bridgewater canal construction update bridgewater canal community stakeholder meeting 3 december...

Download Bridgewater Canal Construction Update Bridgewater Canal Community Stakeholder meeting 3 December 2014

If you can't read please download the document

Upload: edgar-wells

Post on 18-Dec-2015

213 views

Category:

Documents


0 download

TRANSCRIPT

  • Slide 1
  • Bridgewater Canal Construction Update Bridgewater Canal Community Stakeholder meeting 3 December 2014
  • Slide 2
  • Bridgewater Canal construction sites
  • Slide 3
  • Construction packages 24 345 4 4 1 6
  • Slide 4
  • Package 1 Nasmyths Steam Hammer
  • Slide 5
  • Built in 1851 for Elsecar Colliery, Yorkshire At an advanced state of disrepair Contractors appointed: Landscaping Casserly Property Management Restoration works Calibre Metalwork Limited Protective canopy Canal Engineering Limited Landscaping works nearing completion Conservation and canopy works to complete by February 2015
  • Slide 6
  • Nasmyths Steam Hammer
  • Slide 7
  • Package 2 Worsley Green Monument
  • Slide 8
  • Built in 1905 as a monument to the Duke of Bridgewater In a poor state of repair Recclesia Ltd appointed as contractor Works in two stages: Vegetation removal complete by 4 th Dec 2014 (1 day) Conservation works start on site in March 2015, complete by 30 th April 2015 (8 weeks)
  • Slide 9
  • Package 3 Worsley Delph
  • Slide 10
  • Slide 11
  • Worsley Delph - visualisation
  • Slide 12
  • Worsley Delph visualisation
  • Slide 13
  • Worsley Delph - visualisation
  • Slide 14
  • Progress to date Design work progressing and expected to be finalised by February 2015 Site investigations ongoing: - Ecology surveys ongoing - Archaeological trial pits complete - Laser survey and trial pits in workshops complete - Silt stabilisation trials complete - Excavations of sluice gate contractor appointed - Boreholes / trial pits to be provided to contractor as part of tender package Procurement - Tendering Feb 2015 April 2015 Timescales (anticipated) - Contractor appointment June 2015 - De-silting design / regulatory approvals Sept 2015 - Construction phase Sept 2015 July 2016 (36 weeks)
  • Slide 15
  • Work package 4 Civil Engineering
  • Slide 16
  • Towpath improvements
  • Slide 17
  • Boothstown towpath Design work progressing - Alignment agreed with Bridgewater Canal Company - Liaising with Environment Agency / Viridor re: outstanding design issues Timescales (anticipated) - Contractor appointment Jun 2015 - Construction phase Jan May 2016 (18 weeks)
  • Slide 18
  • Barton towpath Design work progressing well - Cross sections to be agreed with Bridgewater Canal Company - Advance tree removal works may need to take place prior to works starting Timescales (anticipated) - Contractor appointment Jun 2015 - Construction phase Aug Nov 2015 (12 weeks)
  • Slide 19
  • Barton Aqueduct Design work to be complete by Dec 2014 - layout agreed with Peel Ports Site investigations / pre-treatment - Japanese Knotweed stem injection treatment undertaken - Ivy removed from Brindleys aqueduct Timescales (anticipated) - Contractor appointment Jun 2015 - Construction phase Aug Dec 2015 (16 weeks)
  • Slide 20
  • Barton Aqueduct - visualisation
  • Slide 21
  • Slide 22
  • Barton Aqueduct ivy removal
  • Slide 23
  • Dukes Drive Design work nearing completion Timescales (anticipated) - Contractor appointment Jun 2015 - Construction phase Jul Aug 2015 (6 weeks)
  • Slide 24
  • Patricroft Canalside Hall Bank Draft options produced Ongoing liaison with Network Rail and Urban Vision Highways Work closely aligned to Port Salford Greenway Timescales (anticipated) - Contractor appointment Jun 2015 - Construction phase August 2015 (4 weeks)
  • Slide 25
  • Work package 5 Bridgewater Park
  • Slide 26
  • Proposed transfer of site from Peel Holdings to city council Funding package needs to be sourced Procurement: - to be procured seperately
  • Slide 27
  • Overarching package Interpretation
  • Slide 28
  • Interpreting the canal some ideas!
  • Slide 29
  • Timetable
  • Slide 30
  • Slide 31
  • Questions?