capital improvement projects overview

8
Capital Improvement Projects Overview FY 2021-2025

Upload: others

Post on 21-Mar-2022

5 views

Category:

Documents


0 download

TRANSCRIPT

Capital Improvement Projects Overview

FY 2021-2025

2 New Braunfels Utilities

TABLE OF CONTENTS

ELECTRICSystem Extensions ......................................................................3

Kohlenberg Substation and Transmission ...............................3

Electric Aging Infrastructure and Pole Replacements ...........3

Sheriff’s Posse T1/T2 and Sheriff’s Posse Feeders ...................3

E.C. Mornhinweg T2 and Feeders ..............................................3

WATERSurface Water Treatment Plant Expansion ..............................4

Avery Park 30-Inch Water Main ................................................4

2.5-MG Bretzke Storage Tank and 24-inch Bretzke Waterline ....4

Weltner Road Ground Storage Tank and Pump Station .........4

Grandview Pump Station Expansion ........................................4

WASTEWATERGruene Wastewater Treatment Plant Relocation and Expansion to the Gruene Water Reclamation Facility ...........5

North and South Kuehler Rehabilitation ..................................5

McKenzie Water Reclamation Facility Expansion ...................5

McKenzie 33-Inch Interceptor Upgrade....................................5

North Kuehler 30, 33, and 42-Inch Interceptor Upgrade .......5

PLANNING FOR THE FUTUREMap of Projects ...................................................................... 6–7

Capital Improvement Projects Overview

INTRODUCTION

New Braunfels Utilities (NBU) has an aggressive

capital improvement projects plan to build

and enhance necessary infrastructure over

the next five years to meet the needs of a

growing community. As New Braunfels and the

NBU service territory continue to experience

unprecedented growth, NBU has committed to

more than $563 million in capital improvement

projects. This will ensure we are well prepared

to meet the electric, water, and wastewater

needs of our customers for decades to come.

While there are 122 capital improvement projects

in progress and/or being planned, the following

pages provide a high-level overview of NBU’s

key projects.

3Capital Improvement Projects Overview FY 2021-2025

ELECTRIC – CAPITAL IMPROVEMENT PROJECTSTop Five Financial Investments, High-Level Overview

System Extensions – $20.2M

These annual expenditures provide service to accommodate system growth. In FY

2021, NBU estimates electric meter connections to increase by 2.2 percent. It is

estimated that three miles of distribution overhead primary will be added and 22

miles of underground distribution will be added. Specific System Extensions include

those within Veramendi, Vintage Oaks, Solms Landing, and many other developments.

Electric Aging Infrastructure and Pole Replacements – $19.1M

This pair of ongoing projects consists of replacing aging infrastructure within the

system. Utility poles, overhead wire, pad-mounted equipment, and underground

cable are included and bring NBU infrastructure up to current standards upon

completion. In particular, newer and technologically superior materials are

anticipated to have a greater lifespan and duty cycle. For example, new underground

cable is designed for a minimum 40-year service life. Critical utility poles are

designed for a minimum 80-year service life.

Kohlenberg Substation and Transmission – $10.6M

New Braunfels Utilities has identified the need for additional transmission and

distribution feeder capacity along FM 1101, near Kohlenberg Road. Growth within

the region includes that of Heatherfield subdivision, the Government Land Office

(GLO) property, and adjacent industrial load. The substation would require a 3.2

mile transmission extension by NBU, and a backside transmission extension by

LCRA TSC in order to provide looped redundancy. The substation would be master-

planned for two power transformers and up to six distribution feeders.

Sheriff’s Posse T1/T2 and Sheriff’s Posse Feeders 13 – $6.6M

To serve anticipated growth along the southeast side of the IH-35 corridor

from FM 1103 to Schmidt Road, NBU is planning to upgrade and replace two legacy

and underrated substation power transformers (PWTs). The existing PWTs are

rated 12/16/20MVA and are insufficient to serve increased growth. Both PWTs

are to be replaced with 20/26.6/33.3MVA capacity. In addition, the substation 138kV

side will be upgraded to a high-reliability ring bus, which effectively eliminates

any single point of failure within the substation. The substation is also master-

planned for a third PWT in the future. New Braunfels Utilities also plans to extend

one new distribution feeder to serve several expanding and newly proposed residential

developments, including Morningside Trails and Morningside Hills.

E.C. Mornhinweg T2 and Feeders 21 and 22 – $5.7M

To serve new commercial and industrial growth along the northwest side

of the IH-35 corridor from FM 1103 to Loop 337, NBU is planning to add a second

Power Transformer at the E.C. Mornhinweg Substation. The substation 138kV

side will be upgraded to a ring bus. Two new feeders are to be immediately

extended from E.C. Mornhinweg, one to the east and one to the west, in order to

serve new growth and provide increased distribution reliability and switching

capacity to the region.

Vintage Oaks System Extension

T1/T2/T3 Feeders

Pole Maintenance

Sheriff's Posse Feeders

E.C. Mornhinweg Feeders

4

WATER – CAPITAL IMPROVEMENT PROJECTSTop Five Financial Investments, High-Level Overview

Surface Water Treatment Plant Expansion - Water Supply Facilities – $38.8M

The current Surface Water Treatment Plant (SWTP) has a design capacity of 8.0 MGD.

This project will double the plant size for a total capacity of 16.0 MGD. This plant

expansion will allow NBU to treat all its Canyon Reservoir water and will increase

NBU’s ability to divert and treat a greater amount of its run-of-river rights. This project

is necessary to meet peak demand and to serve future growth in the community.

Avery Park 30-Inch Water Main – $15.8M

Improvements include replacing portions of the existing 8/10/12‐inch water lines

along Highway 46 from Interstate 35 to Weltner Road, and the existing eight‐inch

line along Weltner Road from Highway 46 to the existing Avery elevated storage

tank (EST). The project was initially proposed as a 20-inch water main; however,

it has been upsized during design to primarily a 30-inch water main in an effort to

accommodate the proposed Weltner Pump Station. Project completion will provide

increased transmission capacity to Avery EST and additional capacity to serve

future growth in the eastern portion of the Downtown Pressure Zone (PZ).

The project will ensure NBU has the capacity to serve the Downtown PZ with

the new water supplies from Seguin and Guadalupe-Blanco River Authority (GBRA).

3.0 MG Bretzke EST and 24-inch Bretzke Waterline – $11.9M

This project installs a 3.0 MG ground storage tank near the intersection of

Bretzke Lane and FM 306 serving the Downtown PZ as elevated storage and will

include a new 24-inch line from the site of the proposed tank to the future 30-inch

SWTP Discharge Line along Gruene Road. Projects include replacing the existing

12-inch line along Hunter Road, and decommissioning the existing Bretzke Phase 1

ground storage tank. These improvements will provide additional elevated storage

capacity and improve operations in the Downtown PZ. In the first phase of the

project, Bretzke was converted from the Kohlenberg PZ to an independent

PZ with a higher hydraulic grade, which increases pressure.

Weltner Road Ground Storage Tank and Pump Station – $10.8M

Project objectives include building the first of two phases of a pump station with

ground storage facilities scheduled to receive and integrate new water supplies

into the east side of the NBU water system. New Braunfels Utilities has currently

identified 10,000 acre-feet of water supply that will be delivered to this pump

station by 2023 with the first portions of that water coming on as early as fall

2020. Phase 1 of this pump station includes a 1.5 million gallon ground storage

tank to receive the entire 10,000 acre-feet of water supply, a 10 MGD pump station,

and the purchase of a site capable of expanding to a 20 MGD facility.

Grandview Pump Station Expansion – $6.4M

The expansion of this station will provide necessary pumping capacity from Well #4 and

additional storage capacity during peak demand due to the postponement of the Trinity

Expansion. The project includes replacement of the existing 0.2 MG ground storage tank with

a new 1.20 MG ground storage tank. Pump station improvements at the Grandview Pump

Station site, and pump upgrades at Well #4 to a capacity of 4,000 Gallons Per Minute (gpm).

New Braunfels Utilities

SWTP Expansion

Avery Park Water Main

Bretzke Waterline

Rendering of Weltner Road Project

Rendering of Grandview Pump Station Expansion

5

WASTEWATER – CAPITAL IMPROVEMENT PROJECTSTop Five Financial Investments, High-Level Overview

Gruene Wastewater Treatment Plant Relocation and Expansion – $58.1M

This project will expand the capacity of the Gruene Wastewater Treatment Plant

and relocate the plant out of the floodplain. Phase 1 will be constructed within

the scope of this project and will have a capacity of 2.5 MGD. The project will

include odor control, sewer transfer pipe from the existing plant to the new plant,

abandonment of the existing plant, abandonment of a lift station, and construction

of a sewer transfer pipe from Blieders Creek.

North and South Kuehler Rehabilitation – $46.3M

The project includes replacing existing aeration equipment, walkways, and gates in

all aerations basins except the new basins at South Kuehler, replacing the existing

clarifiers including the addition of a submerged effluent launder system at South

Kuehler, replacing all existing blowers at North and South Kuehler, replacing the

existing Motor Control Centers (MCC) in the sludge pump buildings, replacing the

MCC in the admin building at South Kuehler, rehabilitation of the existing buried

Return Activated Sludge (RAS) piping at South Kuehler, replacing the existing

drain return pumps at North Kuehler, addition of a new digester blower at North

Kuehler, replacing the existing screening and grit treatment structures at both

plants with a new common headworks with screens, aerated grit chambers,

lift station, and elevated flow split structure, and constructing a new access road

from FM-725 and a private vehicular traffic bridge across the North tributary.

McKenzie Water Reclamation Facility Expansion – $43.6M

This project includes expansion of the Biological Nutrient Removal (BNR)

treatment process from 2.5 MGD to 5 MGD, including: construction of new flow

splitter box, expansion of headworks facilities, construction of new biological

treatment basins, construction of new secondary clarifiers, expansion of tertiary

filters, expansion of UV disinfection equipment, expansion of aerobic digestions,

expansion of solids dewatering system, and construction of new electrical

equipment, site piping, and miscellaneous site civil improvements. This project

will provide additional treatment capacity for future growth in the McKenzie basin.

McKenzie 33-Inch Interceptor Upgrade – $35.0M

A new 30-inch interceptor replacing the northern portion of the existing 21 and

24-inch interceptors conveying flow to the McKenzie Water Reclamation Facility.

This project will provide additional capacity to serve new growth.

North Kuehler 30, 33, and 42-Inch Interceptor Upgrade – $31.6M

A new 30-inch and 33-inch diameter sewer line will be constructed to replace

an existing 21-inch and 27-inch sewer line in the North Kuehler-7 and North

Kuehler-9 drainage basins. Two aerial crossings will be rehabilitated to carry a

larger pipe and a siphon that will be constructed to cross the Guadalupe River.

The existing interceptors are near capacity during peak wet weather flows.

The project will provide additional capacity for growth in the North Kuehler basin.

Capital Improvement Projects Overview FY 2021-2025

Gruene Water Reclamation Facility

Kuehler Rehabilitation

McKenzie Water Reclamation Facility

Interceptor Upgrade

Interceptor Upgrade

6

FM 1863

FM 3009

FM 306

IH 3

5 N

FM 311

FM 725

FM 2673

DR

REB

UH

FM 482

FM 1101

RIV

ER

RD

IH 35 S

STATE HWY 46 W

FM 1044

FM 2722

FM 758

FM 2252

FM 3159

FM 1102

E EVANS RD

LINK RD

GREEN VALLEY RD

LOOP 337

FM 1103

FM 78

STATE HWY 46 S

YOUNGSFORD RD

MARIO

N RD

CREEK RD

DR A

SS

OR

AB

RAB

QUAIL RUN

SCHO

ENTH

AL R

D

WALD RD

PIEPER RD

STATE HWY 46 N

UNION W

INE R

D

BECK

RD

W K

LEIN

RD

ALTW

EIN LN

N LOOP 1604 E

BAT CAVE RD

CORDOVA RD

HUNTER RD

LANDA ST

REB

EC

CA

CR

EE

K R

D

KRUEGER CANYO

N

RUST

WEIL RD

ALVES LN

E COMMON ST

HOFFMANN LN

MER

LOT

E ZIPP R

D

CIB

OLO

VIS

TA

SEAY LN

SAUR LN

LONE OAK RD

SUN

VA

LLE

Y D

R

DR

ES

OLZRA

WH

CS

LEE S

T

BUNKER ST

LOOKOUT RD

WATSON LN E

LOST TRL

WEGNER R

D

KATY ST

ELM CREEK RD

S SEGU

IN AVE

MORNINGSIDE DRCO

YOTE R

UN

IH 10 W

CAMBRIDGE DR

RIVER C

HASE DR

PURG

ATO

RY R

D

POST RD

COPPER TRACE

MAR

Y BL

VDS WALN

UT AVE

DEAN RD

SUMMIT DR

FM 483

BRETZKE LN

SIERR

A DR

KOEHLER RD

AIRPORT RD

CANY

ON

BEN

D

DOERR LN

HANGING

OAK

ORION DR

DR

NO

SNA

WS

SATTLER RD

COLUMBIA

COLLEEN DR

SMITHSON VALLEY RD

OSO ARROYO

DERBY WAY

RAMBLE RDG

RIEBER RD

EWALD R

D

RIG

HT FO

RK

MARBACH LN

FRANCIS H

ARRIS LN

FALLEN OAK

EDWARDS BLVD

MISSION VALLEY RD

OLD BASTROP RD

KROESCHE LN

CO

PPE

R R

IM

FIELD RD

CREEKWO

OD PASS

ECKH

ARD

T RD

DEDEKE DR

ROCK ST

LAR

IAT RD

G

WOODLAKE DR

HILL AVE

DIRETTO DR

REBECCA RANCH

LAS B

RISAS B

LVD

HAVENWOOD BLVD

PECAN ST

RANGE RDH

ARR

ISO

N R

D

BOGEN RD

SHOOTING S

TAR

RIPPLE WAY

APPALACHIAN TRL

ACORN DR

C.O

.E. R

D

NO

RTH

RID

GE

FM 24

39

SARAH

BLUE PT

COPPER CREST

BUCK TRL

NOR-TEX DR

OVERHILL S

T

RU

SCH

LN

HER

ITAG

E O

AKS

SCHMUCKS RD

EASY ST LARK LNBELL ST

TRIPLE PEAK DRFOX

HIL

L

IH 35 N

DR

REB

UH

IH 35 N

FM 78WEIL RD

IH 3

5 N

IH 35 S

C o m a lC o m a l

G u a d a l u p eG u a d a l u p e

PLANNING FOR THE FUTURE

SYSTEM EXTENSIONS – $20.2M

ELECTRIC AGING INFRASTRUCTURE AND POLE

REPLACEMENTS – $19.1M

NORTH AND SOUTH KUEHLER REHABILITATION – $46.3M

GRUENE WASTEWATER TREATMENT PLANT RELOCATION

AND EXPANSION – $58.1M

NORTH KUEHLER 30, 33, AND 42-INCH INTERCEPTOR

UPGRADE – $31.6M

E.C. MORNHINWEG T2 AND FEEDERS 21 AND 22 – $5.7M

New Braunfels Utilities

LegendNBU Electric Service Territory

NBU Water Boundary

NBU Wastewater Boundary

New Braunfels Utilities

is investing in 122 capital

improvement projects.

The following highlighted

projects represent those

that are currently in

design or in progress for

FY 2021–2025.

7

FM 1863

FM 3009

FM 306

IH 3

5 N

FM 311

FM 725

FM 2673

DR

REB

UH

FM 482

FM 1101

RIV

ER

RD

IH 35 S

STATE HWY 46 W

FM 1044

FM 2722

FM 758

FM 2252

FM 3159

FM 1102

E EVANS RD

LINK RD

GREEN VALLEY RD

LOOP 337

FM 1103

FM 78

STATE HWY 46 S

YOUNGSFORD RD

MARIO

N RD

CREEK RD

DR A

SS

OR

AB

RAB

QUAIL RUN

SCHO

ENTH

AL R

D

WALD RD

PIEPER RD

STATE HWY 46 N

UNION W

INE R

D

BECK

RD

W K

LEIN

RD

ALTW

EIN LN

N LOOP 1604 E

BAT CAVE RD

CORDOVA RD

HUNTER RD

LANDA ST

REB

EC

CA

CR

EE

K R

D

KRUEGER CANYO

N

RUST

WEIL RD

ALVES LN

E COMMON ST

HOFFMANN LN

MER

LOT

E ZIPP R

D

CIB

OLO

VIS

TA

SEAY LN

SAUR LN

LONE OAK RD

SUN

VA

LLE

Y D

R

DR

ES

OLZRA

WH

CS

LEE S

T

BUNKER STLOOKOUT RD

WATSON LN E

LOST TRL

WEGNER R

D

KATY ST

ELM CREEK RD

S SEGU

IN AVE

MORNINGSIDE DRCO

YOTE R

UN

IH 10 W

CAMBRIDGE DR

RIVER C

HASE DR

PURG

ATO

RY R

D

POST RD

COPPER TRACE

MAR

Y BL

VDS WALN

UT AVE

DEAN RD

SUMMIT DR

FM 483

BRETZKE LN

SIERR

A DR

KOEHLER RD

AIRPORT RD

CANY

ON

BEN

D

DOERR LN

HANGING

OAK

ORION DR

DR

NO

SNA

WS

SATTLER RD

COLUMBIA

COLLEEN DR

SMITHSON VALLEY RD

OSO ARROYO

DERBY WAY

RAMBLE RDG

RIEBER RD

EWALD R

D

RIG

HT FO

RK

MARBACH LN

FRANCIS H

ARRIS LN

FALLEN OAK

EDWARDS BLVD

MISSION VALLEY RD

OLD BASTROP RD

KROESCHE LN

CO

PPE

R R

IM

FIELD RD

CREEKWO

OD PASS

ECKH

ARD

T RD

DEDEKE DR

ROCK ST

LAR

IAT RD

G

WOODLAKE DR

HILL AVE

DIRETTO DR

REBECCA RANCH

LAS B

RISAS B

LVD

HAVENWOOD BLVD

PECAN ST

RANGE RD

HAR

RIS

ON

RD

BOGEN RD

SHOOTING S

TAR

RIPPLE WAY

APPALACHIAN TRL

ACORN DR

C.O

.E. R

D

NO

RTH

RID

GE

FM 24

39

SARAH

BLUE PT

COPPER CREST

BUCK TRL

NOR-TEX DR

OVERHILL S

T

RU

SCH

LN

HER

ITAG

E O

AKS

SCHMUCKS RD

EASY ST LARK LNBELL ST

TRIPLE PEAK DRFOX

HIL

L

IH 35 N

DR

REB

UH

IH 35 N

FM 78WEIL RD

IH 3

5 N

IH 35 S

C o m a lC o m a l

G u a d a l u p eG u a d a l u p eAuthor: John David AmaroSystems ControlDate: 3/7/2019

KOHLENBERG SUBSTATION AND TRANSMISSION – $10.6M

GRANDVIEW PUMP STATION EXPANSION – $6.4M

AVERY PARK 30-INCH MAIN – $15.8M

SHERIFF’S POSSE T1/T2 AND SHERIFF’S POSSE

FEEDERS 13 – $6.6M

WELTNER ROAD GROUND STORAGE TANK AND

PUMP STATION – $10.8M

SURFACE WATER TREATMENT PLANT EXPANSION - $38.8M

MCKENZIE 33-INCH INTERCEPTOR

UPGRADE – $35.0M

MCKENZIE WATER RECLAMATION FACILITY EXPANSION – $43.6M

3.0 MG BRETZKE EST AND 24-INCH BRETZKE

WATERLINE – $11.9M

Capital Improvement Projects Overview FY 2021-2025

For more information visit, nbutexas.com/planning-for-the-future-of-new-braunfels/

08.20.2020