chris brown manager civil assets network operations ... · level crossing at arduard rd, blackwater...
TRANSCRIPT
Commercial in Confidence
Aurizon Network
Chris Brown Manager Civil Assets Network OperationsSeptember 2015
Commercial in Confidence
Overview of CQCN
Commercial in Confidence
3
Central Queensland Coal Network Overview Managing track access to 2,700km of rail network with 2,000km
electrified
Longest distance between mine and port of 438km
Loading at 40 mines
Delivering to 6 export coal terminals and 7 domestic customers
Communicating with 7 Rail Operators across Coal (4), Freight (2) and Passenger(1) services
Average railings of 612kt per day for FY15
Hay Point Expansion
Cost: $121mAdditional Capacity: 11mtpa
GAPE
Cost: $1100mAdditional Capacity: 33mtpa
Rolleston Electrification
Cost: $163mElectrification of 113km track
Wiggins Island Rail Project
Cost: $858mAdditional Capacity: 27mtpa
GROWTH PROJECTS
180
230
200
220
170
0
210
190
Mill
ion
Tonn
es
2013/14
227
2011/12
+35.8%
2012/13
211
2014/15
181
223
2010/11 2015/16 Forecast
165 165
Commercial in Confidence
4
Organisational Structure
Safety
Volume
Reliability
Cost
People
Maintenance and Renewals Assurance Strategy for Civil, Signals,
Telecoms and Electrical assets
Maintenance
Plant
CQCN Operations
Infrastructure, Signals, Traction, Control and Communications Systems
Extreme weather preparation Preventative maintenance
Resurfacing Ballast Cleaning Maintenance of Plant
Control Centre Management Critical capacity planning Scheduling of access paths Performance analysis
Planning Strategic system planning System planning principles Closure optimisation
Asset Management
NETWORK FINANCE
NETWORK REGULATION
NETWORK OPERATIONS
NETWORK COMMERCIAL
Commercial in Confidence
5
Blackwater Moura Goonyella Newlands CQCN
Coal Rail Operators AurizonPacific National
Aurizon AurizonPacific National
BMA Rail
AurizonPacific National
AurizonPacific National
BMA Rail
Average Cycle Time 25.6 17.1 18.4 18.2 20.5
Standard Payloads 8,144 6,234 9,979 6,656 8,573
Average Trains per Day 22.1 5.3 31.9 12.1 71.4
Record Trains in a Day 30 13 43 18 90
Volume in FY15 65.77mt 11.99mt 116.37mt 29.34mt 223.47mt
CQCN Train Services Fast Facts
Commercial in Confidence
6
Assets Blackwater Moura Goonyella Newlands CQCN
Track (km) 1,186 260 980 320 2,746km
Electrified Track 1,030 0 980 0 2,010km
Rail 2,296 520 1,960 640 5,416km
Turnouts 394 67 453 89 1,003 T/O
Culverts 1,371 679 1,168 591 3,809
Bridges 134 56 115 32 337
Sleepers 1.94 0.43 1.62 0.53 4.52 million
CQCN Asset Fast Facts
Commercial in Confidence
7
Automated remotely monitored rail lubricators installed at key locations on the network reduce rail
wear and improve the rail/wheel interface
Completed trackslab installationCooling Channel Bridge
Infra-red analysis
Innovation in Assets and Maintenance Low Profile Composite Sleepers
Renewing culverts under traffic improves the asset while maintaining
capacity
High definition images
Unmanned Aerial Vehicles
Resin Based Culvert Solution
Completed culvert
Drones reduce the time required on track for inspections while providing data for preventative
maintenance and minimising exposure to working at height for staff.
Ballastless Trackslab
Ballast heavily fouled by coal dust needs replacement every 2 years; high cost, major impact on network
availability and velocity
Improved total cost of ownership and service life with lower maintenance
compared to existing sleepers
Electric Rail Lubricators
Commercial in Confidence
8
• Wheel impact detects identify flat wheels which impact rail, increase the risk of rail break and reduce rail life
Reliability & Asset Protection – Protection
Commercial in Confidence
9
Safety – Level Crossings
• Lasers detect high loads and alarm driver to stop. • Protects against dewirements at level crossings• Continual safety improvement project for level crossing
Leading edge asset diagnosis is key to improve asset condition knowledge and move to a complete predictive focus
Note: Whole Network complete
Note: Tendering for remote recording equipment for locomotives with automatic download
Ground Penetrating Radar Track Defect Inspection Reporting
Commercial in Confidence
11
Level Crossing at Arduard Rd, Blackwater
Level Crossing at Arduard Rd, Blackwater
Delivering Improvements – Safety (Level Crossings)
• Over height Detectors – Blackwater and Dingo• Gracemere Overbridge – removed two level
crossings
Commercial in Confidence
12
Reliability & Asset Protection - Reliability
• Installation Points monitoring; the force to move a turnout predicts failure• Being installed at high use turnout• Alarms sent to Fault Control Centre automatically
Measurement and alarm trigger shown below
Commercial in Confidence
13
Commercial In Confidence
Delivering Efficiency Improvement - Mt Larcom Vital GE In-sleeper points machine
In-sleeper points machine allows tamping over the points machine. The manufacturer promises increased reliability and decreased maintenance. Trailability of machine should eliminate roddingdamage after run throughs.
Points condition monitors installed handled by the FCC
Jammed
Delivering Reliability Improvements – Points Monitoring
13
Cooling Channel Bridge Ballast-less Track
1
In July 2015, Cooling Channel Bridge was converted from a ballast deck bridge to a ballast-less track bridge in a 94 hour closure.
Previously, ballast on the bridge was required to be replaced every 18-24 months due to coal fouling.
The new track slab has an expected life of 50 years
The project pay back period is 8-10 years compared
Less closures associated with maintaining the track over the bridge will be required.
The design will looked to be implemented on other critical bridges
Design features:
Precast panels encased by super workable high strength concrete
Delkor rail fastenings pre-attached to precast slabs for quick installation
Self cleaning drainage system retrofitted to treat run-off before discharge
For further info contact Reannan Moodie
Innovative Delivery in FY16 - Culvert Solution
1
Current State Culverts are placed in the wettest part of the track formation to direct water flow and prevent
formation damage and washout Corrugated metal pipes have been commonly used for culverts, while cost effective, are only
2mm thick and rust in damp conditions with significant risk of catastrophic failure Culvert replacements are relatively expensive (~$300 – 400k for 3 pipes) and require
significant network closure time due to the impact on formation, ballast and trackFuture State Berolina system is a corrosion resistant fiberglass sock with 12mm thick UV‐light cured
polyester resin that coats the inside of the existing pipe Designed and manufactured in Germany to suit specific pipe geometry, represent a
collaboration between Aurizon and contractor ITS Pipetech Maintains existing hydraulic performance, 50 year design life (RPEQ Certified)
Advantages Track remains undisturbed and lines remain open– no possession
or post work speed restrictions required! At least 30% cheaper than traditional culvert replacement The potential to save Aurizon up to $100 million in direct CAPEX
costs over the next 20 years Supports 30t axle load for potential future load increases
Trains running while resin installation in progress
Culverts after completion of resin and fibreglass liner
Corrugated metal culvert showing extensive corrosion
Network Asset Update
Supersites - Providing real time data collection to better manage below rail assets
A “Supersite” is a strategically selected location that houses a range of wayside equipment in a common on track location. These locations (1 per coal system) are selected due to their position of the rail Network, (relative to traffic task), security of power, strong communications and convenient , safe access.
Designed primarily as a site for co-location of asset protection systems such as mainline weighbridges, wheel impact detectors (WILD) and pantograph defect detection (Pancam), sites are also available for installation of above rail operator’s equipment for further measurement and condition monitoring of rollingstock.
An exhaustive site selection process was undertaken to find sites suitable for the equipment to be installed in terms of speed, topology, access and access to communications and power. All fours sites were identified and project progress is as below:
Wandoo Supersite building and compound
WILD installation at Wandoo 1
Civil works complete WILD Weighbridge Pancam
Goonyella (Wandoo) Jun-14 Jun – 14 2017 2017Blackwater (Kalapa) Feb-15 Oct – 15 Mar-16 2017Moura (Graham) Sep-15 Dec - 15 2017 x
Newlands (Abbot Point) Jul-15 x Apr-16 xApplication of Data (data will be available to operators via the Network assets Portal)• The Mainline weighers will form the missing link in our wagon weighing systems,
allowing direct comparison between sites and automatic detection of accuracy drift• WILD data will be used to identify defective wheels causing impact to the rail and assist
operators to manage their wheel defects below the alarm thresholds• Pancam will provide additional reference information for the interface between the train
pantograph and the overhead at line speedBenefits • Mainline weighing will form the voice of reason for weight disputes, and put an end to
accuracy questions, thereby increasing certainty and reducing delays • Application of WILD will both protect the assets for defective wheels and allow operators
to better plan wheel change outs informed from wear data• Pancan information will held reduce pan related dewirements and allow operators to
better manage the carbon change out schedule on train pantographs
Commercial in Confidence
17
Commercial In Confidence
TAS – Track Access System: Innovation through technology
A joint venture with QR, scheduled for field rollout in September 2015. Factory Acceptance Testing underway. Possible delay due to Pluto implementation in Control Centre.
17
• View of the train control screen to the field, allowing personnel to see rail traffic and adjacent work groups.
• GPS location and translation to train control system layouts –providing an engineering control for identification of location (for both field and control centre)
• Electronic communication –provides an engineering control to eliminate human error in communication
Commercial in Confidence
18
Reliability & Asset Protection - Protection
• Dragging Equipment Detectors (DED): Detect derailed trains, broken axles and alert train control and driver to stop train and limit damage
• Left if old style required attention after operation (response expense and risk if run trains before reset)
• Right is more reliable, new, resetting DED.
CQCN ION Meter Blackwater
1
2
Safety
Cost
Reliability
Volume
Operational LAN WAN
2
Photo STC HBD new Web Portal
2
Photo STC HBD new Web Portal
Photo of CMS (WILD and HBD Systems)
Commercial in Confidence
24
UAV (Unmanned Aerial Vehicle)
Overview
Automated collection of track condition data for traction assetsHigh Def Imagery and Infra-Red analysis Condition-based maintenance and renewals programsProgress so far:
Proceeding with procurement of 2 systems Training for linesman - completedStart data collection - completedAnalysis Outputs
24
Commercial in Confidence
25
UAV Business BenefitsThe project will:Provide detailed asset condition data to inform the investment and maintenance program Maximise reliability by targeting corrective works based on analysisReduce business impact of inspection activities by not requiring track access or HV isolationPreviously imagery acquired with full-sized aircraft (Big $$ 500k+)Total UAV project cost $324k
High Def imagery like this shows great detail of asset condition information
25
Commercial in Confidence
26
Innovation in Planning, Scheduling and Day of Operations
Network Forecasts and Planning
Plan and Schedule Generator
Real-Time PlanningSupport
Conflict Resolution & Optimization
Day of Operations (DOO)
Supply Chain Optimisation
Real‐Time Traffic Management
Business rules embedded into solution
Real-time train movement (interactive graphs)
Conflict detection and resolution (manual > automated)
Performance Dashboards (plan v’s actual)
Recovery to Plan with CQCN impacts consideration
Forecasts / Plans (2 years to DOO) ‘What-if’ opportunity analysis Plan to Schedule creation and
optimisation
Advanced Planning and Execution (APEX) is a transformational tool integrating industry proven technologies into a single solution to optimise planning, scheduling and day of operations for the Central Queensland Coal Network
Network Asset Management System (NAMS) is a multi-phase business transformation project. It will provide a single source of comprehensive asset data with In-field mobile devices to support maintenance delivery Standardisation of work delivery processes Asset condition datacapture including photos, design drawings & safety
information Asset level costing, analysis, planning and scheduling.
Commercial in Confidence
Network Operations CQCN Transformation and Strategic Focus
Commercial in Confidence
28
Network Ops CQCN Transformation Journey
45
Support planning and execution with increasing complexity
• More mine to port combinations• Increased volumes
Better utilisation of capacity and existing asset ‐more trains, maintenance and track activity
Further reduce Day of Operation losses through decision making with full system view vs individual sections
Replace manual processes and legacy in‐house systems
Provide integrated solution from long term planning, to scheduling and day of operations
Platform for ‘auto routing’
Remaining Business Need
Consolidation of Mackay and Rockhampton based Control Centres to form CQCN Control Centre in Rockhampton (2011);
Consolidation of Network Operations North and South to form Network Operations CQCN with restructure of leadership, planning and business system teams (2013);
Implementation of consistent planning tools across CQCN (2014);
Review of Business Execution Rules and implementation across all Rail Operators and Ports;
KPI reporting to Rail Operators and Supply Chain Forums implementation (2014).
Recent Transformation Activities
Commercial in Confidence
29
Building a sustainable future through partnering with customers to achieve repeatable excellence in below rail operations through planning, scheduling and execution and supply chain coordination.
We are a disciplined operator of below rail assets and integral to supply chain coordination, using transferrable, repeatable processes to deliver for our customers.
Build and promote our repeatable, transferrable operational skills for below rail planning, scheduling and execution, using reputation for excellence in CQCN to attract growth opportunities both domestically and internationally. This growth may be through direct operations or consultancy opportunities to other rail networks.
Translating Aurizon’s Blueprint for Network Operations CQCN
Commercial in Confidence
30
We’re driven by smartprocess, not only smart people.
Disciplined Planning is Key.
Embed a ‘Lift and Shift’Mentality.
Move to portfolio approach for Supply Chain Coordination
Market the Outcomes
and Offering.
Our 5 Year Strategy
Step Change
Step Change to Achieve Our 5 Year Strategy
Commercial in Confidence
31
Step Change How will we know when we have achieved each step change?
We’re driven by smart process, notonly smart people.
… when our processes have the rules built into them, and stand‐alone red tape like ‘System Rules’ will no longer exist.
DisciplinedPlanning is Key
… when our smart processes and our tools are widely known and trusted, offering value‐add to supply chains and driving discipline within Network and Supply Chain activities.
Move to portfolio approach for Supply Chain Coordination
… when our processes are packaged into core uniform modules, with checklists/tools that tailor our approach to the needs of individual supply chains (including mine production and shipping considerations).
Embed a Lift and Shift Mentality
… when can ‘lift and shift’ our process modules to grow new opportunities in our existing Supply Chains & also secure opportunities in new Networks and Supply Chains.
Market the Outcomes and Offering
… when our services will be ‘in demand’, with existing and new customers seeking and agreeing to partner with us to provide then with new services because of the value‐add and discipline we offer.
Step
Cha
nge to a Sustainab
le Future
Commercial in Confidence
32
Commercial in Confidence