CAPITAL EXPENDITURE PROPOSAL OF SBU-T

Upload: others

Post on 29-Mar-2022

1 views

Category:

Documents


0 download

TRANSCRIPT

Slide 1SBU-T
Para 5.3.5 of the National Electricity Policy notified by the Ministry of Power, Government of India,
under Section 3 of the Act vide Resolution No.23/40/2004-R&R (Vol.II) dated 12.2.2005 provides as
under:
“5.3.5 To facilitate orderly growth and development of the power sector and
also for secure and reliable operation of the grid, adequate margins in
transmission system should be created. The transmission capacity would be
planned and built to cater to both the redundancy levels and margins keeping in
view international standards and practices. A well planned and strong
transmission system will ensure not only optimal utilization of transmission
capacities but also of generation facilities and would facilitate achieving
ultimate objective of cost effective delivery of power”.
• The growth of transmission system must be ahead of generation both
in time and capacity to avoid congestion or bottling up of power.
• Efficient operation of transmission system in terms of providing
reliability, avoidance of disturbance, maintaining voltage level and
reducing transmission losses requires continuous strengthening of
transmission system.
Transmission Planning
• Provide 24 x 7 power supply to all consumers with n-1 and n-1-1 and
n-2 reliability.
• With Open Access in transmission, the role of transmission has
changed from a mere infrastructure to an enabler in operation of a
competitive power market.
Transmission Planning Objectives
The power requirement of the state has been increasing rapidly in the
past decades.
The maximum demand has crossed 4000 MW in 2016 (27-April-
2016).
The demand is expected to rise to 4,900MW within the next five
years
Kerala 23,929 25,008 25,991 27,061 28,226 29,481 30,802 41,062
SUR Model Baseline
PAM Baseline Scenario
Kerala 25,106 26,262 27,681 29,247 30,951 32,802 34,759 50,222
comprehensive transmission development scheme named TRANSGRID 2.0has been developed
to relieve the system of its present constraints, building sufficient import capability for the
future, facilitate complete power evacuation from generating stations within the state, to
reduce transmission losses to the possible maximum while fully meeting power demand of the
state. The project requires a total investment plan of about Rs. 6,375Cr within 5 years
SBU – Transmission Present statistics (SBU-T handles 66KV and above)
Transmission System statistics
2019)
5 33KV lines Ckt-km 2006.54 2082.69
6 400 kV Substations Nos 5* + 1 5* + 1
7 220 kV Substations Nos 22 22
8 110 kV Substations Nos 157 162
9 66KV Substations Nos 74 70
10 33 KV Substations Nos 153 158
11 Total transmission capacity (MVA) MVA 20820.90 20933.40
*PGCIL owned **Madakkathara-Malaparambu 400KV line addition
Capital Investment Plan
Provisions in KSERC (Terms and Conditions for determination of Tariff) Regulations, 2018
“54. Capital investment plan. – (1) The transmission business/licensee shall along the petition for Aggregate Revenue Requirements for the Control Period submit to the Commission for its approval, a detailed capital investment plan, financing plan and physical targets. Such investments may be undertaken for strengthening and augmenting the intra-State transmission system for meeting the requirement of power evacuation, load growth, reduction in transmission losses, improvement in quality of supply, reliability, metering, etc., for the Control Period, in accordance with the ‘Guidelines for In-principle Clearance of Capital Investment’ specified at Annexure-IV.”
KSEBL submitted the CIP along with MYT ARR petition on 31-10-2018.
As per Regulation 10(2) of the KSERC(Terms and Conditions for determination of Tariff)
Regulations, 2018 issued by Hon’ble Commission, every generating business/company or
transmission business/licensee or distribution business/licensee or State Load Despatch Centre
shall file, on or before the Thirtieth day of November 2019, the Mid-term Performance Review
(MPR) which shall comprise the truing up for the financial year upto 2018-19 and midyear
performance review for the year 2019-20 and the revised forecast for the year 2020-21 and
2021-22 on account of unexpected variations if any on controllable and uncontrollable
parameters.
Accordingly the mid year performance review for the year 2019-20 and the revised forecast
for the years 2020-21 and 2021-22 of SBU-T submitted on
Capital Investment Plan
Reliability & Quality New technology
Capacity Utilization Dedicated teams
2021-22
SBU-T has evolved a multi year capital expenditure plan which is
grouped as follows:
Normal capital works (above 10Cr) proposed in the control period
2018-19 to 2021-22
Sl.No Work 2018-19 2019-20 2020-21 2021-22 Total
SBU-T
works
804.12 568.73 196.28 254.26 1823.39
2 New Capital Works above 10Cr 0 662.59 421.83 41.65 1126.07
3 Transgrid Works 0 362.57 2073.84 260.96 2697.37
Total 804.12 1593.89 2691.95 556.89 5646.85
SLDC
works
5 New projects 12 53 12 212.45 289.45
Total 26.72 60.14 12 212.45 311.31
Total CAPEX for SBU-T & SLDC 830.84 1654.03 2703.95 769.34 5958.16
Transgrid 2.0 Projects
DPR Revised DPR Actual/Expected
3 Kothamangalam & Chithirapuram 398.86 364.47 2020-21 2020-21
4 Kottayam, Thuravur & Ettumanoor 541.67 541.67 2020-21 2020-21
5 Chalakudy 71.42 79.58 2020-21 2020-21
6 Kunnamkulam 130.3 134.41 2020-21 2020-21
7 Manjeri 51.1 38.87 2020-21 2019-20
8 Thalasseri 157.03 170.47 2020-21 2020-21
9 Kunnamangalam 91.9 77.25 2020-21 2020-21
10 Eranad 552 595.77 2020-21 2020-21
11 NRHTLS 79.57 69.3 2020-21 2020-21
12 Kolathunadu 260.96 287.35 2021-22 2021-22
13 Sabari Package 248 248 2021-22 2021-22
14 Vengallur GIS & TLSP Phase II 204.18 204.18 2021-22 2021-22
15 Vizhinjam 220/110 kV GIS sub 71 71 2021-22 2021-22
Aluva Package
Aluva is a major load centre now fed by Kalamassery at 110kV level and partly supported by 66kV line from Pallivasal. Considering the load growth, the present feeding will not be sufficient.
This line will provide redundancy as well as enable KSEBL to import more power from the interstate PGCIL substation.
The estimated cost of the project is Rs.168 Cr and is expected to be commissioned in 2019-20.
Relieves loading of Kalamassery S/s by feeding downstream stations and provides backup.
Power evacuation from Pallivasal Extension Scheme (60 MW) HEP
Necessity Benefits of Package
commission has been submitted.
Date of COD: 2019-20
Construction of
(a) 11.10Km 220KV DC line from 440kV Cochin East (Pallikara) PGCL substation to Aluva
(b) Construction of 220 KV GIS at Aluva
Project Components
Kaloor Package
by Kalamassery – Kaloor 110kV double circuit
feeder. With the present load growth, this line will
reach its full capacity by 2018-19.
Increase the reliability of supply
Enhances the flexibility in operation and avoids
total black out in case of feeder failures.
System loss will be reduced by 10.71 MW
(energy savings of 52 MU) per year.
Necessity Benefits of Package
Date of COD: 2019-20
Project Components
• 220kV GIS is at the existing Kaloor substation premises with a capacity of 360MVA.
• 4.5 kM of 220/110 kV MCMV line along the existing RoW of 110 kV Brahmapuram– Kalamassery 1 & 2
feeders up to Thuthiyur and through UG cable from Thuthiyoor to Kaloor.
Kothamangalam and Chithirapuram Package
This station is a vital transmission nodal point catering the
power requirement of load centers like Kothamangalam,
Perumbavoor, Aluva, Muvattupuzha, Koothattukulam etc. The
station also serves as the backup power supply to Idamalayar
power house in an emergency situation through a 66kV SC
feeder. Station Minimum voltage level breaches to 56kV.
To provide secure and reliable transmission system for
evacuating 500 MW from under construction/Planned
projects in Idukki.
Date of COD: 2020-21
(b) 220kV Sub station at Chithirapuram
(c) Upgradation of 66kV Pallivasal Aluva line to 220/110kV MCMV line
(d) Construction of 220/110kV MCMV line from Karukadom to Kothamangalam
Kottayam Upgradation Package
import power from PGCIL 400kV Grid
To strengthen the Power evacuation from the
existing network of Kottayam & Alappuzha
region.
and Thravur SS
Strengthening of the transmission system in
Kottayam District and the Northern side of
Alappuzha District.
Date of COD 2020-21
• Substations
• 220kV GIS at Ettumanoor,
• 220kV AIS at Thuravur.
• 27.6 km 220/110 KV MCMV line from Kottayam to Thuravoor
• 6.5 km 220/110 KV MCMV line from Kottayam to Ettumanoor
• 3.8 km 220kV double circuit LILO from Pallom-Ambalamugal o to Kottayam Substation
• 4.8 km 110kV DC line in Kuravilangad – Vaikom – Ettumanoor line route
Chalakudy 220kV AIS & North-South Interlink Package (Phase I)
No redundant and dependable back up support to Chalakudy substation, which receives power from Sholayar, Porigalkuthu and Idamalayar HEPS.
The central and southern regions of Thrissur district, including feeding substations, will face black out in the case of major disturbances in the line.
Create back up power to Thrissur district
Evacuating Power from proposed high capacity ISTS
Projects.
connecting the Central and Northern part of Kerala
for uninterrupted transmission of power flow
Necessity Benefits of Package
Revised Project cost is Rs.79.58 Cr Date of COD 2020-21
Project Components
Up gradation of existing 110kV AIS to 220kV AIS at Chalakudy in Thrissur District with station capacity 2x100 MVA
Transformer and 4 x 220 kV feeder bays
Konnakuzhy-Chalakudy 220/110kVline (NSIP Phase 1 Project A) : Upgrading existing Poringal - Chalakudy 110kV DC
Transmission line to 220/110kV MCMV Transmission line in Thrissur District (LILO from Madakkathara – Lower periyar)
Kunnamangalam 220kV GIS
Kozhikode and nearby areas now fed from Nallalam 220kV S/S. No backup supply to Kozhikode in case of failure of Nallalam supply. Kunnamangalam will serve as back up source to Kozhikode with 220kV feeding from Areekode Kaniyampetta Line.
Improve reliability and quality of transmission
system and relieves transmission congestion at
Kunnamangalam town & Kozhikode area.
Reduction in transmission losses
nearby areas during shutdown/emergency situation
at 220kV Nallom
Revised Project cost is Rs.77.25 Cr Date of COD 2020-21.
Project Components
Upgradation of existing 110kV AIS to 220kV GIS at Kunnamangalam in Kozhikode District with station capacity
2x100 MVA Transformers and 2 x 220 kV feeder bays
Upgrading portion of existing 110kV Agastyamuzhi - Kunnamkulam DC Transmission line to 220/110kV MCMV
Transmission line istrict (LILO to Areekode - Kaniyampetta)
Manjeri 220kV AIS & Lines
Severe power supply problems in Malappuram district (areas fed from Manjeri, Nilambur, Edakkara & Pookkottumpadam S/s) due to overloading of transmission lines.
No alternatives available in case of failure of SC feeder catering to the above S/s.
Enhance the reliability of the System
Integral development of the transmission system in
the eastern part of the Malappuram District
especially Manjeri, Nilambur and Edakkara areas.
Better load sharing in Madaakkathara - Arekode
DC Feeder
Necessity Benefits of Package
Revised Project cost is Rs. 38.87 Cr Date of COD: 2020-21.
Project Components
• Construction of new 220 kV Air Insulated Substation at Manjeri
• 220kV LILO arrangement to Manjeri substation
Thalasseri 220/110 kV GIS
feeding substation to 110kV Thalasseri
Substation, causes system instability in Thalasseri
regions.
Thalasseri and adjusted areas are rapidly
increasing.
reliability of supply in the Thalasseri regions.
Reduction in transmission losses –Peak load
loss reduction 26.2 MW
have system stability in the region
Necessity Benefits of Package
Revised Project cost is Rs. 170.47 Cr Date of COD 2020-21.
Project Components
• Construction of 220/110kV Gas-Insulated-Substation (GIS).
• Construction / Up gradation of 66kV SC line to 220/110kV DC line using narrow base
MCMV Towers from Mundayad to Thalassery.
220kV GIS Substation, Kunnamkulam & Wadakkanchery - Kunnamkulam
220kV DC line
In case of power disturbances from Madakkathara or any disturbances occurred to the Central costal region line, including Guruvayur, causes black out as there are no redundant and dependable back up supporting lines.
Reduction of transmission congestion and improves power
reliability and stability. Reducess transmission losses.
Evacuation of power between Southern and northern
region.
Malapparamba/Nallalam sub station
The load on 110kV bus at Madakkathara SS released to
great extend.
Necessity Benefits of Package
Revised Project cost is Rs. 134.41 Cr Date of COD 2020-21.
Project Components
• Upgradation of existing 110kV AIS to 220kV GIS at Kunnamkulam in Thrissur District with station capacity 2x100 MVA
Transformers and 2 x 220 kV feeder bays
• Upgrading existing Wadakkanchery - Kunnamkulam 66kV SC Transmission line to 220kV DC Transmission line in Thrissur
District (LILO to Madakkathara - Malapparamba/Nallalam) using HTLS Drake equivalent conductor – Route Length 22.8
km .
Constraints are experienced for importing power to Areacode from Mysore .
Transmission constraints are experienced in down stream network especially in Kannur and Kasaragod district
Severe low voltage profile creates constraints to power transfer.
Provides a robust highway from 400kV from North to South of Kerala facilitating bulk power transfer either way.
Mitigates congestion in the 400kV ISTS Mysore Areacode tie line.
Enables Power evacuation capability power from 2000MW HVDC Station to northern part of Kerala
Peak load reduction by 23.3MW(Energy savings of 112.9 MU)
Necessity Benefits of Package
Revised Project cost is Rs. 595.77 Cr Date of COD 2020-21.
Project Components
PSDF Grant is Rs. 333.93 Cr
NRHTLS
Stranded generation at Kakkayam HEP due to inadequate power evacuation capacity of the existing Kakkayam – Nallalam line.
Enhancing the loading capacity of the lines
without changing the tower or upgrading the
transmission voltage level.
Kozhikode
Date of COD 2020-21.
• Up-grading Nallalam – Chevayur - Westhill – Koyilandy - Mepayur 110kV Single Circuit line in to
Double Circuit line (32km).
PACKAGE
Kasaragode district now fed from thorugh 220kV DC feeder from Kanhirode(Kannur) to Mylatti.
No back up 220kV Source available for Kasaragode district in case of failure of Kanhirode - Mylatti feeder
To import power from Solar power station at Ambalathara ,
b) To provide alternate 220KV corridor between Kannur
and Kasargod Districts and
Kasargod districts.
d) To meet the incident demand and to reduce the system
losses so as to keep the
transmission system reliable and secure at par with the
international standards
from Mylatty to Kanhirode
Necessity Benefits of Package
Revised Project cost is Rs. 239.77 Cr Date of COD:2021-22
Project Components
• Construction of 220 kV double circuit line on 220/110 kV MCMV towers from Kanhirode to
Mundayad.
• Construction of 220kV /110kV Multi circuit Multi voltage (MCMV) line from Mundayad (Kannur District) to Mylatty
(Kasaragod District).
Pathanamthitta, Kozhenchery and Ranni are fast developing thereby increasing the power demand growth exponentially.
Considering the Power demand growth, stability of power supply in Pathanamthitta district and an alternate route for power evacuation for Kakkad belt ,it is highly necessary to construct a 220/110 kV substation at Pathanamthitta
Offers Pathanamthitta a 220kV substation with
connectivity to Sabarigiri-Edamon line and
Edappon substation, satisfying N-1 criteria
Ensure power system stability and full utilisation of
power houses in the Kakkad belt.
Loss reduction of 4MW in the system
Necessity Benefits of Package
Project cost is Rs. 248 Cr Date of COD: 2021-22
Project Components
• Construction / Upgradation of 220/110kV line using narrow base MCMV Towers • Construction of New 220/110KV Gas Insulated Substation at Pathanamthitta • Construction of New 220/110KV Gas Insulated Substation at Kakkad
220kV VIZHINJAM GIS SUBSTATION
demand anticipated due to
development of Vizhinjam area
International seaport.
network satisfying N-1 criteria in this area and there
will be a good relief in the loading of the existing
feeders.
part and the coastal area of Thiruvananthapuram
District.
Necessity Benefits of Package
Project Components
• Upgradation of the existing 66kV, Vizhinjam substation to a 220kV GIS substation
Date of COD: 2021-22
THRISSIVAPERUR LINE STRENGHTNING PACKAGE
The loading pattern in the existing 110/11kV AIS Tirur, having
capacity of 52.5MVA {2x20MVA + 1x12.5MVA} has reached its
safe loading limits and hence either the station capacity need to be
enhanced nor new substation has to be built in to cover up the future
power demand.
existing transformers at Tirur 110kV AIS were 70% and 53%
respectively in the year 2015, which has now increased to 85% and
75% respectively.
The proposed scheme will also mitigate the high loading of the
110kV DC feeder from 220kV Substation Areekode to Keezhissery.
Under the non-availability of this scheme any failure / fault in the
above 110kV corridor or at 220kV Substation Areekode can plunge
Malappuram and adjoining areas into black out state.
This project is proposed to build necessary
downstream side infrastructure to evacuate power
from PGCIL HVDC station at Mannuthy
offering a stable, reliable and alternate power
transmission and distribution network in the
Malappuram District
central and southern regions {Aluva-North Paravur-
Kodungallur-Irinjalakuda-Kunnamkulam-Vengallur}
Project cost is Rs. 204.18 Cr Date of COD: 2021-22
• Construction of 110/11kV GIS at Vengallur, Malappuram district • Construction of 42km 220/110kV MCMV transmission line from Kunnamkulam Substation in Thrissur
district to Vengallur • Construction of 220/110kV GIS at Vengallur
110/11kV GIS & 220/110kV GIS, VENGALLUR MALAPPURAM DISTRICT & THRISSIVAPERUR
LINE STRENGHTNING PACKAGE
Normal Capital works proposed (Rs Cr) No. Project
1 Linking between 110kV Kanhangad – Cheruvathuer feeder to 220kV S/s Ambalathara
2 Upgradation of 66kV Palakkad Medical College Substation and line
3 110 kV GIS Project Vennakkara
4 Construction of Palakkad- Malampuzha 110kV Line
5 110kV Substation Pattambi
7 Upgradation of 66kV Substation Ettumanoor to 110kV
8 Upgradation of 66kV Substation, Kuravilangadu and Koothattukulam-Kuravilangadu to 110 kV
9 Upgradation of 66kV Substation Koothattukulam to 110 kV
10 Upgradation of 66KV Kothamangalam- Kotthttukulam Feeder to 110 KV
11 Upgradation of 66kV SC Pala-Ettumanoor feeders to 110kV
12 Upgradation of 66kV Substation Anchal to 110kV and Upgradation of 66kV SC Edamon –Anchal-Ayur line to 110kV DC
13 Up gradation of 66kV Substation, Karunagappally and 66kV SC Sasthamcotta-Karunagapally line to 110kV DC
14 Construction of 110kV Substation, Chithara
15 Interlinking 110kV GIS Substation, Kollam and 110kV Kottiyam Substation
16 110kV GIS substation at Kowdiar, Thiruvananthapuram
17 Upgradation of 66kV Substation Palode to 110kV
18 66kV Substation, Ambalavayal and 66kV DC line from 66kV Kaniyambetta-Sulthanbathery feeder in 110kV Parameters
19 110kV Substation, Chemperi and line
20 Upgradation of Kunnamangalam _ Thamarasserry line to 110kV
Normal Capital works proposed (Rs Cr)
No. Project
22 Upgradation of Mankada S/s to 110kV
23 Upgradation of 66kV Substation, Mankavu to 110kV
24 Upgradation of 110kV SC/DC line to 220/110kV MC MV line from Mylatty s/s to Vidyanagar
25 110kV Substation, Pulikkal
26 110kV Substation, Seethangoli
27 Upgradation of 33 kV Substation Thambalamanna to 110 kV & 110 kV Agasthiamuzhy - Thambalamanna (S/c, UG cable)
28 220KV Substation Kottayi
29 Upgradation of Pudukkad to Kattoor 66kV SC Line to 110kV DC Line
30 Conversion of Ollur Viyyur feeder to 110 kV
31 Upgradation of 66kV Pallom-Ettumanoor feeder and associated substations to 110kV
32 Construction of 110kV substation Vazhoor
33 Upgradation of 66kV Substation Kuttanadu to 110kV
34 Upgradation of 66kV PUNNAPRA-ALAPPUZHA DC Feeder to 110 kV
35 110kV Switching Cum Substation at PANTHALACODE
36 Upgradation of 66 kV TVT No. I & II feeders
37 Renovation and modernisation 110kV GIS Substation, Malappuram
38 LILO on 110kV Edarikode- Tirur to Parappanangadi S/s
39 Construction of 110kV GIS Substation , Vengaloor
40 Construction of new 110kV DC line from Kayamkulam to Karunagapally
The capital expenditure projected for the control period
Sl.No Work 2018-19 2019-20 2020-21 2021-22 Total
SBU-T
1 Ongoing projects plus new small works 804.12 568.73 196.28 254.26 1823.39
2 New Capital Works above 10Cr 0 662.59 421.83 41.65 1126.07
3 Transgrid Works 0 786.60 1097.4 1051 2935
Total 804.12 2017.92 1715.51 1346.91 5884.46
SLDC
4 Ongoing projects plus new small works 14.72 7.14 0 0 21.86
5 New projects 12 53 12 212.45 289.45
Total 26.72 60.14 12 212.45 311.31
Total CAPEX for SBU-T & SLDC 830.84 1654.03 2703.95 769.34 5958.16
CAPEX SBU-T (MORE THAN 10 CR)
CAPEX SBU-T (More than 10 Cr)
Linking between 110kV Kanhangad – Cheruvathuer feeder to 220kV S/s Ambalathara
Project Cost: 36.06 Cr Date of COD: 2019-20
Revised Project Cost: 8.17 Cr Expected Date of COD: 2020-21
Upgradation of 66kV Palakkad Medical College Substation and line
Project Cost: 23.1 Cr Date of COD: 2019-20
Revised Project Cost: Expected Date of COD:
Project will be taken up after commissioning of Vennakkara GIS SS
110 kV GIS Project Vennakkara
Project Cost: 36.6 Cr Date of COD: 2019-20
Revised Project Cost: 44.6 Cr Expected Date of COD: 2020-21
CAPEX SBU-T (More than 10 Cr)
Construction of Palakkad- Malampuzha 110kV Line
Project Cost: 14.38 Cr Date of COD : 2019-20
Revised Project Cost: 14.38 Cr Expected Date of COD: 2020-21
110kV Substation Pattambi
Revised Project Cost: 25.5 Cr Expected Date of COD : 2020-21
Mannuthy 110 kV GIS Project
Project Cost: 26.3 Cr Date of COD : 2019-20
Revised Project Cost: 11.6 Cr Expected Date of COD : 2020-21
GIS SS changed to AIS
CAPEX SBU-T (More than 10 Cr)
Upgradation of 66kV Substation Ettumanoor to 110kV
Project Cost: 20.8 Cr Date of COD : 2019-20
Revised Project Cost: 7.7 Cr Expected Date of COD : 2020-21
GIS SS included in TRANSGRID, delay in completing GIS SS
Upgradation of 66kV Substation, Kuravilangadu and Koothattukulam-Kuravilangadu to 110 kV
Project Cost: 21.65 Cr Date of COD : 2021-22
Revised Project Cost: 21.65 Cr Expected Date of COD: 2021-22
Upgradation of 66kV Substation Koothattukulam to 110 kV
Project Cost: 15.01 Cr Date of COD: 2019-20
Revised Project Cost: 13.27 Cr Expected Date of COD : 2020-21
CAPEX SBU-T (More than 10 Cr)
Upgradation of 66KV Kothamangalam- Kotthttukulam Feeder to 110 KV
Project Cost: 14.67 Cr Date of COD: 2019-20
Revised Project Cost: 24 Cr Expected Date of COD: 2020-21
Due to space constraints and public objections special type towers are to be used. Delay in tender finalization
Upgradation of 66kV SC Pala-Ettumanoor feeders to 110kV
Project Cost: 15.75 Cr Date of COD: 2019-20
Revised Project Cost: 24.5 Cr Expected Date of COD: 2020-21
Delay in tender finalization
Upgradation of 66kV Substation Anchal to 110kV and Upgradation of 66kV SC Edamon –Anchal-Ayur line to 110kV DC
Project Cost: 42.66 Cr Date of COD: 2019-20
Revised Project Cost: 28.85 Cr Expected Date of COD: 2019-20
CAPEX SBU-T (More than 10 Cr)
Up gradation of 66kV Substation, Karunagappally and 66kV SC Sasthamcotta-Karunagapally line to 110kV DC
Project Cost: 18.20 Cr Date of COD: 2019-20
Revised Project Cost: 16.5 Cr Expected Date of COD: 2019-20
Construction of 110kV Substation, Chithara
Non availability of suitable land
Interlinking 110kV GIS Substation, Kollam and 110kV Kottiyam Substation
Project Cost: 63.23 Cr Date of COD: 2021-22
Revised Project Cost: 63.23 Cr Expected Date of COD: 2021-22
CAPEX SBU-T (More than 10 Cr)
110kV GIS substation at Kowdiar, Thiruvananthapuram
Non availability of suitable land
Alternate options being considered
Project Cost: 18.45 Cr Date of COD: 2019-20
Revised Project Cost: 19.75 Cr Expected Date of COD: 2021-22
66kV Substation, Ambalavayal and 66kV DC line from 66kV Kaniyambetta-Sulthanbathery feeder in 110kV Parameters
Project Cost: 13.49 Cr Date of COD: 2020-21
Revised Project Cost: 15.24 Cr Expected Date of COD: 2020-21
CAPEX SBU-T (More than 10 Cr)
110kV Substation, Chemperi and line
Project Cost: 27.77 Cr Date of COD: 2019-20
Revised Project Cost: 19.00 Cr Actual Date of COD: 30/05/2020
Upgradation of Kunnamangalam _ Thamarasserry line to 110kV
Project Cost: 18.06 Cr Date of COD:2019-20
Revised Project Cost: 18.06 Cr Expected Date of COD: 2022-23
Upgradation of Kuthumunda to110kV GIS
Project Cost: 33.98 Cr Date of COD: 2021-22
Revised Project Cost: 15.75 Cr Expected Date of COD: 2022-23
GIS SS changed to AIS
CAPEX SBU-T (More than 10 Cr)
Upgradation of Mankada S/s to 110kV
Project Cost: 14.65 Cr Date of COD: 2019-20
Revised Project Cost: 15.75 Cr Expected Date of COD: 2020-21
Upgradation of 66kV Substation, Mankavu to 110kV
Project Cost: 13.56 Cr Date of COD: 2019-20
Revised Project Cost14.44 Cr Expected Date of COD: 2020-21
Upgradation of 110kV SC/DC line to 220/110kV MC MV line from Mylatty s/s to Vidyanagar
Project Cost: 29.43 Cr Date of COD: 2019-20
Revised Project Cost: 31.96 Cr Expected Date of COD: 2019-20
CAPEX SBU-T (More than 10 Cr)
110kV Substation, Pulikkal
Revised Project Cost: 24 Cr Expected Date of COD: 2021-22
Delay in Procurement of Land
110kV Substation, Seethangoli
Revised Project Cost: 13.41 Cr Expected Date of COD: 2021-22
Preliminary steps to get land started
Upgradation of 33 kV Substation Thambalamanna to 110 kV & 110 kV Agasthiamuzhy -Thambalamanna
(S/C, UG cable)
Revised Project Cost: 33.25 Cr Expected Date of COD: 2020-21
CAPEX SBU-T (More than 10 Cr)
220KV Substation Kottayi
Dropped
Upgradation of Pudukkad to Kattoor 66kV SC Line to 110kV DC Line
Project Cost: 13.91 Cr Date of COD: 2020-21
Revised Project Cost: 13.91 Cr Expected Date of COD: 2020-21
Delayed due to Case Pending at Honorable High Court
Conversion of Ollur Viyyur feeder to 110 kV
Project Cost: 16.72 Cr Date of COD: 2020-21
Revised Project Cost: 16.72 Cr Expected Date of COD: 2021-22
Possible only after upgradation of 66kV SS of Thrissur cooperation
CAPEX SBU-T (More than 10 Cr)
Upgradation of 66kV Pallom-Ettumanoor feeder and associated substations to 110kV
Project Cost: 69.54 Cr Date of COD: 2020-21
Revised Project Cost: 61.4 Cr Expected Date of COD: 2021-22
Construction of 110kV substation Vazhoor
Project Cost: 14.4 Cr Date of COD: 2020-21
Revised Project Cost: 12.3 Cr Expected Date of COD: 2021-22
Upgradation of 66kV Substation Kuttanadu to 110kV
Project Cost: 15.16 Cr Date of COD: 2020-21
Revised Project Cost: 14.2 Cr Expected Date of COD: 2021-22
CAPEX SBU-T (More than 10 Cr)
Upgradation of 66kV PUNNAPRA-ALAPPUZHA DC Feeder to 110 kV
Project Cost: 17.54 Cr Date of COD: 2020-21
Revised Project Cost: 21 Cr Expected Date of COD: 2021-22
110kV Switching Cum Substation at PANTHALACODE
Project Cost: 25.16 Cr Date of COD: 2020-21
Revised Project Cost: 25.16 Cr Expected Date of COD: 2021-22
Upgradation of 66 kV TVT No. I & II feeders
Project Cost: 60.03 Cr Date of COD: 2021-22
Revised Project Cost: 60.03 Cr Expected Date of COD: 2021-22
CAPEX SBU-T (More than 10 Cr)
Renovation and modernisation 110kV GIS Substation, Malappuram
Project Cost: 62.02 Cr Date of COD: 2020-21
Revised Project Cost: 38.5 Cr Expected Date of COD: 2022-23
GIS converted to AIS (shifted to new control Period)
LILO on 110kV Edarikode- Tirur to Parappanangadi S/s
Project Cost: 14.96 Cr Date of COD: 2020-21
Revised Project Cost: 17.16 Cr Expected Date of COD: 2020-21
Delay due to waterlogging in line survey areas
Construction of 110kV GIS Substation, Vengaloor
Project Cost: 46.39 Cr Date of COD:2020-21
CAPEX SBU-T (More than 10 Cr)
Construction of new 110kV DC line from Kayamkulam to Karunagapally
Project Cost: 41.65 Cr Date of COD: 2021-22
Construction of 110/11 kV Vengara SS
Project Cost: 28.24 Cr Date of COD: 2021-22
Construction of 110kV SS Adivaram
Project Cost: 16.89 Cr Date of COD: 2020-21
CAPEX SBU-T (More than 10 Cr)
Construction of 110 kV SS Kadampuzha
Project Cost: 23.53 Cr Date of COD: 2020-21
Upgradation of Mavelikara Pallom 66kV DC
Project Cost: 41.8 Cr Date of COD: 2021-22
Construction of 110kV DC line from 66kV SS Kattapana to 66 kV Peerumedu
Project Cost: 40.7 Cr Date of COD: 2021-22
Upgradtion of 66kV Sasthankotta Chavara DC line
Project Cost: 21.85 Cr Date of COD: 2021-22
Upgradtion of 66kV Edappon Kozhenchery SC line and associated Bays
Project Cost: 20.65Cr Date of COD: 2021-22
Construction of 110kV SS Thiruvali
Project Cost: 13.41 Cr Date of COD: 2020-21
CAPEX SBU-T (More than 10 Cr)
CAPEX SBU-T (More than 10 Cr)
Construction of Thimiri SS
Construction of Munnar SS and associated lines
Project Cost: 22.13 Cr Date of COD: 2021-22
Kuthungal Nedugandam line
CAPEX SBU-T (More than 10 Cr)
Aluva Kothamangalam Line
110kV SS Murikkasery
CAPEX SLDC
Completion
Remarks