Capital Project 2019 Caledonia-Mumford CSD Proud of Our Past...Excited About Our Future Message From the Superintendent Dear Caledonia-Mumford Central School District Community Members, On September 18, 2018 the Caledonia-Mumford Central School District residents will be voting on a “NO ADDITIONAL TAX IMPACT” capital project. The Board of Education has been working towards creating a project that both addresses the District’s current needs while simultaneously being good stewards of the District’s money. The project is designed to enhance the District’s facilities through focusing on health and safety improvements and replacement of aging infrastructure items. The goal is to protect investments already made by our community as well as to prepare our facilities to meet future needs in a fiscally responsible way. The capital project will cost $3,665,000 and does not require additional taxes on the part of our community. There will be a community meeting held on September 10, 2018. This meeting will include a presentation of the details of the proposed project with a question and answer session to follow. We encourage all District residents to attend this informational presentation to learn the specifics of this proposed capital project and what it can do for our community. We believe you will find that the proposed project will only improve the Caledonia-Mumford Central School District and positively impact our community as a whole. Sincerely, Robert Molisani, Superintendent of Schools SEP 18 12:00 noon - 9:00 pm District Office 99 North St. Caledonia, NY Please ote!

Upload: others

Post on 14-Jun-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Caledonia-Mumford CSD - Cal-Mum€¦ · • Gymnasium Floor Refinishing • Gymasium Bleacher Replacement • Roof Replacement MIDDLE/HIGH SCHOOL • Auditorium Sound/Lighting/Rigging

Capital Project 2019Caledonia-Mumford CSD

Proud of Our Past...Excited About Our Future

Message From the SuperintendentDear Caledonia-Mumford Central School District Community Members,

On September 18, 2018 the Caledonia-Mumford Central School District residents will be voting on a “NO ADDITIONAL TAX IMPACT” capital project. The Board of Education has been working towards creating a project that both addresses the District’s current needs while simultaneously being good stewards of the District’s money. The project is designed to enhance the District’s facilities through focusing on health and safety improvements and replacement of aging infrastructure items. The goal is to protect investments already made by our community as well as to prepare our facilities to meet future needs in a fiscally responsible way.

The capital project will cost $3,665,000 and does not require additional taxes on the part of our community. There will be a community meeting held on September 10, 2018. This meeting will include a presentation of the details of the proposed project with a question and answer session to follow. We encourage all District residents to attend this informational presentation to learn the specifics of this proposed capital project and what it can do for our community. We believe you will find that the proposed project will only improve the Caledonia-Mumford Central School District and positively impact our community as a whole.

Sincerely,Robert Molisani, Superintendent of Schools

S E P 18

12:00 noon - 9:00 pmDistrict Office

99 North St. Caledonia, NY

Please ote!

Page 2: Caledonia-Mumford CSD - Cal-Mum€¦ · • Gymnasium Floor Refinishing • Gymasium Bleacher Replacement • Roof Replacement MIDDLE/HIGH SCHOOL • Auditorium Sound/Lighting/Rigging

Financial InformationThe total cost of the proposed project is $3,665,000. It will be funded and paid for with no additional tax impact for residents of the Caledonia-Mumford Central School District.Project funds will come from the following areas:

Building Aid

Capital Reserve

$2,725,000

$940,000

NO ADDITIONAL TAX IMPACT

Proposed Project HighlightsBelow are a few of the project scope items that have been included in the capital project proposition. These items have been specifically chosen because of the need for improvements and upgrades to our District.

It’s crucial that we address the work outlined in the project at a time where critical funding is available

-Robert MolisaniSuperintendent of Schools

“”

ELEMENTARY SCHOOL• Gymnasium Floor Refinishing• Gymasium Bleacher Replacement• Roof Replacement

MIDDLE/HIGH SCHOOL• Auditorium Sound/Lighting/Rigging

Upgrades• Roof Replacement

ATHLETIC COMPLEX• New Pole Vault Concrete Pads• Installation of a Soccer Safety Net• Press Box Window Replacements• Track Resurfacing• Synthetic Turf Replacement• Increased Field Drainage• Installation of a Shock Pad

DISTRICT-WIDE• Septic System Improvements

For project related questions please contact the Caledonia-Mumford CSD office at (585) 538-3400.

Building Aid $2,725,000

Capital Reserves $940,000

Total Cost of Project $3,665,000

Tax Impact ZERO

Project funds will come from the following areas:

Page 3: Caledonia-Mumford CSD - Cal-Mum€¦ · • Gymnasium Floor Refinishing • Gymasium Bleacher Replacement • Roof Replacement MIDDLE/HIGH SCHOOL • Auditorium Sound/Lighting/Rigging

Questions & AnswersQ. What is the scope of the proposed project?A. A primary scope item is partial roof replacement at the elementary and middle/high schools, covering about 17,500 square feet in total. With the roofs being at the end of their useful life, this is an item that requires immediate attention. Additional scope items include renovations to the Middle/High School Auditorium and Elementary School Gymnasium. The auditorium will see upgrades to the sound, lighting and rigging systems and the gymnasium will receive new bleachers, and the refinishing of the gym floor. Other project highlights are scheduled for the Hamilton Field Athletic Complex. Enhancements include increased drainage, the installation of a shock pad, track resurfacing and synthetic turf replacement. Miscellaneous improvements include installation of a soccer safety net, new pole vault concrete pads and the replacement of windows in the press box.

Q. Why is this project important?A. The project is necessary to address repairs and renovations required by the NY State mandated 5-year Building Conditions Survey (BCS), to upgrade our facilities to accommodate 21st Century programs and to address building code issues. Renovating these scope items will extend the life of the District’s athletics fields and building structures, and this project will focus on increasing students’ health and safety on the campus.

Q. Why now?A. Our District will receive 81.2% of aid from NYS on eligible project components. Utilizing the voter authorized capital reserve (that was established to offset any local share of a future capital project) and this aid scenario allows for a zero impact to taxes. This is truly an unprecedented opportunity. The District is also pursuing this project to take advantage of historically low interest rates. In addition, we are in a favorable bidding climate and we anticipate construction bids to be more competitive, therefore, our constituents will get more value for their tax dollar. In summary, there really is no better time than now!

Q. How long will the project take?A. With positive community support this estimated calendar of planning will occur:

• September 2018 to October 2018 the architects will facilitate Stakeholder Planning and Design Meetings to further develop the plans

• October 2018 through January 2019 (approximately 16 weeks) submitted plans will be reviewed and approved by the NY State Education Department

• February 2019 to March 2019 the project will be competitively bid based on the approved plans • March 2019 through November 2019 construction will occur • Fall 2019 construction ends

This is an estimated timeline based on typical planning and the NY State Education Department approval and bidding process.

Q. How has the Athletic Complex been designed to maximize state aid?A: As NYS considers the funding (i.e. “aid”) of capital replacements differently than capital improvements, the proposed capital project has been designed to provide for system improvements and enhancements to the greatest extent possible to maximize the amount of state aid received. For example a new fully-aided shock pad and perimeter drainage line is proposed as an improvement, which will enhance not only the safety of the field but also the drainage capability. These enhancements provide a longer lifespan for the field and, consequently, will maximize the aidability of the current and future projects.

Q. Are there any Athletic Complex components that aren’t being fully aided by NYS?A. NYS fully aids the replacement of eligible project components that have been installed for a minimum of 15 years, and elements requiring early replacement receive a proportional amount of aid. For example, at the time of construction, the synthetic turf carpet, infill mix, and track surfacing will be 13 years old and therefore will receive 13/15ths of state aid. The district met with NYS Education Department earlier this year and negotiated the maximum amount of components to be aided at the district’s full aid ratio. Any unaided portions of the project are funded through the Capital Reserve.

Q. How will this project affect my child’s school experience?A. In an effort to reduce impacts to the educational calendar to the greatest extent possible, the majority of construction will occur during the 2019 summer months, including septic system replacements. The construction timeline could po-tentially impact summer camps and sport practices throughout the summer, as well as late season track events. To prevent impact on students and community members the District may look to reschedule these events at a neighboring school or community facility.

For more information please visit our website at www.cal-mum.org or check us out on Facebook and Twitter.

Page 4: Caledonia-Mumford CSD - Cal-Mum€¦ · • Gymnasium Floor Refinishing • Gymasium Bleacher Replacement • Roof Replacement MIDDLE/HIGH SCHOOL • Auditorium Sound/Lighting/Rigging

ABSENTEE BALLOTThe option of using an absentee ballot is available to qualified voters of the school district who are unable to personally appear to vote. An application must be completed in order to receive an absentee ballot. The completed ballot must be received by the District Clerk no later than 5 PM on Tuesday, September 18, 2018. You may call (585) 538-3400 to request an application.

COMMUNITY MEETING VOTE INFORMATION

The community meeting will include a presentation of the proposed project details followed by a question and answer session. The middle/high school is located at 99 North St. Caledonia, NY 14423

Tuesday, September 18, 201812:00 noon - 9:00pm

District Office99 North St. Caledonia, NY

VOTER ELIGIBILITY

Monday, September 10, 20187:00pm

Middle/High School Auditorium

For project related questions please contact the Caledonia-Mumford CSD office at (585) 538-3400. For more information please visit www.cal-mum.org or check us out on Facebook and Twitter.

• Citizen of U.S.• At least 18 years of age• Legal resident of the Caledonia-Mumford Central

School District at least 30 days prior to vote• You do not need to be a registered voter

Caledonia-Mumford Central School

Caledonia NY 14423

ECRWSSTo Boxholder or Resident

Non-Profit ORGU.S. Postage

PAIDPermit #15

Avon, NY 14414

IMPORTANT 2019 YEARBOOK NEWS2019 senior yearbook information packets will be mailed to the current juniors very soon On November 7 2018 senior2019 senior yearbook information packets will be mailed to the current juniors very soon. On November 7, 2018, senior pictures and senior sibling pictures are due to be uploaded to the Jostens site for the yearbook.

Senior quotes, name, and other information are due to Ms. Barbis via fi lling out the Google form sent through seniors’ school email account. All seniors need to log into this and complete this form in September when it’s made available. 

Senior recognition ads (aka baby ads or senior send off s) are submitted online only to Jostens for a fee. Th e fi nal date for these ads is November28, 2018. Yearbooks for everyone are ordered online only from Jostens from September 1, 2018-December 15, 2018 for lowest price (pricesTBD). Price increases by $5 on December 16, 2018 and online ordering closes March 31, 2019.

Visit (www.jostensyearbooks.com or call 1-877-767-5217). Watch for fl yers and emails from Jostens to be mailed to you this fall. Parents andstudents are also encouraged to submit photos to the yearbook for consideration by using the Jostens Replayit app for phones and devices or www.replayit.com. Look for Caledonia Mumford Middle High. We need sport pictures, event and friend candids, senior retro pictures, and seniors wav-ing goodbye for last page. Be sure to give your photo a description where indicated (ex. senior picture, sibling picture, varsity softball, etc.).