cern-rrb-2010-011 marzio nessi cern, 20 th april 2010 atlas detector status (i) 1

37
CERN-RRB-2010-011 Marzio Nessi CERN, 20 th April 2010 ATLAS detector status (I) 1

Upload: beverly-russell

Post on 19-Jan-2016

234 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: CERN-RRB-2010-011 Marzio Nessi CERN, 20 th April 2010 ATLAS detector status (I) 1

CERN-RRB-2010-011Marzio Nessi

CERN, 20th April 2010

ATLAS detector status (I)

1

Page 2: CERN-RRB-2010-011 Marzio Nessi CERN, 20 th April 2010 ATLAS detector status (I) 1

…. since last RRB (12th October)

From 10th November 2009 to 16th December the detector has been taking physics data at 450 GeV and 1.18 GeV per beam (single beams and collisions)

From 17th December 2009 to early February 2010 we have been in shutdown mode, but with no internal detector opening. Just access to the external services and to the muon spectrometer

From 28th February 2010 (first 2010 beams injections) we went back to data taking mode with up to now ~400 b-1 =~ 22M collisions events registered at 3.5 TeV per beam with the entire detector active

2

Page 3: CERN-RRB-2010-011 Marzio Nessi CERN, 20 th April 2010 ATLAS detector status (I) 1

Data taking efficiency

3

Stable beam flag

Data taking efficiency

In the last few weeks our data taking efficiency has been in average around 94%, some time is still lost in turning on the inner detectors once the stable beam flag is set by LHC

Page 4: CERN-RRB-2010-011 Marzio Nessi CERN, 20 th April 2010 ATLAS detector status (I) 1

Operation resources

4

After the initial learning period we will now operate ATLAS with 55 shifts/day (including Tier0 and distributed computing) at P1

… on top of this, we need ~ 140 x 8 hours-equivalent shifts for experts on call, satellite rooms shifts or remote shifts outside CERN, …… = ~ 150 people involved/day to keep the entire machinery running !

Page 5: CERN-RRB-2010-011 Marzio Nessi CERN, 20 th April 2010 ATLAS detector status (I) 1

Operation Tasks (OT) sharing

5

ATLAS operation (detector, data quality and calibration, software, world-wide computing, including all kinds of shifts …) requires ~ 800 FTE (physics is not an OT)

OT are distributed in a fair way across Institutions: proportional to the number of authors - students get favorable treatment as they are weighted 0.75 - new Institutions contribute more the first two years (weight factors 1.5, 1.25)

200 FTE (out of 800 total) are for shifts: ~ 50000 shifts in 2010 (~20 per author) - 70% CERN-based (Control Room or on-call); 30% remote shifts - we have recently reduced the number of Control Room shifts by 15% - as we gain experience less shifts in general, in particular less CERN-based shifts

Funding Agency

Covered-expected expected

Distribution per FA in 2009 (CERN-based shifts not included)Zero means ok, negative is bad

FTE requirements and FA contributions reviewed and updated yearly

Page 6: CERN-RRB-2010-011 Marzio Nessi CERN, 20 th April 2010 ATLAS detector status (I) 1

Shutdown activities

6

Most of the active detectors components have been switched off for the Xmas break. This has been the occasion for fixing some known problems or upgrade some components in view of the long run in front of us

Page 7: CERN-RRB-2010-011 Marzio Nessi CERN, 20 th April 2010 ATLAS detector status (I) 1

Shutdown activities

7

All magnets were left floating in temperature to save operation resources and allow some interventions to fix problem (Shield Refrigerator cryo-filter clogging and Current Lead thermal repair)

Phase separator temperature

Toroid inlet

temperature

At 4K, start of Helium

pumps

Ramp to 20.4kA

Cool down of Toroids and Solenoid 28 Jan-11 Feb,

13 days from start at 126K to Cryo_ready flag

Since then we have established all records on magnets stable operation !

Page 8: CERN-RRB-2010-011 Marzio Nessi CERN, 20 th April 2010 ATLAS detector status (I) 1

Shutdown activities

Fixed a water leak in the caver floor Consolidated the access structure to the inside of the detector Continued the installation of the staged EE chambers (barrel forward) Fixed problems of LV and HV in the muon spectr., fixed elect. problems Replaced gas filters (MDT), solved gas leaks problems RPC brought trigger coverage to practically 100% Got CSC readout chain operational inside the overall TDAQ system Added redundancy to several infrastructure key elements (electrical

and UPS distribution, magnet safety, ventilation, …. ) Anticipated yearly maintenance on various safety systems Consolidated gas and detector cooling systems Installed the first ALFA detector station (1/8), testing methods and time ……

Page 9: CERN-RRB-2010-011 Marzio Nessi CERN, 20 th April 2010 ATLAS detector status (I) 1

Detectors status

9

Page 10: CERN-RRB-2010-011 Marzio Nessi CERN, 20 th April 2010 ATLAS detector status (I) 1

Pixel tracker

10

p

K

d

Pixel operation

Recovered few modulesNon operational 45 modules (2.5 %)

Improved timing, soon ready for high number of bunches

Pixel hits ad vertices in all ATLAS analysis

dE/dx demonstrates how well the pixel-by-pixel calibration works and it has been widely used for all “re-discoveries”

The resolution on the primary vertex in the beam direction would be much worse (40% effect) without for example the b-layer.

Page 11: CERN-RRB-2010-011 Marzio Nessi CERN, 20 th April 2010 ATLAS detector status (I) 1

Pixel tracker

11

p

K

d

Pixel operation

Recovered few modulesNon operational 45 modules (2.5 %)

Improved timing, soon ready for high number of bunches

Pixel hits ad vertices in all ATLAS analysis

dE/dx demonstrates how well the pixel-by-pixel calibration works and it has been widely used for all “re-discoveries”

The resolution on the primary vertex in the beam direction would be much worse (40% effect) without for example the b-layer.

Page 12: CERN-RRB-2010-011 Marzio Nessi CERN, 20 th April 2010 ATLAS detector status (I) 1

SCT Tracker

12

Modules Excluded

Barrel End-Cap-C

End-Cap-A

Total

Cooling Loop - 13 - 13LV Problems 5(4) 1(1) 0 6(5)HV Problems 1(1) 1(1) 4(0) 6(2)RO Problems 2 0 1 3Other 1 - - 1Number of Modules

2112 988 988 4088

Total Modules Excluded

9 15 5 29

As a % 0.43 1.51 0.51 0.71

Page 13: CERN-RRB-2010-011 Marzio Nessi CERN, 20 th April 2010 ATLAS detector status (I) 1

TRT (Transition Radiation Tracker)

13

BarrelBarrel

End-capsEnd-caps

pions

electron

92%

Page 14: CERN-RRB-2010-011 Marzio Nessi CERN, 20 th April 2010 ATLAS detector status (I) 1

LAr Calorimeters (LVPS & OTx)

14

• Today: 58/58 operational FE-LVPS• 5 have lost the redundancy on one voltage line

• Backup in preparation• 2 vendors prepared 2 prototypes each

• A Source Selection Committee selected the best one

• Production Readiness Review 28.04.2010• Then place the order

• Production should be completed by end of 2010

• Setting-up a large test bench at CERN for 16 units• Long term running

• Installation next time we open the detector

Page 15: CERN-RRB-2010-011 Marzio Nessi CERN, 20 th April 2010 ATLAS detector status (I) 1

LAr Calorimeters (LVPS & OTx)

15

• Optical Transmitters Status • For 19 FEB-OTx: VCSEL died between

May 2009 & April 2010

• The width of the optical spectrum has been found as an indicator of the weakness

• After the measurement was performed (07.2009) all the OTx which died had a narrow OS

• There are ~50 remaining OTx with narrow spectrum on the detector

• Narrow OS OTx have been kept OFF until mid-March (start of LHC)

• OS spectra measured three times since July 2009: stable

• Failure rate ~ 3/month . None since 3 weeks!

• Future• 2 backup solutions in preparation (choose before the

summer)• B1: Replacement by a single VCSEL from a different

producer

• B2: Replacement by a double VCSEL + layout of double fibers

Page 16: CERN-RRB-2010-011 Marzio Nessi CERN, 20 th April 2010 ATLAS detector status (I) 1

Tiles Calorimeter

16

Cosmics: Signal /Noise = 29

97.3% Tile cells powered ON

3.2% cells are masked/bad for physics:• 0.5% noise or dig. corrupted data• 2.7% OFF:

- 5 (1.9%) LVPS- 2 (0.8%) S-drawers

We have a solution to be implemented in the next shutdown (needs opening)

Page 17: CERN-RRB-2010-011 Marzio Nessi CERN, 20 th April 2010 ATLAS detector status (I) 1

Muon spectrometer (CSC flagged as a problem last RRB)

17

• CSC now routinely run in the combined partition

• Very stable CSC DAQ operation

• Current Read-out rate limit 43 KHz, new versions expected at 53 KHz

• CSC tracking commissioning on-going, Ex: good Residual Pool distribution

Page 18: CERN-RRB-2010-011 Marzio Nessi CERN, 20 th April 2010 ATLAS detector status (I) 1

Muon Spectrometer Performance (precision chambers)

18

MDT detector coverage very good: 99.7%

Small sectorsLarge

sectors

Stand alone momentum resolution measured with cosmics

Page 19: CERN-RRB-2010-011 Marzio Nessi CERN, 20 th April 2010 ATLAS detector status (I) 1

TGC trigger timing and efficiency : first results

TGC Trigger timing TGC Trigger efficiency vs PT

Page 20: CERN-RRB-2010-011 Marzio Nessi CERN, 20 th April 2010 ATLAS detector status (I) 1

Today’s major worries

Tiles Calorimeter LV power suppliers failure (5 out of 256 modules since ~8 months) LAr OTX : additional failure of the light emitting component (VCSEL) on optical

transmitters (1 every 2-3 weeks)

Keep the evaporative cooling plant operational (proximity compressor plant).

Magnets shield refrigerator filter clogging (H2O contamination)

Follow up evolution of power supplies failures in the muon spectrometer Follow up evolution of fragile gas inlets (RPCs)

20

Solutions are being worked out, but it requires a 11 weeks shutdown to make the interventions possible (next Xmas period ?)

Page 21: CERN-RRB-2010-011 Marzio Nessi CERN, 20 th April 2010 ATLAS detector status (I) 1

Today’s major worries

Tiles Calorimeter LV power suppliers failure (5 out of 256 modules since ~8 months) LAr OTX : additional failure of the light emitting component (VCSEL) on optical

transmitters (1 every 2-3 weeks)

Keep the evaporative cooling plant operational (proximity compressor plant).

Magnets shield refrigerator filter clogging (H2O contamination)

Follow up evolution of power supplies failures in the muon spectrometer Follow up evolution of fragile gas inlets (RPCs)

21

A new evaporative cooling plant is being evaluated and is under study

A major upgrade of possible single point of failure is being pursued. It should be ready by 2012

Page 22: CERN-RRB-2010-011 Marzio Nessi CERN, 20 th April 2010 ATLAS detector status (I) 1

ID evaporative cooling plant problems

22

Important traces of debris impacts have been found on the cylinder

and piston head. The origin of the failure and the debris has been

identified in the suction valve of the first stage of the compressors.

A new problem was found in March on 2 out of the 7 compressors, which forced us to a major repair once more …. But we managed to keep the plant nevertheless operational (with 4 units) …. No impact on physics!

Page 23: CERN-RRB-2010-011 Marzio Nessi CERN, 20 th April 2010 ATLAS detector status (I) 1

ID evaporative cooling plant : 2 solutions under evaluation

23

PR

thermalscreen

others

4 liquid lines

4 gas lines

condenser

liquidtank

pneumaticvalve

manualvalve

manualvalve

dummyload

Heater

BPR

pixel

6 X SCT

manualvalve

pneumaticvalve

Low temperature chiller (-70 C)

UX15 USA15

USA15

Surface

Full thermo-siphon solution which uses gravity to establish correct pressure conditions, no active mechanical components …. But it requires a large chiller plant on surface to condensate the liquid!

Page 24: CERN-RRB-2010-011 Marzio Nessi CERN, 20 th April 2010 ATLAS detector status (I) 1

ID evaporative cooling plant : 2 solutions under evaluation

24

PR

thermalscreen

others

4 liquid lines

4 gas lines

condenser

liquidtank

pneumaticvalve

manualvalve

manualvalve

dummyload

Heater

BPR

pixel

6 X SCT

manualvalve

pneumaticvalve

StandardChiller

UX15 USA15

USA15

Surface

Hybrid solution where condensation is helped by a new generation of compressors (vibrations and oil free, magnetic bearings) …. It requires a standard chiller plant on surface (-10C)! One of such compressors is now under test at CERN!

Page 25: CERN-RRB-2010-011 Marzio Nessi CERN, 20 th April 2010 ATLAS detector status (I) 1

ID evaporative cooling plant : Thermo-siphon solution R&D

25

Tests of a mini thermo-siphon in bldg 191 successfully finished :

o 13 meters height, silent no mechanical stress

o Stable operation at -22 oC

o -30 oC reached

o Start up procedure and limitations well understood

Next step : installation and test at Point1o A full (geometrical) scale thermo-siphon circuit

should allow us to study thermo-dynamics and time constants and to study blends C3F8-C2F6

o Vertical piping installed from SH1 to USA15 level 3Our goal : ready for 2012 shutdown

Page 26: CERN-RRB-2010-011 Marzio Nessi CERN, 20 th April 2010 ATLAS detector status (I) 1

Magnet system consolidation work

26

Most shut-downs are related to cryogenics :1) Today we have 1 main compressor in the Main Refrigerator, when it breaks we are down for 9-12

months. Cure: install redundant main compressor for the Main Refrigerator

2) We are experiencing several problems of filter clogging (water contamination). To solve the problem we have just identified an air dryer to install in the next few months

3) The main Helium pump represents another single point of failure, solutions are been worked out, this adds to other consolidation needs on vacuum, controls, ….. All must be ready for 2012

Page 27: CERN-RRB-2010-011 Marzio Nessi CERN, 20 th April 2010 ATLAS detector status (I) 1

Today’s major worries

Tiles Calorimeter LV power suppliers failure (5 out of 256 modules since ~8 months) LAr OTX : additional failure of the light emitting component (VCSEL) on optical

transmitters (1 every 2-3 weeks)

Keep the evaporative cooling plant operational (proximity compressor plant).

Magnets shield refrigerator filter clogging (H2O contamination)

Follow up evolution of power supplies failures in the muon spectrometer Follow up evolution of fragile gas inlets (RPCs) A new potential problem of hot cells in the LAr Had endcaps is being investigated

27

Page 28: CERN-RRB-2010-011 Marzio Nessi CERN, 20 th April 2010 ATLAS detector status (I) 1

What is next on the detector side ?

The detector is ready for a long run in 2010/2011. It is performing well

We have solutions for the problems we are facing. To fix the Calorimeters % problems we will need access and therefore enough time to open and close the detector (~11 weeks)

A consolidation of the cryogenics system and of the evaporative cooling plant is foreseen for the long shutdown in 2012. We are actively preparing it.

We have learned enormously on the way to operate the detector. Now we can start to optimize the necessary resources, in particular the manpower needs for operation!

28

Page 29: CERN-RRB-2010-011 Marzio Nessi CERN, 20 th April 2010 ATLAS detector status (I) 1

… and on the medium/long term ? (upgrade/consolidation)

We are developing plans in 3 phases:

Phase 0: when we will fix all problems we know (cryogenics, evaporative cooling plant, calorimeters LVPS, optical transmitters, various single points of failure,….). We will also substitute the Fe beam pipe with a lighter one (Al or Al/Be) in order to minimize radiation backgrounds 2012 LHC shutdown

Phase 1: when we have collected enough statistics (at least 50 fb-1) and we will feel ready to make changes to the detector itself. We want the best possible detector for the bulk of the data we will take at LHC (~300fb-1). We need then a detector capable of ultimate Luminosity. We can improve on b-tagging and on the sharpness of the LVL1 trigger

Phase 2: we will then prepare the detector for the sLHC challenge. We will need to construct and install a new ID (after 300-400 fb-1)

29

Page 30: CERN-RRB-2010-011 Marzio Nessi CERN, 20 th April 2010 ATLAS detector status (I) 1

30

Our strategy !

Phase -0

Phase -1

Phase -2

Int.

Lum

inos

ity

year

Shutdown requirements :

Phase-0 : 12-14 months (defined by the LHC consolidation)Phase-1 : 8-9 months (time necessary to install at least the new pixel b-layer)Phase-2 : 18-20 months to install and debug the new ID detector

Consolidation + new beam pipe

- Be ready for ultimate Luminosity- Insert new pixel b-layer- Upgrade various systems for a better and sharper LVL1 trigger

Be ready for sLHCNew ID + solve LAr end-caps problems

We need to input our requirements in the overall LHC optimization plans

Page 31: CERN-RRB-2010-011 Marzio Nessi CERN, 20 th April 2010 ATLAS detector status (I) 1

31

Our strategy for Phase-1

Phase -0

Phase -1

Phase -2

Int.

Lum

inos

ity

yearWe are preparing projects to be ready for phase-1 :

- The first one is the insertable pixel b-layer (IBL). We will be ready at the end of 2014, in case the pixel detector will start showing problems. We will then install it as soon as a long shutdown can be scheduled. The construction is starting. We have drafts of a TDR and MOU- We are in the process of defining other projects, which can be organized in a way similar to the IBL. Most of these projects relate to an upgrade of the trigger system (more detector trigger granularity in the muon system, new generation of trigger hardware, a fast track processor, ….)

- Be ready for ultimate Luminosity- Insert new pixel b-layer- Upgrade various systems for a better and sharper LVL1 trigger

Page 32: CERN-RRB-2010-011 Marzio Nessi CERN, 20 th April 2010 ATLAS detector status (I) 1

The present 7m long section of the beam-pipe will be cut (flange too big to pass inside the existing pixel) and extracted in situ:

The new beam-pipe with the IBL will be inserted at its place.

ISTIBL Support

Tube

Alignment wirers

PP1 Collar

IBL (insertable B layer) Detector

IBL Staves

Sealing service ring

Existing B-layer

IBL (Staves)

Page 33: CERN-RRB-2010-011 Marzio Nessi CERN, 20 th April 2010 ATLAS detector status (I) 1

Technical Status of the IBL ProjectFE-I4 – New pixel front-end chip for IBL

20 x 19 mm2 real-estate, more that 70 M-transistors, largest HEP chip ever. 2 year design work for a team of ~15 engineers + several physicists from 5 laboratories. Three design reviews: 17/3/2008, 3-4/11/2009, 16/4/2010 - submission to IBM: 17/5/2010

Sensor prototypes for FE-I4 under processing – 3 technologies considered: Planar Sensors, 3D Sensors, Diamonds. Expected sensors bump-bonded to FE-I4 for next fall

IBL Layout finalised – 14 staves with 32 FE-I4 chip modules at R=3.2 cm

Stave baseline (following last December review’s recommendations) Low density carbon foam (ρ = 0.2 g/cm3), thin wall titanium cooling pipe (d=2mm), CO2 cooling.

Fitting and permanent cooling joints under prototyping. FEA analysis on going, thermal figure of merit measurement on samples

Mechanical design of the whole IBL detector 3D model and FEA for the whole detector on going. Installation mock-up under construction in bld.180 at CERN. Internal electrical services, flex hybrid in prototype phase.

New ROD/BOC (off-detector readout). Modernized version of the Pixel VME ROD – more compact (x4 more channels/board) increased

performance, large reduction of component count with state of the art FPGA technology.

Page 34: CERN-RRB-2010-011 Marzio Nessi CERN, 20 th April 2010 ATLAS detector status (I) 1

Memorandum of Understanding

IBL Memorandum of Understanding (MoU) Between The ATLAS COLLABORATION, and Funding Agency/Institution of the ATLAS

Collaboration

IBL MoU – Steps toward project shaping: “IBL Kick-off” meeting (8/7/2009) – Institutes express their interest in the IBL based on

project WBS (Workpackage Breakdown Structure). Sharing of Resources (draft) discussed in the (interim) Institute Board (1/3/2010) –

Contribution to the Cost presented to the National Contact Physicists in ATLAS (ATLAS NCP meeting – 25/2/2010).

IBL interim MoU Ad Interim MoU until sensor technology is chosen (Planar Silicon / 3D Silicon / Diamond) -

Decision on sensor technology (early 2011) – Sensor R&D and IBL communities work in tight collaboration to finalise a design matching IBL specification.

Consolidate interest of Institutes and availability of funds

Page 35: CERN-RRB-2010-011 Marzio Nessi CERN, 20 th April 2010 ATLAS detector status (I) 1

MOU Annex 4: Tentative Contribution to IBL

Note: the numbers in the table "are not final, nor are the suggested financial contributions yet firm, but are meant for a common overall discussion.”

Technology options refer to supplementary costs that are sensor technology specific and will be known before the definite MoU takes effect.

So far, France, Italy and US have requested their shares to be moved from M&O B to Project part.

Page 36: CERN-RRB-2010-011 Marzio Nessi CERN, 20 th April 2010 ATLAS detector status (I) 1

36

Phase-2 Upgrade (sLHC)

We have centrally organized a vigorous R&D program for most of the technology we have to act on (more then 20 active R&D projects have been approved and are operational)

The optimization of the layout of the new Inner Detector is at the moment the major concern. Most of the work is on simulation! The process is ongoing

The first step of detailed engineering has started, we are now facing a new phase where we need to decide on the construction of large prototypes (staves, modules, services layout, support structures,….) to demonstrate feasibility. The time needed for mass production is probably around 7-8 years, once the project is fully defined

Page 37: CERN-RRB-2010-011 Marzio Nessi CERN, 20 th April 2010 ATLAS detector status (I) 1

37