boardman river wall stabilization project

14
BOARDMAN RIVER WALL STABILIZATION PROJECT DOWNTOWN DEVELOPMENT AUTHORITY MEETING APRIL 16, 2021

Upload: others

Post on 15-Nov-2021

1 views

Category:

Documents


0 download

TRANSCRIPT

BOARDMAN RIVER WALL STABILIZATION

PROJECT

DOWNTOWN DEVELOPMENT AUTHORITY MEETING

APRIL 16, 2021

PROJECT CONTEXT

2 smithgroup.com

Study Area-100 and 200 blocks of East Front Street

Front Street

Un

ion

Str

ee

t

Ca

ss

Str

ee

t

WALL CONDITIONS

3 smithgroup.com

Existing Wall

River Scouring Under Wall

Existing Surface

Soil Subsidence

Timber Piles Supporting Wall

Existing 24”Sanitary Sewer

Wall Cross Section Looking West

WALL CONDITIONS

4 smithgroup.com

Wall Elevation View From River

Summary of Issues• Continued soil subsidence = pavement failure and disappearing parking

signs.• Issues with multiple sanitary sewer service line failures and river pollution.• Ground water infiltration into sanitary sewer increases treatment plant costs

and potential for sewage releases into river.• Long term destabilization of wall and sewer main.

WALL ASSESSMENT PROCESS

5 smithgroup.com

Elements of the Study• Topographic Survey

• Geotechnical Soil Borings

• Inspection of wall and review of existing documents

• Engineering Alternatives

• Hydraulic Modeling

• Evaluation and Recommendations

ALTERNATIVES CONSIDERED

6 smithgroup.com

Alternatives Considered Include-

• Sheet Pile on Land Side of the Wall

• Concrete Filled Geotextile Tube

• Cores in the Footer • Wall Removal and

Sewer Relocation• Sheet Pile Wall

Protection

Criteria for Evaluation of Alternatives1. Provide long term protection for

adjacent properties and sanitary sewer.

2. Maintain the alley and service access on the north side of the commercial buildings.

3. Limit impact on the flooding elevation of the river; especially upstream of the project area.

4. Preserve opportunities in the future to achieve the developing goals of the UNIFIED PLAN

5. Be cost effective.

1. Protect from scouring and soil loss

2. Backfill voids in soil

ALTERNATIVES EVALUATION

7 smithgroup.com

Alternatives

Long Term Protection –

Adjacent Properties and Sanitary Sewer

Maintain Alley and Service

Functions

Limit Flood Impacts to

Project Area

Achieves goals of the Unified Plan

Cost Effective*

Overall Rating

Sheet Pile –Land Side

2 3 3 1 2 2

Concrete Filled

Geotextile1 3 1 1 1 1

Cores in Footer

1 3 3 1 1 2

Wall Removal &

Sewer Relocation

3 2 3 3 3 3

Sheet Pile –River Side

3 3 2 1 3 2.5

RECOMMENDATION – 100 BLOCK

8 smithgroup.com

Plan of 100 Block

Section of 100 Block

Un

ion

Str

ee

t

Ca

ss

Str

ee

t

RECOMMENDATION – 100 BLOCK

9 smithgroup.com

100 Block of Front St, looking east

RECOMMENDATION – 200 BLOCK

10 smithgroup.com

Plan of 200 Block

Section of 200 Block

Ca

ss

Str

ee

t

Pa

rk S

tre

et

HYDRAULIC MODELLING RESULTS

11 smithgroup.com

River Bottom

River SurfaceP

ark

Str

ee

t B

rid

ge

Ca

ss

Str

ee

t B

rid

ge

Un

ion

Str

ee

t B

rid

ge

Profile of River Looking South

The recommended approach will lead to a rise in flood elevation within the project area of approximately 0.10 feet but does not result in a change upstream or downstream from the project area.

UNIFIED PLAN

12 smithgroup.com

DISCUSSIONS TO DATE

Key priorities from the Community Engagement Process

• Providing public access

• Soften shore treatment/restore natural edge

• Remove/Limit parking from riverbanks

• Utilize best practices to manage stormwater and other means of improving water quality.

• Shift the balance towards habitat and nature over human recreation and economic development

• Keep river corridor natural and passive

SHORT-TERM MEASURES

13 smithgroup.com

1. Coordinate potential FEMA permitting with the Fish Pass project

2. Enact a monitoring program to track potential infrastructure failures between now and construction, including-

Survey of the existing wall and monitoring the wall’s cant biannually

Place benchmark nails in the pavement to the south of the wall and track their elevation fluctuations monthly

Measure the width of pavement cracks monthly

Measure point locations of scour depth monthly

Conduct annual underwater scour inspections

Monitor flows in the wastewater line to identify new infiltration resulting from a break in the sewer line

Televise the existing 24” sanitary sewer main and sewer service connections in both the 100 and 200 blocks

STEPS FORWARD

Seek support for project by elected and appointed officials.

Find source(s) of funding to limit financial impact to residents

Submit for Permits

Prepare Final Engineering Plans and Specifications

Bidding and Construction

14 smithgroup.com