TE EPC. Bulding 245 schedule update. LIU Booster Meeting 13-09-2012 Serge Pittet, Fulvio Boattini TE-EPC. Building 245 Position. TE EPC. France. Limit for edification. France-Swiss border. Switzerland. Building 245 Preliminary D esign. TE EPC. HVAC room at ground floor - PowerPoint PPT Presentation

TRANSCRIPT

Bulding 245 schedule update

LIU Booster Meeting 13-09-2012Serge Pittet, Fulvio Boattini

TE-EPC

TE EPC

Building 245 Position

13/09/2011 TE-EPC - Serge Pittet, Fulvio Boattini 2

TE EPC

France-Swiss border

Limit for edification

France

Switzerland

Building 245 Preliminary Design

13/09/2011 TE-EPC - Serge Pittet, Fulvio Boattini 3

TE EPC

Input Transformers

Cooling towers

HVAC room at ground floorControl rooms at first floor

Storage capacitorsMain entrance

Converter building

MPSB Time Schedule

13/09/2011 TE-EPC - Serge Pittet, Fulvio Boattini 4

TE EPC

physics LS1 physics LS2 physics

2012 2013 2014 2015 2016 2017 2018 2019

26 May 2016Building ReadyNo ressources

Services Integration(EL, CV,..)

GS/SE studies and procurement

Building construction

Cooling installati

on

Air conditioning and cooling

pipes installation

17 October 201320 March 2014 26 March 2015

FCLV cabinets installation.Lights and

other services

18kV cabinets

installation

Cooling and Conditioning operating

Lights and electrical cabinets installed

Overhead Crane installed

Fire alarm system

installation

Fire alarm system installation

14 April 2017Start

Commissioning on dummy load

MPSB Time Schedule

13/09/2011 TE-EPC - Serge Pittet, Fulvio Boattini 5

TE EPC

physics LS1 physics LS2 physics

2012 2013 2014 2015 2016 2017 2018 2019

26 May 2016Building ReadyNo ressources

Services Integration(EL, CV,..)

GS/SE studies and procurement

Building construction

Power converterDesign & specification

Market Survey& Call for tender

Power converterDesign

(supplier)

Power converterconstruction

Power converter

Installation and cold

commissioning

Systemcommissioning

on PSB magnets

17 October 201320 March 2014 26 March 2015

FC

25 August 201620 June 2014FC

14 April 2017Start

Commissioning on dummy load

Power converter

commissioning on test

magnets

MPSB Time Schedule 2018

13/09/2011 TE-EPC - Serge Pittet, Fulvio Boattini 6

TE EPC

LS2 2018

Jan Feb Mar Apr May June July Aug Sept Oct Nov Dec

System Ready and Debugged

Preliminary test of 1 MPS converter on half magnets string:4 Weeks

Testing on spare magnets

Tests of 1 MPS + 1 Trim on half magnet string:4 weeks

Commissioning testing of all converters:(8 Weeks)

Testing on spare magnets

Is this slot feasible?

Of the utmost importance

MPSB Time Schedule: Building constructionTE EPC

Integration is the first phase. Planned starting: October 2013Required resources: 1 Engineer + 1 CAD designer for the most involved services

Not a Full Time activity during the all integration phase

TE-EPC - Serge Pittet, Fulvio Boattini 713/09/2012

DeadLine for building with services

Oct 2013 all services shall start to work to the integration

TE-EPC - Serge Pittet, Fulvio Boattini 8

THANKS FOR THE ATTENTION

QUESTIONS?

Bulding 245 schedule update

TE EPC

13/09/2012

SPARE SLIDES

06/09/2011 TE-EPC - Serge Pittet, Fulvio Boattini 9

MPSB Technical Baseline

06/09/2011 TE-EPC - Serge Pittet, Fulvio Boattini 10

TE EPC

• Overall voltage available increases and would allow a reduction of the RMS current using a faster ramping.

• The capacitor bank totally absorbs the peak power on the 18kV network. Meyrin SVC would then become optional.

• Spare sharing between MPS A and B and possibly with POPS.

• Only a few new cables needed between the reference magnet (BCER) and the MPS.

• New B-field regulation to minimize eddy currents and saturation effects impact at higher current and acceleration rate.

• Some additional trim converters might be needed for shorter dipoles in the injection region.

Reference magnet

Ring 2&3

GND

MPS B2500V5500A

QFO600V450A

QDE600V450A

GND

MPS A2500V5500A

DC3

DC

DC +

-

MAGNETS

V_F3

UdcF3

AC

CC1

AC

MV7308

DC

DIP+QF+REF

DC3

DC

DC +

-

V_F3

UdcF3

AC

CC1

AC

MV7308

DC

DIP+QD+REF

DC3

DC

DC +

-

UdcF3

AC

CC1

AC

MV7308

DC

64 BHZ Rings 1&4

128 QFO Rings 1,2,3&4

64 QDE Rings 1,2,3&4

64 BHZ Rings 2&3

Reference magnet

Ring 1&4

Ring 1 B-filedmeasurement

Ring 2 B-filedmeasurement

06/09/2011 TE-EPC - Serge Pittet, Fulvio Boattini 11

TE EPCMPSB Preliminary dimensioning

0 100 200 300 400 500 600 700 800 900

-3500

-2500

-1500

-500

500

1500

2500

3500

4500

5500900ms cycle 2GeV

Pafe [kW]

Current [A]

Udc_C

Vref [V]

Time [ms]

PTrn=2.4MW

PAFEpk=2.8MW PDCDCpk=13.7MW

Storage=0.25F@5kV

Output ripple specification to be published soon

Trim(s?) still to be dimensioned

MPSB Time Schedule: Building construction

06/09/2011 TE-EPC - Serge Pittet, Fulvio Boattini 12

TE EPC

physics LS1 physics LS2 physics

2012 2013 2014 2015 2016 2017 2018 2019

Building infrastructure & services ready

Services Integration(EL, CV,..)

GS/SEEngineering

Building construction

ServicesInstallation(EL,CV…)

Cooling station

installation

Doing the integration Now and until beginning LS1 will allow GS/SE to start with specification.

No ressources

MPSB Time Schedule

06/09/2011 TE-EPC - Serge Pittet, Fulvio Boattini 13

TE EPC

physics LS1 physics LS2 physics

2012 2013 2014 2015 2016 2017 2018 2019

26 May 2016Building ready

First tests on PSB magnets

Converters performance

commissioned and ready for operation

Converter manufactured and installed

No ressourcesServices

Integration(EL, CV,..)

GS/SE studies and procurement

Building construction

ServicesInstallation

Cooling station

installation

17 October 2013

20 March 2014

26 March 2015FC

MPSB Time Schedule

06/09/2011 TE-EPC - Serge Pittet, Fulvio Boattini 14

TE EPC

physics LS1 physics LS2 physics

2012 2013 2014 2015 2016 2017 2018 2019

26 May 2016Building ReadyNo ressources

Services Integration(EL, CV,..)

GS/SE studies and procurement

Building construction

Cooling installati

on

Air conditioning and cooling

pipes installation

17 October 201320 March 2014 26 March 2015

FCLV cabinets installation.Lights and

other services

18kV cabinets

installation

Cooling and Conditioning operating

Lights and electrical cabinets installed

Overhead Crane installed

Fire alarm system

installation

Fire alarm system installation

14 April 2017Start

Commissioning on dummy load