bidders’ conference it-4123 supply, replacement and repair of crane rails introduction to cern and...
TRANSCRIPT
Bidders’ conference IT-4123Supply, Replacement and Repair of Crane Rails
Introduction to CERN and rails consolidation program
Handling Engineering Group
IT-4123 Technical Specification01/09/2015
CERN is a Global LabCERN was founded in 1954 as a Peace Initiative by 12 European States
Today it counts 21 Member States : Austria, Belgium, Bulgaria, the Czech Republic, Denmark, Finland, France, Germany, Greece, Hungary, Israel, Italy, the Netherlands, Norway, Poland, Portugal, Slovakia, Spain, Sweden, Switzerland and the United Kingdom
2300 staff
physicists, engineers, technicians, administrative personnel
1000 personnel on contract
11000 users
who represent more than half of the living particle physicists originating from 500 universities and institutes and of more than 80 nationalities
IT-4123 Technical Specification01/09/2015
The Missions of CERN Push forward the frontiers of
knowledgee.g. the secrets of the Big Bang … what was the matter like within the first moments of the Universe’s existence?
Develop new technologies for accelerators and detectorsInformation technology - the Web and the GRID
Medicine - diagnosis and therapy
Train the scientists and the engineers of tomorrow
Unite people from different countries and cultures
IT-4123 Technical Specification01/09/2015
CERN Accelerator Complex
IT-4123 Technical Specification01/09/2015
The LHCA collider situated in an underground 27 km in an almost circular tunnel designed to accelerate two proton beams to 7 TeV
1982 : First studies1994 : Project Approved by the CERN Council1996 : Final Decision and start of the construction2004 : Installation Starts2006 : Hardware Commissioning Starts2008 : End of Hardware Commissioning2009-2030: Physics
10 GJ = 55 km/h
+ t
ha
n 2
5 y
ears
IT-4123 Technical Specification01/09/2015
The structure of CERN
IT-4123 Technical Specification01/09/2015
EN Department
Head of Department’s Office (EN-HDO)R. Saban
Cooling & Ventilation (EN-CV)M. Nonis
Electrical Engineering (EN-EL)S. Baird
Handlling Engineering (EN-HE)I. Rühl
Machines & Experimental Facilities (EN-MEF)K. Foraz
Sources, Targets & Interactions (EN-STI)R. Losito
General Management & Secretariats
(EN-GMS)S. Prodon
Industrial Controls & Engineering
(EN-ICE)Ph. Gayet
Mechanical & Materials Engineering (EN-MME)F. Bertinelli
58
64 11
24 33
7486
38
4
Operation Infrastructure Accelerators Experimental
Areas Projects
Consolidation Upgrades New facilities Design &
Manufacturing Studies
Department Head: R. SabanDeputy: S. Baird
IT-4123 Technical Specification01/09/2015
Handling Engineering Group
The mandate : provide transport and handling services for the technical infrastructure of CERN, accelerators and experiments. This includes the design, the tendering/procurement, the installation, the commissioning, the operation, the maintenance and decommissioning of standard industrial and custom built transport and handling equipment.
Group LeaderIngo Rühl
IT-4123 Technical Specification01/09/2015
Handling Maintenance Section
HM - Handling Maintenance Section leader: Helder LOURENÇO
EOT cranes
Gilles Roche
Jean-Pierre Granchelli
Oliver Böttcher
Roberto Rinaldesi
Industrial trucks
Bruno Feral
Jean-Maurice Chevalley
Documentation
Cathelijne Hazelaar-Bal
IT-4123 Technical Specification01/09/201501/09/2015
EN-HE Transport and Handling Equipment
350 Cranes / 800 Hoists
2000 Lifting Beams
80 Working Platforms
400 Lifting Equipment
100 Tractors
50 Special Vehicles
About 4000 assets in Total
IT-4123 Technical Specification01/09/2015
Introduction to Rails Consolidation Program
• Long-term program which concerns the renovation of old
and worn crane rails
• Some rails are 50 years old
• Inventory under preparation (~ 250 buildings)
• Most critical cases already identified
• 15-20 rails will be subject to intervention in the next 5 years
• Program priorities as following CERN operations
requirements
IT-4123 Technical Specification01/09/2015
Introduction to Rails Consolidation Program