cern mbhsm0101 general status f. savary on behalf of the 11t dipole project team

27
CERN-FNAL Video Meeting #12 Progress of the 11T Dipole short model program (Task 2 of HL-LHC WP-11) CERN MBHSM0101 general status F. Savary on behalf of the 11T Dipole Project Team

Upload: evelia

Post on 17-Feb-2016

58 views

Category:

Documents


2 download

DESCRIPTION

CERN-FNAL Video Meeting #12 Progress of the 11T Dipole short model program (Task 2 of HL-LHC WP-11). CERN MBHSM0101 general status F. Savary on behalf of the 11T Dipole Project Team. Contributions. - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: CERN MBHSM0101 general  status F. Savary on behalf of the 11T Dipole Project Team

CERN-FNAL Video Meeting 12

Progress of the 11T Dipole short model program (Task 2 of HL-LHC WP-11)

CERN MBHSM0101 general statusF Savary on behalf of the 11T Dipole Project Team

Click here to add footer 2

Contributionsbull Bateman R1 Batts S 1 Bourcey N Cote D Duret M

Fernandes C Izquierdo Bermudez S Gauthier R Guinchard M Grand-Clement L Grosclaude P Grospelier E Jokinen A 1 Juchno M Julien V Karppinen M Lackner F Lambert L Loumlffler C Lyon T-J Mazet J Peray N Pincot F-O Savary F Schmid N Smekens D Willering G

bull 1Oxford Instrument

Click here to add footer 3

Main design featuresbull Single aperture 6-bloc designbull 56 turns

bull 22 on IL (4 blocs)bull 34 on OL (2 blocs)

bull Aperture 60 mmbull Coil length 18 mbull Yoke OD 510 mmbull Shell thickness 12 mm [AISI 304L]

Click here to add footer 4

Specific featuresbull Copper coil 101

bull End spacers CERN v0 longer coilbull Sc coil 105

bull Cable OST RRP 108127bull ODS alloy wedgesbull CERN V4 end spacers SLS (with flex hinge legs)bull Metallic saddles and splice blocksbull External trace glued on coil OD carrying V-taps and quench

heaters (next slide)bull Collars and yoke laminations produced by EDM

bull Collars YUS130S Nippon Steel 3 mm thickness (LHC dipole)bull Yoke laminations Arcelor Magnetil Low C steel 58 mm

thickness (LHC dipole)

Click here to add footer 5

Assembly conditions - Windingbull Winding tension

bull Coil 101 300 N insulation defects gt1bull Coil 105 250 N insulation defects 0

bull Cable insulationbull Coils 101 and 105

bull Outer sleeve AGY S-2 Glass 11 Tex direct braidingbull Inner dielectric Cogebi Firox 80 microm Mica ndash Fiber glass tape

bull Winding monitoring during coil 105 production

D SmekensJ Mazet

Coils longer than expected ~20 mm

Click here to add footer 6

Binder curingbull Binder CTD 1202-X qty

bull Coil 101 IL in excess OL in excessbull Coil 105 IL 100 g OL 100 g

bull Shimming nominal (shimming such that in the press the mid-plane of the cured coil is like in the magnet 012 mm above center axis)bull This is different compared to FERMILAB where oversized shimming

is used to compact the coil mid-plane beyond its nominal position in order to obtain a smaller coil size before entering into reaction

bull With a load of 08 MN the mold is nearly closed (lt 01mm)bull Then a load of 2 MN is used for IL and 42 MN for the OL

(complete pole)bull The stress in the coils may not exceed 37 MPa at that stage

D SmekensJ Mazet

Click here to add footer 7

Reaction treatmentbull Cavity of the reaction fixture is radially bigger than the curing

mold by 01 mm and of similar dimension at coil mid-planebull Thus if the curing press can be closed before reaching 37

MPa the coil cannot be subjected to higher stress when closing the fixture However the dry fiber glass and the tight tolerances induce large friction also a possible dimensional problem with the sealing foils could have generated interference between the sealing foil and the baseplate preventing correct closure of the fixture

bull The tightening torque to close the fixture was of the order of 300 Nm (FNAL applies 110 Nm to 160 Nm)

bull Not clear no coil contraction after reaction actually less that 1 mm when 45 mm were expected

D SmekensN BourceyF Lackner

Click here to add footer 8

Reaction treatment ndash Coil 105

Adjustment of dwell time to compensate the delay between the

temperature and tooling temperature

The homogeneity of T during ramp up was not very good plusmn

9degCHowever it is OK during

dwell time

N BourceyF Lackner

Click here to add footer 9

Impregnationbull Resin CTD 101K

bull Anhydride cured epoxy system with excellent performance at cryogenic temperature and radiation resistance

bull The resin is preheated and the coil is impregnated at 60degC

bull Curing 110degC for 5 hoursbull Post curing heating 125degC for 16 hours

R GauthierD Smekens

Temperature [degC] Pot life [h] Viscosity [mmmiddotPas]25 145 1300

40 60 400

60 20 100

Click here to add footer 10

Instrumentation outer layer

Outer layer instrumentation incorporated in a Trace which is applied after impregnationThere are 2 ldquoUrdquo shaped SS quench heaters with Cu overlay with Cu masked off to provide heating regions Heater width is 19mm in low-field region with heater regions 90mm apart In the high-field region the heater width is 24mm and the heater regions are 130mm apartThere are 13 voltage taps on the Trace including 6 on the pole turn 1 on the layer jump and 4 on the mid-plane turn

EES5O

I

EE5O12-

+

EES5OO

EE5O11EE5O10

EE5O9

EE5O8 EE5O6EE5O7 EE5O5

EE5O4EE5O3EE5O2

EE5O1

Click here to add footer 11

Instrumentation inner layer

Inner layer instrumentation consists only of voltage taps There are 16 voltage taps including 6 on the pole turn 1 on the layer jump and 4 on the mid-plane turn with other taps adjacent to spacer block edges

S Izquierdo BermudezF-O PincotR Bateman

Click here to add footer 12

Quench heaters

50 70 90 110 130 150 170 19000

200400600800

100012001400160018002000

Low Field Region High Field Region

Heater Current (A)

Pow

er d

ensi

ty (W

cm

2)

Operation area

bull Width -gt Cover as many turns as possible

bull LF 19 mm bull HF 24 mm

bull Power densitybull LF asymp 75 Wcm2

bull HFasymp 55 Wcm2

Even if the operational current is expected to be in the range 100-120 A it would be good to have the possibility to go up to 150 A during short model tests to check the saturation of the system in terms of heater delays

119875119889=1198682119877119908119871

119877=120588 119871119908119905

119875119889=1198682 1205881199082119905

Heater width19 mm LF 24 mm HFρss=7310-7Ωm RRR=134

bull Distance between heater stations -gt quench propagation in between stations asymp 5 msbull LF 90 mmbull HF 130 mm

bull Coverage maximum coverage keeping the resistance within the allowable limits for a 55 m magnet (depends on the number of power suppliesheater circuits)

Cu

50 90130

192

4

Cu

Click here to add footer 13

Coils size

bull Both coils 101 and 105 were oversized only in the mid-plane

bull Best-fit on the outer diameter and the loading plates (interface with pole)

Click here to add footer 14

Excess in mid-plane

-150 -50 50 20

030

040

050

060

070

080

090

090

011

0012

0013

0014

000

100

200

300

400

500

600

700

800

leftrightaverage

Coil length [mm]

Inte

rfer

ence

[microm

]

Click here to add footer 15

Collaring steps

2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 320

50100150200250300350400

Distance to collaring position right lead endright return endleft lead endleft return end

F [MN]

offs

et k

ey g

roov

e [micro

m]

With 8MN the stoppers of the collaring tool were in contact

Click here to add footer 16

Shimming planbull Mid-plane is 650 microm beyond expectations To compensate

bull One layer of Kapton was removed on the mid-plane

bull Changed one layer of insulation to 005 microm thickness (in lieu of 0125 microm)

Click here to add footer 17

Yoking welding of the shellsF Lackner

1 2 3 4 5 6 7 80

100200300400500600700800

0

110

206

361426

526610

686Pressure rising April 28th 2014

Pressure rising step

Tota

l cha

rge

in to

ns

3154906157901240166520652225

002040608

SIDE B 0110206361426526610686

Length in [mm]

Yoke

gap

[mm

]

Tota

l loa

d in

tons

Max charge 500 tm on central section to close the welding gap

0

02

04

06

SIDE A0110206361426526610686

Length in [mm]

Yoke

gap

[mm

]

Tota

l loa

d in

tons

Click here to add footer 18

Structural analysis vs measurements

Click here to add footer 19

FEA Results 11T Mirror

FEA Max Cap gauge

pressure (MPa)

FEA Avg Cap gauge

pressure (MPa)

FEA Min Cap gauge

pressure (MPa)

Collar nose

stress (MPa)

Coil Min stress (MPa)

Coil Max Stress (MPa)

Avg Shell Stress (MPa)

Collaring Load 48 33 18 88 -7 -90

Post-Collaring 39 28 16 72 -7 -69

Collar in yoke 40 28 17 73 -9 -66

Max Press force 46 31 15 81 -14 -60 10

Shell Weld + Press Force 50 33 14 87 -16 -61 187

Shell Welded no Press Force 48 32 15 85 -15 -60 194

Collaring Load Post-Collaring Collar in yoke Max Press force Shell Weld + Press Force

Shell Welded no Press Force

Shell Welded - 297K

Cool Down (18K)

11-Tesla0

10

20

30

40

50

60Mirror Coil - contact pressure at pole (Cap Gauge)

FEA Max Cap gauge - pressure (MPa)

FEA Avg Cap gauge - pressure (MPa)

FEA Min Cap gauge - pressure (MPa)

Measured Coil Data (10 error bars)

Pres

sure

(MPa

)

Click here to add footer 20

ANSYS Forecast at 11-Tesla

Assembly Step

Max Capacitive gauge -

pressure (MPa)

Avg Capacitive gauge -

pressure (MPa)

Min Capacitive gauge -

pressure (MPa)

Collar-nose stress (MPa)

Coil Min stress (MPa)

Coil Max Stress (MPa)

Avg Shell Stress (MPa)

MirrorCoil

Shell Welded - 297K 48 32 15 85 -15 -60 195

Cool Down (18K) 37 21 5 62 -5 -74 375

11-Tesla 1 05 0 63 +13 -117 377

NominalCoil

Shell Welded - 297K 107 58 8 150 -14 -119 191

Cool Down (18K) 86 43 1 123 -21 -125 373

11-Tesla 22 11 0 57 -4 -120 374

Collar Nose Von-Mises Stress

At 11T

Coil BlocksAzimuthal Stress

At 11T

FEA predicted results

Click here to add footer 21

Bullet gauges loadingM GuinchardP Grosclaude

8 to 9 kN per bullet

Click here to add footer 22

Electrical tests ndash WhenF-O PincotL Grand Cleacutement

Are performed beforeafter each important construction step Test of pole Nb3Sn before curing - PBC Test of pole Nb3Sn before reaction ndash PBR Test of pole Nb3Sn after reaction ndash PAR Test of pole Nb3Sn after impregnation out of the mould ndash PAI Test of pole Nb3Sn after impregnation with instrumentation ndash PAIWI Test of collared coil before collaring ndash BC Test of collared coil after collaring ndash AC Test of the magnet under load before welding ndash UL Test of the magnet after shell welding ndash AW Test of the magnet after longitudinal coil loading ndash AL Test of the magnet after interconnection ndash AI Final Test of the magnet before delivery - FINAL

Click here to add footer 23

Electrical tests ndash WhatF-O PincotL Grand CleacutementAccording to the construction step we define

specific test valueselectrical tests among which

Resistance measurement(Coils Quench heaters Voltage taps Instrumentation) Inductance measurement Capacitance measurement Dielectric measurement(between coils QH instrumentation ground)

bull Insulation (up to 1kV 30s)bull current leakage (up to 1kV 5min)

Discharge test on coilUp to 1kV

Discharge test on quench heatersUp to 900V or 80AQH

Click here to add footer 24

Electrical testsF-O PincotL Grand Cleacutement

Resistance Insulation dielectric Inductance Capacitance Coil discharge QH discharge

Test phase

code

PBC X X X

PBR X X X

PAR X X X

PAI X X X X

PAIWI X X X X

BC X X X X X X

AC X X X X X X

UL X X

AW X X X X X X

AL X X X X X X

AI X X X X X X

FINAL X X X X X X

Click here to add footer 25

Click here to add footer 26

Plan for power tests coldbull RRR and strain gauge measurementsbull Preliminary tests ndash Setup protection ndash Splice resistance

measurements (current plateaus at 2 4 6 8 and 10 kA) ndash 3 hoursbull Training 43 K ndash 15 quenches ndash 3 days bull Training 19 K ndash 10 quenches ndash 25 days

Stability on current plateau ndash 05 daybull Ramp-rate study 100 As and 50 As ndash 05 day

AC-loss measurements (includes inductance measurement) at 5 to 100 As ndash 05 day

bull Quench heater efficiency study 3 different settings of QH pulse for 3 currents each Long re-cooling of the magnet due to delay of energy extraction ndash 3 days

bull High MIIts tests (protection delay) 6 quenches ndash 3 days

bull Quench propagation velocity measurements acquired for the training quenches

G Willeringbull Cool down bull Day 1

bull Day 2-4bull Day 5-7

bull Day 8

bull Day 9-11

bull Day 12-14

Click here to add footer 27

Further actionsbull After cold tests warm magnetic

measurements will be carried out with the two coils connected

bull Model 1 MBHSP101 single aperture with cable OST RRP 108127 for both polesbull Instrumentation of coils 106 and 107 going onbull Collaring scheduled around middle of June

  • CERN-FNAL Video Meeting 12 Progress of the 11T Dipole short m
  • Contributions
  • Main design features
  • Specific features
  • Assembly conditions - Winding
  • Binder curing
  • Reaction treatment
  • Reaction treatment ndash Coil 105
  • Impregnation
  • Instrumentation outer layer
  • Instrumentation inner layer
  • Quench heaters
  • Coils size
  • Excess in mid-plane
  • Collaring steps
  • Shimming plan
  • Yoking welding of the shells
  • Structural analysis vs measurements
  • FEA Results
  • ANSYS Forecast at 11-Tesla
  • Bullet gauges loading
  • Electrical tests ndash When
  • Electrical tests ndash What
  • Electrical tests
  • Slide 25
  • Plan for power tests cold
  • Further actions
Page 2: CERN MBHSM0101 general  status F. Savary on behalf of the 11T Dipole Project Team

Click here to add footer 2

Contributionsbull Bateman R1 Batts S 1 Bourcey N Cote D Duret M

Fernandes C Izquierdo Bermudez S Gauthier R Guinchard M Grand-Clement L Grosclaude P Grospelier E Jokinen A 1 Juchno M Julien V Karppinen M Lackner F Lambert L Loumlffler C Lyon T-J Mazet J Peray N Pincot F-O Savary F Schmid N Smekens D Willering G

bull 1Oxford Instrument

Click here to add footer 3

Main design featuresbull Single aperture 6-bloc designbull 56 turns

bull 22 on IL (4 blocs)bull 34 on OL (2 blocs)

bull Aperture 60 mmbull Coil length 18 mbull Yoke OD 510 mmbull Shell thickness 12 mm [AISI 304L]

Click here to add footer 4

Specific featuresbull Copper coil 101

bull End spacers CERN v0 longer coilbull Sc coil 105

bull Cable OST RRP 108127bull ODS alloy wedgesbull CERN V4 end spacers SLS (with flex hinge legs)bull Metallic saddles and splice blocksbull External trace glued on coil OD carrying V-taps and quench

heaters (next slide)bull Collars and yoke laminations produced by EDM

bull Collars YUS130S Nippon Steel 3 mm thickness (LHC dipole)bull Yoke laminations Arcelor Magnetil Low C steel 58 mm

thickness (LHC dipole)

Click here to add footer 5

Assembly conditions - Windingbull Winding tension

bull Coil 101 300 N insulation defects gt1bull Coil 105 250 N insulation defects 0

bull Cable insulationbull Coils 101 and 105

bull Outer sleeve AGY S-2 Glass 11 Tex direct braidingbull Inner dielectric Cogebi Firox 80 microm Mica ndash Fiber glass tape

bull Winding monitoring during coil 105 production

D SmekensJ Mazet

Coils longer than expected ~20 mm

Click here to add footer 6

Binder curingbull Binder CTD 1202-X qty

bull Coil 101 IL in excess OL in excessbull Coil 105 IL 100 g OL 100 g

bull Shimming nominal (shimming such that in the press the mid-plane of the cured coil is like in the magnet 012 mm above center axis)bull This is different compared to FERMILAB where oversized shimming

is used to compact the coil mid-plane beyond its nominal position in order to obtain a smaller coil size before entering into reaction

bull With a load of 08 MN the mold is nearly closed (lt 01mm)bull Then a load of 2 MN is used for IL and 42 MN for the OL

(complete pole)bull The stress in the coils may not exceed 37 MPa at that stage

D SmekensJ Mazet

Click here to add footer 7

Reaction treatmentbull Cavity of the reaction fixture is radially bigger than the curing

mold by 01 mm and of similar dimension at coil mid-planebull Thus if the curing press can be closed before reaching 37

MPa the coil cannot be subjected to higher stress when closing the fixture However the dry fiber glass and the tight tolerances induce large friction also a possible dimensional problem with the sealing foils could have generated interference between the sealing foil and the baseplate preventing correct closure of the fixture

bull The tightening torque to close the fixture was of the order of 300 Nm (FNAL applies 110 Nm to 160 Nm)

bull Not clear no coil contraction after reaction actually less that 1 mm when 45 mm were expected

D SmekensN BourceyF Lackner

Click here to add footer 8

Reaction treatment ndash Coil 105

Adjustment of dwell time to compensate the delay between the

temperature and tooling temperature

The homogeneity of T during ramp up was not very good plusmn

9degCHowever it is OK during

dwell time

N BourceyF Lackner

Click here to add footer 9

Impregnationbull Resin CTD 101K

bull Anhydride cured epoxy system with excellent performance at cryogenic temperature and radiation resistance

bull The resin is preheated and the coil is impregnated at 60degC

bull Curing 110degC for 5 hoursbull Post curing heating 125degC for 16 hours

R GauthierD Smekens

Temperature [degC] Pot life [h] Viscosity [mmmiddotPas]25 145 1300

40 60 400

60 20 100

Click here to add footer 10

Instrumentation outer layer

Outer layer instrumentation incorporated in a Trace which is applied after impregnationThere are 2 ldquoUrdquo shaped SS quench heaters with Cu overlay with Cu masked off to provide heating regions Heater width is 19mm in low-field region with heater regions 90mm apart In the high-field region the heater width is 24mm and the heater regions are 130mm apartThere are 13 voltage taps on the Trace including 6 on the pole turn 1 on the layer jump and 4 on the mid-plane turn

EES5O

I

EE5O12-

+

EES5OO

EE5O11EE5O10

EE5O9

EE5O8 EE5O6EE5O7 EE5O5

EE5O4EE5O3EE5O2

EE5O1

Click here to add footer 11

Instrumentation inner layer

Inner layer instrumentation consists only of voltage taps There are 16 voltage taps including 6 on the pole turn 1 on the layer jump and 4 on the mid-plane turn with other taps adjacent to spacer block edges

S Izquierdo BermudezF-O PincotR Bateman

Click here to add footer 12

Quench heaters

50 70 90 110 130 150 170 19000

200400600800

100012001400160018002000

Low Field Region High Field Region

Heater Current (A)

Pow

er d

ensi

ty (W

cm

2)

Operation area

bull Width -gt Cover as many turns as possible

bull LF 19 mm bull HF 24 mm

bull Power densitybull LF asymp 75 Wcm2

bull HFasymp 55 Wcm2

Even if the operational current is expected to be in the range 100-120 A it would be good to have the possibility to go up to 150 A during short model tests to check the saturation of the system in terms of heater delays

119875119889=1198682119877119908119871

119877=120588 119871119908119905

119875119889=1198682 1205881199082119905

Heater width19 mm LF 24 mm HFρss=7310-7Ωm RRR=134

bull Distance between heater stations -gt quench propagation in between stations asymp 5 msbull LF 90 mmbull HF 130 mm

bull Coverage maximum coverage keeping the resistance within the allowable limits for a 55 m magnet (depends on the number of power suppliesheater circuits)

Cu

50 90130

192

4

Cu

Click here to add footer 13

Coils size

bull Both coils 101 and 105 were oversized only in the mid-plane

bull Best-fit on the outer diameter and the loading plates (interface with pole)

Click here to add footer 14

Excess in mid-plane

-150 -50 50 20

030

040

050

060

070

080

090

090

011

0012

0013

0014

000

100

200

300

400

500

600

700

800

leftrightaverage

Coil length [mm]

Inte

rfer

ence

[microm

]

Click here to add footer 15

Collaring steps

2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 320

50100150200250300350400

Distance to collaring position right lead endright return endleft lead endleft return end

F [MN]

offs

et k

ey g

roov

e [micro

m]

With 8MN the stoppers of the collaring tool were in contact

Click here to add footer 16

Shimming planbull Mid-plane is 650 microm beyond expectations To compensate

bull One layer of Kapton was removed on the mid-plane

bull Changed one layer of insulation to 005 microm thickness (in lieu of 0125 microm)

Click here to add footer 17

Yoking welding of the shellsF Lackner

1 2 3 4 5 6 7 80

100200300400500600700800

0

110

206

361426

526610

686Pressure rising April 28th 2014

Pressure rising step

Tota

l cha

rge

in to

ns

3154906157901240166520652225

002040608

SIDE B 0110206361426526610686

Length in [mm]

Yoke

gap

[mm

]

Tota

l loa

d in

tons

Max charge 500 tm on central section to close the welding gap

0

02

04

06

SIDE A0110206361426526610686

Length in [mm]

Yoke

gap

[mm

]

Tota

l loa

d in

tons

Click here to add footer 18

Structural analysis vs measurements

Click here to add footer 19

FEA Results 11T Mirror

FEA Max Cap gauge

pressure (MPa)

FEA Avg Cap gauge

pressure (MPa)

FEA Min Cap gauge

pressure (MPa)

Collar nose

stress (MPa)

Coil Min stress (MPa)

Coil Max Stress (MPa)

Avg Shell Stress (MPa)

Collaring Load 48 33 18 88 -7 -90

Post-Collaring 39 28 16 72 -7 -69

Collar in yoke 40 28 17 73 -9 -66

Max Press force 46 31 15 81 -14 -60 10

Shell Weld + Press Force 50 33 14 87 -16 -61 187

Shell Welded no Press Force 48 32 15 85 -15 -60 194

Collaring Load Post-Collaring Collar in yoke Max Press force Shell Weld + Press Force

Shell Welded no Press Force

Shell Welded - 297K

Cool Down (18K)

11-Tesla0

10

20

30

40

50

60Mirror Coil - contact pressure at pole (Cap Gauge)

FEA Max Cap gauge - pressure (MPa)

FEA Avg Cap gauge - pressure (MPa)

FEA Min Cap gauge - pressure (MPa)

Measured Coil Data (10 error bars)

Pres

sure

(MPa

)

Click here to add footer 20

ANSYS Forecast at 11-Tesla

Assembly Step

Max Capacitive gauge -

pressure (MPa)

Avg Capacitive gauge -

pressure (MPa)

Min Capacitive gauge -

pressure (MPa)

Collar-nose stress (MPa)

Coil Min stress (MPa)

Coil Max Stress (MPa)

Avg Shell Stress (MPa)

MirrorCoil

Shell Welded - 297K 48 32 15 85 -15 -60 195

Cool Down (18K) 37 21 5 62 -5 -74 375

11-Tesla 1 05 0 63 +13 -117 377

NominalCoil

Shell Welded - 297K 107 58 8 150 -14 -119 191

Cool Down (18K) 86 43 1 123 -21 -125 373

11-Tesla 22 11 0 57 -4 -120 374

Collar Nose Von-Mises Stress

At 11T

Coil BlocksAzimuthal Stress

At 11T

FEA predicted results

Click here to add footer 21

Bullet gauges loadingM GuinchardP Grosclaude

8 to 9 kN per bullet

Click here to add footer 22

Electrical tests ndash WhenF-O PincotL Grand Cleacutement

Are performed beforeafter each important construction step Test of pole Nb3Sn before curing - PBC Test of pole Nb3Sn before reaction ndash PBR Test of pole Nb3Sn after reaction ndash PAR Test of pole Nb3Sn after impregnation out of the mould ndash PAI Test of pole Nb3Sn after impregnation with instrumentation ndash PAIWI Test of collared coil before collaring ndash BC Test of collared coil after collaring ndash AC Test of the magnet under load before welding ndash UL Test of the magnet after shell welding ndash AW Test of the magnet after longitudinal coil loading ndash AL Test of the magnet after interconnection ndash AI Final Test of the magnet before delivery - FINAL

Click here to add footer 23

Electrical tests ndash WhatF-O PincotL Grand CleacutementAccording to the construction step we define

specific test valueselectrical tests among which

Resistance measurement(Coils Quench heaters Voltage taps Instrumentation) Inductance measurement Capacitance measurement Dielectric measurement(between coils QH instrumentation ground)

bull Insulation (up to 1kV 30s)bull current leakage (up to 1kV 5min)

Discharge test on coilUp to 1kV

Discharge test on quench heatersUp to 900V or 80AQH

Click here to add footer 24

Electrical testsF-O PincotL Grand Cleacutement

Resistance Insulation dielectric Inductance Capacitance Coil discharge QH discharge

Test phase

code

PBC X X X

PBR X X X

PAR X X X

PAI X X X X

PAIWI X X X X

BC X X X X X X

AC X X X X X X

UL X X

AW X X X X X X

AL X X X X X X

AI X X X X X X

FINAL X X X X X X

Click here to add footer 25

Click here to add footer 26

Plan for power tests coldbull RRR and strain gauge measurementsbull Preliminary tests ndash Setup protection ndash Splice resistance

measurements (current plateaus at 2 4 6 8 and 10 kA) ndash 3 hoursbull Training 43 K ndash 15 quenches ndash 3 days bull Training 19 K ndash 10 quenches ndash 25 days

Stability on current plateau ndash 05 daybull Ramp-rate study 100 As and 50 As ndash 05 day

AC-loss measurements (includes inductance measurement) at 5 to 100 As ndash 05 day

bull Quench heater efficiency study 3 different settings of QH pulse for 3 currents each Long re-cooling of the magnet due to delay of energy extraction ndash 3 days

bull High MIIts tests (protection delay) 6 quenches ndash 3 days

bull Quench propagation velocity measurements acquired for the training quenches

G Willeringbull Cool down bull Day 1

bull Day 2-4bull Day 5-7

bull Day 8

bull Day 9-11

bull Day 12-14

Click here to add footer 27

Further actionsbull After cold tests warm magnetic

measurements will be carried out with the two coils connected

bull Model 1 MBHSP101 single aperture with cable OST RRP 108127 for both polesbull Instrumentation of coils 106 and 107 going onbull Collaring scheduled around middle of June

  • CERN-FNAL Video Meeting 12 Progress of the 11T Dipole short m
  • Contributions
  • Main design features
  • Specific features
  • Assembly conditions - Winding
  • Binder curing
  • Reaction treatment
  • Reaction treatment ndash Coil 105
  • Impregnation
  • Instrumentation outer layer
  • Instrumentation inner layer
  • Quench heaters
  • Coils size
  • Excess in mid-plane
  • Collaring steps
  • Shimming plan
  • Yoking welding of the shells
  • Structural analysis vs measurements
  • FEA Results
  • ANSYS Forecast at 11-Tesla
  • Bullet gauges loading
  • Electrical tests ndash When
  • Electrical tests ndash What
  • Electrical tests
  • Slide 25
  • Plan for power tests cold
  • Further actions
Page 3: CERN MBHSM0101 general  status F. Savary on behalf of the 11T Dipole Project Team

Click here to add footer 3

Main design featuresbull Single aperture 6-bloc designbull 56 turns

bull 22 on IL (4 blocs)bull 34 on OL (2 blocs)

bull Aperture 60 mmbull Coil length 18 mbull Yoke OD 510 mmbull Shell thickness 12 mm [AISI 304L]

Click here to add footer 4

Specific featuresbull Copper coil 101

bull End spacers CERN v0 longer coilbull Sc coil 105

bull Cable OST RRP 108127bull ODS alloy wedgesbull CERN V4 end spacers SLS (with flex hinge legs)bull Metallic saddles and splice blocksbull External trace glued on coil OD carrying V-taps and quench

heaters (next slide)bull Collars and yoke laminations produced by EDM

bull Collars YUS130S Nippon Steel 3 mm thickness (LHC dipole)bull Yoke laminations Arcelor Magnetil Low C steel 58 mm

thickness (LHC dipole)

Click here to add footer 5

Assembly conditions - Windingbull Winding tension

bull Coil 101 300 N insulation defects gt1bull Coil 105 250 N insulation defects 0

bull Cable insulationbull Coils 101 and 105

bull Outer sleeve AGY S-2 Glass 11 Tex direct braidingbull Inner dielectric Cogebi Firox 80 microm Mica ndash Fiber glass tape

bull Winding monitoring during coil 105 production

D SmekensJ Mazet

Coils longer than expected ~20 mm

Click here to add footer 6

Binder curingbull Binder CTD 1202-X qty

bull Coil 101 IL in excess OL in excessbull Coil 105 IL 100 g OL 100 g

bull Shimming nominal (shimming such that in the press the mid-plane of the cured coil is like in the magnet 012 mm above center axis)bull This is different compared to FERMILAB where oversized shimming

is used to compact the coil mid-plane beyond its nominal position in order to obtain a smaller coil size before entering into reaction

bull With a load of 08 MN the mold is nearly closed (lt 01mm)bull Then a load of 2 MN is used for IL and 42 MN for the OL

(complete pole)bull The stress in the coils may not exceed 37 MPa at that stage

D SmekensJ Mazet

Click here to add footer 7

Reaction treatmentbull Cavity of the reaction fixture is radially bigger than the curing

mold by 01 mm and of similar dimension at coil mid-planebull Thus if the curing press can be closed before reaching 37

MPa the coil cannot be subjected to higher stress when closing the fixture However the dry fiber glass and the tight tolerances induce large friction also a possible dimensional problem with the sealing foils could have generated interference between the sealing foil and the baseplate preventing correct closure of the fixture

bull The tightening torque to close the fixture was of the order of 300 Nm (FNAL applies 110 Nm to 160 Nm)

bull Not clear no coil contraction after reaction actually less that 1 mm when 45 mm were expected

D SmekensN BourceyF Lackner

Click here to add footer 8

Reaction treatment ndash Coil 105

Adjustment of dwell time to compensate the delay between the

temperature and tooling temperature

The homogeneity of T during ramp up was not very good plusmn

9degCHowever it is OK during

dwell time

N BourceyF Lackner

Click here to add footer 9

Impregnationbull Resin CTD 101K

bull Anhydride cured epoxy system with excellent performance at cryogenic temperature and radiation resistance

bull The resin is preheated and the coil is impregnated at 60degC

bull Curing 110degC for 5 hoursbull Post curing heating 125degC for 16 hours

R GauthierD Smekens

Temperature [degC] Pot life [h] Viscosity [mmmiddotPas]25 145 1300

40 60 400

60 20 100

Click here to add footer 10

Instrumentation outer layer

Outer layer instrumentation incorporated in a Trace which is applied after impregnationThere are 2 ldquoUrdquo shaped SS quench heaters with Cu overlay with Cu masked off to provide heating regions Heater width is 19mm in low-field region with heater regions 90mm apart In the high-field region the heater width is 24mm and the heater regions are 130mm apartThere are 13 voltage taps on the Trace including 6 on the pole turn 1 on the layer jump and 4 on the mid-plane turn

EES5O

I

EE5O12-

+

EES5OO

EE5O11EE5O10

EE5O9

EE5O8 EE5O6EE5O7 EE5O5

EE5O4EE5O3EE5O2

EE5O1

Click here to add footer 11

Instrumentation inner layer

Inner layer instrumentation consists only of voltage taps There are 16 voltage taps including 6 on the pole turn 1 on the layer jump and 4 on the mid-plane turn with other taps adjacent to spacer block edges

S Izquierdo BermudezF-O PincotR Bateman

Click here to add footer 12

Quench heaters

50 70 90 110 130 150 170 19000

200400600800

100012001400160018002000

Low Field Region High Field Region

Heater Current (A)

Pow

er d

ensi

ty (W

cm

2)

Operation area

bull Width -gt Cover as many turns as possible

bull LF 19 mm bull HF 24 mm

bull Power densitybull LF asymp 75 Wcm2

bull HFasymp 55 Wcm2

Even if the operational current is expected to be in the range 100-120 A it would be good to have the possibility to go up to 150 A during short model tests to check the saturation of the system in terms of heater delays

119875119889=1198682119877119908119871

119877=120588 119871119908119905

119875119889=1198682 1205881199082119905

Heater width19 mm LF 24 mm HFρss=7310-7Ωm RRR=134

bull Distance between heater stations -gt quench propagation in between stations asymp 5 msbull LF 90 mmbull HF 130 mm

bull Coverage maximum coverage keeping the resistance within the allowable limits for a 55 m magnet (depends on the number of power suppliesheater circuits)

Cu

50 90130

192

4

Cu

Click here to add footer 13

Coils size

bull Both coils 101 and 105 were oversized only in the mid-plane

bull Best-fit on the outer diameter and the loading plates (interface with pole)

Click here to add footer 14

Excess in mid-plane

-150 -50 50 20

030

040

050

060

070

080

090

090

011

0012

0013

0014

000

100

200

300

400

500

600

700

800

leftrightaverage

Coil length [mm]

Inte

rfer

ence

[microm

]

Click here to add footer 15

Collaring steps

2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 320

50100150200250300350400

Distance to collaring position right lead endright return endleft lead endleft return end

F [MN]

offs

et k

ey g

roov

e [micro

m]

With 8MN the stoppers of the collaring tool were in contact

Click here to add footer 16

Shimming planbull Mid-plane is 650 microm beyond expectations To compensate

bull One layer of Kapton was removed on the mid-plane

bull Changed one layer of insulation to 005 microm thickness (in lieu of 0125 microm)

Click here to add footer 17

Yoking welding of the shellsF Lackner

1 2 3 4 5 6 7 80

100200300400500600700800

0

110

206

361426

526610

686Pressure rising April 28th 2014

Pressure rising step

Tota

l cha

rge

in to

ns

3154906157901240166520652225

002040608

SIDE B 0110206361426526610686

Length in [mm]

Yoke

gap

[mm

]

Tota

l loa

d in

tons

Max charge 500 tm on central section to close the welding gap

0

02

04

06

SIDE A0110206361426526610686

Length in [mm]

Yoke

gap

[mm

]

Tota

l loa

d in

tons

Click here to add footer 18

Structural analysis vs measurements

Click here to add footer 19

FEA Results 11T Mirror

FEA Max Cap gauge

pressure (MPa)

FEA Avg Cap gauge

pressure (MPa)

FEA Min Cap gauge

pressure (MPa)

Collar nose

stress (MPa)

Coil Min stress (MPa)

Coil Max Stress (MPa)

Avg Shell Stress (MPa)

Collaring Load 48 33 18 88 -7 -90

Post-Collaring 39 28 16 72 -7 -69

Collar in yoke 40 28 17 73 -9 -66

Max Press force 46 31 15 81 -14 -60 10

Shell Weld + Press Force 50 33 14 87 -16 -61 187

Shell Welded no Press Force 48 32 15 85 -15 -60 194

Collaring Load Post-Collaring Collar in yoke Max Press force Shell Weld + Press Force

Shell Welded no Press Force

Shell Welded - 297K

Cool Down (18K)

11-Tesla0

10

20

30

40

50

60Mirror Coil - contact pressure at pole (Cap Gauge)

FEA Max Cap gauge - pressure (MPa)

FEA Avg Cap gauge - pressure (MPa)

FEA Min Cap gauge - pressure (MPa)

Measured Coil Data (10 error bars)

Pres

sure

(MPa

)

Click here to add footer 20

ANSYS Forecast at 11-Tesla

Assembly Step

Max Capacitive gauge -

pressure (MPa)

Avg Capacitive gauge -

pressure (MPa)

Min Capacitive gauge -

pressure (MPa)

Collar-nose stress (MPa)

Coil Min stress (MPa)

Coil Max Stress (MPa)

Avg Shell Stress (MPa)

MirrorCoil

Shell Welded - 297K 48 32 15 85 -15 -60 195

Cool Down (18K) 37 21 5 62 -5 -74 375

11-Tesla 1 05 0 63 +13 -117 377

NominalCoil

Shell Welded - 297K 107 58 8 150 -14 -119 191

Cool Down (18K) 86 43 1 123 -21 -125 373

11-Tesla 22 11 0 57 -4 -120 374

Collar Nose Von-Mises Stress

At 11T

Coil BlocksAzimuthal Stress

At 11T

FEA predicted results

Click here to add footer 21

Bullet gauges loadingM GuinchardP Grosclaude

8 to 9 kN per bullet

Click here to add footer 22

Electrical tests ndash WhenF-O PincotL Grand Cleacutement

Are performed beforeafter each important construction step Test of pole Nb3Sn before curing - PBC Test of pole Nb3Sn before reaction ndash PBR Test of pole Nb3Sn after reaction ndash PAR Test of pole Nb3Sn after impregnation out of the mould ndash PAI Test of pole Nb3Sn after impregnation with instrumentation ndash PAIWI Test of collared coil before collaring ndash BC Test of collared coil after collaring ndash AC Test of the magnet under load before welding ndash UL Test of the magnet after shell welding ndash AW Test of the magnet after longitudinal coil loading ndash AL Test of the magnet after interconnection ndash AI Final Test of the magnet before delivery - FINAL

Click here to add footer 23

Electrical tests ndash WhatF-O PincotL Grand CleacutementAccording to the construction step we define

specific test valueselectrical tests among which

Resistance measurement(Coils Quench heaters Voltage taps Instrumentation) Inductance measurement Capacitance measurement Dielectric measurement(between coils QH instrumentation ground)

bull Insulation (up to 1kV 30s)bull current leakage (up to 1kV 5min)

Discharge test on coilUp to 1kV

Discharge test on quench heatersUp to 900V or 80AQH

Click here to add footer 24

Electrical testsF-O PincotL Grand Cleacutement

Resistance Insulation dielectric Inductance Capacitance Coil discharge QH discharge

Test phase

code

PBC X X X

PBR X X X

PAR X X X

PAI X X X X

PAIWI X X X X

BC X X X X X X

AC X X X X X X

UL X X

AW X X X X X X

AL X X X X X X

AI X X X X X X

FINAL X X X X X X

Click here to add footer 25

Click here to add footer 26

Plan for power tests coldbull RRR and strain gauge measurementsbull Preliminary tests ndash Setup protection ndash Splice resistance

measurements (current plateaus at 2 4 6 8 and 10 kA) ndash 3 hoursbull Training 43 K ndash 15 quenches ndash 3 days bull Training 19 K ndash 10 quenches ndash 25 days

Stability on current plateau ndash 05 daybull Ramp-rate study 100 As and 50 As ndash 05 day

AC-loss measurements (includes inductance measurement) at 5 to 100 As ndash 05 day

bull Quench heater efficiency study 3 different settings of QH pulse for 3 currents each Long re-cooling of the magnet due to delay of energy extraction ndash 3 days

bull High MIIts tests (protection delay) 6 quenches ndash 3 days

bull Quench propagation velocity measurements acquired for the training quenches

G Willeringbull Cool down bull Day 1

bull Day 2-4bull Day 5-7

bull Day 8

bull Day 9-11

bull Day 12-14

Click here to add footer 27

Further actionsbull After cold tests warm magnetic

measurements will be carried out with the two coils connected

bull Model 1 MBHSP101 single aperture with cable OST RRP 108127 for both polesbull Instrumentation of coils 106 and 107 going onbull Collaring scheduled around middle of June

  • CERN-FNAL Video Meeting 12 Progress of the 11T Dipole short m
  • Contributions
  • Main design features
  • Specific features
  • Assembly conditions - Winding
  • Binder curing
  • Reaction treatment
  • Reaction treatment ndash Coil 105
  • Impregnation
  • Instrumentation outer layer
  • Instrumentation inner layer
  • Quench heaters
  • Coils size
  • Excess in mid-plane
  • Collaring steps
  • Shimming plan
  • Yoking welding of the shells
  • Structural analysis vs measurements
  • FEA Results
  • ANSYS Forecast at 11-Tesla
  • Bullet gauges loading
  • Electrical tests ndash When
  • Electrical tests ndash What
  • Electrical tests
  • Slide 25
  • Plan for power tests cold
  • Further actions
Page 4: CERN MBHSM0101 general  status F. Savary on behalf of the 11T Dipole Project Team

Click here to add footer 4

Specific featuresbull Copper coil 101

bull End spacers CERN v0 longer coilbull Sc coil 105

bull Cable OST RRP 108127bull ODS alloy wedgesbull CERN V4 end spacers SLS (with flex hinge legs)bull Metallic saddles and splice blocksbull External trace glued on coil OD carrying V-taps and quench

heaters (next slide)bull Collars and yoke laminations produced by EDM

bull Collars YUS130S Nippon Steel 3 mm thickness (LHC dipole)bull Yoke laminations Arcelor Magnetil Low C steel 58 mm

thickness (LHC dipole)

Click here to add footer 5

Assembly conditions - Windingbull Winding tension

bull Coil 101 300 N insulation defects gt1bull Coil 105 250 N insulation defects 0

bull Cable insulationbull Coils 101 and 105

bull Outer sleeve AGY S-2 Glass 11 Tex direct braidingbull Inner dielectric Cogebi Firox 80 microm Mica ndash Fiber glass tape

bull Winding monitoring during coil 105 production

D SmekensJ Mazet

Coils longer than expected ~20 mm

Click here to add footer 6

Binder curingbull Binder CTD 1202-X qty

bull Coil 101 IL in excess OL in excessbull Coil 105 IL 100 g OL 100 g

bull Shimming nominal (shimming such that in the press the mid-plane of the cured coil is like in the magnet 012 mm above center axis)bull This is different compared to FERMILAB where oversized shimming

is used to compact the coil mid-plane beyond its nominal position in order to obtain a smaller coil size before entering into reaction

bull With a load of 08 MN the mold is nearly closed (lt 01mm)bull Then a load of 2 MN is used for IL and 42 MN for the OL

(complete pole)bull The stress in the coils may not exceed 37 MPa at that stage

D SmekensJ Mazet

Click here to add footer 7

Reaction treatmentbull Cavity of the reaction fixture is radially bigger than the curing

mold by 01 mm and of similar dimension at coil mid-planebull Thus if the curing press can be closed before reaching 37

MPa the coil cannot be subjected to higher stress when closing the fixture However the dry fiber glass and the tight tolerances induce large friction also a possible dimensional problem with the sealing foils could have generated interference between the sealing foil and the baseplate preventing correct closure of the fixture

bull The tightening torque to close the fixture was of the order of 300 Nm (FNAL applies 110 Nm to 160 Nm)

bull Not clear no coil contraction after reaction actually less that 1 mm when 45 mm were expected

D SmekensN BourceyF Lackner

Click here to add footer 8

Reaction treatment ndash Coil 105

Adjustment of dwell time to compensate the delay between the

temperature and tooling temperature

The homogeneity of T during ramp up was not very good plusmn

9degCHowever it is OK during

dwell time

N BourceyF Lackner

Click here to add footer 9

Impregnationbull Resin CTD 101K

bull Anhydride cured epoxy system with excellent performance at cryogenic temperature and radiation resistance

bull The resin is preheated and the coil is impregnated at 60degC

bull Curing 110degC for 5 hoursbull Post curing heating 125degC for 16 hours

R GauthierD Smekens

Temperature [degC] Pot life [h] Viscosity [mmmiddotPas]25 145 1300

40 60 400

60 20 100

Click here to add footer 10

Instrumentation outer layer

Outer layer instrumentation incorporated in a Trace which is applied after impregnationThere are 2 ldquoUrdquo shaped SS quench heaters with Cu overlay with Cu masked off to provide heating regions Heater width is 19mm in low-field region with heater regions 90mm apart In the high-field region the heater width is 24mm and the heater regions are 130mm apartThere are 13 voltage taps on the Trace including 6 on the pole turn 1 on the layer jump and 4 on the mid-plane turn

EES5O

I

EE5O12-

+

EES5OO

EE5O11EE5O10

EE5O9

EE5O8 EE5O6EE5O7 EE5O5

EE5O4EE5O3EE5O2

EE5O1

Click here to add footer 11

Instrumentation inner layer

Inner layer instrumentation consists only of voltage taps There are 16 voltage taps including 6 on the pole turn 1 on the layer jump and 4 on the mid-plane turn with other taps adjacent to spacer block edges

S Izquierdo BermudezF-O PincotR Bateman

Click here to add footer 12

Quench heaters

50 70 90 110 130 150 170 19000

200400600800

100012001400160018002000

Low Field Region High Field Region

Heater Current (A)

Pow

er d

ensi

ty (W

cm

2)

Operation area

bull Width -gt Cover as many turns as possible

bull LF 19 mm bull HF 24 mm

bull Power densitybull LF asymp 75 Wcm2

bull HFasymp 55 Wcm2

Even if the operational current is expected to be in the range 100-120 A it would be good to have the possibility to go up to 150 A during short model tests to check the saturation of the system in terms of heater delays

119875119889=1198682119877119908119871

119877=120588 119871119908119905

119875119889=1198682 1205881199082119905

Heater width19 mm LF 24 mm HFρss=7310-7Ωm RRR=134

bull Distance between heater stations -gt quench propagation in between stations asymp 5 msbull LF 90 mmbull HF 130 mm

bull Coverage maximum coverage keeping the resistance within the allowable limits for a 55 m magnet (depends on the number of power suppliesheater circuits)

Cu

50 90130

192

4

Cu

Click here to add footer 13

Coils size

bull Both coils 101 and 105 were oversized only in the mid-plane

bull Best-fit on the outer diameter and the loading plates (interface with pole)

Click here to add footer 14

Excess in mid-plane

-150 -50 50 20

030

040

050

060

070

080

090

090

011

0012

0013

0014

000

100

200

300

400

500

600

700

800

leftrightaverage

Coil length [mm]

Inte

rfer

ence

[microm

]

Click here to add footer 15

Collaring steps

2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 320

50100150200250300350400

Distance to collaring position right lead endright return endleft lead endleft return end

F [MN]

offs

et k

ey g

roov

e [micro

m]

With 8MN the stoppers of the collaring tool were in contact

Click here to add footer 16

Shimming planbull Mid-plane is 650 microm beyond expectations To compensate

bull One layer of Kapton was removed on the mid-plane

bull Changed one layer of insulation to 005 microm thickness (in lieu of 0125 microm)

Click here to add footer 17

Yoking welding of the shellsF Lackner

1 2 3 4 5 6 7 80

100200300400500600700800

0

110

206

361426

526610

686Pressure rising April 28th 2014

Pressure rising step

Tota

l cha

rge

in to

ns

3154906157901240166520652225

002040608

SIDE B 0110206361426526610686

Length in [mm]

Yoke

gap

[mm

]

Tota

l loa

d in

tons

Max charge 500 tm on central section to close the welding gap

0

02

04

06

SIDE A0110206361426526610686

Length in [mm]

Yoke

gap

[mm

]

Tota

l loa

d in

tons

Click here to add footer 18

Structural analysis vs measurements

Click here to add footer 19

FEA Results 11T Mirror

FEA Max Cap gauge

pressure (MPa)

FEA Avg Cap gauge

pressure (MPa)

FEA Min Cap gauge

pressure (MPa)

Collar nose

stress (MPa)

Coil Min stress (MPa)

Coil Max Stress (MPa)

Avg Shell Stress (MPa)

Collaring Load 48 33 18 88 -7 -90

Post-Collaring 39 28 16 72 -7 -69

Collar in yoke 40 28 17 73 -9 -66

Max Press force 46 31 15 81 -14 -60 10

Shell Weld + Press Force 50 33 14 87 -16 -61 187

Shell Welded no Press Force 48 32 15 85 -15 -60 194

Collaring Load Post-Collaring Collar in yoke Max Press force Shell Weld + Press Force

Shell Welded no Press Force

Shell Welded - 297K

Cool Down (18K)

11-Tesla0

10

20

30

40

50

60Mirror Coil - contact pressure at pole (Cap Gauge)

FEA Max Cap gauge - pressure (MPa)

FEA Avg Cap gauge - pressure (MPa)

FEA Min Cap gauge - pressure (MPa)

Measured Coil Data (10 error bars)

Pres

sure

(MPa

)

Click here to add footer 20

ANSYS Forecast at 11-Tesla

Assembly Step

Max Capacitive gauge -

pressure (MPa)

Avg Capacitive gauge -

pressure (MPa)

Min Capacitive gauge -

pressure (MPa)

Collar-nose stress (MPa)

Coil Min stress (MPa)

Coil Max Stress (MPa)

Avg Shell Stress (MPa)

MirrorCoil

Shell Welded - 297K 48 32 15 85 -15 -60 195

Cool Down (18K) 37 21 5 62 -5 -74 375

11-Tesla 1 05 0 63 +13 -117 377

NominalCoil

Shell Welded - 297K 107 58 8 150 -14 -119 191

Cool Down (18K) 86 43 1 123 -21 -125 373

11-Tesla 22 11 0 57 -4 -120 374

Collar Nose Von-Mises Stress

At 11T

Coil BlocksAzimuthal Stress

At 11T

FEA predicted results

Click here to add footer 21

Bullet gauges loadingM GuinchardP Grosclaude

8 to 9 kN per bullet

Click here to add footer 22

Electrical tests ndash WhenF-O PincotL Grand Cleacutement

Are performed beforeafter each important construction step Test of pole Nb3Sn before curing - PBC Test of pole Nb3Sn before reaction ndash PBR Test of pole Nb3Sn after reaction ndash PAR Test of pole Nb3Sn after impregnation out of the mould ndash PAI Test of pole Nb3Sn after impregnation with instrumentation ndash PAIWI Test of collared coil before collaring ndash BC Test of collared coil after collaring ndash AC Test of the magnet under load before welding ndash UL Test of the magnet after shell welding ndash AW Test of the magnet after longitudinal coil loading ndash AL Test of the magnet after interconnection ndash AI Final Test of the magnet before delivery - FINAL

Click here to add footer 23

Electrical tests ndash WhatF-O PincotL Grand CleacutementAccording to the construction step we define

specific test valueselectrical tests among which

Resistance measurement(Coils Quench heaters Voltage taps Instrumentation) Inductance measurement Capacitance measurement Dielectric measurement(between coils QH instrumentation ground)

bull Insulation (up to 1kV 30s)bull current leakage (up to 1kV 5min)

Discharge test on coilUp to 1kV

Discharge test on quench heatersUp to 900V or 80AQH

Click here to add footer 24

Electrical testsF-O PincotL Grand Cleacutement

Resistance Insulation dielectric Inductance Capacitance Coil discharge QH discharge

Test phase

code

PBC X X X

PBR X X X

PAR X X X

PAI X X X X

PAIWI X X X X

BC X X X X X X

AC X X X X X X

UL X X

AW X X X X X X

AL X X X X X X

AI X X X X X X

FINAL X X X X X X

Click here to add footer 25

Click here to add footer 26

Plan for power tests coldbull RRR and strain gauge measurementsbull Preliminary tests ndash Setup protection ndash Splice resistance

measurements (current plateaus at 2 4 6 8 and 10 kA) ndash 3 hoursbull Training 43 K ndash 15 quenches ndash 3 days bull Training 19 K ndash 10 quenches ndash 25 days

Stability on current plateau ndash 05 daybull Ramp-rate study 100 As and 50 As ndash 05 day

AC-loss measurements (includes inductance measurement) at 5 to 100 As ndash 05 day

bull Quench heater efficiency study 3 different settings of QH pulse for 3 currents each Long re-cooling of the magnet due to delay of energy extraction ndash 3 days

bull High MIIts tests (protection delay) 6 quenches ndash 3 days

bull Quench propagation velocity measurements acquired for the training quenches

G Willeringbull Cool down bull Day 1

bull Day 2-4bull Day 5-7

bull Day 8

bull Day 9-11

bull Day 12-14

Click here to add footer 27

Further actionsbull After cold tests warm magnetic

measurements will be carried out with the two coils connected

bull Model 1 MBHSP101 single aperture with cable OST RRP 108127 for both polesbull Instrumentation of coils 106 and 107 going onbull Collaring scheduled around middle of June

  • CERN-FNAL Video Meeting 12 Progress of the 11T Dipole short m
  • Contributions
  • Main design features
  • Specific features
  • Assembly conditions - Winding
  • Binder curing
  • Reaction treatment
  • Reaction treatment ndash Coil 105
  • Impregnation
  • Instrumentation outer layer
  • Instrumentation inner layer
  • Quench heaters
  • Coils size
  • Excess in mid-plane
  • Collaring steps
  • Shimming plan
  • Yoking welding of the shells
  • Structural analysis vs measurements
  • FEA Results
  • ANSYS Forecast at 11-Tesla
  • Bullet gauges loading
  • Electrical tests ndash When
  • Electrical tests ndash What
  • Electrical tests
  • Slide 25
  • Plan for power tests cold
  • Further actions
Page 5: CERN MBHSM0101 general  status F. Savary on behalf of the 11T Dipole Project Team

Click here to add footer 5

Assembly conditions - Windingbull Winding tension

bull Coil 101 300 N insulation defects gt1bull Coil 105 250 N insulation defects 0

bull Cable insulationbull Coils 101 and 105

bull Outer sleeve AGY S-2 Glass 11 Tex direct braidingbull Inner dielectric Cogebi Firox 80 microm Mica ndash Fiber glass tape

bull Winding monitoring during coil 105 production

D SmekensJ Mazet

Coils longer than expected ~20 mm

Click here to add footer 6

Binder curingbull Binder CTD 1202-X qty

bull Coil 101 IL in excess OL in excessbull Coil 105 IL 100 g OL 100 g

bull Shimming nominal (shimming such that in the press the mid-plane of the cured coil is like in the magnet 012 mm above center axis)bull This is different compared to FERMILAB where oversized shimming

is used to compact the coil mid-plane beyond its nominal position in order to obtain a smaller coil size before entering into reaction

bull With a load of 08 MN the mold is nearly closed (lt 01mm)bull Then a load of 2 MN is used for IL and 42 MN for the OL

(complete pole)bull The stress in the coils may not exceed 37 MPa at that stage

D SmekensJ Mazet

Click here to add footer 7

Reaction treatmentbull Cavity of the reaction fixture is radially bigger than the curing

mold by 01 mm and of similar dimension at coil mid-planebull Thus if the curing press can be closed before reaching 37

MPa the coil cannot be subjected to higher stress when closing the fixture However the dry fiber glass and the tight tolerances induce large friction also a possible dimensional problem with the sealing foils could have generated interference between the sealing foil and the baseplate preventing correct closure of the fixture

bull The tightening torque to close the fixture was of the order of 300 Nm (FNAL applies 110 Nm to 160 Nm)

bull Not clear no coil contraction after reaction actually less that 1 mm when 45 mm were expected

D SmekensN BourceyF Lackner

Click here to add footer 8

Reaction treatment ndash Coil 105

Adjustment of dwell time to compensate the delay between the

temperature and tooling temperature

The homogeneity of T during ramp up was not very good plusmn

9degCHowever it is OK during

dwell time

N BourceyF Lackner

Click here to add footer 9

Impregnationbull Resin CTD 101K

bull Anhydride cured epoxy system with excellent performance at cryogenic temperature and radiation resistance

bull The resin is preheated and the coil is impregnated at 60degC

bull Curing 110degC for 5 hoursbull Post curing heating 125degC for 16 hours

R GauthierD Smekens

Temperature [degC] Pot life [h] Viscosity [mmmiddotPas]25 145 1300

40 60 400

60 20 100

Click here to add footer 10

Instrumentation outer layer

Outer layer instrumentation incorporated in a Trace which is applied after impregnationThere are 2 ldquoUrdquo shaped SS quench heaters with Cu overlay with Cu masked off to provide heating regions Heater width is 19mm in low-field region with heater regions 90mm apart In the high-field region the heater width is 24mm and the heater regions are 130mm apartThere are 13 voltage taps on the Trace including 6 on the pole turn 1 on the layer jump and 4 on the mid-plane turn

EES5O

I

EE5O12-

+

EES5OO

EE5O11EE5O10

EE5O9

EE5O8 EE5O6EE5O7 EE5O5

EE5O4EE5O3EE5O2

EE5O1

Click here to add footer 11

Instrumentation inner layer

Inner layer instrumentation consists only of voltage taps There are 16 voltage taps including 6 on the pole turn 1 on the layer jump and 4 on the mid-plane turn with other taps adjacent to spacer block edges

S Izquierdo BermudezF-O PincotR Bateman

Click here to add footer 12

Quench heaters

50 70 90 110 130 150 170 19000

200400600800

100012001400160018002000

Low Field Region High Field Region

Heater Current (A)

Pow

er d

ensi

ty (W

cm

2)

Operation area

bull Width -gt Cover as many turns as possible

bull LF 19 mm bull HF 24 mm

bull Power densitybull LF asymp 75 Wcm2

bull HFasymp 55 Wcm2

Even if the operational current is expected to be in the range 100-120 A it would be good to have the possibility to go up to 150 A during short model tests to check the saturation of the system in terms of heater delays

119875119889=1198682119877119908119871

119877=120588 119871119908119905

119875119889=1198682 1205881199082119905

Heater width19 mm LF 24 mm HFρss=7310-7Ωm RRR=134

bull Distance between heater stations -gt quench propagation in between stations asymp 5 msbull LF 90 mmbull HF 130 mm

bull Coverage maximum coverage keeping the resistance within the allowable limits for a 55 m magnet (depends on the number of power suppliesheater circuits)

Cu

50 90130

192

4

Cu

Click here to add footer 13

Coils size

bull Both coils 101 and 105 were oversized only in the mid-plane

bull Best-fit on the outer diameter and the loading plates (interface with pole)

Click here to add footer 14

Excess in mid-plane

-150 -50 50 20

030

040

050

060

070

080

090

090

011

0012

0013

0014

000

100

200

300

400

500

600

700

800

leftrightaverage

Coil length [mm]

Inte

rfer

ence

[microm

]

Click here to add footer 15

Collaring steps

2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 320

50100150200250300350400

Distance to collaring position right lead endright return endleft lead endleft return end

F [MN]

offs

et k

ey g

roov

e [micro

m]

With 8MN the stoppers of the collaring tool were in contact

Click here to add footer 16

Shimming planbull Mid-plane is 650 microm beyond expectations To compensate

bull One layer of Kapton was removed on the mid-plane

bull Changed one layer of insulation to 005 microm thickness (in lieu of 0125 microm)

Click here to add footer 17

Yoking welding of the shellsF Lackner

1 2 3 4 5 6 7 80

100200300400500600700800

0

110

206

361426

526610

686Pressure rising April 28th 2014

Pressure rising step

Tota

l cha

rge

in to

ns

3154906157901240166520652225

002040608

SIDE B 0110206361426526610686

Length in [mm]

Yoke

gap

[mm

]

Tota

l loa

d in

tons

Max charge 500 tm on central section to close the welding gap

0

02

04

06

SIDE A0110206361426526610686

Length in [mm]

Yoke

gap

[mm

]

Tota

l loa

d in

tons

Click here to add footer 18

Structural analysis vs measurements

Click here to add footer 19

FEA Results 11T Mirror

FEA Max Cap gauge

pressure (MPa)

FEA Avg Cap gauge

pressure (MPa)

FEA Min Cap gauge

pressure (MPa)

Collar nose

stress (MPa)

Coil Min stress (MPa)

Coil Max Stress (MPa)

Avg Shell Stress (MPa)

Collaring Load 48 33 18 88 -7 -90

Post-Collaring 39 28 16 72 -7 -69

Collar in yoke 40 28 17 73 -9 -66

Max Press force 46 31 15 81 -14 -60 10

Shell Weld + Press Force 50 33 14 87 -16 -61 187

Shell Welded no Press Force 48 32 15 85 -15 -60 194

Collaring Load Post-Collaring Collar in yoke Max Press force Shell Weld + Press Force

Shell Welded no Press Force

Shell Welded - 297K

Cool Down (18K)

11-Tesla0

10

20

30

40

50

60Mirror Coil - contact pressure at pole (Cap Gauge)

FEA Max Cap gauge - pressure (MPa)

FEA Avg Cap gauge - pressure (MPa)

FEA Min Cap gauge - pressure (MPa)

Measured Coil Data (10 error bars)

Pres

sure

(MPa

)

Click here to add footer 20

ANSYS Forecast at 11-Tesla

Assembly Step

Max Capacitive gauge -

pressure (MPa)

Avg Capacitive gauge -

pressure (MPa)

Min Capacitive gauge -

pressure (MPa)

Collar-nose stress (MPa)

Coil Min stress (MPa)

Coil Max Stress (MPa)

Avg Shell Stress (MPa)

MirrorCoil

Shell Welded - 297K 48 32 15 85 -15 -60 195

Cool Down (18K) 37 21 5 62 -5 -74 375

11-Tesla 1 05 0 63 +13 -117 377

NominalCoil

Shell Welded - 297K 107 58 8 150 -14 -119 191

Cool Down (18K) 86 43 1 123 -21 -125 373

11-Tesla 22 11 0 57 -4 -120 374

Collar Nose Von-Mises Stress

At 11T

Coil BlocksAzimuthal Stress

At 11T

FEA predicted results

Click here to add footer 21

Bullet gauges loadingM GuinchardP Grosclaude

8 to 9 kN per bullet

Click here to add footer 22

Electrical tests ndash WhenF-O PincotL Grand Cleacutement

Are performed beforeafter each important construction step Test of pole Nb3Sn before curing - PBC Test of pole Nb3Sn before reaction ndash PBR Test of pole Nb3Sn after reaction ndash PAR Test of pole Nb3Sn after impregnation out of the mould ndash PAI Test of pole Nb3Sn after impregnation with instrumentation ndash PAIWI Test of collared coil before collaring ndash BC Test of collared coil after collaring ndash AC Test of the magnet under load before welding ndash UL Test of the magnet after shell welding ndash AW Test of the magnet after longitudinal coil loading ndash AL Test of the magnet after interconnection ndash AI Final Test of the magnet before delivery - FINAL

Click here to add footer 23

Electrical tests ndash WhatF-O PincotL Grand CleacutementAccording to the construction step we define

specific test valueselectrical tests among which

Resistance measurement(Coils Quench heaters Voltage taps Instrumentation) Inductance measurement Capacitance measurement Dielectric measurement(between coils QH instrumentation ground)

bull Insulation (up to 1kV 30s)bull current leakage (up to 1kV 5min)

Discharge test on coilUp to 1kV

Discharge test on quench heatersUp to 900V or 80AQH

Click here to add footer 24

Electrical testsF-O PincotL Grand Cleacutement

Resistance Insulation dielectric Inductance Capacitance Coil discharge QH discharge

Test phase

code

PBC X X X

PBR X X X

PAR X X X

PAI X X X X

PAIWI X X X X

BC X X X X X X

AC X X X X X X

UL X X

AW X X X X X X

AL X X X X X X

AI X X X X X X

FINAL X X X X X X

Click here to add footer 25

Click here to add footer 26

Plan for power tests coldbull RRR and strain gauge measurementsbull Preliminary tests ndash Setup protection ndash Splice resistance

measurements (current plateaus at 2 4 6 8 and 10 kA) ndash 3 hoursbull Training 43 K ndash 15 quenches ndash 3 days bull Training 19 K ndash 10 quenches ndash 25 days

Stability on current plateau ndash 05 daybull Ramp-rate study 100 As and 50 As ndash 05 day

AC-loss measurements (includes inductance measurement) at 5 to 100 As ndash 05 day

bull Quench heater efficiency study 3 different settings of QH pulse for 3 currents each Long re-cooling of the magnet due to delay of energy extraction ndash 3 days

bull High MIIts tests (protection delay) 6 quenches ndash 3 days

bull Quench propagation velocity measurements acquired for the training quenches

G Willeringbull Cool down bull Day 1

bull Day 2-4bull Day 5-7

bull Day 8

bull Day 9-11

bull Day 12-14

Click here to add footer 27

Further actionsbull After cold tests warm magnetic

measurements will be carried out with the two coils connected

bull Model 1 MBHSP101 single aperture with cable OST RRP 108127 for both polesbull Instrumentation of coils 106 and 107 going onbull Collaring scheduled around middle of June

  • CERN-FNAL Video Meeting 12 Progress of the 11T Dipole short m
  • Contributions
  • Main design features
  • Specific features
  • Assembly conditions - Winding
  • Binder curing
  • Reaction treatment
  • Reaction treatment ndash Coil 105
  • Impregnation
  • Instrumentation outer layer
  • Instrumentation inner layer
  • Quench heaters
  • Coils size
  • Excess in mid-plane
  • Collaring steps
  • Shimming plan
  • Yoking welding of the shells
  • Structural analysis vs measurements
  • FEA Results
  • ANSYS Forecast at 11-Tesla
  • Bullet gauges loading
  • Electrical tests ndash When
  • Electrical tests ndash What
  • Electrical tests
  • Slide 25
  • Plan for power tests cold
  • Further actions
Page 6: CERN MBHSM0101 general  status F. Savary on behalf of the 11T Dipole Project Team

Click here to add footer 6

Binder curingbull Binder CTD 1202-X qty

bull Coil 101 IL in excess OL in excessbull Coil 105 IL 100 g OL 100 g

bull Shimming nominal (shimming such that in the press the mid-plane of the cured coil is like in the magnet 012 mm above center axis)bull This is different compared to FERMILAB where oversized shimming

is used to compact the coil mid-plane beyond its nominal position in order to obtain a smaller coil size before entering into reaction

bull With a load of 08 MN the mold is nearly closed (lt 01mm)bull Then a load of 2 MN is used for IL and 42 MN for the OL

(complete pole)bull The stress in the coils may not exceed 37 MPa at that stage

D SmekensJ Mazet

Click here to add footer 7

Reaction treatmentbull Cavity of the reaction fixture is radially bigger than the curing

mold by 01 mm and of similar dimension at coil mid-planebull Thus if the curing press can be closed before reaching 37

MPa the coil cannot be subjected to higher stress when closing the fixture However the dry fiber glass and the tight tolerances induce large friction also a possible dimensional problem with the sealing foils could have generated interference between the sealing foil and the baseplate preventing correct closure of the fixture

bull The tightening torque to close the fixture was of the order of 300 Nm (FNAL applies 110 Nm to 160 Nm)

bull Not clear no coil contraction after reaction actually less that 1 mm when 45 mm were expected

D SmekensN BourceyF Lackner

Click here to add footer 8

Reaction treatment ndash Coil 105

Adjustment of dwell time to compensate the delay between the

temperature and tooling temperature

The homogeneity of T during ramp up was not very good plusmn

9degCHowever it is OK during

dwell time

N BourceyF Lackner

Click here to add footer 9

Impregnationbull Resin CTD 101K

bull Anhydride cured epoxy system with excellent performance at cryogenic temperature and radiation resistance

bull The resin is preheated and the coil is impregnated at 60degC

bull Curing 110degC for 5 hoursbull Post curing heating 125degC for 16 hours

R GauthierD Smekens

Temperature [degC] Pot life [h] Viscosity [mmmiddotPas]25 145 1300

40 60 400

60 20 100

Click here to add footer 10

Instrumentation outer layer

Outer layer instrumentation incorporated in a Trace which is applied after impregnationThere are 2 ldquoUrdquo shaped SS quench heaters with Cu overlay with Cu masked off to provide heating regions Heater width is 19mm in low-field region with heater regions 90mm apart In the high-field region the heater width is 24mm and the heater regions are 130mm apartThere are 13 voltage taps on the Trace including 6 on the pole turn 1 on the layer jump and 4 on the mid-plane turn

EES5O

I

EE5O12-

+

EES5OO

EE5O11EE5O10

EE5O9

EE5O8 EE5O6EE5O7 EE5O5

EE5O4EE5O3EE5O2

EE5O1

Click here to add footer 11

Instrumentation inner layer

Inner layer instrumentation consists only of voltage taps There are 16 voltage taps including 6 on the pole turn 1 on the layer jump and 4 on the mid-plane turn with other taps adjacent to spacer block edges

S Izquierdo BermudezF-O PincotR Bateman

Click here to add footer 12

Quench heaters

50 70 90 110 130 150 170 19000

200400600800

100012001400160018002000

Low Field Region High Field Region

Heater Current (A)

Pow

er d

ensi

ty (W

cm

2)

Operation area

bull Width -gt Cover as many turns as possible

bull LF 19 mm bull HF 24 mm

bull Power densitybull LF asymp 75 Wcm2

bull HFasymp 55 Wcm2

Even if the operational current is expected to be in the range 100-120 A it would be good to have the possibility to go up to 150 A during short model tests to check the saturation of the system in terms of heater delays

119875119889=1198682119877119908119871

119877=120588 119871119908119905

119875119889=1198682 1205881199082119905

Heater width19 mm LF 24 mm HFρss=7310-7Ωm RRR=134

bull Distance between heater stations -gt quench propagation in between stations asymp 5 msbull LF 90 mmbull HF 130 mm

bull Coverage maximum coverage keeping the resistance within the allowable limits for a 55 m magnet (depends on the number of power suppliesheater circuits)

Cu

50 90130

192

4

Cu

Click here to add footer 13

Coils size

bull Both coils 101 and 105 were oversized only in the mid-plane

bull Best-fit on the outer diameter and the loading plates (interface with pole)

Click here to add footer 14

Excess in mid-plane

-150 -50 50 20

030

040

050

060

070

080

090

090

011

0012

0013

0014

000

100

200

300

400

500

600

700

800

leftrightaverage

Coil length [mm]

Inte

rfer

ence

[microm

]

Click here to add footer 15

Collaring steps

2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 320

50100150200250300350400

Distance to collaring position right lead endright return endleft lead endleft return end

F [MN]

offs

et k

ey g

roov

e [micro

m]

With 8MN the stoppers of the collaring tool were in contact

Click here to add footer 16

Shimming planbull Mid-plane is 650 microm beyond expectations To compensate

bull One layer of Kapton was removed on the mid-plane

bull Changed one layer of insulation to 005 microm thickness (in lieu of 0125 microm)

Click here to add footer 17

Yoking welding of the shellsF Lackner

1 2 3 4 5 6 7 80

100200300400500600700800

0

110

206

361426

526610

686Pressure rising April 28th 2014

Pressure rising step

Tota

l cha

rge

in to

ns

3154906157901240166520652225

002040608

SIDE B 0110206361426526610686

Length in [mm]

Yoke

gap

[mm

]

Tota

l loa

d in

tons

Max charge 500 tm on central section to close the welding gap

0

02

04

06

SIDE A0110206361426526610686

Length in [mm]

Yoke

gap

[mm

]

Tota

l loa

d in

tons

Click here to add footer 18

Structural analysis vs measurements

Click here to add footer 19

FEA Results 11T Mirror

FEA Max Cap gauge

pressure (MPa)

FEA Avg Cap gauge

pressure (MPa)

FEA Min Cap gauge

pressure (MPa)

Collar nose

stress (MPa)

Coil Min stress (MPa)

Coil Max Stress (MPa)

Avg Shell Stress (MPa)

Collaring Load 48 33 18 88 -7 -90

Post-Collaring 39 28 16 72 -7 -69

Collar in yoke 40 28 17 73 -9 -66

Max Press force 46 31 15 81 -14 -60 10

Shell Weld + Press Force 50 33 14 87 -16 -61 187

Shell Welded no Press Force 48 32 15 85 -15 -60 194

Collaring Load Post-Collaring Collar in yoke Max Press force Shell Weld + Press Force

Shell Welded no Press Force

Shell Welded - 297K

Cool Down (18K)

11-Tesla0

10

20

30

40

50

60Mirror Coil - contact pressure at pole (Cap Gauge)

FEA Max Cap gauge - pressure (MPa)

FEA Avg Cap gauge - pressure (MPa)

FEA Min Cap gauge - pressure (MPa)

Measured Coil Data (10 error bars)

Pres

sure

(MPa

)

Click here to add footer 20

ANSYS Forecast at 11-Tesla

Assembly Step

Max Capacitive gauge -

pressure (MPa)

Avg Capacitive gauge -

pressure (MPa)

Min Capacitive gauge -

pressure (MPa)

Collar-nose stress (MPa)

Coil Min stress (MPa)

Coil Max Stress (MPa)

Avg Shell Stress (MPa)

MirrorCoil

Shell Welded - 297K 48 32 15 85 -15 -60 195

Cool Down (18K) 37 21 5 62 -5 -74 375

11-Tesla 1 05 0 63 +13 -117 377

NominalCoil

Shell Welded - 297K 107 58 8 150 -14 -119 191

Cool Down (18K) 86 43 1 123 -21 -125 373

11-Tesla 22 11 0 57 -4 -120 374

Collar Nose Von-Mises Stress

At 11T

Coil BlocksAzimuthal Stress

At 11T

FEA predicted results

Click here to add footer 21

Bullet gauges loadingM GuinchardP Grosclaude

8 to 9 kN per bullet

Click here to add footer 22

Electrical tests ndash WhenF-O PincotL Grand Cleacutement

Are performed beforeafter each important construction step Test of pole Nb3Sn before curing - PBC Test of pole Nb3Sn before reaction ndash PBR Test of pole Nb3Sn after reaction ndash PAR Test of pole Nb3Sn after impregnation out of the mould ndash PAI Test of pole Nb3Sn after impregnation with instrumentation ndash PAIWI Test of collared coil before collaring ndash BC Test of collared coil after collaring ndash AC Test of the magnet under load before welding ndash UL Test of the magnet after shell welding ndash AW Test of the magnet after longitudinal coil loading ndash AL Test of the magnet after interconnection ndash AI Final Test of the magnet before delivery - FINAL

Click here to add footer 23

Electrical tests ndash WhatF-O PincotL Grand CleacutementAccording to the construction step we define

specific test valueselectrical tests among which

Resistance measurement(Coils Quench heaters Voltage taps Instrumentation) Inductance measurement Capacitance measurement Dielectric measurement(between coils QH instrumentation ground)

bull Insulation (up to 1kV 30s)bull current leakage (up to 1kV 5min)

Discharge test on coilUp to 1kV

Discharge test on quench heatersUp to 900V or 80AQH

Click here to add footer 24

Electrical testsF-O PincotL Grand Cleacutement

Resistance Insulation dielectric Inductance Capacitance Coil discharge QH discharge

Test phase

code

PBC X X X

PBR X X X

PAR X X X

PAI X X X X

PAIWI X X X X

BC X X X X X X

AC X X X X X X

UL X X

AW X X X X X X

AL X X X X X X

AI X X X X X X

FINAL X X X X X X

Click here to add footer 25

Click here to add footer 26

Plan for power tests coldbull RRR and strain gauge measurementsbull Preliminary tests ndash Setup protection ndash Splice resistance

measurements (current plateaus at 2 4 6 8 and 10 kA) ndash 3 hoursbull Training 43 K ndash 15 quenches ndash 3 days bull Training 19 K ndash 10 quenches ndash 25 days

Stability on current plateau ndash 05 daybull Ramp-rate study 100 As and 50 As ndash 05 day

AC-loss measurements (includes inductance measurement) at 5 to 100 As ndash 05 day

bull Quench heater efficiency study 3 different settings of QH pulse for 3 currents each Long re-cooling of the magnet due to delay of energy extraction ndash 3 days

bull High MIIts tests (protection delay) 6 quenches ndash 3 days

bull Quench propagation velocity measurements acquired for the training quenches

G Willeringbull Cool down bull Day 1

bull Day 2-4bull Day 5-7

bull Day 8

bull Day 9-11

bull Day 12-14

Click here to add footer 27

Further actionsbull After cold tests warm magnetic

measurements will be carried out with the two coils connected

bull Model 1 MBHSP101 single aperture with cable OST RRP 108127 for both polesbull Instrumentation of coils 106 and 107 going onbull Collaring scheduled around middle of June

  • CERN-FNAL Video Meeting 12 Progress of the 11T Dipole short m
  • Contributions
  • Main design features
  • Specific features
  • Assembly conditions - Winding
  • Binder curing
  • Reaction treatment
  • Reaction treatment ndash Coil 105
  • Impregnation
  • Instrumentation outer layer
  • Instrumentation inner layer
  • Quench heaters
  • Coils size
  • Excess in mid-plane
  • Collaring steps
  • Shimming plan
  • Yoking welding of the shells
  • Structural analysis vs measurements
  • FEA Results
  • ANSYS Forecast at 11-Tesla
  • Bullet gauges loading
  • Electrical tests ndash When
  • Electrical tests ndash What
  • Electrical tests
  • Slide 25
  • Plan for power tests cold
  • Further actions
Page 7: CERN MBHSM0101 general  status F. Savary on behalf of the 11T Dipole Project Team

Click here to add footer 7

Reaction treatmentbull Cavity of the reaction fixture is radially bigger than the curing

mold by 01 mm and of similar dimension at coil mid-planebull Thus if the curing press can be closed before reaching 37

MPa the coil cannot be subjected to higher stress when closing the fixture However the dry fiber glass and the tight tolerances induce large friction also a possible dimensional problem with the sealing foils could have generated interference between the sealing foil and the baseplate preventing correct closure of the fixture

bull The tightening torque to close the fixture was of the order of 300 Nm (FNAL applies 110 Nm to 160 Nm)

bull Not clear no coil contraction after reaction actually less that 1 mm when 45 mm were expected

D SmekensN BourceyF Lackner

Click here to add footer 8

Reaction treatment ndash Coil 105

Adjustment of dwell time to compensate the delay between the

temperature and tooling temperature

The homogeneity of T during ramp up was not very good plusmn

9degCHowever it is OK during

dwell time

N BourceyF Lackner

Click here to add footer 9

Impregnationbull Resin CTD 101K

bull Anhydride cured epoxy system with excellent performance at cryogenic temperature and radiation resistance

bull The resin is preheated and the coil is impregnated at 60degC

bull Curing 110degC for 5 hoursbull Post curing heating 125degC for 16 hours

R GauthierD Smekens

Temperature [degC] Pot life [h] Viscosity [mmmiddotPas]25 145 1300

40 60 400

60 20 100

Click here to add footer 10

Instrumentation outer layer

Outer layer instrumentation incorporated in a Trace which is applied after impregnationThere are 2 ldquoUrdquo shaped SS quench heaters with Cu overlay with Cu masked off to provide heating regions Heater width is 19mm in low-field region with heater regions 90mm apart In the high-field region the heater width is 24mm and the heater regions are 130mm apartThere are 13 voltage taps on the Trace including 6 on the pole turn 1 on the layer jump and 4 on the mid-plane turn

EES5O

I

EE5O12-

+

EES5OO

EE5O11EE5O10

EE5O9

EE5O8 EE5O6EE5O7 EE5O5

EE5O4EE5O3EE5O2

EE5O1

Click here to add footer 11

Instrumentation inner layer

Inner layer instrumentation consists only of voltage taps There are 16 voltage taps including 6 on the pole turn 1 on the layer jump and 4 on the mid-plane turn with other taps adjacent to spacer block edges

S Izquierdo BermudezF-O PincotR Bateman

Click here to add footer 12

Quench heaters

50 70 90 110 130 150 170 19000

200400600800

100012001400160018002000

Low Field Region High Field Region

Heater Current (A)

Pow

er d

ensi

ty (W

cm

2)

Operation area

bull Width -gt Cover as many turns as possible

bull LF 19 mm bull HF 24 mm

bull Power densitybull LF asymp 75 Wcm2

bull HFasymp 55 Wcm2

Even if the operational current is expected to be in the range 100-120 A it would be good to have the possibility to go up to 150 A during short model tests to check the saturation of the system in terms of heater delays

119875119889=1198682119877119908119871

119877=120588 119871119908119905

119875119889=1198682 1205881199082119905

Heater width19 mm LF 24 mm HFρss=7310-7Ωm RRR=134

bull Distance between heater stations -gt quench propagation in between stations asymp 5 msbull LF 90 mmbull HF 130 mm

bull Coverage maximum coverage keeping the resistance within the allowable limits for a 55 m magnet (depends on the number of power suppliesheater circuits)

Cu

50 90130

192

4

Cu

Click here to add footer 13

Coils size

bull Both coils 101 and 105 were oversized only in the mid-plane

bull Best-fit on the outer diameter and the loading plates (interface with pole)

Click here to add footer 14

Excess in mid-plane

-150 -50 50 20

030

040

050

060

070

080

090

090

011

0012

0013

0014

000

100

200

300

400

500

600

700

800

leftrightaverage

Coil length [mm]

Inte

rfer

ence

[microm

]

Click here to add footer 15

Collaring steps

2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 320

50100150200250300350400

Distance to collaring position right lead endright return endleft lead endleft return end

F [MN]

offs

et k

ey g

roov

e [micro

m]

With 8MN the stoppers of the collaring tool were in contact

Click here to add footer 16

Shimming planbull Mid-plane is 650 microm beyond expectations To compensate

bull One layer of Kapton was removed on the mid-plane

bull Changed one layer of insulation to 005 microm thickness (in lieu of 0125 microm)

Click here to add footer 17

Yoking welding of the shellsF Lackner

1 2 3 4 5 6 7 80

100200300400500600700800

0

110

206

361426

526610

686Pressure rising April 28th 2014

Pressure rising step

Tota

l cha

rge

in to

ns

3154906157901240166520652225

002040608

SIDE B 0110206361426526610686

Length in [mm]

Yoke

gap

[mm

]

Tota

l loa

d in

tons

Max charge 500 tm on central section to close the welding gap

0

02

04

06

SIDE A0110206361426526610686

Length in [mm]

Yoke

gap

[mm

]

Tota

l loa

d in

tons

Click here to add footer 18

Structural analysis vs measurements

Click here to add footer 19

FEA Results 11T Mirror

FEA Max Cap gauge

pressure (MPa)

FEA Avg Cap gauge

pressure (MPa)

FEA Min Cap gauge

pressure (MPa)

Collar nose

stress (MPa)

Coil Min stress (MPa)

Coil Max Stress (MPa)

Avg Shell Stress (MPa)

Collaring Load 48 33 18 88 -7 -90

Post-Collaring 39 28 16 72 -7 -69

Collar in yoke 40 28 17 73 -9 -66

Max Press force 46 31 15 81 -14 -60 10

Shell Weld + Press Force 50 33 14 87 -16 -61 187

Shell Welded no Press Force 48 32 15 85 -15 -60 194

Collaring Load Post-Collaring Collar in yoke Max Press force Shell Weld + Press Force

Shell Welded no Press Force

Shell Welded - 297K

Cool Down (18K)

11-Tesla0

10

20

30

40

50

60Mirror Coil - contact pressure at pole (Cap Gauge)

FEA Max Cap gauge - pressure (MPa)

FEA Avg Cap gauge - pressure (MPa)

FEA Min Cap gauge - pressure (MPa)

Measured Coil Data (10 error bars)

Pres

sure

(MPa

)

Click here to add footer 20

ANSYS Forecast at 11-Tesla

Assembly Step

Max Capacitive gauge -

pressure (MPa)

Avg Capacitive gauge -

pressure (MPa)

Min Capacitive gauge -

pressure (MPa)

Collar-nose stress (MPa)

Coil Min stress (MPa)

Coil Max Stress (MPa)

Avg Shell Stress (MPa)

MirrorCoil

Shell Welded - 297K 48 32 15 85 -15 -60 195

Cool Down (18K) 37 21 5 62 -5 -74 375

11-Tesla 1 05 0 63 +13 -117 377

NominalCoil

Shell Welded - 297K 107 58 8 150 -14 -119 191

Cool Down (18K) 86 43 1 123 -21 -125 373

11-Tesla 22 11 0 57 -4 -120 374

Collar Nose Von-Mises Stress

At 11T

Coil BlocksAzimuthal Stress

At 11T

FEA predicted results

Click here to add footer 21

Bullet gauges loadingM GuinchardP Grosclaude

8 to 9 kN per bullet

Click here to add footer 22

Electrical tests ndash WhenF-O PincotL Grand Cleacutement

Are performed beforeafter each important construction step Test of pole Nb3Sn before curing - PBC Test of pole Nb3Sn before reaction ndash PBR Test of pole Nb3Sn after reaction ndash PAR Test of pole Nb3Sn after impregnation out of the mould ndash PAI Test of pole Nb3Sn after impregnation with instrumentation ndash PAIWI Test of collared coil before collaring ndash BC Test of collared coil after collaring ndash AC Test of the magnet under load before welding ndash UL Test of the magnet after shell welding ndash AW Test of the magnet after longitudinal coil loading ndash AL Test of the magnet after interconnection ndash AI Final Test of the magnet before delivery - FINAL

Click here to add footer 23

Electrical tests ndash WhatF-O PincotL Grand CleacutementAccording to the construction step we define

specific test valueselectrical tests among which

Resistance measurement(Coils Quench heaters Voltage taps Instrumentation) Inductance measurement Capacitance measurement Dielectric measurement(between coils QH instrumentation ground)

bull Insulation (up to 1kV 30s)bull current leakage (up to 1kV 5min)

Discharge test on coilUp to 1kV

Discharge test on quench heatersUp to 900V or 80AQH

Click here to add footer 24

Electrical testsF-O PincotL Grand Cleacutement

Resistance Insulation dielectric Inductance Capacitance Coil discharge QH discharge

Test phase

code

PBC X X X

PBR X X X

PAR X X X

PAI X X X X

PAIWI X X X X

BC X X X X X X

AC X X X X X X

UL X X

AW X X X X X X

AL X X X X X X

AI X X X X X X

FINAL X X X X X X

Click here to add footer 25

Click here to add footer 26

Plan for power tests coldbull RRR and strain gauge measurementsbull Preliminary tests ndash Setup protection ndash Splice resistance

measurements (current plateaus at 2 4 6 8 and 10 kA) ndash 3 hoursbull Training 43 K ndash 15 quenches ndash 3 days bull Training 19 K ndash 10 quenches ndash 25 days

Stability on current plateau ndash 05 daybull Ramp-rate study 100 As and 50 As ndash 05 day

AC-loss measurements (includes inductance measurement) at 5 to 100 As ndash 05 day

bull Quench heater efficiency study 3 different settings of QH pulse for 3 currents each Long re-cooling of the magnet due to delay of energy extraction ndash 3 days

bull High MIIts tests (protection delay) 6 quenches ndash 3 days

bull Quench propagation velocity measurements acquired for the training quenches

G Willeringbull Cool down bull Day 1

bull Day 2-4bull Day 5-7

bull Day 8

bull Day 9-11

bull Day 12-14

Click here to add footer 27

Further actionsbull After cold tests warm magnetic

measurements will be carried out with the two coils connected

bull Model 1 MBHSP101 single aperture with cable OST RRP 108127 for both polesbull Instrumentation of coils 106 and 107 going onbull Collaring scheduled around middle of June

  • CERN-FNAL Video Meeting 12 Progress of the 11T Dipole short m
  • Contributions
  • Main design features
  • Specific features
  • Assembly conditions - Winding
  • Binder curing
  • Reaction treatment
  • Reaction treatment ndash Coil 105
  • Impregnation
  • Instrumentation outer layer
  • Instrumentation inner layer
  • Quench heaters
  • Coils size
  • Excess in mid-plane
  • Collaring steps
  • Shimming plan
  • Yoking welding of the shells
  • Structural analysis vs measurements
  • FEA Results
  • ANSYS Forecast at 11-Tesla
  • Bullet gauges loading
  • Electrical tests ndash When
  • Electrical tests ndash What
  • Electrical tests
  • Slide 25
  • Plan for power tests cold
  • Further actions
Page 8: CERN MBHSM0101 general  status F. Savary on behalf of the 11T Dipole Project Team

Click here to add footer 8

Reaction treatment ndash Coil 105

Adjustment of dwell time to compensate the delay between the

temperature and tooling temperature

The homogeneity of T during ramp up was not very good plusmn

9degCHowever it is OK during

dwell time

N BourceyF Lackner

Click here to add footer 9

Impregnationbull Resin CTD 101K

bull Anhydride cured epoxy system with excellent performance at cryogenic temperature and radiation resistance

bull The resin is preheated and the coil is impregnated at 60degC

bull Curing 110degC for 5 hoursbull Post curing heating 125degC for 16 hours

R GauthierD Smekens

Temperature [degC] Pot life [h] Viscosity [mmmiddotPas]25 145 1300

40 60 400

60 20 100

Click here to add footer 10

Instrumentation outer layer

Outer layer instrumentation incorporated in a Trace which is applied after impregnationThere are 2 ldquoUrdquo shaped SS quench heaters with Cu overlay with Cu masked off to provide heating regions Heater width is 19mm in low-field region with heater regions 90mm apart In the high-field region the heater width is 24mm and the heater regions are 130mm apartThere are 13 voltage taps on the Trace including 6 on the pole turn 1 on the layer jump and 4 on the mid-plane turn

EES5O

I

EE5O12-

+

EES5OO

EE5O11EE5O10

EE5O9

EE5O8 EE5O6EE5O7 EE5O5

EE5O4EE5O3EE5O2

EE5O1

Click here to add footer 11

Instrumentation inner layer

Inner layer instrumentation consists only of voltage taps There are 16 voltage taps including 6 on the pole turn 1 on the layer jump and 4 on the mid-plane turn with other taps adjacent to spacer block edges

S Izquierdo BermudezF-O PincotR Bateman

Click here to add footer 12

Quench heaters

50 70 90 110 130 150 170 19000

200400600800

100012001400160018002000

Low Field Region High Field Region

Heater Current (A)

Pow

er d

ensi

ty (W

cm

2)

Operation area

bull Width -gt Cover as many turns as possible

bull LF 19 mm bull HF 24 mm

bull Power densitybull LF asymp 75 Wcm2

bull HFasymp 55 Wcm2

Even if the operational current is expected to be in the range 100-120 A it would be good to have the possibility to go up to 150 A during short model tests to check the saturation of the system in terms of heater delays

119875119889=1198682119877119908119871

119877=120588 119871119908119905

119875119889=1198682 1205881199082119905

Heater width19 mm LF 24 mm HFρss=7310-7Ωm RRR=134

bull Distance between heater stations -gt quench propagation in between stations asymp 5 msbull LF 90 mmbull HF 130 mm

bull Coverage maximum coverage keeping the resistance within the allowable limits for a 55 m magnet (depends on the number of power suppliesheater circuits)

Cu

50 90130

192

4

Cu

Click here to add footer 13

Coils size

bull Both coils 101 and 105 were oversized only in the mid-plane

bull Best-fit on the outer diameter and the loading plates (interface with pole)

Click here to add footer 14

Excess in mid-plane

-150 -50 50 20

030

040

050

060

070

080

090

090

011

0012

0013

0014

000

100

200

300

400

500

600

700

800

leftrightaverage

Coil length [mm]

Inte

rfer

ence

[microm

]

Click here to add footer 15

Collaring steps

2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 320

50100150200250300350400

Distance to collaring position right lead endright return endleft lead endleft return end

F [MN]

offs

et k

ey g

roov

e [micro

m]

With 8MN the stoppers of the collaring tool were in contact

Click here to add footer 16

Shimming planbull Mid-plane is 650 microm beyond expectations To compensate

bull One layer of Kapton was removed on the mid-plane

bull Changed one layer of insulation to 005 microm thickness (in lieu of 0125 microm)

Click here to add footer 17

Yoking welding of the shellsF Lackner

1 2 3 4 5 6 7 80

100200300400500600700800

0

110

206

361426

526610

686Pressure rising April 28th 2014

Pressure rising step

Tota

l cha

rge

in to

ns

3154906157901240166520652225

002040608

SIDE B 0110206361426526610686

Length in [mm]

Yoke

gap

[mm

]

Tota

l loa

d in

tons

Max charge 500 tm on central section to close the welding gap

0

02

04

06

SIDE A0110206361426526610686

Length in [mm]

Yoke

gap

[mm

]

Tota

l loa

d in

tons

Click here to add footer 18

Structural analysis vs measurements

Click here to add footer 19

FEA Results 11T Mirror

FEA Max Cap gauge

pressure (MPa)

FEA Avg Cap gauge

pressure (MPa)

FEA Min Cap gauge

pressure (MPa)

Collar nose

stress (MPa)

Coil Min stress (MPa)

Coil Max Stress (MPa)

Avg Shell Stress (MPa)

Collaring Load 48 33 18 88 -7 -90

Post-Collaring 39 28 16 72 -7 -69

Collar in yoke 40 28 17 73 -9 -66

Max Press force 46 31 15 81 -14 -60 10

Shell Weld + Press Force 50 33 14 87 -16 -61 187

Shell Welded no Press Force 48 32 15 85 -15 -60 194

Collaring Load Post-Collaring Collar in yoke Max Press force Shell Weld + Press Force

Shell Welded no Press Force

Shell Welded - 297K

Cool Down (18K)

11-Tesla0

10

20

30

40

50

60Mirror Coil - contact pressure at pole (Cap Gauge)

FEA Max Cap gauge - pressure (MPa)

FEA Avg Cap gauge - pressure (MPa)

FEA Min Cap gauge - pressure (MPa)

Measured Coil Data (10 error bars)

Pres

sure

(MPa

)

Click here to add footer 20

ANSYS Forecast at 11-Tesla

Assembly Step

Max Capacitive gauge -

pressure (MPa)

Avg Capacitive gauge -

pressure (MPa)

Min Capacitive gauge -

pressure (MPa)

Collar-nose stress (MPa)

Coil Min stress (MPa)

Coil Max Stress (MPa)

Avg Shell Stress (MPa)

MirrorCoil

Shell Welded - 297K 48 32 15 85 -15 -60 195

Cool Down (18K) 37 21 5 62 -5 -74 375

11-Tesla 1 05 0 63 +13 -117 377

NominalCoil

Shell Welded - 297K 107 58 8 150 -14 -119 191

Cool Down (18K) 86 43 1 123 -21 -125 373

11-Tesla 22 11 0 57 -4 -120 374

Collar Nose Von-Mises Stress

At 11T

Coil BlocksAzimuthal Stress

At 11T

FEA predicted results

Click here to add footer 21

Bullet gauges loadingM GuinchardP Grosclaude

8 to 9 kN per bullet

Click here to add footer 22

Electrical tests ndash WhenF-O PincotL Grand Cleacutement

Are performed beforeafter each important construction step Test of pole Nb3Sn before curing - PBC Test of pole Nb3Sn before reaction ndash PBR Test of pole Nb3Sn after reaction ndash PAR Test of pole Nb3Sn after impregnation out of the mould ndash PAI Test of pole Nb3Sn after impregnation with instrumentation ndash PAIWI Test of collared coil before collaring ndash BC Test of collared coil after collaring ndash AC Test of the magnet under load before welding ndash UL Test of the magnet after shell welding ndash AW Test of the magnet after longitudinal coil loading ndash AL Test of the magnet after interconnection ndash AI Final Test of the magnet before delivery - FINAL

Click here to add footer 23

Electrical tests ndash WhatF-O PincotL Grand CleacutementAccording to the construction step we define

specific test valueselectrical tests among which

Resistance measurement(Coils Quench heaters Voltage taps Instrumentation) Inductance measurement Capacitance measurement Dielectric measurement(between coils QH instrumentation ground)

bull Insulation (up to 1kV 30s)bull current leakage (up to 1kV 5min)

Discharge test on coilUp to 1kV

Discharge test on quench heatersUp to 900V or 80AQH

Click here to add footer 24

Electrical testsF-O PincotL Grand Cleacutement

Resistance Insulation dielectric Inductance Capacitance Coil discharge QH discharge

Test phase

code

PBC X X X

PBR X X X

PAR X X X

PAI X X X X

PAIWI X X X X

BC X X X X X X

AC X X X X X X

UL X X

AW X X X X X X

AL X X X X X X

AI X X X X X X

FINAL X X X X X X

Click here to add footer 25

Click here to add footer 26

Plan for power tests coldbull RRR and strain gauge measurementsbull Preliminary tests ndash Setup protection ndash Splice resistance

measurements (current plateaus at 2 4 6 8 and 10 kA) ndash 3 hoursbull Training 43 K ndash 15 quenches ndash 3 days bull Training 19 K ndash 10 quenches ndash 25 days

Stability on current plateau ndash 05 daybull Ramp-rate study 100 As and 50 As ndash 05 day

AC-loss measurements (includes inductance measurement) at 5 to 100 As ndash 05 day

bull Quench heater efficiency study 3 different settings of QH pulse for 3 currents each Long re-cooling of the magnet due to delay of energy extraction ndash 3 days

bull High MIIts tests (protection delay) 6 quenches ndash 3 days

bull Quench propagation velocity measurements acquired for the training quenches

G Willeringbull Cool down bull Day 1

bull Day 2-4bull Day 5-7

bull Day 8

bull Day 9-11

bull Day 12-14

Click here to add footer 27

Further actionsbull After cold tests warm magnetic

measurements will be carried out with the two coils connected

bull Model 1 MBHSP101 single aperture with cable OST RRP 108127 for both polesbull Instrumentation of coils 106 and 107 going onbull Collaring scheduled around middle of June

  • CERN-FNAL Video Meeting 12 Progress of the 11T Dipole short m
  • Contributions
  • Main design features
  • Specific features
  • Assembly conditions - Winding
  • Binder curing
  • Reaction treatment
  • Reaction treatment ndash Coil 105
  • Impregnation
  • Instrumentation outer layer
  • Instrumentation inner layer
  • Quench heaters
  • Coils size
  • Excess in mid-plane
  • Collaring steps
  • Shimming plan
  • Yoking welding of the shells
  • Structural analysis vs measurements
  • FEA Results
  • ANSYS Forecast at 11-Tesla
  • Bullet gauges loading
  • Electrical tests ndash When
  • Electrical tests ndash What
  • Electrical tests
  • Slide 25
  • Plan for power tests cold
  • Further actions
Page 9: CERN MBHSM0101 general  status F. Savary on behalf of the 11T Dipole Project Team

Click here to add footer 9

Impregnationbull Resin CTD 101K

bull Anhydride cured epoxy system with excellent performance at cryogenic temperature and radiation resistance

bull The resin is preheated and the coil is impregnated at 60degC

bull Curing 110degC for 5 hoursbull Post curing heating 125degC for 16 hours

R GauthierD Smekens

Temperature [degC] Pot life [h] Viscosity [mmmiddotPas]25 145 1300

40 60 400

60 20 100

Click here to add footer 10

Instrumentation outer layer

Outer layer instrumentation incorporated in a Trace which is applied after impregnationThere are 2 ldquoUrdquo shaped SS quench heaters with Cu overlay with Cu masked off to provide heating regions Heater width is 19mm in low-field region with heater regions 90mm apart In the high-field region the heater width is 24mm and the heater regions are 130mm apartThere are 13 voltage taps on the Trace including 6 on the pole turn 1 on the layer jump and 4 on the mid-plane turn

EES5O

I

EE5O12-

+

EES5OO

EE5O11EE5O10

EE5O9

EE5O8 EE5O6EE5O7 EE5O5

EE5O4EE5O3EE5O2

EE5O1

Click here to add footer 11

Instrumentation inner layer

Inner layer instrumentation consists only of voltage taps There are 16 voltage taps including 6 on the pole turn 1 on the layer jump and 4 on the mid-plane turn with other taps adjacent to spacer block edges

S Izquierdo BermudezF-O PincotR Bateman

Click here to add footer 12

Quench heaters

50 70 90 110 130 150 170 19000

200400600800

100012001400160018002000

Low Field Region High Field Region

Heater Current (A)

Pow

er d

ensi

ty (W

cm

2)

Operation area

bull Width -gt Cover as many turns as possible

bull LF 19 mm bull HF 24 mm

bull Power densitybull LF asymp 75 Wcm2

bull HFasymp 55 Wcm2

Even if the operational current is expected to be in the range 100-120 A it would be good to have the possibility to go up to 150 A during short model tests to check the saturation of the system in terms of heater delays

119875119889=1198682119877119908119871

119877=120588 119871119908119905

119875119889=1198682 1205881199082119905

Heater width19 mm LF 24 mm HFρss=7310-7Ωm RRR=134

bull Distance between heater stations -gt quench propagation in between stations asymp 5 msbull LF 90 mmbull HF 130 mm

bull Coverage maximum coverage keeping the resistance within the allowable limits for a 55 m magnet (depends on the number of power suppliesheater circuits)

Cu

50 90130

192

4

Cu

Click here to add footer 13

Coils size

bull Both coils 101 and 105 were oversized only in the mid-plane

bull Best-fit on the outer diameter and the loading plates (interface with pole)

Click here to add footer 14

Excess in mid-plane

-150 -50 50 20

030

040

050

060

070

080

090

090

011

0012

0013

0014

000

100

200

300

400

500

600

700

800

leftrightaverage

Coil length [mm]

Inte

rfer

ence

[microm

]

Click here to add footer 15

Collaring steps

2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 320

50100150200250300350400

Distance to collaring position right lead endright return endleft lead endleft return end

F [MN]

offs

et k

ey g

roov

e [micro

m]

With 8MN the stoppers of the collaring tool were in contact

Click here to add footer 16

Shimming planbull Mid-plane is 650 microm beyond expectations To compensate

bull One layer of Kapton was removed on the mid-plane

bull Changed one layer of insulation to 005 microm thickness (in lieu of 0125 microm)

Click here to add footer 17

Yoking welding of the shellsF Lackner

1 2 3 4 5 6 7 80

100200300400500600700800

0

110

206

361426

526610

686Pressure rising April 28th 2014

Pressure rising step

Tota

l cha

rge

in to

ns

3154906157901240166520652225

002040608

SIDE B 0110206361426526610686

Length in [mm]

Yoke

gap

[mm

]

Tota

l loa

d in

tons

Max charge 500 tm on central section to close the welding gap

0

02

04

06

SIDE A0110206361426526610686

Length in [mm]

Yoke

gap

[mm

]

Tota

l loa

d in

tons

Click here to add footer 18

Structural analysis vs measurements

Click here to add footer 19

FEA Results 11T Mirror

FEA Max Cap gauge

pressure (MPa)

FEA Avg Cap gauge

pressure (MPa)

FEA Min Cap gauge

pressure (MPa)

Collar nose

stress (MPa)

Coil Min stress (MPa)

Coil Max Stress (MPa)

Avg Shell Stress (MPa)

Collaring Load 48 33 18 88 -7 -90

Post-Collaring 39 28 16 72 -7 -69

Collar in yoke 40 28 17 73 -9 -66

Max Press force 46 31 15 81 -14 -60 10

Shell Weld + Press Force 50 33 14 87 -16 -61 187

Shell Welded no Press Force 48 32 15 85 -15 -60 194

Collaring Load Post-Collaring Collar in yoke Max Press force Shell Weld + Press Force

Shell Welded no Press Force

Shell Welded - 297K

Cool Down (18K)

11-Tesla0

10

20

30

40

50

60Mirror Coil - contact pressure at pole (Cap Gauge)

FEA Max Cap gauge - pressure (MPa)

FEA Avg Cap gauge - pressure (MPa)

FEA Min Cap gauge - pressure (MPa)

Measured Coil Data (10 error bars)

Pres

sure

(MPa

)

Click here to add footer 20

ANSYS Forecast at 11-Tesla

Assembly Step

Max Capacitive gauge -

pressure (MPa)

Avg Capacitive gauge -

pressure (MPa)

Min Capacitive gauge -

pressure (MPa)

Collar-nose stress (MPa)

Coil Min stress (MPa)

Coil Max Stress (MPa)

Avg Shell Stress (MPa)

MirrorCoil

Shell Welded - 297K 48 32 15 85 -15 -60 195

Cool Down (18K) 37 21 5 62 -5 -74 375

11-Tesla 1 05 0 63 +13 -117 377

NominalCoil

Shell Welded - 297K 107 58 8 150 -14 -119 191

Cool Down (18K) 86 43 1 123 -21 -125 373

11-Tesla 22 11 0 57 -4 -120 374

Collar Nose Von-Mises Stress

At 11T

Coil BlocksAzimuthal Stress

At 11T

FEA predicted results

Click here to add footer 21

Bullet gauges loadingM GuinchardP Grosclaude

8 to 9 kN per bullet

Click here to add footer 22

Electrical tests ndash WhenF-O PincotL Grand Cleacutement

Are performed beforeafter each important construction step Test of pole Nb3Sn before curing - PBC Test of pole Nb3Sn before reaction ndash PBR Test of pole Nb3Sn after reaction ndash PAR Test of pole Nb3Sn after impregnation out of the mould ndash PAI Test of pole Nb3Sn after impregnation with instrumentation ndash PAIWI Test of collared coil before collaring ndash BC Test of collared coil after collaring ndash AC Test of the magnet under load before welding ndash UL Test of the magnet after shell welding ndash AW Test of the magnet after longitudinal coil loading ndash AL Test of the magnet after interconnection ndash AI Final Test of the magnet before delivery - FINAL

Click here to add footer 23

Electrical tests ndash WhatF-O PincotL Grand CleacutementAccording to the construction step we define

specific test valueselectrical tests among which

Resistance measurement(Coils Quench heaters Voltage taps Instrumentation) Inductance measurement Capacitance measurement Dielectric measurement(between coils QH instrumentation ground)

bull Insulation (up to 1kV 30s)bull current leakage (up to 1kV 5min)

Discharge test on coilUp to 1kV

Discharge test on quench heatersUp to 900V or 80AQH

Click here to add footer 24

Electrical testsF-O PincotL Grand Cleacutement

Resistance Insulation dielectric Inductance Capacitance Coil discharge QH discharge

Test phase

code

PBC X X X

PBR X X X

PAR X X X

PAI X X X X

PAIWI X X X X

BC X X X X X X

AC X X X X X X

UL X X

AW X X X X X X

AL X X X X X X

AI X X X X X X

FINAL X X X X X X

Click here to add footer 25

Click here to add footer 26

Plan for power tests coldbull RRR and strain gauge measurementsbull Preliminary tests ndash Setup protection ndash Splice resistance

measurements (current plateaus at 2 4 6 8 and 10 kA) ndash 3 hoursbull Training 43 K ndash 15 quenches ndash 3 days bull Training 19 K ndash 10 quenches ndash 25 days

Stability on current plateau ndash 05 daybull Ramp-rate study 100 As and 50 As ndash 05 day

AC-loss measurements (includes inductance measurement) at 5 to 100 As ndash 05 day

bull Quench heater efficiency study 3 different settings of QH pulse for 3 currents each Long re-cooling of the magnet due to delay of energy extraction ndash 3 days

bull High MIIts tests (protection delay) 6 quenches ndash 3 days

bull Quench propagation velocity measurements acquired for the training quenches

G Willeringbull Cool down bull Day 1

bull Day 2-4bull Day 5-7

bull Day 8

bull Day 9-11

bull Day 12-14

Click here to add footer 27

Further actionsbull After cold tests warm magnetic

measurements will be carried out with the two coils connected

bull Model 1 MBHSP101 single aperture with cable OST RRP 108127 for both polesbull Instrumentation of coils 106 and 107 going onbull Collaring scheduled around middle of June

  • CERN-FNAL Video Meeting 12 Progress of the 11T Dipole short m
  • Contributions
  • Main design features
  • Specific features
  • Assembly conditions - Winding
  • Binder curing
  • Reaction treatment
  • Reaction treatment ndash Coil 105
  • Impregnation
  • Instrumentation outer layer
  • Instrumentation inner layer
  • Quench heaters
  • Coils size
  • Excess in mid-plane
  • Collaring steps
  • Shimming plan
  • Yoking welding of the shells
  • Structural analysis vs measurements
  • FEA Results
  • ANSYS Forecast at 11-Tesla
  • Bullet gauges loading
  • Electrical tests ndash When
  • Electrical tests ndash What
  • Electrical tests
  • Slide 25
  • Plan for power tests cold
  • Further actions
Page 10: CERN MBHSM0101 general  status F. Savary on behalf of the 11T Dipole Project Team

Click here to add footer 10

Instrumentation outer layer

Outer layer instrumentation incorporated in a Trace which is applied after impregnationThere are 2 ldquoUrdquo shaped SS quench heaters with Cu overlay with Cu masked off to provide heating regions Heater width is 19mm in low-field region with heater regions 90mm apart In the high-field region the heater width is 24mm and the heater regions are 130mm apartThere are 13 voltage taps on the Trace including 6 on the pole turn 1 on the layer jump and 4 on the mid-plane turn

EES5O

I

EE5O12-

+

EES5OO

EE5O11EE5O10

EE5O9

EE5O8 EE5O6EE5O7 EE5O5

EE5O4EE5O3EE5O2

EE5O1

Click here to add footer 11

Instrumentation inner layer

Inner layer instrumentation consists only of voltage taps There are 16 voltage taps including 6 on the pole turn 1 on the layer jump and 4 on the mid-plane turn with other taps adjacent to spacer block edges

S Izquierdo BermudezF-O PincotR Bateman

Click here to add footer 12

Quench heaters

50 70 90 110 130 150 170 19000

200400600800

100012001400160018002000

Low Field Region High Field Region

Heater Current (A)

Pow

er d

ensi

ty (W

cm

2)

Operation area

bull Width -gt Cover as many turns as possible

bull LF 19 mm bull HF 24 mm

bull Power densitybull LF asymp 75 Wcm2

bull HFasymp 55 Wcm2

Even if the operational current is expected to be in the range 100-120 A it would be good to have the possibility to go up to 150 A during short model tests to check the saturation of the system in terms of heater delays

119875119889=1198682119877119908119871

119877=120588 119871119908119905

119875119889=1198682 1205881199082119905

Heater width19 mm LF 24 mm HFρss=7310-7Ωm RRR=134

bull Distance between heater stations -gt quench propagation in between stations asymp 5 msbull LF 90 mmbull HF 130 mm

bull Coverage maximum coverage keeping the resistance within the allowable limits for a 55 m magnet (depends on the number of power suppliesheater circuits)

Cu

50 90130

192

4

Cu

Click here to add footer 13

Coils size

bull Both coils 101 and 105 were oversized only in the mid-plane

bull Best-fit on the outer diameter and the loading plates (interface with pole)

Click here to add footer 14

Excess in mid-plane

-150 -50 50 20

030

040

050

060

070

080

090

090

011

0012

0013

0014

000

100

200

300

400

500

600

700

800

leftrightaverage

Coil length [mm]

Inte

rfer

ence

[microm

]

Click here to add footer 15

Collaring steps

2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 320

50100150200250300350400

Distance to collaring position right lead endright return endleft lead endleft return end

F [MN]

offs

et k

ey g

roov

e [micro

m]

With 8MN the stoppers of the collaring tool were in contact

Click here to add footer 16

Shimming planbull Mid-plane is 650 microm beyond expectations To compensate

bull One layer of Kapton was removed on the mid-plane

bull Changed one layer of insulation to 005 microm thickness (in lieu of 0125 microm)

Click here to add footer 17

Yoking welding of the shellsF Lackner

1 2 3 4 5 6 7 80

100200300400500600700800

0

110

206

361426

526610

686Pressure rising April 28th 2014

Pressure rising step

Tota

l cha

rge

in to

ns

3154906157901240166520652225

002040608

SIDE B 0110206361426526610686

Length in [mm]

Yoke

gap

[mm

]

Tota

l loa

d in

tons

Max charge 500 tm on central section to close the welding gap

0

02

04

06

SIDE A0110206361426526610686

Length in [mm]

Yoke

gap

[mm

]

Tota

l loa

d in

tons

Click here to add footer 18

Structural analysis vs measurements

Click here to add footer 19

FEA Results 11T Mirror

FEA Max Cap gauge

pressure (MPa)

FEA Avg Cap gauge

pressure (MPa)

FEA Min Cap gauge

pressure (MPa)

Collar nose

stress (MPa)

Coil Min stress (MPa)

Coil Max Stress (MPa)

Avg Shell Stress (MPa)

Collaring Load 48 33 18 88 -7 -90

Post-Collaring 39 28 16 72 -7 -69

Collar in yoke 40 28 17 73 -9 -66

Max Press force 46 31 15 81 -14 -60 10

Shell Weld + Press Force 50 33 14 87 -16 -61 187

Shell Welded no Press Force 48 32 15 85 -15 -60 194

Collaring Load Post-Collaring Collar in yoke Max Press force Shell Weld + Press Force

Shell Welded no Press Force

Shell Welded - 297K

Cool Down (18K)

11-Tesla0

10

20

30

40

50

60Mirror Coil - contact pressure at pole (Cap Gauge)

FEA Max Cap gauge - pressure (MPa)

FEA Avg Cap gauge - pressure (MPa)

FEA Min Cap gauge - pressure (MPa)

Measured Coil Data (10 error bars)

Pres

sure

(MPa

)

Click here to add footer 20

ANSYS Forecast at 11-Tesla

Assembly Step

Max Capacitive gauge -

pressure (MPa)

Avg Capacitive gauge -

pressure (MPa)

Min Capacitive gauge -

pressure (MPa)

Collar-nose stress (MPa)

Coil Min stress (MPa)

Coil Max Stress (MPa)

Avg Shell Stress (MPa)

MirrorCoil

Shell Welded - 297K 48 32 15 85 -15 -60 195

Cool Down (18K) 37 21 5 62 -5 -74 375

11-Tesla 1 05 0 63 +13 -117 377

NominalCoil

Shell Welded - 297K 107 58 8 150 -14 -119 191

Cool Down (18K) 86 43 1 123 -21 -125 373

11-Tesla 22 11 0 57 -4 -120 374

Collar Nose Von-Mises Stress

At 11T

Coil BlocksAzimuthal Stress

At 11T

FEA predicted results

Click here to add footer 21

Bullet gauges loadingM GuinchardP Grosclaude

8 to 9 kN per bullet

Click here to add footer 22

Electrical tests ndash WhenF-O PincotL Grand Cleacutement

Are performed beforeafter each important construction step Test of pole Nb3Sn before curing - PBC Test of pole Nb3Sn before reaction ndash PBR Test of pole Nb3Sn after reaction ndash PAR Test of pole Nb3Sn after impregnation out of the mould ndash PAI Test of pole Nb3Sn after impregnation with instrumentation ndash PAIWI Test of collared coil before collaring ndash BC Test of collared coil after collaring ndash AC Test of the magnet under load before welding ndash UL Test of the magnet after shell welding ndash AW Test of the magnet after longitudinal coil loading ndash AL Test of the magnet after interconnection ndash AI Final Test of the magnet before delivery - FINAL

Click here to add footer 23

Electrical tests ndash WhatF-O PincotL Grand CleacutementAccording to the construction step we define

specific test valueselectrical tests among which

Resistance measurement(Coils Quench heaters Voltage taps Instrumentation) Inductance measurement Capacitance measurement Dielectric measurement(between coils QH instrumentation ground)

bull Insulation (up to 1kV 30s)bull current leakage (up to 1kV 5min)

Discharge test on coilUp to 1kV

Discharge test on quench heatersUp to 900V or 80AQH

Click here to add footer 24

Electrical testsF-O PincotL Grand Cleacutement

Resistance Insulation dielectric Inductance Capacitance Coil discharge QH discharge

Test phase

code

PBC X X X

PBR X X X

PAR X X X

PAI X X X X

PAIWI X X X X

BC X X X X X X

AC X X X X X X

UL X X

AW X X X X X X

AL X X X X X X

AI X X X X X X

FINAL X X X X X X

Click here to add footer 25

Click here to add footer 26

Plan for power tests coldbull RRR and strain gauge measurementsbull Preliminary tests ndash Setup protection ndash Splice resistance

measurements (current plateaus at 2 4 6 8 and 10 kA) ndash 3 hoursbull Training 43 K ndash 15 quenches ndash 3 days bull Training 19 K ndash 10 quenches ndash 25 days

Stability on current plateau ndash 05 daybull Ramp-rate study 100 As and 50 As ndash 05 day

AC-loss measurements (includes inductance measurement) at 5 to 100 As ndash 05 day

bull Quench heater efficiency study 3 different settings of QH pulse for 3 currents each Long re-cooling of the magnet due to delay of energy extraction ndash 3 days

bull High MIIts tests (protection delay) 6 quenches ndash 3 days

bull Quench propagation velocity measurements acquired for the training quenches

G Willeringbull Cool down bull Day 1

bull Day 2-4bull Day 5-7

bull Day 8

bull Day 9-11

bull Day 12-14

Click here to add footer 27

Further actionsbull After cold tests warm magnetic

measurements will be carried out with the two coils connected

bull Model 1 MBHSP101 single aperture with cable OST RRP 108127 for both polesbull Instrumentation of coils 106 and 107 going onbull Collaring scheduled around middle of June

  • CERN-FNAL Video Meeting 12 Progress of the 11T Dipole short m
  • Contributions
  • Main design features
  • Specific features
  • Assembly conditions - Winding
  • Binder curing
  • Reaction treatment
  • Reaction treatment ndash Coil 105
  • Impregnation
  • Instrumentation outer layer
  • Instrumentation inner layer
  • Quench heaters
  • Coils size
  • Excess in mid-plane
  • Collaring steps
  • Shimming plan
  • Yoking welding of the shells
  • Structural analysis vs measurements
  • FEA Results
  • ANSYS Forecast at 11-Tesla
  • Bullet gauges loading
  • Electrical tests ndash When
  • Electrical tests ndash What
  • Electrical tests
  • Slide 25
  • Plan for power tests cold
  • Further actions
Page 11: CERN MBHSM0101 general  status F. Savary on behalf of the 11T Dipole Project Team

Click here to add footer 11

Instrumentation inner layer

Inner layer instrumentation consists only of voltage taps There are 16 voltage taps including 6 on the pole turn 1 on the layer jump and 4 on the mid-plane turn with other taps adjacent to spacer block edges

S Izquierdo BermudezF-O PincotR Bateman

Click here to add footer 12

Quench heaters

50 70 90 110 130 150 170 19000

200400600800

100012001400160018002000

Low Field Region High Field Region

Heater Current (A)

Pow

er d

ensi

ty (W

cm

2)

Operation area

bull Width -gt Cover as many turns as possible

bull LF 19 mm bull HF 24 mm

bull Power densitybull LF asymp 75 Wcm2

bull HFasymp 55 Wcm2

Even if the operational current is expected to be in the range 100-120 A it would be good to have the possibility to go up to 150 A during short model tests to check the saturation of the system in terms of heater delays

119875119889=1198682119877119908119871

119877=120588 119871119908119905

119875119889=1198682 1205881199082119905

Heater width19 mm LF 24 mm HFρss=7310-7Ωm RRR=134

bull Distance between heater stations -gt quench propagation in between stations asymp 5 msbull LF 90 mmbull HF 130 mm

bull Coverage maximum coverage keeping the resistance within the allowable limits for a 55 m magnet (depends on the number of power suppliesheater circuits)

Cu

50 90130

192

4

Cu

Click here to add footer 13

Coils size

bull Both coils 101 and 105 were oversized only in the mid-plane

bull Best-fit on the outer diameter and the loading plates (interface with pole)

Click here to add footer 14

Excess in mid-plane

-150 -50 50 20

030

040

050

060

070

080

090

090

011

0012

0013

0014

000

100

200

300

400

500

600

700

800

leftrightaverage

Coil length [mm]

Inte

rfer

ence

[microm

]

Click here to add footer 15

Collaring steps

2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 320

50100150200250300350400

Distance to collaring position right lead endright return endleft lead endleft return end

F [MN]

offs

et k

ey g

roov

e [micro

m]

With 8MN the stoppers of the collaring tool were in contact

Click here to add footer 16

Shimming planbull Mid-plane is 650 microm beyond expectations To compensate

bull One layer of Kapton was removed on the mid-plane

bull Changed one layer of insulation to 005 microm thickness (in lieu of 0125 microm)

Click here to add footer 17

Yoking welding of the shellsF Lackner

1 2 3 4 5 6 7 80

100200300400500600700800

0

110

206

361426

526610

686Pressure rising April 28th 2014

Pressure rising step

Tota

l cha

rge

in to

ns

3154906157901240166520652225

002040608

SIDE B 0110206361426526610686

Length in [mm]

Yoke

gap

[mm

]

Tota

l loa

d in

tons

Max charge 500 tm on central section to close the welding gap

0

02

04

06

SIDE A0110206361426526610686

Length in [mm]

Yoke

gap

[mm

]

Tota

l loa

d in

tons

Click here to add footer 18

Structural analysis vs measurements

Click here to add footer 19

FEA Results 11T Mirror

FEA Max Cap gauge

pressure (MPa)

FEA Avg Cap gauge

pressure (MPa)

FEA Min Cap gauge

pressure (MPa)

Collar nose

stress (MPa)

Coil Min stress (MPa)

Coil Max Stress (MPa)

Avg Shell Stress (MPa)

Collaring Load 48 33 18 88 -7 -90

Post-Collaring 39 28 16 72 -7 -69

Collar in yoke 40 28 17 73 -9 -66

Max Press force 46 31 15 81 -14 -60 10

Shell Weld + Press Force 50 33 14 87 -16 -61 187

Shell Welded no Press Force 48 32 15 85 -15 -60 194

Collaring Load Post-Collaring Collar in yoke Max Press force Shell Weld + Press Force

Shell Welded no Press Force

Shell Welded - 297K

Cool Down (18K)

11-Tesla0

10

20

30

40

50

60Mirror Coil - contact pressure at pole (Cap Gauge)

FEA Max Cap gauge - pressure (MPa)

FEA Avg Cap gauge - pressure (MPa)

FEA Min Cap gauge - pressure (MPa)

Measured Coil Data (10 error bars)

Pres

sure

(MPa

)

Click here to add footer 20

ANSYS Forecast at 11-Tesla

Assembly Step

Max Capacitive gauge -

pressure (MPa)

Avg Capacitive gauge -

pressure (MPa)

Min Capacitive gauge -

pressure (MPa)

Collar-nose stress (MPa)

Coil Min stress (MPa)

Coil Max Stress (MPa)

Avg Shell Stress (MPa)

MirrorCoil

Shell Welded - 297K 48 32 15 85 -15 -60 195

Cool Down (18K) 37 21 5 62 -5 -74 375

11-Tesla 1 05 0 63 +13 -117 377

NominalCoil

Shell Welded - 297K 107 58 8 150 -14 -119 191

Cool Down (18K) 86 43 1 123 -21 -125 373

11-Tesla 22 11 0 57 -4 -120 374

Collar Nose Von-Mises Stress

At 11T

Coil BlocksAzimuthal Stress

At 11T

FEA predicted results

Click here to add footer 21

Bullet gauges loadingM GuinchardP Grosclaude

8 to 9 kN per bullet

Click here to add footer 22

Electrical tests ndash WhenF-O PincotL Grand Cleacutement

Are performed beforeafter each important construction step Test of pole Nb3Sn before curing - PBC Test of pole Nb3Sn before reaction ndash PBR Test of pole Nb3Sn after reaction ndash PAR Test of pole Nb3Sn after impregnation out of the mould ndash PAI Test of pole Nb3Sn after impregnation with instrumentation ndash PAIWI Test of collared coil before collaring ndash BC Test of collared coil after collaring ndash AC Test of the magnet under load before welding ndash UL Test of the magnet after shell welding ndash AW Test of the magnet after longitudinal coil loading ndash AL Test of the magnet after interconnection ndash AI Final Test of the magnet before delivery - FINAL

Click here to add footer 23

Electrical tests ndash WhatF-O PincotL Grand CleacutementAccording to the construction step we define

specific test valueselectrical tests among which

Resistance measurement(Coils Quench heaters Voltage taps Instrumentation) Inductance measurement Capacitance measurement Dielectric measurement(between coils QH instrumentation ground)

bull Insulation (up to 1kV 30s)bull current leakage (up to 1kV 5min)

Discharge test on coilUp to 1kV

Discharge test on quench heatersUp to 900V or 80AQH

Click here to add footer 24

Electrical testsF-O PincotL Grand Cleacutement

Resistance Insulation dielectric Inductance Capacitance Coil discharge QH discharge

Test phase

code

PBC X X X

PBR X X X

PAR X X X

PAI X X X X

PAIWI X X X X

BC X X X X X X

AC X X X X X X

UL X X

AW X X X X X X

AL X X X X X X

AI X X X X X X

FINAL X X X X X X

Click here to add footer 25

Click here to add footer 26

Plan for power tests coldbull RRR and strain gauge measurementsbull Preliminary tests ndash Setup protection ndash Splice resistance

measurements (current plateaus at 2 4 6 8 and 10 kA) ndash 3 hoursbull Training 43 K ndash 15 quenches ndash 3 days bull Training 19 K ndash 10 quenches ndash 25 days

Stability on current plateau ndash 05 daybull Ramp-rate study 100 As and 50 As ndash 05 day

AC-loss measurements (includes inductance measurement) at 5 to 100 As ndash 05 day

bull Quench heater efficiency study 3 different settings of QH pulse for 3 currents each Long re-cooling of the magnet due to delay of energy extraction ndash 3 days

bull High MIIts tests (protection delay) 6 quenches ndash 3 days

bull Quench propagation velocity measurements acquired for the training quenches

G Willeringbull Cool down bull Day 1

bull Day 2-4bull Day 5-7

bull Day 8

bull Day 9-11

bull Day 12-14

Click here to add footer 27

Further actionsbull After cold tests warm magnetic

measurements will be carried out with the two coils connected

bull Model 1 MBHSP101 single aperture with cable OST RRP 108127 for both polesbull Instrumentation of coils 106 and 107 going onbull Collaring scheduled around middle of June

  • CERN-FNAL Video Meeting 12 Progress of the 11T Dipole short m
  • Contributions
  • Main design features
  • Specific features
  • Assembly conditions - Winding
  • Binder curing
  • Reaction treatment
  • Reaction treatment ndash Coil 105
  • Impregnation
  • Instrumentation outer layer
  • Instrumentation inner layer
  • Quench heaters
  • Coils size
  • Excess in mid-plane
  • Collaring steps
  • Shimming plan
  • Yoking welding of the shells
  • Structural analysis vs measurements
  • FEA Results
  • ANSYS Forecast at 11-Tesla
  • Bullet gauges loading
  • Electrical tests ndash When
  • Electrical tests ndash What
  • Electrical tests
  • Slide 25
  • Plan for power tests cold
  • Further actions
Page 12: CERN MBHSM0101 general  status F. Savary on behalf of the 11T Dipole Project Team

Click here to add footer 12

Quench heaters

50 70 90 110 130 150 170 19000

200400600800

100012001400160018002000

Low Field Region High Field Region

Heater Current (A)

Pow

er d

ensi

ty (W

cm

2)

Operation area

bull Width -gt Cover as many turns as possible

bull LF 19 mm bull HF 24 mm

bull Power densitybull LF asymp 75 Wcm2

bull HFasymp 55 Wcm2

Even if the operational current is expected to be in the range 100-120 A it would be good to have the possibility to go up to 150 A during short model tests to check the saturation of the system in terms of heater delays

119875119889=1198682119877119908119871

119877=120588 119871119908119905

119875119889=1198682 1205881199082119905

Heater width19 mm LF 24 mm HFρss=7310-7Ωm RRR=134

bull Distance between heater stations -gt quench propagation in between stations asymp 5 msbull LF 90 mmbull HF 130 mm

bull Coverage maximum coverage keeping the resistance within the allowable limits for a 55 m magnet (depends on the number of power suppliesheater circuits)

Cu

50 90130

192

4

Cu

Click here to add footer 13

Coils size

bull Both coils 101 and 105 were oversized only in the mid-plane

bull Best-fit on the outer diameter and the loading plates (interface with pole)

Click here to add footer 14

Excess in mid-plane

-150 -50 50 20

030

040

050

060

070

080

090

090

011

0012

0013

0014

000

100

200

300

400

500

600

700

800

leftrightaverage

Coil length [mm]

Inte

rfer

ence

[microm

]

Click here to add footer 15

Collaring steps

2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 320

50100150200250300350400

Distance to collaring position right lead endright return endleft lead endleft return end

F [MN]

offs

et k

ey g

roov

e [micro

m]

With 8MN the stoppers of the collaring tool were in contact

Click here to add footer 16

Shimming planbull Mid-plane is 650 microm beyond expectations To compensate

bull One layer of Kapton was removed on the mid-plane

bull Changed one layer of insulation to 005 microm thickness (in lieu of 0125 microm)

Click here to add footer 17

Yoking welding of the shellsF Lackner

1 2 3 4 5 6 7 80

100200300400500600700800

0

110

206

361426

526610

686Pressure rising April 28th 2014

Pressure rising step

Tota

l cha

rge

in to

ns

3154906157901240166520652225

002040608

SIDE B 0110206361426526610686

Length in [mm]

Yoke

gap

[mm

]

Tota

l loa

d in

tons

Max charge 500 tm on central section to close the welding gap

0

02

04

06

SIDE A0110206361426526610686

Length in [mm]

Yoke

gap

[mm

]

Tota

l loa

d in

tons

Click here to add footer 18

Structural analysis vs measurements

Click here to add footer 19

FEA Results 11T Mirror

FEA Max Cap gauge

pressure (MPa)

FEA Avg Cap gauge

pressure (MPa)

FEA Min Cap gauge

pressure (MPa)

Collar nose

stress (MPa)

Coil Min stress (MPa)

Coil Max Stress (MPa)

Avg Shell Stress (MPa)

Collaring Load 48 33 18 88 -7 -90

Post-Collaring 39 28 16 72 -7 -69

Collar in yoke 40 28 17 73 -9 -66

Max Press force 46 31 15 81 -14 -60 10

Shell Weld + Press Force 50 33 14 87 -16 -61 187

Shell Welded no Press Force 48 32 15 85 -15 -60 194

Collaring Load Post-Collaring Collar in yoke Max Press force Shell Weld + Press Force

Shell Welded no Press Force

Shell Welded - 297K

Cool Down (18K)

11-Tesla0

10

20

30

40

50

60Mirror Coil - contact pressure at pole (Cap Gauge)

FEA Max Cap gauge - pressure (MPa)

FEA Avg Cap gauge - pressure (MPa)

FEA Min Cap gauge - pressure (MPa)

Measured Coil Data (10 error bars)

Pres

sure

(MPa

)

Click here to add footer 20

ANSYS Forecast at 11-Tesla

Assembly Step

Max Capacitive gauge -

pressure (MPa)

Avg Capacitive gauge -

pressure (MPa)

Min Capacitive gauge -

pressure (MPa)

Collar-nose stress (MPa)

Coil Min stress (MPa)

Coil Max Stress (MPa)

Avg Shell Stress (MPa)

MirrorCoil

Shell Welded - 297K 48 32 15 85 -15 -60 195

Cool Down (18K) 37 21 5 62 -5 -74 375

11-Tesla 1 05 0 63 +13 -117 377

NominalCoil

Shell Welded - 297K 107 58 8 150 -14 -119 191

Cool Down (18K) 86 43 1 123 -21 -125 373

11-Tesla 22 11 0 57 -4 -120 374

Collar Nose Von-Mises Stress

At 11T

Coil BlocksAzimuthal Stress

At 11T

FEA predicted results

Click here to add footer 21

Bullet gauges loadingM GuinchardP Grosclaude

8 to 9 kN per bullet

Click here to add footer 22

Electrical tests ndash WhenF-O PincotL Grand Cleacutement

Are performed beforeafter each important construction step Test of pole Nb3Sn before curing - PBC Test of pole Nb3Sn before reaction ndash PBR Test of pole Nb3Sn after reaction ndash PAR Test of pole Nb3Sn after impregnation out of the mould ndash PAI Test of pole Nb3Sn after impregnation with instrumentation ndash PAIWI Test of collared coil before collaring ndash BC Test of collared coil after collaring ndash AC Test of the magnet under load before welding ndash UL Test of the magnet after shell welding ndash AW Test of the magnet after longitudinal coil loading ndash AL Test of the magnet after interconnection ndash AI Final Test of the magnet before delivery - FINAL

Click here to add footer 23

Electrical tests ndash WhatF-O PincotL Grand CleacutementAccording to the construction step we define

specific test valueselectrical tests among which

Resistance measurement(Coils Quench heaters Voltage taps Instrumentation) Inductance measurement Capacitance measurement Dielectric measurement(between coils QH instrumentation ground)

bull Insulation (up to 1kV 30s)bull current leakage (up to 1kV 5min)

Discharge test on coilUp to 1kV

Discharge test on quench heatersUp to 900V or 80AQH

Click here to add footer 24

Electrical testsF-O PincotL Grand Cleacutement

Resistance Insulation dielectric Inductance Capacitance Coil discharge QH discharge

Test phase

code

PBC X X X

PBR X X X

PAR X X X

PAI X X X X

PAIWI X X X X

BC X X X X X X

AC X X X X X X

UL X X

AW X X X X X X

AL X X X X X X

AI X X X X X X

FINAL X X X X X X

Click here to add footer 25

Click here to add footer 26

Plan for power tests coldbull RRR and strain gauge measurementsbull Preliminary tests ndash Setup protection ndash Splice resistance

measurements (current plateaus at 2 4 6 8 and 10 kA) ndash 3 hoursbull Training 43 K ndash 15 quenches ndash 3 days bull Training 19 K ndash 10 quenches ndash 25 days

Stability on current plateau ndash 05 daybull Ramp-rate study 100 As and 50 As ndash 05 day

AC-loss measurements (includes inductance measurement) at 5 to 100 As ndash 05 day

bull Quench heater efficiency study 3 different settings of QH pulse for 3 currents each Long re-cooling of the magnet due to delay of energy extraction ndash 3 days

bull High MIIts tests (protection delay) 6 quenches ndash 3 days

bull Quench propagation velocity measurements acquired for the training quenches

G Willeringbull Cool down bull Day 1

bull Day 2-4bull Day 5-7

bull Day 8

bull Day 9-11

bull Day 12-14

Click here to add footer 27

Further actionsbull After cold tests warm magnetic

measurements will be carried out with the two coils connected

bull Model 1 MBHSP101 single aperture with cable OST RRP 108127 for both polesbull Instrumentation of coils 106 and 107 going onbull Collaring scheduled around middle of June

  • CERN-FNAL Video Meeting 12 Progress of the 11T Dipole short m
  • Contributions
  • Main design features
  • Specific features
  • Assembly conditions - Winding
  • Binder curing
  • Reaction treatment
  • Reaction treatment ndash Coil 105
  • Impregnation
  • Instrumentation outer layer
  • Instrumentation inner layer
  • Quench heaters
  • Coils size
  • Excess in mid-plane
  • Collaring steps
  • Shimming plan
  • Yoking welding of the shells
  • Structural analysis vs measurements
  • FEA Results
  • ANSYS Forecast at 11-Tesla
  • Bullet gauges loading
  • Electrical tests ndash When
  • Electrical tests ndash What
  • Electrical tests
  • Slide 25
  • Plan for power tests cold
  • Further actions
Page 13: CERN MBHSM0101 general  status F. Savary on behalf of the 11T Dipole Project Team

Click here to add footer 13

Coils size

bull Both coils 101 and 105 were oversized only in the mid-plane

bull Best-fit on the outer diameter and the loading plates (interface with pole)

Click here to add footer 14

Excess in mid-plane

-150 -50 50 20

030

040

050

060

070

080

090

090

011

0012

0013

0014

000

100

200

300

400

500

600

700

800

leftrightaverage

Coil length [mm]

Inte

rfer

ence

[microm

]

Click here to add footer 15

Collaring steps

2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 320

50100150200250300350400

Distance to collaring position right lead endright return endleft lead endleft return end

F [MN]

offs

et k

ey g

roov

e [micro

m]

With 8MN the stoppers of the collaring tool were in contact

Click here to add footer 16

Shimming planbull Mid-plane is 650 microm beyond expectations To compensate

bull One layer of Kapton was removed on the mid-plane

bull Changed one layer of insulation to 005 microm thickness (in lieu of 0125 microm)

Click here to add footer 17

Yoking welding of the shellsF Lackner

1 2 3 4 5 6 7 80

100200300400500600700800

0

110

206

361426

526610

686Pressure rising April 28th 2014

Pressure rising step

Tota

l cha

rge

in to

ns

3154906157901240166520652225

002040608

SIDE B 0110206361426526610686

Length in [mm]

Yoke

gap

[mm

]

Tota

l loa

d in

tons

Max charge 500 tm on central section to close the welding gap

0

02

04

06

SIDE A0110206361426526610686

Length in [mm]

Yoke

gap

[mm

]

Tota

l loa

d in

tons

Click here to add footer 18

Structural analysis vs measurements

Click here to add footer 19

FEA Results 11T Mirror

FEA Max Cap gauge

pressure (MPa)

FEA Avg Cap gauge

pressure (MPa)

FEA Min Cap gauge

pressure (MPa)

Collar nose

stress (MPa)

Coil Min stress (MPa)

Coil Max Stress (MPa)

Avg Shell Stress (MPa)

Collaring Load 48 33 18 88 -7 -90

Post-Collaring 39 28 16 72 -7 -69

Collar in yoke 40 28 17 73 -9 -66

Max Press force 46 31 15 81 -14 -60 10

Shell Weld + Press Force 50 33 14 87 -16 -61 187

Shell Welded no Press Force 48 32 15 85 -15 -60 194

Collaring Load Post-Collaring Collar in yoke Max Press force Shell Weld + Press Force

Shell Welded no Press Force

Shell Welded - 297K

Cool Down (18K)

11-Tesla0

10

20

30

40

50

60Mirror Coil - contact pressure at pole (Cap Gauge)

FEA Max Cap gauge - pressure (MPa)

FEA Avg Cap gauge - pressure (MPa)

FEA Min Cap gauge - pressure (MPa)

Measured Coil Data (10 error bars)

Pres

sure

(MPa

)

Click here to add footer 20

ANSYS Forecast at 11-Tesla

Assembly Step

Max Capacitive gauge -

pressure (MPa)

Avg Capacitive gauge -

pressure (MPa)

Min Capacitive gauge -

pressure (MPa)

Collar-nose stress (MPa)

Coil Min stress (MPa)

Coil Max Stress (MPa)

Avg Shell Stress (MPa)

MirrorCoil

Shell Welded - 297K 48 32 15 85 -15 -60 195

Cool Down (18K) 37 21 5 62 -5 -74 375

11-Tesla 1 05 0 63 +13 -117 377

NominalCoil

Shell Welded - 297K 107 58 8 150 -14 -119 191

Cool Down (18K) 86 43 1 123 -21 -125 373

11-Tesla 22 11 0 57 -4 -120 374

Collar Nose Von-Mises Stress

At 11T

Coil BlocksAzimuthal Stress

At 11T

FEA predicted results

Click here to add footer 21

Bullet gauges loadingM GuinchardP Grosclaude

8 to 9 kN per bullet

Click here to add footer 22

Electrical tests ndash WhenF-O PincotL Grand Cleacutement

Are performed beforeafter each important construction step Test of pole Nb3Sn before curing - PBC Test of pole Nb3Sn before reaction ndash PBR Test of pole Nb3Sn after reaction ndash PAR Test of pole Nb3Sn after impregnation out of the mould ndash PAI Test of pole Nb3Sn after impregnation with instrumentation ndash PAIWI Test of collared coil before collaring ndash BC Test of collared coil after collaring ndash AC Test of the magnet under load before welding ndash UL Test of the magnet after shell welding ndash AW Test of the magnet after longitudinal coil loading ndash AL Test of the magnet after interconnection ndash AI Final Test of the magnet before delivery - FINAL

Click here to add footer 23

Electrical tests ndash WhatF-O PincotL Grand CleacutementAccording to the construction step we define

specific test valueselectrical tests among which

Resistance measurement(Coils Quench heaters Voltage taps Instrumentation) Inductance measurement Capacitance measurement Dielectric measurement(between coils QH instrumentation ground)

bull Insulation (up to 1kV 30s)bull current leakage (up to 1kV 5min)

Discharge test on coilUp to 1kV

Discharge test on quench heatersUp to 900V or 80AQH

Click here to add footer 24

Electrical testsF-O PincotL Grand Cleacutement

Resistance Insulation dielectric Inductance Capacitance Coil discharge QH discharge

Test phase

code

PBC X X X

PBR X X X

PAR X X X

PAI X X X X

PAIWI X X X X

BC X X X X X X

AC X X X X X X

UL X X

AW X X X X X X

AL X X X X X X

AI X X X X X X

FINAL X X X X X X

Click here to add footer 25

Click here to add footer 26

Plan for power tests coldbull RRR and strain gauge measurementsbull Preliminary tests ndash Setup protection ndash Splice resistance

measurements (current plateaus at 2 4 6 8 and 10 kA) ndash 3 hoursbull Training 43 K ndash 15 quenches ndash 3 days bull Training 19 K ndash 10 quenches ndash 25 days

Stability on current plateau ndash 05 daybull Ramp-rate study 100 As and 50 As ndash 05 day

AC-loss measurements (includes inductance measurement) at 5 to 100 As ndash 05 day

bull Quench heater efficiency study 3 different settings of QH pulse for 3 currents each Long re-cooling of the magnet due to delay of energy extraction ndash 3 days

bull High MIIts tests (protection delay) 6 quenches ndash 3 days

bull Quench propagation velocity measurements acquired for the training quenches

G Willeringbull Cool down bull Day 1

bull Day 2-4bull Day 5-7

bull Day 8

bull Day 9-11

bull Day 12-14

Click here to add footer 27

Further actionsbull After cold tests warm magnetic

measurements will be carried out with the two coils connected

bull Model 1 MBHSP101 single aperture with cable OST RRP 108127 for both polesbull Instrumentation of coils 106 and 107 going onbull Collaring scheduled around middle of June

  • CERN-FNAL Video Meeting 12 Progress of the 11T Dipole short m
  • Contributions
  • Main design features
  • Specific features
  • Assembly conditions - Winding
  • Binder curing
  • Reaction treatment
  • Reaction treatment ndash Coil 105
  • Impregnation
  • Instrumentation outer layer
  • Instrumentation inner layer
  • Quench heaters
  • Coils size
  • Excess in mid-plane
  • Collaring steps
  • Shimming plan
  • Yoking welding of the shells
  • Structural analysis vs measurements
  • FEA Results
  • ANSYS Forecast at 11-Tesla
  • Bullet gauges loading
  • Electrical tests ndash When
  • Electrical tests ndash What
  • Electrical tests
  • Slide 25
  • Plan for power tests cold
  • Further actions
Page 14: CERN MBHSM0101 general  status F. Savary on behalf of the 11T Dipole Project Team

Click here to add footer 14

Excess in mid-plane

-150 -50 50 20

030

040

050

060

070

080

090

090

011

0012

0013

0014

000

100

200

300

400

500

600

700

800

leftrightaverage

Coil length [mm]

Inte

rfer

ence

[microm

]

Click here to add footer 15

Collaring steps

2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 320

50100150200250300350400

Distance to collaring position right lead endright return endleft lead endleft return end

F [MN]

offs

et k

ey g

roov

e [micro

m]

With 8MN the stoppers of the collaring tool were in contact

Click here to add footer 16

Shimming planbull Mid-plane is 650 microm beyond expectations To compensate

bull One layer of Kapton was removed on the mid-plane

bull Changed one layer of insulation to 005 microm thickness (in lieu of 0125 microm)

Click here to add footer 17

Yoking welding of the shellsF Lackner

1 2 3 4 5 6 7 80

100200300400500600700800

0

110

206

361426

526610

686Pressure rising April 28th 2014

Pressure rising step

Tota

l cha

rge

in to

ns

3154906157901240166520652225

002040608

SIDE B 0110206361426526610686

Length in [mm]

Yoke

gap

[mm

]

Tota

l loa

d in

tons

Max charge 500 tm on central section to close the welding gap

0

02

04

06

SIDE A0110206361426526610686

Length in [mm]

Yoke

gap

[mm

]

Tota

l loa

d in

tons

Click here to add footer 18

Structural analysis vs measurements

Click here to add footer 19

FEA Results 11T Mirror

FEA Max Cap gauge

pressure (MPa)

FEA Avg Cap gauge

pressure (MPa)

FEA Min Cap gauge

pressure (MPa)

Collar nose

stress (MPa)

Coil Min stress (MPa)

Coil Max Stress (MPa)

Avg Shell Stress (MPa)

Collaring Load 48 33 18 88 -7 -90

Post-Collaring 39 28 16 72 -7 -69

Collar in yoke 40 28 17 73 -9 -66

Max Press force 46 31 15 81 -14 -60 10

Shell Weld + Press Force 50 33 14 87 -16 -61 187

Shell Welded no Press Force 48 32 15 85 -15 -60 194

Collaring Load Post-Collaring Collar in yoke Max Press force Shell Weld + Press Force

Shell Welded no Press Force

Shell Welded - 297K

Cool Down (18K)

11-Tesla0

10

20

30

40

50

60Mirror Coil - contact pressure at pole (Cap Gauge)

FEA Max Cap gauge - pressure (MPa)

FEA Avg Cap gauge - pressure (MPa)

FEA Min Cap gauge - pressure (MPa)

Measured Coil Data (10 error bars)

Pres

sure

(MPa

)

Click here to add footer 20

ANSYS Forecast at 11-Tesla

Assembly Step

Max Capacitive gauge -

pressure (MPa)

Avg Capacitive gauge -

pressure (MPa)

Min Capacitive gauge -

pressure (MPa)

Collar-nose stress (MPa)

Coil Min stress (MPa)

Coil Max Stress (MPa)

Avg Shell Stress (MPa)

MirrorCoil

Shell Welded - 297K 48 32 15 85 -15 -60 195

Cool Down (18K) 37 21 5 62 -5 -74 375

11-Tesla 1 05 0 63 +13 -117 377

NominalCoil

Shell Welded - 297K 107 58 8 150 -14 -119 191

Cool Down (18K) 86 43 1 123 -21 -125 373

11-Tesla 22 11 0 57 -4 -120 374

Collar Nose Von-Mises Stress

At 11T

Coil BlocksAzimuthal Stress

At 11T

FEA predicted results

Click here to add footer 21

Bullet gauges loadingM GuinchardP Grosclaude

8 to 9 kN per bullet

Click here to add footer 22

Electrical tests ndash WhenF-O PincotL Grand Cleacutement

Are performed beforeafter each important construction step Test of pole Nb3Sn before curing - PBC Test of pole Nb3Sn before reaction ndash PBR Test of pole Nb3Sn after reaction ndash PAR Test of pole Nb3Sn after impregnation out of the mould ndash PAI Test of pole Nb3Sn after impregnation with instrumentation ndash PAIWI Test of collared coil before collaring ndash BC Test of collared coil after collaring ndash AC Test of the magnet under load before welding ndash UL Test of the magnet after shell welding ndash AW Test of the magnet after longitudinal coil loading ndash AL Test of the magnet after interconnection ndash AI Final Test of the magnet before delivery - FINAL

Click here to add footer 23

Electrical tests ndash WhatF-O PincotL Grand CleacutementAccording to the construction step we define

specific test valueselectrical tests among which

Resistance measurement(Coils Quench heaters Voltage taps Instrumentation) Inductance measurement Capacitance measurement Dielectric measurement(between coils QH instrumentation ground)

bull Insulation (up to 1kV 30s)bull current leakage (up to 1kV 5min)

Discharge test on coilUp to 1kV

Discharge test on quench heatersUp to 900V or 80AQH

Click here to add footer 24

Electrical testsF-O PincotL Grand Cleacutement

Resistance Insulation dielectric Inductance Capacitance Coil discharge QH discharge

Test phase

code

PBC X X X

PBR X X X

PAR X X X

PAI X X X X

PAIWI X X X X

BC X X X X X X

AC X X X X X X

UL X X

AW X X X X X X

AL X X X X X X

AI X X X X X X

FINAL X X X X X X

Click here to add footer 25

Click here to add footer 26

Plan for power tests coldbull RRR and strain gauge measurementsbull Preliminary tests ndash Setup protection ndash Splice resistance

measurements (current plateaus at 2 4 6 8 and 10 kA) ndash 3 hoursbull Training 43 K ndash 15 quenches ndash 3 days bull Training 19 K ndash 10 quenches ndash 25 days

Stability on current plateau ndash 05 daybull Ramp-rate study 100 As and 50 As ndash 05 day

AC-loss measurements (includes inductance measurement) at 5 to 100 As ndash 05 day

bull Quench heater efficiency study 3 different settings of QH pulse for 3 currents each Long re-cooling of the magnet due to delay of energy extraction ndash 3 days

bull High MIIts tests (protection delay) 6 quenches ndash 3 days

bull Quench propagation velocity measurements acquired for the training quenches

G Willeringbull Cool down bull Day 1

bull Day 2-4bull Day 5-7

bull Day 8

bull Day 9-11

bull Day 12-14

Click here to add footer 27

Further actionsbull After cold tests warm magnetic

measurements will be carried out with the two coils connected

bull Model 1 MBHSP101 single aperture with cable OST RRP 108127 for both polesbull Instrumentation of coils 106 and 107 going onbull Collaring scheduled around middle of June

  • CERN-FNAL Video Meeting 12 Progress of the 11T Dipole short m
  • Contributions
  • Main design features
  • Specific features
  • Assembly conditions - Winding
  • Binder curing
  • Reaction treatment
  • Reaction treatment ndash Coil 105
  • Impregnation
  • Instrumentation outer layer
  • Instrumentation inner layer
  • Quench heaters
  • Coils size
  • Excess in mid-plane
  • Collaring steps
  • Shimming plan
  • Yoking welding of the shells
  • Structural analysis vs measurements
  • FEA Results
  • ANSYS Forecast at 11-Tesla
  • Bullet gauges loading
  • Electrical tests ndash When
  • Electrical tests ndash What
  • Electrical tests
  • Slide 25
  • Plan for power tests cold
  • Further actions
Page 15: CERN MBHSM0101 general  status F. Savary on behalf of the 11T Dipole Project Team

Click here to add footer 15

Collaring steps

2 4 6 8 10 12 14 16 18 20 22 24 26 28 30 320

50100150200250300350400

Distance to collaring position right lead endright return endleft lead endleft return end

F [MN]

offs

et k

ey g

roov

e [micro

m]

With 8MN the stoppers of the collaring tool were in contact

Click here to add footer 16

Shimming planbull Mid-plane is 650 microm beyond expectations To compensate

bull One layer of Kapton was removed on the mid-plane

bull Changed one layer of insulation to 005 microm thickness (in lieu of 0125 microm)

Click here to add footer 17

Yoking welding of the shellsF Lackner

1 2 3 4 5 6 7 80

100200300400500600700800

0

110

206

361426

526610

686Pressure rising April 28th 2014

Pressure rising step

Tota

l cha

rge

in to

ns

3154906157901240166520652225

002040608

SIDE B 0110206361426526610686

Length in [mm]

Yoke

gap

[mm

]

Tota

l loa

d in

tons

Max charge 500 tm on central section to close the welding gap

0

02

04

06

SIDE A0110206361426526610686

Length in [mm]

Yoke

gap

[mm

]

Tota

l loa

d in

tons

Click here to add footer 18

Structural analysis vs measurements

Click here to add footer 19

FEA Results 11T Mirror

FEA Max Cap gauge

pressure (MPa)

FEA Avg Cap gauge

pressure (MPa)

FEA Min Cap gauge

pressure (MPa)

Collar nose

stress (MPa)

Coil Min stress (MPa)

Coil Max Stress (MPa)

Avg Shell Stress (MPa)

Collaring Load 48 33 18 88 -7 -90

Post-Collaring 39 28 16 72 -7 -69

Collar in yoke 40 28 17 73 -9 -66

Max Press force 46 31 15 81 -14 -60 10

Shell Weld + Press Force 50 33 14 87 -16 -61 187

Shell Welded no Press Force 48 32 15 85 -15 -60 194

Collaring Load Post-Collaring Collar in yoke Max Press force Shell Weld + Press Force

Shell Welded no Press Force

Shell Welded - 297K

Cool Down (18K)

11-Tesla0

10

20

30

40

50

60Mirror Coil - contact pressure at pole (Cap Gauge)

FEA Max Cap gauge - pressure (MPa)

FEA Avg Cap gauge - pressure (MPa)

FEA Min Cap gauge - pressure (MPa)

Measured Coil Data (10 error bars)

Pres

sure

(MPa

)

Click here to add footer 20

ANSYS Forecast at 11-Tesla

Assembly Step

Max Capacitive gauge -

pressure (MPa)

Avg Capacitive gauge -

pressure (MPa)

Min Capacitive gauge -

pressure (MPa)

Collar-nose stress (MPa)

Coil Min stress (MPa)

Coil Max Stress (MPa)

Avg Shell Stress (MPa)

MirrorCoil

Shell Welded - 297K 48 32 15 85 -15 -60 195

Cool Down (18K) 37 21 5 62 -5 -74 375

11-Tesla 1 05 0 63 +13 -117 377

NominalCoil

Shell Welded - 297K 107 58 8 150 -14 -119 191

Cool Down (18K) 86 43 1 123 -21 -125 373

11-Tesla 22 11 0 57 -4 -120 374

Collar Nose Von-Mises Stress

At 11T

Coil BlocksAzimuthal Stress

At 11T

FEA predicted results

Click here to add footer 21

Bullet gauges loadingM GuinchardP Grosclaude

8 to 9 kN per bullet

Click here to add footer 22

Electrical tests ndash WhenF-O PincotL Grand Cleacutement

Are performed beforeafter each important construction step Test of pole Nb3Sn before curing - PBC Test of pole Nb3Sn before reaction ndash PBR Test of pole Nb3Sn after reaction ndash PAR Test of pole Nb3Sn after impregnation out of the mould ndash PAI Test of pole Nb3Sn after impregnation with instrumentation ndash PAIWI Test of collared coil before collaring ndash BC Test of collared coil after collaring ndash AC Test of the magnet under load before welding ndash UL Test of the magnet after shell welding ndash AW Test of the magnet after longitudinal coil loading ndash AL Test of the magnet after interconnection ndash AI Final Test of the magnet before delivery - FINAL

Click here to add footer 23

Electrical tests ndash WhatF-O PincotL Grand CleacutementAccording to the construction step we define

specific test valueselectrical tests among which

Resistance measurement(Coils Quench heaters Voltage taps Instrumentation) Inductance measurement Capacitance measurement Dielectric measurement(between coils QH instrumentation ground)

bull Insulation (up to 1kV 30s)bull current leakage (up to 1kV 5min)

Discharge test on coilUp to 1kV

Discharge test on quench heatersUp to 900V or 80AQH

Click here to add footer 24

Electrical testsF-O PincotL Grand Cleacutement

Resistance Insulation dielectric Inductance Capacitance Coil discharge QH discharge

Test phase

code

PBC X X X

PBR X X X

PAR X X X

PAI X X X X

PAIWI X X X X

BC X X X X X X

AC X X X X X X

UL X X

AW X X X X X X

AL X X X X X X

AI X X X X X X

FINAL X X X X X X

Click here to add footer 25

Click here to add footer 26

Plan for power tests coldbull RRR and strain gauge measurementsbull Preliminary tests ndash Setup protection ndash Splice resistance

measurements (current plateaus at 2 4 6 8 and 10 kA) ndash 3 hoursbull Training 43 K ndash 15 quenches ndash 3 days bull Training 19 K ndash 10 quenches ndash 25 days

Stability on current plateau ndash 05 daybull Ramp-rate study 100 As and 50 As ndash 05 day

AC-loss measurements (includes inductance measurement) at 5 to 100 As ndash 05 day

bull Quench heater efficiency study 3 different settings of QH pulse for 3 currents each Long re-cooling of the magnet due to delay of energy extraction ndash 3 days

bull High MIIts tests (protection delay) 6 quenches ndash 3 days

bull Quench propagation velocity measurements acquired for the training quenches

G Willeringbull Cool down bull Day 1

bull Day 2-4bull Day 5-7

bull Day 8

bull Day 9-11

bull Day 12-14

Click here to add footer 27

Further actionsbull After cold tests warm magnetic

measurements will be carried out with the two coils connected

bull Model 1 MBHSP101 single aperture with cable OST RRP 108127 for both polesbull Instrumentation of coils 106 and 107 going onbull Collaring scheduled around middle of June

  • CERN-FNAL Video Meeting 12 Progress of the 11T Dipole short m
  • Contributions
  • Main design features
  • Specific features
  • Assembly conditions - Winding
  • Binder curing
  • Reaction treatment
  • Reaction treatment ndash Coil 105
  • Impregnation
  • Instrumentation outer layer
  • Instrumentation inner layer
  • Quench heaters
  • Coils size
  • Excess in mid-plane
  • Collaring steps
  • Shimming plan
  • Yoking welding of the shells
  • Structural analysis vs measurements
  • FEA Results
  • ANSYS Forecast at 11-Tesla
  • Bullet gauges loading
  • Electrical tests ndash When
  • Electrical tests ndash What
  • Electrical tests
  • Slide 25
  • Plan for power tests cold
  • Further actions
Page 16: CERN MBHSM0101 general  status F. Savary on behalf of the 11T Dipole Project Team

Click here to add footer 16

Shimming planbull Mid-plane is 650 microm beyond expectations To compensate

bull One layer of Kapton was removed on the mid-plane

bull Changed one layer of insulation to 005 microm thickness (in lieu of 0125 microm)

Click here to add footer 17

Yoking welding of the shellsF Lackner

1 2 3 4 5 6 7 80

100200300400500600700800

0

110

206

361426

526610

686Pressure rising April 28th 2014

Pressure rising step

Tota

l cha

rge

in to

ns

3154906157901240166520652225

002040608

SIDE B 0110206361426526610686

Length in [mm]

Yoke

gap

[mm

]

Tota

l loa

d in

tons

Max charge 500 tm on central section to close the welding gap

0

02

04

06

SIDE A0110206361426526610686

Length in [mm]

Yoke

gap

[mm

]

Tota

l loa

d in

tons

Click here to add footer 18

Structural analysis vs measurements

Click here to add footer 19

FEA Results 11T Mirror

FEA Max Cap gauge

pressure (MPa)

FEA Avg Cap gauge

pressure (MPa)

FEA Min Cap gauge

pressure (MPa)

Collar nose

stress (MPa)

Coil Min stress (MPa)

Coil Max Stress (MPa)

Avg Shell Stress (MPa)

Collaring Load 48 33 18 88 -7 -90

Post-Collaring 39 28 16 72 -7 -69

Collar in yoke 40 28 17 73 -9 -66

Max Press force 46 31 15 81 -14 -60 10

Shell Weld + Press Force 50 33 14 87 -16 -61 187

Shell Welded no Press Force 48 32 15 85 -15 -60 194

Collaring Load Post-Collaring Collar in yoke Max Press force Shell Weld + Press Force

Shell Welded no Press Force

Shell Welded - 297K

Cool Down (18K)

11-Tesla0

10

20

30

40

50

60Mirror Coil - contact pressure at pole (Cap Gauge)

FEA Max Cap gauge - pressure (MPa)

FEA Avg Cap gauge - pressure (MPa)

FEA Min Cap gauge - pressure (MPa)

Measured Coil Data (10 error bars)

Pres

sure

(MPa

)

Click here to add footer 20

ANSYS Forecast at 11-Tesla

Assembly Step

Max Capacitive gauge -

pressure (MPa)

Avg Capacitive gauge -

pressure (MPa)

Min Capacitive gauge -

pressure (MPa)

Collar-nose stress (MPa)

Coil Min stress (MPa)

Coil Max Stress (MPa)

Avg Shell Stress (MPa)

MirrorCoil

Shell Welded - 297K 48 32 15 85 -15 -60 195

Cool Down (18K) 37 21 5 62 -5 -74 375

11-Tesla 1 05 0 63 +13 -117 377

NominalCoil

Shell Welded - 297K 107 58 8 150 -14 -119 191

Cool Down (18K) 86 43 1 123 -21 -125 373

11-Tesla 22 11 0 57 -4 -120 374

Collar Nose Von-Mises Stress

At 11T

Coil BlocksAzimuthal Stress

At 11T

FEA predicted results

Click here to add footer 21

Bullet gauges loadingM GuinchardP Grosclaude

8 to 9 kN per bullet

Click here to add footer 22

Electrical tests ndash WhenF-O PincotL Grand Cleacutement

Are performed beforeafter each important construction step Test of pole Nb3Sn before curing - PBC Test of pole Nb3Sn before reaction ndash PBR Test of pole Nb3Sn after reaction ndash PAR Test of pole Nb3Sn after impregnation out of the mould ndash PAI Test of pole Nb3Sn after impregnation with instrumentation ndash PAIWI Test of collared coil before collaring ndash BC Test of collared coil after collaring ndash AC Test of the magnet under load before welding ndash UL Test of the magnet after shell welding ndash AW Test of the magnet after longitudinal coil loading ndash AL Test of the magnet after interconnection ndash AI Final Test of the magnet before delivery - FINAL

Click here to add footer 23

Electrical tests ndash WhatF-O PincotL Grand CleacutementAccording to the construction step we define

specific test valueselectrical tests among which

Resistance measurement(Coils Quench heaters Voltage taps Instrumentation) Inductance measurement Capacitance measurement Dielectric measurement(between coils QH instrumentation ground)

bull Insulation (up to 1kV 30s)bull current leakage (up to 1kV 5min)

Discharge test on coilUp to 1kV

Discharge test on quench heatersUp to 900V or 80AQH

Click here to add footer 24

Electrical testsF-O PincotL Grand Cleacutement

Resistance Insulation dielectric Inductance Capacitance Coil discharge QH discharge

Test phase

code

PBC X X X

PBR X X X

PAR X X X

PAI X X X X

PAIWI X X X X

BC X X X X X X

AC X X X X X X

UL X X

AW X X X X X X

AL X X X X X X

AI X X X X X X

FINAL X X X X X X

Click here to add footer 25

Click here to add footer 26

Plan for power tests coldbull RRR and strain gauge measurementsbull Preliminary tests ndash Setup protection ndash Splice resistance

measurements (current plateaus at 2 4 6 8 and 10 kA) ndash 3 hoursbull Training 43 K ndash 15 quenches ndash 3 days bull Training 19 K ndash 10 quenches ndash 25 days

Stability on current plateau ndash 05 daybull Ramp-rate study 100 As and 50 As ndash 05 day

AC-loss measurements (includes inductance measurement) at 5 to 100 As ndash 05 day

bull Quench heater efficiency study 3 different settings of QH pulse for 3 currents each Long re-cooling of the magnet due to delay of energy extraction ndash 3 days

bull High MIIts tests (protection delay) 6 quenches ndash 3 days

bull Quench propagation velocity measurements acquired for the training quenches

G Willeringbull Cool down bull Day 1

bull Day 2-4bull Day 5-7

bull Day 8

bull Day 9-11

bull Day 12-14

Click here to add footer 27

Further actionsbull After cold tests warm magnetic

measurements will be carried out with the two coils connected

bull Model 1 MBHSP101 single aperture with cable OST RRP 108127 for both polesbull Instrumentation of coils 106 and 107 going onbull Collaring scheduled around middle of June

  • CERN-FNAL Video Meeting 12 Progress of the 11T Dipole short m
  • Contributions
  • Main design features
  • Specific features
  • Assembly conditions - Winding
  • Binder curing
  • Reaction treatment
  • Reaction treatment ndash Coil 105
  • Impregnation
  • Instrumentation outer layer
  • Instrumentation inner layer
  • Quench heaters
  • Coils size
  • Excess in mid-plane
  • Collaring steps
  • Shimming plan
  • Yoking welding of the shells
  • Structural analysis vs measurements
  • FEA Results
  • ANSYS Forecast at 11-Tesla
  • Bullet gauges loading
  • Electrical tests ndash When
  • Electrical tests ndash What
  • Electrical tests
  • Slide 25
  • Plan for power tests cold
  • Further actions
Page 17: CERN MBHSM0101 general  status F. Savary on behalf of the 11T Dipole Project Team

Click here to add footer 17

Yoking welding of the shellsF Lackner

1 2 3 4 5 6 7 80

100200300400500600700800

0

110

206

361426

526610

686Pressure rising April 28th 2014

Pressure rising step

Tota

l cha

rge

in to

ns

3154906157901240166520652225

002040608

SIDE B 0110206361426526610686

Length in [mm]

Yoke

gap

[mm

]

Tota

l loa

d in

tons

Max charge 500 tm on central section to close the welding gap

0

02

04

06

SIDE A0110206361426526610686

Length in [mm]

Yoke

gap

[mm

]

Tota

l loa

d in

tons

Click here to add footer 18

Structural analysis vs measurements

Click here to add footer 19

FEA Results 11T Mirror

FEA Max Cap gauge

pressure (MPa)

FEA Avg Cap gauge

pressure (MPa)

FEA Min Cap gauge

pressure (MPa)

Collar nose

stress (MPa)

Coil Min stress (MPa)

Coil Max Stress (MPa)

Avg Shell Stress (MPa)

Collaring Load 48 33 18 88 -7 -90

Post-Collaring 39 28 16 72 -7 -69

Collar in yoke 40 28 17 73 -9 -66

Max Press force 46 31 15 81 -14 -60 10

Shell Weld + Press Force 50 33 14 87 -16 -61 187

Shell Welded no Press Force 48 32 15 85 -15 -60 194

Collaring Load Post-Collaring Collar in yoke Max Press force Shell Weld + Press Force

Shell Welded no Press Force

Shell Welded - 297K

Cool Down (18K)

11-Tesla0

10

20

30

40

50

60Mirror Coil - contact pressure at pole (Cap Gauge)

FEA Max Cap gauge - pressure (MPa)

FEA Avg Cap gauge - pressure (MPa)

FEA Min Cap gauge - pressure (MPa)

Measured Coil Data (10 error bars)

Pres

sure

(MPa

)

Click here to add footer 20

ANSYS Forecast at 11-Tesla

Assembly Step

Max Capacitive gauge -

pressure (MPa)

Avg Capacitive gauge -

pressure (MPa)

Min Capacitive gauge -

pressure (MPa)

Collar-nose stress (MPa)

Coil Min stress (MPa)

Coil Max Stress (MPa)

Avg Shell Stress (MPa)

MirrorCoil

Shell Welded - 297K 48 32 15 85 -15 -60 195

Cool Down (18K) 37 21 5 62 -5 -74 375

11-Tesla 1 05 0 63 +13 -117 377

NominalCoil

Shell Welded - 297K 107 58 8 150 -14 -119 191

Cool Down (18K) 86 43 1 123 -21 -125 373

11-Tesla 22 11 0 57 -4 -120 374

Collar Nose Von-Mises Stress

At 11T

Coil BlocksAzimuthal Stress

At 11T

FEA predicted results

Click here to add footer 21

Bullet gauges loadingM GuinchardP Grosclaude

8 to 9 kN per bullet

Click here to add footer 22

Electrical tests ndash WhenF-O PincotL Grand Cleacutement

Are performed beforeafter each important construction step Test of pole Nb3Sn before curing - PBC Test of pole Nb3Sn before reaction ndash PBR Test of pole Nb3Sn after reaction ndash PAR Test of pole Nb3Sn after impregnation out of the mould ndash PAI Test of pole Nb3Sn after impregnation with instrumentation ndash PAIWI Test of collared coil before collaring ndash BC Test of collared coil after collaring ndash AC Test of the magnet under load before welding ndash UL Test of the magnet after shell welding ndash AW Test of the magnet after longitudinal coil loading ndash AL Test of the magnet after interconnection ndash AI Final Test of the magnet before delivery - FINAL

Click here to add footer 23

Electrical tests ndash WhatF-O PincotL Grand CleacutementAccording to the construction step we define

specific test valueselectrical tests among which

Resistance measurement(Coils Quench heaters Voltage taps Instrumentation) Inductance measurement Capacitance measurement Dielectric measurement(between coils QH instrumentation ground)

bull Insulation (up to 1kV 30s)bull current leakage (up to 1kV 5min)

Discharge test on coilUp to 1kV

Discharge test on quench heatersUp to 900V or 80AQH

Click here to add footer 24

Electrical testsF-O PincotL Grand Cleacutement

Resistance Insulation dielectric Inductance Capacitance Coil discharge QH discharge

Test phase

code

PBC X X X

PBR X X X

PAR X X X

PAI X X X X

PAIWI X X X X

BC X X X X X X

AC X X X X X X

UL X X

AW X X X X X X

AL X X X X X X

AI X X X X X X

FINAL X X X X X X

Click here to add footer 25

Click here to add footer 26

Plan for power tests coldbull RRR and strain gauge measurementsbull Preliminary tests ndash Setup protection ndash Splice resistance

measurements (current plateaus at 2 4 6 8 and 10 kA) ndash 3 hoursbull Training 43 K ndash 15 quenches ndash 3 days bull Training 19 K ndash 10 quenches ndash 25 days

Stability on current plateau ndash 05 daybull Ramp-rate study 100 As and 50 As ndash 05 day

AC-loss measurements (includes inductance measurement) at 5 to 100 As ndash 05 day

bull Quench heater efficiency study 3 different settings of QH pulse for 3 currents each Long re-cooling of the magnet due to delay of energy extraction ndash 3 days

bull High MIIts tests (protection delay) 6 quenches ndash 3 days

bull Quench propagation velocity measurements acquired for the training quenches

G Willeringbull Cool down bull Day 1

bull Day 2-4bull Day 5-7

bull Day 8

bull Day 9-11

bull Day 12-14

Click here to add footer 27

Further actionsbull After cold tests warm magnetic

measurements will be carried out with the two coils connected

bull Model 1 MBHSP101 single aperture with cable OST RRP 108127 for both polesbull Instrumentation of coils 106 and 107 going onbull Collaring scheduled around middle of June

  • CERN-FNAL Video Meeting 12 Progress of the 11T Dipole short m
  • Contributions
  • Main design features
  • Specific features
  • Assembly conditions - Winding
  • Binder curing
  • Reaction treatment
  • Reaction treatment ndash Coil 105
  • Impregnation
  • Instrumentation outer layer
  • Instrumentation inner layer
  • Quench heaters
  • Coils size
  • Excess in mid-plane
  • Collaring steps
  • Shimming plan
  • Yoking welding of the shells
  • Structural analysis vs measurements
  • FEA Results
  • ANSYS Forecast at 11-Tesla
  • Bullet gauges loading
  • Electrical tests ndash When
  • Electrical tests ndash What
  • Electrical tests
  • Slide 25
  • Plan for power tests cold
  • Further actions
Page 18: CERN MBHSM0101 general  status F. Savary on behalf of the 11T Dipole Project Team

Click here to add footer 18

Structural analysis vs measurements

Click here to add footer 19

FEA Results 11T Mirror

FEA Max Cap gauge

pressure (MPa)

FEA Avg Cap gauge

pressure (MPa)

FEA Min Cap gauge

pressure (MPa)

Collar nose

stress (MPa)

Coil Min stress (MPa)

Coil Max Stress (MPa)

Avg Shell Stress (MPa)

Collaring Load 48 33 18 88 -7 -90

Post-Collaring 39 28 16 72 -7 -69

Collar in yoke 40 28 17 73 -9 -66

Max Press force 46 31 15 81 -14 -60 10

Shell Weld + Press Force 50 33 14 87 -16 -61 187

Shell Welded no Press Force 48 32 15 85 -15 -60 194

Collaring Load Post-Collaring Collar in yoke Max Press force Shell Weld + Press Force

Shell Welded no Press Force

Shell Welded - 297K

Cool Down (18K)

11-Tesla0

10

20

30

40

50

60Mirror Coil - contact pressure at pole (Cap Gauge)

FEA Max Cap gauge - pressure (MPa)

FEA Avg Cap gauge - pressure (MPa)

FEA Min Cap gauge - pressure (MPa)

Measured Coil Data (10 error bars)

Pres

sure

(MPa

)

Click here to add footer 20

ANSYS Forecast at 11-Tesla

Assembly Step

Max Capacitive gauge -

pressure (MPa)

Avg Capacitive gauge -

pressure (MPa)

Min Capacitive gauge -

pressure (MPa)

Collar-nose stress (MPa)

Coil Min stress (MPa)

Coil Max Stress (MPa)

Avg Shell Stress (MPa)

MirrorCoil

Shell Welded - 297K 48 32 15 85 -15 -60 195

Cool Down (18K) 37 21 5 62 -5 -74 375

11-Tesla 1 05 0 63 +13 -117 377

NominalCoil

Shell Welded - 297K 107 58 8 150 -14 -119 191

Cool Down (18K) 86 43 1 123 -21 -125 373

11-Tesla 22 11 0 57 -4 -120 374

Collar Nose Von-Mises Stress

At 11T

Coil BlocksAzimuthal Stress

At 11T

FEA predicted results

Click here to add footer 21

Bullet gauges loadingM GuinchardP Grosclaude

8 to 9 kN per bullet

Click here to add footer 22

Electrical tests ndash WhenF-O PincotL Grand Cleacutement

Are performed beforeafter each important construction step Test of pole Nb3Sn before curing - PBC Test of pole Nb3Sn before reaction ndash PBR Test of pole Nb3Sn after reaction ndash PAR Test of pole Nb3Sn after impregnation out of the mould ndash PAI Test of pole Nb3Sn after impregnation with instrumentation ndash PAIWI Test of collared coil before collaring ndash BC Test of collared coil after collaring ndash AC Test of the magnet under load before welding ndash UL Test of the magnet after shell welding ndash AW Test of the magnet after longitudinal coil loading ndash AL Test of the magnet after interconnection ndash AI Final Test of the magnet before delivery - FINAL

Click here to add footer 23

Electrical tests ndash WhatF-O PincotL Grand CleacutementAccording to the construction step we define

specific test valueselectrical tests among which

Resistance measurement(Coils Quench heaters Voltage taps Instrumentation) Inductance measurement Capacitance measurement Dielectric measurement(between coils QH instrumentation ground)

bull Insulation (up to 1kV 30s)bull current leakage (up to 1kV 5min)

Discharge test on coilUp to 1kV

Discharge test on quench heatersUp to 900V or 80AQH

Click here to add footer 24

Electrical testsF-O PincotL Grand Cleacutement

Resistance Insulation dielectric Inductance Capacitance Coil discharge QH discharge

Test phase

code

PBC X X X

PBR X X X

PAR X X X

PAI X X X X

PAIWI X X X X

BC X X X X X X

AC X X X X X X

UL X X

AW X X X X X X

AL X X X X X X

AI X X X X X X

FINAL X X X X X X

Click here to add footer 25

Click here to add footer 26

Plan for power tests coldbull RRR and strain gauge measurementsbull Preliminary tests ndash Setup protection ndash Splice resistance

measurements (current plateaus at 2 4 6 8 and 10 kA) ndash 3 hoursbull Training 43 K ndash 15 quenches ndash 3 days bull Training 19 K ndash 10 quenches ndash 25 days

Stability on current plateau ndash 05 daybull Ramp-rate study 100 As and 50 As ndash 05 day

AC-loss measurements (includes inductance measurement) at 5 to 100 As ndash 05 day

bull Quench heater efficiency study 3 different settings of QH pulse for 3 currents each Long re-cooling of the magnet due to delay of energy extraction ndash 3 days

bull High MIIts tests (protection delay) 6 quenches ndash 3 days

bull Quench propagation velocity measurements acquired for the training quenches

G Willeringbull Cool down bull Day 1

bull Day 2-4bull Day 5-7

bull Day 8

bull Day 9-11

bull Day 12-14

Click here to add footer 27

Further actionsbull After cold tests warm magnetic

measurements will be carried out with the two coils connected

bull Model 1 MBHSP101 single aperture with cable OST RRP 108127 for both polesbull Instrumentation of coils 106 and 107 going onbull Collaring scheduled around middle of June

  • CERN-FNAL Video Meeting 12 Progress of the 11T Dipole short m
  • Contributions
  • Main design features
  • Specific features
  • Assembly conditions - Winding
  • Binder curing
  • Reaction treatment
  • Reaction treatment ndash Coil 105
  • Impregnation
  • Instrumentation outer layer
  • Instrumentation inner layer
  • Quench heaters
  • Coils size
  • Excess in mid-plane
  • Collaring steps
  • Shimming plan
  • Yoking welding of the shells
  • Structural analysis vs measurements
  • FEA Results
  • ANSYS Forecast at 11-Tesla
  • Bullet gauges loading
  • Electrical tests ndash When
  • Electrical tests ndash What
  • Electrical tests
  • Slide 25
  • Plan for power tests cold
  • Further actions
Page 19: CERN MBHSM0101 general  status F. Savary on behalf of the 11T Dipole Project Team

Click here to add footer 19

FEA Results 11T Mirror

FEA Max Cap gauge

pressure (MPa)

FEA Avg Cap gauge

pressure (MPa)

FEA Min Cap gauge

pressure (MPa)

Collar nose

stress (MPa)

Coil Min stress (MPa)

Coil Max Stress (MPa)

Avg Shell Stress (MPa)

Collaring Load 48 33 18 88 -7 -90

Post-Collaring 39 28 16 72 -7 -69

Collar in yoke 40 28 17 73 -9 -66

Max Press force 46 31 15 81 -14 -60 10

Shell Weld + Press Force 50 33 14 87 -16 -61 187

Shell Welded no Press Force 48 32 15 85 -15 -60 194

Collaring Load Post-Collaring Collar in yoke Max Press force Shell Weld + Press Force

Shell Welded no Press Force

Shell Welded - 297K

Cool Down (18K)

11-Tesla0

10

20

30

40

50

60Mirror Coil - contact pressure at pole (Cap Gauge)

FEA Max Cap gauge - pressure (MPa)

FEA Avg Cap gauge - pressure (MPa)

FEA Min Cap gauge - pressure (MPa)

Measured Coil Data (10 error bars)

Pres

sure

(MPa

)

Click here to add footer 20

ANSYS Forecast at 11-Tesla

Assembly Step

Max Capacitive gauge -

pressure (MPa)

Avg Capacitive gauge -

pressure (MPa)

Min Capacitive gauge -

pressure (MPa)

Collar-nose stress (MPa)

Coil Min stress (MPa)

Coil Max Stress (MPa)

Avg Shell Stress (MPa)

MirrorCoil

Shell Welded - 297K 48 32 15 85 -15 -60 195

Cool Down (18K) 37 21 5 62 -5 -74 375

11-Tesla 1 05 0 63 +13 -117 377

NominalCoil

Shell Welded - 297K 107 58 8 150 -14 -119 191

Cool Down (18K) 86 43 1 123 -21 -125 373

11-Tesla 22 11 0 57 -4 -120 374

Collar Nose Von-Mises Stress

At 11T

Coil BlocksAzimuthal Stress

At 11T

FEA predicted results

Click here to add footer 21

Bullet gauges loadingM GuinchardP Grosclaude

8 to 9 kN per bullet

Click here to add footer 22

Electrical tests ndash WhenF-O PincotL Grand Cleacutement

Are performed beforeafter each important construction step Test of pole Nb3Sn before curing - PBC Test of pole Nb3Sn before reaction ndash PBR Test of pole Nb3Sn after reaction ndash PAR Test of pole Nb3Sn after impregnation out of the mould ndash PAI Test of pole Nb3Sn after impregnation with instrumentation ndash PAIWI Test of collared coil before collaring ndash BC Test of collared coil after collaring ndash AC Test of the magnet under load before welding ndash UL Test of the magnet after shell welding ndash AW Test of the magnet after longitudinal coil loading ndash AL Test of the magnet after interconnection ndash AI Final Test of the magnet before delivery - FINAL

Click here to add footer 23

Electrical tests ndash WhatF-O PincotL Grand CleacutementAccording to the construction step we define

specific test valueselectrical tests among which

Resistance measurement(Coils Quench heaters Voltage taps Instrumentation) Inductance measurement Capacitance measurement Dielectric measurement(between coils QH instrumentation ground)

bull Insulation (up to 1kV 30s)bull current leakage (up to 1kV 5min)

Discharge test on coilUp to 1kV

Discharge test on quench heatersUp to 900V or 80AQH

Click here to add footer 24

Electrical testsF-O PincotL Grand Cleacutement

Resistance Insulation dielectric Inductance Capacitance Coil discharge QH discharge

Test phase

code

PBC X X X

PBR X X X

PAR X X X

PAI X X X X

PAIWI X X X X

BC X X X X X X

AC X X X X X X

UL X X

AW X X X X X X

AL X X X X X X

AI X X X X X X

FINAL X X X X X X

Click here to add footer 25

Click here to add footer 26

Plan for power tests coldbull RRR and strain gauge measurementsbull Preliminary tests ndash Setup protection ndash Splice resistance

measurements (current plateaus at 2 4 6 8 and 10 kA) ndash 3 hoursbull Training 43 K ndash 15 quenches ndash 3 days bull Training 19 K ndash 10 quenches ndash 25 days

Stability on current plateau ndash 05 daybull Ramp-rate study 100 As and 50 As ndash 05 day

AC-loss measurements (includes inductance measurement) at 5 to 100 As ndash 05 day

bull Quench heater efficiency study 3 different settings of QH pulse for 3 currents each Long re-cooling of the magnet due to delay of energy extraction ndash 3 days

bull High MIIts tests (protection delay) 6 quenches ndash 3 days

bull Quench propagation velocity measurements acquired for the training quenches

G Willeringbull Cool down bull Day 1

bull Day 2-4bull Day 5-7

bull Day 8

bull Day 9-11

bull Day 12-14

Click here to add footer 27

Further actionsbull After cold tests warm magnetic

measurements will be carried out with the two coils connected

bull Model 1 MBHSP101 single aperture with cable OST RRP 108127 for both polesbull Instrumentation of coils 106 and 107 going onbull Collaring scheduled around middle of June

  • CERN-FNAL Video Meeting 12 Progress of the 11T Dipole short m
  • Contributions
  • Main design features
  • Specific features
  • Assembly conditions - Winding
  • Binder curing
  • Reaction treatment
  • Reaction treatment ndash Coil 105
  • Impregnation
  • Instrumentation outer layer
  • Instrumentation inner layer
  • Quench heaters
  • Coils size
  • Excess in mid-plane
  • Collaring steps
  • Shimming plan
  • Yoking welding of the shells
  • Structural analysis vs measurements
  • FEA Results
  • ANSYS Forecast at 11-Tesla
  • Bullet gauges loading
  • Electrical tests ndash When
  • Electrical tests ndash What
  • Electrical tests
  • Slide 25
  • Plan for power tests cold
  • Further actions
Page 20: CERN MBHSM0101 general  status F. Savary on behalf of the 11T Dipole Project Team

Click here to add footer 20

ANSYS Forecast at 11-Tesla

Assembly Step

Max Capacitive gauge -

pressure (MPa)

Avg Capacitive gauge -

pressure (MPa)

Min Capacitive gauge -

pressure (MPa)

Collar-nose stress (MPa)

Coil Min stress (MPa)

Coil Max Stress (MPa)

Avg Shell Stress (MPa)

MirrorCoil

Shell Welded - 297K 48 32 15 85 -15 -60 195

Cool Down (18K) 37 21 5 62 -5 -74 375

11-Tesla 1 05 0 63 +13 -117 377

NominalCoil

Shell Welded - 297K 107 58 8 150 -14 -119 191

Cool Down (18K) 86 43 1 123 -21 -125 373

11-Tesla 22 11 0 57 -4 -120 374

Collar Nose Von-Mises Stress

At 11T

Coil BlocksAzimuthal Stress

At 11T

FEA predicted results

Click here to add footer 21

Bullet gauges loadingM GuinchardP Grosclaude

8 to 9 kN per bullet

Click here to add footer 22

Electrical tests ndash WhenF-O PincotL Grand Cleacutement

Are performed beforeafter each important construction step Test of pole Nb3Sn before curing - PBC Test of pole Nb3Sn before reaction ndash PBR Test of pole Nb3Sn after reaction ndash PAR Test of pole Nb3Sn after impregnation out of the mould ndash PAI Test of pole Nb3Sn after impregnation with instrumentation ndash PAIWI Test of collared coil before collaring ndash BC Test of collared coil after collaring ndash AC Test of the magnet under load before welding ndash UL Test of the magnet after shell welding ndash AW Test of the magnet after longitudinal coil loading ndash AL Test of the magnet after interconnection ndash AI Final Test of the magnet before delivery - FINAL

Click here to add footer 23

Electrical tests ndash WhatF-O PincotL Grand CleacutementAccording to the construction step we define

specific test valueselectrical tests among which

Resistance measurement(Coils Quench heaters Voltage taps Instrumentation) Inductance measurement Capacitance measurement Dielectric measurement(between coils QH instrumentation ground)

bull Insulation (up to 1kV 30s)bull current leakage (up to 1kV 5min)

Discharge test on coilUp to 1kV

Discharge test on quench heatersUp to 900V or 80AQH

Click here to add footer 24

Electrical testsF-O PincotL Grand Cleacutement

Resistance Insulation dielectric Inductance Capacitance Coil discharge QH discharge

Test phase

code

PBC X X X

PBR X X X

PAR X X X

PAI X X X X

PAIWI X X X X

BC X X X X X X

AC X X X X X X

UL X X

AW X X X X X X

AL X X X X X X

AI X X X X X X

FINAL X X X X X X

Click here to add footer 25

Click here to add footer 26

Plan for power tests coldbull RRR and strain gauge measurementsbull Preliminary tests ndash Setup protection ndash Splice resistance

measurements (current plateaus at 2 4 6 8 and 10 kA) ndash 3 hoursbull Training 43 K ndash 15 quenches ndash 3 days bull Training 19 K ndash 10 quenches ndash 25 days

Stability on current plateau ndash 05 daybull Ramp-rate study 100 As and 50 As ndash 05 day

AC-loss measurements (includes inductance measurement) at 5 to 100 As ndash 05 day

bull Quench heater efficiency study 3 different settings of QH pulse for 3 currents each Long re-cooling of the magnet due to delay of energy extraction ndash 3 days

bull High MIIts tests (protection delay) 6 quenches ndash 3 days

bull Quench propagation velocity measurements acquired for the training quenches

G Willeringbull Cool down bull Day 1

bull Day 2-4bull Day 5-7

bull Day 8

bull Day 9-11

bull Day 12-14

Click here to add footer 27

Further actionsbull After cold tests warm magnetic

measurements will be carried out with the two coils connected

bull Model 1 MBHSP101 single aperture with cable OST RRP 108127 for both polesbull Instrumentation of coils 106 and 107 going onbull Collaring scheduled around middle of June

  • CERN-FNAL Video Meeting 12 Progress of the 11T Dipole short m
  • Contributions
  • Main design features
  • Specific features
  • Assembly conditions - Winding
  • Binder curing
  • Reaction treatment
  • Reaction treatment ndash Coil 105
  • Impregnation
  • Instrumentation outer layer
  • Instrumentation inner layer
  • Quench heaters
  • Coils size
  • Excess in mid-plane
  • Collaring steps
  • Shimming plan
  • Yoking welding of the shells
  • Structural analysis vs measurements
  • FEA Results
  • ANSYS Forecast at 11-Tesla
  • Bullet gauges loading
  • Electrical tests ndash When
  • Electrical tests ndash What
  • Electrical tests
  • Slide 25
  • Plan for power tests cold
  • Further actions
Page 21: CERN MBHSM0101 general  status F. Savary on behalf of the 11T Dipole Project Team

Click here to add footer 21

Bullet gauges loadingM GuinchardP Grosclaude

8 to 9 kN per bullet

Click here to add footer 22

Electrical tests ndash WhenF-O PincotL Grand Cleacutement

Are performed beforeafter each important construction step Test of pole Nb3Sn before curing - PBC Test of pole Nb3Sn before reaction ndash PBR Test of pole Nb3Sn after reaction ndash PAR Test of pole Nb3Sn after impregnation out of the mould ndash PAI Test of pole Nb3Sn after impregnation with instrumentation ndash PAIWI Test of collared coil before collaring ndash BC Test of collared coil after collaring ndash AC Test of the magnet under load before welding ndash UL Test of the magnet after shell welding ndash AW Test of the magnet after longitudinal coil loading ndash AL Test of the magnet after interconnection ndash AI Final Test of the magnet before delivery - FINAL

Click here to add footer 23

Electrical tests ndash WhatF-O PincotL Grand CleacutementAccording to the construction step we define

specific test valueselectrical tests among which

Resistance measurement(Coils Quench heaters Voltage taps Instrumentation) Inductance measurement Capacitance measurement Dielectric measurement(between coils QH instrumentation ground)

bull Insulation (up to 1kV 30s)bull current leakage (up to 1kV 5min)

Discharge test on coilUp to 1kV

Discharge test on quench heatersUp to 900V or 80AQH

Click here to add footer 24

Electrical testsF-O PincotL Grand Cleacutement

Resistance Insulation dielectric Inductance Capacitance Coil discharge QH discharge

Test phase

code

PBC X X X

PBR X X X

PAR X X X

PAI X X X X

PAIWI X X X X

BC X X X X X X

AC X X X X X X

UL X X

AW X X X X X X

AL X X X X X X

AI X X X X X X

FINAL X X X X X X

Click here to add footer 25

Click here to add footer 26

Plan for power tests coldbull RRR and strain gauge measurementsbull Preliminary tests ndash Setup protection ndash Splice resistance

measurements (current plateaus at 2 4 6 8 and 10 kA) ndash 3 hoursbull Training 43 K ndash 15 quenches ndash 3 days bull Training 19 K ndash 10 quenches ndash 25 days

Stability on current plateau ndash 05 daybull Ramp-rate study 100 As and 50 As ndash 05 day

AC-loss measurements (includes inductance measurement) at 5 to 100 As ndash 05 day

bull Quench heater efficiency study 3 different settings of QH pulse for 3 currents each Long re-cooling of the magnet due to delay of energy extraction ndash 3 days

bull High MIIts tests (protection delay) 6 quenches ndash 3 days

bull Quench propagation velocity measurements acquired for the training quenches

G Willeringbull Cool down bull Day 1

bull Day 2-4bull Day 5-7

bull Day 8

bull Day 9-11

bull Day 12-14

Click here to add footer 27

Further actionsbull After cold tests warm magnetic

measurements will be carried out with the two coils connected

bull Model 1 MBHSP101 single aperture with cable OST RRP 108127 for both polesbull Instrumentation of coils 106 and 107 going onbull Collaring scheduled around middle of June

  • CERN-FNAL Video Meeting 12 Progress of the 11T Dipole short m
  • Contributions
  • Main design features
  • Specific features
  • Assembly conditions - Winding
  • Binder curing
  • Reaction treatment
  • Reaction treatment ndash Coil 105
  • Impregnation
  • Instrumentation outer layer
  • Instrumentation inner layer
  • Quench heaters
  • Coils size
  • Excess in mid-plane
  • Collaring steps
  • Shimming plan
  • Yoking welding of the shells
  • Structural analysis vs measurements
  • FEA Results
  • ANSYS Forecast at 11-Tesla
  • Bullet gauges loading
  • Electrical tests ndash When
  • Electrical tests ndash What
  • Electrical tests
  • Slide 25
  • Plan for power tests cold
  • Further actions
Page 22: CERN MBHSM0101 general  status F. Savary on behalf of the 11T Dipole Project Team

Click here to add footer 22

Electrical tests ndash WhenF-O PincotL Grand Cleacutement

Are performed beforeafter each important construction step Test of pole Nb3Sn before curing - PBC Test of pole Nb3Sn before reaction ndash PBR Test of pole Nb3Sn after reaction ndash PAR Test of pole Nb3Sn after impregnation out of the mould ndash PAI Test of pole Nb3Sn after impregnation with instrumentation ndash PAIWI Test of collared coil before collaring ndash BC Test of collared coil after collaring ndash AC Test of the magnet under load before welding ndash UL Test of the magnet after shell welding ndash AW Test of the magnet after longitudinal coil loading ndash AL Test of the magnet after interconnection ndash AI Final Test of the magnet before delivery - FINAL

Click here to add footer 23

Electrical tests ndash WhatF-O PincotL Grand CleacutementAccording to the construction step we define

specific test valueselectrical tests among which

Resistance measurement(Coils Quench heaters Voltage taps Instrumentation) Inductance measurement Capacitance measurement Dielectric measurement(between coils QH instrumentation ground)

bull Insulation (up to 1kV 30s)bull current leakage (up to 1kV 5min)

Discharge test on coilUp to 1kV

Discharge test on quench heatersUp to 900V or 80AQH

Click here to add footer 24

Electrical testsF-O PincotL Grand Cleacutement

Resistance Insulation dielectric Inductance Capacitance Coil discharge QH discharge

Test phase

code

PBC X X X

PBR X X X

PAR X X X

PAI X X X X

PAIWI X X X X

BC X X X X X X

AC X X X X X X

UL X X

AW X X X X X X

AL X X X X X X

AI X X X X X X

FINAL X X X X X X

Click here to add footer 25

Click here to add footer 26

Plan for power tests coldbull RRR and strain gauge measurementsbull Preliminary tests ndash Setup protection ndash Splice resistance

measurements (current plateaus at 2 4 6 8 and 10 kA) ndash 3 hoursbull Training 43 K ndash 15 quenches ndash 3 days bull Training 19 K ndash 10 quenches ndash 25 days

Stability on current plateau ndash 05 daybull Ramp-rate study 100 As and 50 As ndash 05 day

AC-loss measurements (includes inductance measurement) at 5 to 100 As ndash 05 day

bull Quench heater efficiency study 3 different settings of QH pulse for 3 currents each Long re-cooling of the magnet due to delay of energy extraction ndash 3 days

bull High MIIts tests (protection delay) 6 quenches ndash 3 days

bull Quench propagation velocity measurements acquired for the training quenches

G Willeringbull Cool down bull Day 1

bull Day 2-4bull Day 5-7

bull Day 8

bull Day 9-11

bull Day 12-14

Click here to add footer 27

Further actionsbull After cold tests warm magnetic

measurements will be carried out with the two coils connected

bull Model 1 MBHSP101 single aperture with cable OST RRP 108127 for both polesbull Instrumentation of coils 106 and 107 going onbull Collaring scheduled around middle of June

  • CERN-FNAL Video Meeting 12 Progress of the 11T Dipole short m
  • Contributions
  • Main design features
  • Specific features
  • Assembly conditions - Winding
  • Binder curing
  • Reaction treatment
  • Reaction treatment ndash Coil 105
  • Impregnation
  • Instrumentation outer layer
  • Instrumentation inner layer
  • Quench heaters
  • Coils size
  • Excess in mid-plane
  • Collaring steps
  • Shimming plan
  • Yoking welding of the shells
  • Structural analysis vs measurements
  • FEA Results
  • ANSYS Forecast at 11-Tesla
  • Bullet gauges loading
  • Electrical tests ndash When
  • Electrical tests ndash What
  • Electrical tests
  • Slide 25
  • Plan for power tests cold
  • Further actions
Page 23: CERN MBHSM0101 general  status F. Savary on behalf of the 11T Dipole Project Team

Click here to add footer 23

Electrical tests ndash WhatF-O PincotL Grand CleacutementAccording to the construction step we define

specific test valueselectrical tests among which

Resistance measurement(Coils Quench heaters Voltage taps Instrumentation) Inductance measurement Capacitance measurement Dielectric measurement(between coils QH instrumentation ground)

bull Insulation (up to 1kV 30s)bull current leakage (up to 1kV 5min)

Discharge test on coilUp to 1kV

Discharge test on quench heatersUp to 900V or 80AQH

Click here to add footer 24

Electrical testsF-O PincotL Grand Cleacutement

Resistance Insulation dielectric Inductance Capacitance Coil discharge QH discharge

Test phase

code

PBC X X X

PBR X X X

PAR X X X

PAI X X X X

PAIWI X X X X

BC X X X X X X

AC X X X X X X

UL X X

AW X X X X X X

AL X X X X X X

AI X X X X X X

FINAL X X X X X X

Click here to add footer 25

Click here to add footer 26

Plan for power tests coldbull RRR and strain gauge measurementsbull Preliminary tests ndash Setup protection ndash Splice resistance

measurements (current plateaus at 2 4 6 8 and 10 kA) ndash 3 hoursbull Training 43 K ndash 15 quenches ndash 3 days bull Training 19 K ndash 10 quenches ndash 25 days

Stability on current plateau ndash 05 daybull Ramp-rate study 100 As and 50 As ndash 05 day

AC-loss measurements (includes inductance measurement) at 5 to 100 As ndash 05 day

bull Quench heater efficiency study 3 different settings of QH pulse for 3 currents each Long re-cooling of the magnet due to delay of energy extraction ndash 3 days

bull High MIIts tests (protection delay) 6 quenches ndash 3 days

bull Quench propagation velocity measurements acquired for the training quenches

G Willeringbull Cool down bull Day 1

bull Day 2-4bull Day 5-7

bull Day 8

bull Day 9-11

bull Day 12-14

Click here to add footer 27

Further actionsbull After cold tests warm magnetic

measurements will be carried out with the two coils connected

bull Model 1 MBHSP101 single aperture with cable OST RRP 108127 for both polesbull Instrumentation of coils 106 and 107 going onbull Collaring scheduled around middle of June

  • CERN-FNAL Video Meeting 12 Progress of the 11T Dipole short m
  • Contributions
  • Main design features
  • Specific features
  • Assembly conditions - Winding
  • Binder curing
  • Reaction treatment
  • Reaction treatment ndash Coil 105
  • Impregnation
  • Instrumentation outer layer
  • Instrumentation inner layer
  • Quench heaters
  • Coils size
  • Excess in mid-plane
  • Collaring steps
  • Shimming plan
  • Yoking welding of the shells
  • Structural analysis vs measurements
  • FEA Results
  • ANSYS Forecast at 11-Tesla
  • Bullet gauges loading
  • Electrical tests ndash When
  • Electrical tests ndash What
  • Electrical tests
  • Slide 25
  • Plan for power tests cold
  • Further actions
Page 24: CERN MBHSM0101 general  status F. Savary on behalf of the 11T Dipole Project Team

Click here to add footer 24

Electrical testsF-O PincotL Grand Cleacutement

Resistance Insulation dielectric Inductance Capacitance Coil discharge QH discharge

Test phase

code

PBC X X X

PBR X X X

PAR X X X

PAI X X X X

PAIWI X X X X

BC X X X X X X

AC X X X X X X

UL X X

AW X X X X X X

AL X X X X X X

AI X X X X X X

FINAL X X X X X X

Click here to add footer 25

Click here to add footer 26

Plan for power tests coldbull RRR and strain gauge measurementsbull Preliminary tests ndash Setup protection ndash Splice resistance

measurements (current plateaus at 2 4 6 8 and 10 kA) ndash 3 hoursbull Training 43 K ndash 15 quenches ndash 3 days bull Training 19 K ndash 10 quenches ndash 25 days

Stability on current plateau ndash 05 daybull Ramp-rate study 100 As and 50 As ndash 05 day

AC-loss measurements (includes inductance measurement) at 5 to 100 As ndash 05 day

bull Quench heater efficiency study 3 different settings of QH pulse for 3 currents each Long re-cooling of the magnet due to delay of energy extraction ndash 3 days

bull High MIIts tests (protection delay) 6 quenches ndash 3 days

bull Quench propagation velocity measurements acquired for the training quenches

G Willeringbull Cool down bull Day 1

bull Day 2-4bull Day 5-7

bull Day 8

bull Day 9-11

bull Day 12-14

Click here to add footer 27

Further actionsbull After cold tests warm magnetic

measurements will be carried out with the two coils connected

bull Model 1 MBHSP101 single aperture with cable OST RRP 108127 for both polesbull Instrumentation of coils 106 and 107 going onbull Collaring scheduled around middle of June

  • CERN-FNAL Video Meeting 12 Progress of the 11T Dipole short m
  • Contributions
  • Main design features
  • Specific features
  • Assembly conditions - Winding
  • Binder curing
  • Reaction treatment
  • Reaction treatment ndash Coil 105
  • Impregnation
  • Instrumentation outer layer
  • Instrumentation inner layer
  • Quench heaters
  • Coils size
  • Excess in mid-plane
  • Collaring steps
  • Shimming plan
  • Yoking welding of the shells
  • Structural analysis vs measurements
  • FEA Results
  • ANSYS Forecast at 11-Tesla
  • Bullet gauges loading
  • Electrical tests ndash When
  • Electrical tests ndash What
  • Electrical tests
  • Slide 25
  • Plan for power tests cold
  • Further actions
Page 25: CERN MBHSM0101 general  status F. Savary on behalf of the 11T Dipole Project Team

Click here to add footer 25

Click here to add footer 26

Plan for power tests coldbull RRR and strain gauge measurementsbull Preliminary tests ndash Setup protection ndash Splice resistance

measurements (current plateaus at 2 4 6 8 and 10 kA) ndash 3 hoursbull Training 43 K ndash 15 quenches ndash 3 days bull Training 19 K ndash 10 quenches ndash 25 days

Stability on current plateau ndash 05 daybull Ramp-rate study 100 As and 50 As ndash 05 day

AC-loss measurements (includes inductance measurement) at 5 to 100 As ndash 05 day

bull Quench heater efficiency study 3 different settings of QH pulse for 3 currents each Long re-cooling of the magnet due to delay of energy extraction ndash 3 days

bull High MIIts tests (protection delay) 6 quenches ndash 3 days

bull Quench propagation velocity measurements acquired for the training quenches

G Willeringbull Cool down bull Day 1

bull Day 2-4bull Day 5-7

bull Day 8

bull Day 9-11

bull Day 12-14

Click here to add footer 27

Further actionsbull After cold tests warm magnetic

measurements will be carried out with the two coils connected

bull Model 1 MBHSP101 single aperture with cable OST RRP 108127 for both polesbull Instrumentation of coils 106 and 107 going onbull Collaring scheduled around middle of June

  • CERN-FNAL Video Meeting 12 Progress of the 11T Dipole short m
  • Contributions
  • Main design features
  • Specific features
  • Assembly conditions - Winding
  • Binder curing
  • Reaction treatment
  • Reaction treatment ndash Coil 105
  • Impregnation
  • Instrumentation outer layer
  • Instrumentation inner layer
  • Quench heaters
  • Coils size
  • Excess in mid-plane
  • Collaring steps
  • Shimming plan
  • Yoking welding of the shells
  • Structural analysis vs measurements
  • FEA Results
  • ANSYS Forecast at 11-Tesla
  • Bullet gauges loading
  • Electrical tests ndash When
  • Electrical tests ndash What
  • Electrical tests
  • Slide 25
  • Plan for power tests cold
  • Further actions
Page 26: CERN MBHSM0101 general  status F. Savary on behalf of the 11T Dipole Project Team

Click here to add footer 26

Plan for power tests coldbull RRR and strain gauge measurementsbull Preliminary tests ndash Setup protection ndash Splice resistance

measurements (current plateaus at 2 4 6 8 and 10 kA) ndash 3 hoursbull Training 43 K ndash 15 quenches ndash 3 days bull Training 19 K ndash 10 quenches ndash 25 days

Stability on current plateau ndash 05 daybull Ramp-rate study 100 As and 50 As ndash 05 day

AC-loss measurements (includes inductance measurement) at 5 to 100 As ndash 05 day

bull Quench heater efficiency study 3 different settings of QH pulse for 3 currents each Long re-cooling of the magnet due to delay of energy extraction ndash 3 days

bull High MIIts tests (protection delay) 6 quenches ndash 3 days

bull Quench propagation velocity measurements acquired for the training quenches

G Willeringbull Cool down bull Day 1

bull Day 2-4bull Day 5-7

bull Day 8

bull Day 9-11

bull Day 12-14

Click here to add footer 27

Further actionsbull After cold tests warm magnetic

measurements will be carried out with the two coils connected

bull Model 1 MBHSP101 single aperture with cable OST RRP 108127 for both polesbull Instrumentation of coils 106 and 107 going onbull Collaring scheduled around middle of June

  • CERN-FNAL Video Meeting 12 Progress of the 11T Dipole short m
  • Contributions
  • Main design features
  • Specific features
  • Assembly conditions - Winding
  • Binder curing
  • Reaction treatment
  • Reaction treatment ndash Coil 105
  • Impregnation
  • Instrumentation outer layer
  • Instrumentation inner layer
  • Quench heaters
  • Coils size
  • Excess in mid-plane
  • Collaring steps
  • Shimming plan
  • Yoking welding of the shells
  • Structural analysis vs measurements
  • FEA Results
  • ANSYS Forecast at 11-Tesla
  • Bullet gauges loading
  • Electrical tests ndash When
  • Electrical tests ndash What
  • Electrical tests
  • Slide 25
  • Plan for power tests cold
  • Further actions
Page 27: CERN MBHSM0101 general  status F. Savary on behalf of the 11T Dipole Project Team

Click here to add footer 27

Further actionsbull After cold tests warm magnetic

measurements will be carried out with the two coils connected

bull Model 1 MBHSP101 single aperture with cable OST RRP 108127 for both polesbull Instrumentation of coils 106 and 107 going onbull Collaring scheduled around middle of June

  • CERN-FNAL Video Meeting 12 Progress of the 11T Dipole short m
  • Contributions
  • Main design features
  • Specific features
  • Assembly conditions - Winding
  • Binder curing
  • Reaction treatment
  • Reaction treatment ndash Coil 105
  • Impregnation
  • Instrumentation outer layer
  • Instrumentation inner layer
  • Quench heaters
  • Coils size
  • Excess in mid-plane
  • Collaring steps
  • Shimming plan
  • Yoking welding of the shells
  • Structural analysis vs measurements
  • FEA Results
  • ANSYS Forecast at 11-Tesla
  • Bullet gauges loading
  • Electrical tests ndash When
  • Electrical tests ndash What
  • Electrical tests
  • Slide 25
  • Plan for power tests cold
  • Further actions