MEASUREMENT QUANTITIES FOR PILING WORKS

PREPARED BY :ROHAIDAH BINTI MD NOR013-3648820

Page 2: Boq   piling works

PILING

Building structure that receive load and spread the load to the soil underground

Most important element in building structureCan be obtainable in various form and size.

Type of piling depends on Soils conditions Design loads Site requirements

Page 3: Boq   piling works

COMES IN VARIOUS SIZE3M, 6M, 9M AND 12MRC NORMALLY RETANGULAR SHAPETIMBER IN CIRCULAR SHAPE

SOURCE OF SUPPLYCAN BE OBTAIN DIRECT FROM MANUFACTURER CAST ON SITE

FORMOne pile pont in pile cap-singularMore than 1 –cluster

Page 4: Boq   piling works

CLASSIFICATION OF PILES

CLASSIFICATION OF PILE ACCORDING TO TYPE OF MATERIALS USED :

TIMBERSTEELCONCRETECOMPOSITE PILES

Page 5: Boq   piling works

SEQUENCES OF PILING WORK

Page 6: Boq   piling works
Page 7: Boq   piling works
Page 8: Boq   piling works
Page 9: Boq   piling works
Page 10: Boq   piling works
Page 11: Boq   piling works
Page 12: Boq   piling works
Page 13: Boq   piling works
Page 14: Boq   piling works
Page 15: Boq   piling works
Page 16: Boq   piling works
Page 17: Boq   piling works
Page 18: Boq   piling works
Page 19: Boq   piling works
Page 20: Boq   piling works
Page 21: Boq   piling works
Page 22: Boq   piling works
Page 23: Boq   piling works

LOAD TEST BEING CARRIED OUT

Page 24: Boq   piling works
Page 25: Boq   piling works

SENARAI PENGUKURAN KUANTITI (TAKING OFF LIST)

Definition - List of items that needs to be measured complete with its units

Why prepared?

1)To make sure no missing items2)To cross out the items that already measured so as to avoid doubled measurement

Page 26: Boq   piling works

Examples of Taking Of List (TOL)

Items Units

Bringing in and removing plant Item

Maintaining plant on site Item

Supply of initial piles No

Supply of extension piles <3.00m long M

Supply of extension piles > 3.00m long M

Driven depth M

Pile extension No

Cut Off piles No

Prepare piles head No

Load test Item

Page 27: Boq   piling works

SENARAI PERTANYAAN (QUERRY LIST)

1)Table of query that needs clarification from architect, engineers regarding inaccurate information, discrepancies in drawing and specification, missing items etc2)The architect/engineers needs to verify the queries and answers

Page 28: Boq   piling works

EXAMPLES OF QUERY LISTS

ITEM QUERRIES ASSUMPTIONS

REMARKS

1 Size of ceiling joint 100mm x 50mm

2 Type of timber for roof members

Pressure Treated Grade B timber

3 Height of walls tiles at kitchen not given

To ceiling height(3600mm high)

Page 29: Boq   piling works

SCHEDULE OF PILES CAP

LOCATION TYPES OF PILES CAP

P1 P2 P3

A/1-4 2

B/1-4 2 1

C/1-4 2 1 1

D/1-4 4

TOTAL 10 2 1

Page 30: Boq   piling works

Item Bringing plant to and removing from site all plant required for this section of work

Item Maintaining on site all plant required for this section of work

2/3/4/

1021

Supply 200mm x 200mm Precast concrete piles “UCP” 6.00m long complete with 200mm x 200mm x 1.25 mils steel head and 200mm x 200mm x 10kg m.s. shoe obtainable from UCP Manufacturing Sdn. Bhd.(P1(P2(P3

Page 31: Boq   piling works

2/103/24/1

14.0014.0014.00

Driven, 200mm x 200mm precast concrete piles

(P1(P2(P3

2/103/24/1

222

Precast concrete piles extension

(P1(P2(P3

Page 32: Boq   piling works

2/103/24/1

3.003.003.00

Supply 200mm x200mm Precast concrete extension piles”UCP” not exceeding 3.00m depth

(P1(P2(P3

2/103/24/1

6.006.006.00

Ditto, exceeding 3.00m long

(P1(P2(P3

Page 33: Boq   piling works

2/3/4/

1021

Cut off top of piles to required levels

(P1(P2(P3

2/3/4/

1021

Prepare concrete pile heads and reinforcement for capping

(P1(P2(P3

Page 34: Boq   piling works

Item

Item

Item

Allow for 1 No testing on a group of 4 Nos 200mm x 200mm piles by kentledge s to a total load of 360 tonnes (twice their combined working loads)

&

Ditto, 1 No testing on a group of 3 Nos 200mm x 200mm piles by kentledge s to a total load of 270 tonnes , ditto

&

Ditto, 1 No testing on a group of 2 Nos 200mm x 200mm piles by kentledge s to a total load of 180 tonnes , ditto

Page 35: Boq   piling works