CAPITAL IMPROVEMENT PROJECT UPDATE The information contained within this report is intended to provide a summary of large scale capital projects along with current status and anticipated action. The report is current as of the date noted for each project. Additional informational requests should be directed to the appropriate department and/or point of contact. The Bookmark Pane can be used to navigate directly to specific projects. February 2019

Upload: others

Post on 24-Jun-2020

16 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: CAPITAL IMPROVEMENT PROJECT UPDATE...CAPITAL IMPROVEMENT PROJECT UPDATE The information contained within this report is intended to provide a summary of large scale capital projects

CAPITAL IMPROVEMENT

PROJECT UPDATE

The information contained within this report is intended to provide a summary of large scale capital projects along with current status and anticipated action. The report is current as of the date noted for each project. Additional informational requests should be directed to the appropriate department and/or point of contact. The Bookmark Pane can be used to navigate directly to specific projects.

February 2019

Page 2: CAPITAL IMPROVEMENT PROJECT UPDATE...CAPITAL IMPROVEMENT PROJECT UPDATE The information contained within this report is intended to provide a summary of large scale capital projects

This Page Intentionally Left Blank

Page 3: CAPITAL IMPROVEMENT PROJECT UPDATE...CAPITAL IMPROVEMENT PROJECT UPDATE The information contained within this report is intended to provide a summary of large scale capital projects

Project Name:Updated 28-Feb-19

email address

City Budget F.D.O.T. F.A.A. $ 145,000 $ 145,000 $ 2,610,000

5% 5% 90%

City Project Manager Engineer of Record Contractor

Project Status ReportCurrent Phase:

Construction PhasePercent of Phase:

50%RUNWAY 11/29 REHABILITATION (Design & Construction)

Project Description:This project involves a mill and overlay of Runway 11/29's pavement. This will improve instrument approaches and runway safety. This project also includes lighting Runway 11/29. This will allow for aircraft to utilize the runway at night increasing safety for aircraft requiring the crosswind runway. Funding sources for this project are divided between FAA (90%), FDOT (5%), and the Airport (5%).

Project Location:Winter Haven Regional Airport - KGIF

Contact Information

Ashley Udick Hanson Professional Services Preferred Materials, Inc.Office: 863-298-4551 Office: 321-214-9315 Office: [email protected] [email protected]

Milestones accomplished this month

majority of rough grading work on runway shoulder complete

started installation of conduit for the runway lighting

milling runway

Milestones planned for next month:

milling completion

runway paving to begin

runway striping to begin

Communication Activities:

FundingFunding Source (s)Funding AmountFunding Percentage

0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%

RUNWAY 11/29 REHABILITATION (Design & Construction) FUNDING City Budget

F.D.O.T.

F.A.A.

1 of 46

Page 4: CAPITAL IMPROVEMENT PROJECT UPDATE...CAPITAL IMPROVEMENT PROJECT UPDATE The information contained within this report is intended to provide a summary of large scale capital projects

Commence Complete Duration (days)

5/15/2017 5/15/2017 011/17/2017 11/30/2017 139/19/2016 10/26/2016 3712/1/2017 5/13/2018 163

05/14/2018 6/14/2018 311/7/2019 5/6/2019 1197/31/2019 7/31/2019 0

TOTAL Master Plan Design Construction CEI $ 2,900,000.00 $ - $ 230,000.00 $ 2,400,000.00 $ 270,000.00

$ 599,428.61 $ - $ 230,000.00 $ 318,893.80 $ 50,534.81

CO # Date Amount

Construction Bid

Timeline & Budget

Phase

Grant AwardPD&E / Planning

Design BidDesign

In-house construction

ConstructionContract Completion Date

Budget

Expended to Date

CHANGE ORDERS ISSUEDGeneral Detail

013

37163

31119

Sep-16 Apr-17 Oct-17 May-18 Nov-18 Jun-19

Grant AwardPD&E / Planning

Design BidDesign

In-house constructionConstruction Bid

Construction

RUNWAY 11/29 REHABILITATION (Design & Construction) TIMELINE

Duration (days) Current Status Contract Completion Date

0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%

TOTAL

CEI

Construction

Design

Master Plan

RUNWAY 11/29 REHABILITATION (Design & Construction) BUDGET & EXPENSES

Expended to Date Remaining Budget

2 of 46

Page 5: CAPITAL IMPROVEMENT PROJECT UPDATE...CAPITAL IMPROVEMENT PROJECT UPDATE The information contained within this report is intended to provide a summary of large scale capital projects

Project Name:Updated 28-Feb-19

email address

City Budget F.D.O.T. F.A.A. $ 8,333 $ 8,333 $ 149,985

5% 5% 90%

City Project Manager Engineer of Record Contractor

Project Status ReportCurrent Phase:

Design PhasePercent of Phase:

100%OBSTRUCTION SURVEY AND CLEARING

Project Description:The objective of this project is to re-establish the Airport’s GPS Approaches to Runway 11 and Runway 5, which currently contain obstructions to the 34:1 approach surface, as well as clear the 20:1 Approach Surface for Runway 29 and Runway 23. There are four (4) primary components to this project: 1. Perform an obstruction survey to identify obstructions to the 34:1 and 20:1 approach surfaces; 2. Prepare plans to remove/mitigate the obstructions; 3. Perform obstruction removal/mitigation (construction phase); 4. Verify obstruction removal (per 18B survey) and re-instate GPS and Visual approaches.

Project Location:Winter Haven Regional Airport - KGIF

Contact Information

Name: Ashley Udick Hilary Maull - AvCon, Inc. Name: Not SelectedOffice: 863-298-4551 Office: 407-599-1122 Office: [email protected] [email protected]

Milestones accomplished this month

Received the 2nd official FDOT timeline extension approval for June 2020

Milestones planned for next month:

Going back out to bid for contractors, in June 2019

Communication Activities:

FundingFunding Source (s)Funding AmountFunding Percentage

0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%

OBSTRUCTION SURVEY AND CLEARING FUNDING City Budget

F.D.O.T.

F.A.A.

3 of 46

Page 6: CAPITAL IMPROVEMENT PROJECT UPDATE...CAPITAL IMPROVEMENT PROJECT UPDATE The information contained within this report is intended to provide a summary of large scale capital projects

Commence Complete Duration (days)

5/15/2017 5/15/2017 07/1/2017 8/13/2017 438/14/2017 8/14/2017 09/1/2017 4/30/2018 241

05/1/2019 6/1/2019 3110/1/2019 1/31/2020 1223/31/2020 3/31/2020 0

TOTAL Master Plan Design Construction CEI $ 166,650.00 $ - $ 50,000.00 $ 60,961.00 $ 55,689.00

$ 55,685.00 $ - $ 44,390.00 $ - $ 11,295.00

CO # Date Amount

Construction Bid

Timeline & Budget

Phase

Grant AwardPD&E / Planning

Design BidDesign

In-house construction

ConstructionContract Completion Date

Budget

Expended to Date

CHANGE ORDERS ISSUEDGeneral Detail

043

0241

31122

May-17 Dec-17 Jun-18 Jan-19 Jul-19 Feb-20

Grant AwardPD&E / Planning

Design BidDesign

In-house constructionConstruction Bid

Construction

OBSTRUCTION SURVEY AND CLEARING TIMELINE

Duration (days) Current Status Contract Completion Date

0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%

TOTAL

CEI

Construction

Design

Master Plan

OBSTRUCTION SURVEY AND CLEARING BUDGET & EXPENSES

Expended to Date Remaining Budget

4 of 46

Page 7: CAPITAL IMPROVEMENT PROJECT UPDATE...CAPITAL IMPROVEMENT PROJECT UPDATE The information contained within this report is intended to provide a summary of large scale capital projects

Project Name:Updated 28-Feb-19

email address

City Budget F.D.O.T. $ 80,137 $ 320,547

20% 80%

City Project Manager Engineer of Record Contractor

Project Status ReportCurrent Phase:

Design PhasePercent of Phase:

100%Runway 11 RPZ Road Project

Project Description: Relocate the existing access road to the West quadrant of the Airport to move it out of Runway 11 RPZ, and conduct necessary clearing; improving safety for aircraft operations. This project consists of the physical construction of a new access road and related improvements from US 17 and into the Airport property. The road would cross west of the Runway 11-29 RPZ towards the lake and then turn East towards the Seaplane Base. It would continue to stay outside the southern edge of the RPZ before terminating. The road is expected to be some 1400’ long and with a 24’ wide paved surface. The road would have markings and signage.

Project Location:Winter Haven Regional Airport - KGIF

Contact Information

Ashley Udick Hilary Maull - AvCon, Inc. Name: UnknownOffice: 863-298-4551 Office: 407-599-1122 Office: [email protected] [email protected]

Milestones accomplished this month

FDOT revised the transportation agreement to include wetland mitigation costs

FDOT is requiring left turn lane on US 92, cost is being reviewed by FDOT budget committee for inclusion in FDOT current work program

Milestones planned for next month:

Construction Bid

Communication Activities:

FundingFunding Source (s)Funding AmountFunding Percentage

0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%

Runway 11 RPZ Road Project FUNDING City Budget

F.D.O.T.

5 of 46

Page 8: CAPITAL IMPROVEMENT PROJECT UPDATE...CAPITAL IMPROVEMENT PROJECT UPDATE The information contained within this report is intended to provide a summary of large scale capital projects

Commence Complete Duration (days)

5/3/2018 5/3/2018 05/3/2018 5/14/2018 115/14/2018 5/14/2018 05/22/2018 11/19/2018 181

03/19/2019 4/19/2019 315/19/2019 11/19/2019 184

12/31/2019 12/31/2019 0

TOTAL Master Plan Design Construction CEI $ 400,684.00 $ - $ 24,500.00 $ 327,070.00 $ 68,900.00

$ 55,573.00 $ - $ 24,500.00 $ - $ 31,073.00

CO # Date Amount

Construction Bid

Timeline & Budget

Phase

Grant AwardPD&E / Planning

Design BidDesign

In-house construction

ConstructionContract Completion Date

Budget

Expended to Date

CHANGE ORDERS ISSUEDGeneral Detail

011

0181

31184

May-18 Aug-18 Nov-18 Feb-19 Jun-19 Sep-19 Dec-19

Grant AwardPD&E / Planning

Design BidDesign

In-house constructionConstruction Bid

Construction

Runway 11 RPZ Road Project TIMELINE

Duration (days) Current Status Contract Completion Date

0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%

TOTAL

CEI

Construction

Design

Master Plan

Runway 11 RPZ Road Project BUDGET & EXPENSES

Expended to Date Remaining Budget

6 of 46

Page 9: CAPITAL IMPROVEMENT PROJECT UPDATE...CAPITAL IMPROVEMENT PROJECT UPDATE The information contained within this report is intended to provide a summary of large scale capital projects

Project Name:Updated 28-Feb-19

email address

City Budget F.D.O.T. $ 180,000 $ 720,000

20% 80%

FundingFunding Source (s)Funding AmountFunding Percentage

Milestones planned for next month:

90% Design

Communication Activities:

[email protected] [email protected]

Milestones accomplished this month

60% Design

Ashley Udick Blake Swafford - Hanson P.S. Name: UnknownOffice: 863-298-4551 Office: 321-214-9315 Office: xxx-xxx-xxxx

City Project Manager Engineer of Record Contractor

Project Status ReportCurrent Phase:

Design PhasePercent of Phase:

60%T-Hangar #270

Project Description:Design and construct a new ten unit t-hangar building and related improvements. The completed project will be known as Building # 270. Taxilanes are already in place. Construction of the t-hangar building is listed in the Airport Master Plan and shown on the Airport Layout Plan. The airport has a waiting list of approximately 40 aircraft owners (as of 09/2018). This project will generate revenues for the airport and contribute to its self-sustainability.

Project Location:Winter Haven Regional Airport - KGIF

Contact Information

0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%

T-Hangar #270 FUNDING City Budget

F.D.O.T.

7 of 46

Page 10: CAPITAL IMPROVEMENT PROJECT UPDATE...CAPITAL IMPROVEMENT PROJECT UPDATE The information contained within this report is intended to provide a summary of large scale capital projects

Commence Complete Duration (days)

10/8/2018 10/8/2018 00

10/22/2018 10/22/2018 010/22/2018 12/22/2018 61

03/22/2019 4/22/2019 315/22/2019 9/22/2019 123

11/30/2019 11/30/2019 0

TOTAL Master Plan Design Construction CEI $ 900,000.00 $ - $ 55,000.00 $ 780,000.00 $ 65,000.00

$ 10,685.16 $ - $ 10,685.16 $ - $ -

CO # Date Amount

Expended to Date

CHANGE ORDERS ISSUEDGeneral Detail

ConstructionContract Completion Date

Budget

Construction Bid

Timeline & Budget

Phase

Grant AwardPD&E / Planning

Design BidDesign

In-house construction

0

061

31123

Oct-18 Nov-18 Jan-19 Mar-19 Apr-19 Jun-19 Aug-19 Sep-19 Nov-19

Grant AwardPD&E / Planning

Design BidDesign

In-house constructionConstruction Bid

Construction

T-Hangar #270 TIMELINE

Duration (days) Current Status Contract Completion Date

0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%

TOTAL

CEI

Construction

Design

Master Plan

Runway 11 RPZ Road Project BUDGET & EXPENSES

Expended to Date Remaining Budget

8 of 46

Page 11: CAPITAL IMPROVEMENT PROJECT UPDATE...CAPITAL IMPROVEMENT PROJECT UPDATE The information contained within this report is intended to provide a summary of large scale capital projects

Project Name:Updated 28-Feb-19

email address

City Budget $ 1,500,000

100%

FundingFunding Source (s)Funding AmountFunding Percentage

Milestones planned for next month:

100% Design

Communication Activities:

[email protected] [email protected]

Milestones accomplished this month

90% Design

Ashley Udick Brandon Hiers, AVCON, Inc. Name: UnknownOffice: 863-298-4551 Office: 407-599-1122 Office: xxx-xxx-xxxx

City Project Manager Engineer of Record Contractor

Project Status ReportCurrent Phase:

Design PhasePercent of Phase:

90%Utility Infrastructure Improvement Project

Project Description:Design and Construct new utility lines (Sewer, Water, & Fiber Conduit) into three (3) prime development areas on the airport. This project provides the necessary infrastruture improvements to meet the needs of the 2016 Airport Master Plan Capital Improvement Program.

Project Location:Winter Haven Regional Airport - KGIF

Contact Information

0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%

Utility Infrastructure Improvement Project FUNDING City Budget

9 of 46

Page 12: CAPITAL IMPROVEMENT PROJECT UPDATE...CAPITAL IMPROVEMENT PROJECT UPDATE The information contained within this report is intended to provide a summary of large scale capital projects

Commence Complete Duration (days)

00

10/22/2018 10/22/2018 010/22/2018 3/15/2019 144

04/15/2019 5/15/2019 306/15/2019 3/15/2020 2745/31/2020 5/31/2020 0

TOTAL Master Plan Design Construction CEI $ 1,500,000.00 $ - $ 225,000.00 $ 1,200,000.00 $ 75,000.00

$ 13,885.69 $ - $ 13,885.69 $ - $ -

CO # Date Amount

Expended to Date

CHANGE ORDERS ISSUEDGeneral Detail

ConstructionContract Completion Date

Budget

Construction Bid

Timeline & Budget

Phase

Grant AwardPD&E / Planning

Design BidDesign

In-house construction

0144

30274

Oct-18 Jan-19 May-19 Aug-19 Nov-19 Mar-20

Grant AwardPD&E / Planning

Design BidDesign

In-house constructionConstruction Bid

Construction

Utility Infrastructure Improvement Project TIMELINE

Duration (days) Current Status Contract Completion Date

0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%

TOTAL

CEI

Construction

Design

Master Plan

Utility Infrastructure Improvement Project BUDGET & EXPENSES

Expended to Date Remaining Budget

10 of 46

Page 13: CAPITAL IMPROVEMENT PROJECT UPDATE...CAPITAL IMPROVEMENT PROJECT UPDATE The information contained within this report is intended to provide a summary of large scale capital projects

Project Name:

Updated 1-Mar-19

email address

City Budget Benefactor [Source 3] [ Source 4]

$ 125,000 $ 1,442,866 $ - $ -

8% 92% 0% 0%

City Project Manager Engineer of Record Contractor

Sean Byers Kelly Cranford, PE NA

863-298-7932 863-594-2009 NA

[email protected] [email protected]

Milestones accomplished this

month

Submittal of 60% design plans to FDOT for review on February 14

Project Status ReportCurrent Phase:

Design Phase

Percent of Phase:

60%

Avenue C, SW/Second Street, SW

Project Description:

This project will convert an existing street with two 24-foot travel lanes into a corridor with two 10 to 11-foot

travel lanes, on-street parking, upgraded sidewalks and crosswalks, a multi-use trail, and landscaping

along Avenue C, SW from First Street to Fifth Street, SW. The project will also add 5-foot and 6-foot

sidewalks along Second Street, SW between Avenue C, SW and Avenue G, SW.

Project Location:

Contact Information

Avenue C, SW between 1st Street S and 5th Street, SW; and 2nd Street SW between Avenue C, SW and

Avenue G, SW

Funding

Funding Source (s)

Funding Amount

Funding Percentage

Milestones planned for next

month:

Awaiting FDOT comments on 60% design plans

Neighborhood Open House

Communication Activities:

FDOT quarterly progress meeting on February 20, 2019

0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%

Avenue C, SW/Second Street, SW FUNDING City Budget

Benefactor

[Source 3]

[ Source 4]

11 of 46

Page 14: CAPITAL IMPROVEMENT PROJECT UPDATE...CAPITAL IMPROVEMENT PROJECT UPDATE The information contained within this report is intended to provide a summary of large scale capital projects

Commence Complete Duration (days)

7/1/2017 7/1/2017 0

0

0

10/9/2018 5/31/2019 234

0

0

0

5/31/2019 5/31/2019 0

TOTAL Master Plan Design Construction CEI

$ 1,567,866.00 $ - $ 125,000.00 $ 1,442,866.00 $ -

$ 65,409.00 $ - $ 65,409.00 $ - $ -

CO # Date Amount

Timeline & Budget

Construction Bid

Construction

Contract Completion Date

Budget

Phase

Grant Award

PD&E / Planning

Design Bid

Design

In-house construction

CHANGE ORDERS ISSUED

General Detail

Expended to Date

234

Jun-17 Sep-17 Jan-18 Apr-18 Jul-18 Nov-18 Feb-19 May-19

Grant Award

PD&E / Planning

Design Bid

Design

In-house construction

Construction Bid

Avenue C, SW/Second Street, SW TIMELINE

Duration (days) Current Status Contract Completion Date Grant Award

0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%

TOTAL

CEI

Construction

Design

Master Plan

ENTER PROJECT NAME (ALL CAPS) BUDGET & EXPENSES

Expended to Date Remaining Budget

12 of 46

Page 15: CAPITAL IMPROVEMENT PROJECT UPDATE...CAPITAL IMPROVEMENT PROJECT UPDATE The information contained within this report is intended to provide a summary of large scale capital projects

Project Name:Updated 1-Mar-19

City Budget Polk County Utility Loan [ Source 4] $ 15,000,000 $ 11,000,000 $ 1,220,000 $ -

55% 40% 4% 0%

City Project Manager Engineer of Record Contractor

Project Status ReportCurrent Phase:

Construction PhasePercent of Phase:

30%CHAIN OF LAKES PARK PHASE 1 - FIELD HOUSE / CONF. CENTER

Project Description:The full project will repurpose the entire property to include repurposing the existing Civic Center to focus more on performing arts, banquet facilities, and aquatics; construction of multi-court athletic and convention venue; redesign of the minor league baseball fields to accommodate tournament and league play; and activation of the waterfront area along Lake Lulu. The Polk County BoCC/TDC has committed $10 million dollars toward debt service payments associated with the redevelopment. Phase 1 focuses on the new Field Hosue / Conference Center and renovation of the existing building.

Project Location:210 Cypress Gardens Boulevard

Contact Information

T. Michael Stavres Straughn Trout Arch. (STA) Rodda ConstructionOffice: 863-291-5600 Office: 863-665-6205 Office: [email protected] [email protected]

Milestones accomplished this month

Permit received for FDOT Access Management; design for re-use

water line complete; tilt wall panels poured and prepped for install;

interior demolition continued;

[email protected]

Milestones planned for next month:

Installation of tilt wall panels; complete interior demolition including all

exterior openings; begin interior framing; receive structural steel;

comlpete slab for new Theatre storage building

Communication Activities:

Project/schedule coordination meeting with CMAR, Architect, staff,

TWH, and RAA specific to retrofit of existing systems (2/20)

Coordination meeting with Chamber for Tilt-Up Party (2/22)

FundingFunding Source (s)Funding AmountFunding Percentage

0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%

CHAIN OF LAKES PARK PHASE 1 - FIELD HOUSE / CONF. CENTER FUNDING City Budget

Polk County

Utility Loan

[ Source 4]

13 of 46

Page 16: CAPITAL IMPROVEMENT PROJECT UPDATE...CAPITAL IMPROVEMENT PROJECT UPDATE The information contained within this report is intended to provide a summary of large scale capital projects

Commence Complete Duration (days)

08/1/2016 4/17/2017 2596/12/2017 9/30/2017 110

11/27/2017 11/1/2018 3390

9/26/2017 2/12/2018 1392/13/2018 11/1/2019 62611/1/2019 11/1/2019 0

TOTAL Master Plan Design Construction CEI / City Exp. $ 27,220,000.00 $ 275,000.00 $ 1,882,932.00 $24,518,789.00 $ 497,000.00

$ 4,518,624.60 $ 290,131.00 $ 1,510,729.71 $ 2,686,705.89 $ 31,058.00

CO # Date AmountSTA CO1-5 3/6/18-11/21/18 107,932$ Rodda CO1-4 1/28/19-2/20/19 (2,927,495)$ Rodda CO5 1/28/2019 43,531$

Construction Bid

Timeline & Budget

Phase

Grant AwardPD&E / Planning

Design BidDesign

In-house construction

ConstructionContract Completion Date

Budget

Expended to Date

CHANGE ORDERS ISSUEDGeneral DetailBldg. Sys. audit/design; soil boring; FDOT coord.; storm des.Deductive CO - Direct Purchase items (savings $141,268.28 )Various owner directed changes and site condition items

259110

339

139626

Mar-17 Jul-17 Oct-17 Jan-18 Apr-18 Aug-18 Nov-18 Feb-19 Jun-19 Sep-19

Grant AwardPD&E / Planning

Design BidDesign

In-house constructionConstruction Bid

Construction

CHAIN OF LAKES PARK PHASE 1 - FIELD HOUSE / CONF. CENTER TIMELINE

Duration (days) Current Status Contract Completion Date

-20% 0% 20% 40% 60% 80% 100%

TOTAL

CEI / City Exp.

Construction

Design

Master Plan

CHAIN OF LAKES PARK PHASE 1 - FIELD HOUSE / CONF. CENTER BUDGET & EXPENSES

Expended to Date Remaining Budget

14 of 46

Page 17: CAPITAL IMPROVEMENT PROJECT UPDATE...CAPITAL IMPROVEMENT PROJECT UPDATE The information contained within this report is intended to provide a summary of large scale capital projects

Project Name:Updated 28-Feb-19

City Budget [Source 2] [Source 3] [ Source 4] $ 275,000 $ - $ - $ -

100% 0% 0% 0%

City Project Manager Engineer of Record Contractor

Project Status ReportCurrent Phase:

Design PhasePercent of Phase:

100%L/S 137 HAVENDALE BLVD. (MOOSE LODGE)

Project Description:This project involves the replacement of an old barrel-type lift station with an updated submersible station (wet well, submersible pumps, and control valves) and relocating the station inside an easement on the Moose Lodge property (Havendale Boulevard, west of 21st Street, NW).

Project Location:Havendale Boulevard, west of 21st Street, NW

Contact Information

Name: Amin Hanhan, P.E. Name: Willie Nabong, P.E. Name: TBDOffice: 863-291-5850 Office: 863-291-5850 Office:

Milestones planned for next month:

Contact a property owner to provide a 10 ft. wide Utility Easement.

Prepare submittal package and submit for permitting with FDEP and

FDOT.

Communication Activities:

Provide the 100% plans and bid package for the Utilities Department staff

for their review and comment.

[email protected] [email protected]

Milestones accomplished this month

Design work is at 100%. A draft bid document has been prepared.

A Right of Way Use Permit from Polk County was issued on January 10.

Funding AmountFunding Percentage

FundingFunding Source (s)

0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%

L/S 137 HAVENDALE BLVD. (MOOSE LODGE) FUNDING City Budget

[Source 2]

[Source 3]

[ Source 4]

15 of 46

Page 18: CAPITAL IMPROVEMENT PROJECT UPDATE...CAPITAL IMPROVEMENT PROJECT UPDATE The information contained within this report is intended to provide a summary of large scale capital projects

Commence Complete Duration (days)

000

8/20/2018 11/30/2018 1020

4/1/2019 4/30/2019 297/1/2019 9/30/2019 919/30/2019 9/30/2019 0

TOTAL Master Plan Design Construction CEI $ 275,000.00 $ - $ - $ 275,000.00 $ -

$ - $ - $ - $ - $ -

CO # Date Amount

Timeline & Budget

ConstructionContract Completion Date

Budget

Construction BidIn-house construction

Phase

Grant AwardPD&E / Planning

Design BidDesign

Expended to Date

CHANGE ORDERS ISSUEDGeneral Detail

102

29 91

Aug-18 Oct-18 Nov-18 Jan-19 Mar-19 Apr-19 Jun-19 Aug-19 Sep-19

Grant AwardPD&E / Planning

Design BidDesign

In-house constructionConstruction Bid

Construction

L/S 137 HAVENDALE BLVD. (MOOSE LODGE) TIMELINE

Duration (days) Current Status Contract Completion Date

0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%

TOTAL

CEI

Construction

Design

Master Plan

L/S 137 HAVENDALE BLVD. (MOOSE LODGE) BUDGET & EXPENSES

Expended to Date Remaining Budget

16 of 46

Page 19: CAPITAL IMPROVEMENT PROJECT UPDATE...CAPITAL IMPROVEMENT PROJECT UPDATE The information contained within this report is intended to provide a summary of large scale capital projects

Project Name:Updated 28-Feb-19

City Budget [Source 2] [Source 3] [ Source 4] $ 75,000 $ - $ - $ -

100% 0% 0% 0%

[email protected]

Helena Road-North of bridge to Winterset Road

FundingFunding Source (s)Funding AmountFunding Percentage

Milestones planned for next month:

Start construction by in-house utility crews and annual directional bore

contractor.

Communication Activities:

[email protected] [email protected]

Milestones accomplished this month

City Commission approved the PO for the purchase of the materials on

October 9.

The materials needed for the project have been purcahsed.

Name: Amin Hanhan, P.E. Name: Amin Hanhan, P.E. Name: City of Winter HavenOffice: 863-291-5850 Office: 863-291-5850 Office: 863-291-5853

Project Description:This project involves replacing an existing 6-inch AC water main with a new 8-inch PVC C900 water main.

Project Location:

Contact InformationCity Project Manager Engineer of Record Contractor

HELENA ROAD WATER MAIN EXTENSION-PHASE 3

Project Status ReportCurrent Phase:

Construction PhasePercent of Phase:

<10%

0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%

HELENA ROAD WATER MAIN EXTENSION-PHASE 3 FUNDING City Budget

[Source 2]

[Source 3]

[ Source 4]

17 of 46

Page 20: CAPITAL IMPROVEMENT PROJECT UPDATE...CAPITAL IMPROVEMENT PROJECT UPDATE The information contained within this report is intended to provide a summary of large scale capital projects

Commence Complete Duration (days)

000

5/1/2018 6/1/2018 314/15/2019 6/14/2019 60

00

6/14/2019 6/14/2019 0

TOTAL Master Plan Design Construction CEI $ 75,000.00 $ - $ - $ 75,000.00 $ -

$ - $ - $ - $ - $ -

CO # Date Amount

Expended to Date

CHANGE ORDERS ISSUEDGeneral Detail

ConstructionContract Completion Date

Budget

Grant AwardPD&E / Planning

Design BidDesign

In-house constructionConstruction Bid

Timeline & Budget

Phase

31 60

May-18 Jun-18 Jul-18 Aug-18 Oct-18 Nov-18 Dec-18 Feb-19 Mar-19 Apr-19 Jun-19

Grant AwardPD&E / Planning

Design BidDesign

In-house constructionConstruction Bid

Construction

HELENA ROAD WATER MAIN EXTENSION-PHASE 3 TIMELINE

Duration (days) Current Status Contract Completion Date

0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%

TOTAL

CEI

Construction

Design

Master Plan

HELENA ROAD WATER MAIN EXTENSION-PHASE 3 BUDGET & EXPENSES

Expended to Date Remaining Budget

18 of 46

Page 21: CAPITAL IMPROVEMENT PROJECT UPDATE...CAPITAL IMPROVEMENT PROJECT UPDATE The information contained within this report is intended to provide a summary of large scale capital projects

Project Name:Updated 28-Feb-19

email address

City Budget CDBG [Source 3] [ Source 4] $ - $ 380,000 $ - $ -

0% 100% 0% 0%

City Project Manager Engineer of Record Contractor

Project Status ReportCurrent Phase:

Construction PhasePercent of Phase:

<10%LAKE HOWARD DOCK / HERITAGE PARK PIER

Project Description:The City has obtianed Community Development Block Grant Funding for the design-build of a new dock at Heritage Park on Lake Howard. The City has devloped site plans of the desired renovations including demo of the existing dock and the desired layout of the new dock and pier. A Design - Build team will be selected to utilize the existing site plans, complete all necessay structural, geotechnical, and electrical engineering design and permitting, and construct the dock. The project will include 3 covered areas, 2 floating docks, and a debris catching device.

Project Location:Lake Howard Drive, NW.

Contact Information

Name: Eric Labbe Name: Jason Alligood, P.E. Name: TBDOffice: 863-291-5600 Office: 863-646-1402 Office: xxx-xxx-xxxx

Milestones planned for next month:

The Design Builder to finish designing the structural components of the

project and submit for permitting with the Building Division.

Communication Activities:

[email protected] [email protected]

Milestones accomplished this month

The Design/Build contract was approved by the CC on 1/14/2019.

The Notice to Proceed with the design work was issued and the Design

Builder is progressing with his design work.

Funding AmountFunding Percentage

FundingFunding Source (s)

0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%

LAKE HOWARD DOCK / HERITAGE PARK PIER FUNDING City Budget

CDBG

[Source 3]

[ Source 4]

19 of 46

Page 22: CAPITAL IMPROVEMENT PROJECT UPDATE...CAPITAL IMPROVEMENT PROJECT UPDATE The information contained within this report is intended to provide a summary of large scale capital projects

Commence Complete Duration (days)

000

1/25/2018 8/23/2018 2100

8/23/2018 9/20/2018 283/1/2019 6/29/2019 1206/29/2019 6/29/2019 0

TOTAL Master Plan Design Construction CEI $ 380,000.00 $ - $ 7,900.00 $ 372,100.00 $ -

$ 7,682.87 $ - $ 7,682.87 $ - $ -

CO # Date Amount

Timeline & Budget

ConstructionContract Completion Date

Budget

Construction BidIn-house construction

Phase

Grant AwardPD&E / Planning

Expended to Date

CHANGE ORDERS ISSUEDGeneral Detail

Design BidDesign

210

28 120

Feb-18 May-18 Aug-18 Nov-18 Mar-19 Jun-19

Grant AwardPD&E / Planning

Design BidDesign

In-house constructionConstruction Bid

Construction

LAKE HOWARD DOCK / HERITAGE PARK PIER TIMELINE

Duration (days) Current Status Contract Completion Date

0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%

TOTAL

CEI

Construction

Design

Master Plan

LAKE HOWARD DOCK / HERITAGE PARK PIER BUDGET & EXPENSES

Expended to Date Remaining Budget

20 of 46

Page 23: CAPITAL IMPROVEMENT PROJECT UPDATE...CAPITAL IMPROVEMENT PROJECT UPDATE The information contained within this report is intended to provide a summary of large scale capital projects

Project Name:

Updated 1-Mar-19

email address

City Budget [Source 2] [Source 3] [ Source 4] $ 630,000 $ - $ - $ -

98% 0% 0% 0%Funding AmountFunding Percentage

FundingFunding Source (s)

[email protected] email address

Milestones accomplished this month

RFQ-18-52 Design Build Services Closed January 3, 2019

PSC ranked proposals and submitted to City Manager January 29, 2019

Recommendation of Intent to Award Posted January 31, 2019

Milestones planned for next month:

City Commission consideration of City Manager's recommendation

to begin negotiations with highest ranked Design Build Team

at their March 25, 2019 Regular Commission Meeting.

Communication Activities:

Name: Travis Edwards Name: TBD Name: TBDOffice: 863-291-5656 Office: xxx-xxx-xxxx Office: xxx-xxx-xxxx

City Project Manager Engineer of Record Contractor

Project Status ReportCurrent Phase:

Design-BidPercent of Phase:

100%SKATE PARK

Project Description:The project involves the construction of a permanent skateboarding venue incorporating bowls, surface mount obstacles, street course, and/or snake run, along with the necessary support amenities. The project is anticipated to be 1 acre in size with a skate-able area of approximately 20,000 - 25,000 sf. Total estimated construction cost is $630K.

Project Location:MLK Park - West Side of Lake Silver

Contact Information

0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%

SKATE PARK FUNDING City Budget

[Source 2]

[Source 3]

[ Source 4]

21 of 46

Page 24: CAPITAL IMPROVEMENT PROJECT UPDATE...CAPITAL IMPROVEMENT PROJECT UPDATE The information contained within this report is intended to provide a summary of large scale capital projects

Commence Complete Duration (days)

08/26/2016 2/28/2018 551

11/19/2018 1/3/2019 454/11/2019 8/11/2019 122

00

12/15/2019 5/15/2020 1525/15/2020 5/15/2020 0

TOTAL Master Plan Design Construction CEI $ 645,000.00 $ 15,000.00 $ 630,000.00 $ -

$ 11,300.00 $ 11,300.00 $ - $ - $ -

CO # Date Amount

Timeline & Budget

Construction BidIn-house construction

Phase

Grant AwardPD&E / Planning

Design BidDesign

ConstructionContract Completion Date

Budget

Expended to Date

CHANGE ORDERS ISSUEDGeneral Detail

45 122

152

Nov-18 Feb-19 Jun-19 Sep-19 Dec-19 Apr-20

Grant AwardPD&E / Planning

Design BidDesign

In-house constructionConstruction Bid

Construction

SKATE PARK TIMELINE

Duration (days) Current Status Contract Completion Date

0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%

TOTAL

CEI

Construction

Design

Master Plan

SKATE PARK BUDGET & EXPENSES

Expended to Date Remaining Budget

22 of 46

Page 25: CAPITAL IMPROVEMENT PROJECT UPDATE...CAPITAL IMPROVEMENT PROJECT UPDATE The information contained within this report is intended to provide a summary of large scale capital projects

Project Name:

Updated 1-Mar-19

City Budget Solid Waste Fund [Source 3] [ Source 4]

$ 4,742,191 $ 238,607 $ - $ - 95% 5% 0% 0%

Funding AmountFunding Percentage

Funding

Funding Source (s)

[email protected] [email protected]

Milestones accomplished this month

Begin Closeout of Project

Punchlist items work by Contractor

[email protected]

Milestones planned for next month:

Final Closeout of Project

Communication Activities:

Name: Travis Edwards Name: Kriss Kaye (Envisors) Name: Mulligan Constructors, Inc.Office: 863-291-5656 Office: 863-888-0270 Office: 407-654-6523

City Project Manager Engineer of Record Contractor

Project Status ReportCurrent Phase:

Close OutPercent of Phase:

90%LAKE MAUDE RECREATION PARK

Project Description:The development of approximately 26 acres of city owned land to help address deficiencies in youth athletic venues. Phase I of the project includes a stand-alone football multipurpose field with concessions, restrooms, and spectator areas, two dual purpose fields, playground, group picnic shelters, and ancillary support items (parking, ingress/egress, retention, etc.)

Project Location:7th Street, NE / Avenue O, NE

Contact Information

0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%

LAKE MAUDE RECREATION PARK FUNDING City Budget

Solid WasteFund[Source 3]

23 of 46

Page 26: CAPITAL IMPROVEMENT PROJECT UPDATE...CAPITAL IMPROVEMENT PROJECT UPDATE The information contained within this report is intended to provide a summary of large scale capital projects

Commence Complete Duration (days)

000

7/27/2016 6/1/2017 3090

7/3/2017 8/18/2017 462/12/2018 12/8/2018 2993/8/2019 3/8/2019 0

TOTAL Master Plan Design Construction CEI $ 5,003,280.20 $ - $ 352,260.87 $ 4,651,019.33 $ -

$ 4,761,632.43 $ - $ 328,807.87 $ 4,432,824.56 $ -

CO # Date Amount1 -Design 1/3/2017 $10,2501180001-10 Revised 8/27/2018 $200,281.881180001-13 8/27/2018 $38,325.251180001-14 8/27/2018 $1,971.20

CHANGE ORDERS ISSUEDGeneral DetailCultural Resources Survey required by SHPO & FWSBurn Pit Resolution

Grant AwardPD&E / Planning

Design BidDesign

Expended to Date

Pavilion Redesign Fees

ConstructionContract Completion Date

Budget

Additional Burn Pit Material Hauled/Replaced

Timeline & Budget

Construction BidIn-house construction

Phase

309

46 299

Grant AwardPD&E / Planning

Design BidDesign

In-house constructionConstruction Bid

Construction

LAKE MAUDE RECREATION PARK TIMELINE

Duration (days) Current Status Contract Completion Date

0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%

TOTAL

CEI

Construction

Design

Master Plan

LAKE MAUDE RECREATION PARK BUDGET & EXPENSES

Expended to Date Remaining Budget

24 of 46

Page 27: CAPITAL IMPROVEMENT PROJECT UPDATE...CAPITAL IMPROVEMENT PROJECT UPDATE The information contained within this report is intended to provide a summary of large scale capital projects

Project Name:

Updated 1-Mar-19

City Budget CDBG [Source 3] [ Source 4] $ 21,868 $ 254,364 $ - $ -

9% 91% 0% 0%

Project Status ReportCurrent Phase:

Construction PhasePercent of Phase:

100%Sr. Center Renovations & Improvements

Project Description:

Name: Andy Palmer Amin Hanhan L. Cobb Construction

The Sr. Center Renovations & Improvements Project includes ADA renovations to the auditorum restrooms, new ADA access on east side, sidewalk connections around building, shuffleboard court resurfacing and outdoor excercise area.

Project Location:250 South Lake Silver Drive

Contact InformationCity Project Manager Engineer of Record Contractor

Office: 863-291-5656 Office: 863-291-5855 Office: [email protected] [email protected]

Milestones accomplished this month

Cobb Construction worked twice during February to address ashpalt

concerns in the parking lot. Staff is continuing to monitor the raveling

asphalt.

[email protected]

Milestones planned for next month:

A dedication Ceremony will be helded on March 6.

The project will be closed out.

Communication Activities:

Sr. Center renters and patrons are being kept up to date on

parking concerns when corrections to the asphalt paving are

completed.

FundingFunding Source (s)Funding AmountFunding Percentage

0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%

Sr. Center Renovations & Improvements FUNDING City Budget

CDBG

[Source 3]

[ Source 4]

25 of 46

Page 28: CAPITAL IMPROVEMENT PROJECT UPDATE...CAPITAL IMPROVEMENT PROJECT UPDATE The information contained within this report is intended to provide a summary of large scale capital projects

Commence Complete Duration (days)

000

11/1/2017 4/15/2018 1650

5/4/2018 6/7/2018 348/27/2018 12/24/2018 119

12/24/2018 12/24/2018 0

TOTAL Master Plan Design Construction CEI $ 254,364.00 $ - $ - $ 254,364.00 $ -

$ 276,232.00 $ - $ - $ 21,868.00 $ -

CO # Date Amount1 10/2/2018 $02 10/2/2018 $21,868

Construction Bid

Timeline & Budget

Phase

Grant AwardPD&E / Planning

Design BidDesign

In-house construction

ConstructionContract Completion Date

Budget

Expended to Date

CHANGE ORDERS ISSUEDGeneral DetailTime Extension due to lead time of products. Addition of parking lot paving.

165

34 119

Grant AwardPD&E / Planning

Design BidDesign

In-house constructionConstruction Bid

Construction

Sr. Center Renovations & Improvements TIMELINE

Duration (days) Current Status Contract Completion Date

-20% 0% 20% 40% 60% 80% 100%

TOTAL

CEI

Construction

Design

Master Plan

Sr. Center Renovations & Improvements BUDGET & EXPENSES

Expended to Date Remaining Budget

26 of 46

Page 29: CAPITAL IMPROVEMENT PROJECT UPDATE...CAPITAL IMPROVEMENT PROJECT UPDATE The information contained within this report is intended to provide a summary of large scale capital projects

Project Name:Updated 28-Feb-19

email address

City Budget [Source 2] [Source 3] [ Source 4]$2,898,849 $ - $ - $ -

97% 0% 0% 0%

FundingFunding Source (s)Funding AmountFunding Percentage

Milestones planned for next month:

Remaining 50% of curbing from Central South Installed

Second layer of new base to be installed.

Lighting and signs being installed throughout cooridor.

Communication Activities:

Project Status Meeting (Februrary 15 & 28 2019).

Ongoing communication with residents adjacent to project work zone.

Daily coordination between contractor and project team.

[email protected] [email protected]

Milestones accomplished this month

First layer of new base material installed in majority of cooridor.

New curbing installed 50% from Central Ave. South.

Muck discovered in roadway near Ave. G, remediation plan developed

Name: M.J. Carnevale Name: CivilSurv Design Group Name: Watson Civil ConstructionOffice: 863-291-5600 Office: 863-646-4771 Office: 904-297-1800

City Project Manager Engineer of Record Contractor

Project Status ReportCurrent Phase:

Construction PhasePercent of Phase:

60%7th Street Reconstruction & Water Main Replacement Project

Project Description:This project is designed to improve the roadway, drainage, lighting pedestrian utilization within the corridor. Elements include the milling and resurfacing of the existing roadway; installation of new underground stormwater conveyance system; construction of a new 5-foot sidewalk on the west side of 7th and a corresponding 8-foot wide asphalt mixed use path on the east side; and installation of decorative street lights throughout the corridor. In addition in-house Utilities Department personnel and contractor will cooperate to install a new 8-inch water main.

Project Location:7th Street (Northwest & Southwest) from Lake Howard Dr., Norhtwest to Avenue G, Southwest.

Contact Information

0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%

7th Street Reconstruction & Water Main Replacement Project FUNDING City Budget

[Source 2]

[Source 3]

[ Source 4]

27 of 46

Page 30: CAPITAL IMPROVEMENT PROJECT UPDATE...CAPITAL IMPROVEMENT PROJECT UPDATE The information contained within this report is intended to provide a summary of large scale capital projects

Commence Complete Duration (days)

000

9/2/2014 1/29/2018 12451/2/2018 4/2/2018 901/31/2018 3/8/2018 367/9/2018 7/8/2019 3647/8/2019 7/8/2019 0

TOTAL Master Plan Design Construction CEI $ 3,003,921.68 $ - $156,145 $2,741,072 $106,705

$ 1,784,259.00 $ - $156,145 $1,544,382 $83,732

CO # Date Amount7 2/26/2019 $49,083.636 2/26/2019 $20,946.985 2/26/2019 $6,275.974 2/26/2019 $4,555.033 12/19/2018 $10,195.90

Sanitary Sewer ConflictsRemoval of Conflict Trees

Expended to Date

CHANGE ORDERS ISSUEDGeneral DetailRodway Modification Due to Muck DiscoveryStorm Pipe Muck Removal and Replacement Stormwater Modification

ConstructionContract Completion Date

Budget

Construction Bid

Timeline & Budget

Phase

Grant AwardPD&E / Planning

Design BidDesign

In-house construction

12459036

364

Sep-14 Mar-15 Oct-15 Apr-16 Nov-16 May-17 Dec-17 Jul-18 Jan-19

Grant AwardPD&E / Planning

Design BidDesign

In-house constructionConstruction Bid

Construction

7th Street Reconstruction & Water Main Replacement Project TIMELINE

Duration (days) Current Status Contract Completion Date

0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%

TOTAL

CEI

Construction

Design

Master Plan

7th Street Reconstruction & Water Main Replacement Project BUDGET & EXPENSES

Expended to Date Remaining Budget

28 of 46

Page 31: CAPITAL IMPROVEMENT PROJECT UPDATE...CAPITAL IMPROVEMENT PROJECT UPDATE The information contained within this report is intended to provide a summary of large scale capital projects

Project Name:Updated 28-Feb-19

email address

City Budget [Source 2] [Source 3] [ Source 4]$59,000 $ - $ - $ -

100% 0% 0% 0%

FundingFunding Source (s)Funding AmountFunding Percentage

Milestones planned for next month:

Communication Activities:

This trail project was discussed at the MTAC meeting (1/9/2019)

[email protected] [email protected]

Milestones accomplished this month

No status change at this time

Name: Michael Campbell Name: Chastain Skillman, Inc Name: To Be Determined Office: 863-291-5852 Office: 863-646-5710 Office: xxx-xxx-xxxx

City Project Manager Engineer of Record Contractor

Project Status ReportCurrent Phase:

PD& E /PlanningPercent of Phase:

50%Lake Elbert Drive Trail

Project Description:This project is intended to establish a pedestrian trail corridor along Lake Elbert Drive’s lake side Right-of-way clockwise from Central Avenue to SR542. Both ends will connect to the multi-use trail being constructed by FDOT during their SR542 roadway project. Both projects combined would allow pedestrians to circumnavigate Lake Elbert.

Project Location:Lake Elbert Drive Northeast from East Central Avenue to Dundee Road

Contact Information

0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%

Lake Elbert Drive Trail FUNDING City Budget

[Source 2]

[Source 3]

[ Source 4]

29 of 46

Page 32: CAPITAL IMPROVEMENT PROJECT UPDATE...CAPITAL IMPROVEMENT PROJECT UPDATE The information contained within this report is intended to provide a summary of large scale capital projects

Commence Complete Duration (days)

04/4/2016 4/13/2020 1470

000000

TOTAL Master Plan Design Construction CEI $ 59,000.00 $ - $59,000

$ 51,232.47 $ - $51,232 $ - $ -

CO # Date Amount

Expended to Date

CHANGE ORDERS ISSUEDGeneral Detail

ConstructionContract Completion Date

Budget

Construction Bid

Timeline & Budget

Phase

Grant AwardPD&E / Planning

Design BidDesign

In-house construction

1470

Apr-16 Oct-16 May-17 Nov-17 Jun-18 Dec-18 Jul-19 Feb-20

Grant AwardPD&E / Planning

Design BidDesign

In-house constructionConstruction Bid

Construction

Lake Elbert Drive Trail TIMELINE

Duration (days) Current Status Contract Completion Date

0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%

TOTAL

CEI

Construction

Design

Master Plan

Lake Elbert Drive Trail BUDGET & EXPENSES

Expended to Date Remaining Budget

30 of 46

Page 33: CAPITAL IMPROVEMENT PROJECT UPDATE...CAPITAL IMPROVEMENT PROJECT UPDATE The information contained within this report is intended to provide a summary of large scale capital projects

Project Name:Updated 28-Feb-19

email address

City Budget FDEP SWFWMD Polk County $ 428,625 $ 750,000 $ 857,250 $ 428,625.00

17% 30% 35% 17%

FundingFunding Source (s)Funding AmountFunding Percentage

Milestones planned for next month:

Advertise an ITB for construction.

Finalize MOA with Polk County.

Communication Activities:

Spoke with State agencies regarding agreements and ITB

Spoke with Polk County regarding ITB and MOA.

[email protected] [email protected]

Milestones accomplished this month

ITB prepared for Bid

Name: M.J. Carnevale Name: Jeff PeQueen Name: Enter NameOffice: 863-291-5881 Office: 863-667-2345 Office: xxx-xxx-xxxx

City Project Manager Engineer of Record Contractor

Project Status ReportCurrent Phase:

Construction - BidPercent of Phase:

20%LAKE CONINE TREATMENT WETLAND PROJECT

Project Description:This project aims to improve a 301 acre drainage basin of Lake Connine, an impaired waterbody, by reducing nutrient loads. Water quality improvements from this project are expected to also benefit the lakes downstream (Lake Smart). The proposed stormwater improvements will consist of a series of wetland marsh chambers on a 34-acre site to treat run-off from the surrounding urban drainage network before it enters the lake.

Project Location:1275 Lucern Park Road (Parcel on the Southeast side of Lake Conine)

Contact Information

0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%

LAKE CONINE TREATMENT WETLAND PROJECT FUNDING City Budget

FDEP

SWFWMD

Polk County

31 of 46

Page 34: CAPITAL IMPROVEMENT PROJECT UPDATE...CAPITAL IMPROVEMENT PROJECT UPDATE The information contained within this report is intended to provide a summary of large scale capital projects

Commence Complete Duration (days)

1/1/2018 12/31/2019 72900

6/9/2016 3/1/2017 2650

9/1/2018 10/1/2018 3012/1/2018 11/30/2019 364

12/31/2019 12/31/2019 0

TOTAL Master Plan Design Construction CEI $ 2,478,750.00 $ - $ - $ 2,478,750.00 $ -

$ - $ - $ - $ - $ -

CO # Date Amount

Expended to Date

CHANGE ORDERS ISSUEDGeneral Detail

ConstructionContract Completion Date

Budget

Construction Bid

Timeline & Budget

Phase

Grant AwardPD&E / Planning

Design BidDesign

In-house construction

729

265

30364

Jun-16 Dec-16 Jul-17 Jan-18 Aug-18 Mar-19 Sep-19

Grant AwardPD&E / Planning

Design BidDesign

In-house constructionConstruction Bid

Construction

LAKE CONINE TREATMENT WETLAND PROJECT TIMELINE

Duration (days) Current Status Contract Completion Date

0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%

TOTAL

CEI

Construction

Design

Master Plan

LAKE CONINE TREATMENT WETLAND PROJECT BUDGET & EXPENSES

Expended to Date Remaining Budget

32 of 46

Page 35: CAPITAL IMPROVEMENT PROJECT UPDATE...CAPITAL IMPROVEMENT PROJECT UPDATE The information contained within this report is intended to provide a summary of large scale capital projects

Project Name:Updated 28-Feb-19

email address

City Budget SWFWMD [Source 3] [ Source 4] $ 120,000 $ 120,000 $ - $ -

50% 50% 0% 0%

FundingFunding Source (s)Funding AmountFunding Percentage

Milestones planned for next month:

Revise project timeline. (note old tmeline below)

Prepare agreements for commission approval.

Communication Activities:

Discussion with SWFWMD about strategy and revising agreements

[email protected] [email protected]

Milestones accomplished this month

Revised grant agreement received from SWFWMD.

Name: M.J. Carnevale Name: Blaine Carter Name: Enter NameOffice: 863-291-5881 Office: 863-294-6965 Office: xxx-xxx-xxxx

City Project Manager Engineer of Record Contractor

Project Status ReportCurrent Phase:

Design PhasePercent of Phase:

75%WINTER HAVEN CORE RAINGARDEN PROJECT

Project Description:A grant from the Southwest Florida Water Management District was received for the construction of raingardens and stormwater percolation projects often referred to as Low Impact Developments (LID’s) in and around the Winter Haven core area. The project is intended to store and treat stormwater consistent with the Sustainable Water Resource Management Plan and the Chain of Lakes Water Quality Management Plan. These projects create social, economic, and ecologic benefits helping to improve both drainage and the health of the lakes.

Project Location:Various

Contact Information

0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%

WINTER HAVEN CORE RAINGARDEN PROJECT FUNDING City Budget

SWFWMD

[Source 3]

[ Source 4]

33 of 46

Page 36: CAPITAL IMPROVEMENT PROJECT UPDATE...CAPITAL IMPROVEMENT PROJECT UPDATE The information contained within this report is intended to provide a summary of large scale capital projects

Commence Complete Duration (days)

10/23/2015 12/31/2017 8003/3/2016 9/1/2016 182

011/1/2016 11/1/2017 3651/1/2015 12/15/2018 1444

00

12/15/2018 12/15/2018 0

TOTAL Master Plan Design Construction CEI $ 240,000.00 $ - $ 20,000.00 $ 220,000.00 $ -

$ 12,970.00 $ - $ 2,900.00 $ 10,070.00 $ -

CO # Date Amount

Expended to Date

CHANGE ORDERS ISSUEDGeneral Detail

ConstructionContract Completion Date

Budget

Construction Bid

Timeline & Budget

Phase

Grant AwardPD&E / Planning

Design BidDesign

In-house construction

800182

3651444

Oct-15 May-16 Nov-16 Jun-17 Dec-17 Jul-18 Feb-19 Aug-19

Grant AwardPD&E / Planning

Design BidDesign

In-house constructionConstruction Bid

Construction

WINTER HAVEN CORE RAINGARDEN PROJECT TIMELINE

Duration (days) Current Status Contract Completion Date

0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%

TOTAL

CEI

Construction

Design

Master Plan

WINTER HAVEN CORE RAINGARDEN PROJECT BUDGET & EXPENSES

Expended to Date Remaining Budget

34 of 46

Page 37: CAPITAL IMPROVEMENT PROJECT UPDATE...CAPITAL IMPROVEMENT PROJECT UPDATE The information contained within this report is intended to provide a summary of large scale capital projects

Project Name:Updated 28-Feb-19

email address

City Budget FL Legislature [Source 3] [ Source 4] $ - $ 160,000 $ - $ -

0% 100% 0% 0%

FundingFunding Source (s)Funding AmountFunding Percentage

Milestones planned for next month:

Bid prices were well above original estimates and staff is working with

design team, bidder, and funding partner to develop a strategy.

Communication Activities:

Conversations with FDEP and SWFWMD about strategy.

[email protected] [email protected]

Milestones accomplished this month

Name: M.J. Carnevale Name: Blaine Carter Name: Enter NameOffice: 863-291-5881 Office: 863-294-6965 Office: xxx-xxx-xxxx

City Project Manager Engineer of Record Contractor

Project Status ReportCurrent Phase:

Construction - BidPercent of Phase:

90%WINTER HAVEN AQUIFER RECHARGE PROJECT

Project Description:Legislative appropriations were received in Florida fiscal year 2015 and 2016 for the construction of raingardens and stormwater percolation projects often referred to as Low Impact Developments (LID’s) in and around the Winter Haven core area. The project is intended to store and treat Stormwater consistent with the Sustainable Water Resource Management Plan and the Chain of Lakes Water Quality Management Plan. These projects create social, economic, and ecologic benefits helping to improve both drainage and the health of the lakes.

Project Location:Various

Contact Information

0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%

WINTER HAVEN AQUIFER RECHARGE PROJECT FUNDING City Budget

FL Legislature

[Source 3]

[ Source 4]

35 of 46

Page 38: CAPITAL IMPROVEMENT PROJECT UPDATE...CAPITAL IMPROVEMENT PROJECT UPDATE The information contained within this report is intended to provide a summary of large scale capital projects

Commence Complete Duration (days)

11/25/2014 2/8/2016 4401/1/2013 3/1/2014 424

03/26/2016 4/5/2017 375

06/26/2017 8/17/2017 52

08/31/2018 8/31/2018 0

TOTAL Master Plan Design Construction CEI $ 160,000.00 $ - $ 10,000.00 $ 150,000.00 $ -

$ 7,750.00 $ - $ 7,750.00 $ - $ -

CO # Date Amount

Expended to Date

CHANGE ORDERS ISSUEDGeneral Detail

ConstructionContract Completion Date

Budget

Construction Bid

Timeline & Budget

Phase

Grant AwardPD&E / Planning

Design BidDesign

In-house construction

440

375

52

Nov-14 Jun-15 Dec-15 Jul-16 Feb-17 Aug-17 Mar-18 Sep-18 Apr-19

Grant AwardPD&E / Planning

Design BidDesign

In-house constructionConstruction Bid

Construction

WINTER HAVEN AQUIFER RECHARGE PROJECT TIMELINE

Duration (days) Current Status Contract Completion Date

0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%

TOTAL

CEI

Construction

Design

Master Plan

WINTER HAVEN AQUIFER RECHARGE PROJECT BUDGET & EXPENSES

Expended to Date Remaining Budget

36 of 46

Page 39: CAPITAL IMPROVEMENT PROJECT UPDATE...CAPITAL IMPROVEMENT PROJECT UPDATE The information contained within this report is intended to provide a summary of large scale capital projects

Project Name:

Updated 1-Mar-19

email address

City Budget Benefactor [Source 3] [ Source 4]

$ - $ 1,104,138 $ - $ -

0% 100% 0% 0%

City Project Manager Engineer of Record Contractor

Sean Byers Gary Nadeau, PE NA

863-298-7932 941-379-7600 NA

[email protected] [email protected]

Milestones accomplished this

month

Awaiting FDOT comments on 60% design plans

Project Status ReportCurrent Phase:

Design Phase

Percent of Phase:

70%

South Lake Silver Drive

Project Description:

This project will convert an existing street with two 20-foot travel lanes into a corridor with two 10 to 11-foot

travel lanes, on-street parking, upgraded sidewalks and crosswalks, a multi-use trail, landscaping, traffic

calming features, re-alignment of the South Lake Silver Drive/Third Street, NW intersection, and minor

drainage improvements.

Project Location:

Contact Information

South Lake Silver Drive extending between First Street, North and Fifth Street, NW

Funding

Funding Source (s)

Funding Amount

Funding Percentage

Milestones planned for next

month:

Response to FDOT 60% Plans and preparation of 90% design plans

Communication Activities:

FDOT quarterly progress meeting on February 20, 2019

0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%

South Lake Silver Drive FUNDING City Budget

Benefactor

[Source 3]

[ Source 4]

37 of 46

Page 40: CAPITAL IMPROVEMENT PROJECT UPDATE...CAPITAL IMPROVEMENT PROJECT UPDATE The information contained within this report is intended to provide a summary of large scale capital projects

Commence Complete Duration (days)

7/1/2016 7/1/2016 0

0

12/29/2016 7/9/2018 557

8/13/2018 4/30/2019 260

0

0

0

5/31/2019 5/31/2019 0

TOTAL Master Plan Design Construction CEI

$ 1,104,138.00 $ - $ 126,000.00 $ 978,138.00 $ -

$ 96,454.00 $ - $ 96,454.00 $ - $ -

CO # Date Amount

Timeline & Budget

Construction Bid

Construction

Contract Completion Date

Budget

Phase

Grant Award

PD&E / Planning

Design Bid

Design

In-house construction

CHANGE ORDERS ISSUED

General Detail

Expended to Date

557

260

Jun-17 Sep-17 Jan-18 Apr-18 Jul-18 Nov-18 Feb-19 May-19

Grant Award

PD&E / Planning

Design Bid

Design

In-house construction

Construction Bid

South Lake Silver Drive TIMELINE

Duration (days) Current Status Contract Completion Date Grant Award

0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%

TOTAL

CEI

Construction

Design

Master Plan

ENTER PROJECT NAME (ALL CAPS) BUDGET & EXPENSES

Expended to Date Remaining Budget

38 of 46

Page 41: CAPITAL IMPROVEMENT PROJECT UPDATE...CAPITAL IMPROVEMENT PROJECT UPDATE The information contained within this report is intended to provide a summary of large scale capital projects

Project Name:Updated 4-Mar-19

[email protected]

City Budget [Source 2] [Source 3] [ Source 4] $ 509,586 $ - $ - $ -

100% 0% 0% 0%

Milestones planned for next month:

Contractor will be running conduit for the new electrical components.

Communication Activities:

Electricians will start running conduit the first week in March.

FundingFunding Source (s)Funding AmountFunding Percentage

[email protected] [email protected]

Milestones accomplished this month

Staff and engineers reviewed submittals.

Some parts ordered and some received.

Jeff Crowley Censtate ContractorsOffice: 863-291-5766 Office: 941-358-1440 Office: 863-324-3882

City Project Manager Engineer of Record Contractor

Project Status ReportCurrent Phase:

Construction PhasePercent of Phase:

10%AUTOMATED AERATION CONTROL SYSTEM

Project Description:This project will improve plant efficiency by automatically providing the correct amount of dissolved oxygen to the microorganisms in the wastewater treatment process. New blower motors with VFD's and a computer control system will be the major components of this project.

Project Location:Wastewater Treatment Plant #2 Motor Pool Road

Contact Information

Terry Carver

0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%

AUTOMATED AERATION CONTROL SYSTEM FUNDING City Budget

[Source 2]

[Source 3]

[ Source 4]

39 of 46

Page 42: CAPITAL IMPROVEMENT PROJECT UPDATE...CAPITAL IMPROVEMENT PROJECT UPDATE The information contained within this report is intended to provide a summary of large scale capital projects

Commence Complete Duration (days)

00000

3/15/2018 5/29/2018 757/24/2018 7/1/2019 3427/1/2019 7/1/2019 0

TOTAL Master Plan Design Construction CEI $ 509,586.00 $ - $ - $ 450,000.00 $ 59,586.00

$ 12,724.79 $ - $ - $ - $ 12,724.79

CO # Date Amount1 1/9/2019 $0.00

CHANGE ORDERS ISSUEDGeneral DetailAdded 137 days for completion due to electrical panelsnot arriving until middle of March.

Expended to Date

Construction BidConstruction

Contract Completion Date

Budget

Phase

Grant AwardPD&E / Planning

Design BidDesign

In-house construction

Timeline & Budget

75342

Mar-18 May-18 Jun-18 Aug-18 Oct-18 Nov-18 Jan-19

Grant AwardPD&E / Planning

Design BidDesign

In-house constructionConstruction Bid

Construction

AUTOMATED AERATION CONTROL SYSTEM TIMELINE

Duration (days) Current Status Contract Completion Date

0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%

TOTAL

CEI

Construction

Design

Master Plan

AUTOMATED AERATION CONTROL SYSTEM BUDGET & EXPENSES

Expended to Date Remaining Budget

40 of 46

Page 43: CAPITAL IMPROVEMENT PROJECT UPDATE...CAPITAL IMPROVEMENT PROJECT UPDATE The information contained within this report is intended to provide a summary of large scale capital projects

Project Name:Updated 4-Mar-19

jcourtney@vogelbl

City Budget [Source 2] [Source 3] [ Source 4] $ 2,646,488 $ - $ - $ -

100% 0% 0% 0%

Project Status ReportCurrent Phase:

Construction PhasePercent of Phase:

90%

Office: (941) 358-1440 Office: 863-646-5078

Project Description:

Project Location:

Contact InformationCity Project Manager Engineer of Record Contractor

Milestones accomplished this month

[email protected] [email protected]

A punch list was created and the contractor started addressing the

issues. O & M Manuals were submitted. Some revisions are needed.

Milestones planned for next month:

Communication Activities:

Contractor is scheduled to complete the rest of the punch list items.Finalize O & M Manuals.

Finalize Record Drawings.

Performance testing was completed February 1, 2019.

The final punch list was created February 15, 2019.

FundingFunding Source (s)Funding AmountFunding Percentage

NEW SAND FILTER PLANT 3 CONSTRUCTION

This project is to add a 3rd sand filter to the treatment system at WWTP #3. This additional sand filter will allow the plant to better handle peak flows and allow one unit to be taken off line for maintenance and repairs.

Wastewater Treatment Plant 3 Pollard Road

Terry Carver Jeff Crowley Vogel Office: 863-291-5766

0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%

NEW SAND FILTER PLANT 3 CONSTRUCTION FUNDING City Budget

[Source 2]

[Source 3]

[ Source 4]

41 of 46

Page 44: CAPITAL IMPROVEMENT PROJECT UPDATE...CAPITAL IMPROVEMENT PROJECT UPDATE The information contained within this report is intended to provide a summary of large scale capital projects

Commence Complete Duration (days)

000

3/24/2014 3/30/2015 3710

10/14/2016 11/18/2016 353/17/2017 4/4/2019 7484/4/2019 4/4/2019 0

TOTAL Master Plan Design Construction CEI $ 2,646,488.00 $ - $ 121,270.00 $ 2,379,385.00 $ 145,833.00

$ 1,835,500.75 $ - $ 121,270.00 $ 1,618,477.99 $ 95,752.76

CO # Date Amount1 1/29/2018 $31,611.082 4/21/2018 $62,217.113 5/15/2018 $0.004 7/3/2018 $364,182.345 & 6(Draft) 1/7/19 & 3/4/19 $0.00

Phase

Timeline & Budget

Budget

Expended to Date

Grant AwardPD&E / Planning

Design BidDesign

In-house constructionConstruction Bid

Additional 90 days for training, punch list & record drawings.

CHANGE ORDERS ISSUEDGeneral DetailRelocate power & controls, SCADA upgrade, various demos,etcAdditional expense for pvc line ext., well point rental fees, etcAdditional 34 days for delays due to conduit relocationCost for time and materials to repair filters #2 and #3.

ConstructionContract Completion Date

371

35748

Mar-14 Jan-15 Nov-15 Sep-16 Jul-17 May-18 Feb-19

Grant AwardPD&E / Planning

Design BidDesign

In-house constructionConstruction Bid

Construction

NEW SAND FILTER PLANT 3 CONSTRUCTION TIMELINE

Duration (days) Current Status Contract Completion Date

0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%

TOTAL

CEI

Construction

Design

Master Plan

POLLARD ROAD WATER PLANT BUDGET & EXPENSES

Expended to Date Remaining Budget

42 of 46

Page 45: CAPITAL IMPROVEMENT PROJECT UPDATE...CAPITAL IMPROVEMENT PROJECT UPDATE The information contained within this report is intended to provide a summary of large scale capital projects

Project Name:Updated 4-Mar-19

City Budget [Source 2] [Source 3] [ Source 4] $ 3,400,621 $ - $ - $ -

100% 0% 0% 0%

City Project Manager Engineer of Record Contractor

Project Status ReportCurrent Phase:

Construction PhasePercent of Phase:

10%SR 542 UTILITY ADJUSTMENTS

Project Description:Relocation and installation of water, sewer and reuse mains along SR 542 (Dundee Rd) from 1st street to Buckeye Loop Rd. This project is a result of the roadway improvement project initiated by FDOT and will be constructed under a FDOT contract.

Project Location:SR 542 from 1st Street to Buckeye Loop Rd

Contact Information

Mike Britt Chad Setzer - Atkins Watkins Civil-Matt Schumacher863-291-5853 407-806-4120 [email protected] [email protected]

Milestones accomplished this month

Open cut at LS 147 to replace MH and pipe leading into LS. RFI questions

answered. 3 progress meeting attended. Pressure tested FM from 6th St

to Ave A. City saved $110,588 removing jack and bores.

[email protected]

Milestones planned for next month:

Reroute WM on East end to adjust for unlocated utilities. Open cutcrossings. Meet w/ TECO regarding pole location at LS.

Communication Activities:

RFI questions. Weekly progress meeting.

FundingFunding Source (s)Funding AmountFunding Percentage

0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%

SR 542 UTILITY ADJUSTMENTS FUNDING City Budget

[Source 2]

[Source 3]

[ Source 4]

43 of 46

Page 46: CAPITAL IMPROVEMENT PROJECT UPDATE...CAPITAL IMPROVEMENT PROJECT UPDATE The information contained within this report is intended to provide a summary of large scale capital projects

Commence Complete Duration (days)

000

3/26/2013 5/31/2018 189200

10/30/2018 5/26/2020 5745/26/2020 5/26/2020 0

TOTAL Master Plan Design Construction CEI $ 3,400,621.44 $ - $ 139,103.00 $ 3,102,197.44 $ 159,321.00

$ 3,258,453.04 $ - $ 133,625.25 $ 3,102,197.44 $ 22,630.35

CO # Date Amount

Timeline & Budget

Construction BidConstruction

Contract Completion Date

Phase

Grant AwardPD&E / Planning

Design BidDesign

In-house construction

Budget

CHANGE ORDERS ISSUEDGeneral Detail

Expended to Date

1892

574

Mar-13 Nov-13 Jul-14 Apr-15 Dec-15 Aug-16 Apr-17 Dec-17 Sep-18 May-19 Jan-20

Grant AwardPD&E / Planning

Design BidDesign

In-house constructionConstruction Bid

Construction

SR 542 UTILITY ADJUSTMENTS TIMELINE

Duration (days) Current Status Contract Completion Date

0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%

TOTAL

CEI

Construction

Design

Master Plan

SR 542 UTILITY ADJUSTMENTS BUDGET & EXPENSES

Expended to Date Remaining Budget

44 of 46

Page 47: CAPITAL IMPROVEMENT PROJECT UPDATE...CAPITAL IMPROVEMENT PROJECT UPDATE The information contained within this report is intended to provide a summary of large scale capital projects

Project Name:Updated 4-Mar-19

jeff.watson@r2tinc.

City Budget SRF [Source 3] [ Source 4] $ 143,185 $ 1,650,000 $ - $ -

8% 89% 0% 0%

City Project Manager Engineer of Record Contractor

Project Status ReportCurrent Phase:

Construction PhasePercent of Phase:

90%MECHANICAL BAR SCREEN PLANT 3

Project Description:This project involves constructing a third bar screen to handle the debris that comes from the collection system and to allow maintenance of the other screens.

Project Location:4400 Pollard Road - WWTP # 3

Contact Information

Terry Carver Chastian Skillman R2T, IncOffice:863-291-5766 Office: 863-646-1402 Office: [email protected] [email protected]

Milestones accomplished this month

Completed punch list items.

O & M Manuals approved.

Milestones planned for next month:

Install LED lights.

Complete SCADA integration.

Communication Activities:

A progress meeting was held February 1, 2019.

Next progress meeting is scheduled for March 15, 2019.

FundingFunding Source (s)Funding AmountFunding Percentage

0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%

MECHANICAL BAR SCREEN PLANT 3 FUNDING City Budget

SRF

[Source 3]

[ Source 4]

45 of 46

Page 48: CAPITAL IMPROVEMENT PROJECT UPDATE...CAPITAL IMPROVEMENT PROJECT UPDATE The information contained within this report is intended to provide a summary of large scale capital projects

Commence Complete Duration (days)

000

8/10/2015 6/22/2017 6820

10/13/2017 12/22/2017 704/4/2018 4/4/2019 3654/4/2019 4/4/2019 0

TOTAL Master Plan Design Construction CEI $ 1,846,420.00 $ - $ 122,185.00 $ 1,650,000.00 $ 74,235.00

$ 959,359.70 $ - $ 82,638.47 $ 826,216.09 $ 50,505.14

CO # Date Amount1 1/10/2019 -223,120.59

Timeline & Budget

Construction BidConstruction

Contract Completion Date

Phase

Grant AwardPD&E / Planning

Design BidDesign

In-house construction

Budget

CHANGE ORDERS ISSUEDGeneral DetailCity purchase a bar screen and minor modifications.

Expended to Date

682

70365

Aug-15 Dec-15 Apr-16 Aug-16 Dec-16 Apr-17 Jul-17 Nov-17 Mar-18 Jul-18 Nov-18 Mar-19

Grant AwardPD&E / Planning

Design BidDesign

In-house constructionConstruction Bid

Construction

MECHANICAL BAR SCREEN PLANT 3 TIMELINE

Duration (days) Current Status Contract Completion Date

0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%

TOTAL

CEI

Construction

Design

Master Plan

MECHANICAL BAR SCREEN PLANT 3 BUDGET & EXPENSES

Expended to Date Remaining Budget

46 of 46