carp10026 - rep - g - 001- brl marillana project - pfs report - rev_0

93
0 Issued for use BV PC PC 17 Sep 2010 B Issued for Client Review AHH BV PC July 2010 A Preliminary AHH BV PC June 2010 Rev Description Author Checked Approved Authorised Date Calibre Rail Pty Ltd Brockman Resources Marillana Project Preliminary Feasibility Study Report Marillana Loadout Siding to FMG Tie-in CARP10026-REP-G-001

Upload: gerfreecalls

Post on 07-Apr-2015

373 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: CARP10026 - REP - G - 001- BRL Marillana Project - PFS Report - Rev_0

0 Issued for use BV PC PC 17 Sep 2010

B Issued for Client Review AHH BV PC July 2010

A Preliminary AHH BV PC June 2010

Rev Description Author Checked Approved Authorised Date

Calibre Rail Pty Ltd Brockman Resources Marillana Project Preliminary Feasibility Study Report

Marillana Loadout Siding to FMG Tie-in

CARP10026-REP-G-001

Page 2: CARP10026 - REP - G - 001- BRL Marillana Project - PFS Report - Rev_0
Page 3: CARP10026 - REP - G - 001- BRL Marillana Project - PFS Report - Rev_0

Calibre Rail Document No: CARP10026-REP-G-001

Brockman Resources – Marillana Iron Ore Project Revision No: 0

Preliminary Feasibility Study Report Issue Date: Sep 2010

Page No: i

\\perfps01\CEJV$\PRO-Projects\2010\CARP10026 BR-Marillana Study\02 - PFS Study\06 Engineering\6.12 Reports\BRL Marillana Rail Project PFS Rev 0\CARP10026 - REP - G - 001- Brockman Resources Marillana Project - Pre-Feasibility Study Report - Rev_0.doc

CONTENTS

1.0 EXECUTIVE SUMMARY .................................................................................................. 1

1.1 Overview and Background ........................................................................................ 1

1.1.1 Work Scope ................................................................................................ 1

1.1.2 Work Excluded ............................................................................................ 2

1.2 Alignment Options .................................................................................................... 3

1.3 Engineering .............................................................................................................. 8

1.3.1 Design Criteria ............................................................................................ 8

1.3.2 Earthworks.................................................................................................. 8

1.3.3 Hydrology and Drainage Structures ............................................................ 9

1.3.4 Track Structure ........................................................................................... 9

1.3.5 Train Control, Signalling and Asset Protection........................................... 10

1.3.6 Voice and Data Communication ................................................................ 11

1.3.7 Construction Camps .................................................................................. 11

1.4 Railway Operations................................................................................................. 12

1.4.1 Train Performance Modelling .................................................................... 13

1.5 Track Maintenance ................................................................................................. 13

1.6 Project Schedule..................................................................................................... 14

1.7 Cost Estimates........................................................................................................ 15

1.8 Safety and Environmental Management ................................................................. 15

1.9 Project Risks and Mitigations .................................................................................. 15

1.10 Path Forward .......................................................................................................... 15

1.11 Qualifications and Assumptions .............................................................................. 16

2.0 ENGINEERING DESIGN............................................................................................... 18

2.1 Railway................................................................................................................... 18

2.2 Design Life and Characteristics ............................................................................... 19

2.3 Site Conditions........................................................................................................ 19

2.4 Modular Design....................................................................................................... 19

2.5 Interoperability Requirements ................................................................................ 19

2.6 Topography and Digital Terrain Map....................................................................... 20

2.7 Geotechnical Assessment ....................................................................................... 20

2.8 Construction Water................................................................................................. 21

2.9 Earthworks ............................................................................................................. 22

2.9.1 Cut and Fill Volumes ................................................................................. 22

Page 4: CARP10026 - REP - G - 001- BRL Marillana Project - PFS Report - Rev_0

Calibre Rail Document No: CARP10026-REP-G-001

Brockman Resources – Marillana Iron Ore Project Revision No: 0

Preliminary Feasibility Study Report Issue Date: Sep 2010

Page No: ii

\\perfps01\CEJV$\PRO-Projects\2010\CARP10026 BR-Marillana Study\02 - PFS Study\06 Engineering\6.12 Reports\BRL Marillana Rail Project PFS Rev 0\CARP10026 - REP - G - 001-

Brockman Resources Marillana Project - Pre-Feasibility Study Report - Rev_0.doc

2.9.2 Mass Haul Analysis.................................................................................... 23

2.10 Hydrology and Drainage ......................................................................................... 23

2.10.1 Railway ..................................................................................................... 23

2.10.2 Access Roads ............................................................................................ 24

2.11 Level Crossings....................................................................................................... 24

2.12 Construction Camps................................................................................................ 25

2.12.1 Construction Camp Facilities ..................................................................... 26

2.13 Control, Signalling and Asset Protection System ..................................................... 27

2.13.1 Turnout Point Control................................................................................ 28

2.13.2 Track Circuits ............................................................................................ 29

2.13.3 Interlocking Equipment ............................................................................. 30

2.13.4 Power Supply ............................................................................................ 30

2.13.5 Level Crossing Protection .......................................................................... 30

2.13.6 Broken Rail Detection (BRD) ..................................................................... 31

2.13.7 Dragging Equipment Detectors (DED)....................................................... 31

2.13.8 Hot Wheel/Hot Bearing Detectors (HBWD) ............................................... 31

2.13.9 Stream Flow Detectors (SFD).................................................................... 32

2.14 Voice and Data Communication .............................................................................. 32

2.14.1 Camp Communications ............................................................................. 33

3.0 OPTIONS ....................................................................................................................... 36

3.1 Railway Route Options............................................................................................ 36

3.2 OPT1 HA2 VA2 ....................................................................................................... 42

3.2.1 Route Description ..................................................................................... 42

3.2.2 Railway Operations and Train Performance Modelling............................... 42

3.2.3 Passing Sidings and Refuge siding ............................................................ 43

3.2.4 Geotechnical Desktop Assessment ............................................................ 43

3.2.5 Earthworks................................................................................................ 43

3.2.6 Bridges and Culverts ................................................................................. 44

3.2.7 Construction Camps .................................................................................. 45

3.2.8 Construction Water Requirement Assessment ........................................... 45

3.3 OPT2 HA1 VA1 ....................................................................................................... 46

3.3.1 Route Description ..................................................................................... 46

3.3.2 Railway Operations and Train Performance Modelling............................... 46

3.3.3 Passing Sidings and Refuge siding ............................................................ 47

Page 5: CARP10026 - REP - G - 001- BRL Marillana Project - PFS Report - Rev_0

Calibre Rail Document No: CARP10026-REP-G-001

Brockman Resources – Marillana Iron Ore Project Revision No: 0

Preliminary Feasibility Study Report Issue Date: Sep 2010

Page No: iii

\\perfps01\CEJV$\PRO-Projects\2010\CARP10026 BR-Marillana Study\02 - PFS Study\06 Engineering\6.12 Reports\BRL Marillana Rail Project PFS Rev 0\CARP10026 - REP - G - 001-

Brockman Resources Marillana Project - Pre-Feasibility Study Report - Rev_0.doc

3.3.4 Geotechnical Desktop Assessment ............................................................ 47

3.3.5 Earthworks................................................................................................ 47

3.3.6 Bridges and Culverts ................................................................................. 48

3.3.7 Construction Camps .................................................................................. 49

3.3.8 Construction Water Requirement Assessment ........................................... 49

3.4 Comparison Matrix.................................................................................................. 49

4.0 RAILWAY OPERATIONS AND MAINTENANCE ......................................................... 51

4.1 Operations.............................................................................................................. 51

4.1.1 Preliminary Operations Assessment .......................................................... 51

4.1.2 Train Performance Modelling .................................................................... 53

4.1.3 Passing Sidings and Tracks ....................................................................... 54

4.1.4 Scheduling ................................................................................................ 55

4.2 Maintenance ........................................................................................................... 55

4.2.1 Track Maintenance.................................................................................... 55

4.2.2 BRL Track Maintenance Equipment ........................................................... 56

5.0 CONSTRUCTION METHOD .......................................................................................... 58

5.1 Earthworks ............................................................................................................. 58

5.1.1 Clearing and grubbing............................................................................... 58

5.1.2 Excavation for Cuttings ............................................................................. 58

5.1.3 Embankment and Compaction .................................................................. 58

5.2 Bridges and Culverts............................................................................................... 58

5.3 Track ...................................................................................................................... 59

5.3.1 Rails.......................................................................................................... 59

5.3.2 Sleepers .................................................................................................... 59

5.3.3 Tracklaying ............................................................................................... 59

5.3.4 Ballast ....................................................................................................... 59

6.0 SCHEDULE..................................................................................................................... 60

7.0 COST ESTIMATES......................................................................................................... 62

7.1 CAPITAL COSTS...................................................................................................... 62

7.1.1 Estimate Basis........................................................................................... 62

7.1.2 Indirect Cost Estimate............................................................................... 63

7.2 Capital Estimate Set-Out......................................................................................... 64

7.2.1 Man-hours................................................................................................. 64

7.2.2 Direct Labour Cost .................................................................................... 64

Page 6: CARP10026 - REP - G - 001- BRL Marillana Project - PFS Report - Rev_0

Calibre Rail Document No: CARP10026-REP-G-001

Brockman Resources – Marillana Iron Ore Project Revision No: 0

Preliminary Feasibility Study Report Issue Date: Sep 2010

Page No: iv

\\perfps01\CEJV$\PRO-Projects\2010\CARP10026 BR-Marillana Study\02 - PFS Study\06 Engineering\6.12 Reports\BRL Marillana Rail Project PFS Rev 0\CARP10026 - REP - G - 001-

Brockman Resources Marillana Project - Pre-Feasibility Study Report - Rev_0.doc

7.2.3 Construction Equipment Cost .................................................................... 65

7.2.4 Plant/Equipment Cost ............................................................................... 66

7.2.5 Bulk Materials Cost.................................................................................... 66

7.2.6 Freight ...................................................................................................... 66

7.2.7 Subcontract Indirects ................................................................................ 66

7.2.8 Total Cost ................................................................................................. 67

7.2.9 Rail Facilities Capital Cost.......................................................................... 67

7.2.10 Engineering Costs ..................................................................................... 67

7.3 Insurances.............................................................................................................. 67

7.4 Scope Exclusion...................................................................................................... 68

7.5 Operating costs ...................................................................................................... 68

7.6 Comparison with OoM Estimate .............................................................................. 69

8.0 APPROVALS .................................................................................................................. 72

9.0 SAFETY AND ENVIRONMENTAL MANAGEMENT ...................................................... 74

9.1 Safety Management................................................................................................ 74

9.2 Environmental Management ................................................................................... 74

10.0 ACTS, REGULATIONS AND STANDARDS FOR THE PROJECT ................................. 76

10.1 Document Precedence ............................................................................................ 76

10.2 Statutory Authorities............................................................................................... 76

10.3 Environmental Regulations ..................................................................................... 76

10.4 Australian Standards............................................................................................... 77

11.0 PROJECT RISKS MITIGATION ................................................................................... 77

12.0 CONCLUSION AND RECOMMENDATIONS ................................................................ 77

13.0 PATH FORWARD........................................................................................................... 79

14.0 APPENDICES................................................................................................................. 81

Page 7: CARP10026 - REP - G - 001- BRL Marillana Project - PFS Report - Rev_0

Calibre Rail Document No: CARP10026-REP-G-001

Brockman Resources – Marillana Iron Ore Project Revision No: 0

Preliminary Feasibility Study Report Issue Date: Sep 2010

Page No: v

\\perfps01\CEJV$\PRO-Projects\2010\CARP10026 BR-Marillana Study\02 - PFS Study\06 Engineering\6.12 Reports\BRL Marillana Rail Project PFS Rev 0\CARP10026 - REP - G - 001-

Brockman Resources Marillana Project - Pre-Feasibility Study Report - Rev_0.doc

TABLES

Table 1.1 Earthwork Cost Estimates of alignment options ........................................................ 3 Table 1.2 Summary of Railway Formation Earthwork Volumes (million m3).............................. 8 Table 1.3 Required Bridges for OPT1 HA2 VA2 and OPT2 HA1 VA1 ......................................... 9 Table 1.4 Train Operating Simulation Results Comparison ..................................................... 13 Table 1.5 Railway Capex for Studied Alignments.................................................................... 15 Table 2.1 Key Design Criteria ................................................................................................. 18 Table 2.2 Key Earthwork Design Criteria ................................................................................ 22 Table 3.1 Options Earthworks Cost Estimates ........................................................................ 38 Table 3.2 Four Options: Advantages and Disadvantages........................................................ 40 Table 3.3 Track and Operational Lengths to OPT 1 Junction on FMG Line.............................. 42 Table 3.4 Geotechnical Desktop Assessment for OPT1 HA2 VA2 ............................................ 43 Table 3.5 Bridges & Major culverts Locations and Lengths..................................................... 44 Table 3.6 Additional Earthworks for Bridges/Major Culverts ................................................... 45 Table 3.7 Geotechnical Desktop Assessment for OPT2 HA1 VA1 ............................................ 47 Table 3.8 Bridges/ Major Culverts Locations and Lengths ...................................................... 48 Table 3.9 Additional Earthworks for Bridges/Major Culvert..................................................... 48 Table 3.10 Key Parameters Comparison for Alignments ........................................................... 49 Table 4.1 Rolling Stock and operational Data ......................................................................... 52 Table 4.2 Ore Train Cycle Time .............................................................................................. 52 Table 4.3 Consists Modelled ................................................................................................... 54 Table 4.4 Simulations Results Comparison ............................................................................. 54 Table 7.1 Summary of Capex Estimates ................................................................................. 62 Table 7.2 OoM and PFS estimate comparison......................................................................... 69 Table 7.3 Comparison with OoM estimate – cost driving items ............................................ 70

FIGURES

Figure 1.1 Simplified Layout of Corridors................................................................................... 4 Figure 1.2 Simplified Layout of four Alignments ........................................................................ 6 Figure 1.3 Simplified Schematic Diagrams of the preferred Alignments.................................... 7 Figure 2.1 OPT1 HA2 VA2 Air Strip Crossing............................................................................ 25 Figure 2.2 Landing strip near Ch. 77 Km. ................................................................................ 25 Figure 3.1 Corridors for 12 Alignment Options......................................................................... 37 Figure 3.2 Alignment Options selected for Train Performance Study ....................................... 39 Figure 3.3 Simplified Layout of Final Two Alignment Options .................................................. 41

Page 8: CARP10026 - REP - G - 001- BRL Marillana Project - PFS Report - Rev_0

Calibre Rail Document No: CARP10026-REP-G-001

Brockman Resources – Marillana Iron Ore Project Revision No: 0

Preliminary Feasibility Study Report Issue Date: Sep 2010

Page No: vi

\\perfps01\CEJV$\PRO-Projects\2010\CARP10026 BR-Marillana Study\02 - PFS Study\06 Engineering\6.12 Reports\BRL Marillana Rail Project PFS Rev 0\CARP10026 - REP - G - 001-

Brockman Resources Marillana Project - Pre-Feasibility Study Report - Rev_0.doc

Acronyms

Acronym Meaning

1v:xh slope of 1 vertical in x horizontal

AC Alternating Current

ACI Automatic Car Identification

ACMA Australian Communications and Media Authority

AHD Australian Height Datum

ALARP as low as reasonably practical

ALS airborne laser scanning

ARI average recurrence interval

AS Australian Standards

ATP automatic train protection

AWS automatic warning system

BHPBIO BHP Billiton Iron Ore

BRD broken rail detection

BRL Brockman Resources Limited

Ch. chainage in km unless otherwise noted

CAR Calibre Rail

CSP corrugated steel pipe

CWR continuously welded rail

DC Direct Current

DED dragging equipment detector

DFS definitive feasibility study

DEM digital elevation model

DFS detailed feasibility study

DTM digital terrain model

EPCM engineering procurement & construction management

FBW flash butt weld

FMG Fortescue Metals Group

FOB free on board

FOT free on truck

GMT gross million tonnes

GSD geodetic survey data

GST goods and service tax

HBWD hot bearing/wheel detector

hr hour

IP internet protocol

km kilometre

LIDAR light detection and ranging

LoA limit of authority

m metre

Page 9: CARP10026 - REP - G - 001- BRL Marillana Project - PFS Report - Rev_0

Calibre Rail Document No: CARP10026-REP-G-001

Brockman Resources – Marillana Iron Ore Project Revision No: 0

Preliminary Feasibility Study Report Issue Date: Sep 2010

Page No: vii

\\perfps01\CEJV$\PRO-Projects\2010\CARP10026 BR-Marillana Study\02 - PFS Study\06 Engineering\6.12 Reports\BRL Marillana Rail Project PFS Rev 0\CARP10026 - REP - G - 001-

Brockman Resources Marillana Project - Pre-Feasibility Study Report - Rev_0.doc

Acronym Meaning

min minute

mm millimetre

Mtpa Million tonnes per annum

OMC optimum moisture contents

OoM order of magnitude

PFS preliminary feasibility study

RBM rail bound manganese

RBS radio base station

RMT rail maintenance track

SDH synchronous digital hierarchy

sec second

SFD stream flow detector

SMOF single-mode optical fibre

SNX swing nose crossing

STM synchronous transport module

t tonne

tal tonnes axle load

TCC train control centre

TCS train control system

TPC train performance calculation

UHF ultra high frequency

WA Western Australia

Page 10: CARP10026 - REP - G - 001- BRL Marillana Project - PFS Report - Rev_0

Calibre Rail Document No: CARP10026-REP-G-001

Brockman Resources – Marillana Iron Ore Project Revision No: 0

Preliminary Feasibility Study Report Issue Date: Sep 2010

Page No: viii

\\perfps01\CEJV$\PRO-Projects\2010\CARP10026 BR-Marillana Study\02 - PFS Study\06 Engineering\6.12 Reports\BRL Marillana Rail Project PFS Rev 0\CARP10026 - REP - G - 001-

Brockman Resources Marillana Project - Pre-Feasibility Study Report - Rev_0.doc

Intentionally Blank

Page 11: CARP10026 - REP - G - 001- BRL Marillana Project - PFS Report - Rev_0

Calibre Rail Document No: CARP10026-REP-G-001

Brockman Resources – Marillana Iron Ore Project Revision No: 0

Preliminary Feasibility Study Report Issue Date: Sep 2010

Page No: Page 1 of 93

\\perfps01\CEJV$\PRO-Projects\2010\CARP10026 BR-Marillana Study\02 - PFS Study\06 Engineering\6.12 Reports\BRL Marillana Rail Project PFS Rev 0\CARP10026 - REP - G - 001-

Brockman Resources Marillana Project - Pre-Feasibility Study Report - Rev_0.doc

1.0 EXECUTIVE SUMMARY

1.1 Overview and Background Brockman Resources Limited (BRL) is developing a Marillana iron ore project in the Pilbara region of Western Australia. The project is likely to commence production in 2013 at a nominal rate of 17 Mtpa with an estimated mine life of 20 years.

In June 2009 Engenium Pty Ltd completed an order of magnitude (OoM) study for a rail spur connecting the Marillana mines to the existing Fortescue Metals Group (FMG) rail line using a rail corridor that FMG considered as part of a Mindy Mindy development. The OoM estimated the construction capital cost for a 112 km railway line as $372 million. The FMG’s rail network from Cloudbreak to Port Hedland including port facilities at Port Hedland are owned and operated by The Pilbara Infrastructure (TPI), a wholly-owned subsidiary of Fortescue Metals Group. The TPI railway was built under the Railway and Port (The Pilbara Infrastructure Pty Ltd) Agreement Act 2004, and has been included in the WA rail access regime since 1 July 2008. The aim of the act was to develop a multi-user railway and multi-user port facilities in the Pilbara region of the WA. In March 2010, BRL commissioned Calibre Rail to study the rail connectivity options for their Marillana mines. The study scope was divided into two parts as follows:

• Study 1: A Definitive Feasibility Study (DFS) for a proposed rail loadout loop, and grade-separated crossing over a BHPBIO railway line to a battery limit in the vicinity of 8 km from the BHPBIO crossing. The estimate accuracy was ±15%.

• Study 2: A Preliminary Feasibility Study (PFS) to explore railway alignment options for a rail line from the battery limit to a tie-in with the FMG line. The study was to:

− consider three route options; and

− provide an estimate accurate to ±30%.

Study 1 is complete and the report forms part of a Calibre Project’s “Marillana Iron Ore Project Definitive Engineering Study, Product Loadout Facility” (CPJP 10006-0520-REP-G-007) report for mining operations.

This report is for study 2 which concerns the construction of a new railway line from the mine loadout battery limit to the FMG main line. The BRL railway will link Marillana mines to the existing FMG’s Cloudbreak to Port Hedland railway. The study scope also includes the necessary railway infrastructure, including a signalling and communications conceptual design sufficient to determine high level capital costs.

1.1.1 Work Scope The PFS work scope is to design a railway from the battery limit to a tie-in point on the FMG railway via three BRL specified alignment corridors identified in an earlier study.

Page 12: CARP10026 - REP - G - 001- BRL Marillana Project - PFS Report - Rev_0

Calibre Rail Document No: CARP10026-REP-G-001

Brockman Resources – Marillana Iron Ore Project Revision No: 0

Preliminary Feasibility Study Report Issue Date: Sep 2010

Page No: Page 2 of 93

\\perfps01\CEJV$\PRO-Projects\2010\CARP10026 BR-Marillana Study\02 - PFS Study\06 Engineering\6.12 Reports\BRL Marillana Rail Project PFS Rev 0\CARP10026 - REP - G - 001-

Brockman Resources Marillana Project - Pre-Feasibility Study Report - Rev_0.doc

The Scope includes the following major elements:

• Track;

• Earthworks;

• Hydrology and high-level drainage design for bridge structures;

• Signalling and communications systems that can interface with existing systems;

• Access roads; and

• Temporary infrastructure necessary to construct the works.

The battery limits for the PFS railway is between about 8 km northeast of the grade separation over the BHPBIO railway and the FMG railway tie-in.

1.1.2 Work Excluded The following works are excluded from this study:

• Compilation and management of the overall definitive feasibility study;

• Ground disturbance work for geotechnical or hydrogeological studies;

• Formation of overall study and project policy;

• Environmental, heritage and native title approvals, studies and surveys;

• Land tenure, government and other statutory approvals necessary to execute the project;

• Aerial survey works;

• Access agreements;

• Safety accreditation for the railway;

• Marketing and sales analysis;

• Water and building licences;

• Procurement and contracting strategy planning including identification of long-lead items;

• Obtaining detailed quotations;

• Rolling stock selection;

• Design verification;

• Legal costs;

• Detailed design and site facilities and infrastructure;

• Hydrology and drainage design for culverts;

Page 13: CARP10026 - REP - G - 001- BRL Marillana Project - PFS Report - Rev_0

Calibre Rail Document No: CARP10026-REP-G-001

Brockman Resources – Marillana Iron Ore Project Revision No: 0

Preliminary Feasibility Study Report Issue Date: Sep 2010

Page No: Page 3 of 93

\\perfps01\CEJV$\PRO-Projects\2010\CARP10026 BR-Marillana Study\02 - PFS Study\06 Engineering\6.12 Reports\BRL Marillana Rail Project PFS Rev 0\CARP10026 - REP - G - 001-

Brockman Resources Marillana Project - Pre-Feasibility Study Report - Rev_0.doc

• Detailed drainage for bridges;

• Detailed geotechnical analysis for structures including bridges;

• Development of a railway maintenance strategy, except to the degree required to help select an alignment; and

• Option to connect into the BHPBIO Port Hedland−Newman railway.

1.2 Alignment Options Calibre Rail studied 12 potential alignments in three corridors. These were compared and ranked on the basis of the preliminary earthwork costs estimate. Table 1.1 indicates estimated earthwork costs. Figure 1.1 shows the simplified layout of corridors for these alignments.

Table 1.1 Earthwork Cost Estimates of alignment options

Options Length (km)

Earthworks Capital Cost

($M)

Cost Per km ($M)

Rank in each corridor

(total cost)

OPT1 HA1 VA1 99.59 225.9 2.27 4

OPT1 HA2 VA1 95.34 163.6 1.72 1

OPT1 HA2 VA2 95.34 207.3 2.17 2

OPT1 HA3 VA1 95.89 224.9 2.35 3

OPT1 HA4 VA1 98.71 232.1 2.35 5

OPT2 HA1 VA1 70.47 110.1 1.56 1

OPT2 HA1 VA2 70.44 142.6 2.02 2

OPT2 HA2 VA2 69.77 180.1 2.58 3

OPT3 HA1 VA1 70.25 125.7 1.79 1

OPT3 HA1 VA2 70.25 310.6 4.42 3

OPT3 HA2 VA2 70.29 306.1 4.36 2

OPT3 HA3 VA3 71.70 394.6 5.50 4

Page 14: CARP10026 - REP - G - 001- BRL Marillana Project - PFS Report - Rev_0

Calibre Rail Document No: CARP10026-REP-G-001

Brockman Resources – Marillana Iron Ore Project Revision No: 0

Preliminary Feasibility Study Report Issue Date: Sep 2010

Page No: Page 4 of 93

\\perfps01\CEJV$\PRO-Projects\2010\CARP10026 BR-Marillana Study\02 - PFS Study\06 Engineering\6.12 Reports\BRL Marillana Rail Project PFS Rev 0\CARP10026 - REP - G - 001-

Brockman Resources Marillana Project - Pre-Feasibility Study Report - Rev_0.doc

Figure 1.1 Simplified Layout of Corridors

Page 15: CARP10026 - REP - G - 001- BRL Marillana Project - PFS Report - Rev_0

Calibre Rail Document No: CARP10026-REP-G-001

Brockman Resources – Marillana Iron Ore Project Revision No: 0

Preliminary Feasibility Study Report Issue Date: Sep 2010

Page No: Page 5 of 93

\\perfps01\CEJV$\PRO-Projects\2010\CARP10026 BR-Marillana Study\02 - PFS Study\06 Engineering\6.12 Reports\BRL Marillana Rail Project PFS Rev 0\CARP10026 - REP - G - 001-

Brockman Resources Marillana Project - Pre-Feasibility Study Report - Rev_0.doc

Out of the 12 alignments options, the best four were selected and studied in more detail. The four alignments are OPT1 HA2 VA1, OPT1 HA2 VA2, OPT2 HA1 VA1 and OPT3 HA1 VA1. These are shown in Figure 1.2 and highlighted on Table 1.1. Train simulations with standard a Brockman/FMG consist were run on these four alignments. Simulation of alignments OPT1 HA2 VA1 and OPT3 HA1 VA1 demonstrated unsatisfactory operational performance due to steep continuous rising gradients against the loaded train journey and were discounted from further investigation. Further study and simulations were carried out on the two remaining alignments OPT1 HA2 VA2 and OPT2 HA1 VA1. Figure 1.3 is a schematic of alignments OPT1 HA2 VA2 and OPT2 HA1 VA1. Appendix A provides a register of related and supporting documents that have been used for this study. The drawings developed for this study are in appendix D.

Page 16: CARP10026 - REP - G - 001- BRL Marillana Project - PFS Report - Rev_0

Calibre Rail Document No: CARP10026-REP-G-001

Brockman Resources – Marillana Iron Ore Project Revision No: 0

Preliminary Feasibility Study Report Issue Date: Sep 2010

Page No: Page 6 of 93

\\perfps01\CEJV$\PRO-Projects\2010\CARP10026 BR-Marillana Study\02 - PFS Study\06 Engineering\6.12 Reports\BRL Marillana Rail Project PFS Rev 0\CARP10026 - REP - G - 001-

Brockman Resources Marillana Project - Pre-Feasibility Study Report - Rev_0.doc

Alignment OPT1-HA2-VA1and

Alignment OPT1-HA2-VA2

AlignmentOPT2-HA1-VA1

AlignmentOPT3-HA1-VA1

Commonalignment

Scientific Reserve

Brockman Stage 2 battery limit

Brockman Stage 1Railway alignmentFMG railway

Legend

Road

BHPBIO railway

Figure 1.2 Simplified Layout of four Alignments

Page 17: CARP10026 - REP - G - 001- BRL Marillana Project - PFS Report - Rev_0

Calibre Rail Document No: CARP10026-REP-G-001

Brockman Resources – Marillana Iron Ore Project Revision No: 0

Preliminary Feasibility Study Report Issue Date: Sep 2010

Page No: Page 7 of 93

\\perfps01\CEJV$\PRO-Projects\2010\CARP10026 BR-Marillana Study\02 - PFS Study\06 Engineering\6.12 Reports\BRL Marillana Rail Project PFS Rev 0\CARP10026 - REP - G - 001- Brockman Resources Marillana Project - Pre-Feasibility Study Report -

Rev_0.doc

Bridge 2

Ch.88.1

Bridge 4

Ch.42.9

Bridge 3

Ch.41.7

Bridge2

Ch.41.3

Bridge 1

Ch.40.7

Bridge 5

Ch.44.0

LegendProposed rail

Railway bridge

Passing siding

Waterway

Spur

Existing rail

Bridge 6

Ch.88.1

FMGLine

BHPBIOLine

Ch.105.5

Ch.15.4

Ch.12.4

Brockman Line

Ch.102.0

Ch.105.0

Ch.52.3

Batterylimit

Ch.10.2

Ch.39.3

Ch.36.3

Ch.35.1

Ch.117.1

BHPBIOLine

Rail-over-rail bridge

Alignment OPT1-HA2-VA2

Alignment OPT2-HA1-VA1

Bridge 1

Ch.11.8

Ch.105.5

Brockman Line

Ch.102.0

Ch.105.0

Ch.52.3

Batterylimit

FMGLine

Ch.117.1 Loadout

siding

BrockmanStage 1 rail

Loadoutsiding

BrockmanStage 1 rail

Rail-over-rail bridge

Figure 1.3 Simplified Schematic Diagrams of the preferred Alignments

Page 18: CARP10026 - REP - G - 001- BRL Marillana Project - PFS Report - Rev_0

Calibre Rail Document No: CARP10026-REP-G-001

Brockman Resources – Marillana Iron Ore Project Revision No: 0

Preliminary Feasibility Study Report Issue Date: Sep 2010

Page No: Page 8 of 93

\\perfps01\CEJV$\PRO-Projects\2010\CARP10026 BR-Marillana Study\02 - PFS Study\06 Engineering\6.12 Reports\BRL Marillana Rail Project PFS Rev 0\CARP10026 - REP - G - 001-

Brockman Resources Marillana Project - Pre-Feasibility Study Report - Rev_0.doc

1.3 Engineering

1.3.1 Design Criteria The design criteria are contained in the document “Calibre Rail−Brockman Resources Marillana Creek Project – Basis of Design” (CPJP10006-0525-STD-G-001). The Acts, Regulations and Standards that the design conforms to are listed in appendix B of the above referred document.

1.3.2 Earthworks The earthworks design parameters are largely based on the FMG standards for it’s Pilbara operations. The design parameters applicable to this project will be modified after geotechnical investigations are concluded during the DFS phase. A preliminary assessment of cutting material and borrow sources along the alignment has been done as part of the desktop geotechnical study. This data combined with the cut and fill volumes produced from 12D, has been used for the mass-haul analysis. The proposed strategy aims to balance cut and fill material where practical to maximise haulage efficiency. Where cut material is inadequate for fill, suitable fill material will be sourced from borrow areas. Haul distances from cuttings have generally been maintained at less than five kilometres where local borrow is available and haul distances for spoil have been maintained at or less than two kilometres. Table 1.2 shows the summary of formation earthworks quantities for the two options.

Table 1.2 Summary of Railway Formation Earthwork Volumes (million m3)

Material OPT1 HA2 VA2 OPT2 HA1 VA1

Cut 7.11 1.04

Fill 2.43 2.13

Additional fill for raising alignment at Bridge location

0.75 1.20

Page 19: CARP10026 - REP - G - 001- BRL Marillana Project - PFS Report - Rev_0

Calibre Rail Document No: CARP10026-REP-G-001

Brockman Resources – Marillana Iron Ore Project Revision No: 0

Preliminary Feasibility Study Report Issue Date: Sep 2010

Page No: Page 9 of 93

\\perfps01\CEJV$\PRO-Projects\2010\CARP10026 BR-Marillana Study\02 - PFS Study\06 Engineering\6.12 Reports\BRL Marillana Rail Project PFS Rev 0\CARP10026 - REP - G - 001-

Brockman Resources Marillana Project - Pre-Feasibility Study Report - Rev_0.doc

1.3.3 Hydrology and Drainage Structures Limited design work was done for the drainage structures which enabled the identification of bridge and culvert requirements. Catchment area analysis and the likely bridge configuration are based upon the following criteria:

• A waterway was considered to be a potential bridge site when the peak flow for the 50-year average recurrence interval (ARI) is greater than or approaches 200 m3/sec. Some of such locations have however been classified as major culverts; and

• The stream profiles were estimated from the contour lines.

Culverts have been proposed at other drain crossings with corrugated steel pipes or reinforced concrete box depending on the site conditions. Alignment OPT1 HA2 VA2 has two bridges and four major culverts, and OPT2 HA1 VA1 has six bridges and four major culverts. Table 1.3 shows the required bridges for both alignments.

Table 1.3 Required Bridges for OPT1 HA2 VA2 and OPT2 HA1 VA1

Options Chainage (Km) Total Length (m)

11.8 120 OPT1 HA2 VA2

88.1 260

40.7 200

41.3 160

41.7 180

42.9 160

44.0 140

OPT2 HA1 VA1

88.1 260

Option to provide RMT culverts is to be studied in the DFS phase.

1.3.4 Track Structure

• The mainline track structure will comprise:

- Continuously welded head-hardened 68 kg/m rails compliant with AS1085.1;

- 1435 mm gauge;

- Concrete sleepers at 675 mm centres; and

- 250 mm of under sleeper ballast.

Page 20: CARP10026 - REP - G - 001- BRL Marillana Project - PFS Report - Rev_0

Calibre Rail Document No: CARP10026-REP-G-001

Brockman Resources – Marillana Iron Ore Project Revision No: 0

Preliminary Feasibility Study Report Issue Date: Sep 2010

Page No: Page 10 of 93

\\perfps01\CEJV$\PRO-Projects\2010\CARP10026 BR-Marillana Study\02 - PFS Study\06 Engineering\6.12 Reports\BRL Marillana Rail Project PFS Rev 0\CARP10026 - REP - G - 001-

Brockman Resources Marillana Project - Pre-Feasibility Study Report - Rev_0.doc

• All turnouts routinely traversed by loaded trains will be swing-nose crossing (SNX) turnout type;

• Mainline turnouts will be 1:20 SNX turnouts and turnouts from passing track to backtrack will be 1:12 SNX turnouts;

• Turnouts from backtracks to spurs/sidings and turnouts in yards traversed by empty trains will be 1:12 solid frog turnouts; and

• For yards, 150 mm of under sleeper ballast is specified.

1.3.5 Train Control, Signalling and Asset Protection A “train order” train control practise is considered adequate to safely operate the Brockman railway spur for tonnages up to 25Mtpa. The train order system uses a train voice radio network linked to a train control centre via a communications backbone. However, since the train consists will travel along the FMG main line railway, the locomotives will have to conform to the FMG specifications and this will include compliance with the safety management system. The equipment specified includes in-cab signalling and the appropriate automatic train protection equipment (ATP). As the BRL railway spur will connect to the FMG main line railway, Calibre Rail assumes that all train control for the BRL train journey will be under FMG train control. For trains operating along the BRL spur railway, train orders will be issued from FMG train control centre (TCC). If applied in the future, a computer-based train control system (TCS) will track train movements using track occupancy indications. The control system will include:

• Track circuits along the railway; and

• Appropriate operating rules and procedures beyond those of train orders;

Asset protection devices are required to protect the rail infrastructure to minimise disruption to train operations. These may include;

• Stream flow detectors (SFDs);

• Dragging equipment detectors (DEDs); and

• Hot box/hot wheel detectors (HBWDs).

As the BRL railway will constitute a railway spur off the FMG main line railway, all track systems may be required to meet the FMG specifications.

Page 21: CARP10026 - REP - G - 001- BRL Marillana Project - PFS Report - Rev_0

Calibre Rail Document No: CARP10026-REP-G-001

Brockman Resources – Marillana Iron Ore Project Revision No: 0

Preliminary Feasibility Study Report Issue Date: Sep 2010

Page No: Page 11 of 93

\\perfps01\CEJV$\PRO-Projects\2010\CARP10026 BR-Marillana Study\02 - PFS Study\06 Engineering\6.12 Reports\BRL Marillana Rail Project PFS Rev 0\CARP10026 - REP - G - 001-

Brockman Resources Marillana Project - Pre-Feasibility Study Report - Rev_0.doc

1.3.6 Voice and Data Communication A reliable voice communication network with redundant coverage is essential for safe and efficient rail operation using a train order system. The communication options are based on a 25 year life. The communications system will:

• Support an internet protocol (IP) network for rail signalling/asset protection and mobile voice communications for railway operations;

• Provide temporary and permanent communications for camps;

• Allow voice communications during construction; and

• Be compliant with FMG standards for interoperability.

The communications backbone can be either a fibre-optic cable or a microwave radio system. The fibre-optic solution is likely to be more expensive. However, it may be the better option based on the anticipated project life. The system can provide sufficient capacity for future expansion and support other services, such as mine and port communication/ control systems. The microwave radio option potentially has a lower Capex, but it:

• May not be adequate for operations over a 25 year project life; and

• Will provide limited capacity for future expansion.

This study assumes that:

• Fibre-optic cable will be adopted. The Capex for the fibre optic option has been estimated to ±25% accuracy; and

• It will be able to interface successfully with the FMG network backbone systems, if required.

1.3.7 Construction Camps Due to the large volume of materials anticipated from cuttings for the first 50 km of the OPT1 HA2 VA2 alignment, the earthworks package for rail formation has been divided into four work fronts with daily production rate ranging from 6000m3 to 10,000m3. The first three earthwork fronts will operate within 50 km from the tie-in point with the existing FMG railway, and the fourth front will work from the mine end heading towards north. Based on this assumption, three temporary construction camps are required to meet the project schedule. Camp size for this option will be up to 600 rooms at the peak of construction.

Page 22: CARP10026 - REP - G - 001- BRL Marillana Project - PFS Report - Rev_0

Calibre Rail Document No: CARP10026-REP-G-001

Brockman Resources – Marillana Iron Ore Project Revision No: 0

Preliminary Feasibility Study Report Issue Date: Sep 2010

Page No: Page 12 of 93

\\perfps01\CEJV$\PRO-Projects\2010\CARP10026 BR-Marillana Study\02 - PFS Study\06 Engineering\6.12 Reports\BRL Marillana Rail Project PFS Rev 0\CARP10026 - REP - G - 001-

Brockman Resources Marillana Project - Pre-Feasibility Study Report - Rev_0.doc

For the OPT2 HA1 VA1 alignment, which is the shorter of the two alignments, two temporary construction camps are considered sufficient to meet the project schedule. In order to accommodate bridge crews for construction of 6 bridges, camp size is expected to go up to 500 rooms at the peak of construction. Construction crew numbers for each construction activity were estimated based on previous construction experience from similar projects in the Pilbara, and peak level of workforce during the construction determined the required camp sizing at a specific location where the following engineering criteria were assessed:

• Minimising travel distances between camp and work site to maximise productivity and minimise fatigue related incidents; and

• The proximity of existing access roads to the camp sites.

Although it is anticipated that the camps at the mine end will be shared facilities with mine construction, the camp sizing used in this estimate allows for rail construction crews only. Further refinements to the camp sizing will be carried out during the next study phase.

1.4 Railway Operations A preliminary assessment of train operations supporting 17Mtpa production for each alignment has been undertaken. This assessment will provide:

• The number of passing sidings required to support a mine production up to 17 Mtpa;

• Passing siding locations;

• Typical train cycles on the Marillana rail spur; and

• A calculation of trains required from mine to port per annum.

The operational assessment has been based on the following assumptions:

• Axle load is 40 tonne;

• Maximum train speeds are 80 km/h for empty and 80 Km/h for loaded trains;

• Train loading rate is 8000 t/h;

• The car dumper at the port will be used for unloading;

• The car dumper unloads all the ore cars in a consist without splitting train;

• BRL trains can normally enter the FMG network when scheduled, without excessive delays;

• BRL trains can leave the port when scheduled;

Page 23: CARP10026 - REP - G - 001- BRL Marillana Project - PFS Report - Rev_0

Calibre Rail Document No: CARP10026-REP-G-001

Brockman Resources – Marillana Iron Ore Project Revision No: 0

Preliminary Feasibility Study Report Issue Date: Sep 2010

Page No: Page 13 of 93

\\perfps01\CEJV$\PRO-Projects\2010\CARP10026 BR-Marillana Study\02 - PFS Study\06 Engineering\6.12 Reports\BRL Marillana Rail Project PFS Rev 0\CARP10026 - REP - G - 001-

Brockman Resources Marillana Project - Pre-Feasibility Study Report - Rev_0.doc

• Ore cars can hold 137 t of ore (refer table 4.1 for details);

• Passing sidings on the existing FMG network can accommodate the increased traffic from BRL trains; and

• Train operations will be modelled on 348 working days per year.

At this stage train cycle is estimated to be around 22 hours. The cycle time estimation is based on current available data. Some interaction with FMG will be required in next project phase to appreciate the anticipated train operations, and to enable accurate assessment of train cycle times.

1.4.1 Train Performance Modelling Calibre Rail uses “Open Track” train performance simulation software to analyse alignments during the development process to determine:

• Train performance on each alignment with a standard FMG train consist of two GE C44-9W (Dash 9 DC) locomotives and 240 ore wagons, with two similar banking locomotives where required; and

• Track design;

Table 1.4 outlines the simulation results for the OPT1 HA2 VA2 and OPT2 HA1 VA1 alignments. Simulation graphs are in appendix B.

Table 1.4 Train Operating Simulation Results Comparison

Fuel Consumption (L)

Option

Alignment Length to Junction (km)

Travel time (mins)

Min. Speed (km/h)1

Empty 2 locos

Loaded 4 locos

Total

OPT1 HA2 VA2 95.3 143 20 2,656 5,766 8,422

OPT2 HA1 VA1 70.5 99 26 1,869 3,922 5,791

1.5 Track Maintenance The proposed track maintenance plan is based on preventive maintenance to provide a safe, efficient and cost effective train operation. The outline maintenance plan is detailed in section 4.2 of this report.

1 Reference to “Minimum speed” in the table relates to the slowest speed the train runs at along the alignment before

losing momentum and stalling. This figure is compared to the “Minimum Continuous Speed” design criteria, the chosen locomotive type can sustain. This measurement assists in the development of the railway design criteria for the railway alignment in terms of adequate grades and vertical and horizontal curvature of the track.

Page 24: CARP10026 - REP - G - 001- BRL Marillana Project - PFS Report - Rev_0

Calibre Rail Document No: CARP10026-REP-G-001

Brockman Resources – Marillana Iron Ore Project Revision No: 0

Preliminary Feasibility Study Report Issue Date: Sep 2010

Page No: Page 14 of 93

\\perfps01\CEJV$\PRO-Projects\2010\CARP10026 BR-Marillana Study\02 - PFS Study\06 Engineering\6.12 Reports\BRL Marillana Rail Project PFS Rev 0\CARP10026 - REP - G - 001-

Brockman Resources Marillana Project - Pre-Feasibility Study Report - Rev_0.doc

Calibre Rail would anticipate that an appropriate commercial service arrangement would be negotiated with The Pilbara Infrastructure (TPI) to include maintenance of the Marillana railway spur into the FMG railway maintenance program.

1.6 Project Schedule Preliminary project construction schedules have been developed for OPT1 HA2 VA2 and OPT2 HA1 VA1 alignments taking into account the major group of activities. These are attached in appendix C. The major assumptions made for these construction schedules are;

• Project environmental approval by July 2011; and

• Commence major construction works in August 2011 including flycamp establishment, camp earthworks, laydown areas, construction water facilities and access road.

Based on the schedules, construction camp sizing has been estimated and the project durations have been determined for each option. The project finish dates are respectively;

• 19 July 2013 for OPT1 HA2 VA2; and

• 10 July 2013 for OPT2 HA1 VA1.

Note: these may change following the completion of the findings of the detailed geotechnical, hydrological and bridge studies.

Page 25: CARP10026 - REP - G - 001- BRL Marillana Project - PFS Report - Rev_0

Calibre Rail Document No: CARP10026-REP-G-001

Brockman Resources – Marillana Iron Ore Project Revision No: 0

Preliminary Feasibility Study Report Issue Date: Sep 2010

Page No: Page 15 of 93

\\perfps01\CEJV$\PRO-Projects\2010\CARP10026 BR-Marillana Study\02 - PFS Study\06 Engineering\6.12 Reports\BRL Marillana Rail Project PFS Rev 0\CARP10026 - REP - G - 001-

Brockman Resources Marillana Project - Pre-Feasibility Study Report - Rev_0.doc

1.7 Cost Estimates Table 1.5 shows the summary Capex.

Table 1.5 Railway Capex for Studied Alignments

COST ($M)* ITEMS

OPT1 HA2 VA2 OPT2 HA1 VA1

Earthworks & Drainage $301.19 $123.98

Haul Roads $2.44 $1.81

Track Supply & Construction $77.29 $57.74

Bridges and Major Culverts $49.74 $144.93

Signals and Communications $41.43 $41.71

Construction Facilities $90.31 $104.28

Subtotal Directs $562.41 $474.44

Contractor Overheads & Indirects $66.44 $72.21

EPCM $56.16 $61.85

Subtotal Indirects $122.60 $134.05

Grand Total $685.01 $608.50

Track length Km 102.92 77.58

Cost per km* $6.66 $7.84 *Excludes rolling stock and maintenance facilities

1.8 Safety and Environmental Management During this PFS, safety and environmental management has mainly focussed on designing for safety and environmental care.

1.9 Project Risks and Mitigations For the PFS study no risk analysis has been carried out. This will be required during the definitive feasibility study (DFS) phase.

1.10 Path Forward The path forward for the project is to conduct a detailed feasibility study to achieve greater accuracy and more detailed engineering and cost estimation on a selected route. Some of the key works recommended as part of the definitive feasibility study are:

• Aerial survey;

• Ground breaking geotechnical investigation along the alignment;

• Detailed geotechnical investigation of bridge location;

Page 26: CARP10026 - REP - G - 001- BRL Marillana Project - PFS Report - Rev_0

Calibre Rail Document No: CARP10026-REP-G-001

Brockman Resources – Marillana Iron Ore Project Revision No: 0

Preliminary Feasibility Study Report Issue Date: Sep 2010

Page No: Page 16 of 93

\\perfps01\CEJV$\PRO-Projects\2010\CARP10026 BR-Marillana Study\02 - PFS Study\06 Engineering\6.12 Reports\BRL Marillana Rail Project PFS Rev 0\CARP10026 - REP - G - 001-

Brockman Resources Marillana Project - Pre-Feasibility Study Report - Rev_0.doc

• Review of basis of design document;

• Detailed alignment design;

• Temporary infrastructure requirement assessment;

• Risk assessment; and

• Construction safety plans etc.

1.11 Qualifications and Assumptions The alignments were constrained within BRL specified corridors OPT1, OPT2 and OPT3, each about 2km wide. Investigation outside the specified corridors may provide a more cost-effective alignment. The waterways analysis was carried out on the basis of information derived from DEM data/imageries collected from Landgate. The hydraulic modelling should be reviewed based on airborne laser scanning (ALS) data in the next project phase. Bridges are specified at most of the locations with Q50 ≥ 200 m3/sec. Bridge configurations are assumed on the basis of peak flow, formation height and channel width. A detailed bridge study will be required during the next project phase. The earthworks design and bridge foundations design is based on a preliminary desktop geotechnical assessment from available information about the region. No site inspection or ground-disturbing investigations were done. The earthworks design and bridge foundations design may change when more detailed geotechnical data is acquired. Temporary infrastructure, other than the construction camps, has not been included in this study. Safety management, environmental management and environmental risk management will have to be discussed in detail before starting construction. Only a standard 2.5 m wide side drain has been considered in the earthworks model for OPT1 HA2 VA2. The high runoff in a long cutting will require wider side drains. This will further increase the quantity of earthworks in cuttings. Further investigation is proposed in the next project phase.

Page 27: CARP10026 - REP - G - 001- BRL Marillana Project - PFS Report - Rev_0

Calibre Rail Document No: CARP10026-REP-G-001

Brockman Resources – Marillana Iron Ore Project Revision No: 0

Preliminary Feasibility Study Report Issue Date: Sep 2010

Page No: Page 17 of 93

\\perfps01\CEJV$\PRO-Projects\2010\CARP10026 BR-Marillana Study\02 - PFS Study\06 Engineering\6.12 Reports\BRL Marillana Rail Project PFS Rev 0\CARP10026 - REP - G - 001-

Brockman Resources Marillana Project - Pre-Feasibility Study Report - Rev_0.doc

Intentionally Blank

Page 28: CARP10026 - REP - G - 001- BRL Marillana Project - PFS Report - Rev_0

Calibre Rail Document No: CARP10026-REP-G-001

Brockman Resources – Marillana Iron Ore Project Revision No: 0

Preliminary Feasibility Study Report Issue Date: Sep 2010

Page No: Page 18 of 93

\\perfps01\CEJV$\PRO-Projects\2010\CARP10026 BR-Marillana Study\02 - PFS Study\06 Engineering\6.12 Reports\BRL Marillana Rail Project PFS Rev 0\CARP10026 - REP - G - 001-

Brockman Resources Marillana Project - Pre-Feasibility Study Report - Rev_0.doc

2.0 ENGINEERING DESIGN

2.1 Railway The project design criteria are in a “Calibre Rail−Brockman Resources Marillana Creek Project – Basis of Design” document (CPJP10006-0525-STD-G-001). The key criteria are shown on table 2.1.

Table 2.1 Key Design Criteria

Criteria/Parameter Value

Standard ore train consist 2 GE C44-9W (Dash 9 DC) head end locos + 240 ore cars+2 banker locos (where required)

Consist length (m) 2800

Tonne axle loading (t) 40

Maximum speed 80 km/hr loaded and 80 km/hr empty2

Maximum Vertical Grades

Loaded direction 0.55% compensated

Empty direction 1.50% compensated

Grade compensation 0.04% per degree of curvature

Horizontal Curve Radius

Desirable Minimum (m) 2,000

Absolute Minimum( m) 1,000

Vertical Curve Radius (Min.)

Summit (m) 3,000

Sag (m) 6,000

Formation

Width 6.6 m in fill & cut with 2.5 m wide side drains

Sub-ballast capping thickness 250 mm

Cut batter slopes 1v:1.5h

Fill batter slopes 1v:2h

Drainage structures

Design peak flow frequency 1 in 50 year

Freeboard for bridges & formation 500 mm

Track

Gauge 1435 mm standard gauge

Rail AS 68 kg/m, head-hardened

Sleepers Pre-stressed Concrete at 675 mm centres

Fasteners Elastic Rail Clip Pandrol E-type

Turnouts 1:12 and 1:20 SNX and fixed frog

Ballast 250 mm deep with 50 mm nominal size ballast

Spacing 8 m between tracks

Rail maintenance track 10 m wide unsealed

Signalling Communications-based centralised train control system on FMG main line with train-order and remotely controlled mainline points on BRL spur railway.

2 Advised by FMG to Calibre Rail on 15/09/2010

Page 29: CARP10026 - REP - G - 001- BRL Marillana Project - PFS Report - Rev_0

Calibre Rail Document No: CARP10026-REP-G-001

Brockman Resources – Marillana Iron Ore Project Revision No: 0

Preliminary Feasibility Study Report Issue Date: Sep 2010

Page No: Page 19 of 93

\\perfps01\CEJV$\PRO-Projects\2010\CARP10026 BR-Marillana Study\02 - PFS Study\06 Engineering\6.12 Reports\BRL Marillana Rail Project PFS Rev 0\CARP10026 - REP - G - 001-

Brockman Resources Marillana Project - Pre-Feasibility Study Report - Rev_0.doc

2.2 Design Life and Characteristics The design life of the structures is:

• 50 years for bridges; and

• 20 years for all other structures.

The design life assumes that regular and routine maintenance practices are developed and implemented in accordance with best practices for railways in the Pilbara.

2.3 Site Conditions The design:

• Considers site conditions as specified by public gazetted recognised charts and mappings;

• Includes information derived from a desktop geotechnical study, imageries and available data in the public domain; and

• Is in accordance with design codes/ standards for the region.

A more detailed site assessment will be required in the next study phase.

2.4 Modular Design Where possible all structures use modular designs. In this way offsite fabrication and assembly is maximised, and onsite erection and installation is minimised.

2.5 Interoperability Requirements The railway is designed for interoperability with the FMG railway network. The requirements are:

• Compatible locomotives and rolling stock;

• Similar track structure and track tolerances;

• Compatible signalling and communication systems; and

• Similar train consists.

The BRL railway design conforms to typical Pilbara railway standards. These standards do however, vary between operators. Interoperability with other networks in the region has not been assessed.

Page 30: CARP10026 - REP - G - 001- BRL Marillana Project - PFS Report - Rev_0

Calibre Rail Document No: CARP10026-REP-G-001

Brockman Resources – Marillana Iron Ore Project Revision No: 0

Preliminary Feasibility Study Report Issue Date: Sep 2010

Page No: Page 20 of 93

\\perfps01\CEJV$\PRO-Projects\2010\CARP10026 BR-Marillana Study\02 - PFS Study\06 Engineering\6.12 Reports\BRL Marillana Rail Project PFS Rev 0\CARP10026 - REP - G - 001-

Brockman Resources Marillana Project - Pre-Feasibility Study Report - Rev_0.doc

2.6 Topography and Digital Terrain Map The survey data used for the design alignments of this study are:

• Digital Elevation Model (DEM) data, unedited with spot height on a 10 to 20 m grid and expected vertical accuracy for 90% of the points within ±1.5 m sourced from Landgate; and

• Imagery at 1.5 m resolution (GSD) obtained from Landgate.

Unless stated otherwise, the vertical datum used is the Australian Height Datum (AHD). The project datum will be adjusted from AHD to match the FMG line levels. For detailed design in the next phase, more accurate data is required from a DEM derived from either:

• Digital photogrammetric data sourced from aerial photography over the selected route for coverage of 1:10,000 map sheets; or

• Light detection and ranging (LIDAR) or airborne laser scanning (ALS) data with accurate up to ±1 cm.

A site survey may be required to verify the digital model accuracy, especially in areas of dense vegetation. A detailed site survey is also required at the tie in point with FMG alignment.

2.7 Geotechnical Assessment The geotechnical assessment is based on a desktop study of:

• Geological maps (1:250,000);

• Cadastral maps; and

• Satellite imageries.

Site inspection reports and information collected for the Marillana Loadout Loop DFS have also been applied. No site inspection or sub surface investigations have been carried out. Tables 3.4 and 3.7 in this document outline anticipated geotechnical characteristics along each proposed alignment option. A ground-disturbing geotechnical investigation will also be required that includes sampling and geological testing at the DFS stage.

Page 31: CARP10026 - REP - G - 001- BRL Marillana Project - PFS Report - Rev_0

Calibre Rail Document No: CARP10026-REP-G-001

Brockman Resources – Marillana Iron Ore Project Revision No: 0

Preliminary Feasibility Study Report Issue Date: Sep 2010

Page No: Page 21 of 93

\\perfps01\CEJV$\PRO-Projects\2010\CARP10026 BR-Marillana Study\02 - PFS Study\06 Engineering\6.12 Reports\BRL Marillana Rail Project PFS Rev 0\CARP10026 - REP - G - 001-

Brockman Resources Marillana Project - Pre-Feasibility Study Report - Rev_0.doc

2.8 Construction Water Construction water supplies will be required for the following:

• Railway formation construction;

• Construction camps;

• Site office and amenities;

• Bridge construction;

• Road maintenance; and

• Dust suppression.

No hydrogeological work has been undertaken at this stage however it will be required in the next phase. Construction water requirements have been assessed for the OPT1 HA2 VA2 and OPT2 HA1 VA1 alignments. Where permissible, construction water may be drawn from viable surface water sources. A construction water standpipe for refilling water carts will be provided every 5 km along the railway alignment. The standpipe will draw water from either a local creek or from a turkey’s nest dam filled with bore water. In order to address possible restrictions to drawing surface water, the Capex estimate includes an allowance to drill, equip and operate one groundwater production bore at 5 km intervals along the alignment. The earthworks and drainage contractor will drill and equip the construction water supply bores required on a section of the railway alignment before the bulk earthwork starts.

Page 32: CARP10026 - REP - G - 001- BRL Marillana Project - PFS Report - Rev_0

Calibre Rail Document No: CARP10026-REP-G-001

Brockman Resources – Marillana Iron Ore Project Revision No: 0

Preliminary Feasibility Study Report Issue Date: Sep 2010

Page No: Page 22 of 93

\\perfps01\CEJV$\PRO-Projects\2010\CARP10026 BR-Marillana Study\02 - PFS Study\06 Engineering\6.12 Reports\BRL Marillana Rail Project PFS Rev 0\CARP10026 - REP - G - 001-

Brockman Resources Marillana Project - Pre-Feasibility Study Report - Rev_0.doc

2.9 Earthworks The earthworks design parameters are largely based on FMG standards for it’s Pilbara operations. The design parameters will be refined after geotechnical investigations during the DFS phase. Table 2.2 lists the key earthworks design criteria.

Table 2.2 Key Earthwork Design Criteria

Description Criteria

Minimum embankment width 6.6 m shoulder-to-shoulder at top of sub-ballast capping layer in fills and cuttings

Formation profile at top of sub ballast

capping

2.7 m wide level central surface and 1:30 cross fall to formation shoulders

Fill side slopes 1v:2h

Cut batter slopes 1v: 1.5h

Typical side drain cross section

in cuttings

Trapezoidal shaped drain 2.5 m wide at the base and 0.5 m deep

Minimum thickness of sub ballast

capping material at formation

centreline

250 mm

A preliminary assessment of cutting material and borrow sources along the alignment was completed as part of the desktop geotechnical study. Combined with the bulk cut and fill volumes produced from 12D, the geotechnical data has been used for the mass haul analysis. Normally, earthworks are the biggest variable cost for railway projects. Therefore, future design effort should focus on minimising quantities through alignment optimisation and a better cut-to-fill balance.

2.9.1 Cut and Fill Volumes 12D software was used to calculate volumes by the end-area method using the:

• Digital terrain model created from the available survey data;

• Design parameters in table 2-2; and

• Cut and fill slopes anticipated from the results of the geotechnical desktop study.

Where identified along the alignment, additional quantities of unsuitable material, foundation improvement and over-excavation in rock have been calculated from first principles.

Page 33: CARP10026 - REP - G - 001- BRL Marillana Project - PFS Report - Rev_0

Calibre Rail Document No: CARP10026-REP-G-001

Brockman Resources – Marillana Iron Ore Project Revision No: 0

Preliminary Feasibility Study Report Issue Date: Sep 2010

Page No: Page 23 of 93

\\perfps01\CEJV$\PRO-Projects\2010\CARP10026 BR-Marillana Study\02 - PFS Study\06 Engineering\6.12 Reports\BRL Marillana Rail Project PFS Rev 0\CARP10026 - REP - G - 001-

Brockman Resources Marillana Project - Pre-Feasibility Study Report - Rev_0.doc

2.9.2 Mass Haul Analysis The proposed strategy for cut and fill maximises haulage efficiency by balancing cut and fill material where practical. Where cut material is inadequate for fill requirements, suitable fill material will be sourced from borrow areas. Haul distances from cuttings have generally been maintained at less than 5 km where local borrow is available and haul distances for spoil to 2 km, where possible.

2.10 Hydrology and Drainage

2.10.1 Railway The drainage catchments and stream flow locations were identified from the DTM generated from survey data received from Landgate. The catchments for the options were delineated using a CatchSim program which provides a preliminary assessment of catchment areas. The derived catchment peak flows are based on David Flavell’s Revised Pilbara Flood Frequency Procedure. Flavell’s method is based on about twice the length of stream flow records used to develop the procedures given in Australian Rainfall and Runoff (Institution of Engineers, Australia, 1987). Flavell’s method will be used under license in the next phase of study. Catchment areas analysis and the likely bridge configurations are based on following:

• A waterway is considered to be a potential bridge site when the peak flow for the 50-year ARI is greater than or approaches 200 m3/sec.

For the PFS level of accuracy:

• The stream profiles were estimated from the contour lines and one universal latitude and longitude value was used for all catchments; and

• A full drainage review has not been done for each rail option. Typical culvert quantities were estimated from similar railway projects in the Pilbara. In later studies, a detailed catchment assessment will be completed and engineered for drainage along the selected route option.

Guide banks, levees, stream training works, rock scour protection and other erosion protection works have not been studied or estimated at this stage. The PFS rail alignment at some bridge locations will need to be optimised in the next phase. No bridge design consultants were engaged. The bridge lengths are estimated from the:

• Flow at each location;

• Rail formation height; and

Page 34: CARP10026 - REP - G - 001- BRL Marillana Project - PFS Report - Rev_0

Calibre Rail Document No: CARP10026-REP-G-001

Brockman Resources – Marillana Iron Ore Project Revision No: 0

Preliminary Feasibility Study Report Issue Date: Sep 2010

Page No: Page 24 of 93

\\perfps01\CEJV$\PRO-Projects\2010\CARP10026 BR-Marillana Study\02 - PFS Study\06 Engineering\6.12 Reports\BRL Marillana Rail Project PFS Rev 0\CARP10026 - REP - G - 001-

Brockman Resources Marillana Project - Pre-Feasibility Study Report - Rev_0.doc

• The waterway channel opening.

No further calculations were done to refine the estimate. Bridge deck could be either steel or concrete structure. More accurate assessment of the required bridges and culverts will be possible when the ALS or LIDAR data is applied.

2.10.2 Access Roads A 20 m wide unsealed access road is required for construction and will be provided by the earthwork contractor. After construction, half of the road width will be rehabilitated and the other half will become a 10 m wide Rail Maintenance Track (RMT). Options to provide RMT culverts and/or to seal its surface may be further studied in the DFS phase. All access roads will be designed for a 5-year ARI peak flow.

2.11 Level Crossings There are no high traffic roads, major named roads or other significant roads crossing the railway. RMT crossings will be installed at 10 km intervals and regional minor roads will be diverted to these crossings. The diversion of minor roads was not included in the study or the Capex estimate. Level crossings with standard signs will be provided where:

• Existing access tracks to exploration areas cross the railway; and

• The RMT crosses the railway.

Crossing details for each location will be confirmed in subsequent studies. The level of protection at level crossings will be based on risk assessments undertaken during further study and in compliance with Austroads Standards. An aerial map from Google earth indicates that the OPT1 HA2 VA2 alignment crosses an air strip at Ch. 15 Km. Whether the strip is in operation will have to be confirmed with appropriate authorities. Figure 2.1 shows the crossing at the airstrip.

Page 35: CARP10026 - REP - G - 001- BRL Marillana Project - PFS Report - Rev_0

Calibre Rail Document No: CARP10026-REP-G-001

Brockman Resources – Marillana Iron Ore Project Revision No: 0

Preliminary Feasibility Study Report Issue Date: Sep 2010

Page No: Page 25 of 93

\\perfps01\CEJV$\PRO-Projects\2010\CARP10026 BR-Marillana Study\02 - PFS Study\06 Engineering\6.12 Reports\BRL Marillana Rail Project PFS Rev 0\CARP10026 - REP - G - 001-

Brockman Resources Marillana Project - Pre-Feasibility Study Report - Rev_0.doc

Figure 2.1 OPT1 HA2 VA2 Air Strip Crossing

One landing strip was observed almost parallel to a common section of alignments near Ch. 77 Km. The lateral distance from alignment is varying from 100 m to 250 m. It appears to be in disuse. Figure 2.2 indicates the landing strip.

Figure 2.2 Landing strip near Ch. 77 Km.

2.12 Construction Camps A preliminary analysis assessed the number and size of construction camps required for the both viable alignments. The analysis was based on the construction schedule. Crew numbers per construction activity were calculated based on previous construction experience on similar projects in the Pilbara. In assessing the location and size of camps, key criteria include:

OPT1 HA2 VA2 Alignment

Air Strip

Landing Strip

Page 36: CARP10026 - REP - G - 001- BRL Marillana Project - PFS Report - Rev_0

Calibre Rail Document No: CARP10026-REP-G-001

Brockman Resources – Marillana Iron Ore Project Revision No: 0

Preliminary Feasibility Study Report Issue Date: Sep 2010

Page No: Page 26 of 93

\\perfps01\CEJV$\PRO-Projects\2010\CARP10026 BR-Marillana Study\02 - PFS Study\06 Engineering\6.12 Reports\BRL Marillana Rail Project PFS Rev 0\CARP10026 - REP - G - 001-

Brockman Resources Marillana Project - Pre-Feasibility Study Report - Rev_0.doc

• Minimising travel distances from camp to work site to help maximise productivity;

• Keeping the camps near the work fronts; and

• Using existing infrastructure to access the camp.

Further refinement of camp sizing and location will be done during the next project phase.

2.12.1 Construction Camp Facilities The standard of accommodation to be provided is typical of recent Pilbara construction camps and includes the following:

• Accommodation rooms, with ensuite bathrooms, split system air conditioning, satellite TV, refrigerator and four rooms to a building.

Central facilities would comprise:

• Administrative building;

• Kitchen and dining room;

• Laundries and linen stores;

• Administration office, communications room and shop;

• Dry mess with seating for 60% occupancy. Refrigeration and dry storage for one months supplies;

• Wet mess with outdoor beer garden;

• Ice machine facilities;

• Public telephone facilities (if not provided to rooms);

• Gymnasium;

• Recreation buildings with TV and internet rooms;

• Sports courts;

• Swimming pool;

• Medical centre with ambulance bay; and

• Male and Female toilets;

Site services will comprise:

• Access road and car park;

• Water bores and water supply and treatment;

Page 37: CARP10026 - REP - G - 001- BRL Marillana Project - PFS Report - Rev_0

Calibre Rail Document No: CARP10026-REP-G-001

Brockman Resources – Marillana Iron Ore Project Revision No: 0

Preliminary Feasibility Study Report Issue Date: Sep 2010

Page No: Page 27 of 93

\\perfps01\CEJV$\PRO-Projects\2010\CARP10026 BR-Marillana Study\02 - PFS Study\06 Engineering\6.12 Reports\BRL Marillana Rail Project PFS Rev 0\CARP10026 - REP - G - 001-

Brockman Resources Marillana Project - Pre-Feasibility Study Report - Rev_0.doc

• Fire protection and fire breaks;

• Electrical power generation and distribution;

• Sewerage system, treatment plant and effluent disposal system;

• Satellite TV for cable system and radio receiver and rebroadcast system;

• Communications system for telephone, fax, data and email;

• Fuel storage and dispensing; and

• Transport system (buses).

2.13 Control, Signalling and Asset Protection System A train order system is considered adequate to safely operate the Brockman railway spur for capacity up to 17 Mtpa. Trains would operate under train orders for both the options. The train order system uses a voice radio network linked to a train control centre via a communications backbone. Radio coverage over the entire railway network is essential for train order operation. Calibre Rail is of the opinion that FMG would be the most likely train services provider for BRL. Regardless of which entity operates the trains, FMG (TPI) will be the main line access provider and to this end all trains operating on the network will need to comply with all standards and systems prescribed by FMG. One integral system, that all locomotives will require, will be in-cab signalling and automatic train protection (ATP). in terms of operations on the Brockman rail spur the train order system will:

• Be computer based which is more accurate and issues train orders faster; and

• Use the voice and data transmission radio network to communicate orders to railway users.

Issued orders will print out in hardcopy in locomotive cabs and the drivers will report details back to train control verbally before authorisation to proceed is granted. The driver reports the authorised movement to (assumed FMG) the Train Controller, and the Controller will keep an electronic and hard copy as a record of the train order movement Train orders will control all rail vehicle movements including inspection (Hi-rail) and on-rail track maintenance vehicles. Where rail vehicles cannot shunt the track circuits, the Train Controller will apply a track block to secure the path of an order. If applied on BRL rail spur the computer-based train control system (TCS) will monitor train movements using track occupancy indications. Track circuits will:

Page 38: CARP10026 - REP - G - 001- BRL Marillana Project - PFS Report - Rev_0

Calibre Rail Document No: CARP10026-REP-G-001

Brockman Resources – Marillana Iron Ore Project Revision No: 0

Preliminary Feasibility Study Report Issue Date: Sep 2010

Page No: Page 28 of 93

\\perfps01\CEJV$\PRO-Projects\2010\CARP10026 BR-Marillana Study\02 - PFS Study\06 Engineering\6.12 Reports\BRL Marillana Rail Project PFS Rev 0\CARP10026 - REP - G - 001-

Brockman Resources Marillana Project - Pre-Feasibility Study Report - Rev_0.doc

• Lock all remotely controlled points at turnouts using wayside interlocking; and

• Help detect physically separated broken rails.

Remotely controlled turnouts on the BRL spur will have points approach locking to prevent movements in front of trains. The length of the approach locking track circuit on the railway will take into account the train characteristics and track alignment such as breaking distance, gradient and so on. Where approach track circuits are not available, such as depot exits, backtracks and bad order spurs, the movement over the points will be controlled using rail operating rules and procedures. Operating rules and procedures will be developed so train drivers can receive and verbally confirm train orders in motion. This will allow the loaded trains to proceed while crossing empty trains at the assigned passing sidings, where possible. Block section limit-of-authority (LoA) boards will be provided on the mainline, passing sidings, and approaches to the passing sidings, depot, mine and port. Trains will run to schedules and allocated pathways, which will be generated by computer-based train graph plans. A BRL rail corridor TCC will control mainline points, backtrack end points and catch points protecting the mainline. Points indicators, visible over the normal braking distance, will be positioned on the mainline for driver interface. Smaller versions of these indicators will be used in yard areas, backtracks and depots. Track circuits associated with the points will be used to provide point locking (dead locking) for safety. Asset protection devices are required to protect the rail infrastructure to minimise disruption to train operations. Asset protection includes:

• Stream flow detectors (SFDs);

• Dragging equipment detectors (DEDs); and

• Hot box/hot wheel detectors (HBWDs).

These wayside detectors will be strategically located along the railway and linked to the FMG TCC via the communications backbone. The TCC will monitor the hazards that may endanger train movements on the rail infrastructure.

2.13.1 Turnout Point Control

Points on the mainline at passing sidings, the mine loop and terminal points will be remotely controlled from the TCC. Point motors will be configured to allow manual operation during a power failure or maintenance. Backtrack points and catchpoints will be manually operated after the Train Controller releases them.

Page 39: CARP10026 - REP - G - 001- BRL Marillana Project - PFS Report - Rev_0

Calibre Rail Document No: CARP10026-REP-G-001

Brockman Resources – Marillana Iron Ore Project Revision No: 0

Preliminary Feasibility Study Report Issue Date: Sep 2010

Page No: Page 29 of 93

\\perfps01\CEJV$\PRO-Projects\2010\CARP10026 BR-Marillana Study\02 - PFS Study\06 Engineering\6.12 Reports\BRL Marillana Rail Project PFS Rev 0\CARP10026 - REP - G - 001-

Brockman Resources Marillana Project - Pre-Feasibility Study Report - Rev_0.doc

The interlocking will secure the points, and will:

• Track-lock or dead-lock the points when this track circuit is occupied; and

• Approach-lock the points when trains are detected on the approach track.

When the point machine is switched to manual control it will isolate the electrical operation for safety. This control transfer will be managed under the rail operating rules and procedure with permission from the TCC. Remotely controlled points have indicators that show the driver whether the points are set to either straight or diverge. The indicators are visible from a sufficient distance so that the driver can stop if the point setting is not as expected.

2.13.2 Track Circuits Track circuits will be provided for train detection along the railway and passing siding. Coded track circuits provide the best long distance performance because they minimise wayside equipment and telemetry links to train control. Coded track circuits can transmit vital information to the in-cab signalling system. Audio frequency overlay track circuits will be provided for points dead locking at the passing sidings and yard to minimise the number of insulated rail joints. Track circuit lengths will be scaled to suit the ballast condition for reliable operation. The maximum length of coded track circuits is 8 km. The last single line track circuit on the approach to a passing siding, yard, port and mine will typically be 5 km long. This length will be confirmed in later project phases considering:

• The line speed taking into account braking distance;

• Grade; and

• Train characteristic; and so on.

Mid-blocks will be required for track circuits. The track circuits beyond the first location will be selected and spaced about 8 km apart. Where practical, all wayside equipment near SFD sites will be located a safe distance from the detector to minimise the risk of equipment damage from flooding. The area beyond the catchpoints at the backtrack, depot, port and mine do not require track circuits, and are considered as dark territory for signalling and control purposes. Track circuits do not always detect broken or fractured rails and so a maintenance strategy may be needed to mitigate this track circuit function.

Page 40: CARP10026 - REP - G - 001- BRL Marillana Project - PFS Report - Rev_0

Calibre Rail Document No: CARP10026-REP-G-001

Brockman Resources – Marillana Iron Ore Project Revision No: 0

Preliminary Feasibility Study Report Issue Date: Sep 2010

Page No: Page 30 of 93

\\perfps01\CEJV$\PRO-Projects\2010\CARP10026 BR-Marillana Study\02 - PFS Study\06 Engineering\6.12 Reports\BRL Marillana Rail Project PFS Rev 0\CARP10026 - REP - G - 001-

Brockman Resources Marillana Project - Pre-Feasibility Study Report - Rev_0.doc

2.13.3 Interlocking Equipment Wayside interlocking equipment will be provided to secure remotely controlled points. The interlocking will be programmable solid state equipment with safety integrity level 4 (SIL4) that can support:

• Track circuits;

• A wide range of interface options;

• Data logging; and

• Remote and local diagnostic facilities.

Standardisation and interoperability with FMG rail infrastructure will be addressed in the detailed design phase.

2.13.4 Power Supply Solar power with a battery back up power supply will be provided for wayside equipment. Wayside signal locations using solar power will have a power socket to allow local signal site operation from a portable generator for battery maintenance or prolonged overcast conditions. The system will:

• Maintain power to the site for eight days without solar input; and

• Have a recharge period of twenty days from nominal maximum discharge.

Nominal maximum discharge will be designed to prevent damage to the batteries from over discharge. Solar charge controllers will ensure the batteries have a long and trouble-free operational life. Power supply status and solar panel unit monitoring information will be transmitted to the TCC via the communications backbone to warn of high and low capacity and security. Each signalled site will be constructed with an earth grid to provide a low resistance path for lightning. Photo-voltaic arrays of high capacity solar cells will power most signal locations. The cells will charge sealed, low-maintenance, gel cell lead-acid battery banks.

2.13.5 Level Crossing Protection Most railway crossings for both options will be protected by signs. The level of protection at crossing locations will be further assessed in later studies.

Page 41: CARP10026 - REP - G - 001- BRL Marillana Project - PFS Report - Rev_0

Calibre Rail Document No: CARP10026-REP-G-001

Brockman Resources – Marillana Iron Ore Project Revision No: 0

Preliminary Feasibility Study Report Issue Date: Sep 2010

Page No: Page 31 of 93

\\perfps01\CEJV$\PRO-Projects\2010\CARP10026 BR-Marillana Study\02 - PFS Study\06 Engineering\6.12 Reports\BRL Marillana Rail Project PFS Rev 0\CARP10026 - REP - G - 001-

Brockman Resources Marillana Project - Pre-Feasibility Study Report - Rev_0.doc

2.13.6 Broken Rail Detection (BRD) Broken rail detectors are not provided. Track construction method and regular maintenance practices such as ultrasonic inspections will greatly reduced the incidence of broken rails. Using conventional track circuits designed to operate over extreme distances purely for broken rail detection is possible. However, their operating reliability over long distances needs to be assessed. Track circuits will help to detect broken rails and train occupation on a section of the railway. Since track occupations occur in a logical sequence as trains move along the track, the TCS can indicate to the Train Controller:

• Unexpected track occupations; or

• Track occupations after a train should have passed.

Such situations can occur if a broken rail occurs during train passage or if one or more wagons are left behind.

2.13.7 Dragging Equipment Detectors (DED) DEDs will:

• Identify any dragging equipment from rolling stock;

• Be located a safe braking distance from mainline turnouts and bridges; and

• Send alarms to the TCC and transmit to the train driver to bring the train to stop, thus minimising damages to the infrastructure.

2.13.8 Hot Wheel/Hot Bearing Detectors (HBWD) HBWDs will be installed along the railway to detect high temperatures in rolling stock wheels and bearings. Their location will be on level straight sections of the railway, with no or small gradients and where brakes should not have been used recently. HBWD sites must also be at sufficient distance from terminals to allow wheels and bearings to have reached normal operating temperature and where there are nearby sidings to allow defective wagons to be cut out of rakes easily. Local temperature and fault alarms are transmitted by voice radio to the train driver, and to the TCC. HBWD data can be used to predict bearing failures and provide information for planned wagon maintenance and so are recommended for this project. The locations of HBWDs will be assessed in a future study.

Page 42: CARP10026 - REP - G - 001- BRL Marillana Project - PFS Report - Rev_0

Calibre Rail Document No: CARP10026-REP-G-001

Brockman Resources – Marillana Iron Ore Project Revision No: 0

Preliminary Feasibility Study Report Issue Date: Sep 2010

Page No: Page 32 of 93

\\perfps01\CEJV$\PRO-Projects\2010\CARP10026 BR-Marillana Study\02 - PFS Study\06 Engineering\6.12 Reports\BRL Marillana Rail Project PFS Rev 0\CARP10026 - REP - G - 001-

Brockman Resources Marillana Project - Pre-Feasibility Study Report - Rev_0.doc

2.13.9 Stream Flow Detectors (SFD) SFDs will be located where hydrological data suggests that water could overtop the railway and compromise track integrity. If a SFD alarm comes on the associated track circuit shows the track as occupied on the TCS. Locations requiring SFDs will be identified in later studies.

2.14 Voice and Data Communication The scope of the communications study includes:

• Develop an architecture and roadmap for a BRL rail communications system;

• Consider the following systems/technologies:

− Microwave radio system;

− Fibre Optic Cable;

− Wayside vital and/or non-vital communication systems;

− Land mobile two-way radio system that;

� has three channels for train control and operational personnel;

� has wide area conventional analogue voting system; and

� can provide construction camp communications.

• The communication system should be able to integrated into the FMG communication system.

Reliable voice communication network with redundant coverage is essential for safe and efficient rail operation. The communication options are based on a 25 year life. The communications system will:

• Support an internet protocol (IP) network for rail signalling, asset protection and mobile voice communications for railway operations;

• Provide temporary and permanent communications for camps; and

• Allow voice communications during construction.

The communications backbone can be either a fibre-optic cable or a microwave radio system. Fibre-optic cable is likely to be more expensive. However, it may be the best option based on the anticipated project life. The system can provide:

• Sufficient capacity for future expansion; and

Page 43: CARP10026 - REP - G - 001- BRL Marillana Project - PFS Report - Rev_0

Calibre Rail Document No: CARP10026-REP-G-001

Brockman Resources – Marillana Iron Ore Project Revision No: 0

Preliminary Feasibility Study Report Issue Date: Sep 2010

Page No: Page 33 of 93

\\perfps01\CEJV$\PRO-Projects\2010\CARP10026 BR-Marillana Study\02 - PFS Study\06 Engineering\6.12 Reports\BRL Marillana Rail Project PFS Rev 0\CARP10026 - REP - G - 001-

Brockman Resources Marillana Project - Pre-Feasibility Study Report - Rev_0.doc

• Support other services, such as mine and port communication and control systems.

The microwave radio system has a lower Capex, but it:

• Will not be adequate for operations over a 25 year project life; and

• Provides limited capacity for future expansion.

It may provide Capex savings in the short term and equipment could be upgraded later as necessary. A microwave radio system has more uncertainty and so further investigation is required to determine whether it is feasible based on:

• Signal propagation;

• Terrain data;

• Maintenance; and

• Capital cost.

This study assumes that:

• Fibre-optic cable will be adopted. The Capex for the fibre has been estimated to ±25% accuracy; and

• It is possible to interface successfully to the FMG network backbone systems, if necessary.

2.14.1 Camp Communications Camp communications infrastructure will provide:

• Satellite communications;

• Mobile phone systems;

• Telephone systems;

• Internet access; and

• Construction two-way radio systems.

The base case is a satellite system that will provide communications into and out of the construction camps. The camps will share a nominal 10 Mbps bandwidth of dedicated capacity. This bandwidth will be shared by the following:

Page 44: CARP10026 - REP - G - 001- BRL Marillana Project - PFS Report - Rev_0

Calibre Rail Document No: CARP10026-REP-G-001

Brockman Resources – Marillana Iron Ore Project Revision No: 0

Preliminary Feasibility Study Report Issue Date: Sep 2010

Page No: Page 34 of 93

\\perfps01\CEJV$\PRO-Projects\2010\CARP10026 BR-Marillana Study\02 - PFS Study\06 Engineering\6.12 Reports\BRL Marillana Rail Project PFS Rev 0\CARP10026 - REP - G - 001-

Brockman Resources Marillana Project - Pre-Feasibility Study Report - Rev_0.doc

• Telephone;

• Mobile phone;

• Business data network for Client’s and major contractors’ use; and

• Internet for camp residents.

The requirement for mobile phone systems will be assessed in the next phase of the project. A decision could be made to provide mobile phone capability or fixed telephone services in each camp room. Construction camp residents are commonly provided internet access for personal communications, business and entertainment. Camp residents’ internet can be provided by:

• The primary satellite network;

• A dedicated satellite network; and/or

• A 3G mobile data network.

The most appropriate approach for the construction camps will be determined in the detailed design phase. Additional radio channels will also be required for construction. The construction radio systems can be located at either:

• The construction camps where AC power will be available but will require radio masts; or

• Existing sites where existing masts can be used but where the solar power must be augmented.

The location will be determined during the detailed design phase.

Page 45: CARP10026 - REP - G - 001- BRL Marillana Project - PFS Report - Rev_0

Calibre Rail Document No: CARP10026-REP-G-001

Brockman Resources – Marillana Iron Ore Project Revision No: 0

Preliminary Feasibility Study Report Issue Date: Sep 2010

Page No: Page 35 of 93

\\perfps01\CEJV$\PRO-Projects\2010\CARP10026 BR-Marillana Study\02 - PFS Study\06 Engineering\6.12 Reports\BRL Marillana Rail Project PFS Rev 0\CARP10026 - REP - G - 001-

Brockman Resources Marillana Project - Pre-Feasibility Study Report - Rev_0.doc

Intentionally Blank

Page 46: CARP10026 - REP - G - 001- BRL Marillana Project - PFS Report - Rev_0

Calibre Rail Document No: CARP10026-REP-G-001

Brockman Resources – Marillana Iron Ore Project Revision No: 0

Preliminary Feasibility Study Report Issue Date: Sep 2010

Page No: Page 36 of 93

\\perfps01\CEJV$\PRO-Projects\2010\CARP10026 BR-Marillana Study\02 - PFS Study\06 Engineering\6.12 Reports\BRL Marillana Rail Project PFS Rev 0\CARP10026 - REP - G - 001-

Brockman Resources Marillana Project - Pre-Feasibility Study Report - Rev_0.doc

3.0 OPTIONS This study considered the following major railway and infrastructure options:

• Railway routes from the BRL mine to the FMG line through three corridors; and

• Conceptual signalling and communications designs.

3.1 Railway Route Options For the railway route, the PFS scope was to develop and compare railway alignments within three BRL-specified corridors. The study terms of reference stipulated that alignments must remain within the corridors. Figure 3.1 shows the study corridors. These corridors are about 2 km wide. Starting from the mine, for about 36 km all three corridors are common and run parallel to an existing BHPBIO railway line. After that:

• Corridor OPT3 branches out to join the FMG rail line.

• Corridors OPT1 and OPT2 continue further as one corridor for about 9 km parallel to BHPBIO line and diverge eastwards for next 13 km. At this point:

− Corridor OPT2 goes east to join FMG line; and

− Corridor OPT1 goes back towards the BHPBIO line, runs north, and stays within 1 km of the BHPBIO line until it joins the FMG line.

CAR developed a large number of alignments within each corridor to find the optimum alignment. Based on experience, judgement and the design criteria, the following 12 horizontal alignments, with vertical variations in each corridor, were selected for further study:

• 5 in corridor OPT1;

• 3 in corridor OPT2; and

• 4 in corridor OPT3.

High level Capex estimates based on the earthwork quantities were produced and shown in Table 3.1. The options under each corridor are ranked on the basis of earthworks capital cost. Plan layouts of these alignments are on general arrangement drawing CARP10026-SKE-C-0074 in appendix D.

Page 47: CARP10026 - REP - G - 001- BRL Marillana Project - PFS Report - Rev_0

Calibre Rail Document No: CARP10026-REP-G-001

Brockman Resources – Marillana Iron Ore Project Revision No: 0

Preliminary Feasibility Study Report Issue Date: Sep 2010

Page No: Page 37 of 93

\\perfps01\CEJV$\PRO-Projects\2010\CARP10026 BR-Marillana Study\02 - PFS Study\06 Engineering\6.12 Reports\BRL Marillana Rail Project PFS Rev 0\CARP10026 - REP - G - 001-

Brockman Resources Marillana Project - Pre-Feasibility Study Report - Rev_0.doc

Figure 3.1 Corridors for 12 Alignment Options

Page 48: CARP10026 - REP - G - 001- BRL Marillana Project - PFS Report - Rev_0

Calibre Rail Document No: CARP10026-REP-G-001

Brockman Resources – Marillana Iron Ore Project Revision No: 0

Preliminary Feasibility Study Report Issue Date: Sep 2010

Page No: Page 38 of 93

\\perfps01\CEJV$\PRO-Projects\2010\CARP10026 BR-Marillana Study\02 - PFS Study\06 Engineering\6.12 Reports\BRL Marillana Rail Project PFS Rev 0\CARP10026 - REP - G - 001-

Brockman Resources Marillana Project - Pre-Feasibility Study Report - Rev_0.doc

Table 3.1 Options Earthworks Cost Estimates

Options Length (km)

Earthworks Capital Cost

($M)

Cost Per km ($M)

Rank in each

corridor

OPT1 HA1 VA1 99.59 225.9 2.27 4

OPT1 HA2 VA1 95.34 163.6 1.72 1

OPT1 HA2 VA2 95.34 207.3 2.17 2

OPT1 HA3 VA1 95.89 224.9 2.35 3

OPT1 HA4 VA1 98.71 232.1 2.35 5

OPT2 HA1 VA1 70.47 110.1 1.56 1

OPT2 HA1 VA2 70.44 142.6 2.02 2

OPT2 HA2 VA2 69.77 180.1 2.58 3

OPT3 HA1 VA1 70.25 125.7 1.79 1

OPT3 HA1 VA2 70.25 310.6 4.42 3

OPT3 HA2 VA2 70.29 306.1 4.36 2

OPT3 HA3 VA3 71.70 394.6 5.50 4

The alignments selected for train performance study were:

• OPT1 HA2 VA1;

• OPT1 HA2 VA2;

• OPT2 HA1 VA1. and

• OPT3 HA1 VA1 .

Figure 3.2 shows these alignments. The advantages and disadvantages of these Options are shown on table 3.2.

Page 49: CARP10026 - REP - G - 001- BRL Marillana Project - PFS Report - Rev_0

Calibre Rail Document No: CARP10026-REP-G-001

Brockman Resources – Marillana Iron Ore Project Revision No: 0

Preliminary Feasibility Study Report Issue Date: Sep 2010

Page No: Page 39 of 93

\\perfps01\CEJV$\PRO-Projects\2010\CARP10026 BR-Marillana Study\02 - PFS Study\06 Engineering\6.12 Reports\BRL Marillana Rail Project PFS Rev 0\CARP10026 - REP - G - 001-

Brockman Resources Marillana Project - Pre-Feasibility Study Report - Rev_0.doc

Alignment OPT1-HA2-VA1and

Alignment OPT1-HA2-VA2

AlignmentOPT1-HA1-VA1

AlignmentOPT3-HA1-VA1

Commonalignment

Scientific Reserve

Brockman Stage 2 battery limit

Brockman Stage 1Railway alignmentFMG railway

Legend

Road

BHPBIO railway

Figure 3.2 Alignment Options selected for Train Performance Study

Alignment OPT2-HA1-VA1

Page 50: CARP10026 - REP - G - 001- BRL Marillana Project - PFS Report - Rev_0

Calibre Rail Document No: CARP10026-REP-G-001

Brockman Resources – Marillana Iron Ore Project Revision No: 0

Preliminary Feasibility Study Report Issue Date: Sep 2010

Page No: Page 40 of 93

\\perfps01\CEJV$\PRO-Projects\2010\CARP10026 BR-Marillana Study\02 - PFS Study\06 Engineering\6.12 Reports\BRL Marillana Rail Project PFS Rev 0\CARP10026 - REP - G - 001-

Brockman Resources Marillana Project - Pre-Feasibility Study Report - Rev_0.doc

Table 3.2 Four Options: Advantages and Disadvantages

Alignment Options

Advantages Disadvantages Comments

OPT1 HA2 VA1 Lowest cost in corridor OPT1 Lowest loaded train speed is 14 k/hr for a distance of 2 km which is below the recommended minimum speed of 18.5 km for DC locomotives

The alignment has not been studied further due to unsatisfactory operational performance.

OPT1 HA2 VA2 • Minimum train speed is 20 k/hr for 1 km only

• Travel time reduced by 7 mins.

• Train performance has improved.

Higher Capital Cost as compared to OPT1 HA2 VA1

This option has been studied in more detail in this PFS.

OPT2 HA1 VA1 Lowest unit and overall earthworks cost

Loaded train speed falls to less than is 18 km/hr for 3 km which is undesirable for sustaining train speed for DC locomotives on this alignment.

This option has been studied in more detail in this PFS.

OPT3 HA1 VA1 Lowest cost in OPT3 corridor Lowest loaded train speed is 14 Km/hr for a distance of 4 Km just before joining FMG main line. This is below the recommended minimum continuous speed of 18.5 Km for DC locomotives.

The alignment has not been studied further due to poor operational performance.

OPT1 HA2 VA2 and OPT2 HA1 VA1 were selected for further study. Figure 3.3 shows the final two alignments considered. Table 3.3 shows the approximate track lengths and operational lengths from the loadout loop battery limit to the OPT1 HA2 VA2 and OPT2 HA1 VA1 junctions with the FMG line.

Page 51: CARP10026 - REP - G - 001- BRL Marillana Project - PFS Report - Rev_0

Calibre Rail Document No: CARP10026-REP-G-001

Brockman Resources – Marillana Iron Ore Project Revision No: 0

Preliminary Feasibility Study Report Issue Date: Sep 2010

Page No: Page 41 of 93

\\perfps01\CEJV$\PRO-Projects\2010\CARP10026 BR-Marillana Study\02 - PFS Study\06 Engineering\6.12 Reports\BRL Marillana Rail Project PFS Rev 0\CARP10026 - REP - G - 001-

Brockman Resources Marillana Project - Pre-Feasibility Study Report - Rev_0.doc

Alignment OPT2-HA1-VA1

Commonalignment

Scientific Reserve

Brockman Stage 2 battery limit

Brockman Stage 1Railway alignment

Alignment OPT1-HA2-VA2

FMG railway

Legend

RoadBHPBIO railway

Marillanamines

Figure 3.3 Simplified Layout of Final Two Alignment Options

Page 52: CARP10026 - REP - G - 001- BRL Marillana Project - PFS Report - Rev_0

Calibre Rail Document No: CARP10026-REP-G-001

Brockman Resources – Marillana Iron Ore Project Revision No: 0

Preliminary Feasibility Study Report Issue Date: Sep 2010

Page No: Page 42 of 93

\\perfps01\CEJV$\PRO-Projects\2010\CARP10026 BR-Marillana Study\02 - PFS Study\06 Engineering\6.12 Reports\BRL Marillana Rail Project PFS Rev 0\CARP10026 - REP - G - 001-

Brockman Resources Marillana Project - Pre-Feasibility Study Report - Rev_0.doc

Table 3.3 Track and Operational Lengths to OPT 1 Junction on FMG Line

Options Route Length (km)

Operation on FMG Line to OPT1 HA2 VA2

Junction (km)

Total Operation Length (km)

OPT1 HA2 VA2 95.3 0.0 95.3

OPT2 HA1 VA1 70.5 29.6 100.1

3.2 OPT1 HA2 VA2

3.2.1 Route Description The OPT1 HA2 VA2 route:

• Starts from the mine loadout battery limit at Ch. 105.5;

• Runs parallel to BHPBIO’s line up to Ch. 69.0 on the east side;

• Detours between Ch. 69.0 and Ch 35.0. to avoid high ground;

• Runs almost parallel to the BHPBIO line offset 1 km to Ch. 29.0; and

• Head east to joins the FMG line at Ch. 10.2 (FMG assumed Ch. 190)

This alignment shares the same horizontal alignment with the OPT1 HA2 VA1. The vertical profile has been modified to meet the minimum locomotive speed requirement.

3.2.2 Railway Operations and Train Performance Modelling Based on the details mentioned in section 4, following conclusions can be drawn:

• This option will work with two headend DC traction locomotives, 240 loaded ore cars and two banking locomotives where required as shown below;

b rockman

resources.

bro ckman

resources.

broc kman

resources.

br ockman

resources .

240 loaded ore cars2 head-end Mainline DC locomotives 2 Banker DC locomotives

• On this alignment option, the banker locomotives are not required on FMG mainline and can return back to mine on their own (light engine);

• Loaded trains operating over the Chichester Ranges from Ch. 15 to 29 will be speed-limited to 50km/h using ECP and dynamic braking on all four locomotives;

• All empty trains can be hauled by 2 locomotives on the return trip;

Page 53: CARP10026 - REP - G - 001- BRL Marillana Project - PFS Report - Rev_0

Calibre Rail Document No: CARP10026-REP-G-001

Brockman Resources – Marillana Iron Ore Project Revision No: 0

Preliminary Feasibility Study Report Issue Date: Sep 2010

Page No: Page 43 of 93

\\perfps01\CEJV$\PRO-Projects\2010\CARP10026 BR-Marillana Study\02 - PFS Study\06 Engineering\6.12 Reports\BRL Marillana Rail Project PFS Rev 0\CARP10026 - REP - G - 001-

Brockman Resources Marillana Project - Pre-Feasibility Study Report - Rev_0.doc

• Passing sidings are not required for two loaded trains per day for transportation of 17 Mtpa iron ore; and

• From an operational point of view, this alignment is the preferred option because it avoids the need for banker locomotives to operate s on the FMG mainline.

3.2.3 Passing Sidings and Refuge siding Though operational studies have not indicated requirement of passing sidings, two passing sidings are required, one just before junction with FMG to take care of the situation where BRL may have to hold an empty train bound for mines in order to provide unhindered entry to loaded train on FMG rail line and other near mines to hold mine bound trains. In addition, a 450 m clear standing length refuge siding is proposed about midway along the BRL line. With proposed passing sidings and refuge siding total length of track for this alignment comes to 102.92 Km.

3.2.4 Geotechnical Desktop Assessment Table 3.4 shows the geotechnical desktop assessment for excavation in cuttings along this option.

Table 3.4 Geotechnical Desktop Assessment for OPT1 HA2 VA2

Chainage Method Materials

From To Common (%)

Rock (%)

Types 2 & 3F1 (%)

Type 3G2 (%)

Type 3C2 (%)

10.0 70.0 10 90 30 30 40

70.0 105.0 100 0 100 0 0 1 types 2 & 3F materials are suitable for top 1m below the subgrade level in transition layer, 2 type 3G/3C material is suitable for layers below transition layer.

3.2.5 Earthworks Bulk earthworks for this option are estimated to be about:

• 7.11 million m3 of cut;

• 2.43 million m3 of fill; and

• 0.75 million m3 of additional fill for lifting alignment at bridge locations.

Page 54: CARP10026 - REP - G - 001- BRL Marillana Project - PFS Report - Rev_0

Calibre Rail Document No: CARP10026-REP-G-001

Brockman Resources – Marillana Iron Ore Project Revision No: 0

Preliminary Feasibility Study Report Issue Date: Sep 2010

Page No: Page 44 of 93

\\perfps01\CEJV$\PRO-Projects\2010\CARP10026 BR-Marillana Study\02 - PFS Study\06 Engineering\6.12 Reports\BRL Marillana Rail Project PFS Rev 0\CARP10026 - REP - G - 001-

Brockman Resources Marillana Project - Pre-Feasibility Study Report - Rev_0.doc

About 3.3 million m3 of earthworks is confined in a cutting of about 10.6 km length between Ch. 35.0 and 45.6. The maximum cutting depth is 18.6 m with an average depth of 9.5 m. The long cutting was unavoidable in order to achieve a rising gradient of 0.25% required for maintaining minimum train speed over long continuous ascent. There are two short, fill embankments with culverts at Ch. 44 km and 44.8 Km which might assist in draining this cutting. A standard 2.5 m wide side drain has been considered in the earthworks model. The high runoff in long cuttings may require wider side drains which will further increase the cutting earthwork quantities. This additional earthwork will have to be quantified in the next study phase. Due to the large volume of materials anticipated from cuttings for the first 50 km of this alignment, earthworks package for rail formation has been divided into four work fronts with output ranging from 6000m3 to 10,0003. First three earthwork fronts will operate within 50 km from the tie-in point with the existing FMG railway, and the fourth front will work from the mine end heading northerly direction. Although the cutting quantities are much larger than the fill quantities, about 1.7 million m3 of borrow soil will be required due to haul distance limitations and unsuitability of cut material at some locations. Raising of alignment at bridge locations has added about 0.750 million m3 to the earthwork in fill. Modifying the track alignment model may result into corresponding reduction in cut volumes there by compensating addition cost of this earthwork in fill. Due to very high volumes in cuttings, mostly assumed to be rock, this activity is critical and drives the project duration.

3.2.6 Bridges and Culverts A high level review of the major catchments for this alignment identified 2 potential sites for bridges and 4 potential sites for major culverts. Both options share an alignment section from Ch. 69 to 105 in which these 4 potential Major Culverts are located. Table 3.5 shows the bridge & major culvert locations and approximate lengths on OPT1 HA2 VA2.

Table 3.5 Bridges & Major culverts Locations and Lengths

No. Type of Waterway

Crossing Chainage (Km) Total Length (m)

1 Bridge 11.8 120

2 Major Culvert 82.1 100

3 Major Culvert 83.7 80

4 Bridge 88.1 260

5 Major Culvert 95.4 100

6 Major Culvert 101.1 100

Page 55: CARP10026 - REP - G - 001- BRL Marillana Project - PFS Report - Rev_0

Calibre Rail Document No: CARP10026-REP-G-001

Brockman Resources – Marillana Iron Ore Project Revision No: 0

Preliminary Feasibility Study Report Issue Date: Sep 2010

Page No: Page 45 of 93

\\perfps01\CEJV$\PRO-Projects\2010\CARP10026 BR-Marillana Study\02 - PFS Study\06 Engineering\6.12 Reports\BRL Marillana Rail Project PFS Rev 0\CARP10026 - REP - G - 001-

Brockman Resources Marillana Project - Pre-Feasibility Study Report - Rev_0.doc

The vertical alignment has not been reviewed from a drainage perspective. However, two of the bridge/major culvert sites will need to be lifted by at least 1.7 m which will require about 749,000 m3 of additional fill. Table 3.6 shows the additional earthworks required.

Table 3.6 Additional Earthworks for Bridges/Major Culverts

Chainage Lift (m) Fill Increase (m3)

82.1 1.7 453,000

88.1 1.7 296,000

This alignment runs parallel to existing BHPBIO railway for 36 km from Marillana mines towards the port. Five waterway crossings have been proposed in this section from Sr. No. 2 to 6 as shown in table 3.5. As the proposed BRL alignment is on the downstream side of BHPB railway, the bridges/culverts on BHPB rail line may significantly affect the hydrological design on BR alignment. Since no site inspection has been done, the BHPBIO bridge and culvert locations are not known at this stage. Three bridge crews are required to construct three bridges/Major Culverts simultaneously. Since earthworks are a critical activity in this option, this requirement must be further evaluated in later study phases.

3.2.7 Construction Camps Construction camp sizing has been determined with the help of march chart, crew sizes, crew productivity, plant types, plant outputs etc. Based on the assumption on earthwork and bridge construction, three temporary construction camps are required to meet the project schedule shown in Figure 6.1. Camp size for this option will be up to 600 rooms at the peak of construction. The actual site conditions may not allow opening of multiple construction fronts altering the overall project duration and construction camp requirements.

3.2.8 Construction Water Requirement Assessment Total requirement of construction water has been assessed as 1.14 billion litres. Para 2.8 discusses details about requirement and sources.

Page 56: CARP10026 - REP - G - 001- BRL Marillana Project - PFS Report - Rev_0

Calibre Rail Document No: CARP10026-REP-G-001

Brockman Resources – Marillana Iron Ore Project Revision No: 0

Preliminary Feasibility Study Report Issue Date: Sep 2010

Page No: Page 46 of 93

\\perfps01\CEJV$\PRO-Projects\2010\CARP10026 BR-Marillana Study\02 - PFS Study\06 Engineering\6.12 Reports\BRL Marillana Rail Project PFS Rev 0\CARP10026 - REP - G - 001-

Brockman Resources Marillana Project - Pre-Feasibility Study Report - Rev_0.doc

3.3 OPT2 HA1 VA1

3.3.1 Route Description The OPT2 HA1 VA1 route:

• Starts from the mine loadout battery limit at Ch. 105.5;

• Runs parallel to BHPBIO’s line up to Ch. 69.0 on the east side; and

• Heads east to joins the FMG line at Ch. 35.1 (FMG assumed Ch. 219.6).

This alignment has been selected because it is the lowest earthworks capital cost option in corridor OPT2. The vertical profile satisfies the operational requirement of DC locomotives and maintains an average loaded train speed of 42 km/hr.

3.3.2 Railway Operations and Train Performance Modelling

• This option will work with two head end DC traction locomotives, 240 loaded ore cars and two banking locomotives where required as shown below;

brockman

resources.

bro ckma n

resources.

br o ckma n

resources.

br ockman

resources.

240 loaded ore cars2 head-end Mainline DC locomotives 2 Banker DC locomotives

• The bankers will remain attached to the loaded trains until beyond Ch. 200 on the FMG mainline or up to Hunter Siding. This may cause capacity constraints on the FMG main line railway due to the extra train pathways required for returning banking locomotives to the BRL railway spur;

• Loaded rains operating over the Chichester Ranges between Ch. 36 and 50 will be speed-limited to 50 km/h using ECP and dynamic braking on all four locos;

• All empty trains can be hauled by two locomotives on the return trip;

• passing sidings are not required for two loaded trains per day for transportation of 17 Mtpa iron ore; and

• From an operational point of view, this alignment may be considered inferior to OPT1 HA2 VA2 because a loaded train must be banked on FMG mainline to Ch. 200 or to Hunter Siding at Ch. 182. Banker locomotives will occupy valuable train pathways on the FMG main line on return trip till BRL rail junction. This may trigger a requirement by FMG for BRL to fund extra capacity infrastructure on the FMG main line to compensate for the extra capacity required.

Page 57: CARP10026 - REP - G - 001- BRL Marillana Project - PFS Report - Rev_0

Calibre Rail Document No: CARP10026-REP-G-001

Brockman Resources – Marillana Iron Ore Project Revision No: 0

Preliminary Feasibility Study Report Issue Date: Sep 2010

Page No: Page 47 of 93

\\perfps01\CEJV$\PRO-Projects\2010\CARP10026 BR-Marillana Study\02 - PFS Study\06 Engineering\6.12 Reports\BRL Marillana Rail Project PFS Rev 0\CARP10026 - REP - G - 001-

Brockman Resources Marillana Project - Pre-Feasibility Study Report - Rev_0.doc

3.3.3 Passing Sidings and Refuge siding Though operational studies have not indicated requirement of passing sidings, two passing sidings have been found essential, one just before tie in with FMG to take care of the situation where BRL may have to hold an empty train bound for mines in order to provide unhindered entry to loaded train on FMG rail line and other near mines to hold mine bound trains. In addition, a 450 m clear standing length refuge siding is proposed about midway along the BRL line. With proposed passing sidings and refuge siding total length of track for this alignment comes to 77.58 Km.

3.3.4 Geotechnical Desktop Assessment

Table 3.7 shows the geotechnical desktop assessment for excavation in cuttings along this option.

Table 3.7 Geotechnical Desktop Assessment for OPT2 HA1 VA1

Chainage Method Materials

From To Common (%)

Rock (%)

Types 2 & 3F1 (%)

Type 3G2 (%)

Type 3C2 (%)

35.0 70.0 10 90 30 30 40

70.0 105.0 100 0 100 0 0 1 types 2 & 3F materials are suitable for top 1m below the subgrade level in transition layer, 2 type 3G/3C material is suitable for layers below transition layer.

3.3.5 Earthworks Bulk earthworks for this option are estimated to be approximately:

• 1.04 million m3 of cut;

• 2.13 million m3 of fill; and

• 1.2 million m3 of additional fill for lifting alignment at bridge locations.

A standard 2.5 m wide side drain has been considered in the earthworks model. Raising of alignment at bridge locations has added about 1.2 million m3 to the earthwork in fill. Modifying the track alignment model may result into corresponding reduction in cut volumes there by compensating addition cost of this earthwork in fill. Two work fronts will be required in cuttings and one work front in borrow area.

Page 58: CARP10026 - REP - G - 001- BRL Marillana Project - PFS Report - Rev_0

Calibre Rail Document No: CARP10026-REP-G-001

Brockman Resources – Marillana Iron Ore Project Revision No: 0

Preliminary Feasibility Study Report Issue Date: Sep 2010

Page No: Page 48 of 93

\\perfps01\CEJV$\PRO-Projects\2010\CARP10026 BR-Marillana Study\02 - PFS Study\06 Engineering\6.12 Reports\BRL Marillana Rail Project PFS Rev 0\CARP10026 - REP - G - 001-

Brockman Resources Marillana Project - Pre-Feasibility Study Report - Rev_0.doc

3.3.6 Bridges and Culverts Six potential bridge sites and 4 potential major culverts sites were identified. One of the bridge sites and four major culvert sites are the same as in OPT1 HA2 VA2. Table 3-8 shows the bridge/major culverts locations and lengths.

Table 3.8 Bridges/ Major Culverts Locations and Lengths

No. Type of Waterway

Crossing Chainage (km) Total Length (m)

1 Bridge 40.7 200

2 Bridge 41.3 160

3 Bridge 41.7 180

4 Bridge 42.9 160

5 Bridge 44.0 140

6 Major Culvert 82.1 100

7 Major Culvert 83.7 80

8 Bridge 88.1 260

9 Major Culvert 95.4 100

10 Major Culvert 101.1 100

The vertical alignment has not been revisited from a drainage perspective. However, five of the bridge/major culvert sites will need to be lifted by about 2.0 m which will require about 1,185,500 m3 of additional fill. Table 3.9 shows the additional earthworks required.

Table 3.9 Additional Earthworks for Bridges/Major Culvert

Bridge Ch. Lift (m) Fill Increase (m3)

41.7 2 403,500

42.9 1 10,000

44.0 1 23,000

82.1 1.7 453,000

88.1 1.7 296,000

This alignment runs parallel to existing BHPBIO railway for 36 km from Marillana mines towards the port. Five waterway crossings have been proposed in this section from Sr. No 6 to 10 as shown in table 3.8. As the proposed BRL alignment is on the downstream side of BHPB railway, the bridges/culverts on BHPB rail line may significantly affect the hydrological design on BR alignment. Since no site inspection has been done, the BHPBIO bridge and culvert locations are not known at this stage. Five bridge crews are required to construct five bridges simultaneously. Since bridge construction is a critical activity in this option, this requirement may be further evaluated in later study phases.

Page 59: CARP10026 - REP - G - 001- BRL Marillana Project - PFS Report - Rev_0

Calibre Rail Document No: CARP10026-REP-G-001

Brockman Resources – Marillana Iron Ore Project Revision No: 0

Preliminary Feasibility Study Report Issue Date: Sep 2010

Page No: Page 49 of 93

\\perfps01\CEJV$\PRO-Projects\2010\CARP10026 BR-Marillana Study\02 - PFS Study\06 Engineering\6.12 Reports\BRL Marillana Rail Project PFS Rev 0\CARP10026 - REP - G - 001-

Brockman Resources Marillana Project - Pre-Feasibility Study Report - Rev_0.doc

3.3.7 Construction Camps Construction camp sizing has been determined with the help of march chart, crew sizes, crew productivity, plant types, plant outputs etc. Two temporary construction camps are considered to be sufficient to meet the project schedule shown in Figure 6.1. In order to accommodate bridge crews for construction of 6 bridges, camp size is expected to go up to 500 rooms at the peak of construction.

3.3.8 Construction Water Requirement Assessment Total requirement of construction water has been assessed as 1.22 billion litres.

3.4 Comparison Matrix Table 3-10 shows a comparison of the key parameters for the alignments.

Table 3.10 Key Parameters Comparison for Alignments

Sr. No.

Items OPT1 HA2

VA2 OPT2 HA1

VA1

1 Corridor OPT1 OPT2

2 Length of construction (km) 95.34 70.47

3 Length of operation till junction of OPT1 (km) 95.34 100.44

4 approx. chainage of FMG rail line at tie-in (km) 190 219.6

5 Operation on FMG rail till junction of OPT 1 (km) 0 29.97

6 Earthwork in cutting –million m3 7.11 1.04

7 Earthwork in filling – million m3 2.43 2.13

8 Earthwork fronts (no.) 4 3

9 Bridges(no.) 2 6

Major culverts (no) 4 4

10 Bridge construction crews (no.) 3 5

11 Linear waterway in bridges (m) 380 1100

12 Total Capex $m 685.01 608.50

13 Average Capex $m per Km 6.66 7.84

14 Average train speed – on BRL line (km/hr) 40 42

15 Running time – on BRL line (mins) 145 100

16 Construction Camps 3 2

17 Construction water requirement billion litres 1.14 1.22

Page 60: CARP10026 - REP - G - 001- BRL Marillana Project - PFS Report - Rev_0

Calibre Rail Document No: CARP10026-REP-G-001

Brockman Resources – Marillana Iron Ore Project Revision No: 0

Preliminary Feasibility Study Report Issue Date: Sep 2010

Page No: Page 50 of 93

\\perfps01\CEJV$\PRO-Projects\2010\CARP10026 BR-Marillana Study\02 - PFS Study\06 Engineering\6.12 Reports\BRL Marillana Rail Project PFS Rev 0\CARP10026 - REP - G - 001-

Brockman Resources Marillana Project - Pre-Feasibility Study Report - Rev_0.doc

Intentionally Blank

Page 61: CARP10026 - REP - G - 001- BRL Marillana Project - PFS Report - Rev_0

Calibre Rail Document No: CARP10026-REP-G-001

Brockman Resources – Marillana Iron Ore Project Revision No: 0

Preliminary Feasibility Study Report Issue Date: Sep 2010

Page No: Page 51 of 93

\\perfps01\CEJV$\PRO-Projects\2010\CARP10026 BR-Marillana Study\02 - PFS Study\06 Engineering\6.12 Reports\BRL Marillana Rail Project PFS Rev 0\CARP10026 - REP - G - 001-

Brockman Resources Marillana Project - Pre-Feasibility Study Report - Rev_0.doc

4.0 RAILWAY OPERATIONS AND MAINTENANCE

4.1 Operations A preliminary assessment of train operations was undertaken for each alignment to provide:

• Number of passing sidings for mine production up to 17 Mtpa;

• Assess the minimum continuous train speed requirements;

• Possible passing siding locations;

• Train cycle time;

• Possible train consists; and

• Trains required per day.

The operations assessment has been based on the following assumptions:

• Axle load is 40 t;

• Maximum train speeds are 80 km/h for empty and 80 Km/h for loaded trains;

• Train loading time at the mine is 8000 t/h;

• An existing car dumper at the port will be used for unloading;

• One car dumper unloads all the ore cars in a consist and consists are not split;

• BRL trains can enter the FMG network when ready, without excessive delays;

• BRL trains can leave the port when ready and not on a specified train schedule;

• Ore cars can hold 137 t of ore;

• Passing sidings on the existing FMG network can accommodate the increased traffic from BRL trains; and

• Train operations over 348 work days per year.

4.1.1 Preliminary Operations Assessment This is a preliminary assessment only. Further analysis is required in future studies. Table 4.1 shows the rolling stock and operational data and table 4.2 shows the ore train cycle times. At this stage train cycle time is estimated to be around 22 hours based on:

• Loading time 4.8 to 5 hr (rate of 8000 t/h and 40 minutes train presentation time);

• Unloading time 6 hr (unloading 90 sec/pair +180 min in marshalling yard); and

Page 62: CARP10026 - REP - G - 001- BRL Marillana Project - PFS Report - Rev_0

Calibre Rail Document No: CARP10026-REP-G-001

Brockman Resources – Marillana Iron Ore Project Revision No: 0

Preliminary Feasibility Study Report Issue Date: Sep 2010

Page No: Page 52 of 93

\\perfps01\CEJV$\PRO-Projects\2010\CARP10026 BR-Marillana Study\02 - PFS Study\06 Engineering\6.12 Reports\BRL Marillana Rail Project PFS Rev 0\CARP10026 - REP - G - 001-

Brockman Resources Marillana Project - Pre-Feasibility Study Report - Rev_0.doc

• Travel time 11 to 12 hr (empty plus loaded).

The cycle time is an estimate based on current data. More work is required in the next project phases and a better understanding of FMG operations is critical to accurately estimate cycle times.

Table 4.1 Rolling Stock and operational Data

Element OPT 1 HA2 VA2 OPT 2 HA1 VA1

Tal 40 40

Number of wagons 240 240

Tonnage (Mtpa) 17 17

Tare Weight (t) 23 23

Wagon Payload (t) 137 137

Operating days 348 348

Distance (km) 280 286

Head end locomotives per train 2 2

Bankers per train where required 2 2

Train Payload (t) 32,880 32,880

No. of Train Cycle per year for 17 Mtpa 517 517

No. of Train Cycle per year per train 380 380

Wagon loads/year 124,088 124,088

Target Iron ore delivery per day (t) 48,851 48,851

Train sets required 2 2

Wagons required with +0.5 consist + 3% extra 618 618

locomotives required1 8 8

1 Does not include reserve due to failures because Calibre Rail assumes that FMG will provide train services and have reserve locomotives as required.

Table 4.2 Ore Train Cycle Time

Time Trip Component

OPT 1 HA2 VA2 OPT 2 HA1 VA1

Travel time one way port to BRL mine (hrs:min) 11:07

(667mins) 11:07

(667mins)

Time at Mine: Loadout @ 8000 t/h + 40 min (hrs:mins) 4:47

(287mins) 4:47

(287mins)

Time at Port: Unloading 90 sec/pair +180 min (hrs:mins) 6:00

(360mins) 6:00

(360mins)

Cycle Time (hrs:mins) 22:13 22:13

No. of trips in 24 hrs for each train 1.09 1.09

Trains per day 1.5 1.5

Page 63: CARP10026 - REP - G - 001- BRL Marillana Project - PFS Report - Rev_0

Calibre Rail Document No: CARP10026-REP-G-001

Brockman Resources – Marillana Iron Ore Project Revision No: 0

Preliminary Feasibility Study Report Issue Date: Sep 2010

Page No: Page 53 of 93

\\perfps01\CEJV$\PRO-Projects\2010\CARP10026 BR-Marillana Study\02 - PFS Study\06 Engineering\6.12 Reports\BRL Marillana Rail Project PFS Rev 0\CARP10026 - REP - G - 001-

Brockman Resources Marillana Project - Pre-Feasibility Study Report - Rev_0.doc

4.1.2 Train Performance Modelling Calibre Rail’s “OpenTrack” train performance simulation software was used to analyse alignments during the development process to determine:

• Train performance on each alignment with a train consist of two GE C44-9W (Dash 9 DC) locomotives, 240 ore wagons and two banking locomotives where required; and

• Appropriate track geometry, gradients and standards for reliable and safe train operations.

The train configuration is identical to FMG fleets. FMG currently operates locomotives with DC traction, and whilst it is understood that future locomotive acquisitions may be with AC traction, simulation of DC traction must occur as this is the inferior performing locomotive that may be used regularly on the BRL rail spur if FMG provides train services. Because of the long and steep falling grades facing the trains, Calibre Rail specifies a speed restriction of 50 km/h on the operation of trains descending the grades through the Chichester Ranges in both directions. This is to avoid trains losing control and achieving dangerous runaway speeds on these stretches. For the track alignment options modelling, the following should be noted:

• FMG railway operations:

− Currently FMG operates DC traction locomotives which will be in FMG service across the network for at least ten years and thus they will form the conservative benchmark for locomotive tractive effort;

− FMG trains currently use ECP braking. This type of braking system is the operating standard for the railway and as such fleets serving the BRL mines will need to comply;

− All trains that operate in the loaded direction beyond Ch. 200 will require banking in the loaded direction. This means that the OPT2 HA1 VA1 alignment requires banking locomotives to run the full length of the Brockman spur and then along the FMG mainline to the passing loop at Summit. This may cause pathway capacity issues for the mainline where bankers must return to the mine after each loaded train movement;

− Both alignment options may require a three kilometre stretch of suitable siding track immediately before the FMG mainline junction to allow trains to stop before entering the mainline, should the entry signal be against them;

− All ore trains are simulated in the following configuration;

Two head-end locomotives 240 ore wagons 2 banker locomotives (where needed); and

− Two locomotives are required for all empty trains on the return trip on both alignments.

Page 64: CARP10026 - REP - G - 001- BRL Marillana Project - PFS Report - Rev_0

Calibre Rail Document No: CARP10026-REP-G-001

Brockman Resources – Marillana Iron Ore Project Revision No: 0

Preliminary Feasibility Study Report Issue Date: Sep 2010

Page No: Page 54 of 93

\\perfps01\CEJV$\PRO-Projects\2010\CARP10026 BR-Marillana Study\02 - PFS Study\06 Engineering\6.12 Reports\BRL Marillana Rail Project PFS Rev 0\CARP10026 - REP - G - 001-

Brockman Resources Marillana Project - Pre-Feasibility Study Report - Rev_0.doc

A number of locomotive types were simulated against the standard FMG train consist to

understand different traction capabilities to explore the potential to remove the use of

banking locomotives. None provided this option.

Table 4.3 shows the consists modelled.

Table 4.3 Consists Modelled

Locomotives Ore cars

SR No.

Dash 9

DC

GE 4400 AC

Number Loaded/Empty Travel Direction

1 4 - 240 L Mine to Junction

2 2 - 240 E Junction to Mine

3 4 - 232 L Mine to Junction

4 5 - 240 L Mine to Junction

5 - 4 240 L Mine to Junction

6 - 5 240 L Mine to Junction

The results indicated that AC traction locomotives do perform better than DC traction locomotives in this task, but not sufficiently to eliminate the banking operation. Calibre Rail maintains that the existing FMG fleet should be the benchmark for all simulations in this project. Table 4.4 indicates benchmark travel time, minimum speed of trains and fuel consumption for both alignments.

Table 4.4 Simulations Results Comparison

Fuel Consumption (L)

Option Alignment Length to

Junction (km)

Travel time (mins)

Min. Speed (km/h)

Empty 2 locos

Loaded 4 locos

Total

OPT1 HA2 VA2 95.34 143 20 2,656 5,766 8,422

OPT2 HA1 VA1 70.47 99 26 1,869 3,922 5,791

4.1.3 Passing Sidings and Tracks Operational studies have shown that passing sidings on the BRL line are not required for two loaded trains per day for transportation of 17 Mtpa iron ore. However, two passing siding are proposed. One is located just before the junction with the FMG main line. This may be required to hold an empty BRL train bound for the mine in order to provide unhindered entry to the main line for a loaded train. The feasibility study of locating passing sidings on the FMG main line near the BRL junction found that grades were not favourable at this location. Second passing siding is located near battery limit of mine loadout.

Page 65: CARP10026 - REP - G - 001- BRL Marillana Project - PFS Report - Rev_0

Calibre Rail Document No: CARP10026-REP-G-001

Brockman Resources – Marillana Iron Ore Project Revision No: 0

Preliminary Feasibility Study Report Issue Date: Sep 2010

Page No: Page 55 of 93

\\perfps01\CEJV$\PRO-Projects\2010\CARP10026 BR-Marillana Study\02 - PFS Study\06 Engineering\6.12 Reports\BRL Marillana Rail Project PFS Rev 0\CARP10026 - REP - G - 001-

Brockman Resources Marillana Project - Pre-Feasibility Study Report - Rev_0.doc

In addition, a 450 m clear standing length refuge siding is proposed about midway along the BRL line. Such a siding will be used for track inspection vehicles, maintenance vehicles, bad order cars and defective locomotives. The proposed passing sidings and refuge spurs are shown in the track schematics for the OPT1 HA2 VA2 and OPT2 HA1 VA1 alignments (Figure 1.3).

4.1.4 Scheduling In order to develop a more detailed operating plan for trains between the port and the mine Calibre Rail proposes that the following work be undertaken:

• Seek assistance from FMG to provide mainline operations data to enable full journey simulation from BRL mine to port for costing purposes;

• Run a train performance calculation (TPC);

• Develop idealised trains schedule simulation, train configurations and passing siding locations; and

• Model the railway and related operations using discrete event simulation techniques.

These steps are interactive and take into consideration different scenarios, schedules, terminal operations and possible changes to the railway profile.

4.2 Maintenance

4.2.1 Track Maintenance The Pilbara railways are well optimised systems operating on a preventive maintenance philosophy. The proposed track maintenance plan is based on preventive maintenance to provide a safe, efficient and cost effective train operation. The outline maintenance plan includes:

• For track and infrastructure maintenance, BRL and/or a full time contractors can do the following:

− track inspection including rail, sleepers, clips, pads etc;

− rail welding;

− rail surfacing including lifting, lining, tamping and ballast profiling;

− cutting and drainage clearing;

− unscheduled track repairs;

− servicing and maintaining switches;

− bridge and culvert inspections; and

Page 66: CARP10026 - REP - G - 001- BRL Marillana Project - PFS Report - Rev_0

Calibre Rail Document No: CARP10026-REP-G-001

Brockman Resources – Marillana Iron Ore Project Revision No: 0

Preliminary Feasibility Study Report Issue Date: Sep 2010

Page No: Page 56 of 93

\\perfps01\CEJV$\PRO-Projects\2010\CARP10026 BR-Marillana Study\02 - PFS Study\06 Engineering\6.12 Reports\BRL Marillana Rail Project PFS Rev 0\CARP10026 - REP - G - 001-

Brockman Resources Marillana Project - Pre-Feasibility Study Report - Rev_0.doc

− signalling and communications inspections and maintenance.

• A contractor could do the following periodic works that requires specialised equipment:

− ultrasonic rail testing;

− laser rail head profile and other non-destructive testing;

− track geometry recording;

− rail profile grinding;

− switch grinding; and

− access road maintenance.

Normally, maintenance requirements will be minimal in the first few years of operation. This period should be used to gather data on wear and tear on the tracks which will provide a basis for future planned maintenance. After the first heavy rains, resurfacing may be required, especially in areas with high embankments. As a part of the construction contract, the initial rail grinding to establish the required rail profile, and some of the resurfacing works could be done.

4.2.2 BRL Track Maintenance Equipment If BRL decides to undertake general maintenance on its own, the following minimum equipment list may be required:

• Ballast regulator;

• On track tamper;

• Excavator for clean out of cuttings and drains;

• Front end loader and tip truck;

• Hi-Rail road vehicles for the track inspection; and

• Rail handling crane(s).

Some of this equipment, in particular the track surfacing machine and rail handling crane may be purchased for construction and then retained for maintenance. There may be cost saving opportunities if:

• Specialised services currently operating on the BHPBIO and/or FMG networks are used; and/or

• Contractors having expertise and equipments are hired.

Page 67: CARP10026 - REP - G - 001- BRL Marillana Project - PFS Report - Rev_0

Calibre Rail Document No: CARP10026-REP-G-001

Brockman Resources – Marillana Iron Ore Project Revision No: 0

Preliminary Feasibility Study Report Issue Date: Sep 2010

Page No: Page 57 of 93

\\perfps01\CEJV$\PRO-Projects\2010\CARP10026 BR-Marillana Study\02 - PFS Study\06 Engineering\6.12 Reports\BRL Marillana Rail Project PFS Rev 0\CARP10026 - REP - G - 001-

Brockman Resources Marillana Project - Pre-Feasibility Study Report - Rev_0.doc

Intentionally Blank

Page 68: CARP10026 - REP - G - 001- BRL Marillana Project - PFS Report - Rev_0

Calibre Rail Document No: CARP10026-REP-G-001

Brockman Resources – Marillana Iron Ore Project Revision No: 0

Preliminary Feasibility Study Report Issue Date: Sep 2010

Page No: Page 58 of 93

\\perfps01\CEJV$\PRO-Projects\2010\CARP10026 BR-Marillana Study\02 - PFS Study\06 Engineering\6.12 Reports\BRL Marillana Rail Project PFS Rev 0\CARP10026 - REP - G - 001-

Brockman Resources Marillana Project - Pre-Feasibility Study Report - Rev_0.doc

5.0 CONSTRUCTION METHOD Calibre Rail makes the assumption that BRL will enter into a service agreement with FMG (TPI) to enable the use of FMG facilities, equipment and services to assist and or construct the railway spur.

5.1 Earthworks

5.1.1 Clearing and grubbing The clearing and grubbing is to be done up to 2 m from cutting tops and embankment toes. Grubbing should be done to 0.5 m below the natural surface or 1.5 m below the finished earthworks level. Holes left after grubbing under proposed embankments should be filled with sound material and compacted in layers as for embankments.

5.1.2 Excavation for Cuttings Excavation should be done using earthmoving equipment such as excavators, rippers, bulldozers, dumpers etc., to the lines, levels, dimensions and slopes shown on the construction drawings and confirming to detailed specifications.

5.1.3 Embankment and Compaction Unsuitable material will be removed and replaced with approved fill for the entire bottom width and up to 2 m on either side. Embankments will be constructed in full width horizontal layers up to 300 mm thick or of a thickness at which desired compaction can be achieved using suitable material from cut and borrow. Normally, uniform material should be used in one layer. Embankment batter slopes will be as shown on the drawings and compaction levels as per specifications.

5.2 Bridges and Culverts Standard 20 m and 35 m spans will be used on all bridges in both the options. Bridge beams/girders will be prefabricated and transported to site. A composite deck slab will be cast insitu. Pile foundation, spread footings, piers and abutments will be reinforced concrete cast insitu.

Page 69: CARP10026 - REP - G - 001- BRL Marillana Project - PFS Report - Rev_0

Calibre Rail Document No: CARP10026-REP-G-001

Brockman Resources – Marillana Iron Ore Project Revision No: 0

Preliminary Feasibility Study Report Issue Date: Sep 2010

Page No: Page 59 of 93

\\perfps01\CEJV$\PRO-Projects\2010\CARP10026 BR-Marillana Study\02 - PFS Study\06 Engineering\6.12 Reports\BRL Marillana Rail Project PFS Rev 0\CARP10026 - REP - G - 001-

Brockman Resources Marillana Project - Pre-Feasibility Study Report - Rev_0.doc

Each bridge will have a simple, 6 m long reinforced concrete run-on slab at each abutment. Culverts will be mostly CSP with diameters ranging from 900 to 3600 mm. Some locations may require a reinforced concrete box due to limited cushion. Configuration of each bridge/culvert will have to be decided in the next study phase.

5.3 Track

5.3.1 Rails Short 25 m rails will be shipped to Port Hedland, unloaded and transported to FMG Rail Service Yard for stockpiling. An existing flash butt welding (FBW) facility at FMG Rail Service Yard will be used to weld the short rails into 325 m strings. A rail train will carry these strings to the track construction work front.

5.3.2 Sleepers Concrete sleepers will be fabricated at an existing manufacturing facility in Port Hedland. Sleepers will be transported to FMG Rail Service Yard for stockpiling. A train will carry the sleepers and rail strings to the track construction work front.

5.3.3 Tracklaying Tracklaying will start from the FMG tie-in point towards the mine site using conventional tracklaying machines for all mainline and passing siding. Schedule durations and Capex estimates are based on an average production rate of about 1.5 km of completed track per day.

5.3.4 Ballast Ballast will be sourced from an existing Elazac quarry. Ballast will be carted by road from the quarry and stockpiled at FMG Rail Service Yard for loading onto ballast trains and transport to site.

Page 70: CARP10026 - REP - G - 001- BRL Marillana Project - PFS Report - Rev_0

Calibre Rail Document No: CARP10026-REP-G-001

Brockman Resources – Marillana Iron Ore Project Revision No: 0

Preliminary Feasibility Study Report Issue Date: Sep 2010

Page No: Page 60 of 93

\\perfps01\CEJV$\PRO-Projects\2010\CARP10026 BR-Marillana Study\02 - PFS Study\06 Engineering\6.12 Reports\BRL Marillana Rail Project PFS Rev 0\CARP10026 - REP - G - 001-

Brockman Resources Marillana Project - Pre-Feasibility Study Report - Rev_0.doc

6.0 SCHEDULE The major assumptions for construction are:

• Project Completion: Post-commissioning operations start − Q2 2013.

• Preliminary environmental approval for geotechnical and bore investigation is obtained by November 2010.

The project completion date is based on project detail design commencement by August 2010. All design will be done during the project environmental approval process timeframe. However, some geotechnical investigation and bore drilling will be required before the environmental approval is likely to be granted. This will require a separate preliminary approval. Preliminary project construction schedules have been developed for the OPT1 HA2 VA2 and OPT2 HA1 VA1 alignment options based on major activities. Project completion date is 19 July 2013 for OPT1 HA2 VA2 and 10 July 2013 for OPT2 HA1 VA1 Schedules are in appendix C. The critical path goes through:

• Environmental approval;

• Camp construction;

• Railway formation and drainage construction;

• Bridges and major culvert sites;

• Signalling and backbone communications installation;

• Tracklaying; and

• Testing and Commissioning.

Page 71: CARP10026 - REP - G - 001- BRL Marillana Project - PFS Report - Rev_0

Calibre Rail Document No: CARP10026-REP-G-001

Brockman Resources – Marillana Iron Ore Project Revision No: 0

Preliminary Feasibility Study Report Issue Date: Sep 2010

Page No: Page 61 of 93

\\perfps01\CEJV$\PRO-Projects\2010\CARP10026 BR-Marillana Study\02 - PFS Study\06 Engineering\6.12 Reports\BRL Marillana Rail Project PFS Rev 0\CARP10026 - REP - G - 001-

Brockman Resources Marillana Project - Pre-Feasibility Study Report - Rev_0.doc

Intentionally Blank

Page 72: CARP10026 - REP - G - 001- BRL Marillana Project - PFS Report - Rev_0

Calibre Rail Document No: CARP10026-REP-G-001

Brockman Resources – Marillana Iron Ore Project Revision No: 0

Preliminary Feasibility Study Report Issue Date: Sep 2010

Page No: Page 62 of 93

\\perfps01\CEJV$\PRO-Projects\2010\CARP10026 BR-Marillana Study\02 - PFS Study\06 Engineering\6.12 Reports\BRL Marillana Rail Project PFS Rev 0\CARP10026 - REP - G - 001-

Brockman Resources Marillana Project - Pre-Feasibility Study Report - Rev_0.doc

7.0 COST ESTIMATES

7.1 CAPITAL COSTS The Capex estimate is:

• Based on the scope definition and basis of design;

• Has a nominal accuracy of ±30%;

• In Australian dollars (AUD); and

• Based on prices and market conditions in Pilbara Region of Western Australia with a base date of July 2010.

Table 7.1 shows summary Capex estimates for both the options.

Table 7.1 Summary of Capex Estimates

COST ($)* ITEMS

OPT1 HA2 VA2 OPT2 HA1 VA1

Earthworks & Drainage $301,189,672 $123,979,307

Haul Roads $2,443,248 $1,806,060

Track Supply & Construction $77,293,678 $57,744,605

Bridges and Major Culverts $49,743,372 $144,927,095

Signals and Communications $41,428,445 $41,705,673

Construction Facilities $90,314,362 $104,279,929

Subtotal Directs $562,412,778 $474,442,669

Contractor Overheads & Indirects $66,438,422 $72,207,179

EPCM $56,162,601 $61,845,205

Subtotal Indirects $122,601,023 $134,052,384

Grand Total $685,013,801 $608,495,053

Track length Km 102.92 77.58

Cost per km* $6,655,789 $7,843,453 *Excludes rolling stock and maintenance facilities

7.1.1 Estimate Basis

Direct works are those facilities installed or constructed for hand-over to the Owner as part of the completed or partially completed rail infrastructure.

Costs and production rates for labour and construction equipment were developed from first principles and were checked against detailed cost data for similar projects.

Page 73: CARP10026 - REP - G - 001- BRL Marillana Project - PFS Report - Rev_0

Calibre Rail Document No: CARP10026-REP-G-001

Brockman Resources – Marillana Iron Ore Project Revision No: 0

Preliminary Feasibility Study Report Issue Date: Sep 2010

Page No: Page 63 of 93

\\perfps01\CEJV$\PRO-Projects\2010\CARP10026 BR-Marillana Study\02 - PFS Study\06 Engineering\6.12 Reports\BRL Marillana Rail Project PFS Rev 0\CARP10026 - REP - G - 001-

Brockman Resources Marillana Project - Pre-Feasibility Study Report - Rev_0.doc

Labour rates were built-up from first principles using information from rates that are anticipated to be based on award rates that reflect the additional payments and allowances usually paid on construction sites in the Pilbara. The assumed site working week was 13 days per fortnight, twelve hours per day (work plus travel) and R&R leave on the fifth week of a work cycle. Estimating factors and unit trade percentages were obtained from previous projects and used for costing of lesser items and for checking the estimated costs. Contractors’ indirect costs, including mobilisation and demobilisation, temporary site facilities, management and supervision, were built up from first principles. Unit rates for the supply of materials such as concrete, rebar and fabricated steelwork were derived from data supplied by a number of suppliers with relevant experience. The overall rates for supply, delivery and installation of these materials were then benchmarked against current industry rates in the region. The quotations for permanent and construction materials generally includes freight free-on-board (FOB) to Port Hedland or free-on-truck (FOT) at site. Current freight costs, on a tonnage or volumetric basis, were applied to all other items.

7.1.2 Indirect Cost Estimate

Indirect works are those that are of a temporary nature required to support the construction of the direct works including the operation and maintenance thereof and support services. Indirect costs consisted of the man-hour costs, consultants and expenses of the EPCM contractor for the project. They also include the cost of temporary facilities required on site during the construction period. Where appropriate, they also include the man-hour costs, expenses and temporary facilities of any subcontractors engaged to construct the works. Indirect costs were derived from:

• A first principle assessment of the man-hours; and

• Expenses for the required deliverable, management and services by both the EPCM and any subcontractors and are to include at home office and site costs.

Man-hour rates appropriate to the industry include salaries, entitlements, payroll burdens and the EPCM Engineer’s and subcontractors overhead costs. Camp Facilities costs and costs associated with maintaining camps during the construction period are included under a separate section called Construction Facilities.

Page 74: CARP10026 - REP - G - 001- BRL Marillana Project - PFS Report - Rev_0

Calibre Rail Document No: CARP10026-REP-G-001

Brockman Resources – Marillana Iron Ore Project Revision No: 0

Preliminary Feasibility Study Report Issue Date: Sep 2010

Page No: Page 64 of 93

\\perfps01\CEJV$\PRO-Projects\2010\CARP10026 BR-Marillana Study\02 - PFS Study\06 Engineering\6.12 Reports\BRL Marillana Rail Project PFS Rev 0\CARP10026 - REP - G - 001-

Brockman Resources Marillana Project - Pre-Feasibility Study Report - Rev_0.doc

Temporary construction facilities will include temporary offices, site services and facilities for the EPCM contractor, construction camps, security, and the establishment, maintenance, removal and cleanup of all sundry provisions required for the construction phase. Fuel prices for this estimate will assume that the diesel fuel rebate does not apply.

7.2 Capital Estimate Set-Out The railway Capital Estimate was produced using a proprietary estimating software system (Quest). The estimating system makes provision for the following inputs for each element of the estimate: • Work breakdown structure (Facilities/Commodity/Items) reference no;

• Item description;

• Quantity;

• Unit;

• Man-hours;

• Direct labour cost;

• Construction equipment cost;

• Plant/equipment cost;

• Bulk material cost;

• Freight cost – if applicable;

• Subcontract indirects; and

• Total cost.

7.2.1 Man-hours

All on-site direct construction labour hours required to complete the works are included, with provisions for expected productivity at the site resulting from location, working hours, etc. It also excludes indirect construction labour hours, such as service and repair labour hours on construction equipment and for foreman and other supervisory hours.

7.2.2 Direct Labour Cost

Direct labour costs include costs up to but excluding foreman level and provide for the following: • Base rate of pay;

Page 75: CARP10026 - REP - G - 001- BRL Marillana Project - PFS Report - Rev_0

Calibre Rail Document No: CARP10026-REP-G-001

Brockman Resources – Marillana Iron Ore Project Revision No: 0

Preliminary Feasibility Study Report Issue Date: Sep 2010

Page No: Page 65 of 93

\\perfps01\CEJV$\PRO-Projects\2010\CARP10026 BR-Marillana Study\02 - PFS Study\06 Engineering\6.12 Reports\BRL Marillana Rail Project PFS Rev 0\CARP10026 - REP - G - 001-

Brockman Resources Marillana Project - Pre-Feasibility Study Report - Rev_0.doc

• Annual leave;

• Annual leave loading;

• Public holiday and sick leave;

• Long service leave;

• Overtime;

• Travel time;

• Superannuation;

• Workers' compensation and payroll tax;

• Messing and accommodation;

• R&R air fares and expenses;

• Site and location allowance;

• Termination allowance,

• Over-award compliance payment;

• Daily travel allowance;

• Boot allowance;

• Bereavement allowance;

• Income protection allowance; and

• Fringe benefits tax on camp meals.

Labour rates were built-up from first principles using information from similar projects in the Pilbara Region. They are based on construction hours of 130 hours/fortnight. Direct labour costs do not include for equipment service and repair labour, which are incorporated in construction equipment rates.

7.2.3 Construction Equipment Cost

Construction equipment is large equipment brought to site during construction and is removed at the completion of construction. Construction equipment includes such items as dozers, dump trucks, water tankers, graders etc. Rates for construction equipment include the following: • Equipment materials and supply including costs for spare parts, fuel and oils and a

reserve for major overhaul;

• Equipment ownership costs (depreciation, insurances, registrations and taxes); and

• Outside equipment hire such as hiring from third parties for minor requirements.

Page 76: CARP10026 - REP - G - 001- BRL Marillana Project - PFS Report - Rev_0

Calibre Rail Document No: CARP10026-REP-G-001

Brockman Resources – Marillana Iron Ore Project Revision No: 0

Preliminary Feasibility Study Report Issue Date: Sep 2010

Page No: Page 66 of 93

\\perfps01\CEJV$\PRO-Projects\2010\CARP10026 BR-Marillana Study\02 - PFS Study\06 Engineering\6.12 Reports\BRL Marillana Rail Project PFS Rev 0\CARP10026 - REP - G - 001-

Brockman Resources Marillana Project - Pre-Feasibility Study Report - Rev_0.doc

7.2.4 Plant/Equipment Cost The full purchase cost of all permanent equipment required for the project is included under this item. Freight costs are included where items are quoted with delivery to site.

7.2.5 Bulk Materials Cost Bulk material is the purchase cost of materials that are bought in quantity and are not part of any item of plant equipment. Costs include all over supply for wastage, any off-site prefabrication, packaging, inland freight to nearest port or place of consolidation, duties and insurances.

7.2.6 Freight Freight is the cost to transport equipment and materials from a port of export to site or place of consolidation or site, including wharf charges, freight forwarding and transhipment costs as required. Freight is only applied to items which are not quoted with delivery to site.

7.2.7 Subcontract Indirects The contractor’s corporate overheads and profit is included in this item. An allowance of 55% of the labour cost has been allowed. The remaining contractor indirects were estimated from first principles and held in the Contractors Overheads item in the WBS. Contractors Overheads will include: • Mobilisation and demobilisation of contractor’s employees, construction equipment,

temporary facilities;

• On-site contractor’s overheads including supervision, (foreman and above) field engineering, management, administration, contractor purchasing and warehousing and service and repair labour not included in equipment rates;

• Site expenses including vehicles, stationery, travel, communications (telephone, fax, Postage) printing, indirect staff R&R leave travel etc;

• Temporary site facilities and services; and

• Indirect staff camp messing and accommodation costs (such costs for direct labour have been included in wage rates).

Page 77: CARP10026 - REP - G - 001- BRL Marillana Project - PFS Report - Rev_0

Calibre Rail Document No: CARP10026-REP-G-001

Brockman Resources – Marillana Iron Ore Project Revision No: 0

Preliminary Feasibility Study Report Issue Date: Sep 2010

Page No: Page 67 of 93

\\perfps01\CEJV$\PRO-Projects\2010\CARP10026 BR-Marillana Study\02 - PFS Study\06 Engineering\6.12 Reports\BRL Marillana Rail Project PFS Rev 0\CARP10026 - REP - G - 001-

Brockman Resources Marillana Project - Pre-Feasibility Study Report - Rev_0.doc

7.2.8 Total Cost This will be Total Estimated Cost for the above items. Sub-totals at each WBS defined cost sections are maintained at the estimate build up summary level.

7.2.9 Rail Facilities Capital Cost Within the Rail Facilities the estimate includes direct labour, bulk materials, permanent equipment and contractor’s indirect costs for:

• Embankments & Cuttings;

• Drainage, Culverts & Embankment Protection;

• Roads and Crossings;

• Trackwork & Trackwork Materials Supply;

• Signalling;

• Communications;

• Bridges;

• Construction Facilities; and

• Contractors Overheads.

7.2.10 Engineering Costs Engineering and Management costs cover the following:

• Project management;

• Detail design not undertaken during the DES;

• Procurement, inspection & expediting;

• Site supervision of works; and

• Owners costs such as insurance, Client support, Perth office costs, legal, audit and minor consultants.

7.3 Insurances No provision has been included within this estimate for the Owner’s specific project insurances. Allowances for all necessary owners insurances are provided in the Owner’s costs.

Page 78: CARP10026 - REP - G - 001- BRL Marillana Project - PFS Report - Rev_0

Calibre Rail Document No: CARP10026-REP-G-001

Brockman Resources – Marillana Iron Ore Project Revision No: 0

Preliminary Feasibility Study Report Issue Date: Sep 2010

Page No: Page 68 of 93

\\perfps01\CEJV$\PRO-Projects\2010\CARP10026 BR-Marillana Study\02 - PFS Study\06 Engineering\6.12 Reports\BRL Marillana Rail Project PFS Rev 0\CARP10026 - REP - G - 001-

Brockman Resources Marillana Project - Pre-Feasibility Study Report - Rev_0.doc

7.4 Scope Exclusion The following items are specifically excluded from the capital cost:

• Heritage and State Agreement Costs;

• Environmental approval costs;

• Study costs and;

• Simulation, modelling, business analysis and other budget and engineering study costs;

• Project funding establishment cost;

• Project finance costs and associated bank charges;

• Project delay in start date or suspension;

• Working capital;

• Marketing costs;

• Exploration/investigation/feasibility study costs;

• Operating cost;

• Cost of any further studies/options, other than design optimisation of the defined scope;

• Goods and services tax (GST);

• Native title claims;

• Legal costs;

• External/independent audits;

• Owner’s costs;

• Escalation;

• Contingency;

• Design growth;

• Rolling stock; and

• Service relocations.

7.5 Operating costs Excluded

Page 79: CARP10026 - REP - G - 001- BRL Marillana Project - PFS Report - Rev_0

Calibre Rail Document No: CARP10026-REP-G-001

Brockman Resources – Marillana Iron Ore Project Revision No: 0

Preliminary Feasibility Study Report Issue Date: Sep 2010

Page No: Page 69 of 93

\\perfps01\CEJV$\PRO-Projects\2010\CARP10026 BR-Marillana Study\02 - PFS Study\06 Engineering\6.12 Reports\BRL Marillana Rail Project PFS Rev 0\CARP10026 - REP - G - 001-

Brockman Resources Marillana Project - Pre-Feasibility Study Report - Rev_0.doc

7.6 Comparison with OoM Estimate Direct item by item comparison between estimates prepared for OoM study and PFS is not practicable due to following reasons:

• The estimates were prepared on different software platforms;

• Base dates for both estimates are different;

• Breakup of the activities and item descriptions are different;

• OoM estimate was at much higher level then PFS estimate;

• Estimates were prepared with different objectives in mind;

• Expected accuracy of both the estimates is different;

• Easis of rates for OoM estimate is not available;

• Eabour rates and fuel rates are different;

• Basis of design for the alignments is different;

• Lengths of railways are different (OoM - 112km, OPT1 – 95.3km, OPT2 – 70.5km); and

• Battery limits are different.

However an attempt has been made to compare OoM estimate with the PFS estimate for OPT1 as shown in table 7.2. OPT2 HA1 VA1 take a completely different corridor hence similar comparison can not be drawn.

Table 7.2 OoM and PFS estimate comparison

Estimated Cost $M Description

OoM PFS OPT1

Difference

Bulk Earthwork - Main Trackwork 64.50 261.62 197.12

Culverts 11.26 39.57 28.31

Turnout Pads 0.02 0.00 -0.02

Trackworks 139.57 77.29 -62.28

Bridgeworks 41.10 49.74 8.64

Signalling & Communications 17.53 41.43 23.90

Road Upgrades & Modifications 0.00 2.44 2.44

Site Facilities 0.00 90.32 90.32

Indirects 98.63 66.44 -32.19

EPCM 0.00 56.16 56.16

Total 372.62 685.01 312.39

Some of the major cost driving items are compared in table 7.3 below:

Page 80: CARP10026 - REP - G - 001- BRL Marillana Project - PFS Report - Rev_0

Calibre Rail Document No: CARP10026-REP-G-001

Brockman Resources – Marillana Iron Ore Project Revision No: 0

Preliminary Feasibility Study Report Issue Date: Sep 2010

Page No: Page 70 of 93

\\perfps01\CEJV$\PRO-Projects\2010\CARP10026 BR-Marillana Study\02 - PFS Study\06 Engineering\6.12 Reports\BRL Marillana Rail Project PFS Rev 0\CARP10026 - REP - G - 001- Brockman Resources Marillana Project - Pre-Feasibility Study Report -

Rev_0.doc

Table 7.3 Comparison with OoM estimate – cost driving items

OoM ( generally corresponds to OPT1)

OPT1 HA2 VA2 Sr. No

Item Description

Unit Qty. Rate $ Amount

$M Unit Quantity Rate* $ Amount $M Diff

1 Place/Compact fill BF M3 4618554 3.95 18,243,288 M3 2208953 10.76 23,768,334 5,525,046

2 Establish borrow pits 0 0.00 0 HA 371 14,677.54 5,445,367 5,445,367

3 Rehabilitate borrow pits 0 0.00 0 HA 371 19,905.91 7,385,093 7,385,093

4 Drill and Blast (Rock) M3 3833647 4.96 19,014,889 M3 6306761 16.00 100,908,176 81,893,287

5 Excavate rock doze & Push 0 0.00 0 M3 6306761 3.51 22,136,731 22,136,731

6 load & haul rock for 2Kms 0 0.00 0 M3 5972500 11.30 67,489,245 67,489,245

7 Culverts LS 0 0.00 11,259,933 LS 0 0.00 39,573,807 28,313,874

8 Site Facilities, indirects & EPCM

LS 0 0.00 98,634,442 LS 0 0.00 212,920,000 114,285,558

* The rates have been derived from current prevailing rates in WA from recent projects undertaken by Calibre. All rates have been pear reviewed and confirmed.

Page 81: CARP10026 - REP - G - 001- BRL Marillana Project - PFS Report - Rev_0

Calibre Rail Document No: CARP10026-REP-G-001

Brockman Resources – Marillana Iron Ore Project Revision No: 0

Preliminary Feasibility Study Report Issue Date: Sep 2010

Page No: Page 71 of 93

\\perfps01\CEJV$\PRO-Projects\2010\CARP10026 BR-Marillana Study\02 - PFS Study\06 Engineering\6.12 Reports\BRL Marillana Rail Project PFS Rev 0\CARP10026 - REP - G - 001-

Brockman Resources Marillana Project - Pre-Feasibility Study Report - Rev_0.doc

Intentionally Blank

Page 82: CARP10026 - REP - G - 001- BRL Marillana Project - PFS Report - Rev_0

Calibre Rail Document No: CARP10026-REP-G-001

Brockman Resources – Marillana Iron Ore Project Revision No: 0

Preliminary Feasibility Study Report Issue Date: Sep 2010

Page No: Page 72 of 93

\\perfps01\CEJV$\PRO-Projects\2010\CARP10026 BR-Marillana Study\02 - PFS Study\06 Engineering\6.12 Reports\BRL Marillana Rail Project PFS Rev 0\CARP10026 - REP - G - 001-

Brockman Resources Marillana Project - Pre-Feasibility Study Report - Rev_0.doc

8.0 APPROVALS The following issues related to land ownership have not been considered as part of this study:

• Tenure;

• Environmental;

• Heritage; and

• Operational regulations.

BRL is responsible for all activities in this area, including studies, negotiations and approvals. This study has not given consideration to current land ownership or leases when selecting rail routes. Note that tenure is required for any ground-disturbing activities, including:

• Geotechnical investigations;

• Water exploration and production drilling;

• Pioneering activities;

• Camp construction; and

• Main works construction.

The likely heritage issues relating to the construction of the railway are as follows:

• Agreements to allow development of the railway through indigenous land;

• Develop and implement procedures to prevent disturbance of heritage sites;

• Install barriers and fences to protect prominent heritage sites; and

• Provide opportunities for indigenous personnel to be involved in the project.

Page 83: CARP10026 - REP - G - 001- BRL Marillana Project - PFS Report - Rev_0

Calibre Rail Document No: CARP10026-REP-G-001

Brockman Resources – Marillana Iron Ore Project Revision No: 0

Preliminary Feasibility Study Report Issue Date: Sep 2010

Page No: Page 73 of 93

\\perfps01\CEJV$\PRO-Projects\2010\CARP10026 BR-Marillana Study\02 - PFS Study\06 Engineering\6.12 Reports\BRL Marillana Rail Project PFS Rev 0\CARP10026 - REP - G - 001-

Brockman Resources Marillana Project - Pre-Feasibility Study Report - Rev_0.doc

Intentionally Blank

Page 84: CARP10026 - REP - G - 001- BRL Marillana Project - PFS Report - Rev_0

Calibre Rail Document No: CARP10026-REP-G-001

Brockman Resources – Marillana Iron Ore Project Revision No: 0

Preliminary Feasibility Study Report Issue Date: Sep 2010

Page No: Page 74 of 93

\\perfps01\CEJV$\PRO-Projects\2010\CARP10026 BR-Marillana Study\02 - PFS Study\06 Engineering\6.12 Reports\BRL Marillana Rail Project PFS Rev 0\CARP10026 - REP - G - 001-

Brockman Resources Marillana Project - Pre-Feasibility Study Report - Rev_0.doc

9.0 SAFETY AND ENVIRONMENTAL MANAGEMENT

9.1 Safety Management During this PFS, safety management has mainly focussed on designing for safety. The following basic principles are an integral part of design and construction process:

• Ensure that a safe design is achieved such that risk of injury to personnel or occupational illness, loss or damage to property and structures and pollution of the environment is eliminated or effectively managed;

• The control of major accident events will be achieved by preventing or reducing the possibility of an event and by controlling/mitigating the damaging effects, and from the inherently safe design of the installation;

• Risks will be eliminated or reduced to ‘As Low As Reasonably Practical’ (ALARP) to ensure the well being of individuals associated with the rail safety work, the public and property;

• Personnel safety, protection of the environment and assets on a risk basis following the principles of AS 4360: Risk Management will be the primary consideration in planning and designing the safety systems for the facilities;

• The emphasis in equipment specification will be on operability, accident and fault prevention and functionality for the design life; and

• Handrails and/or guard-railing will be provided where ever practical to do so.

9.2 Environmental Management The rail route options investigated in this study cross the Fortescue River, associated floodplain and tributaries. This is an environmentally sensitivity area which may significantly affect the project plan and design. The likely environmental issues relating to the construction phase of the railway are:

• Approval to construct the railway on the selected route;

• The development and implementation of procedures to prevent unauthorised or unnecessary clearing or disturbance of vegetation;

• The preservation, where possible, of natural drainage features, including the prevention of drainage shadows downstream of the railway;

• The preservation of sensitive vegetation areas;

• The appropriate storage and containment of hydrocarbons to minimise environmental incident spills;

• The appropriate storage and disposal of waste materials;

Page 85: CARP10026 - REP - G - 001- BRL Marillana Project - PFS Report - Rev_0

Calibre Rail Document No: CARP10026-REP-G-001

Brockman Resources – Marillana Iron Ore Project Revision No: 0

Preliminary Feasibility Study Report Issue Date: Sep 2010

Page No: Page 75 of 93

\\perfps01\CEJV$\PRO-Projects\2010\CARP10026 BR-Marillana Study\02 - PFS Study\06 Engineering\6.12 Reports\BRL Marillana Rail Project PFS Rev 0\CARP10026 - REP - G - 001-

Brockman Resources Marillana Project - Pre-Feasibility Study Report - Rev_0.doc

• The appropriate rehabilitation of disturbed areas for temporary works including haul roads, storage and work areas, and free draining borrow pits; and

• The preservation, where possible, of established vegetation in areas of temporary disturbance such as construction camps and haul roads.

During this PFS, environmental management has focussed on designing for minimising environmental impacts during construction, operation and closure.

Page 86: CARP10026 - REP - G - 001- BRL Marillana Project - PFS Report - Rev_0

Calibre Rail Document No: CARP10026-REP-G-001

Brockman Resources – Marillana Iron Ore Project Revision No: 0

Preliminary Feasibility Study Report Issue Date: Sep 2010

Page No: Page 76 of 93

\\perfps01\CEJV$\PRO-Projects\2010\CARP10026 BR-Marillana Study\02 - PFS Study\06 Engineering\6.12 Reports\BRL Marillana Rail Project PFS Rev 0\CARP10026 - REP - G - 001-

Brockman Resources Marillana Project - Pre-Feasibility Study Report - Rev_0.doc

10.0 ACTS, REGULATIONS AND STANDARDS FOR THE PROJECT

10.1 Document Precedence The document hierarchy of precedence in descending order shall be:

• Project design criteria;

• Pilbara Iron Standard Specifications;

• Australian Standards; and

• Other Standards.

Where conflicting information exists, it shall be the more stringent standard that applies. Where there is absent information, the Principal shall determine and direct on the principles of best practice. None of the above however shall detract from Statutory Requirements which shall be complied with at all times.

10.2 Statutory Authorities Statutory authorities shall for the purpose of this document include the:

• Department of Transport – Office of Rail Safety;

• The WA Rail Safety Act and other regulations;

• Office of Energy W.A. (OOE) and Western Power (Electricity Act and

• Regulations);

• Department of Industry and Resources (Mines Regulation Act and

• Regulations);

• Worksafe Western Australia (Occupational Health Safety and Welfare Act

• and Regulations); and

• Port Hedland Port Authority (PHPA).

10.3 Environmental Regulations The appropriate Australian environmental standards and regulations (WA) shall be used. The approved Public Environmental Reviews (PER) shall be the basis for designing and managing in environmental protection requirements.

Page 87: CARP10026 - REP - G - 001- BRL Marillana Project - PFS Report - Rev_0

Calibre Rail Document No: CARP10026-REP-G-001

Brockman Resources – Marillana Iron Ore Project Revision No: 0

Preliminary Feasibility Study Report Issue Date: Sep 2010

Page No: Page 77 of 93

\\perfps01\CEJV$\PRO-Projects\2010\CARP10026 BR-Marillana Study\02 - PFS Study\06 Engineering\6.12 Reports\BRL Marillana Rail Project PFS Rev 0\CARP10026 - REP - G - 001-

Brockman Resources Marillana Project - Pre-Feasibility Study Report - Rev_0.doc

10.4 Australian Standards All Australian Standards apply unless noted otherwise. The Australian Standards are inclusive of but not limited to those listed in Appendix B of Basis of Design document.

11.0 PROJECT RISKS MITIGATION No risk management was done for the PFS. This will be done during the DFS.

12.0 CONCLUSION AND RECOMMENDATIONS This report is solely to provide a basis of information and comparison to enable Brockman Resources Limited to facilitate further negotiations and strategic planning. As such, no conclusive recommendations have been drawn from this study, nor can any be made until the strategic objectives of the project have been confirmed.

Page 88: CARP10026 - REP - G - 001- BRL Marillana Project - PFS Report - Rev_0

Calibre Rail Document No: CARP10026-REP-G-001

Brockman Resources – Marillana Iron Ore Project Revision No: 0

Preliminary Feasibility Study Report Issue Date: Sep 2010

Page No: Page 78 of 93

\\perfps01\CEJV$\PRO-Projects\2010\CARP10026 BR-Marillana Study\02 - PFS Study\06 Engineering\6.12 Reports\BRL Marillana Rail Project PFS Rev 0\CARP10026 - REP - G - 001-

Brockman Resources Marillana Project - Pre-Feasibility Study Report - Rev_0.doc

Intentionally Blank

Page 89: CARP10026 - REP - G - 001- BRL Marillana Project - PFS Report - Rev_0

Calibre Rail Document No: CARP10026-REP-G-001

Brockman Resources – Marillana Iron Ore Project Revision No: 0

Preliminary Feasibility Study Report Issue Date: Sep 2010

Page No: Page 79 of 93

\\perfps01\CEJV$\PRO-Projects\2010\CARP10026 BR-Marillana Study\02 - PFS Study\06 Engineering\6.12 Reports\BRL Marillana Rail Project PFS Rev 0\CARP10026 - REP - G - 001-

Brockman Resources Marillana Project - Pre-Feasibility Study Report - Rev_0.doc

13.0 PATH FORWARD Building on this Preliminary Feasibility Report, Calibre Rail proposes that the next phase would entail the completion of a detailed Bankable Feasibility Study to develop more detailed engineering and cost estimates on a preferred route to bring the Brockman Resources project closer to fruition. The following engineering, surveying, geotechnical, hydrogeological and estimating work are recommended as part of a feasibility study:

• For the railway route complete the following;

− non ground-disturbing geotechnical reconnaissance;

− geotechnical mapping and reporting;

− additional aerial surveys and mapping;

− hydrogeological desktop study and reconnaissance; and

− non ground-disturbing geotechnical investigation of bridge locations;

• Optimise the railway alignment through detailed design supported by train operations simulation that delivers minimal Capex whilst enabling safe and cost effective long term operations;

• Complete the preliminary designs for:

− drainage;

− bridge, including hydrology, flood levels, scour depths and foundation;

− earthworks; and

− rail maintenance workshop and temporary facilities.

• Determine construction water requirements and sources;

• Assess railway crossings requirements;

• Complete preliminary project and construction schedules;

• Prepare:

− a project implementation strategy;

− contracting and procurement strategy;

− railway design criteria and track structure design; and

− rail operating and maintenance strategy;

• Complete dynamic modelling of rail operations; and

• Prepare a Capex estimate accurate to ±15%.

During and after completion of the detailed feasibility study the following will be required before SDL project approval:

• Value engineering to identify cost savings;

Page 90: CARP10026 - REP - G - 001- BRL Marillana Project - PFS Report - Rev_0

Calibre Rail Document No: CARP10026-REP-G-001

Brockman Resources – Marillana Iron Ore Project Revision No: 0

Preliminary Feasibility Study Report Issue Date: Sep 2010

Page No: Page 80 of 93

\\perfps01\CEJV$\PRO-Projects\2010\CARP10026 BR-Marillana Study\02 - PFS Study\06 Engineering\6.12 Reports\BRL Marillana Rail Project PFS Rev 0\CARP10026 - REP - G - 001-

Brockman Resources Marillana Project - Pre-Feasibility Study Report - Rev_0.doc

• Geotechnical investigations on the railway route including test pits, dozer excavations, drilling, testing and reporting;

• Geotechnical drilling at the bridge foundations including testing and reporting;

• Groundwater exploration drilling, hydrogeological test work, bore testing and reporting;

• Ground surveys for those areas not covered by the current survey;

• Detailed design for railway earthworks and drainage;

• Detailed design for camps, access roads and temporary infrastructure, and signalling and communications;

• Produce detailed design for communications, signalling and asset protection;

• Construction and project schedules;

• Produce tender documents, and start procurement activities for long-lead items;

• Conduct heritage and environmental surveys of the alignment; and

• Install survey control for the railway construction and do an aerial survey for a construction-accuracy model.

Page 91: CARP10026 - REP - G - 001- BRL Marillana Project - PFS Report - Rev_0

Calibre Rail Document No: CARP10026-REP-G-001

Brockman Resources – Marillana Iron Ore Project Revision No: 0

Preliminary Feasibility Study Report Issue Date: Sep 2010

Page No: Page 81 of 93

\\perfps01\CEJV$\PRO-Projects\2010\CARP10026 BR-Marillana Study\02 - PFS Study\06 Engineering\6.12 Reports\BRL Marillana Rail Project PFS Rev 0\CARP10026 - REP - G - 001-

Brockman Resources Marillana Project - Pre-Feasibility Study Report - Rev_0.doc

14.0 APPENDICES Appendices Register

Appendix Title and Number

A Related and Supporting Documents Register

B Simulation results for OPT1 HA2 VA2 and OPT2 HA1 VA1

C Project Schedules for OPT1 HA2 VA2 and OPT2 HA1 VA1

D Engineering Drawings, 12 alignments on Google earth (Drawing 0074), track Schematics and Signalling & Communications Schematics

Page 92: CARP10026 - REP - G - 001- BRL Marillana Project - PFS Report - Rev_0

Calibre Rail Document No: CARP10026-REP-G-001

Brockman Resources – Marillana Iron Ore Project Revision No: 0

Preliminary Feasibility Study Report Issue Date: Sep 2010

Page No: Page 82 of 93

\\perfps01\CEJV$\PRO-Projects\2010\CARP10026 BR-Marillana Study\02 - PFS Study\06 Engineering\6.12 Reports\BRL Marillana Rail Project PFS Rev 0\CARP10026 - REP - G - 001-

Brockman Resources Marillana Project - Pre-Feasibility Study Report - Rev_0.doc

Intentionally Blank

Page 93: CARP10026 - REP - G - 001- BRL Marillana Project - PFS Report - Rev_0

Calibre Rail Document No: CARP10026-REP-G-001

Brockman Resources – Marillana Iron Ore Project Revision No: 0

Preliminary Feasibility Study Report Issue Date: Sep 2010

Page No: Page 83 of 93

\\perfps01\CEJV$\PRO-Projects\2010\CARP10026 BR-Marillana Study\02 - PFS Study\06 Engineering\6.12 Reports\BRL Marillana Rail Project PFS Rev 0\CARP10026 - REP - G - 001-

Brockman Resources Marillana Project - Pre-Feasibility Study Report - Rev_0.doc

Appendix A : Related and Supporting Documents Register

Document No/Source Title/Subject

CPJP10006-0525-STD-G-001 Calibre Rail−Brockman Resources Marillana Creek Project – Basis of Design

CPJP 10006-0520-REP-G-007 Calibre Projects Marillana Iron Ore Project Definitive Engineering Study, Product Loadout Facility

9016A-REP-00-G-001 Brockman Resources Maillana project rail corridor desktop study report

CARS10013 Brockman Resources Marillana Iron Ore Project Work Plan for Rail Engineering; • Study 1 - Definitive Feasibility Study – Loop • Study 2 – Preliminary Feasibility Study – Line to FMG

Tie In DEM 10m post and imagery 1.5 m GSD Purchased from Landgate