(bio)mass appeal - the economist · (bio)mass appeal a symbiotic biomass and battery system for...
TRANSCRIPT
(BIO)MASS APPEAL
A symbiotic biomass and battery system for resilient,
carbon-neutral power generation
Sadie Fulton, Micah Gowen, and Liam O’Callaghan Submitted March 8, 2017
Team GreatMines
1
CONTENTS
ABSTRACT .................................................................................................................................... 2
BACKGROUND AND OBJECTIVES .......................................................................................... 3
AN INNOVATIVE ENERGY SOLUTION ................................................................................... 4
ENERGY SUPPLY RESILIENCE................................................................................................. 6
CARBON EMISSIONS .................................................................................................................. 8
FINANCIAL MODEL .................................................................................................................... 9
Capital Expenditures (CAPEX) .................................................................................................. 9
Operating Expenditures (OPEX) ............................................................................................... 10
Comparison to Status Quo......................................................................................................... 12
Project Financing Considerations ............................................................................................. 12
FINANCIAL SENSITIVITY ANALYSIS ................................................................................... 12
CONCLUSION ............................................................................................................................. 16
APPENDIX ................................................................................................................................... 17
REFERENCES ............................................................................................................................. 18
ADDITIONAL REFERENCES.................................................................................................... 19
Figure 1: Summer energy supply and demand ............................................................................... 6
Figure 2: Winter energy supply and demand .................................................................................. 7
Figure 3: Carbon cycle of natural gas ............................................................................................. 8
Figure 4: Carbon cycle of fast growing fuel-stock trees ................................................................. 8
Figure 5: Discount rate sensitivity ................................................................................................ 13
Figure 6: Yearly escalation sensitivity .......................................................................................... 13
Figure 7: Grid power price sensitivity .......................................................................................... 14
Figure 8: Fuel subsidy sensitivity ................................................................................................. 14
Figure 9: Cost of carbon sensitivity .............................................................................................. 15
Figure 10: Financial model (First five years and lifetime incremental npv) ................................ 17
2
ABSTRACT
Can energy system planners deliver resilient, carbon-neutral energy for the same lifetime cost as
purchasing power from the grid? Even for a five megawatt hospital in New Jersey, where resiliency
is a matter of life or death, our answer is yes. Our financial model shows that by incorporating four
megawatts of combined-heat-and-power (CHP) biomass generation with nine megawatt-hours of
battery storage we can provide carbon-neutral energy to meet all of the hospital’s needs. The
carbon-neutrality of our proposed solution rides on our innovative ‘Sprout Spread’, which shortens
the biomass generator’s carbon cycle to five years and secures long-term, low prices for biomass
fuel. Further, while our conservative parameter assumptions generate lifetime costs equal to those
incurred from purchasing grid power, sensitivity analyses show that it is likely that our plan will
go a step further and generate a net positive return. All told, this plan presents a solid, forward-
thinking investment opportunity for the hospital.
3
BACKGROUND AND OBJECTIVES
Our challenge was to build a financial model that enables the development of an energy system to
power a 2,000 bed hospital in New Jersey. The proposed system must ensure energy supply
resiliency and minimize carbon emissions. Our financial model leads us to propose a system that
incorporates a combined-heat-and-power biomass generator with a large battery bank. The
proposed system delivers, throughout the range of potential realities, reliable power with zero
carbon emissions. This is achieved without incurring additional costs relative to the hospital’s
status quo of purchasing power from the grid.
Our model delivers on the following objectives over the life of the project:
• complete carbon neutrality,
• guaranteed power supply under any conditions,
• complete self-sustainability of power generation, and
• zero additional present-value cost when compared to the hospital’s status quo.
Powering a 2,000 bed hospital presents system planners with unique challenges. These challenges
stem from every hospital’s critical need for delivered energy resiliency; when people’s lives
depend on delivered energy the costs are simply too great to allow for any potential system
downtime. This means that our proposed system must be guaranteed to deliver energy 100% of
the time.
The potential generation sources under consideration each come with their own costs. New
Jersey’s climate does not provide a financially efficient source of solar or wind energy potential.
4
Access to these energy sources does exist in New Jersey, but the quality of either source is
limited.1,2,3 Offshore wind generation in New Jersey is technically feasible, but not financially
viable at the scale of this project. Compared to the other options, fuel cells are prohibitively
expensive to construct and operate, while gas turbines generate high levels of carbon emissions
which incur large social costs.4 In light of these challenges, and as a result of the output of our
financial model, we propose a system which combines biomass power generation with battery
storage.
AN INNOVATIVE ENERGY SOLUTION
Our energy plan encompasses four key points. First, a four megawatt biomass combined-heat-and-
power generator will be installed at the hospital in a dedicated plant building. Second, the generator
will be supplemented by a large bank of battery storage calibrated to distribute stored off-peak
production to meet peak demand. Third, the fuel for the biomass plant, bone-dry wood chips and
pellets, will be sourced through a long-term, subsidized contract with a producer who will manage
14,000 acres of timber land purchased by the hospital. Finally, the timber grown on the purchased
land will be used to create a five-year cycle of carbon sequestration, which allows all power
generated to be carbon neutral.
Four megawatts of biomass CHP generation, combined with nine megawatt-hours of battery
capacity, will meet all of the hospital’s electricity needs. This system is cost-effective; the capital
and operating expenditures of a biomass CHP plant of this scale are comparable to a gas turbine
system of equivalent capacity. Additional benefits of the biomass system are the opportunities to:
enter into an affordable, short carbon cycle; generate power with a range of possible fuels; reduce
5
expenditures on natural gas for heating; and take advantage of enticing policies New Jersey has
enacted to encourage biomass power generation. Supplementing the biomass generator with
battery storage reduces the upfront capital expenditure on required biomass generation capacity.
Our financial model assigns real costs to carbon emissions. First, we estimate the emissions from
the biomass plant, and from competing energy sources, in metric tonnes of CO2 per year. Then,
we define the social cost of carbon as a measure, in dollars, of the global damage done by a ton of
carbon emitted.5,6 This must be comprehensive and will include items such as human health costs
related to air pollution, the value of lost biodiversity, and the value of lost human life. Finally, we
multiply the social cost of carbon by the amount of estimated emissions, giving us the cost to
society of the plan’s emitted carbon. While these costs are intangible to energy producers, they
represent the real cost of damages incurred from emitting carbon. Without including these costs, a
financial model might overvalue a system that generates power with fossil fuels; however, when
included, biomass generation, aided by our innovative path to carbon-neutrality, becomes optimal.
Our primary innovation is the introduction of a concept we have named the ‘Sprout Spread’. This
idea is derived from the ‘Spark’ and ‘Dark’ spreads long utilized by coal and natural gas power
plants to guarantee profit margins. The key points are simple: the hospital purchases timber land
and contracts the rights to the timber produced on the land to an established partner. The partner,
in a five-year cycle, harvests, plants, grows, and once again harvests fast-growing timber. While
the rights to the end products belong to the contracted partner, the hospital receives in return a
subsidized, long-term price on fuel. This is the ‘Sprout Spread’: the difference between the market
price for biofuel pellets and the contracted price for timber grown on the hospital’s land.
Additionally, the five-year cycle of regrowth means that our power generation is carbon-neutral.
6
That is, for all biomass burned, equal amounts of biomass are grown. As such, no net carbon is
emitted.
ENERGY SUPPLY RESILIENCE
The demand curve of the hospital is assumed to reflect those of other medical facilities, and that
of the general consumer demand curve.7,8 Demand peaks in the hottest hours of the day before
gently subsiding to a minimum in the early hours of the morning. This curve has presented a great
challenge to grid operators of the past, but the battery array installation in our plan allows us to
meet peak demand in real-time with reduced installed biomass capacity. The planned biomass
generator produces excess capacity during the night, which is used to fully recharge the battery
(inclusive of efficiency loss) so that the daily cycle is not interrupted. In milder weather and winter,
the combined-heat-and-power capacity of the biomass plant removes some of the weight of cooling
and heating from the electricity supply, allowing the hospital to ramp down the biomass generator
when excess capacity is not required to recharge the batteries overnight.
FIGURE 1: SUMMER ENERGY SUPPLY AND DEMAND
0
1
2
3
4
5
6
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24Ele
ctri
city
in
MW
Time of Day
Summer Supply
Biomass Battery Discharge Efficiency Loss Battery Charge Demand base
7
FIGURE 2: WINTER ENERGY SUPPLY AND DEMAND
Hospitals must always be prepared for worst-case scenarios, and our plan gives the hospital
significantly more leeway than a grid-based solution. The extreme versatility of biomass
generators ensures maximum uptime even in the worst of situations.9 Any sufficiently dry organic
source can be burned in the generator, albeit sometimes at reduced efficiency, ensuring that should
a natural disaster sever the supply lines for biomass pellets and the fuel stock dwindle, the hospital
need not do without power, as it can substitute to whatever biomass is available. The hospital’s
legally-mandated emergency generators are thus relegated to third-level redundancy, behind both
the battery bank and grid connectivity.
0
1
2
3
4
5
6
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Ele
ctri
city
in
MW
Time of Day
Winter Supply
Biomass Battery Discharge Efficiency Loss
Battery Charge Bio Ramp-down Demand base
8
CARBON EMISSIONS
The carbon cycle gives important insight into how we achieve carbon neutrality. To be carbon
neutral, all of the CO2 released by burning a fuel, whether it is gas, coal, or wood, must be
sequestered, or cycled out of the atmosphere.
In the case of fossil fuels, the carbon cycle
operates on the geologic time scale. These fuels
are extracted from the earth and burned,
releasing all of the carbon sequestered within
them into the atmosphere as CO2. To re-
sequester the carbon that was released would
take hundreds of millions of years.10
The carbon cycle of a fast-growing, fuel-stock
tree, grown specifically for biomass, is less than
five years.11,12 Once a tree is cut down and
burned, the carbon contained within it is
released into the atmosphere as CO2. Through
the planting and growth of a new tree, an
equivalent amount of CO2 can be removed from
the atmosphere. This cycle is extremely short
compared to the carbon cycle of fossil fuels.
FIGURE 3: CARBON CYCLE OF NATURAL GAS
FIGURE 4: CARBON CYCLE OF FAST GROWING FUEL-STOCK TREES
9
Without accounting for sequestration measures, the carbon emissions would be significant; over
the 25-year life of the project, our model estimates that approximately 278,500 tonnes of CO2
would be released into the atmosphere. This number is still lower than the 322,100 tonnes of CO2
that would be emitted if power was purchased from the grid in New Jersey for 25 years.13,14
However, accounting for the five-year sequestration cycle of the timber land, the net emissions
from the biomass plant in our model are zero tonnes of CO2 per year.
FINANCIAL MODEL
Capital Expenditures (CAPEX)
There are four main areas of capital spending proposed in this model: biomass plant installation,
battery storage installation, land purchased for carbon sequestration, and Renewable Energy
Credits. This results in a total capital expenditure in year zero of US$ 23.3 million, with additional
discounted spending of US$ 6.1 million spread out over the next four years.
The biomass plant installation CAPEX for this project makes up the bulk of capital spending at
US$ 20 million. This is assuming an all-in cost of US$ 5 million per megawatt of power
installed.15,16 This total is subsequently reduced by a US$ 3 million CHP installation subsidy from
the state of New Jersey.17
The second largest capital expense is the purchase of timber land. It is assumed that timber
producing land can be purchased in large blocks over a five-year time period at an average of US$
600 per acre.18 This timber land purchase will amount to a total of approximately 14,000 acres
which will be enough to offset the complete carbon production of the biomass plant for every year
after the initial five-year purchasing period, continuing out through the life of the project. The
10
timber grown on the land will produce the equivalent of 35,600 bone-dry tonnes of biomass every
year.
Battery storage represents an up-front CAPEX of US$ 3.6 million. Utility-scale battery
installations have declined in price over the past several decades, to the point where companies
like Tesla, Inc. are offering fully scalable products below a half-million USD per megawatt hour.
Our plan assumes the purchase of a Tesla, Inc. scalable battery installation. These batteries are
under warranty for up to 6,000 cycles (approximately 16 years), but we account for a complete
replacement of the installation at the end of year 15 of the project life, for an escalated capital cost
of US$ 2.6 million in 2034.19 This cost includes the effect of a 50% reduction in the price of battery
technology over the 15 years following the initial purchase.
Finally, capital of US$ 280,000 will be required to purchase Renewable Energy Credits (RECs) to
completely offset the carbon produced in the first five years before the timber land is producing at
capacity.20 RECs allow for capital to be reallocated to wind and solar projects in places where it is
most efficient to build them.
Operating Expenditures (OPEX)
Total discounted operating costs for the energy project are estimated to be approximately US$ 30
million over the 25-year life of the project. This can be compared to a discounted cost for the status
quo of purchasing power from the grid of approximately US$ 59 million. These operating costs
are all tied directly to the cost of operating the biomass generator, as the batteries are assumed to
have no associated operating costs.
11
The bulk of the OPEX is the cost of fuel to run the biomass generator. For this model, the market
price of fuel is assumed to be US$ 100 per tonne.16,21 This number was chosen as it represents the
average price of high quality fuel. The ‘Sprout Spread’ guarantees the hospital this price minus a
40% subsidy from timber sales.
The second largest portion of operating costs is composed of the social cost of carbon. A cost of
US$ 50 per tonne of CO2 produced was assumed. Buying power from the grid has an estimated
lifetime carbon cost of US$ 21.7 million.13,14 The total cost of the carbon emissions from the
biomass plant is estimated to be US$ 18.7 million, however once the timberland is in full operation,
the net social cost of carbon from the biomass plant is assumed to be zero.
A subsidy on operating costs is provided by savings on heat generation for the hospital. It was
assumed that capturing waste heat from the CHP generator reduces the hospital’s heating costs by
50%. Based on the heating requirements of the similarly sized New York Presbyterian hospital,
our plan saves 25,000,000 cubic feet of natural gas per year.22
A minor portion of operating costs are derived from fixed and variable maintenance costs required
every year. Fixed maintenance costs are assumed to be 2% of the installed CAPEX. Variable
maintenance costs are assumed to be US$ 0.50 per megawatt-hour generated. Fixed and variable
maintenance costs represent a total year one cost of US$ 420,000 escalated over the life of the
project.16,23
The final operating cost is the cost of purchasing power from the grid in the first year of the plan
while the new system is under construction. This amounts to a total cost of US$ 4.1 million.13,14
12
Comparison to Status Quo
After discounting all of the costs for both our plan and the hospital’s status quo to their present
values at a conservative discount rate of 10%, we find that the estimated present worth costs are
US$ 58.8 million and US$ 58.9 million respectively. An incremental Net Present Value (NPV)
analysis confirms that the up-front capital costs of our proposal are completely offset by the
decreased operating costs over the life of the project.
Project Financing Considerations
As a non-profit organization, the hospital has several financing options available to them.
Traditionally, charitable donations and existing endowments make up a large portion of any capital
spending for a hospital of this size. However, external sources of financing such as low-interest
bank loans and the sale of bonds exist and are available. Furthermore, there may be additional state
and federal subsidies available related to the installation and operation of carbon-neutral power
generation.
FINANCIAL SENSITIVITY ANALYSIS
To validate our findings under a range of potential realities, we vary individual parameter settings
in our financial model. The outcomes are then compared via an incremental NPV analysis to the
status quo of purchasing power from the grid. Our plan generates break-even economics when
compared with the hospital’s status quo. The conservative nature of our baseline assumptions
leaves room for additional benefits under a range of scenarios.
13
The parameter that has the greatest effect on the NPV is the discount rate of the project. The
baseline discount rate of 10% represents the opportunity cost of investing in this project if other
investments could be made earning a 10% return. A decrease in the discount rate to 5% causes the
incremental NPV of the project to increase to US$ 17.2 million.
FIGURE 5: DISCOUNT RATE SENSITIVITY
Costs in our model are assumed to escalate at 2.5% per year. An increase of 1% in the escalation
rate causes the incremental NPV of the project to increase by US$ 3 million. A 1% decrease in the
escalation rate, however, only causes a US$ 2.3 million decrease in NPV.
FIGURE 6: YEARLY ESCALATION SENSITIVITY
($20.0)
($10.0)
$0.0
$10.0
$20.0
$30.0
$40.0
$50.0
NP
V i
n M
US
D
Discount Rate (%)
($6.0)
($4.0)
($2.0)
$0.0
$2.0
$4.0
$6.0
$8.0
$10.0
1.0% 1.5% 2.0% 2.5% 3.0% 3.5% 4.0% 4.5% 5.0%
NP
V i
n M
US
D
Yearly Escalation (%)
14
Changing the cost of grid power and the subsidy for the biomass fuel have nearly the same effect
on the overall NPV. For grid power, every $0.01 change in the price leads to a US$ 4 million
change in NPV. Similarly, a 10% change (from the baseline subsidy of 40%) in the negotiated
biomass fuel subsidy leads to a US$ 3.9 million change in NPV.
FIGURE 7: GRID POWER PRICE SENSITIVITY
FIGURE 8: FUEL SUBSIDY SENSITIVITY
($30.0)
($20.0)
($10.0)
$0.0
$10.0
$20.0
$30.0
$40.0
NP
V i
n M
US
D
Grid Power Price ($/KWh)
($15.0)
($10.0)
($5.0)
$0.0
$5.0
$10.0
$15.0
$20.0
$25.0
$30.0
10% 20% 30% 40% 50% 60% 70% 80% 90% 100%NP
V i
n M
US
D
Fuel Subsidy (%)
15
The final relevant sensitivity is for the cost of carbon. For every US$ 10.00 change in the social
cost of carbon per tonne, the incremental NPV of the project changes by US$ 1.3 million.
FIGURE 9: COST OF CARBON SENSITIVITY
While our conservative baseline parameter assumptions generate a zero incremental NPV relative
to the status quo of purchasing power from the grid, it can be seen that there are likely scenarios
that would generate additional value.
($6.0)
($4.0)
($2.0)
$0.0
$2.0
$4.0
$6.0
$8.0
10 20 30 40 50 60 70 80 90 100
NP
V i
n M
US
D
Cost of Carbon ($/Tonne)
16
CONCLUSION
Our financial model enables the development of an energy system that provides a 2,000 bed
hospital with reliable, carbon-neutral power from day one, at zero additional costs relative to the
hospital’s status quo. The plan provides power that is triply redundant; even in the event of a
catastrophic system failure, the hospital will have two remaining sources of power to rely on.
Further, because of the inherent diversity of fuel stocks available to biofuel generators, the hospital
will not be subject to biofuel supply shocks. Our innovative ‘Sprout Spread’ protects the hospital
from biofuel price volatility and generates a fuel price subsidy which allows for a reduction in
operating costs that completely offsets the additional upfront capital expenditures required for
start-up. The spread creates a level path to a five-year carbon cycle, which ensures the carbon
neutrality of our system. The batteries, biomass plant, and timber land in our proposal work
together in a symbiotic, standalone system that unplugs the hospital from reliance on the grid and
is carbon-neutral from day one.
17
APPENDIX
FIGURE 10: FINANCIAL MODEL (FIRST FIVE YEARS AND LIFETIME INCREMENTAL NPV)
Year 2018 2019 2020 2021 2022
Biomass Plant
CAPEX ($) 20,000,000.00$ -$ -$ -$ -$
CAPEX Subsidy (NJ) (2,400,000.00)$ (600,000.00)$ -$ -$ -$
OPEX ($/year)
Fuel cost -$ 3,504,000.00$ 3,591,600.00$ 3,681,390.00$ 3,773,424.75$
Fixed Maintenance cost -$ 400,000.00$ 410,000.00$ 420,250.00$ 430,756.25$
Variable Maintenance cost -$ 17,520.00$ 17,958.00$ 18,406.95$ 18,867.12$
Social cost of carbon 788,400.00$ 525,600.00$ 538,740.00$ 552,208.50$ 566,013.71$
Heat payback -$ (225,000.00)$ (230,625.00)$ (236,390.63)$ (242,300.39)$
Purchase grid power 4,110,192.00$ -$ -$ -$ -$
Fuel Savings from ramp-down -$ (100,000.00)$ (102,500.00)$ (105,062.50)$ (107,689.06)$
Carbon savings from ramp-down -$ (15,000.00)$ (15,375.00)$ (15,759.38)$ (16,153.36)$
Purchase 14,000 acres 1,680,000.00$ 1,680,000.00$ 1,680,000.00$ 1,680,000.00$ 1,680,000.00$
Value of Fuel Subsidy -$ (1,401,600.00)$ (1,436,640.00)$ (1,472,556.00)$ (1,509,369.90)$
Value of carbon offset -$ -$ (107,748.00)$ (220,883.40)$ (339,608.23)$
Purchase Renewable Energy Credits 70,080.00$ 70,080.00$ 56,064.00$ 42,048.00$ 28,032.00$
Battery Storage
CAPEX 3,600,000.00$ -$ -$ -$ -$
OPEX -$ -$ -$ -$ -$
Total
CAPEX 22,950,080.00$ 1,150,080.00$ 1,736,064.00$ 1,722,048.00$ 1,708,032.00$
OPEX 4,898,592.00$ 2,705,520.00$ 2,665,410.00$ 2,621,603.55$ 2,573,940.90$
Total Cost 27,848,672.00$ 3,855,600.00$ 4,401,474.00$ 4,343,651.55$ 4,281,972.90$
Baseline Power Cost 4,110,192.00$ 4,212,946.80$ 4,318,270.47$ 4,426,227.23$ 4,536,882.91$
Baseline Social Cost of Carbon 788,400.00$ 791,947.80$ 795,511.57$ 799,091.37$ 802,687.28$
Baseline Total Cost 4,898,592.00$ 5,004,894.60$ 5,113,782.04$ 5,225,318.60$ 5,339,570.19$
Baseline Total Cost - Total Cost (22,950,080.00)$ 1,149,294.60$ 712,308.04$ 881,667.05$ 1,057,597.29$
Incremental NPV 128,594.26$
18
REFERENCES
[1] “Photovoltaic Solar Resource.”
http://www.nrel.gov/gis/images/map_pv_us_july_dec2008.jpg
[2] “U.S Photovoltaic Prices and Cost Breakdowns.”
http://www.nrel.gov/docs/fy15osti/64746.pdf
[3] “New Jersey Wind Resource Map and Potential Wind Capacity”
http://apps2.eere.energy.gov/wind/windexchange/wind_resource_maps.asp?stateab=nj
[4] “GE Power Generation” https://powergen.gepower.com/products/heavy-duty-gas-
turbines/9ha-gas-turbine.html
[5] “Technical Update to Environment and Cimate Change Canada’s Social Cost of Greenhous
Gas Estimates” http://ec.gc.ca/cc/default.asp?lang=En&n=BE705779-1
[6] “The Social Cost of Carbon” https://www.epa.gov/climatechange/social-cost-carbon
[7] Hu, S. C., J. D. Chen, and Y. K. Chuah. "Energy cost and consumption in a large acute
hospital." International Journal on Architectural Science 5, no. 1 (2004): 11-19.
[8] “Managing Energy Costs in Hospitals.”
https://www9.nationalgridus.com/non_html/shared_energyeff_hospitals.pdf
[9] “Combined Heat and Power: Enabling Resilient Energy Infrastructure for Critical Facilities.”
https://www1.eere.energy.gov/manufacturing/distributedenergy/pdfs/chp_critical_facilities.pdf
[10] “Where Our Natural Gas Comes From.”
https://www.eia.gov/energyexplained/index.cfm?page=natural_gas_home
[11] “Biomass Explained” https://www.eia.gov/energyexplained/index.cfm?page=biomass_home
[12] “Bioenergy from Biomass” http://www.nrcan.gc.ca/forests/industry/bioproducts/13323
[13] “Markets and Operations” http://www.pjm.com/markets-and-operations.aspx
[14] “2012-2015 CO2, SO2, NOx Emission Rates” http://www.pjm.com/~/media/library/reports-
notices/special-reports/20160318-2015-emissions-report.ashx
[15] “Cost and Performance Data for Power Generation Technologies.”
https://www.bv.com/docs/reports-studies/nrel-cost-report.pdf
19
[16] “Biomass for Power Generation”
https://www.irena.org/DocumentDownloads/Publications/RE_Technologies_Cost_Analysis-
BIOMASS.pdf
[17] “Combined Heat and Power.” http://www.njcleanenergy.com/chp
[18] “Timber Land Investment; A Look Into Timber Land Investing in the Northeast”
http://www.foreconinc.com/timberland-investment-a-look-into-timberland-investing-in-the-
northeast-part-2-2/#iLightbox[gallery942]/0
[19] “Tesla Powerpack: Utility and Business Energy Storage” https://www.tesla.com/powerpack/
[20] “Renewable Energy Credits (RECs)”
http://apps3.eere.energy.gov/greenpower/markets/certificates.shtml?page=1
[21] “The Wood Pellet Value Chain.”
http://www.usendowment.org/images/The_Wood_Pellet_Value_Chain_Revised_Final.pdf
[22] “Energy Characteristics and Energy Consumed in Large Hospital Buildings in the United
States in 2007.” https://www.eia.gov/c
[23] “Biomass to Electricity” http://ucanr.edu/sites/woodybiomass/files/78993.pdf
ADDITIONAL REFERENCES
“Cogeneration- A Win-Win Solution: New York-Presbyterian Hospital Weill Cornell Medical
Center.” https://www.nyserda.ny.gov/-/media/...Heat.../2012-CHP-Grube-Presentation.pdf
"Distributed Generation Renewable Energy Estimate of Costs." NREL: Energy Analysis -
Energy Technology Cost and Performance Data. March 25, 2016.
http://www.nrel.gov/analysis/tech_lcoe_re_cost_est.html.
“New Jersey Energy Master Plan, 2015.”
http://nj.gov/emp/docs/pdf/New_Jersey_Energy_Master_Plan_Update.pdf
“Study of Equipment Prices in the Power Sector.”
https://www.esmap.org/sites/esmap.org/files/TR122-
09_GBL_Study_of_Equipment_Prices_in_the_Power_Sector.pdf