Chapter Six

The Basics of Planning

and Project Management

Page 2: Chapter Six The Basics of Planning and Project Management

Copyright © Houghton Mifflin Company. All rights reserved. Chapter Six | 2

Chapter Objectives

• Distinguish among state, effect, and response uncertainty.

• Identify and define three types of planning.• Write good objectives and discuss the role of

objectives in planning.• Describe the four-step management by objectives

(MBO) process and explain how it can foster individual commitment and motivation.

Page 3: Chapter Six The Basics of Planning and Project Management

Copyright © Houghton Mifflin Company. All rights reserved. Chapter Six | 3

Chapter Objectives (cont’d)

• Discuss project planning within the context of the project life cycle and list six roles played by project managers.

• Compare and contrast flow charts and Gantt charts, and discuss the value of PERT networks.

• Explain how break-even points can be calculated.

Page 4: Chapter Six The Basics of Planning and Project Management

Copyright © Houghton Mifflin Company. All rights reserved. Chapter Six | 4

Coping with Uncertainty

• Planning– Coping with uncertainty by formulating courses of

action to achieve specified results

• Three Types of Uncertainty1. State uncertainty: Occurs when the environment, or a

portion of the environment, is considered unstable

2. Effect uncertainty: Occurs when impacts of environmental change are unpredictable

3. Response uncertainty: Arises when the consequences of decisions are unpredictable

Page 5: Chapter Six The Basics of Planning and Project Management

Copyright © Houghton Mifflin Company. All rights reserved. Chapter Six | 5

Figure 6.1: Planning: The Primary Management Function

Page 6: Chapter Six The Basics of Planning and Project Management

Copyright © Houghton Mifflin Company. All rights reserved. Chapter Six | 6

Coping with Uncertainty (cont’d)

• Organizational Responses to Uncertainty– Defenders: Relying on a primary technology and/or a

narrow product line to remain competitive– Prospectors: Seeking first-mover advantage by

aggressively making things happen and not waiting for them to happen

– Analyzers: Following the market leader and imitating what works, avoiding expensive R&D mistakes

– Reactors: Waiting for adversity (e.g., declining sales) to occur before taking corrective action

Page 7: Chapter Six The Basics of Planning and Project Management

Copyright © Houghton Mifflin Company. All rights reserved. Chapter Six | 7

Page 8: Chapter Six The Basics of Planning and Project Management

Copyright © Houghton Mifflin Company. All rights reserved. Chapter Six | 8

Balancing Planned Action and Spontaneity in the Twenty-First Century

• Command-and-Control Model– Top-down tight control of operations through exact

planning which creates organizational inflexibility to deal with unanticipated events and limited success

• Contingency Model– Planned action balanced with creative flexibility to

take advantage of unexpected opportunities and to cope with the need for change

Page 9: Chapter Six The Basics of Planning and Project Management

Copyright © Houghton Mifflin Company. All rights reserved. Chapter Six | 9

The Essentials of Planning

• A Plan:– Is a specific documented intention consisting of an

objective (end) and an action statement (means)– States what, when, and how something is to be done

• Essentials of Sound Planning– Organizational mission– Types of planning– Objectives– Priorities– The planning/control cycle

Page 10: Chapter Six The Basics of Planning and Project Management

Copyright © Houghton Mifflin Company. All rights reserved. Chapter Six | 10

Organizational Mission

• A clear, formally written, and publicized statement that guides the organization by:– Defining the organization for key stakeholders– Creating an inspiring vision of the organization– Outlining how the vision will be accomplished– Establishing key priorities– Stating a common goal and fostering togetherness– Creating a philosophical anchor for the organization– Generating enthusiasm and a “can do” attitude– Empowering organization members

Page 11: Chapter Six The Basics of Planning and Project Management

Copyright © Houghton Mifflin Company. All rights reserved. Chapter Six | 11

Types of Planning

• Strategic planning: Determining how to pursue long-term goals with available resources

• Intermediate planning: Determining subunits’ contribution with allocated resources

• Operational planning: Determining how to accomplish specific tasks with available resources

Page 12: Chapter Six The Basics of Planning and Project Management

Copyright © Houghton Mifflin Company. All rights reserved. Chapter Six | 12

Figure 6.2: Types of Planning

Page 13: Chapter Six The Basics of Planning and Project Management

Copyright © Houghton Mifflin Company. All rights reserved. Chapter Six | 13

Planning Horizon

• The elapsed time between the formulation and the execution of a planned activity– Planning horizon length corresponds to the type of plan

with which it is associated; lengths shorten as the planning process evolves from strategic to intermediate to operational plans.

Page 14: Chapter Six The Basics of Planning and Project Management

Copyright © Houghton Mifflin Company. All rights reserved. Chapter Six | 14

Objectives

• An objective is a commitment to achieve a measurable result within a specified period.

• Writing Good Objectives– Objectives should be expressed in quantitative,

measurable, and concrete terms.• What specific result is to be achieved?• When is the result to be achieved?• How is the result to be measured?• Who will be responsible for achieving the result?

Page 15: Chapter Six The Basics of Planning and Project Management

Copyright © Houghton Mifflin Company. All rights reserved. Chapter Six | 15

Objectives (cont’d)

• The Importance of Objectives (Uses of)– Target: Sets specific goals to achieve– Measuring stick: Gauges how much was achieved– Commitment: Encourages pursuit of the objective– Motivation: Provides a challenge for achievement

• The Means-Ends Chain of Objectives– Achievement of lower-level objectives creates a means

for achieving higher-level objectives.

Page 16: Chapter Six The Basics of Planning and Project Management

Copyright © Houghton Mifflin Company. All rights reserved. Chapter Six | 16

Figure 6.3: A Typical Means-Ends Chain of Objectives

Page 17: Chapter Six The Basics of Planning and Project Management

Copyright © Houghton Mifflin Company. All rights reserved. Chapter Six | 17

Priorities

• Priorities are a ranking of goals, objectives, or activities in order of importance to guide the order and timing of decisions.

• Management looks at its priorities when deciding how to allocate resources.

Page 18: Chapter Six The Basics of Planning and Project Management

Copyright © Houghton Mifflin Company. All rights reserved. Chapter Six | 18

Priorities (cont’d)

• The A-B-C Priority System – A: “Must do” objectives are critical to successful

performance.– B: “Should do” objectives are necessary for improved

performance.– C: “Nice to do” objectives are desirable for improved

performance but not critical to survival or improved performance.

• The 80/20 Principle (Pareto Analysis)– A majority of causes, inputs, or effort tends to produce

a majority of results, outputs, or rewards.

Page 19: Chapter Six The Basics of Planning and Project Management

Copyright © Houghton Mifflin Company. All rights reserved. Chapter Six | 19

The Planning/Control Cycle

• Planning sets in motion activities to accomplish the planned objectives.

• Control functions direct and monitor activities for deviations from plans (i.e., attainment of objectives).

• Planning uses feedback from controls to improve/alter plans and implement corrective actions where necessary.

Page 20: Chapter Six The Basics of Planning and Project Management

Copyright © Houghton Mifflin Company. All rights reserved. Chapter Six | 20

Figure 6.4: The Basic Planning/Control Cycle

Page 21: Chapter Six The Basics of Planning and Project Management

Copyright © Houghton Mifflin Company. All rights reserved. Chapter Six | 21

Management by Objectives and Project Planning

• Management by Objectives (Peter Drucker)– A comprehensive management system based on

measurable, participatively set objectives

• The MBO Cycle– Step 1: Setting objectives– Step 2: Developing action plans– Step 3: Periodic review– Step 4: Performance appraisal

Page 22: Chapter Six The Basics of Planning and Project Management

Copyright © Houghton Mifflin Company. All rights reserved. Chapter Six | 22

Figure 6.5: MBO’s Strengths and Limitations

Page 23: Chapter Six The Basics of Planning and Project Management

Copyright © Houghton Mifflin Company. All rights reserved. Chapter Six | 23

Project Planning and Management

• Project– A temporary endeavor to achieve a particular aim

• The Project Life Cycle– Conceptualization: Setting project goals and objectives– Planning: Organizing facilities and equipment,

personnel and task assignments, and scheduling– Execution: Beginning actual work on the project – Termination: Turning the project over to the end user

and phasing out project resources

Page 24: Chapter Six The Basics of Planning and Project Management

Copyright © Houghton Mifflin Company. All rights reserved. Chapter Six | 24

Figure 6.6: The Project Life Cycle and Project Planning Activities

Page 25: Chapter Six The Basics of Planning and Project Management

Copyright © Houghton Mifflin Company. All rights reserved. Chapter Six | 25

Page 26: Chapter Six The Basics of Planning and Project Management

Copyright © Houghton Mifflin Company. All rights reserved. Chapter Six | 26

Project Management Software

• Important attributes: flexibility and transparency– Identify and schedule need-to-do activities.– Dynamically shift priorities and schedules.– Provide critical path analysis.– Provide flexibility for plan modifications.– Set priority levels.– Manage all resources flexibly.– Merge plans.– Issue manager alerts for project slippage.– Automatically record time to map against project.– Identify time spent on activities.

Page 27: Chapter Six The Basics of Planning and Project Management

Copyright © Houghton Mifflin Company. All rights reserved. Chapter Six | 27

Project Management Guidelines

• Projects are schedule-driven and results-oriented.• The big picture and the little details are of equal

importance.• Project planning is a necessity, not a luxury.• Project managers know the motivational power of

a deadline.

Page 28: Chapter Six The Basics of Planning and Project Management

Copyright © Houghton Mifflin Company. All rights reserved. Chapter Six | 28

Graphic Planning/Scheduling/Control Tools

• Flow Charts– Arrange events in the order of their actual or desired

occurrence (flow)– Eliminate wasted steps and activities (work

simplification)– Are useful for identifying task components and in TQM– Potential problems:

• They do not indicate the time dimension of tasks.• They are not practical for complex operations where several

activities occur at once.

Page 29: Chapter Six The Basics of Planning and Project Management

Copyright © Houghton Mifflin Company. All rights reserved. Chapter Six | 29

Figure 6.7: A Sample Flow Chart

Page 30: Chapter Six The Basics of Planning and Project Management

Copyright © Houghton Mifflin Company. All rights reserved. Chapter Six | 30

Graphic Planning/Scheduling/Control Tools (cont’d)

• Gantt Charts– A graphic scheduling technique historically used in

production operations• Useful for scheduling large projects where time for each

activity can be specified and progress assessed• Potential problem: Overly complex endeavors are too

cumbersome for Gantt charts.

Page 31: Chapter Six The Basics of Planning and Project Management

Copyright © Houghton Mifflin Company. All rights reserved. Chapter Six | 31

Figure 6.8: A Sample Gantt Chart

Page 32: Chapter Six The Basics of Planning and Project Management

Copyright © Houghton Mifflin Company. All rights reserved. Chapter Six | 32

Graphic Planning/Scheduling/Control Tools (cont’d)

• Program Evaluation and Review Technique (PERT) Networks– Developed in 1958 for use in the development of

the U.S. Navy’s Polaris submarine-launched missile project

– Graphic sequencing and scheduling tool for large, complex, and nonroutine projects

Page 33: Chapter Six The Basics of Planning and Project Management

Copyright © Houghton Mifflin Company. All rights reserved. Chapter Six | 33

PERT Networks

• PERT Terminology– Event: Denotes a performance milestone– Activity: Work (jobs) in process– Time: Estimated weighted times for completion of an

activity—optimistic (most likely) and pessimistic– Critical path: The most time consuming (longest) chain

of required activities and events in a PERT network that must be completed on time or else the entire project will be delayed

Page 34: Chapter Six The Basics of Planning and Project Management

Copyright © Houghton Mifflin Company. All rights reserved. Chapter Six | 34

PERT Networks (cont’d)

• Formula for Calculating Estimated PERT Times

Te = Time estimate (average)

To = Time estimate (optimistic)

Tm = Time estimate (most likely)

Tp = Time estimate (pessimistic)

6

4 pmoe

TTTT

Page 35: Chapter Six The Basics of Planning and Project Management

Copyright © Houghton Mifflin Company. All rights reserved. Chapter Six | 35

PERT Networks (cont’d)

• Positive and Negative Aspects of PERT– Excellent scheduling tool for large, nonroutine projects– Requires envisioning projects in their entirety– Provides a tool for predicting resource needs, potential

problem areas, and the effect of delays– Inappropriate for repetitive assembly-line operations– Only as good as its underlying assumptions about

event completion times– Can be too time-consuming if not computerized

Page 36: Chapter Six The Basics of Planning and Project Management

Copyright © Houghton Mifflin Company. All rights reserved. Chapter Six | 36

Figure 6.9: A Sample PERT Network

Page 37: Chapter Six The Basics of Planning and Project Management

Copyright © Houghton Mifflin Company. All rights reserved. Chapter Six | 37

Break-Even Analysis

• Break-Even Point– The level of sales at which there is no loss or profit– The point at which the total of fixed and variable costs

is equal to total sales revenues

• Fixed Versus Variable Costs– Fixed costs: Contractual costs that must be paid

regardless of output or sales– Variable costs: Costs that vary directly with production

and sales

Page 38: Chapter Six The Basics of Planning and Project Management

Copyright © Houghton Mifflin Company. All rights reserved. Chapter Six | 38

Break-Even Analysis (cont’d)

• The Algebraic Method

• The difference between unit selling price P and unit variable costs VC is the contribution margin that can be applied to recovering fixed costs.

VCP

FCBEP

)unitsin(

FC = total fixed costs

P = selling price (per unit)

VC = variable costs (per unit)

BEP = break-even point (in units)

Page 39: Chapter Six The Basics of Planning and Project Management

Copyright © Houghton Mifflin Company. All rights reserved. Chapter Six | 39

Break-Even Analysis (cont’d)

• Price Planning– Determining the impact of changes in unit selling price

on the break-even point in units• Rising prices decrease the break-even point; lower prices

increase the break-even point.

000,1047

000,30)unitsin(

BEP

000,1546

000,30)unitsin(

BEP

Page 40: Chapter Six The Basics of Planning and Project Management

Copyright © Houghton Mifflin Company. All rights reserved. Chapter Six | 40

Break-Even Analysis (cont’d)

• Profit Planning– Determining the required level of output to achieve a

profit objective

VCP

FCBEP

profitdesired)unitsin(

000,2047

000,30000,30)unitsin(

BEP

Page 41: Chapter Six The Basics of Planning and Project Management

Copyright © Houghton Mifflin Company. All rights reserved. Chapter Six | 41

Figure 6.10: Graphic Break-Even Analysis

Page 42: Chapter Six The Basics of Planning and Project Management

Copyright © Houghton Mifflin Company. All rights reserved. Chapter Six | 42

Break-Even Analysis: Strengths and Limitations

• Planners are forced to interrelate cost, volume, and profit in a realistic way.

• Planners are able to ask what-if questions concerning the impact of price, costs, and profit objective changes.

• A neat separation of fixed and variable costs is difficult to achieve.

• Complex factors in supply and demand interfere with the linear projections (point estimates) of the analysis.

Page 43: Chapter Six The Basics of Planning and Project Management

Copyright © Houghton Mifflin Company. All rights reserved. Chapter Six | 43

Summary

• Planning is the primary management function.

• A properly written plan tells what, when, and how something is to be accomplished.

• Objectives are the single most important feature of the planning process.

• Management by objectives (MBO) is based on measurable and participatively set goals.

Page 44: Chapter Six The Basics of Planning and Project Management

Copyright © Houghton Mifflin Company. All rights reserved. Chapter Six | 44

Summary (cont’d)

• Project planning occurs throughout the project life cycle.

• Flow charts, Gantt charts, and PERT networks are graphical tolls for planning, scheduling, and controlling operations.

• Break-even analysis gauges the impact of price changes and profit objectives on sales volume.

Page 45: Chapter Six The Basics of Planning and Project Management

Copyright © Houghton Mifflin Company. All rights reserved. Chapter Six | 45

Terms to Understand• Planning• State uncertainty• Effect uncertainty• Response uncertainty• Plan• Strategic planning• Intermediate planning• Operational planning• Planning horizon• Objective• Priorities• 80/20 principle• Management by objectives

(MBO)

• Project • Gantt chart• Program Evaluation and

Review Technique (PERT)• PERT event• PERT activity• PERT times• Critical path• Break-even analysis• Fixed costs• Variable costs• Contribution margin