burkina faso - basic education and capacity building support · pdf filesupport project...

19
Translated document AFRICAN DEVELOPMENT FUND BURKINA FASO BASIC EDUCATION AND CAPACITY BUILDING SUPPORT PROJECT (EDUCATION V) PROJECT COMPLETION REPORT (PCR) OSHD DEPARTMENT February 2014

Upload: phamnhan

Post on 20-Mar-2018

215 views

Category:

Documents


2 download

TRANSCRIPT

Translated document

AFRICAN DEVELOPMENT FUND

BURKINA FASO

BASIC EDUCATION AND CAPACITY BUILDING

SUPPORT PROJECT (EDUCATION V)

PROJECT COMPLETION REPORT

(PCR)

OSHD DEPARTMENT

February 2014

1

I BASIC DATA

A Report Data

Report Date Date of report: 12 December 2013

Mission date From : 22 August 2013

From : 16 September

To : 30 August 2013

To : 25 September 2013

B RESPONSIBLE BANK STAFF

Positions At Approval At Completion

Regional Director NA F. J. M. PERRAULT

Head of Country Office NA G. K. NZAU-MUTETA

Sector Director Z. EL BAKRI A. SOUCAT

Sector Manager J. E. PORGO B. SAVADOGO

Task Manager M. G. BAYEMI A.R. OUEDRAOGO

Alternate Task Manager NA NA

PCR Team Leader Alfred R. OUEDRAOGO

PCR Team Members

Pierre C. OUEDRAOGO, Marianick

DIABIRA, Adèle KERE, Zounoubaté

N’ZOMBIE, Issaka ADAMOU, Samba-

Diom Bâ

C Project data

Project Name: Basic Education and Capacity Building Support Project (Education V)

Project Code:

P-BF-IAO-005

Financing Instrument(s) number(s): Loan No. 2100150007112

Grant No. 2100155001954

Project Type: Investment Sector: Education

Country: Burkina Faso Environmental Categorization (1-3): II

Processing milestones

– Bank approved financing only

Key Events Disbursements and Closing Dates

Financing Source/Instrument 1: ADF

loan: UA 12,000,000

Financing Source/Instrument 1:

ADF loan: UA 12,000,000

Financing Source/Instrument 1:

ADF loan: UA 12,000,000

Date Approved: 16/7/2003 Cancelled amount: UA

1,008,028.72

Original disbursement deadline:

Date signed: 2/9/2003 Supplementary financing: NA Original closing date: 31/12/2009

Date of entry into force: 12/05/2005 Restructuring: NA Revised disbursement date: 30/10/

2013 that is 3.83 years

Date effective for first disbursement:

29/12/2006

Extensions: 2009, 2011, 2013 Revised closing date: 30/10/2013

PROJECT COMPLETION REPORT FOR PUBLIC SECTOR OPERATIONS (PCR)

2

Date of actual first disbursement:

13/03/2007

Financing Source/Instrument 2:

ADF Grant: UA 5 000 000

Financing Source/Instrument 2 :

ADF Grant: UA 5,000,000

Financing Source/Instrument 2:

Don ADF Grant : UA 5,000,000

Date approved: 16/07/2003 Cancelled amount: UA

2 399 660.71

Disbursement deadline: -

Date signed : 02/09/2003 Supplementary financing: NA Original closing date: 31/12/2009

Date of entry into force: 2/9/2003 Restructuring: NA Revised disbursement date : 30/10/

2013 that is 3.83 years

Date effective of first disbursement:

29/12/2006

Extensions: 2009, 2011, 2013 Revised closing date: 30/10/2013

Date of actual first disbursement:

13/3/2007

Financing source (UA): Disbursed

amount

(amount, UA) :

Percentage

disbursed (%):

Amount

disbursed (UA):

Percentage

undisbursed

(%):

Financing source/instrument 1:

ADF loan

12 000 000 91.60 10 991 971.28 8.40

Financing source/instrument 2:

ADF Grant

5 000 000 52.01 2 600 339.29 47.99

Government: Burkina Faso 2 194 411 91.86 2 858 961.30 8.14

Other NA NA NA NA

TOTAL 19 194 411 78.4 16 451271.87 21.6

Executing and implementing agency (ies): Ministries of Secondary and Higher Education (MESS)/Education

Project Execution Unit (BEPE) supervised by a Steering Committee set up by an inter-Ministerial order and

chaired by the Secretary-General of MESS.

D Management review and comments

Report reviewed by Name Date reviewed Comments

Head of Country Office G. K. NZAU-MUTETA 12 December 2013

Date approved

Regional Director F. J. M. PERRAULT … December 2013 Date approved

Sector Manager B. SAVADOGO 12 December 2013 Date approved

12/12/2013

Sector Director A. SOUCAT … December 2013 Date approved

3

II Project Performance Assessment

A Relevance

1. Relevance of Project Development Objective

Rating* Narrative Assessment

4 The Poverty Reduction Strategic Framework (PRSF) adopted in 2000 identified education as one of the priority

sectors with a significant impact on poverty reduction. In consultation with the technical and financial partners

(TFPs), Burkina Faso developed a Ten-year Basic Education Development Plan (PDDEB 2000/2010). Education V

Project is in response to a request submitted to the Bank for support for the implementation of PDDEB and the

Secondary Education Development Programme. The project is in compliance with the guidelines of ADF IX,

particularly the focusing of programmed activities on the following main areas: policy reform, primary education,

adult literacy and the promotion of technical education and vocational training. As regards of investment, the

project falls within a programme approach and helps to boost the contribution of the other TFPs to the

development of education in Burkina Faso. The project is also in conformity with the Millennium Development

Goals and the orientations of the Bank’s CSP (2002-2004) for Burkina Faso, which highlights poverty reduction

and human resource development.

At closure, the project met most of the following constraints identified during evaluation:

i) increase in resources and access to education and literacy;

ii) reduced disparities access to education; and

iii) Improvement of the sector coordination, planning and management capacities of the various Ministries involved

in education.

* For all ratings in the PCR, use the following scale: 4 (Highly satisfactory), 3 (Satisfactory), 2 (Unsatisfactory), 1

(Highly unsatisfactory)

2. Relevance of Project Design

Rating* Narrative Assessment (max 250 words)

4 A request was submitted to the Bank concerning the shortage of school and administrative infrastructure in

some areas (outskirts of Ouagadougou and Bobo-Dioulasso) and remote provinces of the country, as well

as the need to strengthen professional and technical studies.

Taking into account the constraints of Burkinabe education system, the project is part of a process already

instituted by the other development partners to implement the PDDEB and the Poverty Reduction Strategic

Framework (PRSF) which defines basic education as a priority, without neglecting the other levels of

education. By selecting these intervention areas and activities, the project is designed as a complementary

and coordinated contribution to the action of other TFPs involved in the PDDEB.

The project idea and planned activities were discussed and validated by government authorities, technical

and financial partners, teachers, students and parents of students, civil society and private sector

organizations, as well as education experts.

The project was placed under the supervision of MESS and covers activities of three other Ministries. This

organization showed some weaknesses in the implementation phase of the project with the lack of

involvement of MENA, which is the primary beneficiary of the outputs. This weakness was remedied by a

close monitoring mechanism established during the last year of the project.

Overall, the design is considered appropriate to achieve the outcomes.

4

3 Lessons learned related to relevance

B Effectiveness

1. Progress towards the project’s development objective (project purpose)

Comments

Provide a brief description of the Project (components) and the context in which it was designed and implemented.

State the project development objective (usually the project purpose as set out in the RLF) and assess progress.

Unanticipated outcomes should also be accounted for, as well as specific reference of gender equality in the project.

Indicative max length: 400 words.

The sector goal of the project is to contribute to the development of education and training so as to achieve the Millennium

Development Goals. The specific objectives of the project are as follows: (i) improve access and quality of basic education

in some disadvantaged areas, and (ii) build capacities and enhance coordination of the education and training sector.

COMPONENT 1: Increased Access and Improvement of the Quality of Basic Education: This component seeks to help

increase the intake capacities of basic education and the literacy rate by constructing schools equipped with furniture

(primary and secondary) and literacy schools (CPAF), as well as conducting literacy awareness campaigns (particularly for

girls). Prior to the project, children had access neither to schools nor desks for education. The project has also improved the

quality of education by supplying teaching aids. Overall, 1980 students have been admitted in the first cycle of secondary

education in nine departments without secondary schools. In all, 479 classrooms were built and equipped (desks, offices,

cupboards, boreholes or connection to drinking water network) in the project areas.

COMPONENT 2: Capacity building: This component helped to build the institutional capacity of the main Ministries in

charge of education and training by providing them with computers and office automation, and training MESS senior

administrative staff, science teachers and regional directorate teams. Prevention campaigns were conducted against high

prevalence diseases, especially HIV/AIDS, malaria and tuberculosis. A study was conducted on the operation and impact

of existing rural promotion centres.

COMPONENT 3: Project management: This component helped to finance the refurbishment of BEPE premises and

replacement of some computer and office automation equipment, as well as the operating costs and means of transport

(monitoring of activities).

Key Issues (max 5; add rows as needed Lessons Target Audience

Project management structure General education and vocational and technical

education are under the supervisory authority of

several Ministries. This situation is not conducive for

a holistic vision of the education system because it

reduces means and resources. The project was placed

under the supervisory authority of MESS, whereas

most (80%) of the project’s outputs fall within the

supervisory authority of MENA.

Bank/Borrower

Limit of project approach compared to

programme support or sector budget

support

The Bank will, in compliance with the Paris

Declaration and the Accra Forum on Aid

Effectiveness, continue to support reforms aimed at

strengthening public finance management systems,

procurement and auditing. This requires the use of

country systems in accordance with objectives and

conditionalities on reform priorities and

programmes.

Bank/Borrower

Multi-disciplinary BEPE experts Lack of a monitoring and evaluation specialist.

Implementation would have been more efficient if

the project had a specialist with this profile.

Bank/Borrower

5

2. Outcome Reporting

3. O

u

t

c

o

m

e

I

n

d

i

c

a

t

o

r

s

Baseline

Value (year) (A)

Most

Recent

Value (B)

End

target (C)

(expected

value at

project

completion)

Progress

towards

realization of

target (%

realized) [(B-

A)/(C-A)]

Narrative Assessment

(indicative max length:

50 words per outcome)

Core Sector

Indicator

(Yes/No)

Outcome 1: Access to and quality of basic education in some disadvantaged areas has been improved

1.1 Increase in the

number of pupils in

the priority

provinces of Soum,

Séno and

Namentenga

1.2 Increase in the

number of pupils in

primary education in

Ouagadougou

(Kadiogo) and

Bobo-Dioulasso

(Houet).

0

0

3432

1612

3744

1612

91.66%, 47 %

of whom are

girls

100%, 51% of

whom are girls

Objective virtually met.

The unsuccessful

procurement hampered

complete success.

Objective met.

Yes

1.3 Increase in the

number of students in the

first cycle of secondary

education in nine

departments without

CEG.

0 1440 1620 89%, 47% of

whom are girls

Objective partially met

because of unsuccessful

procurement.

Yes

Outcome 2: The capacity of Ministries in charge of the basic education sector is strengthened.

2.1 Number of Ministries

in charge of basic

education producing

national and provincial

statistics yearbook as well

scorecards and

management indicators.

0

4

4

100%

Objective met. Yes

2.2 Percentage of schools

benefiting from

implementation of

secondary school projects.

0 33% 100 % 55% Objective partially met.

Government opted for

gradual implementation.

Yes

6

2.3 Number of production

units transferred to private

operators.

0 0 3 0% Not achieved because of

change of priority. The

transfer process has

started pending

identification of units,

selection of private

operators and signing of

agreements.

Yes

Rating (See IPR

methodology)*

3 Access and quality of basic education in some disadvantaged areas has been improved, as well as the

capacity of Ministries in charge of the basic education sector.

Based on activities carried out compared to projection, the overall implementation rate was slightly

above 90%. The infrastructure helped to increase intake capacity and provided a conducive working

and learning environment for teachers, students and learners. The implementation time frame

generally exceeds the expected time limit.

3 Output Reporting

Output Indicators (as

specified in RFL: add

rows as needed)

Most

Recent

Value

(A)

End target (B) (expected value at

project completion)

Progress

towards target (% realized)

(A/B)

Narrative Assessment

(indicative max length: 50

words per output)

Core Sector

Indicator

(Yes/No)

Output1: Increase in primary education supply in towns (Ouagadougou, Bobo-Dioulasso) and provinces (Soum, Séno

and Namentenga) covered by the project.

1.1 Number of

classrooms constructed

and equipped in the

project areas

72 77 94% Objective almost met.

The shortfall is due to

unsuccessful procurement

Yes.

1.2 Number of boreholes

drilled for students and

teachers

0 101 87% Objective almost met.

The shortfall is due to

poorly constructed

boreholes.

Yes.

Output 2: Overall level of literacy improved

2.1 Number of learners

received after evaluation

of the literacy level in

2008/2009

42 295

47 789

88.5 %, 53%

of whom are

women

Objective almost met

despite the suspension of

financing to FONAENF.

Yes.

2.2 Number of learners

received after evaluation

of the literacy level in

2011/2012.

50 359 53 913 87.2%, 55% of

whom are

women

Objective almost met

despite the suspension of

financing to FONAENF.

Yes.

7

Output 3: Building management and planning capacity of central and decentralized education services.

3.1 Number of training

seminars organized for

teams in charge of

management and school

life.

27 64 42.18% Objective below average

due to suspension of

disbursements.

Yes.

Output 4: CPR programmes have been readapted.

4.1 Number of training

seminars organized on

the skill-based modular

concept.

0 8 0% Not achieved due to the

suspension of

disbursements.

Yes.

Output 5: Skills of science teachers have been improved

5.1 Number of science

teachers trained

657 1000 66%, 42% of

whom are

women

Objective met above

average. Activity not

completely carried out

due to the suspension of

disbursements.

Yes

Output 6: Fight against high prevalence diseases, STIs and tobacco abuse has been intensified

6.1 Number of students

whose awareness is

raised on high prevalence

diseases and tobacco

abuse

105 000 200 000 52.5%, 55% of

whom are

women

Objective partially met.

Activity not completely

carried out due to the

suspension of

disbursements.

Yes

6.2 Number of teachers

whose awareness is

raised on the HIV/AIDS

pandemic, malaria,

tuberculosis and tobacco

abuse

1 585 5 000 31.7%, 60% of

whom are

women

Objective not met due to

the suspension of

disbursements.

Yes

8

Rating (See IPR

methodology)* Narrative Assessment

3 Most of the activities on training, literacy and more generally capacity building of structures in

charge of education, technical training and vocational training were carried out. An evaluation

report was prepared. Studies and other reports are available and reflect what was envisaged in the

evaluation report. The Ministries in charge of basic education have a statistical production

mechanism.

In light of the activities carried out compared to those proposed, the overall implementation rate

stands at 90%. This implementation level is due to the suspension of disbursements that made it

impossible to carry out activities financed by the revolving capital (training, awareness campaigns,

etc.). Furthermore, supplier deficiencies led to the termination of some contracts (mechanic kits,

computer hardware).

The drilling of boreholes or connection of schools (22) to water supply enabled teachers and

students to prevent water-borne diseases, improve their hygiene conditions, and care for vegetable

gardens and trees.

The construction and equipping of classrooms helped to improve the supply and quality of

teaching by offering an ideal working environment to teachers and students. Distances covered by

the children and teachers have been effectively reduced.

4. Development Objective (DO) Rating

DO rating (from IPR

update )*

Narrative Assessment

3 The sector goal of the project is to contribute to the development of education and training so as to achieve the

Millennium Development Goals. Despite considerable delays at project start-up, the level of project execution

and expected outcomes clearly demonstrate that most of the outputs and outcomes were satisfactorily achieved.

The Government was informed of activities pending implementation, and undertook to complete the unfinished

activities. This will increase and strengthen the outcomes already achieved.

By helping to improve the level of literacy, education and training, the project has contributed to enhancing and

boosting economic growth required for poverty reduction. The building of primary school classrooms in the

three priority provinces and in urban outskirts has offered the most underprivileged people access to basic

education.

The project lays particular emphasis on women and young girls through different types of training. However,

the creation of income-generating activities was not mentioned.

The construction of school infrastructures helped to create jobs which had a positive impact on poverty.

The outcomes and outputs are rated as satisfactory.

9

5. Beneficiaries (add rows as needed)

Actual (A) Planned (B) Progress towards target (%

realized A/B) % of women Category (e.g. farmers,

students)

92 654 101 702 91.10% 54 % Learners (literacy)

10 10 100% 40 % Staffs from the Ministries

concerned were trained.

657 1 000 66% 33 % Science teachers trained

85 80 106,25% 55 % Peer educators trained

6. Gender Equality

Assessment of gender performance analysis in the arrangement(indicative max length: 250 words)

The women trained, representing approximately 45.5% or slightly below average, have strengthened their technical skills. This

capacity building offers them more opportunity to qualify for better managerial jobs at both central and decentralized levels. To

sustain this process, however, the level of representation of women in decision-making bodies of the administration should be

increased and improved.

7. Unanticipated or additional outcomes

Type (e.g. gender,

climate change,

social , other)

Positive or

negative

Impact on project

(High, Medium, Low)

The International Court of Justice at The Hague issued a ruling on the

border dispute between Burkina Faso and Niger that modified the

territory of Burkina Faso. Following this decision, two schools built

before the decision of the Court are now on Niger territory.

Social and political Positive Low

Creation of temporary jobs during the works Economic and

social

Positive Medium

Hygiene improved through drinking water supply, and the boreholes

in primary schools and CEG are also beneficial to local residents,

especially women.

Environment Positive High

8. Lessons learned related to effectiveness

Key issues(5 max; add rows as needed ) Lessons learned Target Audience

Improvement of literacy

The financing method of this activity hampered its

implementation. The disbursement method of

resources allocated to literacy also hampered the use

of funds. Attempts by FONAENF to submit a third

plan of action were unfruitful because of the

suspension of disbursements and the time left for

closing the project. The expected objectives were not

fully met for these reasons.

Learners, youths

and women

Reduction of gender and location disparities The project outputs helped to reduce gender and

location disparities (rural, semi-urban and urban) in

the project areas.

The proportion of girls in functional schools in the

project area increased. This improvement is,

however, slightly below 50%.

Male and female

students

10

Training adapted to needs The report on all the training confirms the relevance

of the training offered by the project. A little more

flexibility in the choice of training would have

achieved better results.

Ministries

concerned

Close monitoring Considering the start-up difficulties, the location of

the project officer at the Bank Headquarters during

the early years of the project did not allow for

effective monitoring of project implementation.

Bank

Visibility of project outputs The lack of a strategy and resources for

communication activities did not allow for project

visibility.

Government

C Efficiency

1. Timeliness

Planned Project Duration – year (A)

(as per PAR) Actual Implementation Rate –

year (B) (from effectiveness for 1st

disbursement)

Ratio of planned and actual

implementation time (A/B)

Rating*

5 years–31 December 2009 7 and one half years -30 June 2013 66.6% 2

Narrative Assessment

The project was approved on 16 July 2003. The deadline for the last disbursement initially set at 31 December 2009 was

extended to 30 December 2011, then to 31 December 2012, and finally to 30 October 2013. The operational activities of the

project began at end of 2006. The Bank’s first disbursement (ADF Loan and ADF Grant) was made in March 2007.

The project start-up was hampered and delayed by difficulties in recruiting the Project Manager, the provision of the national

counterpart contribution, the quality of procurement files and the relatively long processing time of files, especially during the

early years of the project.

This situation was compounded by: (i) the late establishment of BEPE and release of the initial revolving capital; (ii) the

significant decline in UA/CFAF parity resulting in considerable drop in value that required resizing of activities (reduction of

works, goods and services) in July 2007 leading to the counterpart taking measures to mitigate the loss in value; and (iii)

frequent changes of school and borehole sites (unsuccessful drilling), in particular, extended the implementation time frames.

The suspension of disbursements from December 2011 to the end of the project had negative consequences on effectiveness and

even efficiency, leading to extensions of project implementation time frames.

2. Resource Use Efficiency

Median % physical implementation

of RLF outputs financed by all

financiers (A) (see II.B.3)

Commitment Rate (%) (B) (see

Table 1.C – Total commitment rate

of all financiers)

Ratio of the median percentage

physical implementation and

commitment rate (A/B)

Rating*

54.90% 90.33% 60.7% 2

Narrative Assessment

The places offered in basic education have increased access by people in the most disadvantaged provinces and in the outskirts of

Ouagadougou and Bobo-Dioulasso to education, training and literacy. The new buildings and equipment of infrastructure have

improved admission conditions as well as the work of students and teachers, thereby leading to better academic performance in the

short and medium- term.

Non-implementation of some activities in vocational and technical training, such as training seminars in the skills-based modular

concept and practical training in scientific disciplines will not fallow for better quality of teaching in this area.

Literacy for youths and women, community communication and the production of awareness-raising brochures have helped to

reinforce learning and the relevance of education in rural areas.

Under-consumption of the grant is largely due to the specificity of FONANEF which operates on the basis of advances received

from contributors. This provision is inconsistent with the Bank’s rules.

11

Overall, there is some consistency between the mobilized/used resources, the project objectives and the expected outcomes. Most

of the project objectives have been achieved.

3. Cost-benefit Analysis

Economic Rate of Return (at approval) Updated Economic Rate of Return

(at completion)

Rating*

NA NA NA

Narrative Assessment

A cost-benefit analysis was not conducted to assess the project efficiency.

4. Implementation Progress (IP)

IP Rating

(derived from

IPR update) *

Narrative Comments (commenting specifically on those IP items that were rated Unsatisfactory or

Highly Unsatisfactory, as per last IPR.

3 Based on the outcomes, the physical implementation rate is estimated at 90%. The disbursement rates stand

at 91.60% and 52.01% for the Loan and Grant respectively. Up to 91.86% of the counterpart funds was

disbursed. The commitment rates are as follows: Loan 93.07%, Grant 52.01% and Government 97.86%.

The commitment rate for the entire project is 90.33%.

The implementation level of component 1 (90%) is satisfactory in relation to the expectations. The slight

gap is partly due to shortcomings of some businesses and monitoring firms that led to the termination of

contracts, as well as to difficulties in disbursement of funds to FONAENF for literacy activities.

The implementation level of component 2 (90%) is satisfactory, and could have been higher. Suspension of

disbursements did not allow for implementation of activities financed by the revolving capital (training,

awareness campaigns, literacy, etc.). The deficiencies of suppliers also led to the termination of some

contracts (mechanical kits, competitive hardware).

The construction works of primary school classrooms, latrines, colleges and boreholes have been

completed. All the equipment was purchased. Training for senior staff in Ministries and teachers has been

partially conducted. Component 3 has been fully and satisfactorily implemented.

Delays in release of the counterpart funds affected the implementation of project activities, particularly the

works. Thereafter, its release rate was satisfactory.

Following the Bank’s internal audit, the 2009, 2010 and 2011 audit reports had to be redone due to

procedural flaws in the recruitment of the audit firm. Disbursements were therefore suspended (December

2011 until the end of the project). The situation has now been restored and is satisfactory. All audit reports

have been redone and approved by the Bank.

5. Lessons learned related to efficiency

Key Issues (max 5; add rows as needed) Lessons Learned Target Audience

Maximum use of resources Given the delays in project start-up, other

partners constructed school facilities on some

sites initially identified for the project, thereby

leading to frequent changes of sites (schools,

colleges) or infrastructure congestion (latrines).

This occurred about once in six cases. Proper

planning and greater flexibility would have

prevented such a situation.

Government

12

Implementation time frame and arrangements

In most cases, the contract execution time

frames are not respected.

Furthermore, implementation by a civil society

organization (RCS NGO) was not efficient. The

same activity carried out by governmental

structures was more effective than the activity

carried out by the NGO.

Government/Bank

D Sustainability

1. Financial Sustainability

Rating* Narrative Assessment

3 The project, which was approved on 16 July 2003, officially started up in January 2007. The four (4) years delay

resulted in a loss of ADF resources because of significant fluctuation of Unit of Account (UA) rates.

All the infrastructure built under the project is allocated to the relevant Ministries (MENA and MESS), which

bear the recurrent costs. The construction of education infrastructure requires financial resources for basic

servicing and maintenance. In addition to local initiatives by the education community (especially parents of

students), the Government (MENA) plans to provide schools with funds to meet the related expenditures.

The project activities have helped to establish mechanisms to ensure financial sustainability for consolidation of

outputs.

2. Institutional Sustainability and Capacity Building

Rating* Narrative Assessment

3 Under the "Capacity Building" component, the following training courses were conducted: (i) the training of 10

administrative senior staff, (ii) management teams of MESS regional directorates for the implementation of

institutional and school life projects, (iii) programme on the prevention of HIV and high prevalence diseases, and

(iv) scientific disciplines in teaching activities. The training of senior staff was included in the strategic plan for

MENA capacity building.

The suspension of disbursements of grant did not allow for implementation of all the planned activities, such as

the widespread implementation of institutional and school life projects, training, literacy, etc.

In all, 657 out of 1,000 teachers in programmed scientific disciplines were trained. The training sessions: (i)

contributed to the initial and continued training of teachers of physics, mathematics, and life and natural sciences,

(ii) improved formative assessment, (iii) promoted interdisciplinary activities, and (iv) explored the teaching and

learning of physics, mathematics, and life and natural sciences using the skills-based approach.

Overall, the institutional capacity building activities were carried out satisfactorily. The systems and human

capacity of the Borrower were increased to ensure continuous flow of project benefits.

3. Ownership and Sustainability of Partnerships

Rating* Narrative Assessment

3 The outcomes (constructions) were defined in partnership with the relevant Ministries on the basis of the

expressed needs.

In most cases, Parent/Teachers’ Associations were associated at certain levels, from the design to the

implementation of activities.

Since the project fell within PDDEB, the interventions of other basic education TFPs were considered. BEPE

participation in consultation meetings with the Government and other TFPs provided information on PDDEB

implementation. The project approach in this project isolates it from other TFPs that provide funds through a

special treasury allocation based on a programme approach.

13

Difficulties encountered in financing the master plan for vocational and technical education and the

implementation of ensuing measures led Government to implement the plan with the support of other TFPs; this

shows complementarity of the activities.

Project activities were considered effective in involving most of the stakeholders. Ownership among beneficiaries

is progressive. Partnerships have been established with the stakeholders, and are considered sufficient to ensure

preservation and proper management of project outputs.

4. Environmental and Social Sustainability

Rating* Narrative Assessment

3 Project activities (Category II) have no negative impact on the environment. The construction of infrastructures is

usually accompanied by tree planting in schools and by the use of solar energy (CEG). In addition, boreholes and

drinking water supply to schools allow for regular watering and growth of planted trees. The awareness raising of

communities on the environment will contribute positively to its protection. During site visits, there was no cause

for concern about the sound management of the environment.

Social sustainability seems to be guaranteed by the management of infrastructures by the beneficiaries.

Poverty of the people in the project areas is a medium risk in effective maintenance of the infrastructure and

equipment.

Institutional capacity and funding are considered sufficient to ensure environmental and social sustainability of

the operation.

5. Lessons learned related to sustainability

Key Issues(max 5; add rows as needed ) Lessons Learned Target Audience

Standard plan and models of education infrastructure Adapt building plans to the context and the

natural environment.

Government/municip

alities

Involvement and participation of the people and

municipalities

The beneficiary population and municipalities

concerned are the best guarantors of

sustainability of the outputs. Their role and

responsibility will be clearly identified and

defined.

The neighbouring communities and residents do

not always recognize the boundaries of the

school land, and this result in trespassing on

school grounds.

Bank /Government

Financial and accounting management

Delays in signing the works and supplies

contracts, as well as implementation time

frames that are extended beyond the closing

date rendered some expenses ineligible for Bank

financing.

Proper financial implementation requires the

preparation of an administrative, accounting and

financial procedures manual as well as the

installation of a powerful accounting software

upon project start-up.

Bank/Government

14

III Performance of Stakeholders

A Relevance

1. Bank Performance

Rating* Narrative assessment by the Borrower on the Bank’s performance as well as other aspects of the project

(both quantitative and qualitative). See guidance note on issues to cover.

3 The processing time of files received at the Bank was considered relatively long (2-4 months on average). This

lasted until end-2011.

The establishment of a new emergency system in January 2013 resulted in more expeditious processing of files

(less than 10 days on average). Availability of the Bank’s project managers in the field helped to meet the

Government’s requests. In addition, there was close Bank monitoring. Over the past two years, 3-4 supervisions

undertaken on average per year. Besides, the first mission did not always include all the required experts to solve

the problems.

The last extension request was not granted in a timely manner for continuation and realistic programming of

activities.

The Bank should pay special attention and ensure compliance with time limits for execution of contracts signed

during the six months preceding the closing date of projects (late signing of some contracts).

Bank performance may be considered satisfactory despite the difficulties noted at certain moments of project

execution.

Use national procurement procedures and speed up the processing of files to reduce reaction time to project requests.

Key Issues (related to Bank performance, max 5;add rows as

needed) Lessons Learned

Close Bank monitoring and supervision

Bank decentralization to Burkina Faso as from 2007, revision

of its procurement rules and procedures in 2008, and

implementation of the delegation of authority matrix in 2009

for procurements helped to improve the effectiveness of the

project’s fiduciary functions.

2. Borrower Performance

Rating* Narrative assessment on the Borrower’s performance to be inserted by the Bank (both quantitative and

qualitative, depending on the available information) See guidance note on issues to cover

2 Project start-up was delayed for about 4 years (between signature and first disbursement). Lack of familiarity or

non-compliance with Bank rules and procedures resulted in deadlock at several levels such as works, site

monitoring, audit and complaints. The regular production of quarterly progress reports did not provide solutions,

especially during the early years of the project. The Borrower complied with most of the social and environmental

protection requirements. The late and random release of counterpart funds helped to slow down the works. The

procurement plan was not respected.

The lack of capacity of construction companies was frequently raised. The Government inadequately

implemented the regulations in force concerning non-compliance with implementation time frames or fraudulent

practices (furniture contract).

The Government did not set up an internal monitoring and assessment system in BEPE to inform and alert the

team on the level of project outcomes. Most (3/4) of the recommendations made by the supervisory or audit

mission have been implemented. Some shortcomings in contract management made project implementation

(audit, works, and goods) more complicated.

15

Key Issues (related to Borrower performance, max 5; add

rows as needed) Lessons Learned

Capacity building

Capacity building of the project implementation team is

essential for effective and efficient implementation of projects.

This was not the case due to suspension of disbursements.

Discussions on ways of strengthening the capacity of local

contractors and service providers should be organized.

Monitoring and supervision Close monitoring of files and their diligent processing at all

levels are prerequisite for proper project implementation.

The institution of permanent dialogue between the

management units, donors, Government, contractors and

beneficiaries upon project start-up allows for proper

coordination and effective project implementation.

Application of instruments in force The Government submitted a request for the lifting of delay

penalties on construction companies. The request was rejected,

and the penalties rigorously enforced.

3. Performance of other Stakeholders

Rating* Narrative assessment on the performance of other stakeholders, including co-financiers, contractors and

service providers. See guidance note on issues to cover.

2 Companies awarded contracts for the supply of goods (equipment, furniture and materials) supplied goods

corresponding to the descriptions and of acceptable quality. There were delays in delivery, particularly for works

and equipment due to the weak capacity of the companies and difficulties in accessing some parts of the country,

especially during the rainy season.

Firms and consultants were qualified to carry out the mission assigned them. The quality of technical assistance

and some studies was considered satisfactory on the whole. However, works monitoring and control encountered

many difficulties. Most contractors had financial and organizational weaknesses, which resulted in non-

compliance with contractual deadlines; in some cases (1/7), the procedure was relaunched, resulting in delays.

Close control of work sites would have helped to avoid delays and poor execution of certain works. Irregular

monitoring resulted in some works being redone. The NGO “Reseau des communications sociales” (RCS), that

was recruited, was not effective in raising awareness on the education of children in the underprivileged

provinces.

Parents/Teachers’ Associations expressed interest in project activities, particularly in monitoring infrastructure

equipment.

Key Issues (related to the

performance of other stakeholders,

max 5; add rows as needed)

Lessons Learned (max 5) Target Audience (for

lessons learned)

Increased involvement by

municipalities

Burkina Faso has opted for territorial decentralization. A sub-

sector like basic education has been placed under the

management of councils. Appropriate participation and

involvement of municipalities would have helped to produce

more positive outcomes.

Better partnership is required for maintenance and minor

infrastructure repairs.

Government/Bank

16

IV Summary of key lessons learned and recommendations

1. Key lessons learned

Key Issues(max 5; add rows as

needed) Key Lessons Learned Target Audience

Quality at entry and

implementation of activities

Better selection of activities prevents dispersal of activities and

work sites with many small contracts in several areas. This

would have allowed for achievement of better outcomes.

Shortcomings in the quality of files (procurement,

disbursements, and audit reports) by the Borrower and long

processing times by the Borrower and the Bank had a negative

impact on the achievement of objectives. There is need for

national capacity building for use, at very short notice, of the

country’s fiduciary system in line with the Paris Declaration.

Bank/Government

Procurement

Use, as much as possible, of national rules and procedures

(national procurements) better mastered by national

stakeholders.

There is need to increase the average size of contracts. Focus on

specific areas with fewer activities but larger size is

recommended.

Bank decentralization to Burkina Faso as from 2007, revision of

its procurement rules and procedures in 2008 and

implementation of a delegation of authority matrix in 2009 for

procurements helped to improve the efficiency of the project’s

fiduciary functions.

Bank/Government

Disbursement Agree on best disbursement methods adapted to the country’s

context and realities. A case in point is the low disbursement to

FONAENF. Since the methods are standard, the Government

should clearly define its specific expectations at appraisal and

negotiation.

Bank

Financial and accounting

management

Since the closing audit had to be conducted after 30 September

2013, the project was faced with the need to keep staff

necessary to carry out that mission although ADF funds could

not be obtained after 30 September 2013. This constraint should

be considered in future.

Government

Monitoring and supervision As regards high risk projects, provide for a close monitoring

mechanism and means involving key stakeholders (civil society

organizations).

Bank/Government

Local ownership Greater empowerment of direct beneficiaries (communities and

municipalities) in project implementation.

Government/

municipalities:

beneficiaries’

associations

17

2. Key Recommendations (with particular emphasis on ensuing sustainability of project benefits)

Key Issues (max 10; add rows as needed) Key Recommendation Responsible Deadline

Planning quality and quality at entry

Reduce time frames for effectiveness

of projects.

Government/ Bank Ongoing

Capacities of project implementation team

Strengthen the recruitment process

so as to employ people with proven

expertise and experience within the

required time limit.

Government

Ongoing

Strengthening of high-level permanent dialogue Revitalize dialogue between

management units, the Bank,

Government, contractors, other TFPs

and beneficiaries at project start-up

to ensure better coordination and

effective project implementation.

Government/

Bank/Other TFPs

Ongoing

Involvement of stakeholders concerned and local

management

Set up a framework to facilitate

participation of the civil society,

including Parents/Teachers’

Associations, in monitoring activities

that guarantee better ownership and

implementation of the activities.

Government,

Bank, and civil

society

organizations

Ongoing

Close monitoring and diligent processing of files Diligent processing of files at all

levels for proper project

implementation.

Make efforts to reduce the time

frames for approval of procurement

files.

Government

Bank

Ongoing

Technical and financial ability of national contractors Ensure stricter criteria for capacity

of contractors so as to make them

more realistic in terms of the

economic environment of the

Borrower. This could ensure better

quality work and compliance with

execution deadlines.

Government

Ongoing

Sustainability of outputs

Obtain from Government assurance

(budget estimate) that measures will

be taken to finalize the routine

maintenance and servicing strategy

for the infrastructures under

construction.

Government

Ongoing

Financial and accounting management Require, at project start-up, the

preparation of an administrative,

accounting and financial procedures

manual and an efficient accounting

software for proper financial

implementation.

Bank Ongoing

18

V Overall PCR Rating

Dimensions and criteria Rating*

DIMENSION A : RELEVANCE 4

Relevance of the programme development objective (II.A.1) 4

Relevance of project design (II.A.2) 4

DIMENSION B : EFFECTIVENESS 3

Development Objective (DO) (II.B.4) 3

DIMENSION C : EFFICIENCY 2.33

Timeliness (II.C.1) 2

Resource use efficiency (II.C.2) 2

Cost-benefit analysis (II.C.3) NA

Implementation Progress (IP) (II.C.4) 3

DIMENSION D: SUSTAINABILITY 3

Financial sustainability (II.D.1) 3

Institutional sustainability and strengthening of capacities (II.D.2) 3

Ownership and sustainability of partners (II.D.3) 3

Environmental and financial sustainability (II.D.4) 3

DIMENSIONS AVERAGE 3.08

OVERALL PROJECT COMPLETION RATING S

VI Acronyms and Abbreviations

Acronyms Description

AfDB African Development Bank

BEPE Education Project Execution Unit

CAST Special Treasury Allocation Account

CEG Secondary Schools

CPAF Continuing Literacy Centre

CSP Country Strategy Paper

DECF Directorate of Schools and Training Centres

HIV/AIDS Human Immuno-deficiency Virus/Acquired Immuno-Deficiency Syndrome

MASA Ministry of Agriculture and Food Security

MENA Ministry of National Education and Literacy

MESS Ministry of Secondary and Higher Education

MJEFP Ministry of Youth, Employment and Vocational Training

NGO Non-Governmental Organization

PAEN National Education Support Project

PRSF Poverty Reduction Strategic Framework

TFP Technical and Financial Partners

UA Unit of Account