c3010 highway engineering unit2

Upload: idiotfellow

Post on 10-Oct-2015

29 views

Category:

Documents


0 download

DESCRIPTION

C3010 Highway Engineering UNIT2

TRANSCRIPT

  • TECHNIQE IN PLANNING AND PRE-CONSTRUCTION OF ROAD WORKHighway Engineering C3010 / UNIT2

    i

    TECHNIQUE IN PLANNING AND PRE-CONSTRUCTION OF ROADWORK

    OBJECTIVES

    General Objective

    To understand the planning activities and all pre-construction works

    Specific Objectives

    At the end of the unit you should be able to :-

    describe the planning objective. state the procedures to identify a new road. state the procedures for site investigation describe the method of site exploration. describe the survey works.

    UNIT 2

  • TECHNIQE IN PLANNING AND PRE-CONSTRUCTION OF ROAD WORKHighway Engineering C3010 / UNIT2

    TECHNIQUE IN PLANNING AND PRE-CONSTRUCTIONROADWORKS

    2.0 TECHNIQUES IN PLANNING AND PRE-CONSTRUCTION ROADWORK.

    A construction of a new road must under go an extensive planning,

    accurate land surveying and economic planning.

    2.0.1 Planning Requirements

    A modern highway construction would include:-

    1. A collection of a tabulated information on the existing transportation

    facilities in the area.

    2. The determination of the general inter-relation of all branches of the

    transportation system and their effect on each other.

    3. The determination of the adequacy or otherwise of the existing

    facilities as per present needs and the improvement and extension

    of these facilities for anticipated future needs for a certain period.

    4. Methods of financing the projects and the duration of the

    construction.

    5. An estimation of construction and maintenance.

  • TECHNIQE IN PLANNING AND PRE-CONSTRUCTION OF ROAD WORKHighway Engineering C3010 / UNIT2

    Any highway planning study can be sub-divided into :-

    1. Road inventory study.

    2. Traffic studies.

    3. Economic planning studies.

    4. Financial planning studies.

    2.0.2 Preparation and Planning Scheme of a New Road.

    Planning expertise, evaluation on survey work, knowledge

    on geology and experience on civil engineering area are essentially

    needed in constructing of a new road. The traffic needs, the

    purpose on planning at certain route and approximate cost thus

    become very vital information to be considered before constructing

    a new road.

    The synopsis of procedures that is used for identifying,

    planning and constructing a new road are listed in the following

    page. However, not all new roads follow these procedures. Some of

    the procedures are valid for certain terms and conditions only.

    Below is set of procedure that is used for identifying,

    planning and constructing a new road. The procedures are;

    1. Identify the problem in traffic congestion, accident and

    environment by making a research on transportation and

    problematic areas.

    2. Identify the maintenance and new construction work needed.

    3. Identify the organization and Ministries that are responsible with

    the construction work such as JKR, TNB etc.

  • TECHNIQE IN PLANNING AND PRE-CONSTRUCTION OF ROAD WORKHighway Engineering C3010 / UNIT2

    4. Collect the information for briefing.

    5. Prepare the following plans: -

    a. Topography plan.

    b. Usage land plan.

    c. Geology plan.

    d. Agriculture area plan.

    e. Domestic plan.

    f. Traffic flow plan.

    g. Town Consult planning document.

    6. Draw a temporary layout sketch and include related

    suggestion.

    7. Get information on;

    a. Junctions.

    b. River and drainage.

    c. Survey information.

    d. The latest traffic data.

    e. Ground Level.

    8. Prepare a detailed layout with consideration to environmental

    impact.

    9. Make a valuation.

    10. Choose the best road to be constructed. However, the

    alternative road should be equally prepared in the planning.

    11.Negotiate with other related group such as :-

    a. Ministry of Science and Environment.

    b. Ministry of Transportation.

    c. Water Board, Forestry Department, Telecom Company

    d. National Museum.

    e. Railway Station.

    f. Geology and Mineral Department.

    12.Present a report on the entire technical problems.

  • TECHNIQE IN PLANNING AND PRE-CONSTRUCTION OF ROAD WORKHighway Engineering C3010 / UNIT2

    13.Analyze the problems faced by the public.

    14.Prepare the preliminary report based on the above information

    and submit it to the planning division.

    15.Wait for the outcome or result.

    a. If it is acceptable, draw a road design at 1 : 2500 scale

    and proceed to the particular ministry.

    b. If it is unacceptable, it needs to be revised thoroughly or

    it will be cancelled.

    16.Proceed with the following: -

    a. Start planning the main task (the identified road).

    b. Start planning the alternative roads.

    c. Start purchasing the important materials.

    17.Get the information from the public on the suggested road and

    the other roads involved. Set a panel that consists of external

    lawyers and other professionals to conduct a survey.

    18.Submit the report to the respective Ministry and wait for the

    approval.

    19.Prepare the financial report based on the cost benefit analysis

    to determine the advantages will bring to the public.

    20.Advertise a tender notice and the selected contractor will then

    need to prepare and submit the quotation of the contract plan

    and document.

    21.Accept the tender and start the construction work.

    There are 3 stages in planning the construction of a new road :-

    1. Stage 1 - Prepare a preliminary report.

    2. Stage 2 - Submit the preliminary report.

    3. Stage 3 - Finalize the report.

  • TECHNIQE IN PLANNING AND PRE-CONSTRUCTION OF ROAD WORKHighway Engineering C3010 / UNIT2

    2.0.3 Stage 1- Preparing a preliminary report.

    In this stage, it includes all the preliminary reports and

    information that are received during the ensuing stage (refer to

    2.0.2, Procedure 14). They are: -

    a. Traffic surveying work.

    b. Evaluation on the information and planning. Consider

    suggestion if there is another useful choice.

    c. Design using 6 : 1 mile scale.

    d. Budget of the construction and its advantages.

    e. Identify the certain road.

    f. Report on the alternative road, which includes the

    topography, geology and traffic flow, soil consuming and

    historical places.

    g. Obtain cooperation from the related group such as town

    council and state government.

    h. If the project is over budgeted the ministry must be inform

    and no further work shall be proceed.

    2.0.4 Stage 2 - Submitting the preliminary report.

    In the preliminary report, it explains about the proposal and its

    alternatives of the identified project. It then is submitted to the

    person in-charged to obtain permission. However, the following

    questions need to be considered.

    a. Are the suggestions fulfilled the planning needs at the

    national level.

    b. Are the advantages accepted?

  • TECHNIQE IN PLANNING AND PRE-CONSTRUCTION OF ROAD WORKHighway Engineering C3010 / UNIT2

    c. Are the suggested solution accepted in term of

    political or environmental aspect.

    While the preliminary report is being studied further, other

    experiments should be done such as:-

    a. Further soil investigation.

    b. The plan preparation on the new road and other related

    roads. Report and work are to be prepared. It will only be

    submitted if the preliminary report is accepted.

    2.0.5 Stage 3 - Finalizing the Report

    a. When the preliminary report is accepted, prepare the

    road plan with 1:2500 scale.

    b. When the final report is completed, submit it to the Head

    Quarter for approval. Here, a right budget and

    advantages of the project shall be included for approval

    purposes.

    c. After the costing and advantages valuation are done, this

    final report will be submitted to the responsible person to

    start off the construction work.

    d. If there is no protest from the public or other parties in

    fact, the tender will be offered and the selected

    contractor. Then, all the construction works will start.

    e. If there is a protest, a committee member will be set up

    for further investigation.

  • TECHNIQE IN PLANNING AND PRE-CONSTRUCTION OF ROAD WORKHighway Engineering C3010 / UNIT2

    2.0.6 The content of the Preliminary Report

    The preliminary report which includes the plan must contain the

    following aspects:-

    a. The existence situation which is on physical shape and

    scheme objective of the existence road.

    b. The traffic situation based on the latest data (not more

    than 3 years). A report should include content the total of

    traffic user.

    c. The alternative roads, which include the costing,

    advantages and the environmental impact.

    d. Road classification identify the road classification that is

    to be built; highway or ordinary road.

    e. Negotiation on the report and the result.

    f. Budget the total of roadwork cost, bridges work and

    earthwork approximately 20% from the previous budget.

    The cost report should comprise the following:

    Roadwork:-

    - Site clearing cost.

    - Earthwork cost.

    - Pavement construction and road shoulder work

    cost.

    - Road furniture work.

    - Facilities service work.

    - Contingency stretch cost.

    g. Valuation is to see the economical aspect of the project.

  • TECHNIQE IN PLANNING AND PRE-CONSTRUCTION OF ROAD WORKHighway Engineering C3010 / UNIT2

    h. Enclosed plans plan with 6:1 mile scale is used for

    new scheme. For the city or village area a bigger scale is

    used. Plan must show the following:-

    a. The plan of the approved alternative roads.

    b. The type of junction and its location.

    Avoid using the existence plan. Beside the, the activities

    which would be included in the planning and pre-

    construction road work are as follow:

    1. Site investigation.

    2. Survey works and setting out.

    3. Site clearing and top soil deletions.

    4. Earth works.

  • TECHNIQE IN PLANNING AND PRE-CONSTRUCTION OF ROAD WORKHighway Engineering C3010 / UNIT2

    TEST YOUR UNDERSTANDING BEFORE YOU CONTINUE WITH THE NEXT INPUT

    1. State the planning objective of planning in executing a new road

    development.

    2. State four other activities in planning and pre-construction roadworks.

    a.

    b.

    c.

    d.

    ACTIVITY 2 A

    Question

  • TECHNIQE IN PLANNING AND PRE-CONSTRUCTION OF ROAD WORKHighway Engineering C3010 / UNIT2

    1. The objective of planning is to provide a highway system which

    would give maximum transportation facilities at a minimum cost.

    2. The other activities in planning and pre-construction roadworks be

    as follows :

    1. Site investigation.

    2. Survey works and setting out.

    3. Site clearing and top soil deletions.

    4. Earth works.

    FEEDBACK ON ACTIVITY 2 A

    Answer

  • TECHNIQE IN PLANNING AND PRE-CONSTRUCTION OF ROAD WORKHighway Engineering C3010 / UNIT2

    2.1 SITE INVESTIGATION

    Road structures are the structure which is supported by the ground.

    The interaction between the structure and the soil beneath it is complex,

    and therefore knowledge of the site and soil condition is important.

    2.1.1 Procedures of the investigation

    2.1.1.1 Compact sites

    In the case of compact sites for road structure, the

    investigation requires deep and closely speed borings. The

    actual number and position of borings depend on the types

    of structure and nature of sites. However, the number of

    bore hole should be such as to given a clear picture of all

    significant variations in the soil over the site, and the depth

    of such bore hole should be such as to reach all strata

    likely to influence the stability of the works.

    2.1.1.2 Method of site exploration

    When discussing the procedure of the investigation,

    reference is made to borings as a means of the

    investigation. This is perhaps it is the most common

    method of site exploration, but certainly not the only one.

    Considering new works, from the very small to the very

    large contract, a general guide to exploration would be as

    follows:

    1. Small works- trial pits up to 3m deep.

  • TECHNIQE IN PLANNING AND PRE-CONSTRUCTION OF ROAD WORKHighway Engineering C3010 / UNIT2

    2. Medium to large scale works borings up to 30m

    deep

    3. Very large scale works a combination of deep

    boring, pits and insitu examination from heading and

    shafts.

    It must be noted that the above is only guide: the

    detailed methods of exploration would depend on the types

    of the construction and the site involved.

    a. Trial pits

    This is the cheapest form of exploration in shallow

    depth; above 3 m deep the cost increases rapidly compared

    with boring. The main advantage is that soils and rocks can

    be exposed and examined insitu. This method shows

    changes in strata much more clearly than by boring. The pits

    are dug out either by local labour or by a small tractor

    mounted excavator. The plan size of a pits depends on

    method of excavation, but approximately 1.2 x 1.2 m and

    should be dug at distances 20m apart in either direction.

    Problem occurs in water bearing soils, particularly

    sands, and therefore the economies of shoring and pumping

    pits may outweigh the savings gained against specialist

    borings. In dry condition these pits are particularly valuable

    since they allow hand cut sample to be taken, thereby

    minimizing the disturbance of the sample and maximizing

    the condition for accurate testing. Deeper trial pits maybe

    used for investigation of rock fissures or to explore layer of

  • TECHNIQE IN PLANNING AND PRE-CONSTRUCTION OF ROAD WORKHighway Engineering C3010 / UNIT2

    weak rock which cannot be removed intact in normal boring

    operations. Such deep pits are costly to construct and would

    be used only a large scale exploration. Trial pits are the best

    method of exploring back filled areas and side overlain by

    variable natural deposit.

    b. Borings

    All boring should be should be spaced sufficiently

    closed together to prevent false deduction concerning the

    uniformity of horizontal strata. The deeps of boring will be

    determined by the type of loading involved but account must

    be taken of any slope in the strata and variation in their

    thickness. In particular, when boring through glacial

    deposits, care must be exercised to insure that borders are

    not mistaken for bedrock.

    There are three main factors which govern the depth

    of exploration:

    1. The depth to which the soil is to be significantly stressed.

    2. The depth to which weathering is likely to affect the soil.

    3. The depth at which impermeable strata occur.

    c. Wash Borings.

    The soil is loosened and removes from the bore hole

    by mean of a strong jet of water or drilling mud. The liquid is

    jetted through a steel tube which is work up and down the

    hole. The liquid disintegrates the soil and carries it up the

    annular space between the tube and casing. Wash boring as

  • TECHNIQE IN PLANNING AND PRE-CONSTRUCTION OF ROAD WORKHighway Engineering C3010 / UNIT2

    the advantage that the soil is not disturbed by blows of a tool

    or shell, but it is limited to soil which do not contain boulders

    or large gravels. Mud such as bentonite, allows boring to be

    carried out without linings is non-cohesive soils. The soil in it

    settled-out state can be dried and use for identification

    purposes.

    2.2 SURVEY WORK AND SETTING OUT

    2.2.1 Preliminary Survey

    The preliminary survey consist in running a accurate

    traverse line, usually called the Base Line along the route already

    recommended as a result of reconnaissance survey, in order to

    obtain sufficient data for final location. Similar traverses may also

    be run along the secondary routes, if any. The preliminary survey

    shall help gather all the physical information which might affect the

    final location of the highway. The traverse being an Open one,

    adjustment cannot be made as in the case of closed traverse so

    that in order to ensure some standard of accuracy, certain

    precaution especially in the measurement of angels and chaining,

    etc., are necessary.

    After establishing the Base Line, important topographical

    features may also be recorded. These features include swamps,

    lakes and any other features which affect the final location and

    design of the highway. All the information collected by preliminary

    survey work is used in preparing a map, often called the basic plan

    or Preliminary Survey Plan.

  • TECHNIQE IN PLANNING AND PRE-CONSTRUCTION OF ROAD WORKHighway Engineering C3010 / UNIT2

    The next step after recording all the available details on the

    basic plan is to locate the center line of the proposed highway on it.

    A number of trial lines are drawn on the plan, avoiding valuable

    property, obstruction and difficult areas such as water-logged

    areas, etc. Having thus selected the center-line on the plan, the

    next step consist in transferring on to the field.

    2.2.2 Setting Out

    The first task is to establish a Base Line from which the

    whole of the road can be set out. The position of this line must be

    clearly marked on-site so that it can be re-established at any time.

    Setting out was done by plotting the construction boundaries after

    being referred from the previous survey on Preliminary Survey Plan

    and Base Line. Wooden pact shall be placed at each reference

    point and can be easily seen.

  • TECHNIQE IN PLANNING AND PRE-CONSTRUCTION OF ROAD WORKHighway Engineering C3010 / UNIT2

    TEST YOUR UNDERSTANDING BEFORE YOU CONTINUE WITH THE NEXT INPUT

    1. State the two methods that are used in soil exploration.

    a. ________________________________

    b. ________________________________

    2. State the three main factors which govern the depth of exploration.

    a. _________________________________

    b. _________________________________

    c. _________________________________

    ACTIVITY 2 B

    Question 1

  • TECHNIQE IN PLANNING AND PRE-CONSTRUCTION OF ROAD WORKHighway Engineering C3010 / UNIT2

    1. a. Trial pits

    b. Borings

    2. There are three main factors which govern the depth of

    exploration:

    1. The depth to which the soil is to be significantly

    stressed.

    2. The depth to which weathering is likely to affect

    the soil.

    3. The depth at which impermeable strata occur.

    FEEDBACK ON ACTIVITY 2 B

    Answer

  • TECHNIQE IN PLANNING AND PRE-CONSTRUCTION OF ROAD WORKHighway Engineering C3010 / UNIT2

    1. What are the procedures in identifying the construction of a new road.

    2. Describe the following aspects: -

    a. Preliminary Survey.

    b. Setting Out

    3. Describe the Trial Pits of soil exploration.

    Question

  • TECHNIQE IN PLANNING AND PRE-CONSTRUCTION OF ROAD WORKHighway Engineering C3010 / UNIT2

    The procedures to identify a new road include:-

    2a. Preliminary Survey

    The preliminary survey consist in running a accurate

    traverse line, usually called the Base Line along the route already

    recommended as a result of reconnaissance survey, in order to

    obtain sufficient data for final location. Similar traverses may also

    be run along the secondary routes, if any. The preliminary survey

    shall help gather all the physical information which might affect the

    final location of the highway. The traverse being an Open one,

    adjustment cannot be made as in the case of closed traverse so

    that in order to ensure some standard of accuracy, certain

    precaution especially in the measurement of angels and chaining,

    etc., are necessary.

    After establishing the Base Line, important topographical

    features may also be recorded. These features include swamps,

    lakes and any other features which affect the final location and

    design of the highway. All the information collected by preliminary

    Answer

  • TECHNIQE IN PLANNING AND PRE-CONSTRUCTION OF ROAD WORKHighway Engineering C3010 / UNIT2

    survey work is used in preparing a map, often called the basic plan

    or Preliminary Survey Plan.

    The next step after recording all the available details on the

    basic plan is to locate the center line of the proposed highway on it.

    A number of trial lines are drawn on the plan, avoiding valuable

    property, obstruction and difficult areas such as water-logged

    areas, etc. Having thus selected the center-line on the plan, the

    next step consist in transferring on to the field.

    2b. Setting Out

    The first task is to establish a Base Line from which the

    whole of the road can be set out. The position of this line must be

    clearly marked on-site so that it can be re-established at any time.

    Setting out was done by plotting the construction boundaries after

    being referred from the previous survey on Preliminary Survey Plan

    and Base Line. Wooden pact shall be placed at each reference

    point and can be easily seen.

    .

    3. Trial pits

    This is the cheapest form of exploration in shallow depth;

    above 3 m deep the cost increases rapidly compared with boring.

    The main advantage is that soils and rocks can be exposed and

    examined insitu. This method shows changes in strata much more

    clearly than by boring. The pits are dug out either by local labour or

    by a small tractor mounted excavator. The plan size of a pits

    depends on method of excavation, but approximately 1.2 x 1.2 m

    and should be dug at distances 20m apart in either direction. Trial

  • TECHNIQE IN PLANNING AND PRE-CONSTRUCTION OF ROAD WORKHighway Engineering C3010 / UNIT2

    pits are the best method of exploring back filled areas and side

    overlain by variable natural deposit.