Brown Middle School
Weekly Construction Report May 27, 2016
Page 1
Brown Middle School Weekly Progress Report 5/27/2016
Picture 1: Sod at softball field
Picture 2: Fencing at football track
Picture 3: Canopy installation at West elevation
Picture 4: Framing and sheathing east gym canopy
Brown Middle School
Weekly Construction Report May 27, 2016
Page 2
Brown Middle School Weekly Progress Report 5/27/2016
Picture 5: GAB on at north parking lot Picture 6: Stucco soffit at media center entrance
Picture 7: Radial steps at media center entrance
Picture 8: Cafeteria corridor paint and VCT
Brown Middle School
Weekly Construction Report May 27, 2016
Page 3
Brown Middle School Weekly Progress Report 5/27/2016
Picture 9: VCT installed at the cafeteria
Picture 10: Pin mounted lettering at the cafeteria serving line
Picture 11: Lockers in boys locker room
Picture 12: New window sills in lower level classroom building
Brown Middle School
Weekly Construction Report May 27, 2016
Page 4
Brown Middle School Weekly Progress Report 5/27/2016
Aerial view looking to the North
Ongoing: Site:
Sidewalks
Trees
Canopies
EIFS at screen wall
Addition:
Final paint
VCT
Interior storefront
Schedule Status: Base contract – June 29, 2016
On schedule *Basement Scope Schedule - TBD
Upcoming: Site:
Gym entrance stairs
Paving at north parking lot
Striping Addition:
Blinds
Carpet and rubber base
Locker room epoxy flooring
Final clean
Budget Status: Project Budget - $20,028,944
Spent to Date - $18,774,617
On budget *Basement Scope Budget – TBD