challenges during design and construction of an underground chip factory (waferfab)
TRANSCRIPT
1
WTC 2013, Design and Construction of an Underground Chip Factory (Waferfab)
Challenges during Design and Construction of an Underground Chip Factory (Waferfab)
Christoph Rüegg and Helmut Wannenmacher, Amberg Engineering AG
Christian Schönlechner, Jäger Bau GmbH
2
WTC 2013, Design and Construction of an Underground Chip Factory (Waferfab)
Topic
Overview of waferfab
The project idea; from implementation to construction
Design challenges of an underground chip factory
Challenges during construction
Conclusion
3
WTC 2013, Design and Construction of an Underground Chip Factory (Waferfab)
OverviewWhy Underground?
Sensitive industrial process for optoelectronic semiconductor chip production (strict vibration and temperature control)
Best economic solution:Central utility building (CUB) with two shallow caverns for optoelectronic semiconductor chip production
->favorable foundation / constant climate conditions for chip production
PRODUCTION &
LITHO CAVERN
EVACUATION &VENTILATION TUNNEL
ACCESS TUNNEL
MAINTENANCE TUNNEL
CUB
4
WTC 2013, Design and construction of an underground chip factory (waferfab)
Overview
View from the access tunnel to the main production cavern with the perpendicularly oriented litho cavern on the left hand side
5
WTC 2013, Design and Construction of an Underground Chip Factory (Waferfab)
The Project Idea - from Implementation to Construction
The project idea was part of the global engineering strategy of Amberg Engineering Ltd. focusing on solutions for underground production and storage facilities.
Presented in spring 2007 to the client, epc
Economical / technical feasibility studies and detailed study in summer 2007
Decision for an underground solution was made in October 2007 (in total, 5 months from project idea to decision)
Another 8 months for approval design, final project and tender documents
->In total, 13 months from project idea to construction start
6
WTC 2013, Design and Construction of an Underground Chip Factory (Waferfab)
Design Challenges for an Underground Chip Factory
Integrative approach of all design parties under •Operational aspects•Constructional aspects•Environmental and safety aspects
Most important challenge:Reconsile contrary aspects of all design parties and work out a cost-effective production facility fab
7
WTC 2013, Design and Construction of an Underground Chip Factory (Waferfab)
Design Challenges for an Underground Chip FactoryExample: General Layout
8
WTC 2013, Design and Construction of an Underground Chip Factory (Waferfab)
Design Challenges for an Underground Chip FactoryExample: Layout of Production Cavern
Roof constructionShotcrete lining
Wafertable
Maintenance / Supply air
Supply / Disposal
Clean room
Access tunnel
Maintenance tunnel
9
WTC 2013, Design and Construction of an Underground Chip Factory (Waferfab)
Design Challenges for an Underground Chip FactoryExample: Dimensions of Access and Maintenance Tunnel
access tunnel
maintenance tunnel
10
WTC 2013, Design and Construction of an Underground Chip Factory (Waferfab)
Design Challenges for an Underground Chip FactoryExample: Escape Path and Ventilation System
S UBFAB
CLE ANROOM
V ENTILA TION
CLE ANROOM
P LE NUM
ROOF
CLE ANROOMV ENTILA TION
PLAN VIEW PLAN VIEW
SECTION A-A SECTION A-A
82.90
8.00 56.90 18.00
99
.15
37
.85
18
.00
42
.30
82.90
8.00 56.90 18.00
16
.80
5.0
01
1.8
0
CLE ANROOM
Ma
i nte
na
nc
e T
unn
el
Ac
ce
ss
Tun
nel
0
SCALE10 m5
11
WTC 2013, Design and Construction of an Underground Chip Factory (Waferfab)
Challenges during ConstructionStability of Cavern
Huge cross-section with low overburden -> low horizontal stress
Simulation of spontaneous
rock instability
12
WTC 2013, Design and Construction of an Underground Chip Factory (Waferfab)
Challenges during ConstructionStability of Cavern
Open joints of up to 1 m
-> hardly any horizontal stress
13
WTC 2013, Design and Construction of an Underground Chip Factory (Waferfab)
Challenges during ConstructionStability of Cavern
Overbreaks
torn out rock bolt
14
WTC 2013, Design and Construction of an Underground Chip Factory (Waferfab)
Challenges during ConstructionStability of Cavern
Measurement Control System
Start excavation middle/left side g
Start excavation right side
max. deformation 7 mm
- extensometer
- 3D survey with anchor
Results- rapidly declinig deformations
- max. deformation of 8 mm, up to 8 m into rock
15
WTC 2013, Design and Construction of an Underground Chip Factory (Waferfab)
Conclusion
Underground space for production facilities with strict limitations on vibration and/or climatic conditions is an economic alternative.
Premises:
Good rock conditions, low water inflow
Direct and short access to the production facility
Integrative approach of all design parties