cern mbhsm0101 general status f. savary on behalf of the 11t dipole project team
DESCRIPTION
CERN-FNAL Video Meeting #12 Progress of the 11T Dipole short model program (Task 2 of HL-LHC WP-11). CERN MBHSM0101 general status F. Savary on behalf of the 11T Dipole Project Team. Contributions. - PowerPoint PPT PresentationTRANSCRIPT
CERN-FNAL Video Meeting 12
Progress of the 11T Dipole short model program (Task 2 of HL-LHC WP-11)
CERN MBHSM0101 general statusF Savary on behalf of the 11T Dipole Project Team
Click here to add footer 2
Contributionsbull Bateman R1 Batts S 1 Bourcey N Cote D Duret M
Fernandes C Izquierdo Bermudez S Gauthier R Guinchard M Grand-Clement L Grosclaude P Grospelier E Jokinen A 1 Juchno M Julien V Karppinen M Lackner F Lambert L Loumlffler C Lyon T-J Mazet J Peray N Pincot F-O Savary F Schmid N Smekens D Willering G
bull 1Oxford Instrument
Click here to add footer 3
Main design featuresbull Single aperture 6-bloc designbull 56 turns
bull 22 on IL (4 blocs)bull 34 on OL (2 blocs)
bull Aperture 60 mmbull Coil length 18 mbull Yoke OD 510 mmbull Shell thickness 12 mm [AISI 304L]
Click here to add footer 4
Specific featuresbull Copper coil 101
bull End spacers CERN v0 longer coilbull Sc coil 105
bull Cable OST RRP 108127bull ODS alloy wedgesbull CERN V4 end spacers SLS (with flex hinge legs)bull Metallic saddles and splice blocksbull External trace glued on coil OD carrying V-taps and quench
heaters (next slide)bull Collars and yoke laminations produced by EDM
bull Collars YUS130S Nippon Steel 3 mm thickness (LHC dipole)bull Yoke laminations Arcelor Magnetil Low C steel 58 mm
thickness (LHC dipole)
Click here to add footer 5
Assembly conditions - Windingbull Winding tension
bull Coil 101 300 N insulation defects gt1bull Coil 105 250 N insulation defects 0
bull Cable insulationbull Coils 101 and 105
bull Outer sleeve AGY S-2 Glass 11 Tex direct braidingbull Inner dielectric Cogebi Firox 80 microm Mica ndash Fiber glass tape
bull Winding monitoring during coil 105 production
D SmekensJ Mazet
Coils longer than expected ~20 mm
Click here to add footer 6
Binder curingbull Binder CTD 1202-X qty
bull Coil 101 IL in excess OL in excessbull Coil 105 IL 100 g OL 100 g
bull Shimming nominal (shimming such that in the press the mid-plane of the cured coil is like in the magnet 012 mm above center axis)bull This is different compared to FERMILAB where oversized shimming
is used to compact the coil mid-plane beyond its nominal position in order to obtain a smaller coil size before entering into reaction
bull With a load of 08 MN the mold is nearly closed (lt 01mm)bull Then a load of 2 MN is used for IL and 42 MN for the OL
(complete pole)bull The stress in the coils may not exceed 37 MPa at that stage
D SmekensJ Mazet
Click here to add footer 7
Reaction treatmentbull Cavity of the reaction fixture is radially bigger than the curing
mold by 01 mm and of similar dimension at coil mid-planebull Thus if the curing press can be closed before reaching 37
MPa the coil cannot be subjected to higher stress when closing the fixture However the dry fiber glass and the tight tolerances induce large friction also a possible dimensional problem with the sealing foils could have generated interference between the sealing foil and the baseplate preventing correct closure of the fixture
bull The tightening torque to close the fixture was of the order of 300 Nm (FNAL applies 110 Nm to 160 Nm)
bull Not clear no coil contraction after reaction actually less that 1 mm when 45 mm were expected
D SmekensN BourceyF Lackner
Click here to add footer 8
Reaction treatment ndash Coil 105
Adjustment of dwell time to compensate the delay between the
temperature and tooling temperature
The homogeneity of T during ramp up was not very good plusmn
9degCHowever it is OK during
dwell time
N BourceyF Lackner
Click here to add footer 9
Impregnationbull Resin CTD 101K
bull Anhydride cured epoxy system with excellent performance at cryogenic temperature and radiation resistance
bull The resin is preheated and the coil is impregnated at 60degC
bull Curing 110degC for 5 hoursbull Post curing heating 125degC for 16 hours
R GauthierD Smekens
Temperature [degC] Pot life [h] Viscosity [mmmiddotPas]25 145 1300
40 60 400
60 20 100
Click here to add footer 10
Instrumentation outer layer
Outer layer instrumentation incorporated in a Trace which is applied after impregnationThere are 2 ldquoUrdquo shaped SS quench heaters with Cu overlay with Cu masked off to provide heating regions Heater width is 19mm in low-field region with heater regions 90mm apart In the high-field region the heater width is 24mm and the heater regions are 130mm apartThere are 13 voltage taps on the Trace including 6 on the pole turn 1 on the layer jump and 4 on the mid-plane turn
EES5O
I
EE5O12-
+
EES5OO
EE5O11EE5O10
EE5O9
EE5O8 EE5O6EE5O7 EE5O5
EE5O4EE5O3EE5O2
EE5O1
Click here to add footer 11
Instrumentation inner layer
Inner layer instrumentation consists only of voltage taps There are 16 voltage taps including 6 on the pole turn 1 on the layer jump and 4 on the mid-plane turn with other taps adjacent to spacer block edges
S Izquierdo BermudezF-O PincotR Bateman
Click here to add footer 12
Quench heaters
50 70 90 110 130 150 170 19000
200400600800
100012001400160018002000
Low Field Region High Field Region
Heater Current (A)
Pow
er d
ensi
ty (W
cm
2)
Operation area
bull Width -gt Cover as many turns as possible
bull LF 19 mm bull HF 24 mm
bull Power densitybull LF asymp 75 Wcm2
bull HFasymp 55 Wcm2
Even if the operational current is expected to be in the range 100-120 A it would be good to have the possibility to go up to 150 A during short model tests to check the saturation of the system in terms of heater delays
119875119889=1198682119877119908119871
119877=120588 119871119908119905
119875119889=1198682 1205881199082119905
Heater width19 mm LF 24 mm HFρss=7310-7Ωm RRR=134
bull Distance between heater stations -gt quench propagation in between stations asymp 5 msbull LF 90 mmbull HF 130 mm
bull Coverage maximum coverage keeping the resistance within the allowable limits for a 55 m magnet (depends on the number of power suppliesheater circuits)
Cu
50 90130
192
4
Cu
Click here to add footer 13
Coils size
bull Both coils 101 and 105 were oversized only in the mid-plane
bull Best-fit on the outer diameter and the loading plates (interface with pole)
Click here to add footer 14
Excess in mid-plane
-150 -50 50 20
030
040
050
060
070
080
090
090
011
0012
0013
0014
000
100
200
300
400
500
600
700
800
leftrightaverage
Coil length [mm]
Inte
rfer
ence
[microm
]
Click here to add footer 15
Collaring steps
2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 320
50100150200250300350400
Distance to collaring position right lead endright return endleft lead endleft return end
F [MN]
offs
et k
ey g
roov
e [micro
m]
With 8MN the stoppers of the collaring tool were in contact
Click here to add footer 16
Shimming planbull Mid-plane is 650 microm beyond expectations To compensate
bull One layer of Kapton was removed on the mid-plane
bull Changed one layer of insulation to 005 microm thickness (in lieu of 0125 microm)
Click here to add footer 17
Yoking welding of the shellsF Lackner
1 2 3 4 5 6 7 80
100200300400500600700800
0
110
206
361426
526610
686Pressure rising April 28th 2014
Pressure rising step
Tota
l cha
rge
in to
ns
3154906157901240166520652225
002040608
SIDE B 0110206361426526610686
Length in [mm]
Yoke
gap
[mm
]
Tota
l loa
d in
tons
Max charge 500 tm on central section to close the welding gap
0
02
04
06
SIDE A0110206361426526610686
Length in [mm]
Yoke
gap
[mm
]
Tota
l loa
d in
tons
Click here to add footer 18
Structural analysis vs measurements
Click here to add footer 19
FEA Results 11T Mirror
FEA Max Cap gauge
pressure (MPa)
FEA Avg Cap gauge
pressure (MPa)
FEA Min Cap gauge
pressure (MPa)
Collar nose
stress (MPa)
Coil Min stress (MPa)
Coil Max Stress (MPa)
Avg Shell Stress (MPa)
Collaring Load 48 33 18 88 -7 -90
Post-Collaring 39 28 16 72 -7 -69
Collar in yoke 40 28 17 73 -9 -66
Max Press force 46 31 15 81 -14 -60 10
Shell Weld + Press Force 50 33 14 87 -16 -61 187
Shell Welded no Press Force 48 32 15 85 -15 -60 194
Collaring Load Post-Collaring Collar in yoke Max Press force Shell Weld + Press Force
Shell Welded no Press Force
Shell Welded - 297K
Cool Down (18K)
11-Tesla0
10
20
30
40
50
60Mirror Coil - contact pressure at pole (Cap Gauge)
FEA Max Cap gauge - pressure (MPa)
FEA Avg Cap gauge - pressure (MPa)
FEA Min Cap gauge - pressure (MPa)
Measured Coil Data (10 error bars)
Pres
sure
(MPa
)
Click here to add footer 20
ANSYS Forecast at 11-Tesla
Assembly Step
Max Capacitive gauge -
pressure (MPa)
Avg Capacitive gauge -
pressure (MPa)
Min Capacitive gauge -
pressure (MPa)
Collar-nose stress (MPa)
Coil Min stress (MPa)
Coil Max Stress (MPa)
Avg Shell Stress (MPa)
MirrorCoil
Shell Welded - 297K 48 32 15 85 -15 -60 195
Cool Down (18K) 37 21 5 62 -5 -74 375
11-Tesla 1 05 0 63 +13 -117 377
NominalCoil
Shell Welded - 297K 107 58 8 150 -14 -119 191
Cool Down (18K) 86 43 1 123 -21 -125 373
11-Tesla 22 11 0 57 -4 -120 374
Collar Nose Von-Mises Stress
At 11T
Coil BlocksAzimuthal Stress
At 11T
FEA predicted results
Click here to add footer 21
Bullet gauges loadingM GuinchardP Grosclaude
8 to 9 kN per bullet
Click here to add footer 22
Electrical tests ndash WhenF-O PincotL Grand Cleacutement
Are performed beforeafter each important construction step Test of pole Nb3Sn before curing - PBC Test of pole Nb3Sn before reaction ndash PBR Test of pole Nb3Sn after reaction ndash PAR Test of pole Nb3Sn after impregnation out of the mould ndash PAI Test of pole Nb3Sn after impregnation with instrumentation ndash PAIWI Test of collared coil before collaring ndash BC Test of collared coil after collaring ndash AC Test of the magnet under load before welding ndash UL Test of the magnet after shell welding ndash AW Test of the magnet after longitudinal coil loading ndash AL Test of the magnet after interconnection ndash AI Final Test of the magnet before delivery - FINAL
Click here to add footer 23
Electrical tests ndash WhatF-O PincotL Grand CleacutementAccording to the construction step we define
specific test valueselectrical tests among which
Resistance measurement(Coils Quench heaters Voltage taps Instrumentation) Inductance measurement Capacitance measurement Dielectric measurement(between coils QH instrumentation ground)
bull Insulation (up to 1kV 30s)bull current leakage (up to 1kV 5min)
Discharge test on coilUp to 1kV
Discharge test on quench heatersUp to 900V or 80AQH
Click here to add footer 24
Electrical testsF-O PincotL Grand Cleacutement
Resistance Insulation dielectric Inductance Capacitance Coil discharge QH discharge
Test phase
code
PBC X X X
PBR X X X
PAR X X X
PAI X X X X
PAIWI X X X X
BC X X X X X X
AC X X X X X X
UL X X
AW X X X X X X
AL X X X X X X
AI X X X X X X
FINAL X X X X X X
Click here to add footer 25
Click here to add footer 26
Plan for power tests coldbull RRR and strain gauge measurementsbull Preliminary tests ndash Setup protection ndash Splice resistance
measurements (current plateaus at 2 4 6 8 and 10 kA) ndash 3 hoursbull Training 43 K ndash 15 quenches ndash 3 days bull Training 19 K ndash 10 quenches ndash 25 days
Stability on current plateau ndash 05 daybull Ramp-rate study 100 As and 50 As ndash 05 day
AC-loss measurements (includes inductance measurement) at 5 to 100 As ndash 05 day
bull Quench heater efficiency study 3 different settings of QH pulse for 3 currents each Long re-cooling of the magnet due to delay of energy extraction ndash 3 days
bull High MIIts tests (protection delay) 6 quenches ndash 3 days
bull Quench propagation velocity measurements acquired for the training quenches
G Willeringbull Cool down bull Day 1
bull Day 2-4bull Day 5-7
bull Day 8
bull Day 9-11
bull Day 12-14
Click here to add footer 27
Further actionsbull After cold tests warm magnetic
measurements will be carried out with the two coils connected
bull Model 1 MBHSP101 single aperture with cable OST RRP 108127 for both polesbull Instrumentation of coils 106 and 107 going onbull Collaring scheduled around middle of June
- CERN-FNAL Video Meeting 12 Progress of the 11T Dipole short m
- Contributions
- Main design features
- Specific features
- Assembly conditions - Winding
- Binder curing
- Reaction treatment
- Reaction treatment ndash Coil 105
- Impregnation
- Instrumentation outer layer
- Instrumentation inner layer
- Quench heaters
- Coils size
- Excess in mid-plane
- Collaring steps
- Shimming plan
- Yoking welding of the shells
- Structural analysis vs measurements
- FEA Results
- ANSYS Forecast at 11-Tesla
- Bullet gauges loading
- Electrical tests ndash When
- Electrical tests ndash What
- Electrical tests
- Slide 25
- Plan for power tests cold
- Further actions
-
Click here to add footer 2
Contributionsbull Bateman R1 Batts S 1 Bourcey N Cote D Duret M
Fernandes C Izquierdo Bermudez S Gauthier R Guinchard M Grand-Clement L Grosclaude P Grospelier E Jokinen A 1 Juchno M Julien V Karppinen M Lackner F Lambert L Loumlffler C Lyon T-J Mazet J Peray N Pincot F-O Savary F Schmid N Smekens D Willering G
bull 1Oxford Instrument
Click here to add footer 3
Main design featuresbull Single aperture 6-bloc designbull 56 turns
bull 22 on IL (4 blocs)bull 34 on OL (2 blocs)
bull Aperture 60 mmbull Coil length 18 mbull Yoke OD 510 mmbull Shell thickness 12 mm [AISI 304L]
Click here to add footer 4
Specific featuresbull Copper coil 101
bull End spacers CERN v0 longer coilbull Sc coil 105
bull Cable OST RRP 108127bull ODS alloy wedgesbull CERN V4 end spacers SLS (with flex hinge legs)bull Metallic saddles and splice blocksbull External trace glued on coil OD carrying V-taps and quench
heaters (next slide)bull Collars and yoke laminations produced by EDM
bull Collars YUS130S Nippon Steel 3 mm thickness (LHC dipole)bull Yoke laminations Arcelor Magnetil Low C steel 58 mm
thickness (LHC dipole)
Click here to add footer 5
Assembly conditions - Windingbull Winding tension
bull Coil 101 300 N insulation defects gt1bull Coil 105 250 N insulation defects 0
bull Cable insulationbull Coils 101 and 105
bull Outer sleeve AGY S-2 Glass 11 Tex direct braidingbull Inner dielectric Cogebi Firox 80 microm Mica ndash Fiber glass tape
bull Winding monitoring during coil 105 production
D SmekensJ Mazet
Coils longer than expected ~20 mm
Click here to add footer 6
Binder curingbull Binder CTD 1202-X qty
bull Coil 101 IL in excess OL in excessbull Coil 105 IL 100 g OL 100 g
bull Shimming nominal (shimming such that in the press the mid-plane of the cured coil is like in the magnet 012 mm above center axis)bull This is different compared to FERMILAB where oversized shimming
is used to compact the coil mid-plane beyond its nominal position in order to obtain a smaller coil size before entering into reaction
bull With a load of 08 MN the mold is nearly closed (lt 01mm)bull Then a load of 2 MN is used for IL and 42 MN for the OL
(complete pole)bull The stress in the coils may not exceed 37 MPa at that stage
D SmekensJ Mazet
Click here to add footer 7
Reaction treatmentbull Cavity of the reaction fixture is radially bigger than the curing
mold by 01 mm and of similar dimension at coil mid-planebull Thus if the curing press can be closed before reaching 37
MPa the coil cannot be subjected to higher stress when closing the fixture However the dry fiber glass and the tight tolerances induce large friction also a possible dimensional problem with the sealing foils could have generated interference between the sealing foil and the baseplate preventing correct closure of the fixture
bull The tightening torque to close the fixture was of the order of 300 Nm (FNAL applies 110 Nm to 160 Nm)
bull Not clear no coil contraction after reaction actually less that 1 mm when 45 mm were expected
D SmekensN BourceyF Lackner
Click here to add footer 8
Reaction treatment ndash Coil 105
Adjustment of dwell time to compensate the delay between the
temperature and tooling temperature
The homogeneity of T during ramp up was not very good plusmn
9degCHowever it is OK during
dwell time
N BourceyF Lackner
Click here to add footer 9
Impregnationbull Resin CTD 101K
bull Anhydride cured epoxy system with excellent performance at cryogenic temperature and radiation resistance
bull The resin is preheated and the coil is impregnated at 60degC
bull Curing 110degC for 5 hoursbull Post curing heating 125degC for 16 hours
R GauthierD Smekens
Temperature [degC] Pot life [h] Viscosity [mmmiddotPas]25 145 1300
40 60 400
60 20 100
Click here to add footer 10
Instrumentation outer layer
Outer layer instrumentation incorporated in a Trace which is applied after impregnationThere are 2 ldquoUrdquo shaped SS quench heaters with Cu overlay with Cu masked off to provide heating regions Heater width is 19mm in low-field region with heater regions 90mm apart In the high-field region the heater width is 24mm and the heater regions are 130mm apartThere are 13 voltage taps on the Trace including 6 on the pole turn 1 on the layer jump and 4 on the mid-plane turn
EES5O
I
EE5O12-
+
EES5OO
EE5O11EE5O10
EE5O9
EE5O8 EE5O6EE5O7 EE5O5
EE5O4EE5O3EE5O2
EE5O1
Click here to add footer 11
Instrumentation inner layer
Inner layer instrumentation consists only of voltage taps There are 16 voltage taps including 6 on the pole turn 1 on the layer jump and 4 on the mid-plane turn with other taps adjacent to spacer block edges
S Izquierdo BermudezF-O PincotR Bateman
Click here to add footer 12
Quench heaters
50 70 90 110 130 150 170 19000
200400600800
100012001400160018002000
Low Field Region High Field Region
Heater Current (A)
Pow
er d
ensi
ty (W
cm
2)
Operation area
bull Width -gt Cover as many turns as possible
bull LF 19 mm bull HF 24 mm
bull Power densitybull LF asymp 75 Wcm2
bull HFasymp 55 Wcm2
Even if the operational current is expected to be in the range 100-120 A it would be good to have the possibility to go up to 150 A during short model tests to check the saturation of the system in terms of heater delays
119875119889=1198682119877119908119871
119877=120588 119871119908119905
119875119889=1198682 1205881199082119905
Heater width19 mm LF 24 mm HFρss=7310-7Ωm RRR=134
bull Distance between heater stations -gt quench propagation in between stations asymp 5 msbull LF 90 mmbull HF 130 mm
bull Coverage maximum coverage keeping the resistance within the allowable limits for a 55 m magnet (depends on the number of power suppliesheater circuits)
Cu
50 90130
192
4
Cu
Click here to add footer 13
Coils size
bull Both coils 101 and 105 were oversized only in the mid-plane
bull Best-fit on the outer diameter and the loading plates (interface with pole)
Click here to add footer 14
Excess in mid-plane
-150 -50 50 20
030
040
050
060
070
080
090
090
011
0012
0013
0014
000
100
200
300
400
500
600
700
800
leftrightaverage
Coil length [mm]
Inte
rfer
ence
[microm
]
Click here to add footer 15
Collaring steps
2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 320
50100150200250300350400
Distance to collaring position right lead endright return endleft lead endleft return end
F [MN]
offs
et k
ey g
roov
e [micro
m]
With 8MN the stoppers of the collaring tool were in contact
Click here to add footer 16
Shimming planbull Mid-plane is 650 microm beyond expectations To compensate
bull One layer of Kapton was removed on the mid-plane
bull Changed one layer of insulation to 005 microm thickness (in lieu of 0125 microm)
Click here to add footer 17
Yoking welding of the shellsF Lackner
1 2 3 4 5 6 7 80
100200300400500600700800
0
110
206
361426
526610
686Pressure rising April 28th 2014
Pressure rising step
Tota
l cha
rge
in to
ns
3154906157901240166520652225
002040608
SIDE B 0110206361426526610686
Length in [mm]
Yoke
gap
[mm
]
Tota
l loa
d in
tons
Max charge 500 tm on central section to close the welding gap
0
02
04
06
SIDE A0110206361426526610686
Length in [mm]
Yoke
gap
[mm
]
Tota
l loa
d in
tons
Click here to add footer 18
Structural analysis vs measurements
Click here to add footer 19
FEA Results 11T Mirror
FEA Max Cap gauge
pressure (MPa)
FEA Avg Cap gauge
pressure (MPa)
FEA Min Cap gauge
pressure (MPa)
Collar nose
stress (MPa)
Coil Min stress (MPa)
Coil Max Stress (MPa)
Avg Shell Stress (MPa)
Collaring Load 48 33 18 88 -7 -90
Post-Collaring 39 28 16 72 -7 -69
Collar in yoke 40 28 17 73 -9 -66
Max Press force 46 31 15 81 -14 -60 10
Shell Weld + Press Force 50 33 14 87 -16 -61 187
Shell Welded no Press Force 48 32 15 85 -15 -60 194
Collaring Load Post-Collaring Collar in yoke Max Press force Shell Weld + Press Force
Shell Welded no Press Force
Shell Welded - 297K
Cool Down (18K)
11-Tesla0
10
20
30
40
50
60Mirror Coil - contact pressure at pole (Cap Gauge)
FEA Max Cap gauge - pressure (MPa)
FEA Avg Cap gauge - pressure (MPa)
FEA Min Cap gauge - pressure (MPa)
Measured Coil Data (10 error bars)
Pres
sure
(MPa
)
Click here to add footer 20
ANSYS Forecast at 11-Tesla
Assembly Step
Max Capacitive gauge -
pressure (MPa)
Avg Capacitive gauge -
pressure (MPa)
Min Capacitive gauge -
pressure (MPa)
Collar-nose stress (MPa)
Coil Min stress (MPa)
Coil Max Stress (MPa)
Avg Shell Stress (MPa)
MirrorCoil
Shell Welded - 297K 48 32 15 85 -15 -60 195
Cool Down (18K) 37 21 5 62 -5 -74 375
11-Tesla 1 05 0 63 +13 -117 377
NominalCoil
Shell Welded - 297K 107 58 8 150 -14 -119 191
Cool Down (18K) 86 43 1 123 -21 -125 373
11-Tesla 22 11 0 57 -4 -120 374
Collar Nose Von-Mises Stress
At 11T
Coil BlocksAzimuthal Stress
At 11T
FEA predicted results
Click here to add footer 21
Bullet gauges loadingM GuinchardP Grosclaude
8 to 9 kN per bullet
Click here to add footer 22
Electrical tests ndash WhenF-O PincotL Grand Cleacutement
Are performed beforeafter each important construction step Test of pole Nb3Sn before curing - PBC Test of pole Nb3Sn before reaction ndash PBR Test of pole Nb3Sn after reaction ndash PAR Test of pole Nb3Sn after impregnation out of the mould ndash PAI Test of pole Nb3Sn after impregnation with instrumentation ndash PAIWI Test of collared coil before collaring ndash BC Test of collared coil after collaring ndash AC Test of the magnet under load before welding ndash UL Test of the magnet after shell welding ndash AW Test of the magnet after longitudinal coil loading ndash AL Test of the magnet after interconnection ndash AI Final Test of the magnet before delivery - FINAL
Click here to add footer 23
Electrical tests ndash WhatF-O PincotL Grand CleacutementAccording to the construction step we define
specific test valueselectrical tests among which
Resistance measurement(Coils Quench heaters Voltage taps Instrumentation) Inductance measurement Capacitance measurement Dielectric measurement(between coils QH instrumentation ground)
bull Insulation (up to 1kV 30s)bull current leakage (up to 1kV 5min)
Discharge test on coilUp to 1kV
Discharge test on quench heatersUp to 900V or 80AQH
Click here to add footer 24
Electrical testsF-O PincotL Grand Cleacutement
Resistance Insulation dielectric Inductance Capacitance Coil discharge QH discharge
Test phase
code
PBC X X X
PBR X X X
PAR X X X
PAI X X X X
PAIWI X X X X
BC X X X X X X
AC X X X X X X
UL X X
AW X X X X X X
AL X X X X X X
AI X X X X X X
FINAL X X X X X X
Click here to add footer 25
Click here to add footer 26
Plan for power tests coldbull RRR and strain gauge measurementsbull Preliminary tests ndash Setup protection ndash Splice resistance
measurements (current plateaus at 2 4 6 8 and 10 kA) ndash 3 hoursbull Training 43 K ndash 15 quenches ndash 3 days bull Training 19 K ndash 10 quenches ndash 25 days
Stability on current plateau ndash 05 daybull Ramp-rate study 100 As and 50 As ndash 05 day
AC-loss measurements (includes inductance measurement) at 5 to 100 As ndash 05 day
bull Quench heater efficiency study 3 different settings of QH pulse for 3 currents each Long re-cooling of the magnet due to delay of energy extraction ndash 3 days
bull High MIIts tests (protection delay) 6 quenches ndash 3 days
bull Quench propagation velocity measurements acquired for the training quenches
G Willeringbull Cool down bull Day 1
bull Day 2-4bull Day 5-7
bull Day 8
bull Day 9-11
bull Day 12-14
Click here to add footer 27
Further actionsbull After cold tests warm magnetic
measurements will be carried out with the two coils connected
bull Model 1 MBHSP101 single aperture with cable OST RRP 108127 for both polesbull Instrumentation of coils 106 and 107 going onbull Collaring scheduled around middle of June
- CERN-FNAL Video Meeting 12 Progress of the 11T Dipole short m
- Contributions
- Main design features
- Specific features
- Assembly conditions - Winding
- Binder curing
- Reaction treatment
- Reaction treatment ndash Coil 105
- Impregnation
- Instrumentation outer layer
- Instrumentation inner layer
- Quench heaters
- Coils size
- Excess in mid-plane
- Collaring steps
- Shimming plan
- Yoking welding of the shells
- Structural analysis vs measurements
- FEA Results
- ANSYS Forecast at 11-Tesla
- Bullet gauges loading
- Electrical tests ndash When
- Electrical tests ndash What
- Electrical tests
- Slide 25
- Plan for power tests cold
- Further actions
-
Click here to add footer 3
Main design featuresbull Single aperture 6-bloc designbull 56 turns
bull 22 on IL (4 blocs)bull 34 on OL (2 blocs)
bull Aperture 60 mmbull Coil length 18 mbull Yoke OD 510 mmbull Shell thickness 12 mm [AISI 304L]
Click here to add footer 4
Specific featuresbull Copper coil 101
bull End spacers CERN v0 longer coilbull Sc coil 105
bull Cable OST RRP 108127bull ODS alloy wedgesbull CERN V4 end spacers SLS (with flex hinge legs)bull Metallic saddles and splice blocksbull External trace glued on coil OD carrying V-taps and quench
heaters (next slide)bull Collars and yoke laminations produced by EDM
bull Collars YUS130S Nippon Steel 3 mm thickness (LHC dipole)bull Yoke laminations Arcelor Magnetil Low C steel 58 mm
thickness (LHC dipole)
Click here to add footer 5
Assembly conditions - Windingbull Winding tension
bull Coil 101 300 N insulation defects gt1bull Coil 105 250 N insulation defects 0
bull Cable insulationbull Coils 101 and 105
bull Outer sleeve AGY S-2 Glass 11 Tex direct braidingbull Inner dielectric Cogebi Firox 80 microm Mica ndash Fiber glass tape
bull Winding monitoring during coil 105 production
D SmekensJ Mazet
Coils longer than expected ~20 mm
Click here to add footer 6
Binder curingbull Binder CTD 1202-X qty
bull Coil 101 IL in excess OL in excessbull Coil 105 IL 100 g OL 100 g
bull Shimming nominal (shimming such that in the press the mid-plane of the cured coil is like in the magnet 012 mm above center axis)bull This is different compared to FERMILAB where oversized shimming
is used to compact the coil mid-plane beyond its nominal position in order to obtain a smaller coil size before entering into reaction
bull With a load of 08 MN the mold is nearly closed (lt 01mm)bull Then a load of 2 MN is used for IL and 42 MN for the OL
(complete pole)bull The stress in the coils may not exceed 37 MPa at that stage
D SmekensJ Mazet
Click here to add footer 7
Reaction treatmentbull Cavity of the reaction fixture is radially bigger than the curing
mold by 01 mm and of similar dimension at coil mid-planebull Thus if the curing press can be closed before reaching 37
MPa the coil cannot be subjected to higher stress when closing the fixture However the dry fiber glass and the tight tolerances induce large friction also a possible dimensional problem with the sealing foils could have generated interference between the sealing foil and the baseplate preventing correct closure of the fixture
bull The tightening torque to close the fixture was of the order of 300 Nm (FNAL applies 110 Nm to 160 Nm)
bull Not clear no coil contraction after reaction actually less that 1 mm when 45 mm were expected
D SmekensN BourceyF Lackner
Click here to add footer 8
Reaction treatment ndash Coil 105
Adjustment of dwell time to compensate the delay between the
temperature and tooling temperature
The homogeneity of T during ramp up was not very good plusmn
9degCHowever it is OK during
dwell time
N BourceyF Lackner
Click here to add footer 9
Impregnationbull Resin CTD 101K
bull Anhydride cured epoxy system with excellent performance at cryogenic temperature and radiation resistance
bull The resin is preheated and the coil is impregnated at 60degC
bull Curing 110degC for 5 hoursbull Post curing heating 125degC for 16 hours
R GauthierD Smekens
Temperature [degC] Pot life [h] Viscosity [mmmiddotPas]25 145 1300
40 60 400
60 20 100
Click here to add footer 10
Instrumentation outer layer
Outer layer instrumentation incorporated in a Trace which is applied after impregnationThere are 2 ldquoUrdquo shaped SS quench heaters with Cu overlay with Cu masked off to provide heating regions Heater width is 19mm in low-field region with heater regions 90mm apart In the high-field region the heater width is 24mm and the heater regions are 130mm apartThere are 13 voltage taps on the Trace including 6 on the pole turn 1 on the layer jump and 4 on the mid-plane turn
EES5O
I
EE5O12-
+
EES5OO
EE5O11EE5O10
EE5O9
EE5O8 EE5O6EE5O7 EE5O5
EE5O4EE5O3EE5O2
EE5O1
Click here to add footer 11
Instrumentation inner layer
Inner layer instrumentation consists only of voltage taps There are 16 voltage taps including 6 on the pole turn 1 on the layer jump and 4 on the mid-plane turn with other taps adjacent to spacer block edges
S Izquierdo BermudezF-O PincotR Bateman
Click here to add footer 12
Quench heaters
50 70 90 110 130 150 170 19000
200400600800
100012001400160018002000
Low Field Region High Field Region
Heater Current (A)
Pow
er d
ensi
ty (W
cm
2)
Operation area
bull Width -gt Cover as many turns as possible
bull LF 19 mm bull HF 24 mm
bull Power densitybull LF asymp 75 Wcm2
bull HFasymp 55 Wcm2
Even if the operational current is expected to be in the range 100-120 A it would be good to have the possibility to go up to 150 A during short model tests to check the saturation of the system in terms of heater delays
119875119889=1198682119877119908119871
119877=120588 119871119908119905
119875119889=1198682 1205881199082119905
Heater width19 mm LF 24 mm HFρss=7310-7Ωm RRR=134
bull Distance between heater stations -gt quench propagation in between stations asymp 5 msbull LF 90 mmbull HF 130 mm
bull Coverage maximum coverage keeping the resistance within the allowable limits for a 55 m magnet (depends on the number of power suppliesheater circuits)
Cu
50 90130
192
4
Cu
Click here to add footer 13
Coils size
bull Both coils 101 and 105 were oversized only in the mid-plane
bull Best-fit on the outer diameter and the loading plates (interface with pole)
Click here to add footer 14
Excess in mid-plane
-150 -50 50 20
030
040
050
060
070
080
090
090
011
0012
0013
0014
000
100
200
300
400
500
600
700
800
leftrightaverage
Coil length [mm]
Inte
rfer
ence
[microm
]
Click here to add footer 15
Collaring steps
2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 320
50100150200250300350400
Distance to collaring position right lead endright return endleft lead endleft return end
F [MN]
offs
et k
ey g
roov
e [micro
m]
With 8MN the stoppers of the collaring tool were in contact
Click here to add footer 16
Shimming planbull Mid-plane is 650 microm beyond expectations To compensate
bull One layer of Kapton was removed on the mid-plane
bull Changed one layer of insulation to 005 microm thickness (in lieu of 0125 microm)
Click here to add footer 17
Yoking welding of the shellsF Lackner
1 2 3 4 5 6 7 80
100200300400500600700800
0
110
206
361426
526610
686Pressure rising April 28th 2014
Pressure rising step
Tota
l cha
rge
in to
ns
3154906157901240166520652225
002040608
SIDE B 0110206361426526610686
Length in [mm]
Yoke
gap
[mm
]
Tota
l loa
d in
tons
Max charge 500 tm on central section to close the welding gap
0
02
04
06
SIDE A0110206361426526610686
Length in [mm]
Yoke
gap
[mm
]
Tota
l loa
d in
tons
Click here to add footer 18
Structural analysis vs measurements
Click here to add footer 19
FEA Results 11T Mirror
FEA Max Cap gauge
pressure (MPa)
FEA Avg Cap gauge
pressure (MPa)
FEA Min Cap gauge
pressure (MPa)
Collar nose
stress (MPa)
Coil Min stress (MPa)
Coil Max Stress (MPa)
Avg Shell Stress (MPa)
Collaring Load 48 33 18 88 -7 -90
Post-Collaring 39 28 16 72 -7 -69
Collar in yoke 40 28 17 73 -9 -66
Max Press force 46 31 15 81 -14 -60 10
Shell Weld + Press Force 50 33 14 87 -16 -61 187
Shell Welded no Press Force 48 32 15 85 -15 -60 194
Collaring Load Post-Collaring Collar in yoke Max Press force Shell Weld + Press Force
Shell Welded no Press Force
Shell Welded - 297K
Cool Down (18K)
11-Tesla0
10
20
30
40
50
60Mirror Coil - contact pressure at pole (Cap Gauge)
FEA Max Cap gauge - pressure (MPa)
FEA Avg Cap gauge - pressure (MPa)
FEA Min Cap gauge - pressure (MPa)
Measured Coil Data (10 error bars)
Pres
sure
(MPa
)
Click here to add footer 20
ANSYS Forecast at 11-Tesla
Assembly Step
Max Capacitive gauge -
pressure (MPa)
Avg Capacitive gauge -
pressure (MPa)
Min Capacitive gauge -
pressure (MPa)
Collar-nose stress (MPa)
Coil Min stress (MPa)
Coil Max Stress (MPa)
Avg Shell Stress (MPa)
MirrorCoil
Shell Welded - 297K 48 32 15 85 -15 -60 195
Cool Down (18K) 37 21 5 62 -5 -74 375
11-Tesla 1 05 0 63 +13 -117 377
NominalCoil
Shell Welded - 297K 107 58 8 150 -14 -119 191
Cool Down (18K) 86 43 1 123 -21 -125 373
11-Tesla 22 11 0 57 -4 -120 374
Collar Nose Von-Mises Stress
At 11T
Coil BlocksAzimuthal Stress
At 11T
FEA predicted results
Click here to add footer 21
Bullet gauges loadingM GuinchardP Grosclaude
8 to 9 kN per bullet
Click here to add footer 22
Electrical tests ndash WhenF-O PincotL Grand Cleacutement
Are performed beforeafter each important construction step Test of pole Nb3Sn before curing - PBC Test of pole Nb3Sn before reaction ndash PBR Test of pole Nb3Sn after reaction ndash PAR Test of pole Nb3Sn after impregnation out of the mould ndash PAI Test of pole Nb3Sn after impregnation with instrumentation ndash PAIWI Test of collared coil before collaring ndash BC Test of collared coil after collaring ndash AC Test of the magnet under load before welding ndash UL Test of the magnet after shell welding ndash AW Test of the magnet after longitudinal coil loading ndash AL Test of the magnet after interconnection ndash AI Final Test of the magnet before delivery - FINAL
Click here to add footer 23
Electrical tests ndash WhatF-O PincotL Grand CleacutementAccording to the construction step we define
specific test valueselectrical tests among which
Resistance measurement(Coils Quench heaters Voltage taps Instrumentation) Inductance measurement Capacitance measurement Dielectric measurement(between coils QH instrumentation ground)
bull Insulation (up to 1kV 30s)bull current leakage (up to 1kV 5min)
Discharge test on coilUp to 1kV
Discharge test on quench heatersUp to 900V or 80AQH
Click here to add footer 24
Electrical testsF-O PincotL Grand Cleacutement
Resistance Insulation dielectric Inductance Capacitance Coil discharge QH discharge
Test phase
code
PBC X X X
PBR X X X
PAR X X X
PAI X X X X
PAIWI X X X X
BC X X X X X X
AC X X X X X X
UL X X
AW X X X X X X
AL X X X X X X
AI X X X X X X
FINAL X X X X X X
Click here to add footer 25
Click here to add footer 26
Plan for power tests coldbull RRR and strain gauge measurementsbull Preliminary tests ndash Setup protection ndash Splice resistance
measurements (current plateaus at 2 4 6 8 and 10 kA) ndash 3 hoursbull Training 43 K ndash 15 quenches ndash 3 days bull Training 19 K ndash 10 quenches ndash 25 days
Stability on current plateau ndash 05 daybull Ramp-rate study 100 As and 50 As ndash 05 day
AC-loss measurements (includes inductance measurement) at 5 to 100 As ndash 05 day
bull Quench heater efficiency study 3 different settings of QH pulse for 3 currents each Long re-cooling of the magnet due to delay of energy extraction ndash 3 days
bull High MIIts tests (protection delay) 6 quenches ndash 3 days
bull Quench propagation velocity measurements acquired for the training quenches
G Willeringbull Cool down bull Day 1
bull Day 2-4bull Day 5-7
bull Day 8
bull Day 9-11
bull Day 12-14
Click here to add footer 27
Further actionsbull After cold tests warm magnetic
measurements will be carried out with the two coils connected
bull Model 1 MBHSP101 single aperture with cable OST RRP 108127 for both polesbull Instrumentation of coils 106 and 107 going onbull Collaring scheduled around middle of June
- CERN-FNAL Video Meeting 12 Progress of the 11T Dipole short m
- Contributions
- Main design features
- Specific features
- Assembly conditions - Winding
- Binder curing
- Reaction treatment
- Reaction treatment ndash Coil 105
- Impregnation
- Instrumentation outer layer
- Instrumentation inner layer
- Quench heaters
- Coils size
- Excess in mid-plane
- Collaring steps
- Shimming plan
- Yoking welding of the shells
- Structural analysis vs measurements
- FEA Results
- ANSYS Forecast at 11-Tesla
- Bullet gauges loading
- Electrical tests ndash When
- Electrical tests ndash What
- Electrical tests
- Slide 25
- Plan for power tests cold
- Further actions
-
Click here to add footer 4
Specific featuresbull Copper coil 101
bull End spacers CERN v0 longer coilbull Sc coil 105
bull Cable OST RRP 108127bull ODS alloy wedgesbull CERN V4 end spacers SLS (with flex hinge legs)bull Metallic saddles and splice blocksbull External trace glued on coil OD carrying V-taps and quench
heaters (next slide)bull Collars and yoke laminations produced by EDM
bull Collars YUS130S Nippon Steel 3 mm thickness (LHC dipole)bull Yoke laminations Arcelor Magnetil Low C steel 58 mm
thickness (LHC dipole)
Click here to add footer 5
Assembly conditions - Windingbull Winding tension
bull Coil 101 300 N insulation defects gt1bull Coil 105 250 N insulation defects 0
bull Cable insulationbull Coils 101 and 105
bull Outer sleeve AGY S-2 Glass 11 Tex direct braidingbull Inner dielectric Cogebi Firox 80 microm Mica ndash Fiber glass tape
bull Winding monitoring during coil 105 production
D SmekensJ Mazet
Coils longer than expected ~20 mm
Click here to add footer 6
Binder curingbull Binder CTD 1202-X qty
bull Coil 101 IL in excess OL in excessbull Coil 105 IL 100 g OL 100 g
bull Shimming nominal (shimming such that in the press the mid-plane of the cured coil is like in the magnet 012 mm above center axis)bull This is different compared to FERMILAB where oversized shimming
is used to compact the coil mid-plane beyond its nominal position in order to obtain a smaller coil size before entering into reaction
bull With a load of 08 MN the mold is nearly closed (lt 01mm)bull Then a load of 2 MN is used for IL and 42 MN for the OL
(complete pole)bull The stress in the coils may not exceed 37 MPa at that stage
D SmekensJ Mazet
Click here to add footer 7
Reaction treatmentbull Cavity of the reaction fixture is radially bigger than the curing
mold by 01 mm and of similar dimension at coil mid-planebull Thus if the curing press can be closed before reaching 37
MPa the coil cannot be subjected to higher stress when closing the fixture However the dry fiber glass and the tight tolerances induce large friction also a possible dimensional problem with the sealing foils could have generated interference between the sealing foil and the baseplate preventing correct closure of the fixture
bull The tightening torque to close the fixture was of the order of 300 Nm (FNAL applies 110 Nm to 160 Nm)
bull Not clear no coil contraction after reaction actually less that 1 mm when 45 mm were expected
D SmekensN BourceyF Lackner
Click here to add footer 8
Reaction treatment ndash Coil 105
Adjustment of dwell time to compensate the delay between the
temperature and tooling temperature
The homogeneity of T during ramp up was not very good plusmn
9degCHowever it is OK during
dwell time
N BourceyF Lackner
Click here to add footer 9
Impregnationbull Resin CTD 101K
bull Anhydride cured epoxy system with excellent performance at cryogenic temperature and radiation resistance
bull The resin is preheated and the coil is impregnated at 60degC
bull Curing 110degC for 5 hoursbull Post curing heating 125degC for 16 hours
R GauthierD Smekens
Temperature [degC] Pot life [h] Viscosity [mmmiddotPas]25 145 1300
40 60 400
60 20 100
Click here to add footer 10
Instrumentation outer layer
Outer layer instrumentation incorporated in a Trace which is applied after impregnationThere are 2 ldquoUrdquo shaped SS quench heaters with Cu overlay with Cu masked off to provide heating regions Heater width is 19mm in low-field region with heater regions 90mm apart In the high-field region the heater width is 24mm and the heater regions are 130mm apartThere are 13 voltage taps on the Trace including 6 on the pole turn 1 on the layer jump and 4 on the mid-plane turn
EES5O
I
EE5O12-
+
EES5OO
EE5O11EE5O10
EE5O9
EE5O8 EE5O6EE5O7 EE5O5
EE5O4EE5O3EE5O2
EE5O1
Click here to add footer 11
Instrumentation inner layer
Inner layer instrumentation consists only of voltage taps There are 16 voltage taps including 6 on the pole turn 1 on the layer jump and 4 on the mid-plane turn with other taps adjacent to spacer block edges
S Izquierdo BermudezF-O PincotR Bateman
Click here to add footer 12
Quench heaters
50 70 90 110 130 150 170 19000
200400600800
100012001400160018002000
Low Field Region High Field Region
Heater Current (A)
Pow
er d
ensi
ty (W
cm
2)
Operation area
bull Width -gt Cover as many turns as possible
bull LF 19 mm bull HF 24 mm
bull Power densitybull LF asymp 75 Wcm2
bull HFasymp 55 Wcm2
Even if the operational current is expected to be in the range 100-120 A it would be good to have the possibility to go up to 150 A during short model tests to check the saturation of the system in terms of heater delays
119875119889=1198682119877119908119871
119877=120588 119871119908119905
119875119889=1198682 1205881199082119905
Heater width19 mm LF 24 mm HFρss=7310-7Ωm RRR=134
bull Distance between heater stations -gt quench propagation in between stations asymp 5 msbull LF 90 mmbull HF 130 mm
bull Coverage maximum coverage keeping the resistance within the allowable limits for a 55 m magnet (depends on the number of power suppliesheater circuits)
Cu
50 90130
192
4
Cu
Click here to add footer 13
Coils size
bull Both coils 101 and 105 were oversized only in the mid-plane
bull Best-fit on the outer diameter and the loading plates (interface with pole)
Click here to add footer 14
Excess in mid-plane
-150 -50 50 20
030
040
050
060
070
080
090
090
011
0012
0013
0014
000
100
200
300
400
500
600
700
800
leftrightaverage
Coil length [mm]
Inte
rfer
ence
[microm
]
Click here to add footer 15
Collaring steps
2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 320
50100150200250300350400
Distance to collaring position right lead endright return endleft lead endleft return end
F [MN]
offs
et k
ey g
roov
e [micro
m]
With 8MN the stoppers of the collaring tool were in contact
Click here to add footer 16
Shimming planbull Mid-plane is 650 microm beyond expectations To compensate
bull One layer of Kapton was removed on the mid-plane
bull Changed one layer of insulation to 005 microm thickness (in lieu of 0125 microm)
Click here to add footer 17
Yoking welding of the shellsF Lackner
1 2 3 4 5 6 7 80
100200300400500600700800
0
110
206
361426
526610
686Pressure rising April 28th 2014
Pressure rising step
Tota
l cha
rge
in to
ns
3154906157901240166520652225
002040608
SIDE B 0110206361426526610686
Length in [mm]
Yoke
gap
[mm
]
Tota
l loa
d in
tons
Max charge 500 tm on central section to close the welding gap
0
02
04
06
SIDE A0110206361426526610686
Length in [mm]
Yoke
gap
[mm
]
Tota
l loa
d in
tons
Click here to add footer 18
Structural analysis vs measurements
Click here to add footer 19
FEA Results 11T Mirror
FEA Max Cap gauge
pressure (MPa)
FEA Avg Cap gauge
pressure (MPa)
FEA Min Cap gauge
pressure (MPa)
Collar nose
stress (MPa)
Coil Min stress (MPa)
Coil Max Stress (MPa)
Avg Shell Stress (MPa)
Collaring Load 48 33 18 88 -7 -90
Post-Collaring 39 28 16 72 -7 -69
Collar in yoke 40 28 17 73 -9 -66
Max Press force 46 31 15 81 -14 -60 10
Shell Weld + Press Force 50 33 14 87 -16 -61 187
Shell Welded no Press Force 48 32 15 85 -15 -60 194
Collaring Load Post-Collaring Collar in yoke Max Press force Shell Weld + Press Force
Shell Welded no Press Force
Shell Welded - 297K
Cool Down (18K)
11-Tesla0
10
20
30
40
50
60Mirror Coil - contact pressure at pole (Cap Gauge)
FEA Max Cap gauge - pressure (MPa)
FEA Avg Cap gauge - pressure (MPa)
FEA Min Cap gauge - pressure (MPa)
Measured Coil Data (10 error bars)
Pres
sure
(MPa
)
Click here to add footer 20
ANSYS Forecast at 11-Tesla
Assembly Step
Max Capacitive gauge -
pressure (MPa)
Avg Capacitive gauge -
pressure (MPa)
Min Capacitive gauge -
pressure (MPa)
Collar-nose stress (MPa)
Coil Min stress (MPa)
Coil Max Stress (MPa)
Avg Shell Stress (MPa)
MirrorCoil
Shell Welded - 297K 48 32 15 85 -15 -60 195
Cool Down (18K) 37 21 5 62 -5 -74 375
11-Tesla 1 05 0 63 +13 -117 377
NominalCoil
Shell Welded - 297K 107 58 8 150 -14 -119 191
Cool Down (18K) 86 43 1 123 -21 -125 373
11-Tesla 22 11 0 57 -4 -120 374
Collar Nose Von-Mises Stress
At 11T
Coil BlocksAzimuthal Stress
At 11T
FEA predicted results
Click here to add footer 21
Bullet gauges loadingM GuinchardP Grosclaude
8 to 9 kN per bullet
Click here to add footer 22
Electrical tests ndash WhenF-O PincotL Grand Cleacutement
Are performed beforeafter each important construction step Test of pole Nb3Sn before curing - PBC Test of pole Nb3Sn before reaction ndash PBR Test of pole Nb3Sn after reaction ndash PAR Test of pole Nb3Sn after impregnation out of the mould ndash PAI Test of pole Nb3Sn after impregnation with instrumentation ndash PAIWI Test of collared coil before collaring ndash BC Test of collared coil after collaring ndash AC Test of the magnet under load before welding ndash UL Test of the magnet after shell welding ndash AW Test of the magnet after longitudinal coil loading ndash AL Test of the magnet after interconnection ndash AI Final Test of the magnet before delivery - FINAL
Click here to add footer 23
Electrical tests ndash WhatF-O PincotL Grand CleacutementAccording to the construction step we define
specific test valueselectrical tests among which
Resistance measurement(Coils Quench heaters Voltage taps Instrumentation) Inductance measurement Capacitance measurement Dielectric measurement(between coils QH instrumentation ground)
bull Insulation (up to 1kV 30s)bull current leakage (up to 1kV 5min)
Discharge test on coilUp to 1kV
Discharge test on quench heatersUp to 900V or 80AQH
Click here to add footer 24
Electrical testsF-O PincotL Grand Cleacutement
Resistance Insulation dielectric Inductance Capacitance Coil discharge QH discharge
Test phase
code
PBC X X X
PBR X X X
PAR X X X
PAI X X X X
PAIWI X X X X
BC X X X X X X
AC X X X X X X
UL X X
AW X X X X X X
AL X X X X X X
AI X X X X X X
FINAL X X X X X X
Click here to add footer 25
Click here to add footer 26
Plan for power tests coldbull RRR and strain gauge measurementsbull Preliminary tests ndash Setup protection ndash Splice resistance
measurements (current plateaus at 2 4 6 8 and 10 kA) ndash 3 hoursbull Training 43 K ndash 15 quenches ndash 3 days bull Training 19 K ndash 10 quenches ndash 25 days
Stability on current plateau ndash 05 daybull Ramp-rate study 100 As and 50 As ndash 05 day
AC-loss measurements (includes inductance measurement) at 5 to 100 As ndash 05 day
bull Quench heater efficiency study 3 different settings of QH pulse for 3 currents each Long re-cooling of the magnet due to delay of energy extraction ndash 3 days
bull High MIIts tests (protection delay) 6 quenches ndash 3 days
bull Quench propagation velocity measurements acquired for the training quenches
G Willeringbull Cool down bull Day 1
bull Day 2-4bull Day 5-7
bull Day 8
bull Day 9-11
bull Day 12-14
Click here to add footer 27
Further actionsbull After cold tests warm magnetic
measurements will be carried out with the two coils connected
bull Model 1 MBHSP101 single aperture with cable OST RRP 108127 for both polesbull Instrumentation of coils 106 and 107 going onbull Collaring scheduled around middle of June
- CERN-FNAL Video Meeting 12 Progress of the 11T Dipole short m
- Contributions
- Main design features
- Specific features
- Assembly conditions - Winding
- Binder curing
- Reaction treatment
- Reaction treatment ndash Coil 105
- Impregnation
- Instrumentation outer layer
- Instrumentation inner layer
- Quench heaters
- Coils size
- Excess in mid-plane
- Collaring steps
- Shimming plan
- Yoking welding of the shells
- Structural analysis vs measurements
- FEA Results
- ANSYS Forecast at 11-Tesla
- Bullet gauges loading
- Electrical tests ndash When
- Electrical tests ndash What
- Electrical tests
- Slide 25
- Plan for power tests cold
- Further actions
-
Click here to add footer 5
Assembly conditions - Windingbull Winding tension
bull Coil 101 300 N insulation defects gt1bull Coil 105 250 N insulation defects 0
bull Cable insulationbull Coils 101 and 105
bull Outer sleeve AGY S-2 Glass 11 Tex direct braidingbull Inner dielectric Cogebi Firox 80 microm Mica ndash Fiber glass tape
bull Winding monitoring during coil 105 production
D SmekensJ Mazet
Coils longer than expected ~20 mm
Click here to add footer 6
Binder curingbull Binder CTD 1202-X qty
bull Coil 101 IL in excess OL in excessbull Coil 105 IL 100 g OL 100 g
bull Shimming nominal (shimming such that in the press the mid-plane of the cured coil is like in the magnet 012 mm above center axis)bull This is different compared to FERMILAB where oversized shimming
is used to compact the coil mid-plane beyond its nominal position in order to obtain a smaller coil size before entering into reaction
bull With a load of 08 MN the mold is nearly closed (lt 01mm)bull Then a load of 2 MN is used for IL and 42 MN for the OL
(complete pole)bull The stress in the coils may not exceed 37 MPa at that stage
D SmekensJ Mazet
Click here to add footer 7
Reaction treatmentbull Cavity of the reaction fixture is radially bigger than the curing
mold by 01 mm and of similar dimension at coil mid-planebull Thus if the curing press can be closed before reaching 37
MPa the coil cannot be subjected to higher stress when closing the fixture However the dry fiber glass and the tight tolerances induce large friction also a possible dimensional problem with the sealing foils could have generated interference between the sealing foil and the baseplate preventing correct closure of the fixture
bull The tightening torque to close the fixture was of the order of 300 Nm (FNAL applies 110 Nm to 160 Nm)
bull Not clear no coil contraction after reaction actually less that 1 mm when 45 mm were expected
D SmekensN BourceyF Lackner
Click here to add footer 8
Reaction treatment ndash Coil 105
Adjustment of dwell time to compensate the delay between the
temperature and tooling temperature
The homogeneity of T during ramp up was not very good plusmn
9degCHowever it is OK during
dwell time
N BourceyF Lackner
Click here to add footer 9
Impregnationbull Resin CTD 101K
bull Anhydride cured epoxy system with excellent performance at cryogenic temperature and radiation resistance
bull The resin is preheated and the coil is impregnated at 60degC
bull Curing 110degC for 5 hoursbull Post curing heating 125degC for 16 hours
R GauthierD Smekens
Temperature [degC] Pot life [h] Viscosity [mmmiddotPas]25 145 1300
40 60 400
60 20 100
Click here to add footer 10
Instrumentation outer layer
Outer layer instrumentation incorporated in a Trace which is applied after impregnationThere are 2 ldquoUrdquo shaped SS quench heaters with Cu overlay with Cu masked off to provide heating regions Heater width is 19mm in low-field region with heater regions 90mm apart In the high-field region the heater width is 24mm and the heater regions are 130mm apartThere are 13 voltage taps on the Trace including 6 on the pole turn 1 on the layer jump and 4 on the mid-plane turn
EES5O
I
EE5O12-
+
EES5OO
EE5O11EE5O10
EE5O9
EE5O8 EE5O6EE5O7 EE5O5
EE5O4EE5O3EE5O2
EE5O1
Click here to add footer 11
Instrumentation inner layer
Inner layer instrumentation consists only of voltage taps There are 16 voltage taps including 6 on the pole turn 1 on the layer jump and 4 on the mid-plane turn with other taps adjacent to spacer block edges
S Izquierdo BermudezF-O PincotR Bateman
Click here to add footer 12
Quench heaters
50 70 90 110 130 150 170 19000
200400600800
100012001400160018002000
Low Field Region High Field Region
Heater Current (A)
Pow
er d
ensi
ty (W
cm
2)
Operation area
bull Width -gt Cover as many turns as possible
bull LF 19 mm bull HF 24 mm
bull Power densitybull LF asymp 75 Wcm2
bull HFasymp 55 Wcm2
Even if the operational current is expected to be in the range 100-120 A it would be good to have the possibility to go up to 150 A during short model tests to check the saturation of the system in terms of heater delays
119875119889=1198682119877119908119871
119877=120588 119871119908119905
119875119889=1198682 1205881199082119905
Heater width19 mm LF 24 mm HFρss=7310-7Ωm RRR=134
bull Distance between heater stations -gt quench propagation in between stations asymp 5 msbull LF 90 mmbull HF 130 mm
bull Coverage maximum coverage keeping the resistance within the allowable limits for a 55 m magnet (depends on the number of power suppliesheater circuits)
Cu
50 90130
192
4
Cu
Click here to add footer 13
Coils size
bull Both coils 101 and 105 were oversized only in the mid-plane
bull Best-fit on the outer diameter and the loading plates (interface with pole)
Click here to add footer 14
Excess in mid-plane
-150 -50 50 20
030
040
050
060
070
080
090
090
011
0012
0013
0014
000
100
200
300
400
500
600
700
800
leftrightaverage
Coil length [mm]
Inte
rfer
ence
[microm
]
Click here to add footer 15
Collaring steps
2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 320
50100150200250300350400
Distance to collaring position right lead endright return endleft lead endleft return end
F [MN]
offs
et k
ey g
roov
e [micro
m]
With 8MN the stoppers of the collaring tool were in contact
Click here to add footer 16
Shimming planbull Mid-plane is 650 microm beyond expectations To compensate
bull One layer of Kapton was removed on the mid-plane
bull Changed one layer of insulation to 005 microm thickness (in lieu of 0125 microm)
Click here to add footer 17
Yoking welding of the shellsF Lackner
1 2 3 4 5 6 7 80
100200300400500600700800
0
110
206
361426
526610
686Pressure rising April 28th 2014
Pressure rising step
Tota
l cha
rge
in to
ns
3154906157901240166520652225
002040608
SIDE B 0110206361426526610686
Length in [mm]
Yoke
gap
[mm
]
Tota
l loa
d in
tons
Max charge 500 tm on central section to close the welding gap
0
02
04
06
SIDE A0110206361426526610686
Length in [mm]
Yoke
gap
[mm
]
Tota
l loa
d in
tons
Click here to add footer 18
Structural analysis vs measurements
Click here to add footer 19
FEA Results 11T Mirror
FEA Max Cap gauge
pressure (MPa)
FEA Avg Cap gauge
pressure (MPa)
FEA Min Cap gauge
pressure (MPa)
Collar nose
stress (MPa)
Coil Min stress (MPa)
Coil Max Stress (MPa)
Avg Shell Stress (MPa)
Collaring Load 48 33 18 88 -7 -90
Post-Collaring 39 28 16 72 -7 -69
Collar in yoke 40 28 17 73 -9 -66
Max Press force 46 31 15 81 -14 -60 10
Shell Weld + Press Force 50 33 14 87 -16 -61 187
Shell Welded no Press Force 48 32 15 85 -15 -60 194
Collaring Load Post-Collaring Collar in yoke Max Press force Shell Weld + Press Force
Shell Welded no Press Force
Shell Welded - 297K
Cool Down (18K)
11-Tesla0
10
20
30
40
50
60Mirror Coil - contact pressure at pole (Cap Gauge)
FEA Max Cap gauge - pressure (MPa)
FEA Avg Cap gauge - pressure (MPa)
FEA Min Cap gauge - pressure (MPa)
Measured Coil Data (10 error bars)
Pres
sure
(MPa
)
Click here to add footer 20
ANSYS Forecast at 11-Tesla
Assembly Step
Max Capacitive gauge -
pressure (MPa)
Avg Capacitive gauge -
pressure (MPa)
Min Capacitive gauge -
pressure (MPa)
Collar-nose stress (MPa)
Coil Min stress (MPa)
Coil Max Stress (MPa)
Avg Shell Stress (MPa)
MirrorCoil
Shell Welded - 297K 48 32 15 85 -15 -60 195
Cool Down (18K) 37 21 5 62 -5 -74 375
11-Tesla 1 05 0 63 +13 -117 377
NominalCoil
Shell Welded - 297K 107 58 8 150 -14 -119 191
Cool Down (18K) 86 43 1 123 -21 -125 373
11-Tesla 22 11 0 57 -4 -120 374
Collar Nose Von-Mises Stress
At 11T
Coil BlocksAzimuthal Stress
At 11T
FEA predicted results
Click here to add footer 21
Bullet gauges loadingM GuinchardP Grosclaude
8 to 9 kN per bullet
Click here to add footer 22
Electrical tests ndash WhenF-O PincotL Grand Cleacutement
Are performed beforeafter each important construction step Test of pole Nb3Sn before curing - PBC Test of pole Nb3Sn before reaction ndash PBR Test of pole Nb3Sn after reaction ndash PAR Test of pole Nb3Sn after impregnation out of the mould ndash PAI Test of pole Nb3Sn after impregnation with instrumentation ndash PAIWI Test of collared coil before collaring ndash BC Test of collared coil after collaring ndash AC Test of the magnet under load before welding ndash UL Test of the magnet after shell welding ndash AW Test of the magnet after longitudinal coil loading ndash AL Test of the magnet after interconnection ndash AI Final Test of the magnet before delivery - FINAL
Click here to add footer 23
Electrical tests ndash WhatF-O PincotL Grand CleacutementAccording to the construction step we define
specific test valueselectrical tests among which
Resistance measurement(Coils Quench heaters Voltage taps Instrumentation) Inductance measurement Capacitance measurement Dielectric measurement(between coils QH instrumentation ground)
bull Insulation (up to 1kV 30s)bull current leakage (up to 1kV 5min)
Discharge test on coilUp to 1kV
Discharge test on quench heatersUp to 900V or 80AQH
Click here to add footer 24
Electrical testsF-O PincotL Grand Cleacutement
Resistance Insulation dielectric Inductance Capacitance Coil discharge QH discharge
Test phase
code
PBC X X X
PBR X X X
PAR X X X
PAI X X X X
PAIWI X X X X
BC X X X X X X
AC X X X X X X
UL X X
AW X X X X X X
AL X X X X X X
AI X X X X X X
FINAL X X X X X X
Click here to add footer 25
Click here to add footer 26
Plan for power tests coldbull RRR and strain gauge measurementsbull Preliminary tests ndash Setup protection ndash Splice resistance
measurements (current plateaus at 2 4 6 8 and 10 kA) ndash 3 hoursbull Training 43 K ndash 15 quenches ndash 3 days bull Training 19 K ndash 10 quenches ndash 25 days
Stability on current plateau ndash 05 daybull Ramp-rate study 100 As and 50 As ndash 05 day
AC-loss measurements (includes inductance measurement) at 5 to 100 As ndash 05 day
bull Quench heater efficiency study 3 different settings of QH pulse for 3 currents each Long re-cooling of the magnet due to delay of energy extraction ndash 3 days
bull High MIIts tests (protection delay) 6 quenches ndash 3 days
bull Quench propagation velocity measurements acquired for the training quenches
G Willeringbull Cool down bull Day 1
bull Day 2-4bull Day 5-7
bull Day 8
bull Day 9-11
bull Day 12-14
Click here to add footer 27
Further actionsbull After cold tests warm magnetic
measurements will be carried out with the two coils connected
bull Model 1 MBHSP101 single aperture with cable OST RRP 108127 for both polesbull Instrumentation of coils 106 and 107 going onbull Collaring scheduled around middle of June
- CERN-FNAL Video Meeting 12 Progress of the 11T Dipole short m
- Contributions
- Main design features
- Specific features
- Assembly conditions - Winding
- Binder curing
- Reaction treatment
- Reaction treatment ndash Coil 105
- Impregnation
- Instrumentation outer layer
- Instrumentation inner layer
- Quench heaters
- Coils size
- Excess in mid-plane
- Collaring steps
- Shimming plan
- Yoking welding of the shells
- Structural analysis vs measurements
- FEA Results
- ANSYS Forecast at 11-Tesla
- Bullet gauges loading
- Electrical tests ndash When
- Electrical tests ndash What
- Electrical tests
- Slide 25
- Plan for power tests cold
- Further actions
-
Click here to add footer 6
Binder curingbull Binder CTD 1202-X qty
bull Coil 101 IL in excess OL in excessbull Coil 105 IL 100 g OL 100 g
bull Shimming nominal (shimming such that in the press the mid-plane of the cured coil is like in the magnet 012 mm above center axis)bull This is different compared to FERMILAB where oversized shimming
is used to compact the coil mid-plane beyond its nominal position in order to obtain a smaller coil size before entering into reaction
bull With a load of 08 MN the mold is nearly closed (lt 01mm)bull Then a load of 2 MN is used for IL and 42 MN for the OL
(complete pole)bull The stress in the coils may not exceed 37 MPa at that stage
D SmekensJ Mazet
Click here to add footer 7
Reaction treatmentbull Cavity of the reaction fixture is radially bigger than the curing
mold by 01 mm and of similar dimension at coil mid-planebull Thus if the curing press can be closed before reaching 37
MPa the coil cannot be subjected to higher stress when closing the fixture However the dry fiber glass and the tight tolerances induce large friction also a possible dimensional problem with the sealing foils could have generated interference between the sealing foil and the baseplate preventing correct closure of the fixture
bull The tightening torque to close the fixture was of the order of 300 Nm (FNAL applies 110 Nm to 160 Nm)
bull Not clear no coil contraction after reaction actually less that 1 mm when 45 mm were expected
D SmekensN BourceyF Lackner
Click here to add footer 8
Reaction treatment ndash Coil 105
Adjustment of dwell time to compensate the delay between the
temperature and tooling temperature
The homogeneity of T during ramp up was not very good plusmn
9degCHowever it is OK during
dwell time
N BourceyF Lackner
Click here to add footer 9
Impregnationbull Resin CTD 101K
bull Anhydride cured epoxy system with excellent performance at cryogenic temperature and radiation resistance
bull The resin is preheated and the coil is impregnated at 60degC
bull Curing 110degC for 5 hoursbull Post curing heating 125degC for 16 hours
R GauthierD Smekens
Temperature [degC] Pot life [h] Viscosity [mmmiddotPas]25 145 1300
40 60 400
60 20 100
Click here to add footer 10
Instrumentation outer layer
Outer layer instrumentation incorporated in a Trace which is applied after impregnationThere are 2 ldquoUrdquo shaped SS quench heaters with Cu overlay with Cu masked off to provide heating regions Heater width is 19mm in low-field region with heater regions 90mm apart In the high-field region the heater width is 24mm and the heater regions are 130mm apartThere are 13 voltage taps on the Trace including 6 on the pole turn 1 on the layer jump and 4 on the mid-plane turn
EES5O
I
EE5O12-
+
EES5OO
EE5O11EE5O10
EE5O9
EE5O8 EE5O6EE5O7 EE5O5
EE5O4EE5O3EE5O2
EE5O1
Click here to add footer 11
Instrumentation inner layer
Inner layer instrumentation consists only of voltage taps There are 16 voltage taps including 6 on the pole turn 1 on the layer jump and 4 on the mid-plane turn with other taps adjacent to spacer block edges
S Izquierdo BermudezF-O PincotR Bateman
Click here to add footer 12
Quench heaters
50 70 90 110 130 150 170 19000
200400600800
100012001400160018002000
Low Field Region High Field Region
Heater Current (A)
Pow
er d
ensi
ty (W
cm
2)
Operation area
bull Width -gt Cover as many turns as possible
bull LF 19 mm bull HF 24 mm
bull Power densitybull LF asymp 75 Wcm2
bull HFasymp 55 Wcm2
Even if the operational current is expected to be in the range 100-120 A it would be good to have the possibility to go up to 150 A during short model tests to check the saturation of the system in terms of heater delays
119875119889=1198682119877119908119871
119877=120588 119871119908119905
119875119889=1198682 1205881199082119905
Heater width19 mm LF 24 mm HFρss=7310-7Ωm RRR=134
bull Distance between heater stations -gt quench propagation in between stations asymp 5 msbull LF 90 mmbull HF 130 mm
bull Coverage maximum coverage keeping the resistance within the allowable limits for a 55 m magnet (depends on the number of power suppliesheater circuits)
Cu
50 90130
192
4
Cu
Click here to add footer 13
Coils size
bull Both coils 101 and 105 were oversized only in the mid-plane
bull Best-fit on the outer diameter and the loading plates (interface with pole)
Click here to add footer 14
Excess in mid-plane
-150 -50 50 20
030
040
050
060
070
080
090
090
011
0012
0013
0014
000
100
200
300
400
500
600
700
800
leftrightaverage
Coil length [mm]
Inte
rfer
ence
[microm
]
Click here to add footer 15
Collaring steps
2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 320
50100150200250300350400
Distance to collaring position right lead endright return endleft lead endleft return end
F [MN]
offs
et k
ey g
roov
e [micro
m]
With 8MN the stoppers of the collaring tool were in contact
Click here to add footer 16
Shimming planbull Mid-plane is 650 microm beyond expectations To compensate
bull One layer of Kapton was removed on the mid-plane
bull Changed one layer of insulation to 005 microm thickness (in lieu of 0125 microm)
Click here to add footer 17
Yoking welding of the shellsF Lackner
1 2 3 4 5 6 7 80
100200300400500600700800
0
110
206
361426
526610
686Pressure rising April 28th 2014
Pressure rising step
Tota
l cha
rge
in to
ns
3154906157901240166520652225
002040608
SIDE B 0110206361426526610686
Length in [mm]
Yoke
gap
[mm
]
Tota
l loa
d in
tons
Max charge 500 tm on central section to close the welding gap
0
02
04
06
SIDE A0110206361426526610686
Length in [mm]
Yoke
gap
[mm
]
Tota
l loa
d in
tons
Click here to add footer 18
Structural analysis vs measurements
Click here to add footer 19
FEA Results 11T Mirror
FEA Max Cap gauge
pressure (MPa)
FEA Avg Cap gauge
pressure (MPa)
FEA Min Cap gauge
pressure (MPa)
Collar nose
stress (MPa)
Coil Min stress (MPa)
Coil Max Stress (MPa)
Avg Shell Stress (MPa)
Collaring Load 48 33 18 88 -7 -90
Post-Collaring 39 28 16 72 -7 -69
Collar in yoke 40 28 17 73 -9 -66
Max Press force 46 31 15 81 -14 -60 10
Shell Weld + Press Force 50 33 14 87 -16 -61 187
Shell Welded no Press Force 48 32 15 85 -15 -60 194
Collaring Load Post-Collaring Collar in yoke Max Press force Shell Weld + Press Force
Shell Welded no Press Force
Shell Welded - 297K
Cool Down (18K)
11-Tesla0
10
20
30
40
50
60Mirror Coil - contact pressure at pole (Cap Gauge)
FEA Max Cap gauge - pressure (MPa)
FEA Avg Cap gauge - pressure (MPa)
FEA Min Cap gauge - pressure (MPa)
Measured Coil Data (10 error bars)
Pres
sure
(MPa
)
Click here to add footer 20
ANSYS Forecast at 11-Tesla
Assembly Step
Max Capacitive gauge -
pressure (MPa)
Avg Capacitive gauge -
pressure (MPa)
Min Capacitive gauge -
pressure (MPa)
Collar-nose stress (MPa)
Coil Min stress (MPa)
Coil Max Stress (MPa)
Avg Shell Stress (MPa)
MirrorCoil
Shell Welded - 297K 48 32 15 85 -15 -60 195
Cool Down (18K) 37 21 5 62 -5 -74 375
11-Tesla 1 05 0 63 +13 -117 377
NominalCoil
Shell Welded - 297K 107 58 8 150 -14 -119 191
Cool Down (18K) 86 43 1 123 -21 -125 373
11-Tesla 22 11 0 57 -4 -120 374
Collar Nose Von-Mises Stress
At 11T
Coil BlocksAzimuthal Stress
At 11T
FEA predicted results
Click here to add footer 21
Bullet gauges loadingM GuinchardP Grosclaude
8 to 9 kN per bullet
Click here to add footer 22
Electrical tests ndash WhenF-O PincotL Grand Cleacutement
Are performed beforeafter each important construction step Test of pole Nb3Sn before curing - PBC Test of pole Nb3Sn before reaction ndash PBR Test of pole Nb3Sn after reaction ndash PAR Test of pole Nb3Sn after impregnation out of the mould ndash PAI Test of pole Nb3Sn after impregnation with instrumentation ndash PAIWI Test of collared coil before collaring ndash BC Test of collared coil after collaring ndash AC Test of the magnet under load before welding ndash UL Test of the magnet after shell welding ndash AW Test of the magnet after longitudinal coil loading ndash AL Test of the magnet after interconnection ndash AI Final Test of the magnet before delivery - FINAL
Click here to add footer 23
Electrical tests ndash WhatF-O PincotL Grand CleacutementAccording to the construction step we define
specific test valueselectrical tests among which
Resistance measurement(Coils Quench heaters Voltage taps Instrumentation) Inductance measurement Capacitance measurement Dielectric measurement(between coils QH instrumentation ground)
bull Insulation (up to 1kV 30s)bull current leakage (up to 1kV 5min)
Discharge test on coilUp to 1kV
Discharge test on quench heatersUp to 900V or 80AQH
Click here to add footer 24
Electrical testsF-O PincotL Grand Cleacutement
Resistance Insulation dielectric Inductance Capacitance Coil discharge QH discharge
Test phase
code
PBC X X X
PBR X X X
PAR X X X
PAI X X X X
PAIWI X X X X
BC X X X X X X
AC X X X X X X
UL X X
AW X X X X X X
AL X X X X X X
AI X X X X X X
FINAL X X X X X X
Click here to add footer 25
Click here to add footer 26
Plan for power tests coldbull RRR and strain gauge measurementsbull Preliminary tests ndash Setup protection ndash Splice resistance
measurements (current plateaus at 2 4 6 8 and 10 kA) ndash 3 hoursbull Training 43 K ndash 15 quenches ndash 3 days bull Training 19 K ndash 10 quenches ndash 25 days
Stability on current plateau ndash 05 daybull Ramp-rate study 100 As and 50 As ndash 05 day
AC-loss measurements (includes inductance measurement) at 5 to 100 As ndash 05 day
bull Quench heater efficiency study 3 different settings of QH pulse for 3 currents each Long re-cooling of the magnet due to delay of energy extraction ndash 3 days
bull High MIIts tests (protection delay) 6 quenches ndash 3 days
bull Quench propagation velocity measurements acquired for the training quenches
G Willeringbull Cool down bull Day 1
bull Day 2-4bull Day 5-7
bull Day 8
bull Day 9-11
bull Day 12-14
Click here to add footer 27
Further actionsbull After cold tests warm magnetic
measurements will be carried out with the two coils connected
bull Model 1 MBHSP101 single aperture with cable OST RRP 108127 for both polesbull Instrumentation of coils 106 and 107 going onbull Collaring scheduled around middle of June
- CERN-FNAL Video Meeting 12 Progress of the 11T Dipole short m
- Contributions
- Main design features
- Specific features
- Assembly conditions - Winding
- Binder curing
- Reaction treatment
- Reaction treatment ndash Coil 105
- Impregnation
- Instrumentation outer layer
- Instrumentation inner layer
- Quench heaters
- Coils size
- Excess in mid-plane
- Collaring steps
- Shimming plan
- Yoking welding of the shells
- Structural analysis vs measurements
- FEA Results
- ANSYS Forecast at 11-Tesla
- Bullet gauges loading
- Electrical tests ndash When
- Electrical tests ndash What
- Electrical tests
- Slide 25
- Plan for power tests cold
- Further actions
-
Click here to add footer 7
Reaction treatmentbull Cavity of the reaction fixture is radially bigger than the curing
mold by 01 mm and of similar dimension at coil mid-planebull Thus if the curing press can be closed before reaching 37
MPa the coil cannot be subjected to higher stress when closing the fixture However the dry fiber glass and the tight tolerances induce large friction also a possible dimensional problem with the sealing foils could have generated interference between the sealing foil and the baseplate preventing correct closure of the fixture
bull The tightening torque to close the fixture was of the order of 300 Nm (FNAL applies 110 Nm to 160 Nm)
bull Not clear no coil contraction after reaction actually less that 1 mm when 45 mm were expected
D SmekensN BourceyF Lackner
Click here to add footer 8
Reaction treatment ndash Coil 105
Adjustment of dwell time to compensate the delay between the
temperature and tooling temperature
The homogeneity of T during ramp up was not very good plusmn
9degCHowever it is OK during
dwell time
N BourceyF Lackner
Click here to add footer 9
Impregnationbull Resin CTD 101K
bull Anhydride cured epoxy system with excellent performance at cryogenic temperature and radiation resistance
bull The resin is preheated and the coil is impregnated at 60degC
bull Curing 110degC for 5 hoursbull Post curing heating 125degC for 16 hours
R GauthierD Smekens
Temperature [degC] Pot life [h] Viscosity [mmmiddotPas]25 145 1300
40 60 400
60 20 100
Click here to add footer 10
Instrumentation outer layer
Outer layer instrumentation incorporated in a Trace which is applied after impregnationThere are 2 ldquoUrdquo shaped SS quench heaters with Cu overlay with Cu masked off to provide heating regions Heater width is 19mm in low-field region with heater regions 90mm apart In the high-field region the heater width is 24mm and the heater regions are 130mm apartThere are 13 voltage taps on the Trace including 6 on the pole turn 1 on the layer jump and 4 on the mid-plane turn
EES5O
I
EE5O12-
+
EES5OO
EE5O11EE5O10
EE5O9
EE5O8 EE5O6EE5O7 EE5O5
EE5O4EE5O3EE5O2
EE5O1
Click here to add footer 11
Instrumentation inner layer
Inner layer instrumentation consists only of voltage taps There are 16 voltage taps including 6 on the pole turn 1 on the layer jump and 4 on the mid-plane turn with other taps adjacent to spacer block edges
S Izquierdo BermudezF-O PincotR Bateman
Click here to add footer 12
Quench heaters
50 70 90 110 130 150 170 19000
200400600800
100012001400160018002000
Low Field Region High Field Region
Heater Current (A)
Pow
er d
ensi
ty (W
cm
2)
Operation area
bull Width -gt Cover as many turns as possible
bull LF 19 mm bull HF 24 mm
bull Power densitybull LF asymp 75 Wcm2
bull HFasymp 55 Wcm2
Even if the operational current is expected to be in the range 100-120 A it would be good to have the possibility to go up to 150 A during short model tests to check the saturation of the system in terms of heater delays
119875119889=1198682119877119908119871
119877=120588 119871119908119905
119875119889=1198682 1205881199082119905
Heater width19 mm LF 24 mm HFρss=7310-7Ωm RRR=134
bull Distance between heater stations -gt quench propagation in between stations asymp 5 msbull LF 90 mmbull HF 130 mm
bull Coverage maximum coverage keeping the resistance within the allowable limits for a 55 m magnet (depends on the number of power suppliesheater circuits)
Cu
50 90130
192
4
Cu
Click here to add footer 13
Coils size
bull Both coils 101 and 105 were oversized only in the mid-plane
bull Best-fit on the outer diameter and the loading plates (interface with pole)
Click here to add footer 14
Excess in mid-plane
-150 -50 50 20
030
040
050
060
070
080
090
090
011
0012
0013
0014
000
100
200
300
400
500
600
700
800
leftrightaverage
Coil length [mm]
Inte
rfer
ence
[microm
]
Click here to add footer 15
Collaring steps
2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 320
50100150200250300350400
Distance to collaring position right lead endright return endleft lead endleft return end
F [MN]
offs
et k
ey g
roov
e [micro
m]
With 8MN the stoppers of the collaring tool were in contact
Click here to add footer 16
Shimming planbull Mid-plane is 650 microm beyond expectations To compensate
bull One layer of Kapton was removed on the mid-plane
bull Changed one layer of insulation to 005 microm thickness (in lieu of 0125 microm)
Click here to add footer 17
Yoking welding of the shellsF Lackner
1 2 3 4 5 6 7 80
100200300400500600700800
0
110
206
361426
526610
686Pressure rising April 28th 2014
Pressure rising step
Tota
l cha
rge
in to
ns
3154906157901240166520652225
002040608
SIDE B 0110206361426526610686
Length in [mm]
Yoke
gap
[mm
]
Tota
l loa
d in
tons
Max charge 500 tm on central section to close the welding gap
0
02
04
06
SIDE A0110206361426526610686
Length in [mm]
Yoke
gap
[mm
]
Tota
l loa
d in
tons
Click here to add footer 18
Structural analysis vs measurements
Click here to add footer 19
FEA Results 11T Mirror
FEA Max Cap gauge
pressure (MPa)
FEA Avg Cap gauge
pressure (MPa)
FEA Min Cap gauge
pressure (MPa)
Collar nose
stress (MPa)
Coil Min stress (MPa)
Coil Max Stress (MPa)
Avg Shell Stress (MPa)
Collaring Load 48 33 18 88 -7 -90
Post-Collaring 39 28 16 72 -7 -69
Collar in yoke 40 28 17 73 -9 -66
Max Press force 46 31 15 81 -14 -60 10
Shell Weld + Press Force 50 33 14 87 -16 -61 187
Shell Welded no Press Force 48 32 15 85 -15 -60 194
Collaring Load Post-Collaring Collar in yoke Max Press force Shell Weld + Press Force
Shell Welded no Press Force
Shell Welded - 297K
Cool Down (18K)
11-Tesla0
10
20
30
40
50
60Mirror Coil - contact pressure at pole (Cap Gauge)
FEA Max Cap gauge - pressure (MPa)
FEA Avg Cap gauge - pressure (MPa)
FEA Min Cap gauge - pressure (MPa)
Measured Coil Data (10 error bars)
Pres
sure
(MPa
)
Click here to add footer 20
ANSYS Forecast at 11-Tesla
Assembly Step
Max Capacitive gauge -
pressure (MPa)
Avg Capacitive gauge -
pressure (MPa)
Min Capacitive gauge -
pressure (MPa)
Collar-nose stress (MPa)
Coil Min stress (MPa)
Coil Max Stress (MPa)
Avg Shell Stress (MPa)
MirrorCoil
Shell Welded - 297K 48 32 15 85 -15 -60 195
Cool Down (18K) 37 21 5 62 -5 -74 375
11-Tesla 1 05 0 63 +13 -117 377
NominalCoil
Shell Welded - 297K 107 58 8 150 -14 -119 191
Cool Down (18K) 86 43 1 123 -21 -125 373
11-Tesla 22 11 0 57 -4 -120 374
Collar Nose Von-Mises Stress
At 11T
Coil BlocksAzimuthal Stress
At 11T
FEA predicted results
Click here to add footer 21
Bullet gauges loadingM GuinchardP Grosclaude
8 to 9 kN per bullet
Click here to add footer 22
Electrical tests ndash WhenF-O PincotL Grand Cleacutement
Are performed beforeafter each important construction step Test of pole Nb3Sn before curing - PBC Test of pole Nb3Sn before reaction ndash PBR Test of pole Nb3Sn after reaction ndash PAR Test of pole Nb3Sn after impregnation out of the mould ndash PAI Test of pole Nb3Sn after impregnation with instrumentation ndash PAIWI Test of collared coil before collaring ndash BC Test of collared coil after collaring ndash AC Test of the magnet under load before welding ndash UL Test of the magnet after shell welding ndash AW Test of the magnet after longitudinal coil loading ndash AL Test of the magnet after interconnection ndash AI Final Test of the magnet before delivery - FINAL
Click here to add footer 23
Electrical tests ndash WhatF-O PincotL Grand CleacutementAccording to the construction step we define
specific test valueselectrical tests among which
Resistance measurement(Coils Quench heaters Voltage taps Instrumentation) Inductance measurement Capacitance measurement Dielectric measurement(between coils QH instrumentation ground)
bull Insulation (up to 1kV 30s)bull current leakage (up to 1kV 5min)
Discharge test on coilUp to 1kV
Discharge test on quench heatersUp to 900V or 80AQH
Click here to add footer 24
Electrical testsF-O PincotL Grand Cleacutement
Resistance Insulation dielectric Inductance Capacitance Coil discharge QH discharge
Test phase
code
PBC X X X
PBR X X X
PAR X X X
PAI X X X X
PAIWI X X X X
BC X X X X X X
AC X X X X X X
UL X X
AW X X X X X X
AL X X X X X X
AI X X X X X X
FINAL X X X X X X
Click here to add footer 25
Click here to add footer 26
Plan for power tests coldbull RRR and strain gauge measurementsbull Preliminary tests ndash Setup protection ndash Splice resistance
measurements (current plateaus at 2 4 6 8 and 10 kA) ndash 3 hoursbull Training 43 K ndash 15 quenches ndash 3 days bull Training 19 K ndash 10 quenches ndash 25 days
Stability on current plateau ndash 05 daybull Ramp-rate study 100 As and 50 As ndash 05 day
AC-loss measurements (includes inductance measurement) at 5 to 100 As ndash 05 day
bull Quench heater efficiency study 3 different settings of QH pulse for 3 currents each Long re-cooling of the magnet due to delay of energy extraction ndash 3 days
bull High MIIts tests (protection delay) 6 quenches ndash 3 days
bull Quench propagation velocity measurements acquired for the training quenches
G Willeringbull Cool down bull Day 1
bull Day 2-4bull Day 5-7
bull Day 8
bull Day 9-11
bull Day 12-14
Click here to add footer 27
Further actionsbull After cold tests warm magnetic
measurements will be carried out with the two coils connected
bull Model 1 MBHSP101 single aperture with cable OST RRP 108127 for both polesbull Instrumentation of coils 106 and 107 going onbull Collaring scheduled around middle of June
- CERN-FNAL Video Meeting 12 Progress of the 11T Dipole short m
- Contributions
- Main design features
- Specific features
- Assembly conditions - Winding
- Binder curing
- Reaction treatment
- Reaction treatment ndash Coil 105
- Impregnation
- Instrumentation outer layer
- Instrumentation inner layer
- Quench heaters
- Coils size
- Excess in mid-plane
- Collaring steps
- Shimming plan
- Yoking welding of the shells
- Structural analysis vs measurements
- FEA Results
- ANSYS Forecast at 11-Tesla
- Bullet gauges loading
- Electrical tests ndash When
- Electrical tests ndash What
- Electrical tests
- Slide 25
- Plan for power tests cold
- Further actions
-
Click here to add footer 8
Reaction treatment ndash Coil 105
Adjustment of dwell time to compensate the delay between the
temperature and tooling temperature
The homogeneity of T during ramp up was not very good plusmn
9degCHowever it is OK during
dwell time
N BourceyF Lackner
Click here to add footer 9
Impregnationbull Resin CTD 101K
bull Anhydride cured epoxy system with excellent performance at cryogenic temperature and radiation resistance
bull The resin is preheated and the coil is impregnated at 60degC
bull Curing 110degC for 5 hoursbull Post curing heating 125degC for 16 hours
R GauthierD Smekens
Temperature [degC] Pot life [h] Viscosity [mmmiddotPas]25 145 1300
40 60 400
60 20 100
Click here to add footer 10
Instrumentation outer layer
Outer layer instrumentation incorporated in a Trace which is applied after impregnationThere are 2 ldquoUrdquo shaped SS quench heaters with Cu overlay with Cu masked off to provide heating regions Heater width is 19mm in low-field region with heater regions 90mm apart In the high-field region the heater width is 24mm and the heater regions are 130mm apartThere are 13 voltage taps on the Trace including 6 on the pole turn 1 on the layer jump and 4 on the mid-plane turn
EES5O
I
EE5O12-
+
EES5OO
EE5O11EE5O10
EE5O9
EE5O8 EE5O6EE5O7 EE5O5
EE5O4EE5O3EE5O2
EE5O1
Click here to add footer 11
Instrumentation inner layer
Inner layer instrumentation consists only of voltage taps There are 16 voltage taps including 6 on the pole turn 1 on the layer jump and 4 on the mid-plane turn with other taps adjacent to spacer block edges
S Izquierdo BermudezF-O PincotR Bateman
Click here to add footer 12
Quench heaters
50 70 90 110 130 150 170 19000
200400600800
100012001400160018002000
Low Field Region High Field Region
Heater Current (A)
Pow
er d
ensi
ty (W
cm
2)
Operation area
bull Width -gt Cover as many turns as possible
bull LF 19 mm bull HF 24 mm
bull Power densitybull LF asymp 75 Wcm2
bull HFasymp 55 Wcm2
Even if the operational current is expected to be in the range 100-120 A it would be good to have the possibility to go up to 150 A during short model tests to check the saturation of the system in terms of heater delays
119875119889=1198682119877119908119871
119877=120588 119871119908119905
119875119889=1198682 1205881199082119905
Heater width19 mm LF 24 mm HFρss=7310-7Ωm RRR=134
bull Distance between heater stations -gt quench propagation in between stations asymp 5 msbull LF 90 mmbull HF 130 mm
bull Coverage maximum coverage keeping the resistance within the allowable limits for a 55 m magnet (depends on the number of power suppliesheater circuits)
Cu
50 90130
192
4
Cu
Click here to add footer 13
Coils size
bull Both coils 101 and 105 were oversized only in the mid-plane
bull Best-fit on the outer diameter and the loading plates (interface with pole)
Click here to add footer 14
Excess in mid-plane
-150 -50 50 20
030
040
050
060
070
080
090
090
011
0012
0013
0014
000
100
200
300
400
500
600
700
800
leftrightaverage
Coil length [mm]
Inte
rfer
ence
[microm
]
Click here to add footer 15
Collaring steps
2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 320
50100150200250300350400
Distance to collaring position right lead endright return endleft lead endleft return end
F [MN]
offs
et k
ey g
roov
e [micro
m]
With 8MN the stoppers of the collaring tool were in contact
Click here to add footer 16
Shimming planbull Mid-plane is 650 microm beyond expectations To compensate
bull One layer of Kapton was removed on the mid-plane
bull Changed one layer of insulation to 005 microm thickness (in lieu of 0125 microm)
Click here to add footer 17
Yoking welding of the shellsF Lackner
1 2 3 4 5 6 7 80
100200300400500600700800
0
110
206
361426
526610
686Pressure rising April 28th 2014
Pressure rising step
Tota
l cha
rge
in to
ns
3154906157901240166520652225
002040608
SIDE B 0110206361426526610686
Length in [mm]
Yoke
gap
[mm
]
Tota
l loa
d in
tons
Max charge 500 tm on central section to close the welding gap
0
02
04
06
SIDE A0110206361426526610686
Length in [mm]
Yoke
gap
[mm
]
Tota
l loa
d in
tons
Click here to add footer 18
Structural analysis vs measurements
Click here to add footer 19
FEA Results 11T Mirror
FEA Max Cap gauge
pressure (MPa)
FEA Avg Cap gauge
pressure (MPa)
FEA Min Cap gauge
pressure (MPa)
Collar nose
stress (MPa)
Coil Min stress (MPa)
Coil Max Stress (MPa)
Avg Shell Stress (MPa)
Collaring Load 48 33 18 88 -7 -90
Post-Collaring 39 28 16 72 -7 -69
Collar in yoke 40 28 17 73 -9 -66
Max Press force 46 31 15 81 -14 -60 10
Shell Weld + Press Force 50 33 14 87 -16 -61 187
Shell Welded no Press Force 48 32 15 85 -15 -60 194
Collaring Load Post-Collaring Collar in yoke Max Press force Shell Weld + Press Force
Shell Welded no Press Force
Shell Welded - 297K
Cool Down (18K)
11-Tesla0
10
20
30
40
50
60Mirror Coil - contact pressure at pole (Cap Gauge)
FEA Max Cap gauge - pressure (MPa)
FEA Avg Cap gauge - pressure (MPa)
FEA Min Cap gauge - pressure (MPa)
Measured Coil Data (10 error bars)
Pres
sure
(MPa
)
Click here to add footer 20
ANSYS Forecast at 11-Tesla
Assembly Step
Max Capacitive gauge -
pressure (MPa)
Avg Capacitive gauge -
pressure (MPa)
Min Capacitive gauge -
pressure (MPa)
Collar-nose stress (MPa)
Coil Min stress (MPa)
Coil Max Stress (MPa)
Avg Shell Stress (MPa)
MirrorCoil
Shell Welded - 297K 48 32 15 85 -15 -60 195
Cool Down (18K) 37 21 5 62 -5 -74 375
11-Tesla 1 05 0 63 +13 -117 377
NominalCoil
Shell Welded - 297K 107 58 8 150 -14 -119 191
Cool Down (18K) 86 43 1 123 -21 -125 373
11-Tesla 22 11 0 57 -4 -120 374
Collar Nose Von-Mises Stress
At 11T
Coil BlocksAzimuthal Stress
At 11T
FEA predicted results
Click here to add footer 21
Bullet gauges loadingM GuinchardP Grosclaude
8 to 9 kN per bullet
Click here to add footer 22
Electrical tests ndash WhenF-O PincotL Grand Cleacutement
Are performed beforeafter each important construction step Test of pole Nb3Sn before curing - PBC Test of pole Nb3Sn before reaction ndash PBR Test of pole Nb3Sn after reaction ndash PAR Test of pole Nb3Sn after impregnation out of the mould ndash PAI Test of pole Nb3Sn after impregnation with instrumentation ndash PAIWI Test of collared coil before collaring ndash BC Test of collared coil after collaring ndash AC Test of the magnet under load before welding ndash UL Test of the magnet after shell welding ndash AW Test of the magnet after longitudinal coil loading ndash AL Test of the magnet after interconnection ndash AI Final Test of the magnet before delivery - FINAL
Click here to add footer 23
Electrical tests ndash WhatF-O PincotL Grand CleacutementAccording to the construction step we define
specific test valueselectrical tests among which
Resistance measurement(Coils Quench heaters Voltage taps Instrumentation) Inductance measurement Capacitance measurement Dielectric measurement(between coils QH instrumentation ground)
bull Insulation (up to 1kV 30s)bull current leakage (up to 1kV 5min)
Discharge test on coilUp to 1kV
Discharge test on quench heatersUp to 900V or 80AQH
Click here to add footer 24
Electrical testsF-O PincotL Grand Cleacutement
Resistance Insulation dielectric Inductance Capacitance Coil discharge QH discharge
Test phase
code
PBC X X X
PBR X X X
PAR X X X
PAI X X X X
PAIWI X X X X
BC X X X X X X
AC X X X X X X
UL X X
AW X X X X X X
AL X X X X X X
AI X X X X X X
FINAL X X X X X X
Click here to add footer 25
Click here to add footer 26
Plan for power tests coldbull RRR and strain gauge measurementsbull Preliminary tests ndash Setup protection ndash Splice resistance
measurements (current plateaus at 2 4 6 8 and 10 kA) ndash 3 hoursbull Training 43 K ndash 15 quenches ndash 3 days bull Training 19 K ndash 10 quenches ndash 25 days
Stability on current plateau ndash 05 daybull Ramp-rate study 100 As and 50 As ndash 05 day
AC-loss measurements (includes inductance measurement) at 5 to 100 As ndash 05 day
bull Quench heater efficiency study 3 different settings of QH pulse for 3 currents each Long re-cooling of the magnet due to delay of energy extraction ndash 3 days
bull High MIIts tests (protection delay) 6 quenches ndash 3 days
bull Quench propagation velocity measurements acquired for the training quenches
G Willeringbull Cool down bull Day 1
bull Day 2-4bull Day 5-7
bull Day 8
bull Day 9-11
bull Day 12-14
Click here to add footer 27
Further actionsbull After cold tests warm magnetic
measurements will be carried out with the two coils connected
bull Model 1 MBHSP101 single aperture with cable OST RRP 108127 for both polesbull Instrumentation of coils 106 and 107 going onbull Collaring scheduled around middle of June
- CERN-FNAL Video Meeting 12 Progress of the 11T Dipole short m
- Contributions
- Main design features
- Specific features
- Assembly conditions - Winding
- Binder curing
- Reaction treatment
- Reaction treatment ndash Coil 105
- Impregnation
- Instrumentation outer layer
- Instrumentation inner layer
- Quench heaters
- Coils size
- Excess in mid-plane
- Collaring steps
- Shimming plan
- Yoking welding of the shells
- Structural analysis vs measurements
- FEA Results
- ANSYS Forecast at 11-Tesla
- Bullet gauges loading
- Electrical tests ndash When
- Electrical tests ndash What
- Electrical tests
- Slide 25
- Plan for power tests cold
- Further actions
-
Click here to add footer 9
Impregnationbull Resin CTD 101K
bull Anhydride cured epoxy system with excellent performance at cryogenic temperature and radiation resistance
bull The resin is preheated and the coil is impregnated at 60degC
bull Curing 110degC for 5 hoursbull Post curing heating 125degC for 16 hours
R GauthierD Smekens
Temperature [degC] Pot life [h] Viscosity [mmmiddotPas]25 145 1300
40 60 400
60 20 100
Click here to add footer 10
Instrumentation outer layer
Outer layer instrumentation incorporated in a Trace which is applied after impregnationThere are 2 ldquoUrdquo shaped SS quench heaters with Cu overlay with Cu masked off to provide heating regions Heater width is 19mm in low-field region with heater regions 90mm apart In the high-field region the heater width is 24mm and the heater regions are 130mm apartThere are 13 voltage taps on the Trace including 6 on the pole turn 1 on the layer jump and 4 on the mid-plane turn
EES5O
I
EE5O12-
+
EES5OO
EE5O11EE5O10
EE5O9
EE5O8 EE5O6EE5O7 EE5O5
EE5O4EE5O3EE5O2
EE5O1
Click here to add footer 11
Instrumentation inner layer
Inner layer instrumentation consists only of voltage taps There are 16 voltage taps including 6 on the pole turn 1 on the layer jump and 4 on the mid-plane turn with other taps adjacent to spacer block edges
S Izquierdo BermudezF-O PincotR Bateman
Click here to add footer 12
Quench heaters
50 70 90 110 130 150 170 19000
200400600800
100012001400160018002000
Low Field Region High Field Region
Heater Current (A)
Pow
er d
ensi
ty (W
cm
2)
Operation area
bull Width -gt Cover as many turns as possible
bull LF 19 mm bull HF 24 mm
bull Power densitybull LF asymp 75 Wcm2
bull HFasymp 55 Wcm2
Even if the operational current is expected to be in the range 100-120 A it would be good to have the possibility to go up to 150 A during short model tests to check the saturation of the system in terms of heater delays
119875119889=1198682119877119908119871
119877=120588 119871119908119905
119875119889=1198682 1205881199082119905
Heater width19 mm LF 24 mm HFρss=7310-7Ωm RRR=134
bull Distance between heater stations -gt quench propagation in between stations asymp 5 msbull LF 90 mmbull HF 130 mm
bull Coverage maximum coverage keeping the resistance within the allowable limits for a 55 m magnet (depends on the number of power suppliesheater circuits)
Cu
50 90130
192
4
Cu
Click here to add footer 13
Coils size
bull Both coils 101 and 105 were oversized only in the mid-plane
bull Best-fit on the outer diameter and the loading plates (interface with pole)
Click here to add footer 14
Excess in mid-plane
-150 -50 50 20
030
040
050
060
070
080
090
090
011
0012
0013
0014
000
100
200
300
400
500
600
700
800
leftrightaverage
Coil length [mm]
Inte
rfer
ence
[microm
]
Click here to add footer 15
Collaring steps
2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 320
50100150200250300350400
Distance to collaring position right lead endright return endleft lead endleft return end
F [MN]
offs
et k
ey g
roov
e [micro
m]
With 8MN the stoppers of the collaring tool were in contact
Click here to add footer 16
Shimming planbull Mid-plane is 650 microm beyond expectations To compensate
bull One layer of Kapton was removed on the mid-plane
bull Changed one layer of insulation to 005 microm thickness (in lieu of 0125 microm)
Click here to add footer 17
Yoking welding of the shellsF Lackner
1 2 3 4 5 6 7 80
100200300400500600700800
0
110
206
361426
526610
686Pressure rising April 28th 2014
Pressure rising step
Tota
l cha
rge
in to
ns
3154906157901240166520652225
002040608
SIDE B 0110206361426526610686
Length in [mm]
Yoke
gap
[mm
]
Tota
l loa
d in
tons
Max charge 500 tm on central section to close the welding gap
0
02
04
06
SIDE A0110206361426526610686
Length in [mm]
Yoke
gap
[mm
]
Tota
l loa
d in
tons
Click here to add footer 18
Structural analysis vs measurements
Click here to add footer 19
FEA Results 11T Mirror
FEA Max Cap gauge
pressure (MPa)
FEA Avg Cap gauge
pressure (MPa)
FEA Min Cap gauge
pressure (MPa)
Collar nose
stress (MPa)
Coil Min stress (MPa)
Coil Max Stress (MPa)
Avg Shell Stress (MPa)
Collaring Load 48 33 18 88 -7 -90
Post-Collaring 39 28 16 72 -7 -69
Collar in yoke 40 28 17 73 -9 -66
Max Press force 46 31 15 81 -14 -60 10
Shell Weld + Press Force 50 33 14 87 -16 -61 187
Shell Welded no Press Force 48 32 15 85 -15 -60 194
Collaring Load Post-Collaring Collar in yoke Max Press force Shell Weld + Press Force
Shell Welded no Press Force
Shell Welded - 297K
Cool Down (18K)
11-Tesla0
10
20
30
40
50
60Mirror Coil - contact pressure at pole (Cap Gauge)
FEA Max Cap gauge - pressure (MPa)
FEA Avg Cap gauge - pressure (MPa)
FEA Min Cap gauge - pressure (MPa)
Measured Coil Data (10 error bars)
Pres
sure
(MPa
)
Click here to add footer 20
ANSYS Forecast at 11-Tesla
Assembly Step
Max Capacitive gauge -
pressure (MPa)
Avg Capacitive gauge -
pressure (MPa)
Min Capacitive gauge -
pressure (MPa)
Collar-nose stress (MPa)
Coil Min stress (MPa)
Coil Max Stress (MPa)
Avg Shell Stress (MPa)
MirrorCoil
Shell Welded - 297K 48 32 15 85 -15 -60 195
Cool Down (18K) 37 21 5 62 -5 -74 375
11-Tesla 1 05 0 63 +13 -117 377
NominalCoil
Shell Welded - 297K 107 58 8 150 -14 -119 191
Cool Down (18K) 86 43 1 123 -21 -125 373
11-Tesla 22 11 0 57 -4 -120 374
Collar Nose Von-Mises Stress
At 11T
Coil BlocksAzimuthal Stress
At 11T
FEA predicted results
Click here to add footer 21
Bullet gauges loadingM GuinchardP Grosclaude
8 to 9 kN per bullet
Click here to add footer 22
Electrical tests ndash WhenF-O PincotL Grand Cleacutement
Are performed beforeafter each important construction step Test of pole Nb3Sn before curing - PBC Test of pole Nb3Sn before reaction ndash PBR Test of pole Nb3Sn after reaction ndash PAR Test of pole Nb3Sn after impregnation out of the mould ndash PAI Test of pole Nb3Sn after impregnation with instrumentation ndash PAIWI Test of collared coil before collaring ndash BC Test of collared coil after collaring ndash AC Test of the magnet under load before welding ndash UL Test of the magnet after shell welding ndash AW Test of the magnet after longitudinal coil loading ndash AL Test of the magnet after interconnection ndash AI Final Test of the magnet before delivery - FINAL
Click here to add footer 23
Electrical tests ndash WhatF-O PincotL Grand CleacutementAccording to the construction step we define
specific test valueselectrical tests among which
Resistance measurement(Coils Quench heaters Voltage taps Instrumentation) Inductance measurement Capacitance measurement Dielectric measurement(between coils QH instrumentation ground)
bull Insulation (up to 1kV 30s)bull current leakage (up to 1kV 5min)
Discharge test on coilUp to 1kV
Discharge test on quench heatersUp to 900V or 80AQH
Click here to add footer 24
Electrical testsF-O PincotL Grand Cleacutement
Resistance Insulation dielectric Inductance Capacitance Coil discharge QH discharge
Test phase
code
PBC X X X
PBR X X X
PAR X X X
PAI X X X X
PAIWI X X X X
BC X X X X X X
AC X X X X X X
UL X X
AW X X X X X X
AL X X X X X X
AI X X X X X X
FINAL X X X X X X
Click here to add footer 25
Click here to add footer 26
Plan for power tests coldbull RRR and strain gauge measurementsbull Preliminary tests ndash Setup protection ndash Splice resistance
measurements (current plateaus at 2 4 6 8 and 10 kA) ndash 3 hoursbull Training 43 K ndash 15 quenches ndash 3 days bull Training 19 K ndash 10 quenches ndash 25 days
Stability on current plateau ndash 05 daybull Ramp-rate study 100 As and 50 As ndash 05 day
AC-loss measurements (includes inductance measurement) at 5 to 100 As ndash 05 day
bull Quench heater efficiency study 3 different settings of QH pulse for 3 currents each Long re-cooling of the magnet due to delay of energy extraction ndash 3 days
bull High MIIts tests (protection delay) 6 quenches ndash 3 days
bull Quench propagation velocity measurements acquired for the training quenches
G Willeringbull Cool down bull Day 1
bull Day 2-4bull Day 5-7
bull Day 8
bull Day 9-11
bull Day 12-14
Click here to add footer 27
Further actionsbull After cold tests warm magnetic
measurements will be carried out with the two coils connected
bull Model 1 MBHSP101 single aperture with cable OST RRP 108127 for both polesbull Instrumentation of coils 106 and 107 going onbull Collaring scheduled around middle of June
- CERN-FNAL Video Meeting 12 Progress of the 11T Dipole short m
- Contributions
- Main design features
- Specific features
- Assembly conditions - Winding
- Binder curing
- Reaction treatment
- Reaction treatment ndash Coil 105
- Impregnation
- Instrumentation outer layer
- Instrumentation inner layer
- Quench heaters
- Coils size
- Excess in mid-plane
- Collaring steps
- Shimming plan
- Yoking welding of the shells
- Structural analysis vs measurements
- FEA Results
- ANSYS Forecast at 11-Tesla
- Bullet gauges loading
- Electrical tests ndash When
- Electrical tests ndash What
- Electrical tests
- Slide 25
- Plan for power tests cold
- Further actions
-
Click here to add footer 10
Instrumentation outer layer
Outer layer instrumentation incorporated in a Trace which is applied after impregnationThere are 2 ldquoUrdquo shaped SS quench heaters with Cu overlay with Cu masked off to provide heating regions Heater width is 19mm in low-field region with heater regions 90mm apart In the high-field region the heater width is 24mm and the heater regions are 130mm apartThere are 13 voltage taps on the Trace including 6 on the pole turn 1 on the layer jump and 4 on the mid-plane turn
EES5O
I
EE5O12-
+
EES5OO
EE5O11EE5O10
EE5O9
EE5O8 EE5O6EE5O7 EE5O5
EE5O4EE5O3EE5O2
EE5O1
Click here to add footer 11
Instrumentation inner layer
Inner layer instrumentation consists only of voltage taps There are 16 voltage taps including 6 on the pole turn 1 on the layer jump and 4 on the mid-plane turn with other taps adjacent to spacer block edges
S Izquierdo BermudezF-O PincotR Bateman
Click here to add footer 12
Quench heaters
50 70 90 110 130 150 170 19000
200400600800
100012001400160018002000
Low Field Region High Field Region
Heater Current (A)
Pow
er d
ensi
ty (W
cm
2)
Operation area
bull Width -gt Cover as many turns as possible
bull LF 19 mm bull HF 24 mm
bull Power densitybull LF asymp 75 Wcm2
bull HFasymp 55 Wcm2
Even if the operational current is expected to be in the range 100-120 A it would be good to have the possibility to go up to 150 A during short model tests to check the saturation of the system in terms of heater delays
119875119889=1198682119877119908119871
119877=120588 119871119908119905
119875119889=1198682 1205881199082119905
Heater width19 mm LF 24 mm HFρss=7310-7Ωm RRR=134
bull Distance between heater stations -gt quench propagation in between stations asymp 5 msbull LF 90 mmbull HF 130 mm
bull Coverage maximum coverage keeping the resistance within the allowable limits for a 55 m magnet (depends on the number of power suppliesheater circuits)
Cu
50 90130
192
4
Cu
Click here to add footer 13
Coils size
bull Both coils 101 and 105 were oversized only in the mid-plane
bull Best-fit on the outer diameter and the loading plates (interface with pole)
Click here to add footer 14
Excess in mid-plane
-150 -50 50 20
030
040
050
060
070
080
090
090
011
0012
0013
0014
000
100
200
300
400
500
600
700
800
leftrightaverage
Coil length [mm]
Inte
rfer
ence
[microm
]
Click here to add footer 15
Collaring steps
2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 320
50100150200250300350400
Distance to collaring position right lead endright return endleft lead endleft return end
F [MN]
offs
et k
ey g
roov
e [micro
m]
With 8MN the stoppers of the collaring tool were in contact
Click here to add footer 16
Shimming planbull Mid-plane is 650 microm beyond expectations To compensate
bull One layer of Kapton was removed on the mid-plane
bull Changed one layer of insulation to 005 microm thickness (in lieu of 0125 microm)
Click here to add footer 17
Yoking welding of the shellsF Lackner
1 2 3 4 5 6 7 80
100200300400500600700800
0
110
206
361426
526610
686Pressure rising April 28th 2014
Pressure rising step
Tota
l cha
rge
in to
ns
3154906157901240166520652225
002040608
SIDE B 0110206361426526610686
Length in [mm]
Yoke
gap
[mm
]
Tota
l loa
d in
tons
Max charge 500 tm on central section to close the welding gap
0
02
04
06
SIDE A0110206361426526610686
Length in [mm]
Yoke
gap
[mm
]
Tota
l loa
d in
tons
Click here to add footer 18
Structural analysis vs measurements
Click here to add footer 19
FEA Results 11T Mirror
FEA Max Cap gauge
pressure (MPa)
FEA Avg Cap gauge
pressure (MPa)
FEA Min Cap gauge
pressure (MPa)
Collar nose
stress (MPa)
Coil Min stress (MPa)
Coil Max Stress (MPa)
Avg Shell Stress (MPa)
Collaring Load 48 33 18 88 -7 -90
Post-Collaring 39 28 16 72 -7 -69
Collar in yoke 40 28 17 73 -9 -66
Max Press force 46 31 15 81 -14 -60 10
Shell Weld + Press Force 50 33 14 87 -16 -61 187
Shell Welded no Press Force 48 32 15 85 -15 -60 194
Collaring Load Post-Collaring Collar in yoke Max Press force Shell Weld + Press Force
Shell Welded no Press Force
Shell Welded - 297K
Cool Down (18K)
11-Tesla0
10
20
30
40
50
60Mirror Coil - contact pressure at pole (Cap Gauge)
FEA Max Cap gauge - pressure (MPa)
FEA Avg Cap gauge - pressure (MPa)
FEA Min Cap gauge - pressure (MPa)
Measured Coil Data (10 error bars)
Pres
sure
(MPa
)
Click here to add footer 20
ANSYS Forecast at 11-Tesla
Assembly Step
Max Capacitive gauge -
pressure (MPa)
Avg Capacitive gauge -
pressure (MPa)
Min Capacitive gauge -
pressure (MPa)
Collar-nose stress (MPa)
Coil Min stress (MPa)
Coil Max Stress (MPa)
Avg Shell Stress (MPa)
MirrorCoil
Shell Welded - 297K 48 32 15 85 -15 -60 195
Cool Down (18K) 37 21 5 62 -5 -74 375
11-Tesla 1 05 0 63 +13 -117 377
NominalCoil
Shell Welded - 297K 107 58 8 150 -14 -119 191
Cool Down (18K) 86 43 1 123 -21 -125 373
11-Tesla 22 11 0 57 -4 -120 374
Collar Nose Von-Mises Stress
At 11T
Coil BlocksAzimuthal Stress
At 11T
FEA predicted results
Click here to add footer 21
Bullet gauges loadingM GuinchardP Grosclaude
8 to 9 kN per bullet
Click here to add footer 22
Electrical tests ndash WhenF-O PincotL Grand Cleacutement
Are performed beforeafter each important construction step Test of pole Nb3Sn before curing - PBC Test of pole Nb3Sn before reaction ndash PBR Test of pole Nb3Sn after reaction ndash PAR Test of pole Nb3Sn after impregnation out of the mould ndash PAI Test of pole Nb3Sn after impregnation with instrumentation ndash PAIWI Test of collared coil before collaring ndash BC Test of collared coil after collaring ndash AC Test of the magnet under load before welding ndash UL Test of the magnet after shell welding ndash AW Test of the magnet after longitudinal coil loading ndash AL Test of the magnet after interconnection ndash AI Final Test of the magnet before delivery - FINAL
Click here to add footer 23
Electrical tests ndash WhatF-O PincotL Grand CleacutementAccording to the construction step we define
specific test valueselectrical tests among which
Resistance measurement(Coils Quench heaters Voltage taps Instrumentation) Inductance measurement Capacitance measurement Dielectric measurement(between coils QH instrumentation ground)
bull Insulation (up to 1kV 30s)bull current leakage (up to 1kV 5min)
Discharge test on coilUp to 1kV
Discharge test on quench heatersUp to 900V or 80AQH
Click here to add footer 24
Electrical testsF-O PincotL Grand Cleacutement
Resistance Insulation dielectric Inductance Capacitance Coil discharge QH discharge
Test phase
code
PBC X X X
PBR X X X
PAR X X X
PAI X X X X
PAIWI X X X X
BC X X X X X X
AC X X X X X X
UL X X
AW X X X X X X
AL X X X X X X
AI X X X X X X
FINAL X X X X X X
Click here to add footer 25
Click here to add footer 26
Plan for power tests coldbull RRR and strain gauge measurementsbull Preliminary tests ndash Setup protection ndash Splice resistance
measurements (current plateaus at 2 4 6 8 and 10 kA) ndash 3 hoursbull Training 43 K ndash 15 quenches ndash 3 days bull Training 19 K ndash 10 quenches ndash 25 days
Stability on current plateau ndash 05 daybull Ramp-rate study 100 As and 50 As ndash 05 day
AC-loss measurements (includes inductance measurement) at 5 to 100 As ndash 05 day
bull Quench heater efficiency study 3 different settings of QH pulse for 3 currents each Long re-cooling of the magnet due to delay of energy extraction ndash 3 days
bull High MIIts tests (protection delay) 6 quenches ndash 3 days
bull Quench propagation velocity measurements acquired for the training quenches
G Willeringbull Cool down bull Day 1
bull Day 2-4bull Day 5-7
bull Day 8
bull Day 9-11
bull Day 12-14
Click here to add footer 27
Further actionsbull After cold tests warm magnetic
measurements will be carried out with the two coils connected
bull Model 1 MBHSP101 single aperture with cable OST RRP 108127 for both polesbull Instrumentation of coils 106 and 107 going onbull Collaring scheduled around middle of June
- CERN-FNAL Video Meeting 12 Progress of the 11T Dipole short m
- Contributions
- Main design features
- Specific features
- Assembly conditions - Winding
- Binder curing
- Reaction treatment
- Reaction treatment ndash Coil 105
- Impregnation
- Instrumentation outer layer
- Instrumentation inner layer
- Quench heaters
- Coils size
- Excess in mid-plane
- Collaring steps
- Shimming plan
- Yoking welding of the shells
- Structural analysis vs measurements
- FEA Results
- ANSYS Forecast at 11-Tesla
- Bullet gauges loading
- Electrical tests ndash When
- Electrical tests ndash What
- Electrical tests
- Slide 25
- Plan for power tests cold
- Further actions
-
Click here to add footer 11
Instrumentation inner layer
Inner layer instrumentation consists only of voltage taps There are 16 voltage taps including 6 on the pole turn 1 on the layer jump and 4 on the mid-plane turn with other taps adjacent to spacer block edges
S Izquierdo BermudezF-O PincotR Bateman
Click here to add footer 12
Quench heaters
50 70 90 110 130 150 170 19000
200400600800
100012001400160018002000
Low Field Region High Field Region
Heater Current (A)
Pow
er d
ensi
ty (W
cm
2)
Operation area
bull Width -gt Cover as many turns as possible
bull LF 19 mm bull HF 24 mm
bull Power densitybull LF asymp 75 Wcm2
bull HFasymp 55 Wcm2
Even if the operational current is expected to be in the range 100-120 A it would be good to have the possibility to go up to 150 A during short model tests to check the saturation of the system in terms of heater delays
119875119889=1198682119877119908119871
119877=120588 119871119908119905
119875119889=1198682 1205881199082119905
Heater width19 mm LF 24 mm HFρss=7310-7Ωm RRR=134
bull Distance between heater stations -gt quench propagation in between stations asymp 5 msbull LF 90 mmbull HF 130 mm
bull Coverage maximum coverage keeping the resistance within the allowable limits for a 55 m magnet (depends on the number of power suppliesheater circuits)
Cu
50 90130
192
4
Cu
Click here to add footer 13
Coils size
bull Both coils 101 and 105 were oversized only in the mid-plane
bull Best-fit on the outer diameter and the loading plates (interface with pole)
Click here to add footer 14
Excess in mid-plane
-150 -50 50 20
030
040
050
060
070
080
090
090
011
0012
0013
0014
000
100
200
300
400
500
600
700
800
leftrightaverage
Coil length [mm]
Inte
rfer
ence
[microm
]
Click here to add footer 15
Collaring steps
2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 320
50100150200250300350400
Distance to collaring position right lead endright return endleft lead endleft return end
F [MN]
offs
et k
ey g
roov
e [micro
m]
With 8MN the stoppers of the collaring tool were in contact
Click here to add footer 16
Shimming planbull Mid-plane is 650 microm beyond expectations To compensate
bull One layer of Kapton was removed on the mid-plane
bull Changed one layer of insulation to 005 microm thickness (in lieu of 0125 microm)
Click here to add footer 17
Yoking welding of the shellsF Lackner
1 2 3 4 5 6 7 80
100200300400500600700800
0
110
206
361426
526610
686Pressure rising April 28th 2014
Pressure rising step
Tota
l cha
rge
in to
ns
3154906157901240166520652225
002040608
SIDE B 0110206361426526610686
Length in [mm]
Yoke
gap
[mm
]
Tota
l loa
d in
tons
Max charge 500 tm on central section to close the welding gap
0
02
04
06
SIDE A0110206361426526610686
Length in [mm]
Yoke
gap
[mm
]
Tota
l loa
d in
tons
Click here to add footer 18
Structural analysis vs measurements
Click here to add footer 19
FEA Results 11T Mirror
FEA Max Cap gauge
pressure (MPa)
FEA Avg Cap gauge
pressure (MPa)
FEA Min Cap gauge
pressure (MPa)
Collar nose
stress (MPa)
Coil Min stress (MPa)
Coil Max Stress (MPa)
Avg Shell Stress (MPa)
Collaring Load 48 33 18 88 -7 -90
Post-Collaring 39 28 16 72 -7 -69
Collar in yoke 40 28 17 73 -9 -66
Max Press force 46 31 15 81 -14 -60 10
Shell Weld + Press Force 50 33 14 87 -16 -61 187
Shell Welded no Press Force 48 32 15 85 -15 -60 194
Collaring Load Post-Collaring Collar in yoke Max Press force Shell Weld + Press Force
Shell Welded no Press Force
Shell Welded - 297K
Cool Down (18K)
11-Tesla0
10
20
30
40
50
60Mirror Coil - contact pressure at pole (Cap Gauge)
FEA Max Cap gauge - pressure (MPa)
FEA Avg Cap gauge - pressure (MPa)
FEA Min Cap gauge - pressure (MPa)
Measured Coil Data (10 error bars)
Pres
sure
(MPa
)
Click here to add footer 20
ANSYS Forecast at 11-Tesla
Assembly Step
Max Capacitive gauge -
pressure (MPa)
Avg Capacitive gauge -
pressure (MPa)
Min Capacitive gauge -
pressure (MPa)
Collar-nose stress (MPa)
Coil Min stress (MPa)
Coil Max Stress (MPa)
Avg Shell Stress (MPa)
MirrorCoil
Shell Welded - 297K 48 32 15 85 -15 -60 195
Cool Down (18K) 37 21 5 62 -5 -74 375
11-Tesla 1 05 0 63 +13 -117 377
NominalCoil
Shell Welded - 297K 107 58 8 150 -14 -119 191
Cool Down (18K) 86 43 1 123 -21 -125 373
11-Tesla 22 11 0 57 -4 -120 374
Collar Nose Von-Mises Stress
At 11T
Coil BlocksAzimuthal Stress
At 11T
FEA predicted results
Click here to add footer 21
Bullet gauges loadingM GuinchardP Grosclaude
8 to 9 kN per bullet
Click here to add footer 22
Electrical tests ndash WhenF-O PincotL Grand Cleacutement
Are performed beforeafter each important construction step Test of pole Nb3Sn before curing - PBC Test of pole Nb3Sn before reaction ndash PBR Test of pole Nb3Sn after reaction ndash PAR Test of pole Nb3Sn after impregnation out of the mould ndash PAI Test of pole Nb3Sn after impregnation with instrumentation ndash PAIWI Test of collared coil before collaring ndash BC Test of collared coil after collaring ndash AC Test of the magnet under load before welding ndash UL Test of the magnet after shell welding ndash AW Test of the magnet after longitudinal coil loading ndash AL Test of the magnet after interconnection ndash AI Final Test of the magnet before delivery - FINAL
Click here to add footer 23
Electrical tests ndash WhatF-O PincotL Grand CleacutementAccording to the construction step we define
specific test valueselectrical tests among which
Resistance measurement(Coils Quench heaters Voltage taps Instrumentation) Inductance measurement Capacitance measurement Dielectric measurement(between coils QH instrumentation ground)
bull Insulation (up to 1kV 30s)bull current leakage (up to 1kV 5min)
Discharge test on coilUp to 1kV
Discharge test on quench heatersUp to 900V or 80AQH
Click here to add footer 24
Electrical testsF-O PincotL Grand Cleacutement
Resistance Insulation dielectric Inductance Capacitance Coil discharge QH discharge
Test phase
code
PBC X X X
PBR X X X
PAR X X X
PAI X X X X
PAIWI X X X X
BC X X X X X X
AC X X X X X X
UL X X
AW X X X X X X
AL X X X X X X
AI X X X X X X
FINAL X X X X X X
Click here to add footer 25
Click here to add footer 26
Plan for power tests coldbull RRR and strain gauge measurementsbull Preliminary tests ndash Setup protection ndash Splice resistance
measurements (current plateaus at 2 4 6 8 and 10 kA) ndash 3 hoursbull Training 43 K ndash 15 quenches ndash 3 days bull Training 19 K ndash 10 quenches ndash 25 days
Stability on current plateau ndash 05 daybull Ramp-rate study 100 As and 50 As ndash 05 day
AC-loss measurements (includes inductance measurement) at 5 to 100 As ndash 05 day
bull Quench heater efficiency study 3 different settings of QH pulse for 3 currents each Long re-cooling of the magnet due to delay of energy extraction ndash 3 days
bull High MIIts tests (protection delay) 6 quenches ndash 3 days
bull Quench propagation velocity measurements acquired for the training quenches
G Willeringbull Cool down bull Day 1
bull Day 2-4bull Day 5-7
bull Day 8
bull Day 9-11
bull Day 12-14
Click here to add footer 27
Further actionsbull After cold tests warm magnetic
measurements will be carried out with the two coils connected
bull Model 1 MBHSP101 single aperture with cable OST RRP 108127 for both polesbull Instrumentation of coils 106 and 107 going onbull Collaring scheduled around middle of June
- CERN-FNAL Video Meeting 12 Progress of the 11T Dipole short m
- Contributions
- Main design features
- Specific features
- Assembly conditions - Winding
- Binder curing
- Reaction treatment
- Reaction treatment ndash Coil 105
- Impregnation
- Instrumentation outer layer
- Instrumentation inner layer
- Quench heaters
- Coils size
- Excess in mid-plane
- Collaring steps
- Shimming plan
- Yoking welding of the shells
- Structural analysis vs measurements
- FEA Results
- ANSYS Forecast at 11-Tesla
- Bullet gauges loading
- Electrical tests ndash When
- Electrical tests ndash What
- Electrical tests
- Slide 25
- Plan for power tests cold
- Further actions
-
Click here to add footer 12
Quench heaters
50 70 90 110 130 150 170 19000
200400600800
100012001400160018002000
Low Field Region High Field Region
Heater Current (A)
Pow
er d
ensi
ty (W
cm
2)
Operation area
bull Width -gt Cover as many turns as possible
bull LF 19 mm bull HF 24 mm
bull Power densitybull LF asymp 75 Wcm2
bull HFasymp 55 Wcm2
Even if the operational current is expected to be in the range 100-120 A it would be good to have the possibility to go up to 150 A during short model tests to check the saturation of the system in terms of heater delays
119875119889=1198682119877119908119871
119877=120588 119871119908119905
119875119889=1198682 1205881199082119905
Heater width19 mm LF 24 mm HFρss=7310-7Ωm RRR=134
bull Distance between heater stations -gt quench propagation in between stations asymp 5 msbull LF 90 mmbull HF 130 mm
bull Coverage maximum coverage keeping the resistance within the allowable limits for a 55 m magnet (depends on the number of power suppliesheater circuits)
Cu
50 90130
192
4
Cu
Click here to add footer 13
Coils size
bull Both coils 101 and 105 were oversized only in the mid-plane
bull Best-fit on the outer diameter and the loading plates (interface with pole)
Click here to add footer 14
Excess in mid-plane
-150 -50 50 20
030
040
050
060
070
080
090
090
011
0012
0013
0014
000
100
200
300
400
500
600
700
800
leftrightaverage
Coil length [mm]
Inte
rfer
ence
[microm
]
Click here to add footer 15
Collaring steps
2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 320
50100150200250300350400
Distance to collaring position right lead endright return endleft lead endleft return end
F [MN]
offs
et k
ey g
roov
e [micro
m]
With 8MN the stoppers of the collaring tool were in contact
Click here to add footer 16
Shimming planbull Mid-plane is 650 microm beyond expectations To compensate
bull One layer of Kapton was removed on the mid-plane
bull Changed one layer of insulation to 005 microm thickness (in lieu of 0125 microm)
Click here to add footer 17
Yoking welding of the shellsF Lackner
1 2 3 4 5 6 7 80
100200300400500600700800
0
110
206
361426
526610
686Pressure rising April 28th 2014
Pressure rising step
Tota
l cha
rge
in to
ns
3154906157901240166520652225
002040608
SIDE B 0110206361426526610686
Length in [mm]
Yoke
gap
[mm
]
Tota
l loa
d in
tons
Max charge 500 tm on central section to close the welding gap
0
02
04
06
SIDE A0110206361426526610686
Length in [mm]
Yoke
gap
[mm
]
Tota
l loa
d in
tons
Click here to add footer 18
Structural analysis vs measurements
Click here to add footer 19
FEA Results 11T Mirror
FEA Max Cap gauge
pressure (MPa)
FEA Avg Cap gauge
pressure (MPa)
FEA Min Cap gauge
pressure (MPa)
Collar nose
stress (MPa)
Coil Min stress (MPa)
Coil Max Stress (MPa)
Avg Shell Stress (MPa)
Collaring Load 48 33 18 88 -7 -90
Post-Collaring 39 28 16 72 -7 -69
Collar in yoke 40 28 17 73 -9 -66
Max Press force 46 31 15 81 -14 -60 10
Shell Weld + Press Force 50 33 14 87 -16 -61 187
Shell Welded no Press Force 48 32 15 85 -15 -60 194
Collaring Load Post-Collaring Collar in yoke Max Press force Shell Weld + Press Force
Shell Welded no Press Force
Shell Welded - 297K
Cool Down (18K)
11-Tesla0
10
20
30
40
50
60Mirror Coil - contact pressure at pole (Cap Gauge)
FEA Max Cap gauge - pressure (MPa)
FEA Avg Cap gauge - pressure (MPa)
FEA Min Cap gauge - pressure (MPa)
Measured Coil Data (10 error bars)
Pres
sure
(MPa
)
Click here to add footer 20
ANSYS Forecast at 11-Tesla
Assembly Step
Max Capacitive gauge -
pressure (MPa)
Avg Capacitive gauge -
pressure (MPa)
Min Capacitive gauge -
pressure (MPa)
Collar-nose stress (MPa)
Coil Min stress (MPa)
Coil Max Stress (MPa)
Avg Shell Stress (MPa)
MirrorCoil
Shell Welded - 297K 48 32 15 85 -15 -60 195
Cool Down (18K) 37 21 5 62 -5 -74 375
11-Tesla 1 05 0 63 +13 -117 377
NominalCoil
Shell Welded - 297K 107 58 8 150 -14 -119 191
Cool Down (18K) 86 43 1 123 -21 -125 373
11-Tesla 22 11 0 57 -4 -120 374
Collar Nose Von-Mises Stress
At 11T
Coil BlocksAzimuthal Stress
At 11T
FEA predicted results
Click here to add footer 21
Bullet gauges loadingM GuinchardP Grosclaude
8 to 9 kN per bullet
Click here to add footer 22
Electrical tests ndash WhenF-O PincotL Grand Cleacutement
Are performed beforeafter each important construction step Test of pole Nb3Sn before curing - PBC Test of pole Nb3Sn before reaction ndash PBR Test of pole Nb3Sn after reaction ndash PAR Test of pole Nb3Sn after impregnation out of the mould ndash PAI Test of pole Nb3Sn after impregnation with instrumentation ndash PAIWI Test of collared coil before collaring ndash BC Test of collared coil after collaring ndash AC Test of the magnet under load before welding ndash UL Test of the magnet after shell welding ndash AW Test of the magnet after longitudinal coil loading ndash AL Test of the magnet after interconnection ndash AI Final Test of the magnet before delivery - FINAL
Click here to add footer 23
Electrical tests ndash WhatF-O PincotL Grand CleacutementAccording to the construction step we define
specific test valueselectrical tests among which
Resistance measurement(Coils Quench heaters Voltage taps Instrumentation) Inductance measurement Capacitance measurement Dielectric measurement(between coils QH instrumentation ground)
bull Insulation (up to 1kV 30s)bull current leakage (up to 1kV 5min)
Discharge test on coilUp to 1kV
Discharge test on quench heatersUp to 900V or 80AQH
Click here to add footer 24
Electrical testsF-O PincotL Grand Cleacutement
Resistance Insulation dielectric Inductance Capacitance Coil discharge QH discharge
Test phase
code
PBC X X X
PBR X X X
PAR X X X
PAI X X X X
PAIWI X X X X
BC X X X X X X
AC X X X X X X
UL X X
AW X X X X X X
AL X X X X X X
AI X X X X X X
FINAL X X X X X X
Click here to add footer 25
Click here to add footer 26
Plan for power tests coldbull RRR and strain gauge measurementsbull Preliminary tests ndash Setup protection ndash Splice resistance
measurements (current plateaus at 2 4 6 8 and 10 kA) ndash 3 hoursbull Training 43 K ndash 15 quenches ndash 3 days bull Training 19 K ndash 10 quenches ndash 25 days
Stability on current plateau ndash 05 daybull Ramp-rate study 100 As and 50 As ndash 05 day
AC-loss measurements (includes inductance measurement) at 5 to 100 As ndash 05 day
bull Quench heater efficiency study 3 different settings of QH pulse for 3 currents each Long re-cooling of the magnet due to delay of energy extraction ndash 3 days
bull High MIIts tests (protection delay) 6 quenches ndash 3 days
bull Quench propagation velocity measurements acquired for the training quenches
G Willeringbull Cool down bull Day 1
bull Day 2-4bull Day 5-7
bull Day 8
bull Day 9-11
bull Day 12-14
Click here to add footer 27
Further actionsbull After cold tests warm magnetic
measurements will be carried out with the two coils connected
bull Model 1 MBHSP101 single aperture with cable OST RRP 108127 for both polesbull Instrumentation of coils 106 and 107 going onbull Collaring scheduled around middle of June
- CERN-FNAL Video Meeting 12 Progress of the 11T Dipole short m
- Contributions
- Main design features
- Specific features
- Assembly conditions - Winding
- Binder curing
- Reaction treatment
- Reaction treatment ndash Coil 105
- Impregnation
- Instrumentation outer layer
- Instrumentation inner layer
- Quench heaters
- Coils size
- Excess in mid-plane
- Collaring steps
- Shimming plan
- Yoking welding of the shells
- Structural analysis vs measurements
- FEA Results
- ANSYS Forecast at 11-Tesla
- Bullet gauges loading
- Electrical tests ndash When
- Electrical tests ndash What
- Electrical tests
- Slide 25
- Plan for power tests cold
- Further actions
-
Click here to add footer 13
Coils size
bull Both coils 101 and 105 were oversized only in the mid-plane
bull Best-fit on the outer diameter and the loading plates (interface with pole)
Click here to add footer 14
Excess in mid-plane
-150 -50 50 20
030
040
050
060
070
080
090
090
011
0012
0013
0014
000
100
200
300
400
500
600
700
800
leftrightaverage
Coil length [mm]
Inte
rfer
ence
[microm
]
Click here to add footer 15
Collaring steps
2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 320
50100150200250300350400
Distance to collaring position right lead endright return endleft lead endleft return end
F [MN]
offs
et k
ey g
roov
e [micro
m]
With 8MN the stoppers of the collaring tool were in contact
Click here to add footer 16
Shimming planbull Mid-plane is 650 microm beyond expectations To compensate
bull One layer of Kapton was removed on the mid-plane
bull Changed one layer of insulation to 005 microm thickness (in lieu of 0125 microm)
Click here to add footer 17
Yoking welding of the shellsF Lackner
1 2 3 4 5 6 7 80
100200300400500600700800
0
110
206
361426
526610
686Pressure rising April 28th 2014
Pressure rising step
Tota
l cha
rge
in to
ns
3154906157901240166520652225
002040608
SIDE B 0110206361426526610686
Length in [mm]
Yoke
gap
[mm
]
Tota
l loa
d in
tons
Max charge 500 tm on central section to close the welding gap
0
02
04
06
SIDE A0110206361426526610686
Length in [mm]
Yoke
gap
[mm
]
Tota
l loa
d in
tons
Click here to add footer 18
Structural analysis vs measurements
Click here to add footer 19
FEA Results 11T Mirror
FEA Max Cap gauge
pressure (MPa)
FEA Avg Cap gauge
pressure (MPa)
FEA Min Cap gauge
pressure (MPa)
Collar nose
stress (MPa)
Coil Min stress (MPa)
Coil Max Stress (MPa)
Avg Shell Stress (MPa)
Collaring Load 48 33 18 88 -7 -90
Post-Collaring 39 28 16 72 -7 -69
Collar in yoke 40 28 17 73 -9 -66
Max Press force 46 31 15 81 -14 -60 10
Shell Weld + Press Force 50 33 14 87 -16 -61 187
Shell Welded no Press Force 48 32 15 85 -15 -60 194
Collaring Load Post-Collaring Collar in yoke Max Press force Shell Weld + Press Force
Shell Welded no Press Force
Shell Welded - 297K
Cool Down (18K)
11-Tesla0
10
20
30
40
50
60Mirror Coil - contact pressure at pole (Cap Gauge)
FEA Max Cap gauge - pressure (MPa)
FEA Avg Cap gauge - pressure (MPa)
FEA Min Cap gauge - pressure (MPa)
Measured Coil Data (10 error bars)
Pres
sure
(MPa
)
Click here to add footer 20
ANSYS Forecast at 11-Tesla
Assembly Step
Max Capacitive gauge -
pressure (MPa)
Avg Capacitive gauge -
pressure (MPa)
Min Capacitive gauge -
pressure (MPa)
Collar-nose stress (MPa)
Coil Min stress (MPa)
Coil Max Stress (MPa)
Avg Shell Stress (MPa)
MirrorCoil
Shell Welded - 297K 48 32 15 85 -15 -60 195
Cool Down (18K) 37 21 5 62 -5 -74 375
11-Tesla 1 05 0 63 +13 -117 377
NominalCoil
Shell Welded - 297K 107 58 8 150 -14 -119 191
Cool Down (18K) 86 43 1 123 -21 -125 373
11-Tesla 22 11 0 57 -4 -120 374
Collar Nose Von-Mises Stress
At 11T
Coil BlocksAzimuthal Stress
At 11T
FEA predicted results
Click here to add footer 21
Bullet gauges loadingM GuinchardP Grosclaude
8 to 9 kN per bullet
Click here to add footer 22
Electrical tests ndash WhenF-O PincotL Grand Cleacutement
Are performed beforeafter each important construction step Test of pole Nb3Sn before curing - PBC Test of pole Nb3Sn before reaction ndash PBR Test of pole Nb3Sn after reaction ndash PAR Test of pole Nb3Sn after impregnation out of the mould ndash PAI Test of pole Nb3Sn after impregnation with instrumentation ndash PAIWI Test of collared coil before collaring ndash BC Test of collared coil after collaring ndash AC Test of the magnet under load before welding ndash UL Test of the magnet after shell welding ndash AW Test of the magnet after longitudinal coil loading ndash AL Test of the magnet after interconnection ndash AI Final Test of the magnet before delivery - FINAL
Click here to add footer 23
Electrical tests ndash WhatF-O PincotL Grand CleacutementAccording to the construction step we define
specific test valueselectrical tests among which
Resistance measurement(Coils Quench heaters Voltage taps Instrumentation) Inductance measurement Capacitance measurement Dielectric measurement(between coils QH instrumentation ground)
bull Insulation (up to 1kV 30s)bull current leakage (up to 1kV 5min)
Discharge test on coilUp to 1kV
Discharge test on quench heatersUp to 900V or 80AQH
Click here to add footer 24
Electrical testsF-O PincotL Grand Cleacutement
Resistance Insulation dielectric Inductance Capacitance Coil discharge QH discharge
Test phase
code
PBC X X X
PBR X X X
PAR X X X
PAI X X X X
PAIWI X X X X
BC X X X X X X
AC X X X X X X
UL X X
AW X X X X X X
AL X X X X X X
AI X X X X X X
FINAL X X X X X X
Click here to add footer 25
Click here to add footer 26
Plan for power tests coldbull RRR and strain gauge measurementsbull Preliminary tests ndash Setup protection ndash Splice resistance
measurements (current plateaus at 2 4 6 8 and 10 kA) ndash 3 hoursbull Training 43 K ndash 15 quenches ndash 3 days bull Training 19 K ndash 10 quenches ndash 25 days
Stability on current plateau ndash 05 daybull Ramp-rate study 100 As and 50 As ndash 05 day
AC-loss measurements (includes inductance measurement) at 5 to 100 As ndash 05 day
bull Quench heater efficiency study 3 different settings of QH pulse for 3 currents each Long re-cooling of the magnet due to delay of energy extraction ndash 3 days
bull High MIIts tests (protection delay) 6 quenches ndash 3 days
bull Quench propagation velocity measurements acquired for the training quenches
G Willeringbull Cool down bull Day 1
bull Day 2-4bull Day 5-7
bull Day 8
bull Day 9-11
bull Day 12-14
Click here to add footer 27
Further actionsbull After cold tests warm magnetic
measurements will be carried out with the two coils connected
bull Model 1 MBHSP101 single aperture with cable OST RRP 108127 for both polesbull Instrumentation of coils 106 and 107 going onbull Collaring scheduled around middle of June
- CERN-FNAL Video Meeting 12 Progress of the 11T Dipole short m
- Contributions
- Main design features
- Specific features
- Assembly conditions - Winding
- Binder curing
- Reaction treatment
- Reaction treatment ndash Coil 105
- Impregnation
- Instrumentation outer layer
- Instrumentation inner layer
- Quench heaters
- Coils size
- Excess in mid-plane
- Collaring steps
- Shimming plan
- Yoking welding of the shells
- Structural analysis vs measurements
- FEA Results
- ANSYS Forecast at 11-Tesla
- Bullet gauges loading
- Electrical tests ndash When
- Electrical tests ndash What
- Electrical tests
- Slide 25
- Plan for power tests cold
- Further actions
-
Click here to add footer 14
Excess in mid-plane
-150 -50 50 20
030
040
050
060
070
080
090
090
011
0012
0013
0014
000
100
200
300
400
500
600
700
800
leftrightaverage
Coil length [mm]
Inte
rfer
ence
[microm
]
Click here to add footer 15
Collaring steps
2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 320
50100150200250300350400
Distance to collaring position right lead endright return endleft lead endleft return end
F [MN]
offs
et k
ey g
roov
e [micro
m]
With 8MN the stoppers of the collaring tool were in contact
Click here to add footer 16
Shimming planbull Mid-plane is 650 microm beyond expectations To compensate
bull One layer of Kapton was removed on the mid-plane
bull Changed one layer of insulation to 005 microm thickness (in lieu of 0125 microm)
Click here to add footer 17
Yoking welding of the shellsF Lackner
1 2 3 4 5 6 7 80
100200300400500600700800
0
110
206
361426
526610
686Pressure rising April 28th 2014
Pressure rising step
Tota
l cha
rge
in to
ns
3154906157901240166520652225
002040608
SIDE B 0110206361426526610686
Length in [mm]
Yoke
gap
[mm
]
Tota
l loa
d in
tons
Max charge 500 tm on central section to close the welding gap
0
02
04
06
SIDE A0110206361426526610686
Length in [mm]
Yoke
gap
[mm
]
Tota
l loa
d in
tons
Click here to add footer 18
Structural analysis vs measurements
Click here to add footer 19
FEA Results 11T Mirror
FEA Max Cap gauge
pressure (MPa)
FEA Avg Cap gauge
pressure (MPa)
FEA Min Cap gauge
pressure (MPa)
Collar nose
stress (MPa)
Coil Min stress (MPa)
Coil Max Stress (MPa)
Avg Shell Stress (MPa)
Collaring Load 48 33 18 88 -7 -90
Post-Collaring 39 28 16 72 -7 -69
Collar in yoke 40 28 17 73 -9 -66
Max Press force 46 31 15 81 -14 -60 10
Shell Weld + Press Force 50 33 14 87 -16 -61 187
Shell Welded no Press Force 48 32 15 85 -15 -60 194
Collaring Load Post-Collaring Collar in yoke Max Press force Shell Weld + Press Force
Shell Welded no Press Force
Shell Welded - 297K
Cool Down (18K)
11-Tesla0
10
20
30
40
50
60Mirror Coil - contact pressure at pole (Cap Gauge)
FEA Max Cap gauge - pressure (MPa)
FEA Avg Cap gauge - pressure (MPa)
FEA Min Cap gauge - pressure (MPa)
Measured Coil Data (10 error bars)
Pres
sure
(MPa
)
Click here to add footer 20
ANSYS Forecast at 11-Tesla
Assembly Step
Max Capacitive gauge -
pressure (MPa)
Avg Capacitive gauge -
pressure (MPa)
Min Capacitive gauge -
pressure (MPa)
Collar-nose stress (MPa)
Coil Min stress (MPa)
Coil Max Stress (MPa)
Avg Shell Stress (MPa)
MirrorCoil
Shell Welded - 297K 48 32 15 85 -15 -60 195
Cool Down (18K) 37 21 5 62 -5 -74 375
11-Tesla 1 05 0 63 +13 -117 377
NominalCoil
Shell Welded - 297K 107 58 8 150 -14 -119 191
Cool Down (18K) 86 43 1 123 -21 -125 373
11-Tesla 22 11 0 57 -4 -120 374
Collar Nose Von-Mises Stress
At 11T
Coil BlocksAzimuthal Stress
At 11T
FEA predicted results
Click here to add footer 21
Bullet gauges loadingM GuinchardP Grosclaude
8 to 9 kN per bullet
Click here to add footer 22
Electrical tests ndash WhenF-O PincotL Grand Cleacutement
Are performed beforeafter each important construction step Test of pole Nb3Sn before curing - PBC Test of pole Nb3Sn before reaction ndash PBR Test of pole Nb3Sn after reaction ndash PAR Test of pole Nb3Sn after impregnation out of the mould ndash PAI Test of pole Nb3Sn after impregnation with instrumentation ndash PAIWI Test of collared coil before collaring ndash BC Test of collared coil after collaring ndash AC Test of the magnet under load before welding ndash UL Test of the magnet after shell welding ndash AW Test of the magnet after longitudinal coil loading ndash AL Test of the magnet after interconnection ndash AI Final Test of the magnet before delivery - FINAL
Click here to add footer 23
Electrical tests ndash WhatF-O PincotL Grand CleacutementAccording to the construction step we define
specific test valueselectrical tests among which
Resistance measurement(Coils Quench heaters Voltage taps Instrumentation) Inductance measurement Capacitance measurement Dielectric measurement(between coils QH instrumentation ground)
bull Insulation (up to 1kV 30s)bull current leakage (up to 1kV 5min)
Discharge test on coilUp to 1kV
Discharge test on quench heatersUp to 900V or 80AQH
Click here to add footer 24
Electrical testsF-O PincotL Grand Cleacutement
Resistance Insulation dielectric Inductance Capacitance Coil discharge QH discharge
Test phase
code
PBC X X X
PBR X X X
PAR X X X
PAI X X X X
PAIWI X X X X
BC X X X X X X
AC X X X X X X
UL X X
AW X X X X X X
AL X X X X X X
AI X X X X X X
FINAL X X X X X X
Click here to add footer 25
Click here to add footer 26
Plan for power tests coldbull RRR and strain gauge measurementsbull Preliminary tests ndash Setup protection ndash Splice resistance
measurements (current plateaus at 2 4 6 8 and 10 kA) ndash 3 hoursbull Training 43 K ndash 15 quenches ndash 3 days bull Training 19 K ndash 10 quenches ndash 25 days
Stability on current plateau ndash 05 daybull Ramp-rate study 100 As and 50 As ndash 05 day
AC-loss measurements (includes inductance measurement) at 5 to 100 As ndash 05 day
bull Quench heater efficiency study 3 different settings of QH pulse for 3 currents each Long re-cooling of the magnet due to delay of energy extraction ndash 3 days
bull High MIIts tests (protection delay) 6 quenches ndash 3 days
bull Quench propagation velocity measurements acquired for the training quenches
G Willeringbull Cool down bull Day 1
bull Day 2-4bull Day 5-7
bull Day 8
bull Day 9-11
bull Day 12-14
Click here to add footer 27
Further actionsbull After cold tests warm magnetic
measurements will be carried out with the two coils connected
bull Model 1 MBHSP101 single aperture with cable OST RRP 108127 for both polesbull Instrumentation of coils 106 and 107 going onbull Collaring scheduled around middle of June
- CERN-FNAL Video Meeting 12 Progress of the 11T Dipole short m
- Contributions
- Main design features
- Specific features
- Assembly conditions - Winding
- Binder curing
- Reaction treatment
- Reaction treatment ndash Coil 105
- Impregnation
- Instrumentation outer layer
- Instrumentation inner layer
- Quench heaters
- Coils size
- Excess in mid-plane
- Collaring steps
- Shimming plan
- Yoking welding of the shells
- Structural analysis vs measurements
- FEA Results
- ANSYS Forecast at 11-Tesla
- Bullet gauges loading
- Electrical tests ndash When
- Electrical tests ndash What
- Electrical tests
- Slide 25
- Plan for power tests cold
- Further actions
-
Click here to add footer 15
Collaring steps
2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 320
50100150200250300350400
Distance to collaring position right lead endright return endleft lead endleft return end
F [MN]
offs
et k
ey g
roov
e [micro
m]
With 8MN the stoppers of the collaring tool were in contact
Click here to add footer 16
Shimming planbull Mid-plane is 650 microm beyond expectations To compensate
bull One layer of Kapton was removed on the mid-plane
bull Changed one layer of insulation to 005 microm thickness (in lieu of 0125 microm)
Click here to add footer 17
Yoking welding of the shellsF Lackner
1 2 3 4 5 6 7 80
100200300400500600700800
0
110
206
361426
526610
686Pressure rising April 28th 2014
Pressure rising step
Tota
l cha
rge
in to
ns
3154906157901240166520652225
002040608
SIDE B 0110206361426526610686
Length in [mm]
Yoke
gap
[mm
]
Tota
l loa
d in
tons
Max charge 500 tm on central section to close the welding gap
0
02
04
06
SIDE A0110206361426526610686
Length in [mm]
Yoke
gap
[mm
]
Tota
l loa
d in
tons
Click here to add footer 18
Structural analysis vs measurements
Click here to add footer 19
FEA Results 11T Mirror
FEA Max Cap gauge
pressure (MPa)
FEA Avg Cap gauge
pressure (MPa)
FEA Min Cap gauge
pressure (MPa)
Collar nose
stress (MPa)
Coil Min stress (MPa)
Coil Max Stress (MPa)
Avg Shell Stress (MPa)
Collaring Load 48 33 18 88 -7 -90
Post-Collaring 39 28 16 72 -7 -69
Collar in yoke 40 28 17 73 -9 -66
Max Press force 46 31 15 81 -14 -60 10
Shell Weld + Press Force 50 33 14 87 -16 -61 187
Shell Welded no Press Force 48 32 15 85 -15 -60 194
Collaring Load Post-Collaring Collar in yoke Max Press force Shell Weld + Press Force
Shell Welded no Press Force
Shell Welded - 297K
Cool Down (18K)
11-Tesla0
10
20
30
40
50
60Mirror Coil - contact pressure at pole (Cap Gauge)
FEA Max Cap gauge - pressure (MPa)
FEA Avg Cap gauge - pressure (MPa)
FEA Min Cap gauge - pressure (MPa)
Measured Coil Data (10 error bars)
Pres
sure
(MPa
)
Click here to add footer 20
ANSYS Forecast at 11-Tesla
Assembly Step
Max Capacitive gauge -
pressure (MPa)
Avg Capacitive gauge -
pressure (MPa)
Min Capacitive gauge -
pressure (MPa)
Collar-nose stress (MPa)
Coil Min stress (MPa)
Coil Max Stress (MPa)
Avg Shell Stress (MPa)
MirrorCoil
Shell Welded - 297K 48 32 15 85 -15 -60 195
Cool Down (18K) 37 21 5 62 -5 -74 375
11-Tesla 1 05 0 63 +13 -117 377
NominalCoil
Shell Welded - 297K 107 58 8 150 -14 -119 191
Cool Down (18K) 86 43 1 123 -21 -125 373
11-Tesla 22 11 0 57 -4 -120 374
Collar Nose Von-Mises Stress
At 11T
Coil BlocksAzimuthal Stress
At 11T
FEA predicted results
Click here to add footer 21
Bullet gauges loadingM GuinchardP Grosclaude
8 to 9 kN per bullet
Click here to add footer 22
Electrical tests ndash WhenF-O PincotL Grand Cleacutement
Are performed beforeafter each important construction step Test of pole Nb3Sn before curing - PBC Test of pole Nb3Sn before reaction ndash PBR Test of pole Nb3Sn after reaction ndash PAR Test of pole Nb3Sn after impregnation out of the mould ndash PAI Test of pole Nb3Sn after impregnation with instrumentation ndash PAIWI Test of collared coil before collaring ndash BC Test of collared coil after collaring ndash AC Test of the magnet under load before welding ndash UL Test of the magnet after shell welding ndash AW Test of the magnet after longitudinal coil loading ndash AL Test of the magnet after interconnection ndash AI Final Test of the magnet before delivery - FINAL
Click here to add footer 23
Electrical tests ndash WhatF-O PincotL Grand CleacutementAccording to the construction step we define
specific test valueselectrical tests among which
Resistance measurement(Coils Quench heaters Voltage taps Instrumentation) Inductance measurement Capacitance measurement Dielectric measurement(between coils QH instrumentation ground)
bull Insulation (up to 1kV 30s)bull current leakage (up to 1kV 5min)
Discharge test on coilUp to 1kV
Discharge test on quench heatersUp to 900V or 80AQH
Click here to add footer 24
Electrical testsF-O PincotL Grand Cleacutement
Resistance Insulation dielectric Inductance Capacitance Coil discharge QH discharge
Test phase
code
PBC X X X
PBR X X X
PAR X X X
PAI X X X X
PAIWI X X X X
BC X X X X X X
AC X X X X X X
UL X X
AW X X X X X X
AL X X X X X X
AI X X X X X X
FINAL X X X X X X
Click here to add footer 25
Click here to add footer 26
Plan for power tests coldbull RRR and strain gauge measurementsbull Preliminary tests ndash Setup protection ndash Splice resistance
measurements (current plateaus at 2 4 6 8 and 10 kA) ndash 3 hoursbull Training 43 K ndash 15 quenches ndash 3 days bull Training 19 K ndash 10 quenches ndash 25 days
Stability on current plateau ndash 05 daybull Ramp-rate study 100 As and 50 As ndash 05 day
AC-loss measurements (includes inductance measurement) at 5 to 100 As ndash 05 day
bull Quench heater efficiency study 3 different settings of QH pulse for 3 currents each Long re-cooling of the magnet due to delay of energy extraction ndash 3 days
bull High MIIts tests (protection delay) 6 quenches ndash 3 days
bull Quench propagation velocity measurements acquired for the training quenches
G Willeringbull Cool down bull Day 1
bull Day 2-4bull Day 5-7
bull Day 8
bull Day 9-11
bull Day 12-14
Click here to add footer 27
Further actionsbull After cold tests warm magnetic
measurements will be carried out with the two coils connected
bull Model 1 MBHSP101 single aperture with cable OST RRP 108127 for both polesbull Instrumentation of coils 106 and 107 going onbull Collaring scheduled around middle of June
- CERN-FNAL Video Meeting 12 Progress of the 11T Dipole short m
- Contributions
- Main design features
- Specific features
- Assembly conditions - Winding
- Binder curing
- Reaction treatment
- Reaction treatment ndash Coil 105
- Impregnation
- Instrumentation outer layer
- Instrumentation inner layer
- Quench heaters
- Coils size
- Excess in mid-plane
- Collaring steps
- Shimming plan
- Yoking welding of the shells
- Structural analysis vs measurements
- FEA Results
- ANSYS Forecast at 11-Tesla
- Bullet gauges loading
- Electrical tests ndash When
- Electrical tests ndash What
- Electrical tests
- Slide 25
- Plan for power tests cold
- Further actions
-
Click here to add footer 16
Shimming planbull Mid-plane is 650 microm beyond expectations To compensate
bull One layer of Kapton was removed on the mid-plane
bull Changed one layer of insulation to 005 microm thickness (in lieu of 0125 microm)
Click here to add footer 17
Yoking welding of the shellsF Lackner
1 2 3 4 5 6 7 80
100200300400500600700800
0
110
206
361426
526610
686Pressure rising April 28th 2014
Pressure rising step
Tota
l cha
rge
in to
ns
3154906157901240166520652225
002040608
SIDE B 0110206361426526610686
Length in [mm]
Yoke
gap
[mm
]
Tota
l loa
d in
tons
Max charge 500 tm on central section to close the welding gap
0
02
04
06
SIDE A0110206361426526610686
Length in [mm]
Yoke
gap
[mm
]
Tota
l loa
d in
tons
Click here to add footer 18
Structural analysis vs measurements
Click here to add footer 19
FEA Results 11T Mirror
FEA Max Cap gauge
pressure (MPa)
FEA Avg Cap gauge
pressure (MPa)
FEA Min Cap gauge
pressure (MPa)
Collar nose
stress (MPa)
Coil Min stress (MPa)
Coil Max Stress (MPa)
Avg Shell Stress (MPa)
Collaring Load 48 33 18 88 -7 -90
Post-Collaring 39 28 16 72 -7 -69
Collar in yoke 40 28 17 73 -9 -66
Max Press force 46 31 15 81 -14 -60 10
Shell Weld + Press Force 50 33 14 87 -16 -61 187
Shell Welded no Press Force 48 32 15 85 -15 -60 194
Collaring Load Post-Collaring Collar in yoke Max Press force Shell Weld + Press Force
Shell Welded no Press Force
Shell Welded - 297K
Cool Down (18K)
11-Tesla0
10
20
30
40
50
60Mirror Coil - contact pressure at pole (Cap Gauge)
FEA Max Cap gauge - pressure (MPa)
FEA Avg Cap gauge - pressure (MPa)
FEA Min Cap gauge - pressure (MPa)
Measured Coil Data (10 error bars)
Pres
sure
(MPa
)
Click here to add footer 20
ANSYS Forecast at 11-Tesla
Assembly Step
Max Capacitive gauge -
pressure (MPa)
Avg Capacitive gauge -
pressure (MPa)
Min Capacitive gauge -
pressure (MPa)
Collar-nose stress (MPa)
Coil Min stress (MPa)
Coil Max Stress (MPa)
Avg Shell Stress (MPa)
MirrorCoil
Shell Welded - 297K 48 32 15 85 -15 -60 195
Cool Down (18K) 37 21 5 62 -5 -74 375
11-Tesla 1 05 0 63 +13 -117 377
NominalCoil
Shell Welded - 297K 107 58 8 150 -14 -119 191
Cool Down (18K) 86 43 1 123 -21 -125 373
11-Tesla 22 11 0 57 -4 -120 374
Collar Nose Von-Mises Stress
At 11T
Coil BlocksAzimuthal Stress
At 11T
FEA predicted results
Click here to add footer 21
Bullet gauges loadingM GuinchardP Grosclaude
8 to 9 kN per bullet
Click here to add footer 22
Electrical tests ndash WhenF-O PincotL Grand Cleacutement
Are performed beforeafter each important construction step Test of pole Nb3Sn before curing - PBC Test of pole Nb3Sn before reaction ndash PBR Test of pole Nb3Sn after reaction ndash PAR Test of pole Nb3Sn after impregnation out of the mould ndash PAI Test of pole Nb3Sn after impregnation with instrumentation ndash PAIWI Test of collared coil before collaring ndash BC Test of collared coil after collaring ndash AC Test of the magnet under load before welding ndash UL Test of the magnet after shell welding ndash AW Test of the magnet after longitudinal coil loading ndash AL Test of the magnet after interconnection ndash AI Final Test of the magnet before delivery - FINAL
Click here to add footer 23
Electrical tests ndash WhatF-O PincotL Grand CleacutementAccording to the construction step we define
specific test valueselectrical tests among which
Resistance measurement(Coils Quench heaters Voltage taps Instrumentation) Inductance measurement Capacitance measurement Dielectric measurement(between coils QH instrumentation ground)
bull Insulation (up to 1kV 30s)bull current leakage (up to 1kV 5min)
Discharge test on coilUp to 1kV
Discharge test on quench heatersUp to 900V or 80AQH
Click here to add footer 24
Electrical testsF-O PincotL Grand Cleacutement
Resistance Insulation dielectric Inductance Capacitance Coil discharge QH discharge
Test phase
code
PBC X X X
PBR X X X
PAR X X X
PAI X X X X
PAIWI X X X X
BC X X X X X X
AC X X X X X X
UL X X
AW X X X X X X
AL X X X X X X
AI X X X X X X
FINAL X X X X X X
Click here to add footer 25
Click here to add footer 26
Plan for power tests coldbull RRR and strain gauge measurementsbull Preliminary tests ndash Setup protection ndash Splice resistance
measurements (current plateaus at 2 4 6 8 and 10 kA) ndash 3 hoursbull Training 43 K ndash 15 quenches ndash 3 days bull Training 19 K ndash 10 quenches ndash 25 days
Stability on current plateau ndash 05 daybull Ramp-rate study 100 As and 50 As ndash 05 day
AC-loss measurements (includes inductance measurement) at 5 to 100 As ndash 05 day
bull Quench heater efficiency study 3 different settings of QH pulse for 3 currents each Long re-cooling of the magnet due to delay of energy extraction ndash 3 days
bull High MIIts tests (protection delay) 6 quenches ndash 3 days
bull Quench propagation velocity measurements acquired for the training quenches
G Willeringbull Cool down bull Day 1
bull Day 2-4bull Day 5-7
bull Day 8
bull Day 9-11
bull Day 12-14
Click here to add footer 27
Further actionsbull After cold tests warm magnetic
measurements will be carried out with the two coils connected
bull Model 1 MBHSP101 single aperture with cable OST RRP 108127 for both polesbull Instrumentation of coils 106 and 107 going onbull Collaring scheduled around middle of June
- CERN-FNAL Video Meeting 12 Progress of the 11T Dipole short m
- Contributions
- Main design features
- Specific features
- Assembly conditions - Winding
- Binder curing
- Reaction treatment
- Reaction treatment ndash Coil 105
- Impregnation
- Instrumentation outer layer
- Instrumentation inner layer
- Quench heaters
- Coils size
- Excess in mid-plane
- Collaring steps
- Shimming plan
- Yoking welding of the shells
- Structural analysis vs measurements
- FEA Results
- ANSYS Forecast at 11-Tesla
- Bullet gauges loading
- Electrical tests ndash When
- Electrical tests ndash What
- Electrical tests
- Slide 25
- Plan for power tests cold
- Further actions
-
Click here to add footer 17
Yoking welding of the shellsF Lackner
1 2 3 4 5 6 7 80
100200300400500600700800
0
110
206
361426
526610
686Pressure rising April 28th 2014
Pressure rising step
Tota
l cha
rge
in to
ns
3154906157901240166520652225
002040608
SIDE B 0110206361426526610686
Length in [mm]
Yoke
gap
[mm
]
Tota
l loa
d in
tons
Max charge 500 tm on central section to close the welding gap
0
02
04
06
SIDE A0110206361426526610686
Length in [mm]
Yoke
gap
[mm
]
Tota
l loa
d in
tons
Click here to add footer 18
Structural analysis vs measurements
Click here to add footer 19
FEA Results 11T Mirror
FEA Max Cap gauge
pressure (MPa)
FEA Avg Cap gauge
pressure (MPa)
FEA Min Cap gauge
pressure (MPa)
Collar nose
stress (MPa)
Coil Min stress (MPa)
Coil Max Stress (MPa)
Avg Shell Stress (MPa)
Collaring Load 48 33 18 88 -7 -90
Post-Collaring 39 28 16 72 -7 -69
Collar in yoke 40 28 17 73 -9 -66
Max Press force 46 31 15 81 -14 -60 10
Shell Weld + Press Force 50 33 14 87 -16 -61 187
Shell Welded no Press Force 48 32 15 85 -15 -60 194
Collaring Load Post-Collaring Collar in yoke Max Press force Shell Weld + Press Force
Shell Welded no Press Force
Shell Welded - 297K
Cool Down (18K)
11-Tesla0
10
20
30
40
50
60Mirror Coil - contact pressure at pole (Cap Gauge)
FEA Max Cap gauge - pressure (MPa)
FEA Avg Cap gauge - pressure (MPa)
FEA Min Cap gauge - pressure (MPa)
Measured Coil Data (10 error bars)
Pres
sure
(MPa
)
Click here to add footer 20
ANSYS Forecast at 11-Tesla
Assembly Step
Max Capacitive gauge -
pressure (MPa)
Avg Capacitive gauge -
pressure (MPa)
Min Capacitive gauge -
pressure (MPa)
Collar-nose stress (MPa)
Coil Min stress (MPa)
Coil Max Stress (MPa)
Avg Shell Stress (MPa)
MirrorCoil
Shell Welded - 297K 48 32 15 85 -15 -60 195
Cool Down (18K) 37 21 5 62 -5 -74 375
11-Tesla 1 05 0 63 +13 -117 377
NominalCoil
Shell Welded - 297K 107 58 8 150 -14 -119 191
Cool Down (18K) 86 43 1 123 -21 -125 373
11-Tesla 22 11 0 57 -4 -120 374
Collar Nose Von-Mises Stress
At 11T
Coil BlocksAzimuthal Stress
At 11T
FEA predicted results
Click here to add footer 21
Bullet gauges loadingM GuinchardP Grosclaude
8 to 9 kN per bullet
Click here to add footer 22
Electrical tests ndash WhenF-O PincotL Grand Cleacutement
Are performed beforeafter each important construction step Test of pole Nb3Sn before curing - PBC Test of pole Nb3Sn before reaction ndash PBR Test of pole Nb3Sn after reaction ndash PAR Test of pole Nb3Sn after impregnation out of the mould ndash PAI Test of pole Nb3Sn after impregnation with instrumentation ndash PAIWI Test of collared coil before collaring ndash BC Test of collared coil after collaring ndash AC Test of the magnet under load before welding ndash UL Test of the magnet after shell welding ndash AW Test of the magnet after longitudinal coil loading ndash AL Test of the magnet after interconnection ndash AI Final Test of the magnet before delivery - FINAL
Click here to add footer 23
Electrical tests ndash WhatF-O PincotL Grand CleacutementAccording to the construction step we define
specific test valueselectrical tests among which
Resistance measurement(Coils Quench heaters Voltage taps Instrumentation) Inductance measurement Capacitance measurement Dielectric measurement(between coils QH instrumentation ground)
bull Insulation (up to 1kV 30s)bull current leakage (up to 1kV 5min)
Discharge test on coilUp to 1kV
Discharge test on quench heatersUp to 900V or 80AQH
Click here to add footer 24
Electrical testsF-O PincotL Grand Cleacutement
Resistance Insulation dielectric Inductance Capacitance Coil discharge QH discharge
Test phase
code
PBC X X X
PBR X X X
PAR X X X
PAI X X X X
PAIWI X X X X
BC X X X X X X
AC X X X X X X
UL X X
AW X X X X X X
AL X X X X X X
AI X X X X X X
FINAL X X X X X X
Click here to add footer 25
Click here to add footer 26
Plan for power tests coldbull RRR and strain gauge measurementsbull Preliminary tests ndash Setup protection ndash Splice resistance
measurements (current plateaus at 2 4 6 8 and 10 kA) ndash 3 hoursbull Training 43 K ndash 15 quenches ndash 3 days bull Training 19 K ndash 10 quenches ndash 25 days
Stability on current plateau ndash 05 daybull Ramp-rate study 100 As and 50 As ndash 05 day
AC-loss measurements (includes inductance measurement) at 5 to 100 As ndash 05 day
bull Quench heater efficiency study 3 different settings of QH pulse for 3 currents each Long re-cooling of the magnet due to delay of energy extraction ndash 3 days
bull High MIIts tests (protection delay) 6 quenches ndash 3 days
bull Quench propagation velocity measurements acquired for the training quenches
G Willeringbull Cool down bull Day 1
bull Day 2-4bull Day 5-7
bull Day 8
bull Day 9-11
bull Day 12-14
Click here to add footer 27
Further actionsbull After cold tests warm magnetic
measurements will be carried out with the two coils connected
bull Model 1 MBHSP101 single aperture with cable OST RRP 108127 for both polesbull Instrumentation of coils 106 and 107 going onbull Collaring scheduled around middle of June
- CERN-FNAL Video Meeting 12 Progress of the 11T Dipole short m
- Contributions
- Main design features
- Specific features
- Assembly conditions - Winding
- Binder curing
- Reaction treatment
- Reaction treatment ndash Coil 105
- Impregnation
- Instrumentation outer layer
- Instrumentation inner layer
- Quench heaters
- Coils size
- Excess in mid-plane
- Collaring steps
- Shimming plan
- Yoking welding of the shells
- Structural analysis vs measurements
- FEA Results
- ANSYS Forecast at 11-Tesla
- Bullet gauges loading
- Electrical tests ndash When
- Electrical tests ndash What
- Electrical tests
- Slide 25
- Plan for power tests cold
- Further actions
-
Click here to add footer 18
Structural analysis vs measurements
Click here to add footer 19
FEA Results 11T Mirror
FEA Max Cap gauge
pressure (MPa)
FEA Avg Cap gauge
pressure (MPa)
FEA Min Cap gauge
pressure (MPa)
Collar nose
stress (MPa)
Coil Min stress (MPa)
Coil Max Stress (MPa)
Avg Shell Stress (MPa)
Collaring Load 48 33 18 88 -7 -90
Post-Collaring 39 28 16 72 -7 -69
Collar in yoke 40 28 17 73 -9 -66
Max Press force 46 31 15 81 -14 -60 10
Shell Weld + Press Force 50 33 14 87 -16 -61 187
Shell Welded no Press Force 48 32 15 85 -15 -60 194
Collaring Load Post-Collaring Collar in yoke Max Press force Shell Weld + Press Force
Shell Welded no Press Force
Shell Welded - 297K
Cool Down (18K)
11-Tesla0
10
20
30
40
50
60Mirror Coil - contact pressure at pole (Cap Gauge)
FEA Max Cap gauge - pressure (MPa)
FEA Avg Cap gauge - pressure (MPa)
FEA Min Cap gauge - pressure (MPa)
Measured Coil Data (10 error bars)
Pres
sure
(MPa
)
Click here to add footer 20
ANSYS Forecast at 11-Tesla
Assembly Step
Max Capacitive gauge -
pressure (MPa)
Avg Capacitive gauge -
pressure (MPa)
Min Capacitive gauge -
pressure (MPa)
Collar-nose stress (MPa)
Coil Min stress (MPa)
Coil Max Stress (MPa)
Avg Shell Stress (MPa)
MirrorCoil
Shell Welded - 297K 48 32 15 85 -15 -60 195
Cool Down (18K) 37 21 5 62 -5 -74 375
11-Tesla 1 05 0 63 +13 -117 377
NominalCoil
Shell Welded - 297K 107 58 8 150 -14 -119 191
Cool Down (18K) 86 43 1 123 -21 -125 373
11-Tesla 22 11 0 57 -4 -120 374
Collar Nose Von-Mises Stress
At 11T
Coil BlocksAzimuthal Stress
At 11T
FEA predicted results
Click here to add footer 21
Bullet gauges loadingM GuinchardP Grosclaude
8 to 9 kN per bullet
Click here to add footer 22
Electrical tests ndash WhenF-O PincotL Grand Cleacutement
Are performed beforeafter each important construction step Test of pole Nb3Sn before curing - PBC Test of pole Nb3Sn before reaction ndash PBR Test of pole Nb3Sn after reaction ndash PAR Test of pole Nb3Sn after impregnation out of the mould ndash PAI Test of pole Nb3Sn after impregnation with instrumentation ndash PAIWI Test of collared coil before collaring ndash BC Test of collared coil after collaring ndash AC Test of the magnet under load before welding ndash UL Test of the magnet after shell welding ndash AW Test of the magnet after longitudinal coil loading ndash AL Test of the magnet after interconnection ndash AI Final Test of the magnet before delivery - FINAL
Click here to add footer 23
Electrical tests ndash WhatF-O PincotL Grand CleacutementAccording to the construction step we define
specific test valueselectrical tests among which
Resistance measurement(Coils Quench heaters Voltage taps Instrumentation) Inductance measurement Capacitance measurement Dielectric measurement(between coils QH instrumentation ground)
bull Insulation (up to 1kV 30s)bull current leakage (up to 1kV 5min)
Discharge test on coilUp to 1kV
Discharge test on quench heatersUp to 900V or 80AQH
Click here to add footer 24
Electrical testsF-O PincotL Grand Cleacutement
Resistance Insulation dielectric Inductance Capacitance Coil discharge QH discharge
Test phase
code
PBC X X X
PBR X X X
PAR X X X
PAI X X X X
PAIWI X X X X
BC X X X X X X
AC X X X X X X
UL X X
AW X X X X X X
AL X X X X X X
AI X X X X X X
FINAL X X X X X X
Click here to add footer 25
Click here to add footer 26
Plan for power tests coldbull RRR and strain gauge measurementsbull Preliminary tests ndash Setup protection ndash Splice resistance
measurements (current plateaus at 2 4 6 8 and 10 kA) ndash 3 hoursbull Training 43 K ndash 15 quenches ndash 3 days bull Training 19 K ndash 10 quenches ndash 25 days
Stability on current plateau ndash 05 daybull Ramp-rate study 100 As and 50 As ndash 05 day
AC-loss measurements (includes inductance measurement) at 5 to 100 As ndash 05 day
bull Quench heater efficiency study 3 different settings of QH pulse for 3 currents each Long re-cooling of the magnet due to delay of energy extraction ndash 3 days
bull High MIIts tests (protection delay) 6 quenches ndash 3 days
bull Quench propagation velocity measurements acquired for the training quenches
G Willeringbull Cool down bull Day 1
bull Day 2-4bull Day 5-7
bull Day 8
bull Day 9-11
bull Day 12-14
Click here to add footer 27
Further actionsbull After cold tests warm magnetic
measurements will be carried out with the two coils connected
bull Model 1 MBHSP101 single aperture with cable OST RRP 108127 for both polesbull Instrumentation of coils 106 and 107 going onbull Collaring scheduled around middle of June
- CERN-FNAL Video Meeting 12 Progress of the 11T Dipole short m
- Contributions
- Main design features
- Specific features
- Assembly conditions - Winding
- Binder curing
- Reaction treatment
- Reaction treatment ndash Coil 105
- Impregnation
- Instrumentation outer layer
- Instrumentation inner layer
- Quench heaters
- Coils size
- Excess in mid-plane
- Collaring steps
- Shimming plan
- Yoking welding of the shells
- Structural analysis vs measurements
- FEA Results
- ANSYS Forecast at 11-Tesla
- Bullet gauges loading
- Electrical tests ndash When
- Electrical tests ndash What
- Electrical tests
- Slide 25
- Plan for power tests cold
- Further actions
-
Click here to add footer 19
FEA Results 11T Mirror
FEA Max Cap gauge
pressure (MPa)
FEA Avg Cap gauge
pressure (MPa)
FEA Min Cap gauge
pressure (MPa)
Collar nose
stress (MPa)
Coil Min stress (MPa)
Coil Max Stress (MPa)
Avg Shell Stress (MPa)
Collaring Load 48 33 18 88 -7 -90
Post-Collaring 39 28 16 72 -7 -69
Collar in yoke 40 28 17 73 -9 -66
Max Press force 46 31 15 81 -14 -60 10
Shell Weld + Press Force 50 33 14 87 -16 -61 187
Shell Welded no Press Force 48 32 15 85 -15 -60 194
Collaring Load Post-Collaring Collar in yoke Max Press force Shell Weld + Press Force
Shell Welded no Press Force
Shell Welded - 297K
Cool Down (18K)
11-Tesla0
10
20
30
40
50
60Mirror Coil - contact pressure at pole (Cap Gauge)
FEA Max Cap gauge - pressure (MPa)
FEA Avg Cap gauge - pressure (MPa)
FEA Min Cap gauge - pressure (MPa)
Measured Coil Data (10 error bars)
Pres
sure
(MPa
)
Click here to add footer 20
ANSYS Forecast at 11-Tesla
Assembly Step
Max Capacitive gauge -
pressure (MPa)
Avg Capacitive gauge -
pressure (MPa)
Min Capacitive gauge -
pressure (MPa)
Collar-nose stress (MPa)
Coil Min stress (MPa)
Coil Max Stress (MPa)
Avg Shell Stress (MPa)
MirrorCoil
Shell Welded - 297K 48 32 15 85 -15 -60 195
Cool Down (18K) 37 21 5 62 -5 -74 375
11-Tesla 1 05 0 63 +13 -117 377
NominalCoil
Shell Welded - 297K 107 58 8 150 -14 -119 191
Cool Down (18K) 86 43 1 123 -21 -125 373
11-Tesla 22 11 0 57 -4 -120 374
Collar Nose Von-Mises Stress
At 11T
Coil BlocksAzimuthal Stress
At 11T
FEA predicted results
Click here to add footer 21
Bullet gauges loadingM GuinchardP Grosclaude
8 to 9 kN per bullet
Click here to add footer 22
Electrical tests ndash WhenF-O PincotL Grand Cleacutement
Are performed beforeafter each important construction step Test of pole Nb3Sn before curing - PBC Test of pole Nb3Sn before reaction ndash PBR Test of pole Nb3Sn after reaction ndash PAR Test of pole Nb3Sn after impregnation out of the mould ndash PAI Test of pole Nb3Sn after impregnation with instrumentation ndash PAIWI Test of collared coil before collaring ndash BC Test of collared coil after collaring ndash AC Test of the magnet under load before welding ndash UL Test of the magnet after shell welding ndash AW Test of the magnet after longitudinal coil loading ndash AL Test of the magnet after interconnection ndash AI Final Test of the magnet before delivery - FINAL
Click here to add footer 23
Electrical tests ndash WhatF-O PincotL Grand CleacutementAccording to the construction step we define
specific test valueselectrical tests among which
Resistance measurement(Coils Quench heaters Voltage taps Instrumentation) Inductance measurement Capacitance measurement Dielectric measurement(between coils QH instrumentation ground)
bull Insulation (up to 1kV 30s)bull current leakage (up to 1kV 5min)
Discharge test on coilUp to 1kV
Discharge test on quench heatersUp to 900V or 80AQH
Click here to add footer 24
Electrical testsF-O PincotL Grand Cleacutement
Resistance Insulation dielectric Inductance Capacitance Coil discharge QH discharge
Test phase
code
PBC X X X
PBR X X X
PAR X X X
PAI X X X X
PAIWI X X X X
BC X X X X X X
AC X X X X X X
UL X X
AW X X X X X X
AL X X X X X X
AI X X X X X X
FINAL X X X X X X
Click here to add footer 25
Click here to add footer 26
Plan for power tests coldbull RRR and strain gauge measurementsbull Preliminary tests ndash Setup protection ndash Splice resistance
measurements (current plateaus at 2 4 6 8 and 10 kA) ndash 3 hoursbull Training 43 K ndash 15 quenches ndash 3 days bull Training 19 K ndash 10 quenches ndash 25 days
Stability on current plateau ndash 05 daybull Ramp-rate study 100 As and 50 As ndash 05 day
AC-loss measurements (includes inductance measurement) at 5 to 100 As ndash 05 day
bull Quench heater efficiency study 3 different settings of QH pulse for 3 currents each Long re-cooling of the magnet due to delay of energy extraction ndash 3 days
bull High MIIts tests (protection delay) 6 quenches ndash 3 days
bull Quench propagation velocity measurements acquired for the training quenches
G Willeringbull Cool down bull Day 1
bull Day 2-4bull Day 5-7
bull Day 8
bull Day 9-11
bull Day 12-14
Click here to add footer 27
Further actionsbull After cold tests warm magnetic
measurements will be carried out with the two coils connected
bull Model 1 MBHSP101 single aperture with cable OST RRP 108127 for both polesbull Instrumentation of coils 106 and 107 going onbull Collaring scheduled around middle of June
- CERN-FNAL Video Meeting 12 Progress of the 11T Dipole short m
- Contributions
- Main design features
- Specific features
- Assembly conditions - Winding
- Binder curing
- Reaction treatment
- Reaction treatment ndash Coil 105
- Impregnation
- Instrumentation outer layer
- Instrumentation inner layer
- Quench heaters
- Coils size
- Excess in mid-plane
- Collaring steps
- Shimming plan
- Yoking welding of the shells
- Structural analysis vs measurements
- FEA Results
- ANSYS Forecast at 11-Tesla
- Bullet gauges loading
- Electrical tests ndash When
- Electrical tests ndash What
- Electrical tests
- Slide 25
- Plan for power tests cold
- Further actions
-
Click here to add footer 20
ANSYS Forecast at 11-Tesla
Assembly Step
Max Capacitive gauge -
pressure (MPa)
Avg Capacitive gauge -
pressure (MPa)
Min Capacitive gauge -
pressure (MPa)
Collar-nose stress (MPa)
Coil Min stress (MPa)
Coil Max Stress (MPa)
Avg Shell Stress (MPa)
MirrorCoil
Shell Welded - 297K 48 32 15 85 -15 -60 195
Cool Down (18K) 37 21 5 62 -5 -74 375
11-Tesla 1 05 0 63 +13 -117 377
NominalCoil
Shell Welded - 297K 107 58 8 150 -14 -119 191
Cool Down (18K) 86 43 1 123 -21 -125 373
11-Tesla 22 11 0 57 -4 -120 374
Collar Nose Von-Mises Stress
At 11T
Coil BlocksAzimuthal Stress
At 11T
FEA predicted results
Click here to add footer 21
Bullet gauges loadingM GuinchardP Grosclaude
8 to 9 kN per bullet
Click here to add footer 22
Electrical tests ndash WhenF-O PincotL Grand Cleacutement
Are performed beforeafter each important construction step Test of pole Nb3Sn before curing - PBC Test of pole Nb3Sn before reaction ndash PBR Test of pole Nb3Sn after reaction ndash PAR Test of pole Nb3Sn after impregnation out of the mould ndash PAI Test of pole Nb3Sn after impregnation with instrumentation ndash PAIWI Test of collared coil before collaring ndash BC Test of collared coil after collaring ndash AC Test of the magnet under load before welding ndash UL Test of the magnet after shell welding ndash AW Test of the magnet after longitudinal coil loading ndash AL Test of the magnet after interconnection ndash AI Final Test of the magnet before delivery - FINAL
Click here to add footer 23
Electrical tests ndash WhatF-O PincotL Grand CleacutementAccording to the construction step we define
specific test valueselectrical tests among which
Resistance measurement(Coils Quench heaters Voltage taps Instrumentation) Inductance measurement Capacitance measurement Dielectric measurement(between coils QH instrumentation ground)
bull Insulation (up to 1kV 30s)bull current leakage (up to 1kV 5min)
Discharge test on coilUp to 1kV
Discharge test on quench heatersUp to 900V or 80AQH
Click here to add footer 24
Electrical testsF-O PincotL Grand Cleacutement
Resistance Insulation dielectric Inductance Capacitance Coil discharge QH discharge
Test phase
code
PBC X X X
PBR X X X
PAR X X X
PAI X X X X
PAIWI X X X X
BC X X X X X X
AC X X X X X X
UL X X
AW X X X X X X
AL X X X X X X
AI X X X X X X
FINAL X X X X X X
Click here to add footer 25
Click here to add footer 26
Plan for power tests coldbull RRR and strain gauge measurementsbull Preliminary tests ndash Setup protection ndash Splice resistance
measurements (current plateaus at 2 4 6 8 and 10 kA) ndash 3 hoursbull Training 43 K ndash 15 quenches ndash 3 days bull Training 19 K ndash 10 quenches ndash 25 days
Stability on current plateau ndash 05 daybull Ramp-rate study 100 As and 50 As ndash 05 day
AC-loss measurements (includes inductance measurement) at 5 to 100 As ndash 05 day
bull Quench heater efficiency study 3 different settings of QH pulse for 3 currents each Long re-cooling of the magnet due to delay of energy extraction ndash 3 days
bull High MIIts tests (protection delay) 6 quenches ndash 3 days
bull Quench propagation velocity measurements acquired for the training quenches
G Willeringbull Cool down bull Day 1
bull Day 2-4bull Day 5-7
bull Day 8
bull Day 9-11
bull Day 12-14
Click here to add footer 27
Further actionsbull After cold tests warm magnetic
measurements will be carried out with the two coils connected
bull Model 1 MBHSP101 single aperture with cable OST RRP 108127 for both polesbull Instrumentation of coils 106 and 107 going onbull Collaring scheduled around middle of June
- CERN-FNAL Video Meeting 12 Progress of the 11T Dipole short m
- Contributions
- Main design features
- Specific features
- Assembly conditions - Winding
- Binder curing
- Reaction treatment
- Reaction treatment ndash Coil 105
- Impregnation
- Instrumentation outer layer
- Instrumentation inner layer
- Quench heaters
- Coils size
- Excess in mid-plane
- Collaring steps
- Shimming plan
- Yoking welding of the shells
- Structural analysis vs measurements
- FEA Results
- ANSYS Forecast at 11-Tesla
- Bullet gauges loading
- Electrical tests ndash When
- Electrical tests ndash What
- Electrical tests
- Slide 25
- Plan for power tests cold
- Further actions
-
Click here to add footer 21
Bullet gauges loadingM GuinchardP Grosclaude
8 to 9 kN per bullet
Click here to add footer 22
Electrical tests ndash WhenF-O PincotL Grand Cleacutement
Are performed beforeafter each important construction step Test of pole Nb3Sn before curing - PBC Test of pole Nb3Sn before reaction ndash PBR Test of pole Nb3Sn after reaction ndash PAR Test of pole Nb3Sn after impregnation out of the mould ndash PAI Test of pole Nb3Sn after impregnation with instrumentation ndash PAIWI Test of collared coil before collaring ndash BC Test of collared coil after collaring ndash AC Test of the magnet under load before welding ndash UL Test of the magnet after shell welding ndash AW Test of the magnet after longitudinal coil loading ndash AL Test of the magnet after interconnection ndash AI Final Test of the magnet before delivery - FINAL
Click here to add footer 23
Electrical tests ndash WhatF-O PincotL Grand CleacutementAccording to the construction step we define
specific test valueselectrical tests among which
Resistance measurement(Coils Quench heaters Voltage taps Instrumentation) Inductance measurement Capacitance measurement Dielectric measurement(between coils QH instrumentation ground)
bull Insulation (up to 1kV 30s)bull current leakage (up to 1kV 5min)
Discharge test on coilUp to 1kV
Discharge test on quench heatersUp to 900V or 80AQH
Click here to add footer 24
Electrical testsF-O PincotL Grand Cleacutement
Resistance Insulation dielectric Inductance Capacitance Coil discharge QH discharge
Test phase
code
PBC X X X
PBR X X X
PAR X X X
PAI X X X X
PAIWI X X X X
BC X X X X X X
AC X X X X X X
UL X X
AW X X X X X X
AL X X X X X X
AI X X X X X X
FINAL X X X X X X
Click here to add footer 25
Click here to add footer 26
Plan for power tests coldbull RRR and strain gauge measurementsbull Preliminary tests ndash Setup protection ndash Splice resistance
measurements (current plateaus at 2 4 6 8 and 10 kA) ndash 3 hoursbull Training 43 K ndash 15 quenches ndash 3 days bull Training 19 K ndash 10 quenches ndash 25 days
Stability on current plateau ndash 05 daybull Ramp-rate study 100 As and 50 As ndash 05 day
AC-loss measurements (includes inductance measurement) at 5 to 100 As ndash 05 day
bull Quench heater efficiency study 3 different settings of QH pulse for 3 currents each Long re-cooling of the magnet due to delay of energy extraction ndash 3 days
bull High MIIts tests (protection delay) 6 quenches ndash 3 days
bull Quench propagation velocity measurements acquired for the training quenches
G Willeringbull Cool down bull Day 1
bull Day 2-4bull Day 5-7
bull Day 8
bull Day 9-11
bull Day 12-14
Click here to add footer 27
Further actionsbull After cold tests warm magnetic
measurements will be carried out with the two coils connected
bull Model 1 MBHSP101 single aperture with cable OST RRP 108127 for both polesbull Instrumentation of coils 106 and 107 going onbull Collaring scheduled around middle of June
- CERN-FNAL Video Meeting 12 Progress of the 11T Dipole short m
- Contributions
- Main design features
- Specific features
- Assembly conditions - Winding
- Binder curing
- Reaction treatment
- Reaction treatment ndash Coil 105
- Impregnation
- Instrumentation outer layer
- Instrumentation inner layer
- Quench heaters
- Coils size
- Excess in mid-plane
- Collaring steps
- Shimming plan
- Yoking welding of the shells
- Structural analysis vs measurements
- FEA Results
- ANSYS Forecast at 11-Tesla
- Bullet gauges loading
- Electrical tests ndash When
- Electrical tests ndash What
- Electrical tests
- Slide 25
- Plan for power tests cold
- Further actions
-
Click here to add footer 22
Electrical tests ndash WhenF-O PincotL Grand Cleacutement
Are performed beforeafter each important construction step Test of pole Nb3Sn before curing - PBC Test of pole Nb3Sn before reaction ndash PBR Test of pole Nb3Sn after reaction ndash PAR Test of pole Nb3Sn after impregnation out of the mould ndash PAI Test of pole Nb3Sn after impregnation with instrumentation ndash PAIWI Test of collared coil before collaring ndash BC Test of collared coil after collaring ndash AC Test of the magnet under load before welding ndash UL Test of the magnet after shell welding ndash AW Test of the magnet after longitudinal coil loading ndash AL Test of the magnet after interconnection ndash AI Final Test of the magnet before delivery - FINAL
Click here to add footer 23
Electrical tests ndash WhatF-O PincotL Grand CleacutementAccording to the construction step we define
specific test valueselectrical tests among which
Resistance measurement(Coils Quench heaters Voltage taps Instrumentation) Inductance measurement Capacitance measurement Dielectric measurement(between coils QH instrumentation ground)
bull Insulation (up to 1kV 30s)bull current leakage (up to 1kV 5min)
Discharge test on coilUp to 1kV
Discharge test on quench heatersUp to 900V or 80AQH
Click here to add footer 24
Electrical testsF-O PincotL Grand Cleacutement
Resistance Insulation dielectric Inductance Capacitance Coil discharge QH discharge
Test phase
code
PBC X X X
PBR X X X
PAR X X X
PAI X X X X
PAIWI X X X X
BC X X X X X X
AC X X X X X X
UL X X
AW X X X X X X
AL X X X X X X
AI X X X X X X
FINAL X X X X X X
Click here to add footer 25
Click here to add footer 26
Plan for power tests coldbull RRR and strain gauge measurementsbull Preliminary tests ndash Setup protection ndash Splice resistance
measurements (current plateaus at 2 4 6 8 and 10 kA) ndash 3 hoursbull Training 43 K ndash 15 quenches ndash 3 days bull Training 19 K ndash 10 quenches ndash 25 days
Stability on current plateau ndash 05 daybull Ramp-rate study 100 As and 50 As ndash 05 day
AC-loss measurements (includes inductance measurement) at 5 to 100 As ndash 05 day
bull Quench heater efficiency study 3 different settings of QH pulse for 3 currents each Long re-cooling of the magnet due to delay of energy extraction ndash 3 days
bull High MIIts tests (protection delay) 6 quenches ndash 3 days
bull Quench propagation velocity measurements acquired for the training quenches
G Willeringbull Cool down bull Day 1
bull Day 2-4bull Day 5-7
bull Day 8
bull Day 9-11
bull Day 12-14
Click here to add footer 27
Further actionsbull After cold tests warm magnetic
measurements will be carried out with the two coils connected
bull Model 1 MBHSP101 single aperture with cable OST RRP 108127 for both polesbull Instrumentation of coils 106 and 107 going onbull Collaring scheduled around middle of June
- CERN-FNAL Video Meeting 12 Progress of the 11T Dipole short m
- Contributions
- Main design features
- Specific features
- Assembly conditions - Winding
- Binder curing
- Reaction treatment
- Reaction treatment ndash Coil 105
- Impregnation
- Instrumentation outer layer
- Instrumentation inner layer
- Quench heaters
- Coils size
- Excess in mid-plane
- Collaring steps
- Shimming plan
- Yoking welding of the shells
- Structural analysis vs measurements
- FEA Results
- ANSYS Forecast at 11-Tesla
- Bullet gauges loading
- Electrical tests ndash When
- Electrical tests ndash What
- Electrical tests
- Slide 25
- Plan for power tests cold
- Further actions
-
Click here to add footer 23
Electrical tests ndash WhatF-O PincotL Grand CleacutementAccording to the construction step we define
specific test valueselectrical tests among which
Resistance measurement(Coils Quench heaters Voltage taps Instrumentation) Inductance measurement Capacitance measurement Dielectric measurement(between coils QH instrumentation ground)
bull Insulation (up to 1kV 30s)bull current leakage (up to 1kV 5min)
Discharge test on coilUp to 1kV
Discharge test on quench heatersUp to 900V or 80AQH
Click here to add footer 24
Electrical testsF-O PincotL Grand Cleacutement
Resistance Insulation dielectric Inductance Capacitance Coil discharge QH discharge
Test phase
code
PBC X X X
PBR X X X
PAR X X X
PAI X X X X
PAIWI X X X X
BC X X X X X X
AC X X X X X X
UL X X
AW X X X X X X
AL X X X X X X
AI X X X X X X
FINAL X X X X X X
Click here to add footer 25
Click here to add footer 26
Plan for power tests coldbull RRR and strain gauge measurementsbull Preliminary tests ndash Setup protection ndash Splice resistance
measurements (current plateaus at 2 4 6 8 and 10 kA) ndash 3 hoursbull Training 43 K ndash 15 quenches ndash 3 days bull Training 19 K ndash 10 quenches ndash 25 days
Stability on current plateau ndash 05 daybull Ramp-rate study 100 As and 50 As ndash 05 day
AC-loss measurements (includes inductance measurement) at 5 to 100 As ndash 05 day
bull Quench heater efficiency study 3 different settings of QH pulse for 3 currents each Long re-cooling of the magnet due to delay of energy extraction ndash 3 days
bull High MIIts tests (protection delay) 6 quenches ndash 3 days
bull Quench propagation velocity measurements acquired for the training quenches
G Willeringbull Cool down bull Day 1
bull Day 2-4bull Day 5-7
bull Day 8
bull Day 9-11
bull Day 12-14
Click here to add footer 27
Further actionsbull After cold tests warm magnetic
measurements will be carried out with the two coils connected
bull Model 1 MBHSP101 single aperture with cable OST RRP 108127 for both polesbull Instrumentation of coils 106 and 107 going onbull Collaring scheduled around middle of June
- CERN-FNAL Video Meeting 12 Progress of the 11T Dipole short m
- Contributions
- Main design features
- Specific features
- Assembly conditions - Winding
- Binder curing
- Reaction treatment
- Reaction treatment ndash Coil 105
- Impregnation
- Instrumentation outer layer
- Instrumentation inner layer
- Quench heaters
- Coils size
- Excess in mid-plane
- Collaring steps
- Shimming plan
- Yoking welding of the shells
- Structural analysis vs measurements
- FEA Results
- ANSYS Forecast at 11-Tesla
- Bullet gauges loading
- Electrical tests ndash When
- Electrical tests ndash What
- Electrical tests
- Slide 25
- Plan for power tests cold
- Further actions
-
Click here to add footer 24
Electrical testsF-O PincotL Grand Cleacutement
Resistance Insulation dielectric Inductance Capacitance Coil discharge QH discharge
Test phase
code
PBC X X X
PBR X X X
PAR X X X
PAI X X X X
PAIWI X X X X
BC X X X X X X
AC X X X X X X
UL X X
AW X X X X X X
AL X X X X X X
AI X X X X X X
FINAL X X X X X X
Click here to add footer 25
Click here to add footer 26
Plan for power tests coldbull RRR and strain gauge measurementsbull Preliminary tests ndash Setup protection ndash Splice resistance
measurements (current plateaus at 2 4 6 8 and 10 kA) ndash 3 hoursbull Training 43 K ndash 15 quenches ndash 3 days bull Training 19 K ndash 10 quenches ndash 25 days
Stability on current plateau ndash 05 daybull Ramp-rate study 100 As and 50 As ndash 05 day
AC-loss measurements (includes inductance measurement) at 5 to 100 As ndash 05 day
bull Quench heater efficiency study 3 different settings of QH pulse for 3 currents each Long re-cooling of the magnet due to delay of energy extraction ndash 3 days
bull High MIIts tests (protection delay) 6 quenches ndash 3 days
bull Quench propagation velocity measurements acquired for the training quenches
G Willeringbull Cool down bull Day 1
bull Day 2-4bull Day 5-7
bull Day 8
bull Day 9-11
bull Day 12-14
Click here to add footer 27
Further actionsbull After cold tests warm magnetic
measurements will be carried out with the two coils connected
bull Model 1 MBHSP101 single aperture with cable OST RRP 108127 for both polesbull Instrumentation of coils 106 and 107 going onbull Collaring scheduled around middle of June
- CERN-FNAL Video Meeting 12 Progress of the 11T Dipole short m
- Contributions
- Main design features
- Specific features
- Assembly conditions - Winding
- Binder curing
- Reaction treatment
- Reaction treatment ndash Coil 105
- Impregnation
- Instrumentation outer layer
- Instrumentation inner layer
- Quench heaters
- Coils size
- Excess in mid-plane
- Collaring steps
- Shimming plan
- Yoking welding of the shells
- Structural analysis vs measurements
- FEA Results
- ANSYS Forecast at 11-Tesla
- Bullet gauges loading
- Electrical tests ndash When
- Electrical tests ndash What
- Electrical tests
- Slide 25
- Plan for power tests cold
- Further actions
-
Click here to add footer 25
Click here to add footer 26
Plan for power tests coldbull RRR and strain gauge measurementsbull Preliminary tests ndash Setup protection ndash Splice resistance
measurements (current plateaus at 2 4 6 8 and 10 kA) ndash 3 hoursbull Training 43 K ndash 15 quenches ndash 3 days bull Training 19 K ndash 10 quenches ndash 25 days
Stability on current plateau ndash 05 daybull Ramp-rate study 100 As and 50 As ndash 05 day
AC-loss measurements (includes inductance measurement) at 5 to 100 As ndash 05 day
bull Quench heater efficiency study 3 different settings of QH pulse for 3 currents each Long re-cooling of the magnet due to delay of energy extraction ndash 3 days
bull High MIIts tests (protection delay) 6 quenches ndash 3 days
bull Quench propagation velocity measurements acquired for the training quenches
G Willeringbull Cool down bull Day 1
bull Day 2-4bull Day 5-7
bull Day 8
bull Day 9-11
bull Day 12-14
Click here to add footer 27
Further actionsbull After cold tests warm magnetic
measurements will be carried out with the two coils connected
bull Model 1 MBHSP101 single aperture with cable OST RRP 108127 for both polesbull Instrumentation of coils 106 and 107 going onbull Collaring scheduled around middle of June
- CERN-FNAL Video Meeting 12 Progress of the 11T Dipole short m
- Contributions
- Main design features
- Specific features
- Assembly conditions - Winding
- Binder curing
- Reaction treatment
- Reaction treatment ndash Coil 105
- Impregnation
- Instrumentation outer layer
- Instrumentation inner layer
- Quench heaters
- Coils size
- Excess in mid-plane
- Collaring steps
- Shimming plan
- Yoking welding of the shells
- Structural analysis vs measurements
- FEA Results
- ANSYS Forecast at 11-Tesla
- Bullet gauges loading
- Electrical tests ndash When
- Electrical tests ndash What
- Electrical tests
- Slide 25
- Plan for power tests cold
- Further actions
-
Click here to add footer 26
Plan for power tests coldbull RRR and strain gauge measurementsbull Preliminary tests ndash Setup protection ndash Splice resistance
measurements (current plateaus at 2 4 6 8 and 10 kA) ndash 3 hoursbull Training 43 K ndash 15 quenches ndash 3 days bull Training 19 K ndash 10 quenches ndash 25 days
Stability on current plateau ndash 05 daybull Ramp-rate study 100 As and 50 As ndash 05 day
AC-loss measurements (includes inductance measurement) at 5 to 100 As ndash 05 day
bull Quench heater efficiency study 3 different settings of QH pulse for 3 currents each Long re-cooling of the magnet due to delay of energy extraction ndash 3 days
bull High MIIts tests (protection delay) 6 quenches ndash 3 days
bull Quench propagation velocity measurements acquired for the training quenches
G Willeringbull Cool down bull Day 1
bull Day 2-4bull Day 5-7
bull Day 8
bull Day 9-11
bull Day 12-14
Click here to add footer 27
Further actionsbull After cold tests warm magnetic
measurements will be carried out with the two coils connected
bull Model 1 MBHSP101 single aperture with cable OST RRP 108127 for both polesbull Instrumentation of coils 106 and 107 going onbull Collaring scheduled around middle of June
- CERN-FNAL Video Meeting 12 Progress of the 11T Dipole short m
- Contributions
- Main design features
- Specific features
- Assembly conditions - Winding
- Binder curing
- Reaction treatment
- Reaction treatment ndash Coil 105
- Impregnation
- Instrumentation outer layer
- Instrumentation inner layer
- Quench heaters
- Coils size
- Excess in mid-plane
- Collaring steps
- Shimming plan
- Yoking welding of the shells
- Structural analysis vs measurements
- FEA Results
- ANSYS Forecast at 11-Tesla
- Bullet gauges loading
- Electrical tests ndash When
- Electrical tests ndash What
- Electrical tests
- Slide 25
- Plan for power tests cold
- Further actions
-
Click here to add footer 27
Further actionsbull After cold tests warm magnetic
measurements will be carried out with the two coils connected
bull Model 1 MBHSP101 single aperture with cable OST RRP 108127 for both polesbull Instrumentation of coils 106 and 107 going onbull Collaring scheduled around middle of June
- CERN-FNAL Video Meeting 12 Progress of the 11T Dipole short m
- Contributions
- Main design features
- Specific features
- Assembly conditions - Winding
- Binder curing
- Reaction treatment
- Reaction treatment ndash Coil 105
- Impregnation
- Instrumentation outer layer
- Instrumentation inner layer
- Quench heaters
- Coils size
- Excess in mid-plane
- Collaring steps
- Shimming plan
- Yoking welding of the shells
- Structural analysis vs measurements
- FEA Results
- ANSYS Forecast at 11-Tesla
- Bullet gauges loading
- Electrical tests ndash When
- Electrical tests ndash What
- Electrical tests
- Slide 25
- Plan for power tests cold
- Further actions
-