capturing changes to paf after proposal is submitted to the sponsor but prior to award option 1 –...
TRANSCRIPT
![Page 1: Capturing Changes to PAF after Proposal is Submitted to the Sponsor but PRIOR to Award Option 1 – Budget change =>20% ( or other triger) 1.PAF sent back](https://reader035.vdocuments.us/reader035/viewer/2022070413/5697bfd31a28abf838cabf9b/html5/thumbnails/1.jpg)
Capturing Changes to PAF after Proposal is Submitted to the Sponsor
but PRIOR to Award
Option 1 – Budget change =>20% ( or other triger)1. PAF sent back by ORSP so the PI team can fix the PAF. Changes are captured on the PAF per ORSP SOP 300.01
Option 2 – All other changes prior to award are to be handled per 2nd FAQ of ORSP SOP 300.01 (item 1 below) and LSA Process (item 2 below)
2. Revised Proposal Documents which are required by a Sponsor, but do not reflect the changes listed in this policy, should be uploaded to the applicable eRPM PAF record via a Posted Comment, and you should include your ORSP Project Representative and Dean’s Office as a Posted Comment recipient. THIS INCLUDES ALL CHANGES NOT JUST BUDGET CHANGES.
3. Commitment changes (ie.budget amount, subcontract amount, subproject grant amount(s), and effort will be added to MUD fields.
![Page 2: Capturing Changes to PAF after Proposal is Submitted to the Sponsor but PRIOR to Award Option 1 – Budget change =>20% ( or other triger) 1.PAF sent back](https://reader035.vdocuments.us/reader035/viewer/2022070413/5697bfd31a28abf838cabf9b/html5/thumbnails/2.jpg)
Capturing Changes to PAF at Award
Option 1 – Change of =>20% between PAF and award1. Follow process in ORSP SOP 400.012. LSA Research Office will require the following prior to their approval:
• Explanation of how budget cut affects aims of project, revised budget and budget justification (posted to PAF via post a comment)
• Update MUD screen for budget amount, subcontract amount, subproject grant amounts(s), and effort
Option 2 – Change of <20% between PAF and award3. LSA Research Office will contact RA requesting the following:
• Copy of completed 7471 (which is required via the PAN). Should be upload via post a comment in eRPM with us selected as comment recipient
• Update MUD screen for budget amount, subcontract amount, subproject grant amounts(s), and effort
Option 3 – No Change between PAF and award4. No updates to MUD5. LSA does not need to see a copy of 7471
![Page 3: Capturing Changes to PAF after Proposal is Submitted to the Sponsor but PRIOR to Award Option 1 – Budget change =>20% ( or other triger) 1.PAF sent back](https://reader035.vdocuments.us/reader035/viewer/2022070413/5697bfd31a28abf838cabf9b/html5/thumbnails/3.jpg)
![Page 4: Capturing Changes to PAF after Proposal is Submitted to the Sponsor but PRIOR to Award Option 1 – Budget change =>20% ( or other triger) 1.PAF sent back](https://reader035.vdocuments.us/reader035/viewer/2022070413/5697bfd31a28abf838cabf9b/html5/thumbnails/4.jpg)
![Page 5: Capturing Changes to PAF after Proposal is Submitted to the Sponsor but PRIOR to Award Option 1 – Budget change =>20% ( or other triger) 1.PAF sent back](https://reader035.vdocuments.us/reader035/viewer/2022070413/5697bfd31a28abf838cabf9b/html5/thumbnails/5.jpg)
![Page 6: Capturing Changes to PAF after Proposal is Submitted to the Sponsor but PRIOR to Award Option 1 – Budget change =>20% ( or other triger) 1.PAF sent back](https://reader035.vdocuments.us/reader035/viewer/2022070413/5697bfd31a28abf838cabf9b/html5/thumbnails/6.jpg)