building a business case for lean
DESCRIPTION
by John Darlington of LERC shown at the Lean Summit 2010 - New Horizons for Lean Thinking on 2/3 November 2010TRANSCRIPT
Building a Business Case for
Dan Jones & John Darlington
Introductions
Observations about
Lean Implementations
both Operational and
Local efforts tackling isolated parts of the system to no overall beneficial effect
Poor understanding of demand and capacity; organisation not being run to maximise the flow of value through the constraint or pacemaker process
Naïve application of tools and techniques often in the wrong place at the wrong time
Inappropriate delegation of leadership
Much improvement activity does not hit
the bottom line why?
Why is it so hard to see the financial benefits
of Lean?
Here are just a few areas of contention and conflict with lean practices: -
Conventional accounting systems encourage overproduction by their clumsy interpretation of the “value adding” principle.
They do not recognise the importance of bottlenecks, constraints or pacemaker processes
They encourage local efficiency and consequently create “islands” of excellence
They have little or nothing to say about lead time
They promote the idea that the bigger the batch the lower the unit cost
They encourage cost reductions which often prove to be “mirages”
We are relying upon Accounting methods and conventions fundamentally designed nearly a century ago
So can we devise a different way of
looking at lean
In operations let’s play down the tools driven approach and look at the whole
In accounting let’s go back to basics (there’s already plenty of good practice around)
A combined common sense approach
We’re in good company
Taiichi OhnoFather of the Toyota Production System
• Taiichi Ohno, who developed the Toyota Production System, also took a down-to-earth approach.
• He called the Toyota system “profit-making industrial engineering”.
Financial Measures
NPNet Profit
ROIReturn on
Investment
CFCash Flow
UP UP UP
Simultaneously
Three Operational Measures
• Throughput– The rate that money is generated by the company through
sales • Inventory
– The money which is invested by the company to purchase things which it intends to sell
• Operating Expense– The money the company spends in order to turn inventory into
throughput
Boundary measures
T£
O.E £’s
£
I
Understand control at thePlant walls:- Real cash flow Real costs
Measures (Simultaneously)
NPNet Profit
UP CFCash Flow
UPROIReturn on
Investment
UP
TThroughput
UP IInventory D
OW
N OEOperatingExpense
DO
WN
?
Inventory and carrying charges. The traditional view
DELIVERY
OP EXP
PRODUCTQUALITY
SPECIFICATION
HIGHER MARGINS
LOWER INVESTMENT PER UNIT
DUE-DATE PERFORMANCE
SHORTER QUOTED LEAD TIMES
A Role For Reduced Inventory?
High Inventory Manufacturing
A0.5
HOURS/U
B0.1
HOURS/U
C1
HOURS/U
D.5
HOURS/U
B0.1
HOURS/U
4 weeks
HOURS 1000 2000
AVERAGEINVENTORY
INVENTORY ORDER1,000UNITS
HOURS 1000 2000
ORDER1,000UNITS
1.5 weeks
INVENTORY
A0.5
HOURS/U
B0.1
HOURS/U
C1
HOURS/U
D.5
HOURS/U
B0.1
HOURS/U
Low Inventory Manufacturing
Quality Improvement Impact
Damage detected weeks after the fault occurred.What is the chance of locating the cause?
Damage is detected while the damaging process is still operating
DAMAGE DONE
DAMAGEDETECTED
1.5 weeks
HOURS 1000 2000
INVENTORY
4 weeks
HOURS 1000 2000
AVERAGEINVENTORY
A0.5
HOURS/U
B0.1
HOURS/U
C1
HOURS/U
D.5
HOURS/U
B0.1
HOURS/U
A0.5
HOURS/U
B0.1
HOURS/U
C1
HOURS/U
D.5
HOURS/U
B0.1
HOURS/U
INVENTORY
Engineering Change Impact
1.5 weeks
HOURS 1000 2000
INVENTORY
4 weeks
HOURS 1000 2000
AVERAGEINVENTORY
A0.5
HOURS/U
B0.1
HOURS/U
C1
HOURS/U
D.5
HOURS/U
B0.1
HOURS/U
A0.5
HOURS/U
B0.1
HOURS/U
C1
HOURS/U
D.5
HOURS/U
B0.1
HOURS/U
INVENTORYImproved product will be available several weeks after engineering make the change
Improved product will be available in less than two weeks
Engineering change
Margin Impact
1.5 weeks
HOURS 1000 2000
INVENTORY
4 weeks
HOURS 1000 2000
AVERAGEINVENTORY
A0.5
HOURS/U
B0.1
HOURS/U
C1
HOURS/U
D.5
HOURS/U
B0.1
HOURS/U
A0.5
HOURS/U
B0.1
HOURS/U
C1
HOURS/U
D.5
HOURS/U
B0.1
HOURS/U
INVENTORY
The plant is forced into considerable overtime to meet the promised delivery
The production lead time is shorter than the lead time promised to the market no overtime will be needed
Investment Impact
1.5 weeks
HOURS 1000 2000
INVENTORY
4 weeks
HOURS 1000 2000
AVERAGEINVENTORY
A0.5
HOURS/U
B0.1
HOURS/U
C1
HOURS/U
D.5
HOURS/U
B0.1
HOURS/U
A0.5
HOURS/U
B0.1
HOURS/U
C1
HOURS/U
D.5
HOURS/U
B0.1
HOURS/U
INVENTORY
The last operation is at peak load for longer, pressure to ship may force plant to invest in extra capacity which will be idle for long periods
The load is more uniform at the last operation no additional investment is required
Due Date Performance
1.5 weeks
HOURS 1000 2000
INVENTORY
4 weeks
HOURS 1000 2000
AVERAGEINVENTORY
A0.5
HOURS/U
B0.1
HOURS/U
C1
HOURS/U
D.5
HOURS/U
B0.1
HOURS/U
A0.5
HOURS/U
B0.1
HOURS/U
C1
HOURS/U
D.5
HOURS/U
B0.1
HOURS/U
INVENTORYProduction starts based on a guess,Plant oscillates between excess Finished goods and poor due date performance
Production starts based on good forecast reliability Due date performance>95%
FORECAST VALIDITY
Finished Goods Impact
1.5 weeks
HOURS 1000 2000
INVENTORY
4 weeks
HOURS 1000 2000
AVERAGEINVENTORY
A0.5
HOURS/U
B0.1
HOURS/U
C1
HOURS/U
D.5
HOURS/U
B0.1
HOURS/U
A0.5
HOURS/U
B0.1
HOURS/U
C1
HOURS/U
D.5
HOURS/U
B0.1
HOURS/U
INVENTORY
Production lead times are proportional to work in process inventory.
Finished goods inventories should be proportional to production lead times!
And what of Service applications?
And what of Service applications?
Sometimes Queues make us feel sooo baaad
Why the obsession with the inventory and
response or lead time?
Big Picture Financial Mapping
ControlCooled
Heat Treatment
Finish – North Line
Finish – South Line
Joy Mining Line
Die Shop
Cutting
Induction Heating
Forge
Shotblast
Shotblast
Con. Cooled £000’sSales 9263Material costs(4179)Throughput 5084
Heat Treated £000’sSales 2738Material costs(1023)Throughput 1715
RM30.8d
3.9d
1.5d
11.4d
19.2d
4.5d
9.6d
5.3d
5.2d
24.5d
Fgds1.8d
Fgds1.3d
Fgds15.7d
Overheads £3048k
£2255k
£366k
£628k
What about looking at the inventory lead times by the distinctive value streams (June results)
Raw material
28.07 days
Finished goods
11.01 days
Work in Progress
33.85 days
What does this tell us….. It is “screamingly” obvious where the biggest issue is at present
CC OTIF 90% by week
HT OTIF 72% by week
Key Drivers Sensitivity AnalysisSept YTD Profit and
Loss Actual 2006 $000’s
A 5% Change for better effects the bottom line by: -
Pareto does exist so use it!
September End Inventory of $211m
Working Capital Relationships: Current State
Finance days
111
Inventory Pipeline in Days
Raw WIP Fin Gds
24 100 7
Debtor days
30
Payables days
50
We don’t need a business case every
month, week or day so to keep us on
track and to encourage the right lean
behaviours we use the “flow cost”.
Let’s look at the VS Map again and make some more observations about what we want from a “costing system”
Flow Costing
Capacity, Lead Time and Unit CostConventional Unit Costing
80 per
hour
75 per
hour
60 per
hour
85 per
hour
Customer Orders
Raw Material
CUT TURN MILL GRIND
RateHours per week Rate
Hours per week Rate
Hours per week Rate
Hours per week
80 37 75 37 60 37 85 37
Quan6ty to Recover 2960 Quan6ty to Recover 2775 Quan6ty to Recover 2220 Quan6ty to Recover 3145
Demonstrated Efficiency 87.0%Demonstrated
Efficiency 85.0%Demonstrated
Efficiency 98.0%Demonstrated
Efficiency 91.0%
Costed Quan6ty 2575.2 Costed Quan6ty 2358.8 Costed Quan6ty 2176 Costed Quan6ty 2862 Total
Process costs
Process costs £1,805 Process costs £2,495 Process costs £1,915 Process costs £2,563 £8,778
Target Cost Recovery Rate £0.70
Target Cost Recovery Rate £1.06
Target Cost Recovery Rate £0.88
Target Cost Recovery Rate £0.90
Unit Cost £3.53
Batch 13
Batch 12 Batch 11
Cutting 1
Batch 10 Batch 9
Turning 2
Batch 8
Batch 7
Batch 6
Batch 5 Batch 4
Milling 3
Batch 2 Batch 1
Grinding 4
Batch 3
Batch Size 500
• 13 Batches in work in process.
• Cycle time per part 45 secs 48 secs 60 secs and 42 secs
• Processing 18.75 hrs + 12.5 hrs + 41.7 hrs + 17.5 hrs = 90.45 hrs
• Total manufacturing lead time 2.4 weeks
Capacity, Lead Time and Flow CostDemand 1740/wk
80 per hour
75 per hour
60 per hour
85 per hour
Customer Orders
Raw Material
CUT TURN MILL GRIND
Capacity, Lead Time and Flow Cost
Value Added minutes = 195 seconds
Lead time 2.4 weeks or 12 days
Flow Cost Calculation
This means that the product is having value added to it or in the process of conversion much less than 1% of the time or
Another way of thinking is that it is not having anything done to it for 99.99…% of the time!
Capacity, Lead Time and Flow Cost
Batch 13
Batch 12 Batch 11
Cutting 1
Batch 10 Batch 9
Turning 2
Batch 8
Batch 7
Batch 6
Batch 5 Batch 4
Milling 3
Batch 2 Batch 1
Grinding 4
Batch 3
Batch Size 500 Demand 1740/wk
• Operating Expense of the System £8778 per week
• Product exposed to the money it takes to run the system for 2.4 weeks or 12 days
• 2.4 weeks x £8778 = £21067.2
• Divide the Total System Cost by the demand (sold) 1740 = Flow Cost of £12.11
Typical Lean Interventions
Introduce a “pull system” to cap work in progress and buffer in relation to variation and vulnerabilityApply 5 “s” including standard work in progress; zero wip at a non pacemaker is okSet up reduction to modify batch sizes…so how do they impact the “cost calculations?”
Typical Lean Interventions
Lean Intervention
Pull system
Real 5 “s”
SMED
80 per hour
75 per hour
60 per hour
85 per hour
Customer Orders
Raw Material
CUT TURN MILL GRIND
Impact on Unit CostProfit down + One off cash increaseProfit down + One off cash increaseIncreases unit cost
Conventional Unit Costing
Target Cost Recovery Rate £0.70
Target Cost Recovery Rate £1.06
Target Cost Recovery Rate £0.88
Target Cost Recovery Rate £0.90
Unit Cost £3.53
Capacity, Lead Time and Flow Cost
Batch 13
Batch 12 Batch 11
Cutting 1
Batch 10 Batch 9
Turning 2
Batch 8
Batch 7
Batch 6
Batch 5 Batch 4
Milling 3
Batch 2 Batch 1
Grinding 4
Batch 3
Batch Size 500 Demand 1740/wk
Lean InterventionPull systemReal 5 “s” SMED
Impact on Flow Cost
Capacity, Lead Time and Flow Cost
Batch 7 Batch 6
Cutting 1
Batch 5
Turning 2
Batch 4
Batch 3 Batch 2
Milling 3
Batch 1
Grinding 4
Batch Size 500 Demand 1740/wk
Lean InterventionPull systemReal 5 “s” SMED
Impact on Flow CostCash + Flow Cost down by £5.59
Capacity, Lead Time and Flow Cost
Batch 6
Cutting 1
Batch 5
Turning 2
Batch 4
Batch 3 Batch 2
Milling 3
Batch 1
Grinding 4
Batch Size 500 Demand 1740/wk
Lean InterventionPull systemReal 5 “s” SMED
Impact on Flow CostCash + Flow cost down by £5.59 Cash + Flow cost down by £0.94
Capacity, Lead Time and Flow Cost
Batch 6
Cutting 1
Batch 5
Turning 2
Batch 4
Batch 3 Batch 2
Milling 3
Batch 1
Grinding 4
Batch Size 250 Demand 1740/wk
Lean InterventionPull systemReal 5 “s” SMED
Impact on Flow CostCash + Flow cost down by £5.59 Cash + Flow cost down by £0.94 Cash + Flow cost down by £2.79
Competitive Edge
Flow Cost Benefits
The whole focus of the methodology is to keep product or information flow moving. The system has been labelled “Inactivity based costing” because it penalises delay.
Typical Unit Cost Interventions
Unit Cost Interventions
Speed up non constraints
Invest in non constraints
Increase batch sizes with no corresponding increase in “Throughput”
80 per hour
75 per hour
60 per hour
85 per hour
Customer Orders
Raw Material
CUT TURN MILL GRIND
Impact on Flow CostConsumes cash + increases the Flow CostConsumes cash + increases the Flow CostConsumes Cash + increases the Flow Cost
Conventional Unit Costing
Target Cost Recovery Rate £0.70
Target Cost Recovery Rate £1.06
Target Cost Recovery Rate £0.88
Target Cost Recovery Rate £0.90
Unit Cost £3.53
The purpose of Flow Costing
In an effort to handle the complexity of a modern organisation we break down “the whole” into smaller “chunks”.
These chunks can be departments but also we have devised ways of breaking overall money spent into “product costs” and we appoint people known as managers to head up these artificial “constructs”.
The dilemma we create in doing this is that the local manager tries to optimise what they can control, her or his local part of the overall system.
The problem this creates can be summed up by the question “are the sum of the local optima the same as the optima of the whole?”
Most people see that trying to optimise parts of the whole is NOT the same as trying to optimise the whole.