chbwv project overview quarterly public meeting feburary... · drums shipment of vitrification...
TRANSCRIPT
![Page 1: CHBWV Project Overview Quarterly Public Meeting Feburary... · drums Shipment of Vitrification Melter, Concentrator Feed Make‐up Tank (CFMT) and Makeup Feed Hold Tank (MFHT) •](https://reader033.vdocuments.us/reader033/viewer/2022060511/5f29ccd17df514739331e6c0/html5/thumbnails/1.jpg)
www.energy.gov/EM 1
CHBWV Project OverviewQuarterly Public Meeting
Daniel CoynePresident and General ManagerCH2M HILL B&W West Valley
February 26, 2014
![Page 2: CHBWV Project Overview Quarterly Public Meeting Feburary... · drums Shipment of Vitrification Melter, Concentrator Feed Make‐up Tank (CFMT) and Makeup Feed Hold Tank (MFHT) •](https://reader033.vdocuments.us/reader033/viewer/2022060511/5f29ccd17df514739331e6c0/html5/thumbnails/2.jpg)
www.energy.gov/EM 2
8 Vertical Storage Casks (VSCs) Completed; 8 more Ordered
8 HLW Over‐packsBeing Fabricated
Main Pad 144 feet by 110 feet by 3-foot-thick
133 tons of reinforcing steel, 1,800 cubic yards of concrete
Approach Apron98 feet by 170 feet by 18-inch thick
110 tons of reinforcing steel, 935 cubic yards of concrete
Recent Accomplishments:
Milestone 1 ‐ HLW Relocation
![Page 3: CHBWV Project Overview Quarterly Public Meeting Feburary... · drums Shipment of Vitrification Melter, Concentrator Feed Make‐up Tank (CFMT) and Makeup Feed Hold Tank (MFHT) •](https://reader033.vdocuments.us/reader033/viewer/2022060511/5f29ccd17df514739331e6c0/html5/thumbnails/3.jpg)
www.energy.gov/EM 3
Milestone 1 ‐ HLW Relocation, cont.
Facility and Site Pathway Evaluations Underway• Roadway between Main Plant Process Building (MPPB) and pad
• Inside MPPB
Indoor Canister Removal Pathway
Haul Path From MPPB
![Page 4: CHBWV Project Overview Quarterly Public Meeting Feburary... · drums Shipment of Vitrification Melter, Concentrator Feed Make‐up Tank (CFMT) and Makeup Feed Hold Tank (MFHT) •](https://reader033.vdocuments.us/reader033/viewer/2022060511/5f29ccd17df514739331e6c0/html5/thumbnails/4.jpg)
www.energy.gov/EM 4
Core Boring in the EDR Testing Load Lowering Device
Scour Pad & Vacuum Decon Microfiber Mop Decon
Milestone 1 ‐ HLW Relocation, cont.
Initiated Modifications for:
Equipment Decontamination Room (EDR)
Chemical Process Cell
Load‐In/Load‐Out Facility
![Page 5: CHBWV Project Overview Quarterly Public Meeting Feburary... · drums Shipment of Vitrification Melter, Concentrator Feed Make‐up Tank (CFMT) and Makeup Feed Hold Tank (MFHT) •](https://reader033.vdocuments.us/reader033/viewer/2022060511/5f29ccd17df514739331e6c0/html5/thumbnails/5.jpg)
www.energy.gov/EM 5
Legacy Low‐Level (LLW) and Mixed LLW (MLLW) Processing and Disposition
• Removing first group of Remote‐Handled (RH) transuranic (TRU) waste drums from the High Level Waste Interim Storage Facility (HLWISF)
• 60 of the 80 drums placed in over‐pack containers to date
• Waste Processing Area (WPA) Phase I processing campaign is 100% complete
• 488 containers processed
Remote TRU Drum Removal From HLWISF
Packaged Waste in On‐Site Storage
![Page 6: CHBWV Project Overview Quarterly Public Meeting Feburary... · drums Shipment of Vitrification Melter, Concentrator Feed Make‐up Tank (CFMT) and Makeup Feed Hold Tank (MFHT) •](https://reader033.vdocuments.us/reader033/viewer/2022060511/5f29ccd17df514739331e6c0/html5/thumbnails/6.jpg)
www.energy.gov/EM 6
Transuranic (TRU) Waste• Completed pre‐decisional report evaluating options to manage RH‐ TRU waste and non‐high level waste drums
Shipment of Vitrification Melter, Concentrator Feed Make‐up Tank (CFMT) and Makeup Feed Hold Tank (MFHT)• Completed grouting operations• Completed technical review and submitted award recommendation to procurement
• DOE‐EMCBC award approved
Nevada National Security Site• Completed Annual Independent Self‐Assessment with no findings
• NNSA Audit corrective action completed
Melter Grouting Operations
Melter Grouting Operations
![Page 7: CHBWV Project Overview Quarterly Public Meeting Feburary... · drums Shipment of Vitrification Melter, Concentrator Feed Make‐up Tank (CFMT) and Makeup Feed Hold Tank (MFHT) •](https://reader033.vdocuments.us/reader033/viewer/2022060511/5f29ccd17df514739331e6c0/html5/thumbnails/7.jpg)
www.energy.gov/EM 7
Legacy Waste shipped contract‐to‐date • Low Level Waste (LLW): 53% complete (70,834 ft3)• Mixed Low Level Waste (MLLW): 100% complete (4,992 ft3)• Industrial: 100% complete (984 ft3)
• Hazardous: 100% complete (163 ft3)
Off‐site Legacy Waste Shipment
![Page 8: CHBWV Project Overview Quarterly Public Meeting Feburary... · drums Shipment of Vitrification Melter, Concentrator Feed Make‐up Tank (CFMT) and Makeup Feed Hold Tank (MFHT) •](https://reader033.vdocuments.us/reader033/viewer/2022060511/5f29ccd17df514739331e6c0/html5/thumbnails/8.jpg)
www.energy.gov/EM 8
Continued deactivation and cleanout of Main Plant Process Building (MPPB) and Vitrification Facility
• Completed deactivation of Upper Warm Aisle
• Completed asbestos abatement of Plant Office Building – 2nd & 3rd floor
• Miscellaneous equipment, materials and debris removed from Vit Cell
Milestone 3 ‐ Facility Disposition
Upper Warm Aisle after Deactivation Vit Cell Cleanup Continues
![Page 9: CHBWV Project Overview Quarterly Public Meeting Feburary... · drums Shipment of Vitrification Melter, Concentrator Feed Make‐up Tank (CFMT) and Makeup Feed Hold Tank (MFHT) •](https://reader033.vdocuments.us/reader033/viewer/2022060511/5f29ccd17df514739331e6c0/html5/thumbnails/9.jpg)
www.energy.gov/EM 9
• Completed waste load‐out of the Expanded Environmental Lab
• Completed backfill of New Cooling Tower & Counting Lab areas
• Initiated demolition of miscellaneous structures
Milestone 4 ‐ Balance of Site Facilities
E‐Lab Footers
Miscellaneous Structures
![Page 10: CHBWV Project Overview Quarterly Public Meeting Feburary... · drums Shipment of Vitrification Melter, Concentrator Feed Make‐up Tank (CFMT) and Makeup Feed Hold Tank (MFHT) •](https://reader033.vdocuments.us/reader033/viewer/2022060511/5f29ccd17df514739331e6c0/html5/thumbnails/10.jpg)
www.energy.gov/EM 10
New Generation Waste Disposition• Industrial Waste Shipped
141,561 ft3 Contract to Date
E‐Lab Demolition and Waste Loadout
Building 01‐14 LLW Shipment to Alaron
E‐Lab Demolition Waste Loadout
![Page 11: CHBWV Project Overview Quarterly Public Meeting Feburary... · drums Shipment of Vitrification Melter, Concentrator Feed Make‐up Tank (CFMT) and Makeup Feed Hold Tank (MFHT) •](https://reader033.vdocuments.us/reader033/viewer/2022060511/5f29ccd17df514739331e6c0/html5/thumbnails/11.jpg)
www.energy.gov/EM 11