Bond Construction Bond Construction UpdateUpdate
Citizen’s Oversight Citizen’s Oversight CommitteeCommittee
Bond Construction Bond Construction UpdateUpdate
Citizen’s Oversight Citizen’s Oversight CommitteeCommittee
Long Beach Community College District January 31, 2011
EDUCATE ENGAGE EMPOWER 1
Agenda
Completed Construction Projects District Wide – Electronic Signage Plan
Current Construction Projects LAC Building A – Student Services Retrofit LAC Parking Structure LAC Building O Complex LAC Infrastructure Improvements Project and District Wide –
Energy Efficiency Project LAC Building I (Bookstore) LAC South Walkway Extension PCC MDAB (Multi-Disciplinary Academic Building) PCC Walnut Ave. Arrival Court District Wide – Monument Signs
Upcoming Construction Projects LAC W Trailers Demo PCC Building CC Retrofit
Q & A
2
Completed Construction ProjectsDistrict Wide – Electronic Signage PlanDistrict Wide – Electronic Signage Plan
Measure E 2008Measure E 2008
3
District Wide Signage Plan complete for LAC & PCC
Construction completed Fall 2010
Current Construction ProjectsLAC Building A – Student Services RetrofitLAC Building A – Student Services Retrofit
Measure E 2008Measure E 2008
4
Adds 6,500 Sq. Ft. to existing building Notice To Proceed given to SMC Construction on 12/29/10 Will house A&R, Counseling, Health Services, Cashier, Transfer Ctr., etc. End of construction anticipated Summer 2012
Current Construction ProjectsLAC Parking Structure – Measure E 2008LAC Parking Structure – Measure E 2008
5
Spaces for 900 Vehicles Finalizing installation of solar arrays, irrigation, signage,
and data/telecom runs Anticipated end of Construction Spring 2011
Current Construction ProjectsLAC Building O Complex – Measure E 2008LAC Building O Complex – Measure E 2008
6
Two structures totaling 87,000 square feet Occupants for Building O2 are Foundation, ERD, tenants,
and ALCI (soon to come) Occupants for Building O1 will be IITS, BMT, and Warehouse
Facility Anticipated completion February 2011
7
LAC Infrastructure Improvement Project and District LAC Infrastructure Improvement Project and District Wide Energy Efficiency Project Measure E Wide Energy Efficiency Project Measure E
20082008
Current Construction Projects
Total annual estimated savings of 1.5 mil. Kwh Project started Fall 2009; currently working on phase 6
(partial), 7, 8A, 9A (Landscape), and 10 (G and H Quad area)
Majority of existing building HVAC systems to be upgraded and connected to the Central Plant Buildings G & H are connected Buildings B, C, D, E, and J will be scheduled in the next couple
months
Exterior lighting and controls upgrades All parking lots north of Lew Davis are on new system
New Reclaimed Water tie-ins to irrigation still to come New gas lines installed for Buildings B, C, D, E, G, H, J, M,
N, and P New domestic lines installed for Buildings B, C, D, E, F, G,
H, I Trailers, J, K,L, M, N, P Anticipated end of construction Winter 2011
Current Construction Projects
8
Adds additional 4,000 square feet to existing building Architecture to match LAC Mediterranean Theme Notice To Proceed given to G2K Construction on 11/15/10 End of Construction anticipated Fall 2011
LAC Building I - Measure E 2008LAC Building I - Measure E 2008
Current Construction ProjectsLAC South Walkway ExtensionLAC South Walkway Extension
Measure E 2008Measure E 2008
9
99% complete Currently going through final punch-list Continues Master Plan pedestrian corridor
Current Construction ProjectsPCC MDAB PCC MDAB
(Multi-Disciplinary Academic Building)(Multi-Disciplinary Academic Building)Measure E 2002 and 2008Measure E 2002 and 2008
10
Notice To Proceed issued on 7/29/10 Currently in phase 1 of construction (DD and EE in construction) Portables for swing space installed Summer 2010 complete
and occupied (MD Trailers) Project to be completed in two phases – estimated completion
for DD and EE is Summer 2012
Current Construction Projects
11
UU/VV demo completed Currently grading site Site to be converted to a parking lot. Estimated end of construction Spring 2011
PCC Walnut Ave. Arrival Court - Measure E 2008PCC Walnut Ave. Arrival Court - Measure E 2008
Current Construction ProjectsDistrict Wide – Monument SignsDistrict Wide – Monument Signs
Measure E 2008Measure E 2008
12
District Wide Monument Signs Locations:
LAC-Clark/Conant – installed January 8, 2011 PCC-20th/Walnut Ave. – installation still to come
Installation of building designators for LAC Bldg. O1 and O2 completed
Estimated construction completion Spring 2011
LAC Bldg. Designator LAC Monument SignPCC Monument Sign
Upcoming Construction Projects
13
Design for site completed W Trailers to be demolished Site to be converted to a parking lot and a bio-swale Board of Trustees approved on 1/18/11 to Green Giant Notice to Proceed to be issued once docs have been submitted by
contractor
LAC W Trailers Demo - Measure E 2008LAC W Trailers Demo - Measure E 2008
Upcoming Construction ProjectsPCC Building CC Retrofit - Measure E 2008PCC Building CC Retrofit - Measure E 2008
14
Houses the Fitness Center, Gymnasium, Weight Room, and Faculty and Staff Offices
Swing space located on PCC Campus (Bldg. GG) Approved by DSA on 1/27/11. Bid process to commence shortly To be completed concurrently with MDAB project phase 1 Anticipated end of construction 2012
l i b
e r
a l
a r
t s
Liberal Arts CampusSite Plan
p a
c i f
i c
c
o a
s t
Pacific Coast CampusSite Plan
QUESTIONS&
ANSWERS
EDUCATE ENGAGE EMPOWER 17