business needs in procurement and supply 2017/d2_march...d2/march 2017 diploma in procurement and...

3
D2/March 2017 Diploma in procurement and supply Business needs in procurement and supply Date Monday 6 March 2017 Time Start 14:00 End 17:00 Duraon 3 hours QUESTION PAPER INSTRUCTIONS FOR CANDIDATES This examinaon has FOUR compulsory quesons worth 25 marks each. 1. Do not open this queson paper unl instructed by the invigilator. 2. All answers must be wrien in the answer booklet provided. 3. All rough work and notes should be wrien in the answer booklet. QP04

Upload: others

Post on 07-Sep-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Business needs in procurement and supply 2017/D2_March...D2/March 2017 Diploma in procurement and supply Business needs in procurement and supply Date Monday 6 March 2017 Time Start

D2/March 2017

Diploma in procurement and supply

Business needs in procurement and supply

Date Monday 6 March 2017

Time Start 14:00 End 17:00 Duration 3 hours

QUESTION PAPERINSTRUCTIONS FOR CANDIDATES

This examination has FOUR compulsory questions worth 25 marks each.

1. Do not open this question paper until instructed by the invigilator.

2. All answers must be written in the answer booklet provided.

3. All rough work and notes should be written in the answer booklet.

QP04

Page 2: Business needs in procurement and supply 2017/D2_March...D2/March 2017 Diploma in procurement and supply Business needs in procurement and supply Date Monday 6 March 2017 Time Start

Page 3 of 8 D2 Exam Questions March 2017

QUESTIONS

You are advised to spend 45 minutes on each question.

Q1 (a) Outline FIVE purposes of financial budgets. (10 marks)

(b) Using examples, describe THREE reasons why the actual price of bought-in materials might be lower than the price shown in the purchasing budget. (15 marks)

Q2 (a) Explain THREE reasons for using clear specifications when procuring products or services. (9 marks)

(b) Describe TWO types of conformance specification, and explain an appropriate example of each type. (16 marks)

Q3 (a) Explain THREE areas where a supplier’s and a buyer’s terms may differ prior to the agreement of a contract. (15 marks)

(b) Explain the difference between ‘liquidated damages clauses’ and ‘penalty clauses’ in contracts. (10 marks)

Q4 Explain FIVE factors that a manufacturing company will take into account when deciding whether to make a component itself or whether to buy it from a supplier. (25 marks)

END OF QUESTION PAPER

Page 3: Business needs in procurement and supply 2017/D2_March...D2/March 2017 Diploma in procurement and supply Business needs in procurement and supply Date Monday 6 March 2017 Time Start

Page 8 of 8 D2 Exam Questions March 2017

PLEASE RETURN TO:

CIPS ASSESSMENT MANAGEMENT CENTRE

c/o LINNEY DIRECT, A2 GOODS IN

BELLAMY ROAD, MANSFIELD

NOTTINGHAMSHIRE NG18 4LN

UNITED KINGDOM

TEL: +44(0) 845 880 1188

FAX: +44(0) 845 880 1187

www.cips.org