case study st patrick’s cathedral - armatile architectural...st. patrick’s cathedral, armagh –...
TRANSCRIPT
Case Study
St Patrick’s Cathedral
ST. PATRICK’S CATHEDRAL, ARMAGH – Tiling & Mosaic Contract
PROJECT DURATION - NOVEMBER 2002 – 26TH MAY 2003
The work we completed for the extensive refurbishment of St. Patrick’s Cathedral,
Armagh was the most significant conservation and restoration project in Ireland in
recent years. One of the most important factors in the winning of the contract to supply
material to this project, was the extent of our manufacturing facility. You will find below
a case study of this project. The intention here is to provide a detailed analysis of the
approach we take with these complex projects.
PROJECT ARCHITECT - P & B GREGORY ARCHITECTS, Belfast
SANCTUARY DESIGN - ROONEY & McCONVILLE ARCHITECTS, Belfast
We manufactured product for use in a number of areas for this project:
• The Sanctuary
• The Baptistery
• The Synod Hall Washrooms
I have detailed the work involved in each area below:
THE SANCTUARY
The responsibility for the design in this area lay with Brian Quinn of Rooney &
McConville Architects (Belfast). In our initial discussions with Brian Quinn concerning
the design, we told him that if he can draw it, we can cut it – he took us at our word.
The design that was presented to us incorporated some very detailed and intricate
patterns. As a result of the various cutting technologies we possess and our previous
experience in this field, we were able to deliver these intricate designs without
compromising on the architects’ original vision. The design of this area was made up of
several different schemes and I have dealt with each individually below.
Celtic Pathways
The original mosaic work that exists in the Cathedral portrays a Celtic theme and the
new design set out to echo this theme. Whereas originally the design had been achieved
through the use of extensive mosaic work, it was decided that given the time constraints
on the project, waterjet technology would allow us to produce Brian Quinn’s new design
to the highest standard possible and in the required time frame.
The first job here was to select the appropriate materials for the project to marry the
new design with the original mosaic work. After careful consideration over many weeks
the material chosen was Italian porcelain stoneware from Italian manufacturers,
Floorgres,
The design on the main Sanctuary floor was also repeated in the surrounding areas. It
was decided that in order to highlight the main Sanctuary and make it stand out we
would use a polished finish here and a Matt finish on the surrounding areas.
You can see from the image above that the Celtic pathways form a cross leading to the
altar in the centre of the Sanctuary. The material chosen as infill for these areas was
polished 45x45cm porcelain stoneware from the Chromwork range by Floorgres. The
design on the tiles you see here is a process we have developed to create the
impression of cuts in the tile. When grouting is completed on these pieces, they appear
to be cut. The purpose of this process is to provide for ease of fitting – each tile can be
fitted as one piece.
While considering the design for this area, careful consideration was given to each and
every aspect of the design. The exact area that we had to cover was considered in
determining the dimensions of the pathways on the Sanctuary. Every effort was made
to ensure that when laid, there would be no small or irregular pieces needed to fill in
around the edges of the design. Only half and quarter tiles were used. The cutting
technologies we possess at our manufacturing facility allow us to factor these
considerations into the design and ensure that every aspect affecting the aesthetics of
the job has been taken into account. The size of the 45x45cm polished tiles was set, but
we were able to manipulate the design of the pathways to help us reach the desired
conclusion.
Another area of the Sanctuary design where this precise approach was taken was with
the polished marble that is featured on it’s steps. There are a number of pillars situated
around the Sanctuary and some of these encroach onto the steps. In order to ensure a
neat finish on these steps we utilised our waterjet cutting facility. We were able to take
templates of the parts of the steps affected by the pillars, take them back to our
manufacturing facility and the required marble pieces were cut to fit. Without the use of
this approach it would have been necessary to cut several small pieces at the foot of the
pillars in order to complete the fitting right up to the pillar. This would have again
affected the overall aesthetics of the Sanctuary. This particular aspect of the service
Armatile offer is unique in the Contracts field in Ireland – not only because of the
technology required to achieve the above results, but as a result of the high level of skill
and experience that is needed to ensure the successful completion of this work
Original mosaic piece
We were also responsible for the manufacture of an original mosaic piece that is
featured behind the Sanctuary. This piece came from a drawing that the Clerk of Works,
Mr. Gerry Gribben, had discovered at the outset of the project. It is believed that this
piece was intended for use in the original construction of the Cathedral, but for some
reason it had not been included. The architects on the project decided they would like
to use this piece in the restoration.
We took the drawing back to our design team, sourced materials to use in the piece and
after careful consideration it was again decided that porcelain stoneware from Floorgres
represented the best material to use for this piece, although it also included some real
gold mosaics. In terms of the actual manufacture of this particular piece, it is a
combination of traditional mosaic and waterjet cutting. The piece measures 3.2m in
length, contains 12,000 mosaic pieces (14mm x 14mm & 10mm x 10mm) and 200
waterjet cut pieces.
The large mosaic was assembled on a mesh in one piece at our factory. Upon
completion it was then cut into seven sections which were individually labeled and the
installers were given detailed instructions concerning the fitting of this piece. The actual
fitting of the piece on site took 2 hours for 2 men. The process of assembling this piece
at our factory and delivering it to site in a series of meshed sections offers dramatic time
savings in terms of the time spent fitting the piece.
Archbishop’s Coat of Arms
On the upper level of the Sanctuary there is a repeat of the Celtic pathway that leads to
the Cathedra. In the centre of this pathway there is a waterjet cut emblem of the
Archbishop’s Coat of Arms. This piece was commissioned by Archbishop Sean Brady.
This emblem measures 800mm diameter and contains some 250 waterjet cut pieces.
This piece was manufactured in one piece and fitted in 10 minutes.
Cathedra
There is also a design cut on the raised area where the Cathedra is placed. This
particular piece is manufactured from polished marble. This particular piece was an
original design by Armatile and was designed to fit in with the original design work by
Brian Quinn. We again used waterjet cutting to create this design.
THE SYNOD WASHROOMS
There is an old Victorian style floor design in the entrance to the Synod Hall. This design
continued into the washrooms just off this entrance hall. While the floor in the entrance
hall remained in good condition, the floor in the washroom area had become badly
damaged and had to be replaced.
We have come across a situations like this before, the most notable being in the
refurbishment of Stormont Castle in Belfast in 2001 – the home of the Northern Ireland
Parliament buildings. The architects had been trying for several months to locate
someone who could supply a new floor similar to the original without any success. They
then approached us with a sample of a Victorian encaustic design and asked for it to be
reproduced. This work involved the complete removal of the old damaged floor and the
laying of our new design.
This Cathedral was potentially more problematic in that our new design was to be laid
beside the original floor. If the old floor is being completed replaced, there is some
room for maneuver concerning the design and colour scheme – it does not have to be
an exact match. However, in this instance we were faced with having to find an exact
match to the original floor.
The original floor had been manufactured from encaustic tiles. This is an old and lengthy
process and the cost can be prohibitive. We realised from previous experience with this
type of material that waterjet technology presented a more efficient alternative in
terms of both time and cost.
The first task of our production and design team was to identify material to be used for
the reproduction of the floor. We set about producing several lab samples to present to
the client and after much consideration agreement was reached on a colour scheme.
Given the complexities of this project we were able to match the colours from the
Progetto range from Floorgres. This is an extensive range of porcelain stoneware in a
wide variety of colours and is the material we use to produce our own Cathedral range
of Victorian style flooring.
The final material was produced on a repeating series of mesh-mounted panels which
offers savings in terms of labour time and therefore cost. We also manufactured borders
to run around the outside of the design – again, an exact replica of the original floor in
the entrance hall. In addition to this there were a number of hand decorated borders
used with the wall tiles featured in this area.
THE BAPTISTERY
At a late stage in the restoration it was decided to rearrange the Baptistery to bring it
into line with current Liturgy. This entailed re-siting the Baptismal Font in the centre and
the removal of balustrades. Once this had been done half the floor was concrete and
the other half was an original mosaic design.
The Restoration Committee were faced with two problems – time and cost. With this in
mind we again set about producing a number of lab samples for approval. To the
surprise of the Restoration Committee we were able to reproduce the original floor with
a combination of mosaic and waterjet cut pieces in our factory well within their budget
and on time. The floor was assembled on a repeating series of mesh-mounted panels as
with the Synod Washrooms. This approach offered considerable time savings over the
alternative of installing the mosaic work piece by piece on site.
The emphasis in this particular area was to create the impression that the original floor
had simply been restored. Since the completion of the project, several parishioners have
commented that they are particularly pleased that this floor did not need to be replaced
which would indicate that our objective has been achieved.
Adhesives & Grouts
All adhesives & grouts used on this project were supplied by Evode Industries (Ireland).
All products came from the Evo-Stik Technik range.
CONCLUSION
From the work outlined here it can be seen that conservation and restoration projects
require a wholly different approach to any other commercial contract. In the vast
majority of cases, the maintenance of the original features in the building is the Primary
concern. However, what is also apparent from our experience in this field is that in most
cases there are some aspects of the original design that are simply too badly damaged
to be refurbished. It is in situations like this where the modern cutting technologies we
possess can allow for the effective reproduction of old designs to a standard that makes
them indistinguishable from the original. The technology itself does not provide the
answer. The whole process of identifying alternatives to the original materials used and
knowing how this material will respond to the various treatments they will be subjected
to requires considerable experience in this area. The work we have completed at St.
Patrick’s Cathedral demonstrates that we have the level of experience required to
complete projects such as this to the high standard that is required and on time.
It is also important to remember that the type of work outlined above is not solely
applicable to conservation & restoration projects. All the techniques and technologies
that have been employed on this project present architects and designers with
unrestricted design possibilities on the full range of commercial projects. As with the
Cathedral project, this ensures the delivery of a unique tile design concept that is
tailored to the specific needs of each individual job.
Contact Details;
Armatile
Station Road Industrial Estate
Loughgall Road
Armagh
Northern Ireland
United Kingdom
BT61 7NP
Tel: 028 37527007 (Head Office)
Tel: 0207 1111 613 (London Office)
Email: [email protected]
Web: www.armatile.com