth in any type of soil and
removing extra excavated materials out of side. Work
shall include supply and filling works of 20cm sand layers
and laying 10cm concrete block with special electrical
warning tape. Work shall also include backfilling with
chosen excavated materials and compacted it with layers
20cm thickness.
M.L. 25
1.3 Main Line Excavation for main telephone cable
1.3.1
Supply all labor and materials to make an excavation of
80cm (deep) x 60cm (wide). The excavations for trenches
80cm width x 100cm depth in any type of soil and
removing extra excavated materials out of side. Work
shall include supply and filling works of 20cm sand layers
and laying 10cm concrete block with special electrical
warning tape. Work shall also include backfilling with
chosen excavated materials and compacted it with layers
20cm thickness.
M.L. 25
1.4 Empty Conduits for Main Cables
1.4.1
Supply, install, test and commission a heavy duty UPVC
conduits dia 4" with pull wire for main incoming power
cables to main distribution board to be laid in the
excavation in item 1.2 with all accessories.
M.L. 50
1.5 Empty Conduits for Main Telephone Cable
1.5.1
Supply, install, test and commission a heavy duty UPVC
pipe dia 2" with pull wire for main telephone cables
complete to be laid in the excavation in item 1.4 with all
accessories.
M.L. 50
2 of 15
King Abdullah Bin Abdulaziz Technical Vocational Training Center
Electrical Works
Item Description Unit QTY Unit Rate Total
1.6 Main Power Manholes
1.6.1
Supply ,install, and test a ready made main civil heavy
round duty manholes and with special cast iron covers 25
Ton Load Capacity and Ø100 with 100cm depth. Work to
include pouring all needed concrete materials for
manholes bases with steel meshØ12mm/20cm in both
directions, work also include backfilling and removing all
extra excavated materials and with all necessary
accessories.
No. 3
1.7 Main Low Voltage Manholes
1.7.1
Supply ,install, and test a ready made main civil heavy
round duty manholes and with special cast iron covers 25
Ton Load Capacity and Ø80 with 80cm depth. Work to
include pouring all needed concrete materials for
manholes bases with steel meshØ12mm/20cm in both
directions, work also include backfilling and removing all
extra excavated materials and with all necessary
accessories.
No 1
Total of Main Feeder Works
3 of 15
King Abdullah Bin Abdulaziz Technical Vocational Training Center
Electrical Works
Item Description Unit QTY Unit Rate Total
2 Electrical Switchboards
Supply, Install and Connect Main and Sub Main
Distribution Board. . Price to include metal panel board
oven painted 1.5mm thickness factory made, Moulded
Case circuit breakers MCCB , miniature circuit breaker
MCB , bus bars, cable clamps, cable glands, protection
equipments, measuring equipment, labeling all circuit
breakers, all necessary excavation, fixing . asdrawings and specifications with all accessories.Types of MCCB's and MCB's, Moller , Merlin GerinGeneral electric or equivalent. Rated BreakingCapacity for circuit breakers as follow
10 A‐16 A ‐ 10 KA
25A ‐125 A ‐ 25 KA
160A ‐400 A ‐ 36 KA
10 A‐16 A ‐ 10 KA
25A ‐125 A ‐ 25 KA
160A ‐400 A ‐ 36 KA
2.1 MDB with Power Factor Correction No. 1
2.2 DB1 No. 1
2.3 DB2 No. 1
2.4 DB3 No. 1
2.5 DB4 No. 1
2.6 PLIFT No. 1
Total of Electrical Switchboard Works
4 of 15
King Abdullah Bin Abdulaziz Technical Vocational Training Center
Electrical Works
Item Description Unit QTY Unit Rate Total
3 Installation in the Building Points
The following items are supply, installation of same,
connection, wiring, commissioning and all other details,
as specified in the technical specification and drawings.
3.1
Wall, ceiling or false ceiling mounted lighting point
normal, waterproof, emergency or exit (Price includes
16mm diameter conduit Nacy , hadash plast type or
equivalent, 3x1.5 mm2 cross section wire itac ,
synenergy type or equivalent, ceiling box and phase line
for emergency lighting point , and leading from the
switch panel to the point including any needed boxes or
accessories).
No. 300
3.2
External flood Light Point (Price includes 1" diameter
conduit, 3x2.5 sq.m N2XY cross section cable or
equivalent, with all excavations needed and leading from
the switch panel to the point including any needed boxes
or accessories).
Point 5
3.3
External wall mounted lighting point (Price
includes16mm diameter conduit Nacy , hadash plast
type or equivalent, 3x1.5 mm2 cross section cable itac ,
synenergy type or equivalent and leading from the
switch panel to the point including any needed boxes or
accessories).
No. 35
3.4
Single pole switch GEWISS Top System GW20571,or
Biticino, Legrand or equivalent Including Boxes,
Supports & Plates, (Price includes 16mm diameter
conduit Nacy , hadash plast type or equivalent, 3x1.5
mm2 cross section wire itac , synenergy type or
equivalent, and all accessories.
No. 6
3.5 Ditto but waterproof No. 6
3.6
Double pole switch Legrand or equivalent Including
Boxes, Supports & Plates, (Price includes 16mm diameter
conduit Nacy , hadash plast type or equivalent, 3x1.5
mm2 cross section wire itac , synenergy type or
equivalent, and all accessories.
No. 22
3.7 Ditto but waterproof No. 1
3.8
Two way switch Legrand or equivalent Including Boxes,
Supports & Plates, (Price includes 16mm diameter
conduit Nacy , hadash plast type or equivalent, 3x1.5
mm2 cross section wire itac , synenergy type or
equivalent, and all accessories.
No. 8
3.9
Intermediate switch Legrand or equivalent Including
Boxes, Supports & Plates, (Price includes 16mm diameter
conduit Nacy , hadash plast type or equivalent, 3x1.5
mm2 cross section wire itac , synenergy type or
equivalent, and all accessories.
No. 1
5 of 15
King Abdullah Bin Abdulaziz Technical Vocational Training Center
Electrical Works
Item Description Unit QTY Unit Rate Total
3.10
Push button with indication lamp Legrand or equivalent
Including Boxes, Supports & Plates, (Price includes 16mm
diameter conduit Nacy , hadash plast type or equivalent,
3x1.5 mm2 cross section wire itac , synenergy type or
equivalent, and all accessories.
No. 10
3.11
Standard 1 ph socket outlet point normal (Price includes
16mm dia. conduits Nacy , hadash plast type or
equivalent, 3x2.5mm2 wire itac , synenergy type or
equivalent , with 16A socket Legrand or equivalent,
Boxes, Supports & Plates and leading from the switch
panel to the point , including all accessories).
No. 60
3.12 Ditto but waterproof No. 25
3.13
Standard 1 ph Double socket outlet point normal (Price
includes 16mm dia. conduits Nacy , hadash plast type or
equivalent, 3x2.5mm2 wire itac , synenergy type or
equivalent , with 16A socket GEWISS Top System
GW20220 type or Biticino, Legrand or equivalent, Boxes,
Supports & Plates and leading from the switch panel to
the point , including all accessories).
No. 35
3.14 Ditto but waterproof No. 3
3.15
16A Industrial three phase wall‐mounted socket outlet
point (Price includes sockets NISKO type N516.110 with
lockable cover, IP 65 , three and single phase Legrand
type or equivalent, 5x2.5mm2 N2XY cable orequivalent, 23mm diameter conduits, and allaccessories leading from distribution board to thepoint).
No. 3
3.16
Single phase electrical connection of Split Unit (Price
includes 3x2.5mm2 N2XY or equivalent cross section
cables, A/C socket LEGRAND type or equivalent, flexible
heat conduits, cable glands, connection boxes, adaptors
and all connections and accessories from relevant panel
to machine .
No. 30
3.17
One phase electrical connection point for electrical
Boiler on roof (Price includes 16mm dia. conduit,
3x2.5mm2 N2XY cross section cable or equivalent, with
ON‐OFF switch Legrand or equivalent. Rates also includes
isolator switch w.p , Boxes, Supports & Plates and leading
from the switch panel to the point , including all
accessories).
No. 1
6 of 15
King Abdullah Bin Abdulaziz Technical Vocational Training Center
Electrical Works
Item Description Unit QTY Unit Rate Total
3.18
On‐off switch with indication lamp ,including Price
includes 16mm dia. conduit, 3x2.5mm2 N2XY cross
section cable or equivalent, with ON‐OFF switch Legrand
or equivalent. Rates also includes Boxes, Supports &
Plates and leading from the switch panel to the point ,
including all accessories).
No. 5
3.19
Telephone connection point wall or table mounted (Price
includes 16mm diameter conduits Nacy , hadash plast
type or equivalent, with 4x0.5mm2 ITAC telephone or
equivalent, telephone socket legrand or equivalent,
Including Boxes, Supports & Plates and leading from
point to the telephone section in LV box).
No. 40
3.20
T.V. antenna connection point (The price includes 16mm
diameter conduits Nacy , hadash plast type or
equivalent, with American common scope coaxial cable
RG6 75 ohms,, as well an outlet with a plastic socket
legrand or equivalent, Including Boxes, Supports & Plates
and leading from point to the connection box on roof.
No. 10
3.21
Satellite antenna connection point (The price includes
16mm diameter conduits Nacy , hadash plast type or
equivalent, with American common scope coaxial cable
RG6 75 ohms, leading from connection box to the points
as well an outlet with a plastic socket GEWISS LEGRAND,
Including Boxes, Supports & Plates and leading from
point to the connection box on roof.
No. 10
3.22
Intercom System connection point (Price includes 16mm
diameter conduits with 8*0.5 mm2 cable ITAC type orequivalent, and leading from point to the LV box orto the nearest point with all accessories).
No. 5
3.23
Fire detection system connection point, (Each outlet for
smoke , heat detectors, break glass , indoor or outdoor
alarm horn, shall be measured as one point. Price
includes 16mm2 conduits and cables 4x0.8 mm2 ITAC
type or equivalent, and leading from point to the fire
detection section in the communication cabinet or to the
nearest point and all accessories).
No. 80
7 of 15
King Abdullah Bin Abdulaziz Technical Vocational Training Center
Electrical Works
Item Description Unit QTY Unit Rate Total
3.24
Computer outlet connection point wall or table mounted
(The price includes 16mm2 conduits with 4 pairs
computer cable shielded type FTP CAT 5E and leading
from the telephone communication cabinet or computer
HUB to the points as well an outlet with a plastic socket
Legrand or equivalent including Boxes, Supports & Plates
and all accessories).
No. 45
3.25
Electrical Connection for 1‐ phase lifting Pumps. (Price
includes all necessary cables 3X1.5mm2 ITAC type or
equivalent , flexible heat conduits, Isolator switch 10A
cable glands, connection boxes w.p, labeling, adaptors
and all accessories and leading from Relevant panel to
machine to the satisfactory of the engineer.
L.S. 1
3.26
Electrical Connection for 1‐ phase Pumps on roof. (Price
includes all necessary cables 3X1.5mm2 ITAC type or
equivalent , flexible heat conduits, Isolator switch 10A
cable glands, connection boxes w.p, labeling, adaptors
and all accessories and leading from Relevant panel to
machine to the satisfactory of the engineer.
L.S. 1
3.27
Electrical connection of Single phase Extract Fan (the
Price includes 16mm diameter conduit, 3x1.5mm2
cables ITAC type or equivalent, Isolator switch 10A cable
glands, connection boxes w.p, labeling, adaptors and all
accessories and leading from Relevant panel to machine
to the satisfactory of the engineer.
Point 4
Total of Installation Works
8 of 15
King Abdullah Bin Abdulaziz Technical Vocational Training Center
Electrical Works
Item Description Unit QTY Unit Rate Total
4 Lighting Fixtures and Accessories
Note: work for lighting fixtures is to include supply of the
fixtures specified, installation of same connection, wiring,
commissioning, lamps OSRAM type, tubes, starters
louvers, connections, suspension, clamps and all other
accessories necessary to provide a complete fitting with
all terminals and rates also includes all L,Z and omega
profiles if needed , great opening for lighting fixtures in
gypsum board and all other details , as specified in the
technical specifications and drawings and as approved by
the engineer.
4.1Type (A) 2x36w surface mounted light fixture with parabolic louvre GAASH or equivalent .
No. 70
4.2Type (A1) 4X18W recessed light fixture with double parabolic as GAASH or equivalent..
Unit 10
4.3Type (B) 2x36w fluorescent surface mounted light fixture IP65 GAASH or equivalent .
No. 45
4.4Type (E1) 1x8w emergency exit sign with 3 hours maintained duration GAASH or equivalent.
No. 5
4.5Type (C) 2X18W surface mounted light fixture with clear prismatic diffuser IP20 GAASH or equivalent .
No. 80
4.6Type (D) 2X26W surface mounted light fixture with clear prismatic diffuser IP54 GAASH or equivalent .
No. 30
4.7Type (F)100W wall mounted light fixture light IP65 with die cast aluminum body grey color GAASH or equivalent .
No. 30
4.9Type (G) 50w 12V spot light including electronic transformer TARGETTI BTT
Unit 20
4.8 Type (H) 18W wall mounted light fixture LUXTEN or equivalent Unit 4
Total of Lighting Fixtures and Accessories
9 of 15
King Abdullah Bin Abdulaziz Technical Vocational Training Center
Electrical Works
Item Description Unit QTY Unit Rate Total
5 Cables & Conductors / Leads
Supply, install, test and connect the following electrical
cables , including insertion into conduit or attachment to
structural elements or laying in ductwork, including all
associated materials, insulation materials, unions,
labeling and connection of cable at both ends and all
accessories).
5.15x16 sq.mm cross section N2XY cable type Synergy or
ITAC or equivalent.M.L. 50
5.25x10 sq.mm cross section N2XY cable type Synergy or
ITAC or equivalent.M.L. 125
5.35x2.5 sq.mm cross section N2XY cable type Synergy or
ITAC or equivalent.M.L 50
5.45x1.5 sq.mm cross section N2XY cable type Synergy or
ITAC or equivalent.M.L 50
5.53x2.5 sq.mm cross section N2XY cable type Synergy or
ITAC or equivalent.M.L 100
5.63x1.5 sq.mm cross section N2XY cable type Synergy or
ITAC or equivalent.M.L 100
5.7Copper conductor with PVC insulation cross section
16sq.mm type Synergy or ITAC or equivalent.M.L 100
Total of Cables & Conductors Works
10 of 15
King Abdullah Bin Abdulaziz Technical Vocational Training Center
Electrical Works
Item Description Unit QTY Unit Rate Total
6 Cable Conduit & Ducts
Supply, install, test and connect the following standard
conduits or color fire proof conduits, processed over or
under plaster or over false ceiling, including junction
boxes, unios, connectors, etc… including galvanized draw
strings, ready for use "Pony last" type or equivalent and
all accessories).
6.142mm diameter heavy, bendable type NACY, Had ash
Plast or equivalent.M.L 150
6.229mm diameter heavy, bendable type NACY, Had ash
Plast or equivalent.M.L 200
6.323mm diameter heavy, bendable type Had ash Plast or
equivalent.M.L 400
6.416mm diameter heavy, bendable type Had ash Plast or
equivalent.M.L 300
Total of Cable Conduit & Ducts
7 Telephone Cable and low voltage box
Supply, install, test and connect metallic low voltage box
for Telephone, TV , CCTV systems .The size of the low
voltage shall be the same height and depth of the
nearest electrical board with 30cm width .
7.1 MLV No. 1
7.2 LV1 No. 1
7.3 LV2 No. 1
7.4 LV3 No. 1
7.5 LV4 No. 1
7.6
Telephone cable 1NO. 32 pairs Superior from telephone
exchange to the low voltage boxes price includes
terminal blocks, corona and 23 mm fire proof conduits.
M.L 100
Total of Telephone Cable and low voltage box
11 of 15
King Abdullah Bin Abdulaziz Technical Vocational Training Center
Electrical Works
Item Description Unit QTY Unit Rate Total
8 Grounding Works
8.1
30x3.5mm galvanized steel strip ( ROLL) to be welded to
building foundation reinforcement and connected to the
equipotential bus bar of (MDB) by means of 35 mm2
insulated copper conductor including cable shoe and all
required materials, boxes, testing terminals, and all
accessories.
Job 1
8.2
Grounding electrode, made up of a 19mm diameter
copper plated steel rod, such as manufactured by
"ARDING", electrode length: 1.5m, including an
inspection chamber40*40 cm and cover, and a 25 sq.mm
exposed, woven copper conductor, from electrodes to
potential equalizing bus bar in MDB complete with all
accessories.
No. 5
8.3
30x3.5mm galvanized steel strip to be welded to
Generator foundation reinforcement and connected to
the equipotential bus bar of generator panels by means
of insulated 50 mm2 copper conductor including all
required materials, earthing boxes, earth bus bar, testing
terminals, and all accessories.
Job 1
8.4
Grounding of cold and hot water piping, fuel piping, air
conditioning piping, ducts, elevator rails, main and sub
main distribution boards, metallic sewage , supply trunks
metallic cable ducts, Generator, EPABX and any other
metallic service in the building. Rate to include 16 mm2
copper conductors as shown on drawings, main and
secondary potential equalizing bus‐bar, protective
conduit, junction box, complete with all necessary
accessories.
Job 1
Total of Grounding Works
12 of 15
King Abdullah Bin Abdulaziz Technical Vocational Training Center
Electrical Works
Item Description Unit QTY Unit Rate Total
9 Fire Alarm System
Supply, install and connect complete in place and in an
operable manner the addressable fire alarm system
BOSCH or equivalent including of the equipment
specified, installation of same connection, wiring
commissioning and all of the details as specified in the
technical specifications and drawing with complete
operation capacity 125 detectors.
9.1
Addressable main fire alarm control panel for 1 loop ,QS1
( QUICK START 1 )expandable including 24 hour backup
batteries and charger or equivalent.
Unit 1
9.2Addressable photo cell electric smoke detector (SIGA‐PS)
or equivalentUnit 35
9.3 Addressable heat detector (SIGA‐HRS) or equivalent Unit 10
9.4 Addressable break glass unit (SIGI‐271) or equivalent Unit 10
9.5 Indoor alarm siren (GIR‐P) or equivalent Unit 8
9.6 Outdoor alarm siren (757‐5A‐T) or equivalent Unit 1
9.7 Telephone dialer (DL‐125C) or equivalent Unit 1
Total of Fire Alarm System Works
10 Computer Network
10.1
Supply, install and connect , testing and commissioning
Rack cabinet 6U with patch panel 24 port, and 3COM
Baseline 24 PORT 10/100/1000 Switch or equivalent and
straight cables (CAT6 ) Shielded cable between switch
and patch panel and all necessary accessories with
complete operation.
No. 2
10.2
Supply, install, connect and programming Linksys
Wireless‐N Gigabit Security Router with VPN Secure, high‐
speed wireless networking or equivalent.
No. 2
Total of Computer Network
11Electronic private Automatic Branch Exchange (EPABX)
System
11.1
Supply, install, connect and test Panasonic KX‐TDA 100 ‐
8 line external and 24 line interior or equivalent ,the
price includes testing and commissioning works and all
accessories with complete operation .
NO 1
Total of Electronic private Automatic Branch Exchange
(EPABX) System
13 of 15
King Abdullah Bin Abdulaziz Technical Vocational Training Center
Electrical Works
Item Description Unit QTY Unit Rate Total
12 Cable Trays
Supply and install cable trays, cable trunking and sleeves
as per drawings and specifications complete with
supports, fixing devices, covers, separators, clamps, end
caps, draw wires, elbows, joints, branches, reducers,
offsets …as show on drawings and specifications.
12.1LV Cable Tray 200x85 mm perforated galvanized iron,
1.5 mm thickness. (NIEDAX type or equivalent).M.L. 30
12.2Power Cable Tray 300x85mm perforated galvanized iron,
1.5 mm thickness. (NIEDAX type or equivalent).M.L. 40
Total of Cable Tray Works
13 Fire Fighting System
Supply install and connect complete in place and in an
operable manner the Fire Fighting system Telefire /Mircom / Kidde or equivalent For main distributionboard at electrical room . The work is to include thesupply of the equipment specified, installation ofsame connection, wiring commissioning and all ofthe details.
13.1
Automatic Valve Cylinder 3 Kg Kidde FM 200 P/ N 90100011001 ( 180 Degree Pendant Nozzle , 3/8" Check Valves , Bracket , Pressure Gauge , Copper pipe , Safe Cap …...with all accessories needed )
No. 1
13.2 Main Control Panel 2‐ Zone Telefire 2-B or equivalent No. 1
13.3Photoelectric Smoke Detector MIR-338H / TFO-440 or equivalent
No. 4
13.4 Heat detector ‐ S.S 5601 P / TFH-220F or equivalent No. 2
13.5 Indication lamp TFL-1N or equivalent No. 2
13.6 Break glass unit TPB-10 R or equivalent No. 1
13.7 Fire Indoor Horn TIP-224A or equivalent No. 1
Total of Fire Fighting System Works
14 of 15
1 Total of Main Feeder Works
2 Total of Electrical Switchboards Works
3 Total of Installation in the Building Points Works
4 Total of Lighting Fixtures Works
5 Total of Cables & Conductors / Leads Works
6 Total of Cable Conduit & Ducts Works
7 Total of low voltage box Works
8 Total of Grounding Works
9 Total of Fire Alarm System Works
10 Total of Computer Network Works
11Total of Electronic private Automatic Branch Exchange(EPABX) System
12 Total of Total of Cable Tray Works
13 Total of Total of Fire Fighting System Works
Total of Electrical works -including provisional items (Not Including Value Added Tax )
Currency of Bid (NIS or USD) : ________________
King Abdullah Bin Abdulaziz Technical & Vocational Training Center
Electrical Works
Electrical Summary
15 of 15
King Abdullah Bin Abdulaziz Technical & Vocational
Training Center
BOQ Landscaping works
King Abdullah Bin Abdulaziz Technical Vocational Training Center
Landscaping Works
Bill No. 1 Excavation and Earth Works
Item No
Description Unit QTY Price/
Unit Total
The Contractor shall when pricing the rates of this bill, take into consideration including and allow for the cost or expenses of all requirements stipulated in the preambles, drawings, and technical specifications. The words engineer below means owner's engineer. The rate include the following:
The contractor has to supply a Mesh Survey plan 5mX5m for the site from approved engineering surveyor before and after the works for quantities measurements .
The Contractor should present a soil investigation report from an approved Building laboratory as per engineering association requiments and standards on his own expenses.Excavation and backfilling for Working Space will not be measured .
In case and after the soil investigation report is done it was required to do more excavations, all excavations work will be carried over the bid unit price, the Contractor has no right for any kind of claims or any unit price change .
1.1
Cut in any kind of soil, concrete or stone walls to reduce level for foundation of retaining and boundary walls and foundation for security room, to reach the desired level(Hard Natural Rock)) according to drawings and site instructions .The price should include using and laying the approved fill material from site and or from outsite to reduce level and all test required to use the approved cut material for filling and watering ,compacting 100% each layer 20 cm and removing the unapproved excavated materials from the site to an approved dump location
m3 80
1.2
Supply and Lay selected & approved base coarse filling First class at 20cm layer to the required level ,watering and compacting 100% , the price include before basecoarse works ,filling approval fill below basecoarse layer ,watering and compaction 100%and where directed by the Engineer.
m2 380
1.3
Supply and install Asphalt layer 3/4'' thick=7cm the price include spread primer coat CO 1 1/2 kgr/m2 and all compaction testing for basecoarse and asphalt and as specification and as shown on drawings .
m2 150
Total of Bill No. 1
1 of 16
King Abdullah Bin Abdulaziz Technical Vocational Training Center
Landscaping Works
Item No
Description Unit QTY Price / Unit Total
2 Concrete Works
The contractor shall, when pricing the rates of this bill, take into consideration including and allow for the costs or expenses of all requirements stipulated in the preambles, drawings and technical specification of the tender.
Each concrete pouring on site will be tested, pouring less than 6m3 will be tested, pouring more than 6m3 will also be tested on 6m3 portions i.e. each concrete truck on site will be tested, all done by an approved testing institute on contractors expense
The price should include cleaning all the foundation excavations, checking the sizes according to drawings, resizing if needed, cleaning, and installing wooden frame to marked the footings as instructed and approved by the site engineer
In case and after the soil investigation report is done, concrete quantities may vary,any Additional or less in bid quantities will be carried over the bid unit price, the Contractor has no right for any kind of claims or any unit price change .
2.1 PLAIN IN-SITU CONCRETE B200[200 Kg / CM2]
Supply & install Concrete B200 of 28 days cube crushing strength 200kg/cm2. Price shall include cleaning, compaction, shuttering and making good of ground surface before casting of concrete. Price shall include all nails, forms and equipments needed.
2.1.1 - Blinding under footing, ground beams thick 10cm m3 10
Bill No. 2 Concrete Works
2 of 16
King Abdullah Bin Abdulaziz Technical Vocational Training Center
Landscaping Works
Item No
Description Unit QTY Price / Unit Total
Bill No. 2 Concrete Works
2.2 REINFORCED IN-SITU / READY MIXED CONCRETE
B300/ 300 Kg / CM2]
Supply & install concrete B300 of 28 days cube crushing strength 300kg/cm2. Price shall include the following:1. Cleaning and making good of surfaces before casting of concrete2. Steel reinforcement workmanship as per drawings.3. Form-work of any type or shape .4. Any materials such as nails, wires , 6mm steel for shuttering or any other material or workmanship needed for a best completion of the works .5. Installation of 2 cm thick. high density polystyrene on expansion joints.6. All steel reinforcement of any diameter and shape of high yield stress steel.7. Cube test 10x10x10cm and slump test before pouring any concrete on site, and vibration the concrete during casting . 8- isolation all buried parts using approved butimunies layer (hot or cold ) as per site engineer instructions and approval.
8.The measurement for slabs from the middle of the walls , and include all drop and inverted beams .
3 of 16
King Abdullah Bin Abdulaziz Technical Vocational Training Center
Landscaping Works
Item No
Description Unit QTY Price / Unit Total
Bill No. 2 Concrete Works
2.2.1Foundation of any shape, depth and size including retaining wall foundations, boundary wall and ground beam for security room footings , when pricing the
A- Check and report to the site engineer the situation of the excavation by an approved surveyorB- Clean the foundations excavations, and making good of any excavation if neededC- Resize the excavations to suit the design if there was any mistake in the excavation processD- Lay a wooden Works Frame Reference around the building to be referenced by an approved surveyor and approved by the site engineer.
m3 30
2.2.2For bearing retaining walls the price include the steel and scaffolding works from one side and as shown on drawings .
m3 100
2.2.3Ditto but for boundary walls the price include the steel and scaffolding and as shown on drawings .
m3 12
2.2.4
For security room reinforced Solid slab Thickness 15cm the price include scaffolding works and steel reinforcement and as shown on drawings and instructed by the site engineer
m2 11
2.2.5
Supply and install septic tank the price include excavation works to reduce level, concrete for blinding ,foundation ,wall and slab and steel reinforcement for all concrete element and all scaffolding works ,the price include also glanz plastering layer and two layers sika top from the inside walls and ceiling and precast Steel cover 25 ton as shown on drawings . all as instructed and approved by the site engineer
job 1
2.2.6
Supply and install plants bed size 1.0mX1.0m the price include excavation works to reduce level , concrete elements, steel reinforcement ,curbestone,plastering .agricultural soil and all scaffolding works and as shown on drawings .
job 17
2.2.7
Supply and install plants bed size 2.4mX0.90m the price include excavation works to reduce level , concrete elements, steel reinforcement , stone and coping ,plastering .agricultural soil and all scaffolding works and as shown on drawings .
job 4
Total of Bill No. 2
4 of 16
King Abdullah Bin Abdulaziz Technical Vocational Training Center
Landscaping Works
Item No
Description Unit QTY Price / Unit Total
3 Stone Works
3.1 STONE BUILDING AND POINTING
The contractor shall, when pricing the rates of this bill, take into consideration including and allow for the costs and expenses of all requirements stipulated in the preambles, drawings and technical specification of the contract. The price includes the following:
All stone should be From Hebron area dark colour class A-A, بند ارضي, with the following specifications:
- Absorption by weight should not exceed 0.9% using ASTM test method C97 - Density (Kg/m3) should not be less than 2700Kg/m3 using ATSM test method C97 - Compressive strength should not be less than 56MPa using ATSM test method C170 - Modulus of rupture should not be less than 6.9MPa using ATSM test method C99 - Abrasion resistance (hardness) should not be less than 10 using ATSM test method C241 - stone should be clear, free from all veins, cracks and salt holes from both sides
1. Steel anchors as specified.2. Flush pointing works composed of white cement and sand (1: 2) with approved additives for better workability, tightness and water proofing. 3. Ф8mm 20X20cm steel mesh reinforcement to be used for all stone concrete backing.4. Stone built shall be measured only " Net Measurements "
Bill No. 3 Stone works
5 of 16
King Abdullah Bin Abdulaziz Technical Vocational Training Center
Landscaping Works
Item No
Description Unit QTY Price / Unit Total
Bill No. 3 Stone works
5. Each building stone must have at least two galvanized anchors from the top and to be fixed to the 3mm steel mesh.Similar stone can be either new stone or old stone from other sites. Both types must be supplied after the approval of the engineer.6. Acceptance of delivered stones should be carried by comparing every stone delivered on the truck to the sample built on site. All stones will be picked up and chosen by a specialist person (dresser) paid by the owner before using the stone.7. Rate includes and kind of stone dressing.8. Copping stones to be Mutabbeh finish for the horizontal surface and Taltish finish for the vertical
sides.
3.1.1
Supply and install 5 cm thick 25cm high TALTEESH stone courses for security room the price including all special pieces i.e. jams, lintels, sills and stone corners (at least 15cm deep), as shown on drawings. The price includes B200 concrete backing 20cm, anchors and steel reinforcement and glanz layer and block 7cm all as shown on drawings, instructed and approved by the site engineer .
m2 35
3.1.2Supply and build 5cm Thick stone copping width in any location as shown on drawings
m2 15
3.2 Stone Cladding
Supply, install stones cladding of excellent quality grade A-A " بند ارضي " with different thickness dressed Mulatash free from cracks. Rate for stone cladding shall include for:
All stone should be Herbron area dark colour class A-A, بند ارضي, with the following specifications:
- Absorption by weight should not exceed 0.9% using ASTM test method C97 - Density (Kg/m3) should not be less than 2700Kg/m3 using ATSM test method C97 - Compressive strength should not be less than 56MPa using ATSM test method C170 - Modulus of rupture should not be less than 6.9MPa using ATSM test method C99 - Abrasion resistance (hardness) should not be less than 10 using ATSM test method C241 - stone should be clear, free from all veins, cracks and salt holes from both sides
6 of 16
King Abdullah Bin Abdulaziz Technical Vocational Training Center
Landscaping Works
Item No
Description Unit QTY Price / Unit Total
Bill No. 3 Stone works
1. Work for all classification in any location.2. Stone shall have a minimum thickness of 5cm after dressing with a rough back preferably.3. Stone built shall be measured only " Net Measurements "4. Stone sills and lintels of any kind shall be measured within the stone building and not separately
5. Corner and jambs stone of any kind shall be measured within the stone building and not separately6. Key stone and any other particular stone shall be measured within the stone building and not separately7. Price shall include concrete backing and Ф6 mm @ 20cm welded steel mesh and steel reinforcement for lintel beams.8. Stones with quality grade A-A (بند ارضي) shall be used only.9. Acceptance of delivered stones should be carried by comparing every stone delivered on the truck to the sample built on site. All stones will be picked up and chosen by a specialist person (dresser) paid by the owner before using the stone.10. Flush pointing works composed of white cement and sand (1: 2) with approved additives for better workability, tightness and water proofing.
3.2.1
Supply and install 5 cm thick 25cm high, stoneTaltish courses of first quality the price including all special pieces i.e. jams and lintels and stone corners, of depth not less than 25cm. The price includes 7-10cm thick B200 concrete backing,steel mesh and galvanized wire 3mm to tie the stone to the steel mesh as shown on drawings. The rate includes for walls and around columns and all special pieces . (Provisional Item)
m2 150
Total of Bill No. 3
7 of 16
King Abdullah Bin Abdulaziz Technical Vocational Training Center
Landscaping Works
Bill No. 4 Plastering Works
Item No
Description Unit QTY Price / Unit Total
WALL PLASTERING
4 External Plaster (Provisional Item)
The contractor shall, when pricing the rates of this bill, take into consideration including and allow for the costs or expenses of all requirements stipulated in the preambles, drawings and technical specification of the contract.
Prepare surfaces, apply a rendering coat (رشة مسمار),apply in two coats of rough and fine finish withordinary Portland cement , sand and lime asspecified. The price includes angle beads andmovement beads.
4.1
On walls 13mm thick external plaster (Shabrees)including patching works for any mechanical, electricalor civil works. Price should include supply and install stiwire mesh 200 mm wide , cloth mesh where required,All as per site engineer instructions .
m2 200
Total of Bill No. 4
8 of 16
King Abdullah Bin Abdulaziz Technical Vocational Training Center
Landscaping Works
Item No
Description Unit QTY Price / Unit Total
5 Tiling WorksThe Contractor shall when pricing the rates of this bill, take into consideration including and allow for the cost or expenses of all requirements stipulated in the preambles, drawings, and technical specifications.Unit rate shall includes all designs and cutting as per drawings with no allowance for wasted tiles. Net engineering measurements on site for square meter will be considered.Unit rates for tiling works shall include the completion of works according to all details shown on drawings. The rate includes the pointing or grouting as specified, the crystal polish of terrazzo tiles.Tiling should be done using WHITE CEMENT only, even if not specified in the item
Terrazzo Tiles
5.1 Tiles
Supply and install the following class A irregular natural tiles with a pattern as per drawings. All bedded in , or backed with white cement and sand mortar (1:3) . The price shall include the supply and spreading of a layer of sand and Portland cement dry mixture under tiles and pointing with white cement thick 5cm and as shown on drawings .
5.1.1 To Floors m2 220
Bill No. 5 Flooring
9 of 16
King Abdullah Bin Abdulaziz Technical Vocational Training Center
Landscaping Works
Item No
Description Unit QTY Price / Unit Total
Bill No. 5 Flooring
5.2 Stone Tiling1- All as per stone samples on site for colour, quality and shape.2- All stone tiles shall be free from cracks with quality grade A-A (بند ارضي) .3- Rates for tiles shall include for straight and curved cutting, waste, grouting and pointing to execute the works to the satisfaction of the Engineer.4- All stone tiles will be picked up and chosen by a specialist person (dresser) paid by the owner before using the stone - Absorption by weight should not exceed 0.9% using ASTM test method C97 - Density (Kg/m3) should not be less than 2700Kg/m3 using ATSM test method C97 - Compressive strength should not be less than 56MPa using ATSM test method C170 - Modulus of rupture should not be less than 6.9MPa using ATSM test method C99 - Abrasion resistance (hardness) should not be less than 10 using ATSM test method C241 - stone should be clear, free from all veins, cracks and salt holes from both sides
5.2.1
Supply and install approved natural stone polished for stair flight thick 3cm for tread and 2cm for riser the price include cement mortar under the stone and filling cement:sand 1:1 below the tiles the price include stone panels and skirting for water resist and as shown on drawings .
m.r. 25
5.2.2
Supply and install approved natural stone frame width 25 cm and thick 5cm between irregular tiles the price include cement mortar under the stone and filling cement:sand 1:1 below the tiles the price include and pointing 1cm and depth 2cm with white cement and as shown on drawings .
m.r. 80
Total of Bill No. 5
10 of 16
King Abdullah Bin Abdulaziz Technical Vocational Training Center
Landscaping Works
Bill No. 6 Water Proofing
Item No
Description Unit QTY Price / Unit Total
6 Water Proofing (Security Room)
The contractor shall, when pricing the rates of this bill, take into consideration including and allow for the costs or expenses of all requirements stipulated in the preambles, drawings and technical specification of the contract.
6.1
Supply and install 4 mm thick layers for top roof of modified bituminous membrane like Pazkar SBS 5/250 laid above two primer coats of GS474 at a rate of .25 kg /m2 or equivalent approved by the engineer on a clean surface of the roof tiling and around the parapets. The price includes supply and install sealant cover at groove" Sikaflex-pro 2HP or equivalent" . The price includes also supply and install 15*15cm angle fillet as shown in the drawings and painting the joints with "Silver PAZ". The application should be carried out in conformity with the manufacturers’ specifications and using propane torch welding only. the price include inclination concrete B-200 1% and the minimum thickness 5cm in near rain pipes .The measurement horizontal dimension .
m2 12
6.2
Supply and apply two coat of Sika Top Seal 107 or equivalent on a clean surface for the wet areas. The price includes 5*5cm angle fillet with smooth sand cement mortar (1:3) surface layer before applying the water proofing materials. The application should be carried out according to details and in conformity with the manufacturers’ specifications price include testing as instructed by the site engineer. The measurement horizontal dimension .
m2 10
Total of Bill No. 6
11 of 16
King Abdullah Bin Abdulaziz Technical Vocational Training Center
Landscaping Works
Item No
Description Unit QTY Price / Unit Total
7 Metal Works
The contractor shall, when pricing the rates of this bill, take into consideration including and allow for the costs or expenses of all requirements stipulated in the preambles, drawings and technical specification of the contract.
The rate for steel works includes the followingA. The submittal of shop drawings for the satisfaction of the Engineer prior to fabricating the units.B. The fabrication and installation of full scale model for part of metal works for inspection and approval of the Engineer before commencement of work.
7.1 ALUMINUM WORKS
Supply and install the following colored (powder coated, Migor'an) Dark gray Metallic color as per sample on site, Aluminum Mifromal Profile as made by NABCO wajhat Zojaj, as shown on drawings ( All hinges and handles have to be powder coated same color as aluminum
Price shall include laminated tempered glass 6/12/6mm , Ironmongery, fixing accessories original from Mifromal or Arpal such as rails, hinges, locks, brushes, rubber EPDM and angles must be original corresponding to each profile.Filling all sides and under the threshold and sills with SIKA FLEX 2H Pro color as of the aluminum color from out side and all exposed joints and MASTIC (NIRLAT made) from inside colored as the aluminum color All as instructed by the site engineer
Supply and install the followings ALUMINUM combinations NAPCO doors and windows 7700, as per drawings and specifications, all as instructed by the site engineer
7.1.1 windows for security room with overall dimensions as per drawings and Details.
m2 3
7.2 Steel Works
The rate for steel works includes the following:
A. The submittal of shop drawings for the satisfaction of the Engineer prior to fabricating the units.
Bill No. 7 Metal Works
12 of 16
King Abdullah Bin Abdulaziz Technical Vocational Training Center
Landscaping Works
Item No
Description Unit QTY Price / Unit Total
Bill No. 7 Metal Works
B. The fabrication and installation of full scale model for part of metal works for inspection and approval of the Engineer before commencement of work.C. cleaning of all steel profiles prior to commencement with painting layers as specified and shown in drawings.
D. Supply all kinds of material and apply two coats of APC antirust paint, and two coats of APC primer (ORANGE COLOR) Product Code: , drying period 3 days between each product
E. Supply all kinds of material and apply painting for steel, the price should include applying two coats of HAMMERITE paint with HAMMERITE dissolvent all as approved and instructed by the site engineer. The application should be carried out according to details and in conformity with the manufacturers’ specifications.
Supply and install the following steel doors, price to include cylinder, lock as made by WALLY, or approved eq., as a complete job,as shown on drawings.
7.2.1Door for security room with overall dimensions as shown on drawings
m2 3
7.2.2 Main external Entrance gate size 4X2.5m m2 10
7.2.3 Gate size 1.80X2.5m m2 5
7.2.4Supply and install metal protection bars for windows and as shown on drawings .
m2 3
Total of Bill No. 7
13 of 16
King Abdullah Bin Abdulaziz Technical Vocational Training Center
Landscaping Works
Item No
Description Unit QTY Price / Unit Total
The contractor shall, when pricing the rates of this bill, take into consideration including and allow for the costs or expenses of all requirements stipulated in the preambles, drawings and technical specification of the contract.
The contractor should allow in his pricing that the engineer will use as many different colours or combination of colours to meet an approved colour scheme. ( Company ready mix original)No hand made color mix is allowed.
The contractor has to prepare a color sample 1*1m on site for each color asked by the site engineer
All paint works should conform to Tambour instruction regarding number of coats , rate of application or drying time.
All protection and care should be taken against paint drips, drops, droplets, and brushing.
The contractor should study well the project, walls, ceilings, gypsum boards, and all finished surfaces before applying the paint, so that if he discovers any mistake or additional needed works, he shall inform the engineer so as to adjust and agreed upon additional items before signing of the contractor. Otherwise the contractor will be responsible and take no extra money for any change of order.
Bill No.8 Painting Works
14 of 16
King Abdullah Bin Abdulaziz Technical Vocational Training Center
Landscaping Works
Item No
Description Unit QTY Price / Unit Total
Bill No.8 Painting Works
8 On Walls & Ceiling
8.1
Supply all kinds of raw material and apply paint Amulsion for security walls room ,and wherever needed or instructed by the site engineer, the price should include preparing surface, clean, remove dust and foregin matter, sanding with well with sand paper, checking the walls with putty, laying two coats of putty (APC brand or an approved equivalent), applying one coat of APC SUPER BOND ROLL and applying Four coats of APC Painting or equivelent Product, all as instructed and approved by the site engineer.
m2 40
8.2
Supply and apply Four coats of APC FILL Aracid Product ceilings over plastering, electrical, mechanical shafts, elevator shaft and wherever needed or instructed by the site engineer.
m2 15
Total of Bill No. 8
15 of 16
King Abdullah Bin Abdulaziz Technical Vocational Training Center
Landscaping Works
Bill No. Description Total
Excavation & Earth Works
Concrete Works
Stone Works
Plastering Works
Tiling Works
Water Proofing Works
Metal Works
Painting Works
Total of Civil Works (External works)-including provisional items(Not Including Value Added Tax )
Currency of Bid (NIS or USD) : ________________
Summary of Civil Works Bills 1 - 8
1
2
3
7
8
4
5
6
16 of 16
King Abdullah Bin Abdulaziz
Technical & Vocational Training Center
GRAND TOTAL SUMMARY SHEET
King Abdullah Bin Abdulaziz Technical Vocational Training Center
Total Summary
Summary Sheet
Bill No. Description Total
1 Summary of Civil Works Bills
2 Summary of Mechanical Works Bills
3 Summary of Electrical Works Bills
4 Summary of External works
Grand Total - including provisional items (Not Including Value Added Tax )
Currency of Bid (NIS or USD) : ________________
The Sum of (in words) :
Contractor:
Authorized Person Name & Title :
Signature & stamp:
Date:
Tel:
Mob:
Fax:
E-mail:
Address: