capital budgeting and cash flows

Upload: arun-s-bharadwaj

Post on 04-Jun-2018

230 views

Category:

Documents


1 download

TRANSCRIPT

  • 8/13/2019 Capital Budgeting and Cash Flows

    1/49

    PROJECT APPRAISAL CRITERIA

  • 8/13/2019 Capital Budgeting and Cash Flows

    2/49

    CAPITAL EXPENDITURES AND THEIR

    IMPORTANCE

    The basic characteristics of a capital expenditure (also

    referred to as a capital investment or just project) is that

    it involves a current outlay (or current and futureoutlays) of funds in the receiving a stream of benefits infuture

    Importance stems from

    Long-term consequences

    Substantial outlays

    Difficulty in reversing

  • 8/13/2019 Capital Budgeting and Cash Flows

    3/49

    PROCESS

    Identification of Potential Investment Opportunities

    Assembling of Investment Proposals

    Decision Making

    Preparation of Capital Budget and Appropriations

    Implementation

    Performance Review

  • 8/13/2019 Capital Budgeting and Cash Flows

    4/49

    PROJECT CLASSIFICATION

    Mandatory Investments

    Replacement Projects

    Expansion Projects

    Diversification Projects

    Research and Development Projects

    Miscellaneous Projects

  • 8/13/2019 Capital Budgeting and Cash Flows

    5/49

    INVESTMENT CRITERIA

    INVESTMENT

    CRITERIA

    DISCOUNTING

    CRITERIA

    NON-DISCOUNTING

    CRITERIA

    NET

    PRESENTVALUE

    BENEFIT

    COSTRATIO

    INTERNAL

    RATE OFRETURN

    PAYBACK

    PERIODACCOUNTING

    RATE OFRETURN

  • 8/13/2019 Capital Budgeting and Cash Flows

    6/49

    PAYBACK PERIOD

    Payback period is the length of time required to recover the initial

    outlay on the projectCapital Project

    Year Cash flow Cumulative cash flow

    0 -100 -100

    1 34 - 66

    2 32.5 -33.53 31.37 - 2.13

    4 30.53 28.40

    Pros Cons

    Simple Fails to consider the time valueof money

    Rough and ready method Ignores cash flows beyond thefor dealing with risk payback period

    Emphasises earlier cash inflows

  • 8/13/2019 Capital Budgeting and Cash Flows

    7/49

    Payback The payback period of a project is the number of

    years it takes before the cumulative forecastedcash flow equals the initial outlay.

    The payback rule says only accept projects thatpayback in the desired time frame.

    This method is flawed, primarily because itignores later year cash flows and the the present

    value of future cash flows.

  • 8/13/2019 Capital Budgeting and Cash Flows

    8/49

    PaybackExample

    Examine the three projects and note the mistakewe would make if we insisted on only takingprojects with a payback period of 2 years or less.

    502050018002000-C

    58-2018005002000-B

    2,624350005005002000-A

    10%@NPVPeriod

    PaybackCCCCProject 3210

    +

    +

  • 8/13/2019 Capital Budgeting and Cash Flows

    9/49

  • 8/13/2019 Capital Budgeting and Cash Flows

    10/49

    NET PRESENT VALUE

    n CtNPV = Initial investment

    t=1 (1 +rt )t

  • 8/13/2019 Capital Budgeting and Cash Flows

    11/49

    NET PRESENT VALUE

    The net present value of a project is the sum of the present value of all the cash

    flows associated with it. The cash flows are discounted at an appropriate discount

    rate (cost of capital)

    Capital Project

    Year Cash flow Discount factor (15%) Presentvalue

    0 -100.00 1.000 -100.00

    1 34.00 0.870 29.58

    2 32.50 0.756 24.57

    3 31.37 0.658 20.64

    4 30.53 0.572 17.46

    5 79.90 0.497 39.71

    Sum = 31.96

    Pros Cons

    Reflects the time value of money Is an absolute measure and not a relative

    Considers the cash flow in its entirely measure

    Squares with the objective of wealth maximisation

  • 8/13/2019 Capital Budgeting and Cash Flows

    12/49

    NPV

  • 8/13/2019 Capital Budgeting and Cash Flows

    13/49

    PROPERTIES OF THE NPV RULE

    NPVs ARE ADDITIVE

    INTERMEDIATE CASH FLOWS ARE INVESTED AT

    COST OF CAPITAL

    NPV CALCULATION PERMITS TIME-VARYINGDISCOUNT RATES

    NPV OF A SIMPLE PROJECT AS THE DISCOUNT

    RATE

  • 8/13/2019 Capital Budgeting and Cash Flows

    14/49

    BENEFIT COST RATIO

    PVB

    Benefit-cost Ratio :BCR =

    I

    PVB = present value of benefits

    I = initial investment

    To illustrate the calculation of these measures, let us consider a project which is being evaluatedby a firm that has a cost of capital of 12 percent.

    Initial investment : Rs 100,000

    Benefits: Year 1 25,000

    Year 2 40,000Year 3 40,000

    Year 4 50,000

    The benefit cost ratio measures for this project are:

    25,000 40,000 40,000 50,000

    (1.12) (1.12)2 (1.12)3 (1.12)4

    BCR = = 1.145

    100,000

    Pros Cons

    Measures benefit per buck Provides no means for aggregation

    + + +

  • 8/13/2019 Capital Budgeting and Cash Flows

    15/49

    Discount rate

    Net Present Value

    INTERNAL RATE OF RETURN

    The internal rate of return (IRR) of a project is the discount rate that

    makes its NPV equal to zero. It is represented by the point of intersectionin the above diagram

    Net Present Value Internal Rate of Return

    Assumes that the Assumes that the netdiscount rate (cost present value is zero

    of capital) is known.

    Calculates the net Figures out the discount rate

    present value, given that makes net present value zero

    the discount rate.

  • 8/13/2019 Capital Budgeting and Cash Flows

    16/49

    IRR

  • 8/13/2019 Capital Budgeting and Cash Flows

    17/49

    NPV & IRR

  • 8/13/2019 Capital Budgeting and Cash Flows

    18/49

    PROBLEMS WITH IRR

    NON-CONVENTIONAL CASH FLOWS

    MUTUALLY EXCLUSIVE PROJECTS

    LENDING VS. BORROWING

    DIFFERENCES BETWEEN SHORT-TERM AND

    LONG-TERM INTEREST RATES

  • 8/13/2019 Capital Budgeting and Cash Flows

    19/49

    Internal Rate of ReturnPitfall 1 - Lending or Borrowing? With some cash flows the NPV of the project increases

    s the discount rate increases. This is contrary to the normal relationship between NPV

    and discount rates.

    364%50500,1000,1364%50500,1000,1

    %10@Project 10

    ++

    +++

    B

    A

    NPVIRRCC

  • 8/13/2019 Capital Budgeting and Cash Flows

    20/49

    Internal Rate of ReturnPitfall 2 - Multiple Rates of Return Certain cash flows can generate NPV=0 at two different discount rates.

    The following cash flow generates NPV= 0 at both IRR% of (-44%)and +11.6%.

    600

    NPV

    300

    0

    -30

    -600

    Discount

    Rate

    IRR=11.6%

    IRR=-44%

  • 8/13/2019 Capital Budgeting and Cash Flows

    21/49

    IRR

  • 8/13/2019 Capital Budgeting and Cash Flows

    22/49

    Internal Rate of Return

    Pitfall 2 - Multiple Rates of Return

    It is possible to have a zero IRR and a positive NPV

    339500,2000,3000,1

    %10@Project 210

    ++++ NoneC

    NPVIRRCCC

  • 8/13/2019 Capital Budgeting and Cash Flows

    23/49

  • 8/13/2019 Capital Budgeting and Cash Flows

    24/49

    Internal Rate of ReturnPitfall 3 - Mutually Exclusive Projects

  • 8/13/2019 Capital Budgeting and Cash Flows

    25/49

    Profitability Index When resources are limited, the profitability

    index (PI) provides a tool for selecting amongvarious project combinations and alternatives

    A set of limited resources and projects can yieldvarious combinations.

    The highest weighted average PI can indicatewhich projects to select.

  • 8/13/2019 Capital Budgeting and Cash Flows

    26/49

    Profitability Index

    Investment

    NPVIndexityProfitabil =

  • 8/13/2019 Capital Budgeting and Cash Flows

    27/49

    Profitability Index

    121555

    1620552153010

    %10@Project 210

    ++

    ++

    ++

    C

    BA

    NPVCCC

    121555

    1620552153010

    %10@Project 210

    ++

    ++

    ++

    C

    BA

    NPVCCC

  • 8/13/2019 Capital Budgeting and Cash Flows

    28/49

    Profitability Index

    2.4125C

    3.2165B2.12110A

    IndexityProfitabil($)NPV($)InvestmentProject

    2.4125C

    3.2165B2.12110A

    IndexityProfitabil($)NPV($)InvestmentProject

    Cash Flows ($ millions)

  • 8/13/2019 Capital Budgeting and Cash Flows

    29/49

    Profitability IndexProj NPV Investment PI

    A 230,000 200,000 1.15

    B 141,250 125,000 1.13C 177,600 160,000 1.11

    D 162,000 150,000 1.08

    Select projects with highest Weighted AvgPI

    WAPI (BD) = 1.13(125) + 1.08(150) + 0.0 (25)(300) (300) (300)

    = 1.01

  • 8/13/2019 Capital Budgeting and Cash Flows

    30/49

    Profitability IndexProj NPV Investment PI

    A 230,000 200,000 1.15

    B 141,250 125,000 1.13C 177,600 160,000 1.11

    D 162,000 150,000 1.08

    Select projects with highest Weighted AvgPI

    WAPI (BD) = 1.01WAPI (A) = 0.77

    WAPI (BC) = 1.06

  • 8/13/2019 Capital Budgeting and Cash Flows

    31/49

    Multi Period

    121555

    162055

    2153010

    %10@Project 210

    ++

    ++

    ++

    C

    B

    A

    NPVCCC

    121555

    162055

    2153010

    %10@Project 210

    ++

    ++

    ++

    C

    B

    A

    NPVCCC

    4.0

    136040%10@Project 210

    PI

    D

    NPVCCC

    +

    4.0

    136040%10@Project 210

    PI

    D

    NPVCCC

    +

  • 8/13/2019 Capital Budgeting and Cash Flows

    32/49

    Linear Programming Maximize Cash flows or NPV

    Minimize costs

    Example

    Max NPV = 21Xn + 16 Xb + 12 Xc + 13 Xdsubject to

    10Xa + 5Xb + 5Xc + 0Xd

  • 8/13/2019 Capital Budgeting and Cash Flows

    33/49

    INVESTMENT APPRAISAL

    IN PRACTICE

    Over time, discounted cash flow methods have gained in

    importance and internal rate of return is the mostpopular evaluation method.

    Firms typically use multiple evaluation methods.

    Accounting rate of return and payback period are

    widely employed as supplementary evaluation methods.

  • 8/13/2019 Capital Budgeting and Cash Flows

    34/49

    CFO Decision Tools

    Profitability

    Index, 12%

    Payback, 57%

    IRR, 76%

    NPV, 75%

    Book rate of

    return, 20%

    0% 10% 20% 30% 40% 50% 60% 70% 80% 90% 100%

    Survey Data on CFO Use of Investment Evaluation Techniques

    SOURCE: Graham and Harvey, The Theory and Practice of Finance: Evidence from the Field,

    Journal of Financial Economics

  • 8/13/2019 Capital Budgeting and Cash Flows

    35/49

    Be consistent in how you handle inflation!!Use nominal interest rates to discount

    nominal cash flows.

    Use real interest rates to discount real cash

    flows.

    You will get the same results, whether youuse nominal or real figures

    InflationINFLATION RULE

  • 8/13/2019 Capital Budgeting and Cash Flows

    36/49

    InflationExample

    You own a lease that will cost you 8,000 nextyear, increasing at 3% a year (the forecastedinflation rate) for 3 additional years (4 years

    total). If discount rates are 10% what is thepresent value cost of the lease?

    1 + real interest rate = 1+nominal interest rate1+inflation rate

  • 8/13/2019 Capital Budgeting and Cash Flows

    37/49

    InflationExample - nominal figures

    Year Cash Flow PV @ 10%1 8000

    2 8000x1.03 = 82408000x1.03 = 8240

    8000x1.03 = 8487.20

    80001.10

    2

    3

    =

    =

    =

    =

    7272 73

    6809 923 6376 56

    4 5970 78429 99

    8240

    1 10

    8487 20

    1 10

    8741 82

    1 10

    2

    3

    4

    .

    ..

    .$26, .

    .

    .

    .

    .

    .

  • 8/13/2019 Capital Budgeting and Cash Flows

    38/49

    InflationExample - real figures

    Year Cash Flow [email protected]%1 = 7766.99

    2 = 7766.99= 7766.99

    = 7766.99

    80001.03

    7766.991.068

    8240

    1.03

    8487.20

    1.03

    8741.82

    1.03

    2

    3

    4

    =

    =

    =

    =

    7272 73

    6809 923 637656

    4 5970 7826 429 99

    7766 99

    1 068

    7766 99

    1 068

    7766 99

    1 068

    2

    3

    4

    .

    .

    .

    .

    .

    .

    .

    .

    .

    .

    = $ , .

  • 8/13/2019 Capital Budgeting and Cash Flows

    39/49

    Equivalent Annual CostEquivalent Annual Cost - The cost per

    period with the same present value as thecost of buying and operating a machine.

  • 8/13/2019 Capital Budgeting and Cash Flows

    40/49

    Equivalent Annual CostEquivalent Annual Cost - The cost per

    period with the same present value as thecost of buying and operating a machine.

    Equivalent annual cost =present value of costs

    annuity factor

  • 8/13/2019 Capital Budgeting and Cash Flows

    41/49

    Example

    Given the following costs of operating two

    machines and a 6% cost of capital, select thelower cost machine using equivalent annual cost

    method.

    Year

    Machine 1 2 3 4 PV@6% EAC

    A 15 5 5 5 28.37 10.61

    B 10 6 6 21.00 11.45

    Equivalent Annual Cost

  • 8/13/2019 Capital Budgeting and Cash Flows

    42/49

    Timing Even projects with positive NPV may be

    more valuable if deferred. The actual NPV is then the current value

    of some future value of the deferredproject.

    tr

    t

    )1(

    dateofasvaluefutureNet

    NPVCurrent +=

  • 8/13/2019 Capital Budgeting and Cash Flows

    43/49

    TimingExample

    You may harvest a set of trees at anytime overthe next 5 years. Given the FV of delaying the

    harvest, which harvest date maximizes current

    NPV?

    9.411.915.420.328.8in valuechange%109.410089.477.564.450(1000s)FVNet

    543210

    YearHarvest

  • 8/13/2019 Capital Budgeting and Cash Flows

    44/49

  • 8/13/2019 Capital Budgeting and Cash Flows

    45/49

    TimingExample - continued

    You may harvest a set of trees at anytime over the next 5 years.Given the FV of delaying the harvest, which harvest date maximizescurrent NPV?

    5.581.10

    64.41yearinharvestedif ==NPV

    67.968.367.264.058.550(1000s)NPV

    543210

    YearHarvest

  • 8/13/2019 Capital Budgeting and Cash Flows

    46/49

    Fluctuating Load Factors

    $30,00015,0002machinestwoofcostoperatingPV

    $15,0001,500/.10pachinepercostoperatingPV$1,5007502machinepercostOperating

    units750machineperoutputAnnual

    MachinesOldTwo

    =

    =

    =

  • 8/13/2019 Capital Budgeting and Cash Flows

    47/49

    Fluctuating Load Factors

    $27,000500,132machinestwoofcostoperatingPV

    $13,500750/.106,000pachinepercostoperatingPV

    $7507501machinepercostOperating

    000,6$machinepercostCapital

    units750machineperoutputAnnual

    MachinesNewTwo

    =

    =+

    =

  • 8/13/2019 Capital Budgeting and Cash Flows

    48/49

    Fluctuating Load Factors

    000,26..$..............................machinestwoofcostoperatingPV

    $16,000.10/000,16,000$10,000,000/.101machinepercostoperatingPV

    $1,000000,11$1,0005002machinepercostOperating

    000,6$0machinepercostCapital

    units1,000units500machineperoutputAnnual

    MachineNewOneMachineOldOne

    =+=

    ==

    What To Discount

  • 8/13/2019 Capital Budgeting and Cash Flows

    49/49

    What To Discount Cash Flows.not accounting

    income/expenses

    Estimate Cash Flows on an Incremental

    BasisDo not confuse average with incremental

    payoffs

    Beware of allocated overhead costsInclude all incidental effects

    Do not forget working capital requirements

    Include opportunity costs

    Forget sunk costs

    Treat inflation consistently

    Post Tax