boiler replacement and plant room refurbishment in the finance …€¦ · the plant room was...

2
Boiler Replacement and Plant Room Refurbishment in the Finance Sector

Upload: others

Post on 05-Jun-2020

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Boiler Replacement and Plant Room Refurbishment in the Finance …€¦ · the plant room was needed to accommodate the new boiler. All pipework, pumps and valves were replaced and

Boiler Replacement and Plant Room Refurbishment in the Finance Sector

Page 2: Boiler Replacement and Plant Room Refurbishment in the Finance …€¦ · the plant room was needed to accommodate the new boiler. All pipework, pumps and valves were replaced and

Antac was instructed to replace

the twenty fi ve year old gas

boilers for a leading fi nancial

services customer. The existing

installation consisted of four

separate boilers feeding into

a common hot water system,

where meeting the heating

demand was achieved through

controlling the number of boilers

operating.

The Challenge

They needed a high effi ciency

heating solution which not only

achieved savings in energy

costs, but helped meet its CSR

objectives. Additionally this

offi ce building would be fully

occupied throughout the four

week programme of works and a

temporary heating solution was

provided by Antac’s own portable

gas boiler.

The Solution

Antac selected an Alpha ARES

Tec condensing boiler as the best

heating solution. This is a fl oor

standing condensing boiler that

provides an infi nitely fl exible

solution for buildings requiring

high output heating. It is made

up of a number of self-contained

heat generating modules

forming a series of boilers linked

together within a single casing.

Each heat generating module

is self-contained, with its own

down-fi ring pre-mix gas burner,

fan, ignition and safety controls.

As system load decreases, a

built-in Boiler Cascade Manager

modulates the boiler down to

the combined minimum. As

the load continues to reduce,

individual modules are switched

off as necessary. This modular

design enables ARES Tec boilers

to optimise energy effi ciency

achieving up to 109%.

Installation

An extensive refurbishment of

the plant room was needed to

accommodate the new boiler.

All pipework, pumps and valves

were replaced and the boiler

was connected indirectly via a

plate heat exchanger to reduce

boiler contamination extending

its life. Alterations had to be

made to the roof due to the

newly installed single fl ue. Antac

integrated the boiler controls

into the existing Trend BMS and

re-commisioned the system.

About Antac >>>

Antac is a multi service provider

established in 2001. Over the

last 14 years our business has

continued to grow and today

we provide services throughout

the UK. Antac has established

an enviable reputation of

delivering quality services,

value for money and customer

care, demonstrated through

our long term relationships and

business retention. Our ethos is

to “deliver what we promise”

making us the service provider

that you can trust.

Our skilled teams enable us to

deliver tailored solutions which

meet our clients differing needs.

Our strong experienced manage-

ment team coupled with our

highly trained operatives and

innovative quality systems

enable Antac to deliver excellent

services to our clients.

Antac Support Services Ltd

Unit 1, Lisle Road

Hughenden Avenue

High Wycombe

HP13 5SQ

www.antac.co.uk

Phone: 0870 600 8686

Email: [email protected]

Project Key Facts:

ü Alpha Ares boiler is up to 109% effi cient

ü Antac provided its own temporary boiler

ü Completed within a four week programme

ü High effi ciency plate heat exchanger used

ü All pipe work, valves and pumps upgraded

Antac removes four obsolete boilers

and replaces them with a single 660

kW high effi ciency condensing boiler.

Project included integration into the

existing Trend BMS.