blue grass chemical agent-destruction pilot plant quarterly update march 12, 2013
Upload: program-executive-office-assembled-chemical-weapons-alternatives-peo-acwa
Post on 07-May-2015
32 views
DESCRIPTION
Presented to: Kentucky Chemical Demilitarization Citizens' Advisory Commission and Kentucky Chemical Destruction Community Advisory BoardTRANSCRIPT
Blue Grass Chemical Agent-Destruction Pilot Plant Quarterly Update
March 12, 2013
Presented to:
Kentucky Chemical Demilitarization Citizens’ Advisory Commission and
Kentucky Chemical Destruction Community Advisory Board
Presented by:
Jeff Brubaker
Site Project Manager
A Partnership for Safe Chemical Weapons Destruction
Construction now more than 65 percent complete
Systemization activities now more than 9 percent complete
Completion of the structural steel on the Munitions Demilitarization Building (MDB)
Delivery of the Munitions Washout System and Rocket Shear Machine equipment
Completion and delivery of the first of two MDB filter bank Clean-Air Exhaust Stacks
Blue Grass Chemical Agent-Destruction Pilot Plant Update
3
One half of the first 120-foot Clean-Air Exhaust Stack is offloaded for temporary storage in the Hwy. 52 lay-down yard. It will be installed in accordance with the construction schedule.
A Partnership for Safe Chemical Weapons Destruction
Final Munitions Demilitarization Building Filter Bank Concrete Placement video on Facebook
Blue Grass Chemical Agent-Destruction Pilot Plant Update (cont’d)
4
The workers spent approximately eight hours placing 540 cubic yards of concrete to complete the second half of the east filter bank foundation.
A Partnership for Safe Chemical Weapons Destruction
4
Northwestern Corner - Observation Point
1 2
1
3
5
2
6
Hydrolysate Storage Area
Control and Support Building
Munitions Demilitarization Building (MDB) Filter Banks
MDB
Utility Building
Supercritical Water Oxidation Building (not visible in photo)
Laboratory Building (not visible in photo)
7 65
4
3
7
4
Blue Grass Chemical Agent-Destruction Pilot Plant Construction Site (March 2013)
A Partnership for Safe Chemical Weapons Destruction
5
Blue Grass Hot Topics
The BGCAPP project team continues to focus on successful construction and is working with the headquarters team to determine potential funding impacts
The project team is looking forward to installing the Munitions Washout System and rocket motor disassembly equipment in the upcoming months
The National Research Council is currently conducting a study on the systemization phase for Supercritical Water Oxidation and reverse osmosis system
In the upcoming months, the project team will be asking the Secondary Waste Working Group to consider options for disposal of rocket motors
A Partnership for Safe Chemical Weapons Destruction
Explosive Destruction Technologies (EDT)
6
National Environmental Policy Act (NEPA) process is continuing
– ACWA is well into the NEPA Environmental Assessment (EA)
– BGCAPP continues to communicate with the Kentucky Department for Environmental Protection on the potential permitting process
– The public comment period for the EA is currently scheduled for the June timeframe
Pueblo has Finding of No Significant Impact
– No significant environmental impacts to result from installation and operation of EDT at Pueblo Chemical Depot
– A EDT technology decision for Pueblo is pending
A Partnership for Safe Chemical Weapons Destruction
Questions/Discussion
7
For more information about the Blue Grass Chemical Agent-Destruction Pilot Plant project, please contact the Blue Grass Chemical Stockpile Outreach Office at (859) 626-8944
Blue Grass Chemical Agent-Destruction Pilot Plant Systems Contractor Update
March 12, 2013
Presented to:
Kentucky Chemical Weapons Demilitarization Citizens’ Advisory Commission and Kentucky Chemical Destruction Community Advisory Board
Presented by:
Tom McKinneyProject Manager, Bechtel Parsons Blue Grass
A Partnership for Safe Chemical Weapons Destruction
9
Safety Performance
12-month rolling rate
Accidents per 200,000 job hours
OSHA Voluntary Protection Program Star site
Lost-time injury rate is 81 percent lower and recordable injury rate 27 percent lower than industry average
As of February 28, 2013, the project has completed 486,000 hours and 110 days without a lost-time accident
OSHA Voluntary Protection Program Star site
Lost-time injury rate is 81 percent lower and recordable injury rate 27 percent lower than industry average
As of February 28, 2013, the project has completed 486,000 hours and 110 days without a lost-time accident
A Partnership for Safe Chemical Weapons Destruction
10
My Brother’s Keeper
Brother’s Keeper mindset gaining traction― Culture of mentoring one another, remaining vigilant
and respectfully challenging unsafe workplace behaviors Encouraging workers to report injuries and near misses Communicating that every worker has “pause work”
and “stop work” authority
A Partnership for Safe Chemical Weapons Destruction
11
Current Staffing
Employment― Total project – 1,047― Richmond, Ky. – 978
• Nonmanual – 528• Craft – 450
― Other locations – 69• Pasco, Wash.• San Diego, Calif.• Columbus, Ohio• Frederick, Md.
Project Controls engineers (above right) inspect progress at the Munitions Demilitarization Building cascading ventilation filter area. Electricians (above left) install underground electrical cable conduit.
A Partnership for Safe Chemical Weapons Destruction
12
Hiring a Local Workforce
Bechtel Parsons Blue Grass
Workforce in Richmond, Kentucky
Workforce includes manual and non-manual employees
Note 1:Local: Metropolitan Statistical Areas (MSAs) and the small business advocacy program include the following counties:
Madison, Woodford, Fayette, Scott, Bourbon, Clark, Jessamine and Rockcastle. MSAs are defined by the Bureau of Labor Statistics.
Note 2: Manual employees are hired through the local Union Hall in Lexington, Kentucky.
Local56%
Outside of Kentucky
40%
Rest of Kentucky4%
A Partnership for Safe Chemical Weapons Destruction
13
Valuing a Diverse Workforce
BPBG – Nonmanual Workforce Kentucky Population
Source: U.S. Census Bureau, 2010
Source: U.S. Census Bureau, 2010
KentuckyArchitecture and Engineering
BPBG – Nonmanual Workforce
A Partnership for Safe Chemical Weapons Destruction
Kentucky Wages, Procurements and Subcontracts
Local payroll to date― $407 million paid― $403 million more to be paid
Acquisitions to date― $105.5 million spent with Kentucky companies― $64.1 million spent in Madison
and surrounding counties
14
BGCAPP-related Procurements and Subcontracts
MadisonEstill
Lee
Wolfe
Clark
Boyle
Lincoln
Rock-castle
Pulaski Laurel
Clay
Casey
Adair
Taylor
Wayne
Fayette
Knox
Whitley Bell
Leslie
Harlan
Knott
Pike
Martin
Floyd
Breathitt
Cumber-land
MarionLarue
Hart
Warren
Allen
Barren
Monroe
Spencer
ShelbyScott
Morgan
Elliott
Carter
GreenupLewisMason
LoganTodd
Christian
Trigg
Calloway
Lyon
Hopkins
Butler
Ohio Grayson
Hardin
BreckinridgeDaviess
Henderson
Union
Bullitt
Crittenden
Jefferson
OldhamHenry
Owen
Grant
Woodfo
rd
Bath
A Partnership for Safe Chemical Weapons Destruction
Corporate Stewardship
Awarded $10,000 in Madison County Teacher Grants for STEM (Science, Technology, Engineering and Mathematics) classroom education projects
Participated in Waco Elementary 5th grade Energy Expo Participated in local college job fairs and recruiting events
– Eastern Kentucky University (EKU) veteran students– Blue Grass Community & Technical College career fair– University of Kentucky (UK) spring career fair
15
Waco Elementary EnergyExpo. Photograph by Kaitlin Keane, Richmond Register.
EKU veteran students career fair.
UK student career fair.
UK student career fair.
A Partnership for Safe Chemical Weapons Destruction
Blue Grass Specific Equipment Update
16
Des
ign
Fabri
cation
On S
ite
Inst
alla
tion
Test
ing
Equipment Purpose
Status
- update since last meeting
A Partnership for Safe Chemical Weapons Destruction
17
Blue Grass Specific Equipment Complete
The Munitions Demilitarization Building’s Munitions Washout System has successfully completed design, fabrication and factory acceptance testing.
A Partnership for Safe Chemical Weapons Destruction
MWS Video
18
A Partnership for Safe Chemical Weapons Destruction
19
Control and Support Building
An electrician installs wiring (above) inside the Control and Support Building. Meanwhile, the Control and Support Building cascading ventilation system duct work (at right) undergoes testing.
A Partnership for Safe Chemical Weapons Destruction
20
Munitions Demilitarization Building
Ironworkers have completed major structural steel installation (above) at the Munitions Demilitarization Building and now focus on installing exterior siding (at right).
A Partnership for Safe Chemical Weapons Destruction
Munitions Demilitarization Building(continued)
21
One of the first munitions handing robots (above) has been placed into a Munitions Demilitarization Building blast proof room. Pipefitters review drawings to install a complex array of piping (at right) into the agent neutralization system room.
A Partnership for Safe Chemical Weapons Destruction
Supercritical Water Oxidation (SCWO)Process Building
22
An electrician installs electrical cable tray (above) inside the SCWO Process Building. Workers have completed siding installation activities (at right) on the north and south portions of the SCWO Process Building.
A Partnership for Safe Chemical Weapons Destruction
Hydrolysate Storage Area
23
Boilermakers fabricate Hydrolysate Storage Area tanks.
A Partnership for Safe Chemical Weapons Destruction
Utility Building
24
The Utility Building (above) is now surrounded by a host of pipe rack steel installation and support infrastructure activities. A pipefitter welds a Utility Building interior piping support.
A Partnership for Safe Chemical Weapons Destruction
Questions/Discussion
25
A Partnership for Safe Chemical Weapons Destruction
CHEMICAL DESTRUCTION CITIZENS ADVISORY BOARD WORKING GROUP UPDATES
Presented by
Craig Williams, CDCAB co-chair
12 March 2013
A Partnership for Safe Chemical Weapons Destruction
Congressional Action
113TH CONGRESS 1ST SESSION H. R. 933 IN THE HOUSE OF REPRESENTATIVES ---MARCH 4, 2013
A BILL Making appropriations for the Department of Defense, the Department of Veterans Affairs, and other departments and agencies for the fiscal year ending September 30, 2013, and for other purposes. CHEMICAL DEMILITARIZATION CONSTRUCTION,DEFENSE-WIDE
For expenses of construction, not otherwise provided for, necessary for the destruction of the United States stockpile of lethal chemical agents and munitions in accordance with section 1412 of the Department of Defense Authorization Act, 1986 (50 U.S.C. 1521), and for the destruction of other chemical warfare materials that are not in the chemical weapon stockpile, as currently authorized by law, $151,000,000, to remain available until September 30, 2017, which shall be only for the AssembledChemical Weapons Alternatives program.
A Partnership for Safe Chemical Weapons Destruction
H. R. 933
CHEMICAL AGENTS AND MUNITIONS DESTRUCTION, DEFENSE For expenses, not otherwise provided for, necessary for the destruction of the United States stockpile of lethal chemical agents and munitions in accordance with the provisions of section 1412 of the Department of Defense Authorization Act, 1986 (50 U.S.C. 1521), and for the destruction of other chemical warfare materials that are not in the chemical weapon stockpile, $1,301,786,000, of which $635,843,000 shall be for operation and maintenance,
of which no less than $53,948,000 shall be for the Chemical Stockpile Emergency Preparedness Program, consisting of $22,214,000 for activities on military installations and $31,734,000, to remain available until September 30, 2014, to assist State and local governments;
$18,592,000 shall be for procurement, to remain available until September 30, 2015, of which $1,823,000 shall be for the Chemical Stockpile Emergency Preparedness Program to assist State and local governments;
and $647,351,000, to remain available until September 30, 2014, shall be for research, development, test and evaluation, of which $627,705,000 shall only be for the Assembled Chemical Weapons Alternatives (ACWA) program.
A Partnership for Safe Chemical Weapons Destruction
ECONOMIC DEVELOPMENT WORKING GROUP
*** ECONOMIC IMPACT STUDY ***
Phase 1 – Job Loss Aversion
• Labor Analysis• Identify tier 1,2, and 3 jobs• Inventory transferrable skills
Phase II – Infrastructure / Tax Impacts /Re-purposing
• Housing Analysis• Transportation Analysis • Tax Impacts• Analysis of future use potential based on CFR (Code of Federal Regulations)
Phase III – Reuse
• Finalize GO/GO - GO/CO - Co/CO options• Identify potential public/private re-purposing • Develop Marketing Package
A Partnership for Safe Chemical Weapons Destruction
PHASE I – Status
• Elements of Study Catalogued (examples)
- Regional Profile- Workforce Skills Analysis- Regional Economic and Workforce Strategy- Key Occupational Profiles- Target Industry Profiles- Etc.
• Operational Workforce Data Gathering (examples)
- ACWA and BPBG Standard Occupational Classifications *- Educational attainment- Crosswalk of compatible occupations- Etc
Phase I Report due 30 June 2013
* Completed 28 February
A Partnership for Safe Chemical Weapons Destruction
Secondary Waste Working Group
Focus: Rocket Separation Operation
• 10 January - Public Meeting regarding required permits was held
• 19 February – Comments on permit due. (CWWG submitted comments – available upon request).
• The SWWG will make a DRAFT recommendation to the full CDCAB regarding this effort after “response to comments” have been issued.
A Partnership for Safe Chemical Weapons Destruction
Rocket Separation
Blue Grass Chemical Activity (BGCA) has been tasked by the Chemical Materials Agency (CMA), their command, to separate 44 M-55 Rockets to validate rocket propellant stability and best practices for continued storage and future demilitarization operations.
Similar operations were successfully and safely completed in Arkansas and Oregon.
Rocket motors (25) will be over-packed and shipped to Picatinny Arsenal, N. J. for analysis. Rocket motors (19) will stay in storage at BGCA for ACWA for analysis prior to demilitarization operations.
Currently BGCA and Kentucky Department of Environmental Protection are engaged in permitting issues associated with the operation.
Operations are expected to begin in the first quarter of 2014.
A Partnership for Safe Chemical Weapons Destruction
A Partnership for Safe Chemical Weapons Destruction
MONITORING WORKING GROUP
• MWG developed a DRAFT recommendation which was circulated to the full CDCAB on 21 February.
• Input was gathered through 1 March and the final recommendation is as follows:
A Partnership for Safe Chemical Weapons Destruction
A Partnership for Safe Chemical Weapons DestructionTherefore the MWG makes the following:
Recommendations: 1) Vents on all BGCA igloos containing chemical agent, other than igloos M, OP and Z should remain open. 2) Methods of mold growth mitigation in the three igloos should continue to be vigorously pursued. 3) Any increase in igloo inspection that might be deemed appropriate due to the vent closures should be continued.
A Partnership for Safe Chemical Weapons Destruction
QUESTIONS / DISCUSSION
A Partnership for Safe Chemical Weapons Destruction
Doug Hindman Chair
Chemical Demilitarization Citizens’ Advisory Commission
Chemical Destruction Community Advisory Board 105 5th Street, Suite 206
Richmond, KY 40475 859.624.4700 / 859.986.7565
Kent Clark Craig Williams
Co-Chairs
To: Lieutenant Colonel Christopher Grice, Commander, BGCA Fr: KY CAC/CDCAB Date: 5 March 2013 Re: Mold Mitigation @ BGCA Dear Lieutenant Colonel Grice, First, we would like to acknowledge the efforts of you and your staff in providing information and transparency regarding the Mold Mitigation efforts underway at the Blue Grass Chemical Activity (BGCA). We appreciate that the Monitoring Working Group (MWG) of the Kentucky CAC/CDCAB (Citizens Advisory Commission/Chemical Destruction Citizens Advisory Board) has been provided the opportunity to be fully engaged in this process. With this in mind, we provide you the following observations and recommendations: Observations:
1) The MWG notes that the empirical evidence provided regarding mold in igloos M,OP and Z recently provided, contradict the findings reported in the Igloo Filtration Study (IFS) as follows: • the IFS showed no appreciable variation in humidity levels with or without any additional equipment being installed in or on the igloos. • the IFS also showed no appreciable variation in humidity levels with the igloo vents open or closed provided leaking igloos are “tarped” or otherwise modified to prevent seepage. 2) The MWG notes that the remaining igloos, those with the vents open do not show noticeable mold growth as do those identified above whose vents are closed. This appears to indicate higher humidity in those three igloos, as such conditions are necessary for such growth. 3) Igloos M, OP and Z pose the greatest risk, although small, of agent release into the BGCAPP construction area. Therefore the MWG makes the following:
Recommendations: 1) Vents on all BGCA igloos containing chemical agent, other than igloos M, OP and Z
should remain open. 2) Methods of mold growth mitigation in the three igloos should continue to be vigorously pursued.
3) Any increase in igloo inspection that might be deemed appropriate due to the vent closures should be continued. Signed: Dr. Douglas Hindman, Chair Kentucky Chemical Demilitarization Citizens Advisory Commission Kent Clark, Co-Chair Kentucky Chemical Destruction Citizens Advisory Board Craig Williams, Co-Chair Kentucky Chemical Destruction Citizens Advisory Board
--