bridgewater canal construction update bridgewater canal community stakeholder meeting 3 december...
TRANSCRIPT
- Slide 1
- Bridgewater Canal Construction Update Bridgewater Canal Community Stakeholder meeting 3 December 2014
- Slide 2
- Bridgewater Canal construction sites
- Slide 3
- Construction packages 24 345 4 4 1 6
- Slide 4
- Package 1 Nasmyths Steam Hammer
- Slide 5
- Built in 1851 for Elsecar Colliery, Yorkshire At an advanced state of disrepair Contractors appointed: Landscaping Casserly Property Management Restoration works Calibre Metalwork Limited Protective canopy Canal Engineering Limited Landscaping works nearing completion Conservation and canopy works to complete by February 2015
- Slide 6
- Nasmyths Steam Hammer
- Slide 7
- Package 2 Worsley Green Monument
- Slide 8
- Built in 1905 as a monument to the Duke of Bridgewater In a poor state of repair Recclesia Ltd appointed as contractor Works in two stages: Vegetation removal complete by 4 th Dec 2014 (1 day) Conservation works start on site in March 2015, complete by 30 th April 2015 (8 weeks)
- Slide 9
- Package 3 Worsley Delph
- Slide 10
- Slide 11
- Worsley Delph - visualisation
- Slide 12
- Worsley Delph visualisation
- Slide 13
- Worsley Delph - visualisation
- Slide 14
- Progress to date Design work progressing and expected to be finalised by February 2015 Site investigations ongoing: - Ecology surveys ongoing - Archaeological trial pits complete - Laser survey and trial pits in workshops complete - Silt stabilisation trials complete - Excavations of sluice gate contractor appointed - Boreholes / trial pits to be provided to contractor as part of tender package Procurement - Tendering Feb 2015 April 2015 Timescales (anticipated) - Contractor appointment June 2015 - De-silting design / regulatory approvals Sept 2015 - Construction phase Sept 2015 July 2016 (36 weeks)
- Slide 15
- Work package 4 Civil Engineering
- Slide 16
- Towpath improvements
- Slide 17
- Boothstown towpath Design work progressing - Alignment agreed with Bridgewater Canal Company - Liaising with Environment Agency / Viridor re: outstanding design issues Timescales (anticipated) - Contractor appointment Jun 2015 - Construction phase Jan May 2016 (18 weeks)
- Slide 18
- Barton towpath Design work progressing well - Cross sections to be agreed with Bridgewater Canal Company - Advance tree removal works may need to take place prior to works starting Timescales (anticipated) - Contractor appointment Jun 2015 - Construction phase Aug Nov 2015 (12 weeks)
- Slide 19
- Barton Aqueduct Design work to be complete by Dec 2014 - layout agreed with Peel Ports Site investigations / pre-treatment - Japanese Knotweed stem injection treatment undertaken - Ivy removed from Brindleys aqueduct Timescales (anticipated) - Contractor appointment Jun 2015 - Construction phase Aug Dec 2015 (16 weeks)
- Slide 20
- Barton Aqueduct - visualisation
- Slide 21
- Slide 22
- Barton Aqueduct ivy removal
- Slide 23
- Dukes Drive Design work nearing completion Timescales (anticipated) - Contractor appointment Jun 2015 - Construction phase Jul Aug 2015 (6 weeks)
- Slide 24
- Patricroft Canalside Hall Bank Draft options produced Ongoing liaison with Network Rail and Urban Vision Highways Work closely aligned to Port Salford Greenway Timescales (anticipated) - Contractor appointment Jun 2015 - Construction phase August 2015 (4 weeks)
- Slide 25
- Work package 5 Bridgewater Park
- Slide 26
- Proposed transfer of site from Peel Holdings to city council Funding package needs to be sourced Procurement: - to be procured seperately
- Slide 27
- Overarching package Interpretation
- Slide 28
- Interpreting the canal some ideas!
- Slide 29
- Timetable
- Slide 30
- Slide 31
- Questions?