carr school update
DESCRIPTION
Carr School Update. 3/5/14. Elevator and Classroom Additions. - PowerPoint PPT PresentationTRANSCRIPT
![Page 1: Carr School Update](https://reader036.vdocuments.us/reader036/viewer/2022062315/568166c5550346895ddad258/html5/thumbnails/1.jpg)
CARR SCHOOL UPDATE3/5/14
![Page 2: Carr School Update](https://reader036.vdocuments.us/reader036/viewer/2022062315/568166c5550346895ddad258/html5/thumbnails/2.jpg)
Elevator and Classroom AdditionsWork is nearly complete. Containment to be removed in the
coming weeks. Hourly checks on the space temperature have ensured proper environment for the masonry work. The elevator itself just arrived to the shop and will be on
site within the week.
![Page 3: Carr School Update](https://reader036.vdocuments.us/reader036/viewer/2022062315/568166c5550346895ddad258/html5/thumbnails/3.jpg)
WindowsWindows are approximately 80% complete. Special care has been taken to ensure that the install is high quality,
with an eye for air sealing and envelope integrity.
![Page 4: Carr School Update](https://reader036.vdocuments.us/reader036/viewer/2022062315/568166c5550346895ddad258/html5/thumbnails/4.jpg)
Mechanical SystemsMost of the HVAC work is complete. A few more air handlers
to be installed, some small things to button up, and in about 4 weeks we’ll be firing up the new high efficiency
condensing boilers.
![Page 5: Carr School Update](https://reader036.vdocuments.us/reader036/viewer/2022062315/568166c5550346895ddad258/html5/thumbnails/5.jpg)
Electrical, Plumbing, Sprinkler, and DataAll interior trade work is moving along quickly. Systems are
mostly installed, and things like pressure testing, safety checks, and final wiring are underway.
![Page 6: Carr School Update](https://reader036.vdocuments.us/reader036/viewer/2022062315/568166c5550346895ddad258/html5/thumbnails/6.jpg)
Interior FinishesAlmost all of the walls are closed up. Plastering is almost
complete, and we’ve started painting.