Work InstructionFunctional Area: Project Systems Change Project
Purpose
Use this procedure to change an existing project.
Trigger
Perform this procedure when an approved Project Change Request Form is received or as changes are required.
Prerequisites
Approved Project Change Request Form Authorization from Capital Finance or Debt Management (Project Change Request Form
should be completed for construction projects at a later date.)
Menu Path
Use the following menu path to begin this transaction:
Select Accounting Project System Project Project Builder to go to theProject Builder screen.
Transaction Code
CJ20N
Business Process Information
The project structure consists of the Project Definition and WBS Elements arranged in a hierarchical manner. The Project Definition as well as the WBS Elements has master data associated with them.
Two types of projects will be created:
A construction project contains all the required accounting information pertaining to the planning, design, and construction of a building. Costs will accumulate for a project and enable the reporting and capitalization of the building.
A debt project contains all the required accounting information pertaining to the issuance of debt and capital leases.
There are two levels of WBS elements under the Project Definition:
WBS Element Level 1 will consist of the project number. WBS Element Level 2 will consist of the type of expense (10 = Construction, 20 = Finance
Costs, 30 = Equipment, 40 = Non-Capital Expenses). Additionally, WBS Element Level 2 will contain revenue postings (70 = Revenue). These categories may be expanded in the future.
Construction projects will post transactions only at the Level 2 WBS Elements. Debt projects will post transactions on both Level 1 and Level 2 WBS Elements.
Helpful Hints
The R/O/C column in the field description tables below defines whether the field is required
Work InstructionFunctional Area: Project Systems Change Project
(R), optional (O), or conditional (C). On certain screens you may have to scroll to view some data entry fields.
Work InstructionFunctional Area: Project Systems Change Project
Procedure
1. Start the transaction using the menu path or transaction code.
Project Builder
2. Select Project Open.
9/11/2017Ver:
25_PS_CJ20N_ChangeProject_0_ProjectSystems_06.udc© University of Cincinnati 3/21
Work InstructionFunctional Area: Project Systems Change Project
Open Project
3. As required, complete/review the following fields:
Field R/O/C Description
Project Definition Conditional Framework of data that is binding to the entire project
Example:01122
This is the Project Definition of the WBS Element for which you want to change. You need to enter a project definition or a WBS Element (not both).
WBS Element Conditional Work Breakdown Structure Element
Example:01122Z
This is the WBS element for which you want to change. You need to enter a project definition or a WBS element (not both).
4.Click .
If you are adding a WBS Element Level 1 or Level 2, refer to the Create Project (CJ20N) work instruction and begin with Step 3.
5. Perform one of the following:If You Searched By Go ToProjection Definition Step 6
9/11/2017Ver:
25_PS_CJ20N_ChangeProject_0_ProjectSystems_06.udc© University of Cincinnati 4/21
Work InstructionFunctional Area: Project Systems Change Project
WBS Element Step 13
Project Builder: Project XXXX
6. Perform one of the following:If You Want To Then Go To
Change basic dataClick the tab.
Step 7
Add or change textClick the tab.
Step 9
Complete the customized fields at the WBS element level Click the tab.
Step 11
Change WBS Element Overview information
Click to the right of the Overview(s): field.
Step 13
Release the project Click to the right of the Overview(s): field.
Step 13
9/11/2017Ver:
25_PS_CJ20N_ChangeProject_0_ProjectSystems_06.udc© University of Cincinnati 5/21
Work InstructionFunctional Area: Project Systems Change Project
Save changes and exit this transaction Click . Step 29
7. As required, complete/review the following fields:
Field R/O/C Description
Unlabeled field (to the right of the Project Def. field)
Optional Description or name of the Project Definition
Example:Central Utility Plant – Addition
Enter text description (name) for the project.
Person Respons. Optional Individual responsible for the project
Example:10000016
This is the primary person responsible for the project. Personnel can be selected from a drop down list.
Applicant no. Optional 8 character identifier that defines the number of the accountant assigned to the project
Example:10000003
This is the Accountant assigned to the project. Personnel can be selected from a list of employees from a drop-down list.
Business area Optional Business Area is the campus to which the cost center is assigned
Example:C Clermont Campus
8. Return to Step 6.
9/11/2017Ver:
25_PS_CJ20N_ChangeProject_0_ProjectSystems_06.udc© University of Cincinnati 6/21
Work InstructionFunctional Area: Project Systems Change Project
Project Builder: Project XXXX (Long txt tab)
9. As required, enter/change long text description, notes, paste emails, Word documents as support documentation for the project.
10. Return to Step 6.
9/11/2017Ver:
25_PS_CJ20N_ChangeProject_0_ProjectSystems_06.udc© University of Cincinnati 7/21
Work InstructionFunctional Area: Project Systems Change Project
Project Builder: Project XXXX (Cust. enhancement tab)
11. As required, complete/review the following fields:
Field R/O/C Description
Unlabeled field (below the Date Description field)
Optional Specifies the type of key project date to be tracked.
Example:Board of Trustees Approval
Select from the dropdown list the description of the date to be tracked.
9/11/2017Ver:
25_PS_CJ20N_ChangeProject_0_ProjectSystems_06.udc© University of Cincinnati 8/21
Work InstructionFunctional Area: Project Systems Change Project
Field R/O/C Description
Unlabeled field (below the Date field)
Optional The key project date to be tracked.
Example:10/19/2004
Enter the date.
Unlabeled field (below the Amount field)
Optional The amount to be tracked with the key project date.
Example:10,000,000.00
If necessary, enter the amount specific to the date to be track.
12. Return to Step 6.
9/11/2017Ver:
25_PS_CJ20N_ChangeProject_0_ProjectSystems_06.udc© University of Cincinnati 9/21
Work InstructionFunctional Area: Project Systems Change Project
Project Builder: Project XXXX (Basic data tab)
13. Perform one of the following:If You Want To Then Go To
Change basic dataClick the tab.
Step 14
Change organization dataClick the tab.
Step 16
Change responsibility informationClick the tab.
Step 18
Change overview dataClick the tab
Step 20
Change the customized fields at the WBS element level
Click on the desired element in the Project Structure: Description area. Step 22
Release the project --- Step 1Save changes and exit this transaction Click . Step 29
9/11/2017Ver:
25_PS_CJ20N_ChangeProject_0_ProjectSystems_06.udc© University of Cincinnati 10/21
Work InstructionFunctional Area: Project Systems Change Project
Project Builder: Project XXXX (Basic data tab)
14. As required, change/review the following fields:
Use the scroll bars to view all fields.
15. Return to Step 13.
9/11/2017Ver:
25_PS_CJ20N_ChangeProject_0_ProjectSystems_06.udc© University of Cincinnati 11/21
Work InstructionFunctional Area: Project Systems Change Project
Project Builder: Project XXXX (Organization tab)
16. As required, complete/review the following fields:
Field R/O/C Description
Bu… (Business area) Optional Business Area is the campus to which the cost center is assigned
Example:C Clermont Campus
17. Return to Step 13.
9/11/2017Ver:
25_PS_CJ20N_ChangeProject_0_ProjectSystems_06.udc© University of Cincinnati 12/21
Work InstructionFunctional Area: Project Systems Change Project
Project Builder: Project XXXX (Responsibilities tab)
18. As required, complete/review the following fields:
Field R/O/C Description
Person… (Person Respons.)
Optional Individual responsible for the project
Example:10000016
This field defaults from the project definition level. However, this information can be changed at each WBS element level.
9/11/2017Ver:
25_PS_CJ20N_ChangeProject_0_ProjectSystems_06.udc© University of Cincinnati 13/21
Work InstructionFunctional Area: Project Systems Change Project
Field R/O/C Description
Applican… (Applicant no.)
Optional 8 character identifier that defines the number of the accountant assigned to the project
Example:10000003
This field defaults from the project definition level. However, this information can be changed at each WBS element level.
Resp. cost… (Resp. cost cntr)
Optional Cost center which is responsible for the order or project; The order or project is therefore organizationally assigned to the cost center
Example:1999999999
Cost centers can be selected from the drop-down menu.
Req.cost c… (Req. cost center)
Optional Costs center which requested the WBS element
Example:1999999999
Cost centers can be selected from the drop-down menu.
19. Return to Step 13.
9/11/2017Ver:
25_PS_CJ20N_ChangeProject_0_ProjectSystems_06.udc© University of Cincinnati 14/21
Work InstructionFunctional Area: Project Systems Change Project
Project Builder: Project XXXX (Over. tab)
20. As required, change/review the necessary data.
The only fields available for change are the fields that appear white. All other fields are grayed out and do not allow entry.
21. Return to Step 13.
9/11/2017Ver:
25_PS_CJ20N_ChangeProject_0_ProjectSystems_06.udc© University of Cincinnati 15/21
Work InstructionFunctional Area: Project Systems Change Project
Project Builder: Project XXXX
22. Click to move between tabs or click for a drop down list of available tabs to go to desired tab (Cust. enhancem…).
9/11/2017Ver:
25_PS_CJ20N_ChangeProject_0_ProjectSystems_06.udc© University of Cincinnati 16/21
Work InstructionFunctional Area: Project Systems Change Project
Project Builder: Project XXXX (Cust. enhancem…)
23. As required, change/review the following fields:
You must use the scroll bars to see all fields.
24.Click .
25. Return to Step 13.
9/11/2017Ver:
25_PS_CJ20N_ChangeProject_0_ProjectSystems_06.udc© University of Cincinnati 17/21
Work InstructionFunctional Area: Project Systems Change Project
Project Builder: Project XXXX (Basic Data)
26.Click to the left of the WBS element(s) for which you want to release.
The next step will change the system status for the WBS elements to released status. Release the project only when transactions are ready to be posted to the project. Do not delete after the project is released. Typically, transactions are posted only after the Program Statement, budget, and funding sources are approved.
27. Select Edit Status Release.
9/11/2017Ver:
25_PS_CJ20N_ChangeProject_0_ProjectSystems_06.udc© University of Cincinnati 18/21
Work InstructionFunctional Area: Project Systems Change Project
Project Builder: Project XXXX (Over. tab) (2)
28. Return to Step 13.
The system displays the message, Status was set.”
9/11/2017Ver:
25_PS_CJ20N_ChangeProject_0_ProjectSystems_06.udc© University of Cincinnati 19/21
Work InstructionFunctional Area: Project Systems Change Project
Project Builder (3)
29.Click until you return to the SAP Easy Access screen.
The system displays the message, “Project XXXX is being changed.”
30. You have completed this transaction.
9/11/2017Ver:
25_PS_CJ20N_ChangeProject_0_ProjectSystems_06.udc© University of Cincinnati 20/21
Work InstructionFunctional Area: Project Systems Change Project
Result
You have changed and released an existing project with Level 1 and Level 2 WBS Elements.