case study, results & discussion -...
TRANSCRIPT
159
Chapter 7
CASE STUDY, RESULTS & DISCUSSION
160
Chapter 7CASE STUDY, RESULTS & DISCUSSION
7.0. INTRODUCTION
The developed model can be used in the block replacement
decisions for a bock of Computers, a block of LCD televisions in hotel
industry, a block of air conditioners, a block of pressure gauges in
filling plants etc.
In this work, a case study is done with reference to a block of
Computer and computer based system. The results of the case study
are presented in the following sections.
7.1 CASE STUDY: Computer And Computer Based System
With the advent of Computers and the widespread of the
internet and fibre optics network across the world, the huge
population comprising good number of unemployed Indian youth
provided a platform for MNCs to open up their ICT branches in India.
Also Banking, Insurance, Railways, Corporate houses etc. are
becoming IT savvy and using computers in large scale for their
operations. Consequently the decisions on capital investment on
Computer and Computer based system became important and a need
for scientific approach for the replacement decisions is felt.
In this study a block of 1000 computers is considered. Though
it is difficult to identify the specific repairable intermediate states, to
make the model simplistic the repairs are grouped as follows:
161
Minor Repairs: Non-working of USB ports, keyboard, mouse, color
flickering, network card connections, LAN card, etc.,
Major repairs: Non-working of mother-board, monitor,
XGA/SVGA/VGA cards, SMPS, memory modules, processor
overheating, etc.,
State of the item: Status of the computer system at a particular
time period is considered as the state of the system.
As two intermediary states are considered between working and
complete failure states, the states can be defined as follows:
State 1: The item (Computer) is in working condition
State 2: The item (Computer) is in minor repairable condition
State 3: The item (Computer) is in major repairable condition
State 4: The item (Computer) is in complete failure
This leads to four-state discrete-time Markov chain with the
following state transition or state space diagram (Fig. 7.1)
Fig. 7.1: State transition or space diagram
1
3 4
2
162
7.1.1 Block Replacement Decision Using First Order Markov
Chain:
N=1000 computers
1C =Individual replacement cost = Rs.40000
2C = Minor repair cost=Rs.1000
3C = Major repair cost= Rs.8000
4C =each item cost under group replacement=Rs.30000/computer
nr =Nominal rate of interest=20%=0.2
020.0045.0085.0850.0XXXXX IV0
III0
II0
I00
Generator of Markov Process, TPM,
10004000.02222.02000.01778.00824.01059.01294.06824.00294.00388.00494.08824.0
P
At the end of the first period, the state probabilities can be calculated
from
PXX 01 )PXX( n0n
44434241
34333231
24232221
14131211
IV0
III0
II0
I0
IV1
III1
II1
I1
PPPPPPPPPPPPPPPP
XXXXXXXX
(where I,II, III & IV represents functional, minor repairable, major
repairable and complete failure states respectively; and Pij = Probability
of items switching over from ith state to jth state in a period)
10004000.02222.02000.01778.00824.01059.01294.06824.00294.00388.00494.08824.0
020.0045.0085.0850.0
163
The transition probabilities for the future time periods are calculated
based on the first order Markov process.
The state probabilities of items at any time period ‘n’ can be computed
as = (probability of items in different states in initial period) X nTPM
i.e. n0n PXX , n=1,2,3,…
OCTAVE software is used to calculate the probabilities of items falling
in different states for future periods (Appendix I ).
The transition and state probabilities for future time periods
and the respective number of failures (n), minor repairs (n) and
major repairs (n) are shown in Appendix II.
The calculations for the replacement decision (without the
influence of Inflation) using first order Markov Chain are shown on
Table 7.1.
Period
(n)
IndividualReplacement cost=n*C1
MinorRepaircost =n*C2
Majorrepair cost
= n*C3
Maintenance
cost(R)R
(lacs)
Groupreplacement cost= N * C4
Total cost(lacs)
AnnualAverage
cost(lacs)
1 27.96 0.61 4.15 32.73 32.73 300.00 332.73 332.732 49.87 0.62 4.19 54.69 87.42 300.00 387.42 193.713 73.75 0.63 4.19 78.58 166.00 300.00 466.00 155.334 100.68 0.63 4.19 105.52 271.53 300.00 571.53 142.885 132.03 0.64 4.19 136.86 408.39 300.00 708.39 141.676 169.33 0.64 4.18 174.17 582.56 300.00 882.56 147.097 214.30 0.65 4.17 219.13 801.70 300.00 1101.70 157.388 269.13 0.65 4.17 273.96 1075.66 300.00 1375.66 171.95
Table 7.1: Computations for block replacement model without theinfluence of Inflation using FOMC
As the average annual cost over a period of 5 years is minimum
and started increasing from 6th year onwards, it can be inferred that
economics can be achieved if the block replacement is done at the end
of 5th year.
164
7.1.2 Influence Of Forecasted Inflation On Block Replacement
Decision Using First Order Markov Chain
Price Inflation for Computer and Computer Based System in
India is studied and forecasted. A regression forecasting model with
trigonometric function is developed to accommodate the cyclical
fluctuations of real time inflation pattern. For this purpose Price
Inflation (based on WPI) for Computer and Computer based system
over a period of time is studied, forecasted and compared with actual
values for the known periods (Sec. 6.5.1).
The developed regression equation is:
π/4)π.5802sin(t59.0369t2.512Ft
Further to this, the Price Inflation for Computer and Computer
based system for the forthcoming time periods is predicted by the
developed Regression model with trigonometric function, which
yielded relatively minimal errors and are tabulated in the Table 6.7
and plotted in the Fig . 6.2.
The forecasted inflation ( tφ ) data thus obtained is used to
calculate the real value of money (or real rate of interest) by
Fisherman’s relation. This real rate of interest is used to calculate
Present worth Factor (PWF).
Real interest rate= tr = t
tn
φ1φr
, from Fisherman’s relation
And for the same data considered in the above section i.e. in
Sec. 7.1.1, the calculation of various costs for replacement decision
165
under the influence of inflation and time value of money using first
order Markov chain is shown in Table 7.2.
1 2 3 4 5 6 7
Period (n) Inflation, (%)
Real rate ofinterest, rt =
(rn - t ) /(1 + t )
PWF, =
1/(1+ rt )
Discountfactor (n-1) n-1 Ind. Replacement
cost= n*C1 * n-1
1 -18.56 0.473 0.679 1 1 27.962 -17.41 0.453 0.688 0.6882 1.6882 34.323 -0.49 0.206 0.829 0.6876 2.3759 50.714 0.65 0.192 0.839 0.5900 2.9659 59.4125 17.58 0.021 0.980 0.9217 3.8877 121.696 18.72 0.011 0.989 0.9477 4.8355 160.497 35.65 -1.115 1.130 2.086 6.9220 447.158 36.8 -0.123 1.140 2.502 9.4243 673.43
8 9 10 =(7+8+9) 11 12 13 = (11+12) 14 = (13/6)
MinorRepair cost
=n*C2 * n-1
Majorrepair cost
=n*C3*n-1
Maintenancecost(R)(in lacs)
R(in lacs)
Groupreplacement
cost =N* C4* n-1
Total cost(TC)
(in lacs)
Weightedaverage annual
cost(Rs. in lacs)
0.61 4.15 32.73 32.73 300.00 332.73 332.730.43 2.88 37.64 70.37 206.47 276.84 163.980.43 2.88 54.04 124.41 206.29 330.70 139.190.37 2.47 62.26 186.67 177.01 363.69 122.620.59 3.86 126.15 312.83 276.52 589.35 151.590.61 3.96 165.07 477.91 284.33 762.24 157.631.36 8.71 457.23 935.14 625.96 1561.11 225.521.64 10.4 685.53 1620.68 750.68 2371.36 251.62
Table 7.2: Computations for block replacement model with theinfluence of Inflation using FOMC
As the average annual cost over a period of 4 years is minimum
and started increasing from 5th year onwards, it can be inferred that
economics can be achieved if the block replacement is done at the end
of 4th year.
i.e. when the inflation with up-trend is considered, the optimal
block replacement period is advanced to 4th year from 5th year.
166
7.1.2.1 Influence of Forecasted Inflation on Block replacement
decision using Second Order Markov chain
N=1000 computers
1C =Individual replacement cost = Rs.40000
2C = Minor repair cost=Rs.1000
3C = Major repair cost= Rs.8000
4C =each item cost under group replacement=Rs.30000/computer
nr =Nominal rate of interest=20%=0.2
Real interest rate= tr = t
tn
φ1φr
, from Fisherman’s relation
020.0045.0085.0850.0XXXXX IV0
III0
II0
I00
To generate/estimate state transition probabilities for future periods,
Weighted Moving Transition Probability Method (WTPM), a
parsimonious model that approximates second order Markov chain is
employed.
Generators of Markov process (TPMs) are
10004000.02222.02000.01778.00824.01059.01294.06824.00294.00388.00494.08824.0
P 2-n 0.2δ, 2n
10005105.00774.00791.03328.01554.00637.00716.07092.00749.00480.00577.08192.0
P 1-n 0.8δ, 1n
167
The state probabilities of items in different states can be computed as
= (probability of items in different states in initial period) X nTPM
i.e. nij0n PXX , where n=1,2,3,…
The transition and state probabilities for future time periods and the
respective number of failures(n), minor repairs (n) and major repairs
(n) are shown in Appendix IV.
The forecasted inflation data (refer Sec. 6.5.1, Table 6.7) is used
to calculate the real value of money (or real rate of interest) by
Fisherman’s relation. This real rate of interest is used to calculate
Present Worth Factor (PWF).
And the calculation of various costs for block replacement
decision under the influence of inflation and time value of money
using second order Markov chain is shown in Table 7.3.
As the weighted average annual cost over a period of 4 years is
minimum and started increasing from 5th year onwards, it can be
inferred that economics can be achieved if the block replacement is
done at the end of 4th year.
i.e. when the inflation with up-trend is considered, the optimal
block replacement period (using SOMC also) is advanced to 4th year
from 5th year.
168
1 2 3 4 5 6 7
Period(n)
Inflation, (%)
Real rate ofinterest, rt =
(rn - t ) /(1 + t )
PWF, =
1/(1+ rt )
Discountfactor (n-1) n-1 Ind. Replacement
cost= n*C1 * n-1
1 -18.56 0.473 0.679 1 1 27.962 -17.41 0.453 0.688 0.6882 1.6882 34.323 -0.49 0.206 0.829 0.6876 2.3759 34.924 0.65 0.192 0.839 0.5900 2.9659 33.835 17.58 0.021 0.980 0.9217 3.8877 58.336 18.72 0.011 0.989 0.9477 4.8355 66.527 35.65 -0.115 1.130 2.0865 6.9220 162.258 36.8 -0.123 1.140 2.5022 9.4243 215.62
8 9 10 =(7+8+9) 11 12 13 =
(11+12) 14 = (13/6)
Minor Repaircost =n*C2 * n-1
Major repaircost =n*C3*n-1
Maintenance cost(R)
(lacs)R
(lacs)
Groupreplacement
cost =N* C4* n-1
Total cost(TC)
(in lacs)
Weightedaverage annual
cost(Rs. in lacs)
0.61 4.15 32.73 32.73 300.00 332.73 332.730.43 2.88 37.64 70.37 206.47 276.84 163.980.45 3.05 38.43 108.80 206.29 315.10 132.620.41 2.74 36.99 145.80 177.01 322.82 108.840.69 4.50 63.53 209.33 276.52 485.85 124.970.75 4.86 72.14 281.47 284.33 565.81 117.011.75 11.24 175.25 456.72 625.96 1082.69 156.412.22 14.16 232.01 688.74 750.68 1439.42 152.73
Table 7.3: Computations for block replacement model with theinfluence of Inflation using SOMC
When the influence of predicted inflation and net worth of the money
is considered, both ways using FOMC and SOMC resulted in the early
replacement of block of computers at the age of 4 years.
Note:A detailed discusion on the results is made in section 7.1.4.
169
7.1.3 Reengineering Treatment On Block Replacements
Table 7.3 shows that the block of computers should be replaced
at the end of 4th year. However this section looks into the possibility of
extending the optimal block replacement age by reengineering the
computer hardware in lieu of replacement option using thin client
technology. Thin client is a generic term for a group of emerging
technologies that reduces costs of hardware, maintenance and
support. Thin client solution can be very well used in IT intensive
banking, insurance, railways etc.
Thin client card, is a PC networking solution to computer
maintenance problems. It will make the maintenance department free
from regular upgradations and maintenance related issues. Also it
makes possible to run latest software on old PCs (P-1/P-II/P-III/P-
IV/celeron/AMD). Thin client solution shows dramatic experience in
the “cost saving” and “Performance enhancement”.
With the following given data, Table 7.4 and Table 7.5 gives the
average annual cost of block replacement without and with
reengineering using second order Markov chain respectively.
Withoutreengineering
Withreengineering
Total number of items in the system N=1000 N=1000Individual replacement cost per unit C1 = Rs.40000 C1r = Rs.30000Minor repair cost C2 = Rs. 1000 C2r = Rs.1000Major repair cost C3 =Rs. 8000 C3r = Rs.8000Group replacement cost (per computer) C4 = Rs.30000 C4r = Rs.30000Reengineering cost*** (Table 7.3B) ---- Cr =Rs.2200000Nominal rate of interest
nr 28% nr 28%
Table 7.3A: Data for reengineering treatment calculations
170
*** Note 1: Break-up for reengineering cost:
Item descriptionQuantity required for
1000 computers netwrok
Each item
cost (Rs.)
Total cost
(Rs.)
Thin client cards(1 card for every clientcomputer)
1000 Nos. 1300 1300000
1 GB RAM at the server side forevery 10 client computer systems
100 Nos. 4000 400000
Server capacity enhancement &installation charges(1 server for every 100 clientcomputers)
10 Nos. 50000 500000
Total reengineering cost = Rs. 22.00 lacs 2200000Table 7.3B: Break-up for reengineering cost
Note 2: As reengineering is aimed at the extension of optimal block
replacement age beyond 4th year (Table 7.3), reengineering will be
done at the end of 4th year. Therefore forecasted inflation from 5th year
onwards (Table 6.7) is employed.
The calculations for the optimal decision without reengineerng
(but replacement at the end of 4th year) are made in following section
Sec.7.1.3.1 and the calculations with reengneering are made in
Sec.7.1.3.2.
171
7.1.3.1 Forecasted Inflation Based Block Replacement Decision
Without Reengineering Using Second Order Markov Chain
020.0045.0085.0850.0XXXXX IV0
III0
II0
I00
To generate/estimate state transition probabilities for future
periods, weighted Moving Transition Probability Method (WTPM), a
parsimonious model that approximates second order Markov chain is
employed.
In case of replacement without reengineering, it is considered to
be the regeneration point of whole life where the operating cost
function initially starts. Therefore the transition probabilities
(Appendix IV) that are considered for the new computer systems are
taken into account here also.
Generators of Markov process (TPMs) are
10004000.02222.02000.01778.00824.01059.01294.06824.00294.00388.00494.08824.0
P 2-n 0.2δ, 2n
10005105.00774.00791.03328.01554.00637.00716.07092.00749.00480.00577.08192.0
P 1-n 0.8δ, 1n
The transition and state probabilities for future time periods
and the respective number of failures (n), minor repairs (n) and
major repairs (n) are shown in Appendix IV.
172
The average annual block replacement cost is computed in
Table 7.4.
1 2 3 4 5 6 7
Period (n) Inflation, (%)
Real rate ofinterest, rt =
(rn - t ) /(1 + t )
PWF, =
1/(1+ rt )
Discountfactor (n-1) n-1 Ind. Replacement
cost= n*C1 * n-1
1 17.58 0.089 0.919 1 1 27.962 18.72 0.078 0.928 0.9275 1.9275 46.253 35.65 -0.056 1.060 1.1231 3.0506 57.034 36.8 -0.064 1.069 1.2207 4.2713 70.005 53.73 -0.167 1.201 2.0806 6.3519 131.67
8 9 10 =(7+8+9) 11 12 13 =
(11+12) 14 = (13)/(6)
Minor Repaircost =n*C2 * n-1
Major repair cost= n*C3*n-1
Maintenancecost(R)(lacs)
R(lacs)
Groupreplacement
cost = N* C4*n-1
Total cost(TC)
(in lacs)
Weightedaverage annual
cost(Rs. in lacs)
0.61 4.15 32.73 32.73 300.00 332.73 332.730.57 3.88 50.72 83.45 278.25 361.70 187.650.75 4.98 62.76 146.22 336.93 483.15 158.380.86 5.67 76.54 222.77 366.22 588.99 137.891.55 10.16 143.40 366.17 624.18 990.36 155.91
Table 7.4: Computations for block replacement modelwithout reengineering
As the average annual cost over a period of 4 years is minimum
and started increasing from 5th year, it can be inferred that economics
can be achieved if the block replacement is done at the end of 4th year.
173
7.1.3.2 Forecasted Inflation Based Block Replacement Decision
WITH REENGINEERING Using Second Order Markov Chain
To generate/estimate state transition probabilities for future
periods, weighted Moving Transition Probability Method (WTPM), a
parsimonious model that approximates second order Markov chain is
employed
The initial state transition probabilities (X0 ) for the
reengineering model are considered as
I II III IV0 0 0 0 0X X X X X 0.780 0.087 0.073 0.060
In case of replacement with reengineering, as the maintenance
related issues are relatively less, the following Markov process
generators (TPMs) are assumed.
Generators of Markov process (TPMs) are
n-2
0.9718 0.0205 0.0038 0.00380.8966 0.0575 0.0345 0.0115
P0.8767 0.0685 0.0274 0.02740.0000 0.0000 0.0000 1.0000
0.2δ, 2n
n-1
0.9526 0.0308 0.0115 0.00510.8621 0.0805 0.0345 0.0230
P0.8493 0.0822 0.0411 0.02740.0000 0.0000 0.0000 1.0000
0.8δ, 1n
The transition and state probabilities for future time periods
and the respective number of failures (n), minor repairs (n) and
major repairs (n) are shown in Appendix VI.
174
The average annual optimal block replacement cost is computed
in Table 7.5.
1 2 3 4 5 6 7 8
Period(n)
Inflation, (%)
Real rate ofinterest, rt =
(rn - t ) /(1 + t )
PWF, =
1/(1+ rt )
Discountfactor (n-1) n-1
Initial cost ofre-
engineering(lacs)
Ind.Replacement
cost= n*C1*n-1
1 17.58 0.089 0.919 1 1 22.00 20.272 18.72 0.078 0.928 0.9275 1.9275 --- 20.093 35.65 -0.056 1.060 1.1231 3.0506 --- 25.974 36.8 -0.064 1.069 1.2207 4.2713 --- 30.145 53.73 -0.167 1.201 2.0806 6.3519 --- 54.85
9 10 11 =(7+8+9+10) 12 13 14 =
(12+13) 15 = (14)/(6)
Minor Repaircost =n*C2 * n-1
Major repaircost =n*C3*n-1
Maintenancecost(R)(lacs)
R(lacs)
Groupreplacementcost = N*C4*n-1
Total cost(TC)
(in lacs)
Weighted averageannual cost(Rs. in lacs)
0.34 1.08 43.70 43.70 300.00 343.70 343.700.33 1.04 21.47 65.18 278.25 343.43 178.170.42 1.27 27.67 92.85 336.93 429.78 140.880.47 1.40 32.02 124.87 366.22 491.10 114.970.84 2.42 58.11 182.99 624.18 807.18 127.07
Table 7.5: Computations for block replacement model withreengineering
The average annual block replacement cost (Rs.93.86 lacs) is
minimum during 4th year. This is less than the average annual block
replacement cost (Rs.137.89 lacs, Table 7.4) without reengineering.
Therefore, it is suggestible to go for reengineering the computer
network with Thin client technology at the end of 4th year and replace
the block of computers at the end of 8th year (4 years from Table 7.3
before reengineering + 4 years from Table 7.5 after reengineering).
175
7.1.4 RESULTS AND ANALYSIS:Table 7.6 and Fig. 7.2 furnish the summary of numerical results
obtained (Table 7.1, Table 7.2 and Table 7.3) for block replacement
decision calculated using - first order Markov chain with and without
inflation, and Weighted Moving Transition Probability (WMTP)
methods.
Timeperiod (n
years)
Weighted Av. Annual Cost (lacs)
Using First Order Markov ChainUsing WMTP for
second orderMarkov chain
without inflation with inflation with inflation1 332.73 332.73 332.732 193.71 163.98 163.983 155.33 139.19 132.624 142.88 122.62 108.845 141.67 151.59 124.976 147.09 157.63 117.017 157.38 225.52 156.418 171.95 251.62 152.73
Table 7.6: Numerical results for weighted average annual costs (withconstant maintenance cost)
Fig. 7.2 Weighted Average Cost per Year (withconstant maintenance cost)
0
50
100
150
200
250
300
350
1 2 3 4 5 6 7 8Time period (years)
Ave
rage
cos
t ( in
lacs
) per
yea
r
FOMC withoutInflationFOMC with Inflation
SOMC with Inflation
176
When the influence of inflation is not considered, First
Order Markov Chain (FOMC) model resulted in the replacement age
as 5 years.
When the influence of predicted inflation and net worth
of the money is considered, both ways using FOMC and SOMC
resulted in the early replacement of block of computers at the age of
4 years i.e. when the inflation with up-trend is considered, the
optimal block replacement period is advanced to 4th year from 5th
year.
If the decision would have been taken without
considering the influence of inflation and money value, it might be
required to allocate and incur huge amounts on maintenance.
In modern economy with the increased business activity,
Inflation, dominantly, is playing a macro economic role influencing the
replacement decisions. If the macro economic variables such as
inflation are not considered in decision-making, service systems
particularly in the field of computers will face pathetic conditions and
incur heavy losses.
When the influence of inflation is considered, WMTP technique
resulted in optimal replacement age as 4 years with less annual
average cost of (Rs.108 lacs) comparative with first order Markov
chain model.
Therefore, for the block of the computers considered for study in
this work, 4 years is the optimal replacement period.
177
However the reengineering at the end of 4th year with thin client
technology in lieu of replacement resulted in reduction in average
annual block replacement cost with optimal replacement period
extended by four years (Sec. 7.1.3.2, Table 7.5). In other words,
reengineering resulted in extending the optimal replacement period to
8 years.
Table 7.7 shows the summary of the numerical results obtained
(Table 7.4 and table 7.5) for annual average block replacement costs
from 5th year onwards without and with reengineering.
Timeperiod (n
years)
Using WMTP method(Second order Markov Chain)
Without reengineering With reengineering
Total cost (lacs)Weighted
Av. AnnualCost(lacs)
Total cost (lacs)Weighted
Av. AnnualCost(lacs)
5 332.73 332.73 343.70 343.706 361.70 187.65 343.43 178.177 483.15 158.38 429.78 140.888 588.99 137.89 491.10 114.979 990.36 155.91 807.18 127.07
Table 7.7 Numerical results for weighted average annual blockreplacement cost without and with reengineering
The average annual block replacement cost (Rs.114.97 lacs) is
minimum during 8th year. This is less than the average annual block
replacement cost (Rs.137 lacs) without reengineering.
Therefore, it is suggestible to go for reengineering the computer
network with Thin client technology at the end of 4th year and replace
the block of computers at the end of 8th year (4 years from Table 7.3
before reengineering + 4 years from Table 7.5 after reengineering).
178
The overall savings are shown in the Table 7.8.
Cost Comparison:
Time period (Years)
Total Cost (maintenance + replacement)(in lacs)
withoutreengineering
(Computers arereplaced at the end
of 4th year)
withreengineering
(Computers arereengineered at
the end of 4th year)1-4 years (From Table 7.3) 322.82 145.80*5-8 years (From Table 7.7) 588.99 491.10Total 911.81 636.90
Savings 274.91% of savings 30.14%
Table 7.8 Cost comparison for block replacement without and withreengineering
*As the reengineering is done at the end of 4th year, only maintenancecost is to be taken; group replacement cost need not be considered.
The cost savings are 30.14% by the way of reengineering.
Therefore for the block of computers considered for study in this work,
8 years is the optimal replacement period with reengineering at the
end of 4th year.
179
7.2 MODEL BEHAVIOUR - FEW MORE OBSERVATIONS
The replacement decision, obtained through the sections 7.1.1,
and 7.1.2, is with constant maintenance cost and forecasted inflation
data. To understand the impact of the variable maintenance cost and
different inflation trends, block replacement strategy is evaluated in
the following cases:
a) Variable maintenance cost – low initial maintenance cost with big
increments during later periods – in the same range of
maintenance cost.
b) Variable maintenance cost - high initial maintenance cost with
small increments during later periods – in the same range of
maintenance cost.
c) Rapid up-trend in inflation (assumed inflation data)
d) Sluggish up-trend in inflation (assumed inflation data)
180
7.2(a) Replacement decision with low initial maintenance cost
and big increments during the later time periods
To understand the influence of variable maintenance cost, a
pattern with low initial maintenance cost (minor and major repair
costs) and big increments at later periods is considered as given in
Table 7.9.
Timeperiod(years)
1 2 3 4 5 6 7 8
Minorrepair cost(Rs.)
200 500 700 900 1100 1300 1300 1300
Majorrepair cost(Rs.)
2000 5000 8000 11000 13000 13000 13000 13000
Table 7.9: Variable maintenance cost - with low initialmaintenance cost and big increments during the later time periods
Note: Variable maintenance cost (minor and major repair costs) is
taken with in the range of fixed maintenance cost.
The remaining data is (taken) same as in the case of fixed
maintenance cost (Sec. 7.1.1).
181
(i) The computations for block replacement decision (without the
influence of inflation) using FOMC with low initial maintenance cost
and big increments during the later time periods are shown in the
Table 7.10.
1 2 3 4 5 6 7
Period
(n)
Individual
Replacement =n*C1
EachMinorrepaircost(C2 )
TotalMinorRepaircost =n*C2
EachMajor
repair cost(C3 )
TotalMajor
repair cost= n*C3
Maintenance
cost(R)
1 27.96 0.002 0.12 0.02 1.03 29.122 49.87 0.005 0.31 0.05 2.61 52.803 73.75 0.007 0.44 0.08 4.19 78.394 100.60 0.009 0.57 0.11 5.77 107.035 132.03 0.011 0.70 0.13 6.81 139.556 169.33 0.013 0.84 0.13 6.80 176.987 214.30 0.013 0.84 0.13 6.79 221.948 269.13 .01300 0.85 0.13 6.78 276.77
8 9 10 11
R(lacs)
Groupreplacementcost = N * C4
Total cost (lacs) Annual Averagecost (lacs)
29.12 300.00 329.12 329.1281.92 300.00 381.92 190.96
160.32 300.00 460.32 153.44267.36 300.00 567.36 141.84406.91 300.00 706.91 141.38583.89 300.00 883.89 147.31805.83 300.00 1105.83 157.97
1082.60 300.00 1382.60 172.82Table 7.10: Computations for block replacement model without the influence of
inflation using FOMC with low initial maintenance cost and big increments duringlater periods
From Table 7.10, as the average annual cost is minimum over a
period of 5 years and started increasing from 6th year onwards, it can
be inferred that economics can be achieved if the block replacement is
done at the end of 5th year.
It is observed that the replacement decision remains same as in
the case of fixed maintenance cost (Sec. 7.1.1, Table 7.1)
182
(ii) Table 7.11 shows the computations for block replacement decision
(with the influence of inflation) using FOMC with low initial
maintenance cost and big increments during the later time periods.
The data (except the minor and major repair costs) is same as in
the case of fixed maintenance cost (Sec. 7.1.1).
1 2 3 4 5 6 7 8
Period(n)
Inflation, (%)
Real rate ofinterest, rt =
(rn - t ) /(1 + t )
PWF, =
1/(1+ rt )
Discountfactor (n-1) n-1
Ind.Replacementcost= n*C1
* n-1
EachMinorrepair
cost (C2 )
1 -18.54 0.473 0.679 1 1 27.96 0.0022 -17.41 0.453 0.688 0.6882 1.6882 34.32 0.0053 -0.49 0.206 0.829 0.6876 2.3759 50.71 0.0074 0.65 0.192 0.839 0.5900 2.9659 59.41 0.0095 17.58 0.021 0.980 0.9217 3.8877 121.69 0.0116 18.72 0.011 0.989 0.9477 4.8355 160.49 0.0137 35.65 -0.115 1.130 2.0865 6.9220 447.15 0.0138 36.8 -0.123 1.140 2.5022 9.4243 673.43 0.013
9 10 11 12 =(7+9+11) 13 14 15 =
(13+14) 16 = (15/6)
TotalMinorRepaircost =n*C2 *n-1
EachMajorrepaircost(C3 )
TotalMajorrepaircost =n*C3*n-
1
Maintenance cost(R) R
Groupreplacement
cost =N* C4* n-1
Total cost(TC)
Weightedaverage
annual cost(Rs. in lacs)
0.12 0.02 1.03 29.12 29.12 300.00 329.12 329.120.21 0.05 1.80 36.34 65.46 206.47 271.94 161.070.30 0.08 2.88 53.91 119.37 206.29 325.67 137.070.33 0.11 3.40 63.15 182.53 177.01 359.55 121.220.65 0.13 6.28 12.86 311.16 276.52 587.68 151.160.79 0.13 6.44 16.77 478.90 284.33 763.24 157.840.17 0.13 1.41 46.30 941.99 625.96 1567.96 226.510.21 0.13 1.69 69.25 1634.5
6750.68 2385.24 253.09
Table 7.11: Computations for block replacement model with the influence ofinflation using FOMC with low initial maintenance cost and big increments duringlater periods
From Table 7.11, as the average annual cost is minimum over a
period of 4 years and started increasing from 5th year onwards, it can
183
be inferred that economics can be achieved if the block replacement is
done at the end of 4th year.
It is observed that the replacement decision remains same as in
the case of fixed maintenance cost (Sec. 7.1.2, Table 7.2). It is also to
be noted that the increase in inflation resulted in the advancement of
replacement period.
(iii) Table 7.12 shows the computations for block replacement
decision (with the influence of inflation) using SOMC with low initial
maintenance cost and big increments during the later time periods.
The data (except the minor and major repair costs) is same as in
the case of fixed maintenance cost (Sec. 7.1.2.1).
From Table 7.12, as the average annual cost is minimum over a
period of 4 years and started increasing from 5th year onwards, it can
be inferred that economics can be achieved if the block replacement is
done at the end of 4th year.
It is observed that the replacement decision remains same as in
the case of fixed maintenance cost (Sec. 7.1.2.1, Table 7.3). It is also
to be noted that the increase in inflation resulted in the advancement
of replacement period.
184
1 2 3 4 5 6 7 8
Period(n)
Inflation, (%)
Real rate ofinterest, rt =
(rn - t ) /(1 + t )
PWF, =
1/(1+ rt )
Discountfactor (n-1) n-1
Ind.Replacementcost= n*C1
* n-1
EachMinorrepair
cost (C2 )
1 -18.54 0.473 0.679 1 1 27.96 0.0022 -17.41 0.453 0.688 0.6882 1.6882 34.32 0.0053 -0.49 0.206 0.829 0.6876 2.3759 34.92 0.0074 0.65 0.192 0.839 0.5900 2.9659 33.83 0.0095 17.58 0.021 0.980 0.9217 3.8877 58.33 0.0116 18.72 0.011 0.989 0.9477 4.8355 66.52 0.0137 35.65 -0.115 1.130 2.0865 6.9220 162.25 0.0138 36.8 -0.123 1.140 2.5022 9.4243 215.62 .01300
9 10 11 12 =(7+9+11) 13 14 15 =
(13+14) 16 = (15/6)
Total MinorRepair cost
=n*C2 * n-1
EachMajorrepaircost(C3 )
Total Majorrepair cost
=n*C3*n-1
Maintenance cost(R) R
Groupreplacemen
t cost =N* C4* n-1
Total cost(TC)
Weightedaverage
annual cost(Rs. in lacs)
0.12 0.02 1.03 29.12 29.12 300.00 329.12 329.120.21 0.05 1.80 36.34 65.46 206.47 271.94 161.070.32 0.08 3.05 38.29 103.76 206.29 310.05 130.500.37 0.11 3.77 37.98 141.74 177.01 318.76 107.470.75 0.13 7.31 66.41 208.16 276.52 484.68 124.670.97 0.13 7.90 75.40 283.56 284.33 567.90 117.442.28 0.13 18.27 182.80 466.37 625.96 1092.34 157.802.89 0.13 23.01 241.53 707.90 750.68 1458.58 154.76
Table 7.12: Computations for block replacement model with the influence ofinflation using SOMC with low initial maintenance cost and big increments duringlater periods.
185
Table 7.13 and Fig. 7.3 furnish the summary of the numerical
results obtained (Table 7.10, Table 7.11 and Table 7.12), for block
replacement decision with low initial maintenance cost and big
increments during the later periods, using - first order Markov chain
with and without inflation, and Weighted Moving Transition
Probability (WMTP) methods.
Timeperiod (n
years)
Using First Order Markov Chain Using SecondOrder Markov chain
without inflation with inflation with inflationAnnual Av.cost(lacs)
Weighted Av.Annual Cost(lacs)
Weighted Av. AnnualCost(lacs)
1 329.12 329.12 329.122 190.96 161.07 161.073 153.44 137.07 130.54 141.84 121.22 107.475 141.38 151.16 124.676 147.31 157.84 117.447 157.97 226.51 157.88 172.82 253.09 154.76
Table 7.13: Numerical results for annual average costs with low initialmaintenance cost and big increments during later periods
fig. 7.3 Average cost per year under low initialmaintenace cost with big increments
0
50
100
150
200
250
300
350
1 2 3 4 5 6 7 8
Time period (years)
Ave
rage
cos
t per
yea
r in
lacs
Without inflation
With inflation uinsgFOMCWith inflation usingSOMC
186
With the low initial maintenance cost and big increments during later
periods:
- When the influence of inflation is not considered, First Order
Markov Chain (FOMC) model resulted in the replacement age as 5
years, and
- When the influence of inflation is considered, FOMC and SOMC
calculations resulted in the early replacement of block of
computers at the age of 4 years.
It can be observed that the optimal replacement decision (block
replacement at the end of 4th year) remains same as in the case of
fixed maintenance cost (Sec. 7.1.4).
187
7.2(b) Replacement Decision With High Initial Maintenance Cost
And Small Increments
To understand the influence of variable maintenance cost,
another pattern with high initial maintenance cost (minor and major
repair costs) and small increments at later periods is considered as
given in Table 7.14.
Note: Variable maintenance cost (minor and major repair costs) is
taken in the range of fixed maintenance cost.
Timeperiod(years)
1 2 3 4 5 6 7 8
Minorrepair cost(Rs.)
1000 1100 1200 1300 1400 1400 1400 1400
Majorrepair cost(Rs.)
8000 9000 10000 11000 12000 13000 13000 13000
Table 7.14: Variable maintenance cost - with high initial maintenancecost and small increments during the later time periods
The remaining data is (taken) same as in the case of fixed
maintenance cost (Sec. 7.1.1).
188
(i) The computations for block replacement decision (without the
influence of inflation) using FOMC with low initial maintenance cost
and big increments during the later time periods are shown in the
Table 7.15.
1 2 3 4 5 6 7
Period
(n)
Individual
Replacement =n*C1
EachMinorrepaircost(C2 )
TotalMinorRepaircost =n*C2
EachMajor
repair cost(C3 )
TotalMajor
repair cost= n*C3
Maintenance
cost(R)
1 27.96 0.010 0.61 0.08 4.15 32.732 49.87 0.011 0.68 0.09 4.71 55.273 73.75 0.012 0.75 0.10 5.24 79.764 100.60 0.013 0.82 0.11 5.77 107.285 132.03 0.014 0.89 0.12 6.29 139.226 169.33 0.014 0.90 0.13 6.80 177.047 214.30 0.014 0.91 0.13 6.79 222.008 269.13 0.014 0.92 0.13 6.78 276.83
8 9 10 11
R(lacs)
Groupreplacementcost = N *
C4
Total cost (lacs) Annual Averagecost (lacs)
32.73 300.00 332.73 332.7388.00 300.00 388.00 194.00
167.77 300.00 467.77 155.92275.06 300.00 575.06 143.76414.28 300.00 714.28 142.85591.32 300.00 891.32 148.55813.33 300.00 1113.33 159.04
1090.17 300.00 1390.17 173.77Table 7.15: Computations for block replacement decision without the influence of
inflation using FOMC with high initial maintenance cost and small incrementsduring later periods
From Table 7.15, as the average annual cost is minimum over a
period of 5 years and started increasing from 6th year onwards, it can
be inferred that economics can be achieved if the block replacement is
done at the end of 5th year.
It is observed that the replacement decision remains same as in the
case of fixed maintenance cost (Sec. 7.1.1, Table 7.1)
189
(ii) Table 7.16 shows the computations for block replacement decision
(with the influence of inflation) using FOMC with high initial
maintenance cost and small increments during the later time periods.
The data (except the minor and major repair costs) is same as in
the case of fixed maintenance cost (Sec. 7.1.1).
1 2 3 4 5 6 7 8
Period(n)
Inflation, (%)
Real rate ofinterest, rt =
(rn - t ) /(1 + t )
PWF, =
1/(1+ rt )
Discountfactor (n-1) n-1
Ind.Replacementcost= n*C1
* n-1
EachMinorrepair
cost (C2 )
1 -18.54 0.473 0.679 1 1 27.96 0.0102 -17.41 0.453 0.688 0.6882 1.6882 34.32 0.0113 -0.49 0.206 0.829 0.6876 2.3759 50.71 0.0124 0.65 0.192 0.839 0.5900 2.9659 59.41 0.0135 17.58 0.021 0.980 0.9217 3.8877 121.69 0.0146 18.72 0.011 0.989 0.9477 4.8355 160.49 0.0147 35.65 -0.115 1.130 2.0865 6.9220 447.15 0.0148 36.8 -0.123 1.140 2.5022 9.4243 673.43 0.014
910
1112 =
(7+9+11)
13 14 15 =(13+14) 16 = (15/6)
Total MinorRepair cost
=n*C2 * n-1
EachMajorrepaircost(C3 )
TotalMajorrepaircost =n*C3*n-1
Maintenance
cost(R)R
Groupreplacement
cost =N* C4* n-1
Total cost(TC)
Weightedaverage annual
cost(Rs. in lacs)
0.61 0.08 4.15 32.73 32.73 300.00 332.73 332.730.47 0.09 3.24 38.04 70.77 206.47 277.25 164.220.52 0.10 3.61 54.84 125.62 206.29 331.92 139.700.48 0.11 3.40 63.30 188.93 177.01 365.95 123.380.82 0.12 5.79 128.32 317.25 276.52 593.78 152.730.85 0.13 6.44 167.80 485.06 284.33 769.39 159.111.90 0.13 14.16 463.22 948.29 625.96 1574.25 227.422.30 0.13 16.98 692.72 1641.0
1750.68 2391.69 253.77
Table 7.16: Computations for block replacement model with the influence ofinflation using FOMC with high initial maintenance cost and small incrementsduring later time periods
From Table 7.16, as the average annual cost is minimum over a
period of 4 years and started increasing from 5th year onwards, it can
190
be inferred that economics can be achieved if the block replacement is
done at the end of 4th year.
It is observed that the replacement decision remains same as in
the case of fixed maintenance cost (Sec. 7.1.2, Table 7.2). It is also to
be noted that the increase in inflation resulted in the advancement of
replacement period.
(iii) Table 7.17 shows the computations for block replacement
decision (with the influence of inflation) using SOMC with high initial
maintenance cost and small increments during the later time periods.
The data (except the minor and major repair costs) is same as in
the case of fixed maintenance cost (Sec. 7.1.2.1).
From Table 7.17, as the average annual cost is minimum over a
period of 4 years and started increasing from 5th year onwards, it can
be inferred that economics can be achieved if the block replacement is
done at the end of 4th year.
It is observed that the replacement decision remains same as in
the case of fixed maintenance cost (Sec. 7.1.2.1, Table 7.3). It is also
to be noted that the increase in inflation resulted in the advancement
of replacement period.
191
1 2 3 4 5 6 7 8
Period (n) Inflation, (%)
Real rate ofinterest, rt =
(rn - t ) /(1 + t )
PWF, =
1/(1+ rt )
Discountfactor (n-1) n-1
Ind.Replacementcost= n*C1
* n-1
EachMinorrepair
cost (C2 )
1 -18.54 0.473 0.679 1 1 27.96 0.0102 -17.41 0.453 0.688 0.6882 1.6882 34.32 0.0113 -0.49 0.206 0.829 0.6876 2.3759 34.92 0.0124 0.65 0.192 0.839 0.5900 2.9659 33.83 0.0135 17.58 0.021 0.980 0.9217 3.8877 58.33 0.0146 18.72 0.011 0.989 0.9477 4.8355 66.52 0.0147 35.65 -0.115 1.130 2.0865 6.9220 162.25 0.0148 36.8 -0.123 1.140 2.5022 9.4243 215.62 0.014
9 10 11 12 =(7+9+11) 13 14 15 =
(13+14) 16 = (15/6)
TotalMinorRepaircost =n*C2 *n-1
EachMajorrepair
cost (C3 )
Total Majorrepair cost
=n*C3*n-1
Maintenance cost(R)
(Rs. inlacs)
R(Rs. inlacs)
Groupreplacemen
t cost =N* C4* n-1
Total cost(TC)
(Rs. inlacs)
Weightedaverage
annual cost(Rs. in lacs)
0.61 0.08 4.15 32.73 32.73 300.00 332.73 332.730.47 0.09 3.24 38.04 70.77 206.47 277.25 164.220.55 0.10 3.81 39.28 110.06 206.29 316.35 133.150.54 0.11 3.77 38.15 148.21 177.01 325.23 109.650.96 0.12 6.75 66.05 214.27 276.52 490.79 126.24
10.05 0.13 7.90 75.48 289.75 284.33 574.09 118.7220.45 0.13 18.27 182.98 472.73 625.96 1098.70 158.7230.12 0.13 23.01 241.75 714.49 750.68 1465.17 155.46
Table 7.17: Computations for block replacement model with the influence of inflationusing SOMC with high initial maintenance cost and small increments during laterperiods
192
Table 7.18 and Fig. 7.4 furnish the summary of the numerical
results obtained (Table 7.15, Table 7.16, Table 7.17), for block
replacement decision with high initial maintenance cost and small
increments during the later periods, using - first order Markov chain
with and without inflation, and Weighted Moving Transition
Probability (WMTP) methods.
Timeperiod (n
years)
Using First Order Markov Chain Using SecondOrder Markov chain
without inflation with inflation with inflationAnnual Av.cost(lacs)
Weighted Av.Annual Cost(lacs)
Weighted Av. AnnualCost(lacs)
1 332.73 332.73 332.732 194.00 164.22 164.223 155.92 139.7 133.154 143.76 123.38 109.655 142.85 152.73 126.246 148.55 159.11 118.727 159.04 227.42 158.728 173.77 253.77 155.46
Table 7.18: Numerical results for annual average costs with highinitial maintenance cost and small increments during later periods
Fig. 7.4 Average cost per year under high initialmaintenanace cost with small increments
0
50
100
150
200
250
300
350
1 2 3 4 5 6 7 8Time period (years)
Ave
rage
cos
t per
yea
r
Without inflationusing FOMCWith inflation usingFOMCWith inflation usingSOMC
193
With the high initial maintenance cost and small increments
during later periods:
- When the influence of inflation is not considered, First Order
Markov Chain (FOMC) model resulted in the replacement age as 5
years, and
- When the influence of inflation is considered, FOMC and SOMC
calculations resulted in the early replacement of block of
computers at the age of 4 years.
It can be observed that the optimal replacement decision (block
replacement at the end of 4th year) remains same as in the case of
fixed maintenance cost (Sec. 7.1.4).
Therefore, when the maintenance cost is varied with different
trends – high initial maintenance cost and small increments; and with
low initial maintenance cost and big increments; – in the same range of
fixed maintenance cost, it is observed that the replacement decision
remains the same as in the case of fixed maintenance cost.
194
7.2(c) Influence Of Changing Inflation TrendsIn the Section 7.1.2, to know the influence of inflation, the
forecasted inflation is used. However to evaluate behaviour of the
developed Block Replacement model under different inflation patterns,
two trends – rapid up-trend and sluggish up-trend – in inflation are
considered.
The data for these rapid and sluggish (inflation) up-trends with
respect to the forecasted inflation (refer Sec. 6.5.1, Table 6.7) is shown
in Table 7.19 and plotted in Fig. 7.5.
Timeperiod(year)
Forecastedinflation (%)
Rapidincrease
in inflation(%)
Sluggishincrease ininflation (%)
1 -18.54 -18.54 -18.542 -17.41 -5 -153 -0.49 5 -124 0.65 20 -95 17.58 30 -66 18.72 40 -37 35.65 50 18 36.8 60 4
Table 7.19: Inflation trends: Rapid and Sluggish up-trends in inflationwith respect to the forecasted inflation.
Fig. 7.5 Inflation trends:Rapid and Sluggish up-trends with respect to forecasted inflation
-30-20-10
010203040506070
1 2 3 4 5 6 7 8
Time period (years)
Infla
tion(
%) Forecasted
inflationRapid increase ininflationSluggish increasein inflation
195
(i) Table 7.20 shows the computations for influence of the rapid
increase in inflation on block replacement decision using FOMC with
fixed maintenance cost.
The remaining data (except the inflation values) is same as in the case
of forecasted inflation (Sec 7.1.1).
1 2 3 4 5 6 7
Period (n) Inflation, (%)
Real rate ofinterest, rt =
(rn - t ) /(1 + t )
PWF, =
1/(1+ rt )
Discountfactor (n-1) n-1 Ind. Replacement
cost= n*C1 * n-1
1 -18.54 0.473 0.679 1 1 27.962 -5 0.263 0.792 0.7916 1.7916 39.483 5 0.143 0.875 0.7656 2.5572 56.464 20 0.000 1.000 1 3.5572 100.685 30 -0.077 1.083 1.3773 4.9346 181.856 40 -0.143 1.167 2.1613 7.0960 366.007 50 -0.200 1.250 3.8146 10.910 817.498 60 -0.250 1.333 7.4915 18.402 2016.19
8 9 10 =(7+8+9) 11 12 13 = (11+12) 14 = (13/6)
MinorRepair cost
=n*C2 * n-1
Majorrepair cost
=n*C3*n-1
Maintenance
cost(R)R
(Rs. inlacs)
Groupreplacemen
t cost =N* C4* n-1
Total cost(TC)
(Rs. in lacs)
Weightedaverage annual
cost(Rs. in lacs)
0.61 4.15 32.73 32.73 300.00 332.73 332.730.49 3.31 43.29 76.02 237.50 313.52 174.990.48 3.21 60.16 136.19 229.68 365.88 143.070.63 4.19 105.52 241.71 300.00 541.71 152.280.88 5.77 188.51 430.23 413.20 843.44 170.921.39 9.05 376.45 806.68 648.41 1455.10 205.052.48 15.94 835.92 1642.6
11144.40 2787.02 255.43
4.93 31.29 2052.42 3695.03
2247.46 5942.49 322.92Table 7.20: Computations for the influence of rapid up-trend in
Inflation on block replacement decision using FOMC
From Table 7.20, as the average annual cost is minimum over a
period of 3 years and started increasing from 4th year onwards, it can
196
be inferred that economics can be achieved if the block replacement is
done at the end of 3rd year.
It is observed that when there is a rapid up-trend in inflation,
the optimal replacement period is advanced by one year with respect
to block replacement decision with forecasted inflation (Sec. 7.1.2,
Table 7.2).
(ii) Table 7.21 shows the computations for influence of the sluggish
up-trend in inflation on block replacement decision using FOMC with
fixed maintenance cost.
The remaining data (except the inflation values) is same as in
the case of forecasted inflation (Sec 7.1.1).
From Table 7.21, as the average annual cost is minimum over a
period of 5 years and started increasing from 6th year onwards, it can
be inferred that economics can be achieved if the block replacement is
done at the end of 5th year.
It is observed that when there is a sluggish up-trend in
inflation, the optimal replacement period is delayed by one year with
respect to block replacement decision with forecasted inflation (Sec.
7.1.2, Table 7.2).
197
1 2 3 4 5 6 7
Period (n) Inflation, (%)
Real rate ofinterest, rt =
(rn - t ) /(1 + t )
PWF, =
1/(1+ rt )
Discountfactor (n-1) n-1 Ind. Replacement
cost= n*C1 * n-1
1 -18.54 0.473 0.679 1 1 27.962 -15 0.412 0.708 0.7083 1.7083 35.323 -12 0.364 0.733 0.5377 2.2461 39.664 -9 0.319 0.758 0.4360 2.6822 43.905 -6 0.277 0.783 0.3765 3.0587 49.716 -3 0.237 0.808 0.3451 3.4038 58.437 1 0.188 0.842 0.3555 3.7593 76.188 4 0.154 0.867 0.3672 4.1265 98.83
8 9 10 =(7+8+9) 11 12 13 =
(11+12) 14 = (13/6)
Minor Repaircost =n*C2 * n-1
Majorrepair cost
=n*C3*n-1
Maintenancecost(R)
(Rs. in lacs)R
(Rs. in lacs)
Groupreplacement
cost =N* C4* n-1
Totalcost(TC)
( in lacs)
Weightedaverage
annual cost(Rs. in lacs)
0.61 4.15 32.73 32.73 300.00 332.73 332.730.44 2.96 38.73 71.47 212.50 283.97 166.220.33 2.25 42.26 113.73 161.33 275.06 122.460.27 1.83 46.01 159.75 130.82 290.57 108.330.24 1.57 51.53 211.28 112.95 324.23 106.000.22 1.44 60.10 271.39 103.53 374.92 110.140.23 1.48 77.90 349.29 106.65 455.94 121.280.24 1.53 100.61 449.90 110.17 560.08 135.72
Table 7.21: Computations for the influence of sluggish up-trend inInflation on block replacement decision using FOMC
Table 7.22 and Fig. 7.6 furnish the summary of the numerical
results obtained (Table 7.2, Table 7.20 and Table 7.21), for the
influence of rapid and sluggish up-trends in inflation (with respect to
the forecasted inflation) on block replacement decision, using first
order Markov chain.
198
Timeperiod( years)
Weighted Average annual cost per year(Rs. in lacs)
forForecastedinflation
(from Table 7.2)
for Rapidincrease ininflation
(from Table 7.20)
for Sluggishincrease ininflation
(from Table 7.21)1 332.73 332.73 332.732 163.98 174.99 166.223 139.19 143.07 122.464 122.62 152.28 108.335 151.59 170.92 106.006 157.63 205.05 110.147 225.52 255.43 121.288 251.62 322.92 135.72
Table 7.22: Average cost per year for rapid and sluggish up-trends in
inflation
Fig. 7.6 Weighted Average cost per year fordifferent inflation trends
0
50
100
150
200
250
300
350
1 2 3 4 5 6 7 8Time period (years)
Ave
rage
cos
t per
yea
r
for Forecastedinflationfor Rapid increase ininflationfor Sluggish increasein inflation
The optimal replacement age for the block items in the case of
forecasted inflation is 4 years. Where as, in case of rapid up-trend in
inflation, the optimal replacement age is advanced to 3rd year and
instead, in case of sluggish up-trend in inflation, the optimal
replacement age for the block of items is delayed to 5th year.
199
Summary: This chapter deals with the case study in which the
developed replacement model using Markov chains approach is
applied to evaluate the replacement strategies and determine the age
at which block replacement can be done that is economical, for a
block of computers and computer based system. To understand the
performance of the developed model, the replacement age obtained
under various conditions is tabulated in Table 7.23 and Table 7.24.
Replacement age in years
Without reengineering Withreengineering
Using First OrderMarkov Chain
Using Second OrderMarkov chain
Using Second OrderMarkov chain
withoutinflation
withinflation with inflation with inflation
With constantmaintenance cost 5 years 4 years 4 years 8 yearsVariable maintenancecost: low initialmaintenance cost withbig increments duringlater periods
5 years 4 years 4 years --
Variable maintenancecost: High initialmaintenance cost withsmall incrementsduring later periods
5 years 4 years 4 years --
Table 7.23: Replacement ages with the developed models
Replacement age in yearsfor
Forecastedinflation
for Rapidincrease ininflation
forSluggish
increase ininflation
4 years 3 years 5 years
Table 7.24: Replacement ages with variable trends in inflation