brief theory of signature bridge

47
Summer training Report on Construction of Signature Bridge Submitted as partial fulfillment for the award of BACHELOR OF TECHNOLOGY DEGREE Session 2015-16 in Civil Engineering By PRAVIN KUMAR GAURAV 1203200077 Under the guidance of Mr. VISHWANATH SINGH ABES ENGINEERING COLLEGE, GHAZIABAD AFFILIATED TO UTTAR PRADESH TECHNICAL UNIVERSITY, LUCKNOW

Upload: pravin-gaurav

Post on 20-Jan-2017

1.412 views

Category:

Engineering


2 download

TRANSCRIPT

Page 1: BRIEF THEORY OF SIGNATURE BRIDGE

Summer training Report on

Construction of Signature Bridge

Submitted as partial fulfillment for the award of

BACHELOR OF TECHNOLOGY

DEGREE

Session 2015-16 in

Civil Engineering

By

PRAVIN KUMAR GAURAV

1203200077

Under the guidance of Mr. VISHWANATH SINGH

ABES ENGINEERING COLLEGE, GHAZIABAD

AFFILIATED TO

UTTAR PRADESH TECHNICAL UNIVERSITY, LUCKNOW

Page 2: BRIEF THEORY OF SIGNATURE BRIDGE

Summer Training Report on

Construction of Signature Bridge

Submitted as partial fulfillment for the award of

BACHELOR OF TECHNOLOGY

DEGREE

Session 2015-16 in

Civil Engineering

By

PRAVIN KUMAR GAURAV

1203200077

Under the guidance of Mr. VISHWANATH SINGH

ABES ENGINEERING COLLEGE, GHAZIABAD

AFFILIATED TO

UTTAR PRADESH TECHNICAL UNIVERSITY, LUCKNOW

Page 3: BRIEF THEORY OF SIGNATURE BRIDGE

Student’s Declaration

I hereby declare that the work being presented in this report

entitled “CONSTRUCTION OF CABLE STAYED BRIDGE

(SIGNATURE BRIDGE)” is an authentic record of my own work

carried out under the supervision of Mr.

“Mr. VISHWANATH SINGH”

The matter embodied in this report has not been submitted by me for

the award of any other degree. Dated Signature of student

Name: - PRAVIN KUMAR GAURAV

Department: CIVIL ENGINEERING

This is to certify that the above statement made by the candidate is correct to the best of my knowledge.

Signature of HOD

Name: - Dr. T. Vishalakshi

Date

Page 4: BRIEF THEORY OF SIGNATURE BRIDGE

ACKNOWLEDGEMENT

I would like to thank Delhi tourism and transport Development Corporation. for giving

me this invaluable opportunity to learn so much practical knowledge which would have

impossible to learn through only looking at images from textbooks. I have gained

invaluable insights into how construction of any superstructure is handled and how

any difficulty which comes in between is tackled. Apart from technical knowledge, I

have gained insights into Construction management, Efficient Man-power

management and lots of other things.

I would like to thank Mr. Vishwanath singh (Project Manager, DTTDC) and special

thanks to Mr. E.Ahmed (Executive engineer, CPWD Training institute) for providing

me this opportunity and giving me valuable support and teaching me values and ethics

of Civil Engineering and specially bridge principles. Also I would like to thank Mr.

Rajesh Chauhan (Site in Charge) and Mr. Sunil Kumar (superintendent Engineer)

for guiding me throughout the project and without whom this training would have been

impossible. Also I would like to thank Mr. R.K.Gupta (Assistant Engineer) for giving

me invaluable information and knowledge into construction processes.

In whole training I was helped by so many Engineers, Supervisors and everyone, it

will impossible to take everyone’s name. In all, I thank DTTDC Family for this

Invaluable opportunity and helping me out in any difficulty however big or small it may

be.

Last but not least, I would like to thank Dr. V. K. Gupta (executive engineering) for

arranging this training and who always have been supporting person for not only me

but for whole department.

PRAVIN KUMAR GAURAV

1203200077

B.TECH

Page 5: BRIEF THEORY OF SIGNATURE BRIDGE

LIST OF CONTENT 1. INTRODUCTION ................................................................................................. 1

2. DESCRIPTION OF PROJECT............................................................................. 2

3. SITE LAYOUT ..................................................................................................... 3

4. MATERIALS USED AT A CONSTRUCTION SITE .............................................. 4

Settling Of Cement ........................................................................................... 5

Initial and final setting time of cement............................................................... 5

Storage of Cement ........................................................................................... 6

Coarse Aggregate ............................................................................................ 6

Fine Aggregate ................................................................................................. 7

5. REINFORCEMENT ............................................................................................. 7

TERMS USED IN REINFORCEMENT ............................................................. 9

6. Shuttering and Scaffolding ................................................................................. 10

7. CLEANING AND TREATMENT OF FORMS ..................................................... 11

Verticality of the Structure .............................................................................. 12

STRIPPING TIME OR REMOVAL OF FORM WORK .................................... 13

Concrete Production ....................................................................................... 13

Properties of Concrete.................................................................................... 14

Curing of Concrete ......................................................................................... 14

8. BATCHING PLANT ............................................................................................ 15

9. FOUNDATIONS ................................................................................................. 17

Well foundation ............................................................................................... 17

Components of well foundation ...................................................................... 17

Sinking of Well Foundation ............................................................................. 18

LOAD APPLICATION ..................................................................................... 20

SINKING PROCEDURE ................................................................................. 20

Measures for rectification of tilts and shifts ..................................................... 21

10. Open foundation/Pile foundation .................................................................... 23

Pile Classification by Construction Method ..................................................... 23

Pilling Steps .................................................................................................... 27

11. PLACING OF GIRDERS ................................................................................ 29

12. QUALITY ASSURANCE/ QUALITY CONTROL ............................................. 30

13. TESTS CONDUCTED .................................................................................... 35

Test Conducted on Fresh Concrete ............................................................... 35

14. CONCLUSION ............................................................................................... 41

Page 6: BRIEF THEORY OF SIGNATURE BRIDGE

LIST OF FIGURES:

Figure 1 Artistic view of Signature Bridge ................................................................... 1

Figure 2 Schematic diagram ...................................................................................... 2

Figure 3 Plan of pile ................................................................................................... 4

Figure 4 Plan of pier ................................................................................................... 4

Figure 5 Tying of reinforcement bar ........................................................................... 7

Figure 6 Pile cap reinforcement ................................................................................. 7

Figure 7 Cover blocks .............................................................................................. 10

Figure 8 Formwork of pier and false wall .................................................................. 11

Figure 9 Curing of well steining ................................................................................ 14

Figure 10: Curing of well foundation ......................................................................... 15

Figure 11: Batching plant ........................................................................................ 16

Figure 12: Schematic diagram of well foundation ..................................................... 17

Figure 13: Jackdown of well foundation ................................................................... 19

Figure 14: Gripper rods anchored in ground ............................................................ 20

Figure 15 Power pack .............................................................................................. 20

Figure 16: Formation of Slumps inside the well ........................................................ 21

Figure 17: Rectifying tilt by eccentric loading ........................................................... 22

Figure 18: Rectifying by pushing well jacks .............................................................. 22

Figure-19:- Well staining……………………………………………………………… …23

Figure 20:- Pile Driving………………………………………………………………….…27

Figure 21:- HSFG 8.8 Grade bolt…..…………………………………………………….29

Figure 22: Placement of steel girder1s ..................................................................... 31

Figure 23: Test and their Frequency ........................................................................ 37

Figure 25: Compression testing machine ................................................................. 40

Figure 26: Silt content test ........................................................................................ 41

Page 7: BRIEF THEORY OF SIGNATURE BRIDGE

1. INTRODUCTION

Figure 1 Artistic view of Signature Bridge

India’s first “Signature Bridge” being constructed across the Yamuna at Wazirabad

promises to be a great attraction of Delhi. An ambitious project of the Delhi tourism, the

cable-stayed bridge will link National Highway number one near existing T-point at

Wazirabad on Western bank and Marginal Bund Road at Khajuri Khas on eastern bank of

the river Yamuna, thus connecting North Delhi with East Delhi.

With a length of about 575 meters and a height of 154 meters the proposed Signature

Bridge would have a bow-shaped pylon in the middle. Two high towers will be there to

provide double cable support in the inner periphery of the carriageway. Equipped with eight lanes, this engineering masterpiece will have 1.2 meter wide central

verge, space for anchoring cables, maintenance walkway and crash barrier on either side

of the central verge. The deck will be composite (steel and concrete) while pylon will be in

steel.

Once operational the Signature Bridge will eventually improve access between North and

west Delhi for the commuters, who have to pass through the narrow lane on the present

bridge in Wazirabad, leading to heavy traffic jam in the peak hours. Also, to facilitate the

movement of vehicular traffic new express lanes will be constructed to connect Ring Road

with the bridge.

1

Page 8: BRIEF THEORY OF SIGNATURE BRIDGE

2. DESCRIPTION OF PROJECT:

PROJECT NAME: Signature Bridge(Yamuna bridge at Wazirabad)

CLIENT: Delhi Tourism & Transportation Development Corporation Ltd.

AGENCY: J.V. of M/s Gammon India & Construtora Cidade, Tensacciai

DESIGN CONSULTANT: J.V. of M/s. Schlaich Bergermann Und Partner, Construma

Consultancy pvt ltd. Mumbai

PROOF CONDULTANT: J.V. of M/s. Systra, Virlogeux & Tandon Consultants.

SUB-CONSULTANT: Ratan J.Batliboi Architects, Mumbai, Department of

EARTHQUAKE ANALYSIS: - IIT Roorkee & structural engg. Research center, Chennai.

LISENCE NO: CLA/c/13N/10

PERIOD OF CONSTRUCTION: 20/3/2013 to 19/12/2016 (ESTIMATED)

COST OF PROJECT: 1591 crore (revised)

TOTAL LENGTH : 575m (8 LANES)

PYLON HEIGHT: 154m (5400 ton)

FOUNDATIONS: 6 open and 18 well foundations

ADDITIONAL WORK: eastern and western approaches

2

Figure 2 Schematic diagram

Page 9: BRIEF THEORY OF SIGNATURE BRIDGE

3. SITE LAYOUT A badly planned and untidy site is the underlying cause of many accidents resulting from

falls of material and collisions between workers and plant or equipment. Space constraints,

particularly in urban work sites, are nearly always the biggest limiting factor and a layout

which caters best for the safety and health of workers may appear to be difficult to reconcile

with productivity. Proper planning by management is an essential part of preparation and

budgeting for the safe and efficient running of a construction operation.

Before work even begins on site, thought needs to be given to: a. The sequence or order in which work will be done and to any especially hazardous

operations or processes.

b. Access for workers on and around the site. Routes should be free from obstruction

and from exposure to hazards such as falling materials, materials-handling equipment

and vehicles. Suitable warning notices should be posted. Routes to and from welfare

facilities need equal consideration. c. Routes for vehicular traffic. These should be “one way “as far as practicable. Traffic

congestion prejudices the safety of workers, especially when impatient drivers unload

goods hurriedly.

d. Storage areas for materials and equipment. Materials need to be stored as close as

possible to the appropriate workstation, e.g. sand and gravel close to the cement-

batching plant, and timber close to the joinery shop. If this is not practicable, it is

important to schedule the arrival of materials. e. The location of construction machinery. This is usually dependent on operational

requirements so that tower cranes are subject to constraints such as their radius of

operation, and pick-up and unloading points.

f. The location of trade workshops –these are not usually moved after they are built. g. The location of medical and welfare facilities. On large sites sanitary facilities for both

sexes should be provided at several locations.

h. Artificial lighting at places where work continues or workers pass after dark. i. Site security. j. Arrangements to keep the site tidy and for the collection and removal of waste.

3

Page 10: BRIEF THEORY OF SIGNATURE BRIDGE

Figure 3 Plan of pile Figure 4 Plan of pier

k. The need for low-voltage electric power supplies for temporary lighting, portable tools and equipment.

4. MATERIALS USED AT A CONSTRUCTION SITE

Cement Portland cement is composed of calcium silicates and aluminates and aluminoferrite It is

obtained by blending predetermined proportions limestone clay and other minerals in small

quantities which is pulverized and heated at high temperature –around 1500 deg.

centigrade to produce ‘clinker’ .The clinker is then ground with small quantities of gypsum

to produce a fine powder called Ordinary Portland Cement (OPC). When mixed with water,

sand and stone, it combines slowly with the water to form a hard mass called concrete.

Cement is a hygroscopic material meaning that it absorbs moisture in presence of moisture

it undergoes chemical reaction termed as hydration. Therefore cement remains in good

condition as long as it does not come in contact with moisture. If cement is more than three

months old then it should be tested for its strength before being taken into use. The Bureau of Indian Standards (BIS) has classified OPC in three different grades The

classification is mainly based on the compressive strength of cement-sand mortar cubes

of face area 50 cm2 composed of 1 part of cement to 3 parts of standard sand by weight

with a water-cement ratio arrived at by a specified procedure. The grades are (i) 33 grade (ii) 43 grade

4

Page 11: BRIEF THEORY OF SIGNATURE BRIDGE

(iii) 53 grade The grade number indicates the minimum compressive strength of cement sand mortar

in N/mm2 at 28 days, as tested by above mentioned procedure. Portland Pozzolana Cement (PPC) is obtained by either intergrinding a pozzolanic material

with clinker and gypsum, or by blending ground Pozzolana with Portland cement.

Nowadays good quality fly ash is available from Thermal Power Plants, which are

processed and used in manufacturing of PPC.

Settling Of Cement

When water is mixed with cement, the paste so formed remains pliable and plastic for a

short time. During this period it is possible to disturb the paste and remit it without any

deleterious effects. As the reaction between water and cement continues, the paste loses

its plasticity. This early period in the hardening of cement is referred to as ‘setting’ of

cement.

Initial and final setting time of cement

Initial set is when the cement paste loses its plasticity and stiffens considerably. Final set

is the point when the paste hardens and can sustain some minor load. Both are arbitrary

points and these are determined by Vicat needle penetration resistance. Slow or fast setting normally depends on the nature of cement. It could also be due to

extraneous factors not related to the cement. The ambient conditions play an important

role. In hot weather, the setting is faster, in cold weather, setting is delayed Some types of

salts, chemicals, clay, etc if inadvertently get mixed with the sand, aggregate and water

could accelerate or delay the setting of concrete.

Storage of Cement

It needs extra care or else can lead to loss not only in terms of financial loss but also in

terms of loss in the quality. Following are the don’t that should be followed -

a) Do not store bags in a building or a go down in which the walls, roof and floor are

not completely weatherproof.

b) Do not store bags in a new warehouse until the interior has thoroughly dried out.

c) Do not be content with badly fitting windows and doors, make sure they fit

5

Page 12: BRIEF THEORY OF SIGNATURE BRIDGE

properly and ensure that they are kept shut.

d) Do not stack bags against the wall. Similarly, don’t pile them on the floor unless

it is a dry concrete floor. If not, bags should be stacked on wooden planks or

sleepers.

e) Do not forget to pile the bags close together

f) Do not pile more than 15 bags high and arrange the bags in a header-and-

stretcher fashion.

g) Do not disturb the stored cement until it is to be taken out for use.

h) Do not take out bags from one tier only. Step back two or three tiers.

i) Do not keep dead storage. The principle of first-in first-out should be followed in

removing bags.

j) Do not stack bags on the ground for temporary storage at work site. Pile them

on a raised, dry platform and cover with tarpaulin or polythene sheet.

Coarse Aggregate Coarse aggregate for the works should be river gravel or crushed stone .It should be hard,

strong, dense, durable, clean, and free from clay or loamy admixtures or quarry refuse or

vegetable matter. The pieces of aggregates should be cubical, or rounded shaped and

should have granular or crystalline or smooth (but not glossy) non-powdery surfaces.

Aggregates should be properly screened and if necessary washed clean before use. Coarse aggregates containing flat, elongated or flaky pieces or mica should be rejected.

The grading of coarse aggregates should be as per specifications of IS-383. After 24-hrs immersion in water, a previously dried sample of the coarse aggregate should

not gain in weight more than 5%.Aggregates should be stored in such a way as to prevent

segregation of sizes and avoid contamination with fines. Depending upon the coarse aggregate color, there quality can be determined as:

a) Black aggregate is considered to have very good quality

b) Blue aggregate is considered to have good quality.

c) Whitish is considered to have bad quality.

6

Page 13: BRIEF THEORY OF SIGNATURE BRIDGE

Fine Aggregate Aggregate which is passed through 4.75 IS Sieve is termed as fine aggregate. Fine

aggregate is added to concrete to assist workability and to bring uniformity in mixture.

Usually, the natural river sand is used as fine aggregate. Important thing to be considered

is that fine aggregates should be free from coagulated lumps.

Grading of natural sand or crushed stone i.e. fine aggregates shall be such that not more

than 5 percent

shall exceed 5 mm in size, not more than 10% shall IS sieve No. 150 not less than 45%

or more than 85%

shall pass IS sieve No. 1.18 mm and not less than 25% or more than 60% shall pass IS

sieve No. 600 micron.

River sand, crushed sand, 20mm msa and 10mm msa aggregate was used for different

purposes.

5. REINFORCEMENT Steel reinforcements are used, generally, in the form of bars of circular cross section in

concrete structure. They are like a skeleton in human body. Plain concrete without steel

or any other reinforcement is strong in compression but weak in tension. Steel is one of

the best forms of reinforcements, to take care of those stresses and to strengthen concrete

to bear all kinds of loads.

Mild steel bars conforming to IS: 432 (Part I) and Cold-worked steel high strength

deformed bars conforming to IS: 1786 (grade Fe 415 and grade Fe 500, where 415 and

500 indicate yield stresses 415 N/mm2 and 500 N/mm2 respectively) are commonly used.

Grade Fe 500 is being used most commonly nowadays. This has limited the use of plain

mild steel bars because of higher yield stress and bond strength resulting in saving of steel

quantity. Some companies have brought thermo mechanically treated (TMT) and

corrosion resistant steel (CRS) bars with added features.

7

Page 14: BRIEF THEORY OF SIGNATURE BRIDGE

Bars range in diameter from 6 to 50 mm. Cold-worked steel high strength deformed bars

start from 8 mm diameter. For general house constructions, bars of diameter 6 to 20 mm

are used

Transverse reinforcements are very important. They not only take care of structural

requirements but also help main reinforcements to remain in desired position. They play

a very significant role while abrupt changes or reversal of stresses like earthquake etc.

They should be closely spaced as per the drawing and properly tied to the

main/longitudinal reinforcement.

In this project, Fe 500 of different diameters was used at all the places.

TERMS USED IN REINFORCEMENT

a) BAR-BENDING-SCHEDULE:-Bar-bending-schedule is the schedule of

reinforcement bars prepared in advance before cutting and bending of rebars. This

schedule contains all details of size, shape and dimension of rebars to be cut.

b) LAP LENGTH:-Lap length is the length overlap of bars tied to extend the

reinforcement length. Lap length about 50 times the diameter of the bar is

considered safe. Laps of neighboring bar lengths should be staggered and should

8

Figure 5: Reinforcement in pier Figure 6: Reinforcement in pile cap

Page 15: BRIEF THEORY OF SIGNATURE BRIDGE

not be provided at one level/line. At one cross section, a maximum of 50% bars should

be lapped. In case, required lap length is not available at junction because of space

and other constraints, bars can be joined with couplers or welded (with correct choice

of method of welding).

c) ANCHORAGE LENGTH:-This is the additional length of steel of one structure

required to be inserted in other at the junction. For example, main bars of beam in

column at beam column junction, column bars in footing etc. The length

requirement is similar to the lap length mentioned in previous question or as per

the design instructions

d) COVER BLOCKS:-Cover blocks are placed to prevent the steel rods from touching

the shuttering plates and thereby providing a minimum cover and fix the

reinforcements as per the design drawings. Sometimes it is commonly seen that

the cover gets misplaced during the concreting activity. To prevent this, tying of

cover with steel bars using thin steel wires called binding wires (projected from

cover surface and placed during making or casting of cover blocks) is

recommended. Covers should be made of cement sand mortar (1:3). Ideally, cover

should have strength similar to the surrounding concrete, with the least perimeter

so that chances of water to penetrate through periphery will be minimized.

Provision of minimum covers as per the Indian standards for durability of the whole

structure should be ensured.

Shape of the cover blocks could be cubical or cylindrical. However, cover indicates

thickness of the cover block. Normally, cubical cover blocks are used. As a thumb

rule, minimum cover of 2”in footings, 1.5”in columns and 1”for other structures may

be ensured.

Figure 7: Cover blocks

Page 16: BRIEF THEORY OF SIGNATURE BRIDGE

6. Shuttering and Scaffolding

The term ‘SHUTTERING’ or ‘FORMWORK’ includes all forms, moulds, sheeting,

shuttering planks, walrus, poles, posts, standards, leizers, V-Heads, struts, and structure,

ties, prights, walling steel rods, bolts, wedges, and all other temporary supports to the

concrete during the process of sheeting.

Forms or moulds or shutters are the receptacles in which concrete is placed, so that it will

have the desired shape or outline when hardened. Once the concrete develops adequate

strength, the forms are removed. Forms are generally made of the materials like timber,

plywood, steel, etc.

Generally camber is provided in the formwork for horizontal members to counteract the

effect of deflection caused due to the weight of reinforcement and concrete placed over

that. A proper lubrication of shuttering plates is also done before the placement of

reinforcement. The oil film sandwiched between concrete and formwork surface not only

helps in easy removal of shuttering but also prevents loss of moisture from the concrete

through absorption and evaporation.

The steel form work was designed and constructed to the shapes, lines and dimensions

shown on the drawings. All forms were sufficiently water tight to prevent leakage of mortar.

Forms were so constructed as to be removable in sections. One side of the column forms

were left open and the open side filled in board by board successively as the concrete is

placed and compacted except when vibrators are used. A key was made at the end of

each casting in concrete columns of appropriate size to give proper bondings to columns

and walls as per relevant IS.

10

Page 17: BRIEF THEORY OF SIGNATURE BRIDGE

Figure 7 Formwork of pier and false wall

7. CLEANING AND TREATMENT OF FORMS

All rubbish, particularly chippings, shavings and saw dust, was removed from the interior

of the forms (steel) before the concrete is placed. The form work in contact with the

concrete was cleaned and thoroughly wetted or treated with an approved composition to

prevent adhesion between form work and concrete. Care was taken that such approved

composition is kept out of contact with the reinforcement.

Design The form-work should be designed and constructed such that the concrete can be

properly placed and thoroughly compacted to obtain the required shape, position, and

levels subject

Erection of Formwork

The following applies to all formwork:

a) Care should be taken that all formwork is set to plumb and true to line and level.

b) When reinforcement passes through the formwork care should be taken to ensure

close fitting joints against the steel bars so as to avoid loss of fines during the

compaction of concrete.

11

Page 18: BRIEF THEORY OF SIGNATURE BRIDGE

c) If formwork is held together by bolts or wires, these should be so fixed that no iron is

exposed on surface against which concrete is to be laid.

d) Provision is made in the shuttering for beams, columns and walls for a port hole of

convenient size so that all extraneous materials that may be collected could be

removed just prior to concreting.

e) Formwork is so arranged as to permit removal of forms without jarring the concrete.

Wedges, clamps, and bolts should be used where practicable instead of nails.

f) Surfaces of forms in contact with concrete are oiled with a mould oil of approved

quality. The use of oil, which darkens the surface of the concrete, is not allowed. Oiling

is done before reinforcement is placed and care taken that no oil comes in contact

with the reinforcement while it is placed in position. The formwork is kept thoroughly

wet during concreting and the whole time that it is left in place.

Immediately before concreting is commenced, the formwork is carefully examined to

ensure the following:

a) Removal of all dirt, shavings, sawdust and other refuse by brushing and washing.

b) The tightness of joint between panels of sheathing and between these and any

hardened core.

c) The correct location of tie bars bracing and spacers, and especially connections

of bracing.

d) That all wedges are secured and firm in position.

e) That provision is made for traffic on formwork not to bear directly on reinforcement

steel.

Verticality of the Structure All the outer columns of the frame were checked for plumb by plumb-bob as the work

proceeds to upper floors. Internal columns were checked by taking measurements from

outer row of columns for their exact position. Jack were used to lift the supporting rods

called props

STRIPPING TIME OR REMOVAL OF FORM WORK

Forms were not struck until the concrete has attained a strength at least twice the stress

to which the concrete may be subjected at the time of removal of form work. The strength

12

Page 19: BRIEF THEORY OF SIGNATURE BRIDGE

referred is that of concrete using the same cement and aggregates with the same

proportions and cured under conditions of temperature and moisture similar to those

existing on the work. Where so required, form work was left longer in normal

circumstances

Form work was removed in such a manner as would not cause any shock or vibration that

would damage the concrete. Before removal of props, concrete surface was exposed to

ascertain that the concrete has sufficiently hardened. Where the shape of element is such

that form work has re-entrant angles, the form work was removed as soon as possible

after the concrete has set, to avoid shrinkage cracking occurring due to the restraint

imposed.

Concrete Production Concrete production is the process of mixing together the various ingredients—water,

aggregate, cement, and any additives—to produce concrete. Concrete production is time-

sensitive. Once the ingredients are mixed, workers must put the concrete in place before

it hardens.

For the project various grades of concrete was produced varying from M25 to M50.

a) Batching: The process of measurement of the different materials for the making of

concrete is known as batching. Batching is usually done in two ways: volume batching

and weight batching. In case of volume

b) batching the measurement is done in the form of volume whereas in the case of

weight batching it is done by the weight

c) Mixing: Mixing of concrete is a very important step for achieving good final

properties, and one of that can be quite difficult without the right equipment. This is

one of the best reasons for using ready mix concrete.

d) Compacting: When concrete is placed it can have air bubbles entrapped in it

which can lead to the reduction of the strength by 30%. In order to reduce the

air bubbles the process of compaction is performed. Compaction is generally

performed in two ways: by hand or by the use of vibrators.

13

Page 20: BRIEF THEORY OF SIGNATURE BRIDGE

Figure 9: Curing of well foundation

e) Curing: Curing is the process in which the concrete is protected from loss of moisture

and kept within a reasonable temperature range. The result of this process is increased

strength and decreased permeability. Curing is also a key player in mitigating cracks

in the concrete, which severely impacts durability.

Properties of Concrete

Concrete has relatively high compressive strength, but much lower tensile strength. For

this reason it is usually reinforced with materials that are strong in tension

The elasticity of concrete is relatively constant at low stress levels but starts decreasing

at higher stress levels as matrix cracking develop. Concrete has a very low coefficient of

thermal expansion and shrinks as it matures. All concrete structures crack to some

extent, due to shrinkage and tension. Concrete that is subjected to long-duration forces

is prone to creep.

Curing of Concrete

Curing concrete is the term used for stopping freshly poured concrete from drying out too

quickly. This is done because concrete, if left to dry out of its own accord, will not develop

the full bond between all of its ingredients. It will be weaker and tend to crack more. The

surface won't be as hard as it could be. Curing can be performed in different ways:-

14

Page 21: BRIEF THEORY OF SIGNATURE BRIDGE

8. BATCHING PLANT

The Signature Bridge Site at Wazirabad had a batching plant of capacity 60m3/hr. The

batching plant had various execution modes for feeding of the aggregates like star batcher,

compartment batcher and in-line silo execution. The four aggregate gates are

pneumatically operated and the weighing is done through electronic load cells. The

aggregates are weighed in a skip bucket and then are moved up to the turbo pan mixer

by two units of pole change motors. These pole change motors operate the skip at two

different speeds to reduce the time cycle at each batch and at the same time protect the

important components of

the weighing system. The batching of water and admixture is by weight. The cement from

the cement silos is fed into the combined cement water weigher through screw conveyors.

The water and cement are weighed in a combined weigher and discharged into the pan

mixer. The Turbo pan mixer is designed to handle various slumps of concrete and to

achieve a homogenous mix in the shortest possible time.

The plant can deliver the 60 m3 per hour output as each and every operation of the plant

has been sequenced to achieve this output. The 60M batching plant is fully computerized

and offers features like material in air compensation. The batching plant can also be fitted

with electronic moisture meter and an interface in the control system provides the Batch

reports through the printer. The interface also facilitates the transfer of all data from the

control system to a computer where the data can be processed as per the customer

requirements. The batching mixer mixes the following-

a. Cement

b. Sand

c. Aggregate

d. Admixture

e. Fly ash

f. Water

15

Page 22: BRIEF THEORY OF SIGNATURE BRIDGE

Figure 11: material hopper

Figure 10: Batching plant

Cement is loaded through a pump in which cement was inserted manually. The main

mixture had six blades for mixing and a hydraulically controlled gate for ejecting the mix.

In a nearby tank water is stored and added via a pipe. Admixture- Naphthalene

Formaldehyde is added to-

Increase the setting time Reduce the water/cement ratio

Sand and aggregate are loaded on a large conveyor belt, whose quantity is electronically

controlled. For each batch production these are transferred through electronic commands.

The batching plant also has an exit for dry concrete that gets blown in the process. These

dry particles are returned to the batching mixture using a compressor. It takes around 20-

30 seconds to mix and rest 30 seconds are used in bringing water,

aggregate and sand. The uniqueness of the batching plant is its ability to achieve the rated

output with minimum break downs. Hence, it is an ideal plant for use in RMC operations

and for projects where the down time of the plant is expensive.

9. FOUNDATIONS

Two types of foundations used for the project are:

1. Well foundation.

2. Open foundation/Pile foundation.

16

Page 23: BRIEF THEORY OF SIGNATURE BRIDGE

Figure 12: Schematic diagram of well foundation

Well foundation Well foundations are the most common types of deep foundations used for bridges in

India.

Components of well foundation

a) Well Cap - The well cap is a RCC slab of sufficient strength to transmit the forces from

pier to the body of well. It is generally kept at low water level. The dimension of the

well cap should be sufficient to accommodate the pier. The recommended minimum

thickness is 0.75 m.

b) Steining –It is the wall of well & is built over a wedge shaped portion called well curb.

The steining is designed such that it can be sunk under it’s own weight. The thickness

should be sufficient so as to overcome skin friction developed during sinking by its

own weight.

c) Well Curb –The well curb supports the steining. The curb should be slightly projected

from the steining to reduce the skin friction during sinking of well. It is made of RCC

with steel cutting edge.

17

Page 24: BRIEF THEORY OF SIGNATURE BRIDGE

d) Cutting Edge –The cutting edge is either projected below the curb as a sharp edge or

can also have flat bottom. The projected edge is likely to be damaged in strata of

gravels and boulders. In such soils the flat bottom cutting edge is provided.

e) Bottom Plug –The bottom plug is made bowled shape in order to have an arch action.

The bottom plug transmits load to soil below. When sunk to its final depth bottom part

is concreted to seal the bottom completely. The thickness varies from ½ to full inside

diameter of the well so as to be able to resist uplift forces. The concreting should be

done in one continuous operation. When wells contain more than one dredge hole all

should be plugged to the same height. If the well is to rest on rock, it should be

anchored properly by taking it 25 cm to 30 cm deep into rock The bottom plug should

be of rich concrete (1:2:4) with extra 10 % of cement. f) Sand Filling - After concreting the bottom plug the sand is filled above the bottom plug

and below top plug. Sand filling provide stability of well, reduce tensile stress

produced by bending moment and distributes the load of super structure on to the

bottom plug. Sand filling relieves load to steining to some extent. g) Top Plug –This is a plug at the top of the well below the well cap. This helps

transferring the load through the granular material into the staining

Sinking of Well Foundation a) Laying of Curbs - In dry ground excavate up to 50 cm in river bed and place the cutting

edge at the required position. If the curb is to be laid under water and depth of water

is greater than 5 m, prepare Sand Island and lay the curb. If depth of water exceeds

5 m built curb in dry ground and float it to the site. b) Construction of Well Steining –the idea is to initially sink the well under its own weight.

The steining should be built in short height of 1.5 m initially and 3 m after a 6 m grip

length is achieved. The verticality should be maintained. The aim of the well sinking

is to sink the well vertically and at the correct position. c) Jackdown sinking: It is basically transferring the forces exerted by the hydraulic jacks

on the earth anchors to the heavy duty pressurization girders resting on the steining

top through stools. The earth anchor pairs are placed such that two girders systems,

both crossing the well sides, can be positioned, with hydraulic jacks at the ends of the

girder, located such that they are directly above the Centre of the earth anchor pair.

18

Page 25: BRIEF THEORY OF SIGNATURE BRIDGE

Figure 13: Jackdown of well foundation

Figure 14: Grippers rod anchored into ground

Following procedure is followed for the jack down of the well foundation:

a. Girder fitted with bottom pieces of gripper rod assembly is placed on the earth

anchors and are fixed by grouting after gripper rod is at 75 m depth.

Supporting stools are then placed on the steining to suit the location of the anchors.

b. Pressurization girders are then erected over the stools and pressure plates fixed on

top of the girders at ends.

c. 250 MT capacity hydraulic jacks along with upper gripper attachments are erected and

the gripper rods are fixed by locking the upper gripper attachment.

d. 1000mm Pieces of Gripper rod is then fixed with the adjustment rods at required height

and held in position by locking the lower gripper assembly.

e. All jacks are aligned and leveled properly.

f. The pressure hoses are connected with power pack and jacks.

g. Loading is applied with power pack

19

Page 26: BRIEF THEORY OF SIGNATURE BRIDGE

Figure 8: Power pack Figure 15 Power pack

h. After lifting of ram by about 40 to 100mm wedges are placed on bearing plates on

either side of the anchor couplers.

i. The lower gripper assembly is locked and upper gripper assembly is released.

j. Ram is brought to its original position and upper gripper assembly is locked.

k. Lower gripper assembly is then unlocked.

l. The above operations are supported by air/water jetting till sinking is achieved.

LOAD APPLICATION

a) Each Jack has Separate Control valve on the power pack for application of

pressure. The adjustment wherever required will be maneuvered by closing or releasing

the control valve.

b) The jacks placed on upper side of the tilted well shall be given with additional load than

that of the lower side.

c) Releasing of pressure on any one jack shall be done with proper care. In case of tilting of

the girder on any side due to releasing of pressure, then releasing shall be done on both

the jacks placed on the said girder

d) To cater for additional safety precautions against lifting of girder in case of any failure of

grips or larger uneven loading the girders shall be arrested to additional rebar placed in

the steining.

e) 25 mm dia. Bar shall be placed in the steining during concreting on each

supporting stool.

20

Page 27: BRIEF THEORY OF SIGNATURE BRIDGE

Figure 16: Formation of Slumps inside the well

SINKING PROCEDURE

In sandy clay strata first sump condition shall be made to the extent of 1.5 to 2 meters

and then loading shall commence with initial 50 MT per Jack and gradually in increments

of 25 MT till well starts sinking. The intensity of loading shall be kept constant till

appreciable sinking is achieved and well is not further going down. Thereafter sump /

hump will be checked and loading shall be released in case of hump / or less sump to

resume grabbing once more.

a. In sandy strata each jack shall be loaded to 100 MT and then grabbing operation is started.

The loading shall be kept at 100 MT till sinking of well starts. After appreciable sinking is

over and with the above loading the sump of the well is checked, and grabbing with the

above loading is continued.

Measures for rectification of tilts and shifts The primary objective while sinking the well is to sink it straight and at a correct position,

however it is not an easy task to achieve this objective. During the sinking the well may tilt

to one side or it may shift away from the desired position. The following precautions are

to be taken as far as possible:

a) Outer surface should be regular and smooth.

b) Radius of the curb should be 2 to 4 cm larger than the radius of the steining.

21

Page 28: BRIEF THEORY OF SIGNATURE BRIDGE

c) Cutting edge should be of uniform thickness and sharpness.

d) Dredging should be done uniformly on all sides. According to IS: 3955-1967 the tilt should generally be limited to 1 in 60, and the shift to

one percent of the depth sunk. In case the tilt and shifts exceeds the above limits the

following measures are taken for their rectification.

i. Eccentric loading: Construct eccentric welded framed bracket and load the

platform thus made with 400 to 600 tons load. This is shown in Fig. below.

Figure 17: Rectifying tilt by eccentric loading

iii. Water jetting: Jett are applied on the outer face of the high side of well, skin

friction is reduced and tilt is rectified.

iv. Excavation under cutting edge: Excavate under cutting edge by dewatering in

case dewatering is not possible divers are sent to loosen the strata.

v. Pulling the well: It is effective only in early stages of sinking. Well is pulled

towards the higher side using steel ropes around the well.

vi. Pushing the wells by jack: It can be done using a suitable arrangement or

hydraulic jacks by resting it against the vertically sunk well.

Page 29: BRIEF THEORY OF SIGNATURE BRIDGE

Figure19: well staining

vii. Changing the pressure in power packs: If the tilting occurs during the Jackdown

process it can be easily rectified by increasing the pressure on the higher jack, by

using the power pack.

Special type of well foundation being used at the site

At Signature Bridge site normally wells used are of 7m inner and 9 m outer diameter with

rock strata at 36m depth but due to varying rock depth and special structural requirement

a special type of well was required to be constructed at one of the locations. At P23

location, where the back stay cables were supposed to be anchored the well foundation

was not only supposed to bear the compressive forces but also were required to overcome

the tensile forces to support the weight of the central pylon.

To overcome this problem the wells were designed with 10.5m inner diameter and 17.5m

outer diameter with depth of well going to 25m, the well steining was designed such that

there were

hollow casings left in the well steining placed at an angle of 22.5⊆at their centre in which

Piles can be driven later on after the sinking of the well. These piles will be driven 6m

inside the rock a stratum over which well is resting. The structure of the well will take the

compressive forces and the piles will cancel the effect of tensile forces that will be

generated by the back stay cables.

23

Page 30: BRIEF THEORY OF SIGNATURE BRIDGE

10. Open foundation/Pile foundation Depending upon the type of soil, foundation piles are used in following ways:

a. Bearing piles

b. Friction piles

c. Friction cum bearing piles

The bearing piles are designed as those which transmit the load to foundation strata

directly without taking in to account the frictional resistance offered by enclosing soil. The

passive earth pressure resistance is taken in to account only for the purpose of

determining its resistance against the horizontal force. Such bearing piles are generally

taken up to or in to the hard strata, soft or hard rock, hard consolidated sandy or gravelly

soil.

Friction piles are those in which the load is transmitted by the pile through friction offered

by surrounding soil. Such piles can be provided in cohesive soils not subjected to heavy

scour. Friction cum bearing piles designed in such a way that the load is transmitted both

by friction of the surrounding soil and the bearing resistance of the founding soil at the tip

of pile.

Pile Classification by Construction Method a) Precast Driven Piles –These are usually of RCC or pre-stressed concrete and

generally small in size for ease in handling. The main advantage of this type of pile is

that its quality, in terms of dimension, use of reinforcement and concrete, can be

ensured as the piles are cast in a yard under controlled conditions. However care is

needed while handling, transporting and driving the pile to avoid damages. More to it,

the limitation of length depending upon the capacity of the driving equipment is a

disadvantage as these cannot be taken very deep except by joining. Generally, the

depth over which these are used is restricted to 36 m.

b) Driven Cast-in-Situ Piles- A steel casing pile with a shoe at the bottom is driven first

to the required depth. The reinforcement cage for the pile is then lowered inside the

casing and the pile is concreted. As the concreting of the pile proceeds upwards, the

casing is withdrawn keeping a suitable overlapping length. When such piles are driven

in soft soil and the tube is withdrawn while concreting, it affects resistance and

changes the property of the soil and this also affects the capacity of individual piles.

These are not suitable for use in soft soils, in greater depths or where keying with the

rock is required. 24

Page 31: BRIEF THEORY OF SIGNATURE BRIDGE

c) Bored cast-in-situ piles –In the bored cast-in-situ process, a larger diameter casing is

used. A casing of 3 to 4 m in length is provided on top of the bore hole which is driven

with the help of a bailor. Boring further below this casing is carried out by chiselling

and the side walls are kept stable by circulating bentonite slurry inside the bore hole.

The boring is continued up to the layer decided for founding the structure. After

reaching the desired founding level, the chisel is removed, bore-hole flushed,

reinforcement cage lowered into the hole, and held in position by tack welding it to

the support bars at the top of the casing. After this, concreting is carried out by using

tremie, keeping its end always below the top level of rising concrete. The concreting

is continued till a good quality concrete is seen at the top of the bore hole. After this,

the tremie is removed and when the concrete has reached the top, the casing pipe

on the top is also removed. The bentonite mix should be periodically checked for its

specific gravity and changed as, due to constant use, it can get mixed with the soil

and deteriorate in quality. This type of pile can be used even where the pile is keyed

into the rock as chiselling in the rock can be carried out more easily. These piles serve

as bearing-cum-friction piles. The diameters of such piles are generally more than

1.0m and can go up to 3.6m or more. They can be used singly or in group and are

good replacements for well foundations required for bridge piers in rivers with clayey

and mixed soils. These kind of piles are used being used for piers at western

approach. d) Bored pre-cast piles –In this, as the name itself suggests, a hole is bored using a

casing and a pre-cast pile is inserted into it. After securing it in position, the casing is

withdrawn. A particular process used for bored pre-cast piles is the Benoto process

which involves a steel tube being pushed into the soil, turned and reversed using

compressed air. The tube is in the form of a casing and is driven for the entire depth

after the soil is progressively grabbed from the tube. The process is continued till the

tube reaches the pre-determined level. Then the pre-cast pile is lowered inside and

held in position. The tube is lifted gradually after filling the annular gap between the

pre-cast pile and the soil by grouting. e) Driven steel piles –Steel piles can be circular or in other structural shapes. The

circular ones are made in the form of either welded or seamless piles. Usually steel

25

Page 32: BRIEF THEORY OF SIGNATURE BRIDGE

or cast iron piles used earlier for bridge structures are of longer diameter and screw

type. These were used in past when loading was less. These piles are suitable for

being driven through cohesive soil to reach up to the hard strata and to serve as

bearing piles. They are not suitable where heavy scour is expected and for foundation

for bridges when foundations are situated wide apart.

f) Driven timber piles –Timber piles have been extensively used in America. These have

been used in India on the railways and highways, for temporary bridges. Timber piles

are of hard wood, and used in natural form with thin end cut or suitably sized. They

are used mostly as end-bearing piles in clusters. They are normally used in lengths

of 12m and extended by splicing for use in deeper channels. The piles protruding

above bed/low water level are suitably braced in cluster.

Cast Insitu Piles During drilling of cast insitu piles at Signature Bridge, Wazirabad bentonite was used as

the drilling fluid. Bentonite is used in drilling fluids to lubricate and cool the cutting tools, to

remove cuttings, and to help prevent blowouts. Relatively small quantities of bentonite

suspended in water form a viscous, shear thinning material. At high enough concentrations

(~60 grams of bentonite per liter of suspension), bentonite suspensions begin to take on

the characteristics of a gel (a fluid with a minimum yield strength required to make it

move).for the above reasons it is widely used in construction industry for drilling purposes.

Measures to be taken while boring for cast insitu piles are:

a) During the boring, samples should be taken and sent to the lab for testing or in-situ

tests should be carried out.

b) Dimension of the pile should not be less than that specified. When an enlarged base

is provided, it should be concentric with the pile with a tolerance of 10%.Slope of the

frustum should not be less than 55o. c) If bentonite is used, it should be maintained a minimum of 1.5m above the water table

d) Adequate temporary casing can be provided for ensuring stability near the ground. It

should be backfilled if rapid loss of drilling fluid occurs. The temporary casing should

be free from projections and distortion during concreting.

e) After concreting of the pile, the empty bore hole should be backfilled.

26

Page 33: BRIEF THEORY OF SIGNATURE BRIDGE

Figure 20: Pile Driving

Measures to be taken for reinforcement of a pile

a) Should be pre-assembled and wired into position b) Minimum clear cover of 40mm should be provided and should be increased if the

concrete is in contact with the earth.

c) Joints should be avoided and shall be provided if the full length is not possible. When

joints are provided, appropriate lap length shall be provided to satisfy the

development length criteria.

Measures to be taken during concreting for cast insitu piles:

a) The workability of the concrete should be such that a continuous monolith shaft of full

cross-section is formed. No contamination of concrete is allowed.

b) It should be ensured that mix and placing of concrete does not result in arching. c) Concrete under water or drilling fluid should be poured through tremmie as per IS

2911.Hopper and pile of the tremmie should be clean and watertight.

d) At all times, tremmie should penetrate the previously prepared concrete so as to

prevent contact with the drilling fluid. Sufficient quantity of concrete should be

maintained in the pipe so that pressure exceeds that of the fluid.

e) Internal diameter of the pipe should not be less than 200mm for concrete with max.

size of aggregate 20mm.

27

Page 34: BRIEF THEORY OF SIGNATURE BRIDGE

Measures to be taken while Extracting Temporary Casing: a) Should be lifted while the concrete is sufficiently workable to avoid disturbance or

lifting. b) Concrete should be placed continuously as casing is extracted. c) Pile should be formed at least 30cm above the cut-off level.

Pilling Steps Bored cast in situ piles are constructed in the following sequence

1) Survey: The surveyor set out the center of the bored pile location.

2) Utility diversion: A circular pit of diameter 1700mm and depth 1500 mm shall be

manually excavated at the location to ensure that the utilities are present.

3) Checks for Pile vertically and position: During the process of boring following checks

should be made:

a) Check the verticality of the casing during installation by plumbing from two

perpendicular directions.

b) Check of the eccentricity of the borehole after installation of casing. If the

eccentricity is more than 50mm then reinstallation is done.

c) The verticality of the casing is checked continuously until the toe is reached and

is kept within a tolerance of 50mm.

d) Variation in dimension is limited to +50mm and - 10mm.

e) Variation of level at the top should not be beyond +25mm. 4) Boring of soil-Boring is carried out with the help of a rig up to the required depth. The

verticality of the hole to be bored is kept on monitored and later checked before the

lowering of the reinforcement cage.

5) Installation of temporary casing to stabilize the upper bore, a temporary steel casing

of length 2.5- 3m is installed:

a) A 1000mm diameter hole is drilled using hydraulic boring machine up to a depth of 3-4m.

b) The casing should then be lowered in the hole with the help of a crane.

c) The casing is then driven in to the ground with the help of a rotatory machine

until about 300mm is left above the ground. The rig is then used to progress the

28

Page 35: BRIEF THEORY OF SIGNATURE BRIDGE

d) excavation to the bottom of the casing pipe and then suitable polymer system is

added before further excavation.

e) Bentonite should be added continuously during excavation. And the depth is

measured with the help of the sounding tape.

6) Cleaning of base:

a) Boring is stopped when the toe of the pile level is reached. The borehole is

cleaned carefully and the soil is removed.

b) The depth is checked before the lowering of the cage. 7) Fabrication and installation of reinforcement cage: a) Cutting and bending of bars shall be carried out with approved schedule in fabrication

yard or on the site. Tie wires shall be used for binding the bars. Circular concrete

spacers shall be provided of the same grade of the pile. Vertical distance between

each layer of spacers shall be 4m. The reinforcement cages shall be lowered in the

borehole using steel slings and shackles. Cages shall be spliced on the fabrication

bed and lowered in the trench.

8) Concrete with slump in the range 175+25mm shall be supplied from batching plant.

All concrete delivered shall be visually inspected and checked against delivery note

before being tested and used. Before a pouring is started two delivery trucks should

be available at site.

9) Concrete shall be placed using pipes. 10) Pipes are joined towards into the hole. The end of the pipe should not be more than

300 mm above the bottom of the pile to ensure that free fall of concrete shall not be

more than 1.5m.

11) The concrete shall be discharged from the delivery truck to a hopper connected to

the pipes. As the level of the concrete in the borehole rises, the s shall be withdrawn

accordingly to aid the flow of concrete. Section of the pipe shall be dismantled from

the top as the pipe is withdrawn.

12) During concreting, the level of concrete inside the borehole shall be monitored

either with a weighted tape or chain. Encasing shall be withdrawn after initial setting

of concrete.

29

Page 36: BRIEF THEORY OF SIGNATURE BRIDGE

Figure 21: HSFG 8.8 grade bolt

Figure 22: Placement of steel girders

11. PLACING OF GIRDERS

The portion of the Signature Bridge between P3 and P19 is cable stayed and will not be

loaded on any piers. To support the load of the slabs temporary structures are being

placed on the river bed which will be removed once the precast slabs are stressed to hold

their own load.

During the entire stretch of the bridge 114 main girders will be placed along with 12 cross

girders which will be placed at the distance of 4.5m each. Before these girders are bolted

to the structures they are rested on temporary structures to have a safe working

environment for the labour.

Girders were made out of S355 grade steel bolts were HSFG 10.9 under the pylon and

HSFG 8.8 at all other places. Full strength fully penetrated welds were made during the

preparation of girders. All the girders were mad in a yard in CHINA and were transported

to site via sea and land

. Following procedure was followed while placing the girders at P19 for Insitu slab casting:

30

Page 37: BRIEF THEORY OF SIGNATURE BRIDGE

12. QUALITY ASSURANCE/ QUALITY CONTROL Quality Assurance (QA) refers to the planned and systematic activities implemented in a

quality system so that quality requirements for a product or service will be fulfilled. It is the

systematic measurement, comparison with a standard, monitoring of processes and an

associated feedback loop that confers error prevention. This can be contrasted with

Quality "Control", which is focused on process outputs.

Two principles included in QA are: "Fit for purpose", the product should be suitable for the

intended purpose; and "Right first time", mistakes should be eliminated. QA includes

management of the quality of raw materials, assemblies, products and components,

services related to production, and management, production and inspection processes.

Suitable Quality is determined by product users, clients or customers, not by society in

general. It is not related to cost and adjectives or descriptors such "High" and "Poor" are

not applicable. For example, a low priced product may be viewed as having high quality

because it is disposable where another may be viewed as having poor quality because it

is not disposable.

Quality assurance in construction can be defined simply as making sure the quality of

construction is what it should be. Process Technical Resources has qualified and

experienced personnel that can plan and perform the systematic steps necessary for a

program of quality assurance in construction.

Quality assurance in construction involves all those planned and systematic actions

necessary to provide confidence that the facility will perform satisfactorily in service.

Quality assurance in construction addresses the overall problem of obtaining the quality

of the facility to be built in the most efficient, economical, and satisfactory manner possible.

Within this broad context, quality assurance involves continued evaluation of the activities

of planning, design, development of plans and specifications, advertising and awarding of

contracts, construction, and maintenance, and the interactions of these activities. In its

broadest form quality assurance includes quality control as one of its elements. Quality

control is the responsibility of the contractor, while quality assurance also includes

acceptance. Acceptance involves sampling, testing, and the assessment of test results to

determine whether or not the quality of construction is acceptable in terms of the

specifications. 31

Page 38: BRIEF THEORY OF SIGNATURE BRIDGE

Construction planning is a complex process that must be kept current with the actual

construction taking place in the field. The construction plans, just in terms of day-to-day

changes, must be kept up-to-date. However, in the ebb and flow of events during

construction there are usually a number of schedule changes that arise as a result of

unforeseen ents. Failure to keep the construction planning dynamic and up-to-date

can create confusion and delays.

Not only must the plans keep pace with the daily events communication of the changes in

the co nstruction plans must be disseminated quickly to the affected personnel.

Quality assurance in construction requires that the procedures for incorporating design

changes into the construction plans be well developed and fully utilized. The earlier that

design changes are recognized and implemented the lower the cost. Quality assurance

efforts in construction must closely monitor how well management of the design, and

change of design processes are functioning. These represent the quality issues that need

to be monitored during the quality assurance effort and acceptance testing. Another area of activity for quality assurance in construction that must be continuously

monitored is the development of plans and specifications. Architectural and engineering

plans and specifications often change during the construction phase of a complex project.

It is important that the procedures for incorporating these changes into the construction

plans be well developed and consistently followed.

In order to minimize construction cost while meeting all of the specifications in the plans

and design requires that the advertising for bids and awarding of contracts be closely

monitored. The qualifications of the contractors and subcontractors to perform the services

advertised and meet the quality requirements should be examined carefully all during the

construction phase of the project. This is an element in the program for quality assurance

in construction. Finally, the construction activities should be closely monitored to ensure

that the engineering plans and specifications are being met or exceeded throughout the

construction process.Process Technical Resources has experienced quality assurance

personnel that can develop a quality assurance in construction program that meets the

needs and requirements of the project owner Quality control, or QC for short, is a process

by which entities review the quality of all factors involved in production.

32

Page 39: BRIEF THEORY OF SIGNATURE BRIDGE

Elements such as controls, job management, defined and well managed processes,

performance and integrity criteria, and identification of records

1. Competence, such as knowledge, skills, experience, and qualifications

3. Soft elements, such as personnel integrity, confidence, organizational culture,

motivation, team spirit, and quality relationships.

Controls include product inspection, where every product is examined visually, and often

using a stereo microscope for fine detail before the product is sold into the external

market. Inspectors will be provided with lists and descriptions of unacceptable product

defects such as cracks or surface blemishes for example.

The quality of the outputs is at risk if any of these three aspects is deficient in any way.

Quality control emphasizes testing of products to uncover defects and reporting to

management who make the decision to allow or deny product release, whereas quality

assurance attempts to improve and stabilize production (and associated processes) to

avoid, or at least minimize, issues which led to the defect(s) in the first place. For contract

work, particularly work awarded by government agencies, quality control issues are

among the top reasons for not renewing a contract.

Quality control during the construction process is extremely important in order to

safeguard the value of the owner's investment. Process Technical Services QAQC

personnel can perform checks and tests throughout the construction process, providing

the project owner assurance that the project is being built according to specifications.

The first step in establishing the requirement for construction QAQC is to develop an

overview of the entire quality program. A quality management plan is essential and the

form of the construction organization needs to be established.

The responsibilities and authorities of the various principals in the construction QA/QC

organization need to be established. These include the Environmental Protection Agency

(EPA), the project owner, the engineer of record, the construction manager, and the

construction contractors. Included in this assignment of responsibilities are the

Construction Manager’s quality assurance personnel and the contractor’s quality control

personnel.

33

Page 40: BRIEF THEORY OF SIGNATURE BRIDGE

maintain all submittal files via a combination of a secure document filing and storage

system, and a computerized document tracking system.

General construction inspection and verification requirements include inspections, QC

testing, QA testing, establishing construction acceptance criteria, construction audits,

compliance with handling, storage, packaging, preservation, and delivery requirements,

and material identification and traceability.

Inspections will uncover construction deficiencies. These will need to be identified,

reported and corrective and preventive action taken.

Document handling and retention procedures are important. Records must be updated

on a daily basis and a daily construction report issued. The construction QAQC plan

requires that all construction drawings be stored and that As-Built drawings be prepared

and reviewed.

For any construction activity the Environmental Protection Agency requires submittals

that conform to regulation and must be approved by the EPA prior to construction.

Field changes for QAQC will be limited to the construction QAQC plan and contractor

quality control plan changes. Changes to construction processes or design plans and

specifications are governed by the remedial action work plan and design change order

procedures.

The project owner, the construction manager, site manager, or construction quality

assurance officer may initiate revisions to this construction QAQC plan. It may be revised

whenever it becomes apparent that the construction QAQC procedures or controls are

inadequate to support work being produced in conformance with the specified quality

requirements, or are deemed to be more excessive than required to support work being

produced in conformance with the specified quality requirements.

Construction of a process plant is complex undertaking. However, the project owner is well

advised to invest in QAQC services in order to prevent poor quality construction that may

result in serious project delays and substantial cost over-runs. Process Technical Services

has experienced and qualified personnel that are familiar with construction QAQC

procedures and are available to establish a construction program for your project, or to

provide support for an established construction QAQC project team.

34

Page 41: BRIEF THEORY OF SIGNATURE BRIDGE

13. TESTS CONDUCTED

Test conducted on various materials Various tests are conducted on materials which are used at site as well as for production

of concrete at the Batching Plant. These includes test on cement, fine aggregate, coarse

aggregate, water, bricks, TMT bars etc. Some of these test can be conducted on site where as others are required to be performed

in a lab. The various tests being conducted at The Signature Bridge, Wazirabad site are:

a) Sieve analysis of all the aggregate.

b) Silt Content.

c) Moisture content.

d) Flakiness and elongation.

e) Impact Value test.

f) Abrasion value test.

g) Crushing Value test.

h) 10% fine test.

i) Water pH level, cl level & SO3 content.

j) Cement physical test.

k) Specific gravity & density test.

l) Water testing.

m) TMT bars rusting inspection

35

Page 42: BRIEF THEORY OF SIGNATURE BRIDGE

Test Conducted on Fresh Concrete

Tests for workability:

Concrete is said to be workable when it is easily placed and compacted homogeneously i.e.

without bleeding or Segregation. Unworkable concrete needs more work or effort to be

compacted in place, also honeycombs &/or pockets may also be visible in finished concrete.

Various tests for workability are:

1. Slump test

2. Compaction Factor test. The most commonly used workability test in the field the slump test is

described below.

SLUMP TEST

Apparatus required for Slump Test:

a) Slump mould with bottom diameter 20 cm, Top diameter 10 cm and Height 30 cm.

b) Base plate for fixing the mould.

c) Tamping rod 16mm dia 600 mm long.

36

Figure 23: Test and their Frequency

Page 43: BRIEF THEORY OF SIGNATURE BRIDGE

d) Steel scale. 2) Test procedure:

a) Sampling:

1) From Mixers: At least three approximately equal sample increments totalling to

0.02 m3 shall be taken from a batch during concrete discharge and each sample

increment shall be collected by passing a clean shovel in to the stream of

concrete.

2) From concrete at the time and place of deposition: The sample shall be taken

while a batch of concrete is being, or immediately after it has been, discharge on

the site. The sample shall be collected from not less than five well-distributed

positions, avoiding the edge of the mass where segregation may occur.

The composite sample obtained by either methods described above, shall be mixed well

to ensure uniformity. The sample thus obtained shall be used for the test.

3) Testing

a) Clean the slump mould and fix it firmly with the base plate and keep in a level

ground.

b) Fill the slump cone with the collected concrete sample. Concrete to be filled in

four layers, each layer compacted with the tamping rod 25 blows.

c) While tamping the blows to be distributed uniformly over the cross section, and

the second and subsequent layer should penetrate into the underlying layer.

d) After filling the mould level the top with a trowel and clean the excess concrete

fallen over the base plate.

e) Gently lift the slump cone and allow the concrete to subside.

f) Measure the slump of concrete in millimeter.

Note: Some indication of cohesiveness and workability of the mix can be obtained, if after

the slump test has completed, the side of the concrete is tapped gently with the tamping

rod, a well-proportioned concrete

which has an appreciable slump will gradually slump further, but if the mix has been badly

proportioned, it is likely to fall apart Test Conducted on Hardened Concrete Cube Testing

is conducted on hardened concrete

37

Page 44: BRIEF THEORY OF SIGNATURE BRIDGE

Figure 24: Cube specimen Figure 25 Cube mould

1. Age of Test:

The test shall be conducted at recognized ages of the test specimens, the most usual

being 7 days and 28 days. Where it may be necessary to obtain the strength tests at

1 day and 3 days can also be made. The ages shall be calculated from the time of the

addition of water to the dry ingredients.

2. Number of specimens:

At least three specimens, preferably from different batches, shall be made for testing

at each selected age.

Note: When a full investigation is being carried out, it is advisable for three separate

batches to be made for each given variable. An equal number of specimens for each

variable should be made.

3. Procedure:

Specimens stored in water shall be tested immediately on removal from the water and

while they are still in wet condition. Surface water and grit shall be wiped off the

specimens and any projecting fins removed. Specimens when received dry shall be

kept in water for 24 hours before they are taken for testing. The dimension to the

nearest 0.2mm and the weight shall be noted before testing.

1. Placing the specimen in the testing machine. The bearing surface of the testing

machine shall be wiped clean and any loose sand or other material removed from

Page 45: BRIEF THEORY OF SIGNATURE BRIDGE

Figure 25: Compression testing machine

the surface of the specimen which are in contact with the bearing plates.

2. The cubes shall be placed inside the machine in such a way the load applied to

the cube in the opposite direction of the cube as cast.

3. Cubes shall be carefully aligned to the center of the bearing plates so that the

axial load is applied to the specimen.

4. No packing to be used between the specimen and the bearing plate. Adjust the

top plate so that it will have a flat seating on the specimen.

5. Apply load at the rate of 140 kg/cm2 (approximately 310 KN) per minute.

6. Apply load until failure of the specimen, (i.e. the specimen shall not sustain any

further loading) and note down the maximum load at which the specimen has

failed.

4. Calculations: The average of the three values of strength shall be taken as the representative strength

of the batch provided. The individual variation is not more than + 15 % form the average.

Maximum load at which the specimen failed

Strength of specimen = ------------------------------------------------------

kg/cm2 Area of the specimen

Page 46: BRIEF THEORY OF SIGNATURE BRIDGE

Figure 26: Silt content test

Silt content Test: There are two types of harmful substances preset in fine aggregates i.e. organic matter

produced by decay of vegetable matter and/or clay and silt,which form coating thus

preventing a good bond between cement and the aggregates. If present in large quantities,

result in the increase water-cement ratio and finally affecting the strength of concrete. Field

test is generally conducted in order to determine the volumetric percentage of silt in natural

sand for percentage up to 8%, otherwise more detailed test as prescribed by standard

code are required to be conducted.

Page 47: BRIEF THEORY OF SIGNATURE BRIDGE

14. CONCLUSION After having completed my training, I have gained some basic knowledge in the field of

bridge construction. This industry has familiarized me with the industry and its

requirements. I have been exposed to the standard requirement that needs to be followed

during designing during my internship period. Also, this internship has proved how crucial

it is to have a good understanding and proper communication between the site and office,

One of the primary objective of the project was to understand the economic factor and how

things are implemented. This internship has further opened the doors of research in this

field and also emphasized on the use of innovative and unconventional means to achieve

the desired objective. Basically, the whole thing can be summed up to the fact that- to

erect a structure that is satisfying the norms within the given limits, using the minimum

possible resources because if the economy of that particular structure is considered and

it is seen that all the resources have been over used, then it is a unnecessary waste of

public money. On the other hand if the resources are under used the structure will be

highly uneconomical but not safe. So, again the public interest is being violated and it is

not permissible at all.

For any country to progress it needs to have a proper infrastructure else no development

can proceed from the word go. So as a civil engineer we will have to be focused and

determined on the things at hand because if we fail in our duties the result will be

hazardous. An engineer learns with time and as he gathers experience. This was a

beginning and still there is a long way to go. There are many things learn from the books

and experience to gather from real life scenarios but all that I hope at this point of time is

that all these factors together mould me into a good civil engineer and more importantly a

better human being.

Finally, I conclude that this project has met all its objectives and the results speak for

themselves. On this note I come to the end of my project.