Work Instruction Functional Area: Project Systems Change Project Purpose Use this procedure to change an existing project. Trigger Perform this procedure when an approved Project Change Request Form is received or as changes are required. Prerequisites Approved Project Change Request Form Authorization from Capital Finance or Debt Management (Project Change Request Form should be completed for construction projects at a later date.) Menu Path Use the following menu path to begin this transaction: Select Accounting Project System Project Project Builder to go to theProject Builder screen. Transaction Code CJ20N Business Process Information The project structure consists of the Project Definition and WBS Elements arranged in a hierarchical manner. The Project Definition as well as the WBS Elements has master data associated with them. Two types of projects will be created: A construction project contains all the required accounting information pertaining to the planning, design, and construction of a building. Costs will accumulate for a project and enable the reporting and capitalization of the building. A debt project contains all the required accounting information pertaining to the issuance of debt and capital leases. There are two levels of WBS elements under the Project Definition: WBS Element Level 1 will consist of the project number. WBS Element Level 2 will consist of the type of expense (10 = Construction, 20 = Finance Costs, 30 = Equipment, 40 = Non-Capital

Upload: others

Post on 27-Feb-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Change Project - uc.edu · Web viewAuthorization from Capital Finance or Debt Management (Project Change Request Form should be completed for construction projects at a later date.)

Work InstructionFunctional Area: Project Systems  Change Project

Purpose

Use this procedure to change an existing project.

Trigger

Perform this procedure when an approved Project Change Request Form is received or as changes are required.

Prerequisites

Approved Project Change Request Form Authorization from Capital Finance or Debt Management (Project Change Request Form

should be completed for construction projects at a later date.)

Menu Path

Use the following menu path to begin this transaction:

Select Accounting  Project System  Project  Project Builder to go to theProject Builder screen.

Transaction Code

CJ20N

Business Process Information

The project structure consists of the Project Definition and WBS Elements arranged in a hierarchical manner. The Project Definition as well as the WBS Elements has master data associated with them.

Two types of projects will be created:

A construction project contains all the required accounting information pertaining to the planning, design, and construction of a building. Costs will accumulate for a project and enable the reporting and capitalization of the building.

A debt project contains all the required accounting information pertaining to the issuance of debt and capital leases.

There are two levels of WBS elements under the Project Definition:

WBS Element Level 1 will consist of the project number. WBS Element Level 2 will consist of the type of expense (10 = Construction, 20 = Finance

Costs, 30 = Equipment, 40 = Non-Capital Expenses). Additionally, WBS Element Level 2 will contain revenue postings (70 = Revenue). These categories may be expanded in the future.

Construction projects will post transactions only at the Level 2 WBS Elements. Debt projects will post transactions on both Level 1 and Level 2 WBS Elements.

Helpful Hints

The R/O/C column in the field description tables below defines whether the field is required

Page 2: Change Project - uc.edu · Web viewAuthorization from Capital Finance or Debt Management (Project Change Request Form should be completed for construction projects at a later date.)

Work InstructionFunctional Area: Project Systems  Change Project

(R), optional (O), or conditional (C). On certain screens you may have to scroll to view some data entry fields.

Page 3: Change Project - uc.edu · Web viewAuthorization from Capital Finance or Debt Management (Project Change Request Form should be completed for construction projects at a later date.)

Work InstructionFunctional Area: Project Systems  Change Project

Procedure

1. Start the transaction using the menu path or transaction code.

Project Builder

2. Select Project Open.

9/11/2017Ver:

25_PS_CJ20N_ChangeProject_0_ProjectSystems_06.udc© University of Cincinnati  3/21

Page 4: Change Project - uc.edu · Web viewAuthorization from Capital Finance or Debt Management (Project Change Request Form should be completed for construction projects at a later date.)

Work InstructionFunctional Area: Project Systems  Change Project

Open Project

3. As required, complete/review the following fields:

Field R/O/C Description

Project Definition Conditional Framework of data that is binding to the entire project

Example:01122

    This is the Project Definition of the WBS Element for which you want to change. You need to enter a project definition or a WBS Element (not both).

WBS Element Conditional Work Breakdown Structure Element

Example:01122Z

    This is the WBS element for which you want to change. You need to enter a project definition or a WBS element (not both).

4.Click  .

If you are adding a WBS Element Level 1 or Level 2, refer to the Create Project (CJ20N) work instruction and begin with Step 3.

5. Perform one of the following:If You Searched By Go ToProjection Definition Step 6

9/11/2017Ver:

25_PS_CJ20N_ChangeProject_0_ProjectSystems_06.udc© University of Cincinnati  4/21

Page 5: Change Project - uc.edu · Web viewAuthorization from Capital Finance or Debt Management (Project Change Request Form should be completed for construction projects at a later date.)

Work InstructionFunctional Area: Project Systems  Change Project

WBS Element Step 13

Project Builder: Project XXXX

6. Perform one of the following:If You Want To Then Go To

Change basic dataClick the  tab.

Step 7

Add or change textClick the  tab.

Step 9

Complete the customized fields at the WBS element level Click the   tab.

Step 11

Change WBS Element Overview information

Click   to the right of the Overview(s): field.

Step 13

Release the project Click   to the right of the Overview(s): field.

Step 13

9/11/2017Ver:

25_PS_CJ20N_ChangeProject_0_ProjectSystems_06.udc© University of Cincinnati  5/21

Page 6: Change Project - uc.edu · Web viewAuthorization from Capital Finance or Debt Management (Project Change Request Form should be completed for construction projects at a later date.)

Work InstructionFunctional Area: Project Systems  Change Project

Save changes and exit this transaction Click   . Step 29

7. As required, complete/review the following fields:

Field R/O/C Description

Unlabeled field (to the right of the Project Def. field)

Optional Description or name of the Project Definition

Example:Central Utility Plant – Addition

    Enter text description (name) for the project.

Person Respons. Optional Individual responsible for the project

Example:10000016

    This is the primary person responsible for the project. Personnel can be selected from a drop down list.

Applicant no. Optional 8 character identifier that defines the number of the accountant assigned to the project

Example:10000003

    This is the Accountant assigned to the project. Personnel can be selected from a list of employees from a drop-down list.

Business area Optional Business Area is the campus to which the cost center is assigned

Example:C          Clermont Campus

8. Return to Step 6.

9/11/2017Ver:

25_PS_CJ20N_ChangeProject_0_ProjectSystems_06.udc© University of Cincinnati  6/21

Page 7: Change Project - uc.edu · Web viewAuthorization from Capital Finance or Debt Management (Project Change Request Form should be completed for construction projects at a later date.)

Work InstructionFunctional Area: Project Systems  Change Project

Project Builder: Project XXXX (Long txt tab)

9. As required, enter/change long text description, notes, paste emails, Word documents as support documentation for the project.

10. Return to Step 6.

9/11/2017Ver:

25_PS_CJ20N_ChangeProject_0_ProjectSystems_06.udc© University of Cincinnati  7/21

Page 8: Change Project - uc.edu · Web viewAuthorization from Capital Finance or Debt Management (Project Change Request Form should be completed for construction projects at a later date.)

Work InstructionFunctional Area: Project Systems  Change Project

Project Builder: Project XXXX (Cust. enhancement tab)

11. As required, complete/review the following fields:

Field R/O/C Description

Unlabeled field (below the Date Description field)

Optional Specifies the type of key project date to be tracked.

Example:Board of Trustees Approval

    Select from the dropdown list the description of the date to be tracked.

9/11/2017Ver:

25_PS_CJ20N_ChangeProject_0_ProjectSystems_06.udc© University of Cincinnati  8/21

Page 9: Change Project - uc.edu · Web viewAuthorization from Capital Finance or Debt Management (Project Change Request Form should be completed for construction projects at a later date.)

Work InstructionFunctional Area: Project Systems  Change Project

Field R/O/C Description

Unlabeled field (below the Date field)

Optional The key project date to be tracked.

Example:10/19/2004

    Enter the date.

Unlabeled field (below the Amount field)

Optional The amount to be tracked with the key project date.

Example:10,000,000.00

    If necessary, enter the amount specific to the date to be track.

12. Return to Step 6.

9/11/2017Ver:

25_PS_CJ20N_ChangeProject_0_ProjectSystems_06.udc© University of Cincinnati  9/21

Page 10: Change Project - uc.edu · Web viewAuthorization from Capital Finance or Debt Management (Project Change Request Form should be completed for construction projects at a later date.)

Work InstructionFunctional Area: Project Systems  Change Project

Project Builder: Project XXXX (Basic data tab)

13. Perform one of the following:If You Want To Then Go To

Change basic dataClick the   tab.

Step 14

Change organization dataClick the   tab.

Step 16

Change responsibility informationClick the  tab.

Step 18

Change overview dataClick the  tab

Step 20

Change the customized fields at the WBS element level

Click on the desired element in the Project Structure: Description area. Step 22

Release the project --- Step 1Save changes and exit this transaction Click   . Step 29

9/11/2017Ver:

25_PS_CJ20N_ChangeProject_0_ProjectSystems_06.udc© University of Cincinnati  10/21

Page 11: Change Project - uc.edu · Web viewAuthorization from Capital Finance or Debt Management (Project Change Request Form should be completed for construction projects at a later date.)

Work InstructionFunctional Area: Project Systems  Change Project

Project Builder: Project XXXX (Basic data tab)

14. As required, change/review the following fields:

Use the scroll bars to view all fields.

15. Return to Step 13.

9/11/2017Ver:

25_PS_CJ20N_ChangeProject_0_ProjectSystems_06.udc© University of Cincinnati  11/21

Page 12: Change Project - uc.edu · Web viewAuthorization from Capital Finance or Debt Management (Project Change Request Form should be completed for construction projects at a later date.)

Work InstructionFunctional Area: Project Systems  Change Project

Project Builder: Project XXXX (Organization tab)

16. As required, complete/review the following fields:

Field R/O/C Description

Bu… (Business area) Optional Business Area is the campus to which the cost center is assigned

Example:C          Clermont Campus

17. Return to Step 13.

9/11/2017Ver:

25_PS_CJ20N_ChangeProject_0_ProjectSystems_06.udc© University of Cincinnati  12/21

Page 13: Change Project - uc.edu · Web viewAuthorization from Capital Finance or Debt Management (Project Change Request Form should be completed for construction projects at a later date.)

Work InstructionFunctional Area: Project Systems  Change Project

Project Builder: Project XXXX (Responsibilities tab)

18. As required, complete/review the following fields:

Field R/O/C Description

Person… (Person Respons.)

Optional Individual responsible for the project

Example:10000016

    This field defaults from the project definition level. However, this information can be changed at each WBS element level.

9/11/2017Ver:

25_PS_CJ20N_ChangeProject_0_ProjectSystems_06.udc© University of Cincinnati  13/21

Page 14: Change Project - uc.edu · Web viewAuthorization from Capital Finance or Debt Management (Project Change Request Form should be completed for construction projects at a later date.)

Work InstructionFunctional Area: Project Systems  Change Project

Field R/O/C Description

Applican… (Applicant no.)

Optional 8 character identifier that defines the number of the accountant assigned to the project

Example:10000003

    This field defaults from the project definition level. However, this information can be changed at each WBS element level.

Resp. cost… (Resp. cost cntr)

Optional Cost center which is responsible for the order or project; The order or project is therefore organizationally assigned to the cost center

Example:1999999999

    Cost centers can be selected from the drop-down menu.

Req.cost c… (Req. cost center)

Optional Costs center which requested the WBS element

Example:1999999999

    Cost centers can be selected from the drop-down menu.

19. Return to Step 13.

9/11/2017Ver:

25_PS_CJ20N_ChangeProject_0_ProjectSystems_06.udc© University of Cincinnati  14/21

Page 15: Change Project - uc.edu · Web viewAuthorization from Capital Finance or Debt Management (Project Change Request Form should be completed for construction projects at a later date.)

Work InstructionFunctional Area: Project Systems  Change Project

Project Builder: Project XXXX (Over. tab)

20. As required, change/review the necessary data.

The only fields available for change are the fields that appear white. All other fields are grayed out and do not allow entry.

21. Return to Step 13.

9/11/2017Ver:

25_PS_CJ20N_ChangeProject_0_ProjectSystems_06.udc© University of Cincinnati  15/21

Page 16: Change Project - uc.edu · Web viewAuthorization from Capital Finance or Debt Management (Project Change Request Form should be completed for construction projects at a later date.)

Work InstructionFunctional Area: Project Systems  Change Project

Project Builder: Project XXXX

22. Click  to move between tabs or click   for a drop down list of available tabs to go to desired tab (Cust. enhancem…).

9/11/2017Ver:

25_PS_CJ20N_ChangeProject_0_ProjectSystems_06.udc© University of Cincinnati  16/21

Page 17: Change Project - uc.edu · Web viewAuthorization from Capital Finance or Debt Management (Project Change Request Form should be completed for construction projects at a later date.)

Work InstructionFunctional Area: Project Systems  Change Project

Project Builder: Project XXXX (Cust. enhancem…)

23. As required, change/review the following fields:

You must use the scroll bars to see all fields.

24.Click  .

25. Return to Step 13.

9/11/2017Ver:

25_PS_CJ20N_ChangeProject_0_ProjectSystems_06.udc© University of Cincinnati  17/21

Page 18: Change Project - uc.edu · Web viewAuthorization from Capital Finance or Debt Management (Project Change Request Form should be completed for construction projects at a later date.)

Work InstructionFunctional Area: Project Systems  Change Project

Project Builder: Project XXXX (Basic Data)

26.Click  to the left of the WBS element(s) for which you want to release.

The next step will change the system status for the WBS elements to released status. Release the project only when transactions are ready to be posted to the project. Do not delete after the project is released. Typically, transactions are posted only after the Program Statement, budget, and funding sources are approved.

27. Select Edit Status Release.

9/11/2017Ver:

25_PS_CJ20N_ChangeProject_0_ProjectSystems_06.udc© University of Cincinnati  18/21

Page 19: Change Project - uc.edu · Web viewAuthorization from Capital Finance or Debt Management (Project Change Request Form should be completed for construction projects at a later date.)

Work InstructionFunctional Area: Project Systems  Change Project

Project Builder: Project XXXX (Over. tab) (2)

28. Return to Step 13.

The system displays the message, Status was set.”

9/11/2017Ver:

25_PS_CJ20N_ChangeProject_0_ProjectSystems_06.udc© University of Cincinnati  19/21

Page 20: Change Project - uc.edu · Web viewAuthorization from Capital Finance or Debt Management (Project Change Request Form should be completed for construction projects at a later date.)

Work InstructionFunctional Area: Project Systems  Change Project

Project Builder (3)

29.Click  until you return to the SAP Easy Access screen.

The system displays the message, “Project XXXX is being changed.”

30. You have completed this transaction.

9/11/2017Ver:

25_PS_CJ20N_ChangeProject_0_ProjectSystems_06.udc© University of Cincinnati  20/21

Page 21: Change Project - uc.edu · Web viewAuthorization from Capital Finance or Debt Management (Project Change Request Form should be completed for construction projects at a later date.)

Work InstructionFunctional Area: Project Systems  Change Project

Result

You have changed and released an existing project with Level 1 and Level 2 WBS Elements.