bond construction update citizen’s oversight committee
DESCRIPTION
Bond Construction Update Citizen’s Oversight Committee. Long Beach Community College District January 25, 2010. EDUCATE ENGAGE EMPOWER. Agenda. Completed Construction Projects LAC South Quad Complex PCC Industrial Tech Phase 1 Los Coyotes Property Upgrades - PowerPoint PPT PresentationTRANSCRIPT
Bond Construction Bond Construction UpdateUpdate
Citizen’s Oversight Citizen’s Oversight CommitteeCommittee
Bond Construction Bond Construction UpdateUpdate
Citizen’s Oversight Citizen’s Oversight CommitteeCommittee
Long Beach Community College District January 25, 2010
EDUCATE ENGAGE EMPOWER 1
Agenda Completed Construction Projects
LAC South Quad Complex PCC Industrial Tech Phase 1 Los Coyotes Property Upgrades Bldg. F - Conversions of rooms F104 and F106 to new classroom space. Bldg. G and H - Repainting
Current & Upcoming Construction Projects LAC Building A, Student Services Retrofit LAC Math Technology Building LAC Parking Structure LAC Building O Complex LAC Infrastructure Improvements LAC Q & R ADA/HVAC UpgradesLAC Q & R ADA/HVAC Upgrades LAC Building I (Bookstore)LAC Building I (Bookstore) PCC MDAB (Multi-Disciplinary Academic Building) PCC Building CC Retrofit District Wide – Electronic Signage Plan Upcoming Projects Planned Phasing of Future Projects
Q & A
2
CompletedConstruction Projects
Space includes Approx. 68,000 ASF 32 modern classrooms and labs 38 faculty offices Executive offices Multipurpose room State of the art Board Room
South Quad Complex – Measure E 2002South Quad Complex – Measure E 2002
3
CompletedConstruction Projects
Modern facility houses Welding Department and other trade programs
Replaces existing antiquated structures New Northern face of the campus
PCC Industrial Technology Center Phase 1PCC Industrial Technology Center Phase 1
Measure E 2002Measure E 2002
4
Current and UpcomingConstruction Projects
LAC Building A – Student Services RetrofitLAC Building A – Student Services Retrofit
Measure E 2008Measure E 2008
5
Plans submitted to DSA September 2009 Adds 6,500 Sq. Ft. to existing building Will house A&R, Counseling, Health Services, Cashier, Transfer Ctr., etc. Estimated start of construction end of Fall 2010
Current and UpcomingConstruction Projects
Completed Schematic Design Will house Math and Culinary Arts instructional
program as well as Reprographics Estimated start of construction Winter 2013
LAC Math Technology Building – Measure E 2008LAC Math Technology Building – Measure E 2008
6
Current and UpcomingConstruction Projects
LAC Parking Structure – Measure E 2008LAC Parking Structure – Measure E 2008
7
Spaces for 900 Vehicles Photovoltaic Electrical Generation Array on top level To be located Southeast corner of Lot J adjacent to the Verizon building Outfitted with single-axis tracking system Minimum 450 KW+ output Curriculum building opportunity Exhibit classroom Groundbreaking anticipated February, 2010
Current and UpcomingConstruction Projects
LAC Building O Complex – Measure E 2008LAC Building O Complex – Measure E 2008
8
Two structures totaling 87,000 square feet
Current Occupants: ERD, Foundation, Warehouse
Facility, and one leasee Future Occupants:
IITS and BMT Potential rental spaces being
assessed
9
LAC Infrastructure Improvement ProjectsLAC Infrastructure Improvement Projects
Measure E 2008Measure E 2008
Current and UpcomingConstruction Projects
Project to be completed in a phased construction schedule
Total annual estimated savings of 1.5 million Kwh
Project started Fall 2009. Anticipated completion Summer 2011
Upgrades include; Reclaimed Water, Domestic Water, Data, etc.
Majority of existing building HVAC systems to be connected to new infrastructure
Landscaping upgrades to be implemented in conjunction with infrastructure project phasing
Current and UpcomingConstruction Projects
10
Complete building ADA upgrade: includes restrooms, stair lift, etc. (Bldg. R)
All new infrastructure: new piping, fixtures, etc. (Bldg. R) Minor renovations to offices (Bldg. R) Total renovation of locker/training rooms (Bldg. R) HVAC upgrade: includes new air handlers, ductwork, etc.
(Bldg. Q & R) Update fire alarm system (Bldg. Q & R) Construction will be done in phases so as to minimize
disruption of classes Final construction documents submitted to DSA Fall 2009 Estimated start of construction Summer 2010
LAC Q & R ADA/HVAC - Measure E 2008LAC Q & R ADA/HVAC - Measure E 2008
Current and UpcomingConstruction Projects
11
Add additional 4,000 square feet to existing building Architecture to match LAC Mediterranean Theme Submitted for DSA review Construction scheduled for Summer 2010
LAC Building I - Measure E 2008LAC Building I - Measure E 2008
Current and UpcomingConstruction Projects
PCC MDAB PCC MDAB (Multi-Disciplinary Academic Building) - Measure E 2002(Multi-Disciplinary Academic Building) - Measure E 2002
12
Received reviewed plans from DSA. Currently in construction drawing technical review phase Install portables for swing space at PCC Spring 2010 Anticipated start of MDAB construction Summer 2010 Project to be completed in two phases
Current and UpcomingConstruction Projects
PCC Building CC Retrofit - Measure E 2008PCC Building CC Retrofit - Measure E 2008
13
To be designed by Hill Partnership Architects Houses the Fitness Center, Gymnasium, Weight Room, and
Faculty and Staff Offices Swing space to be located on PCC Campus (Bldg. GG) To be completed concurrently with MDAB project phase 2 Anticipated start of construction Summer 2011
Current and UpcomingConstruction Projects
District Wide – Electronic Signage PlanDistrict Wide – Electronic Signage Plan Measure E 2008Measure E 2008
14
District Wide Signage Plan complete Final site locations determined Construction bids received/NTP to be issued Anticipated construction completion of
Marquee Signs Summer 2010
Current and UpcomingConstruction Projects
17
LAC Expansion of Building I (Awaiting DSA approval)
Bookstore swing space to be located West of J building. Relocate Bond Management Team Offices to O Building (Community Outreach and
Services Facility) and removal of W trailers (Fall 2010)
Increase parking at Faculty and Lew Davis St. IITS relocation to O building Bldg. K – Roof extension over Kiln area Bldg. J – Theater lighting control panel replacement CDC – new carpet installation
PCC Bldg. JJ – Add new landscaping around perimeter MDAB swing space preparation Install exterior lighting at Tech1 Demolition of UU and VV
Upcoming ProjectsUpcoming Projects
Planned Phasing of Future Projects
18
2009-10 Parking Structure – groundbreaking anticipated
February 2010 Building O2 occupancy scheduled
BMT and IITS – Fall 2010 Begin infrastructure construction – Fall 2009
Master landscaping implementation will follow this project
Install portables for swing space at PCC – Spring 2010
Begin construction of Buildings DD and EE at PCC Anticipating Summer 2010 start
Anticipating swing space move for Building A at LAC – Summer 2010
Marquees complete – Summer 2010
Planned Phasing of Future Projects
19
2010-11 Begin Building R (Gym) HVAC and ADA upgrades –
Summer 2010 Anticipating Summer 2011 completion
Begin construction of Building I (Bookstore) and move to portable swing space – Summer 2010
Retrofit completion of Building Z – Summer 2010 Begin construction of Building A at LAC – Fall 2010
Begin Schematic Design for Buildings C and F at LAC
Submit plans to DSA no later than Summer 2011
Planned Phasing of Future Projects
20
2011-12 Infrastructure project complete at LAC – Summer 2011 Submit plans to DSA for Math/Technology Building at LAC –
Summer 2012
Construction completion of Buildings DD and EE at PCC – Summer 2011
Begin construction of Buildings AA, BB and CC at PCC – Summer 2011
Anticipated construction completion of Building I (Bookstore) at LAC – Fall 2011
Anticipated construction completion of Parking Structure at LAC – Spring 2012
Planned Phasing of Future Projects
21
2012-13 Move Buildings C and F programs into Swing Space (M/N
Building) and begin construction – Summer 2012
Anticipated Construction completion of Building A at LAC – Summer 2012
Submit plans to DSA for M/N Building at LAC and Building MM (Phase 1) at PCC – Summer 2012
Begin Schematic Design for Building P at LAC and Building MM (Phase 2) at PCC – Summer 2012 Submit to DSA – Spring 2013
Begin construction of Math/Technology Building at LAC – Winter 2013
Planned Phasing of Future Projects
22
2012-13 (continued)
Begin Schematic Design for Building D and E renovations – Fall 2013
Anticipated Construction completion of Buildings AA, BB and CC at PCC – Spring 2013
Planned Phasing of Future Projects
23
2013-14 Anticipated Construction completion of Buildings C and F at
LAC – Fall 2013
Begin construction of Buildings M/N at LAC and MM (Phase 1) at PCC – Fall 2013
Submit plans to DSA for Buildings D and E renovations at LAC – Fall 2013
Schematic design for Performing Arts Building (G & H) and Building R at LAC – Spring 2014
Planned Phasing of Future Projects
24
2014-15 Anticipated Construction completion of Math/Technology
Building at LAC – Summer 2014
Begin construction on Buildings D and E at LAC – Fall 2014
Submit plans to DSA for Performing Arts Building and Building R (Gym) at LAC – Spring 2015 Anticipate construction start – Spring 2016
Anticipated construction completion of Buildings M/N at LAC and MM at PCC – late Spring 2015
Begin construction on Buildings P at LAC and MM (Phase 2) at PCC – Spring 2015