bid protests: the costs are real, but the benefits...
TRANSCRIPT
BID PROTESTS: THE COSTS ARE REAL, BUT THE BENEFITS OUTWEIGH THEM
Daniel I. Gordon*
[Note for student editors: Will you insert a table of contents and format the headings of the article consistent with PCLJ’s procedures?]
* 1
TABLE OF CONTENTS
I. INTRODUCTION..............................................2
II. ADMINISTRATIVE AND JUDICIAL VENUES FOR FILING PROTESTS IN THE U.S. FEDERAL SYSTEM...................................2
III. SPREAD OF THE PROTEST PROCESS OUTSIDE THE U.S.............5
IV. CORRECTING MISPERCEPTIONS ABOUT PROTEST STATIISTICS.......7
A. Protests are rare events.............................7
B. It is rare for a protester to win a protest, and even rarer for a winning protester to go on to obtain the contract at issue in the protest....................14
V. COSTS OF THE PROTEST PROCESS.............................17
VI. Benefits of the Protest Process..........................27
VII. Conclusion: The Costs are Overstated, and the Benefits Outweigh Them............................................30
I. INTRODUCTION
This article discusses the benefits and costs of bid
protests—legal challenges by a bidder to the way the gGovernment
has conducted a procurement.1 In the U.S. federal procurement
system, bid protests have existed since the 1920s,2 and criticism
arguing that they are more trouble than they are worth has been
around for nearly that long.3 The article explains why, in the
author’s view, the benefits of the bid protest system
1 See James F. Nagle & Adam K. Lasky, A Practitioner’s Road Map to GAO Bid Protests, 30 CONSTR. LAW , no. 5, Winter 2010, at 5.2 See id.3
2
substantially outweigh the burdens that it imposes on the
procurement system.
II. ADMINISTRATIVE AND JUDICIAL VENUES FOR FILING PROTESTS IN THE U.S. FEDERAL SYSTEM
It was in the U.S. that the first litigation leading to what
came to be recognized as a bid protest decision took place.4 In
1924, a company filed a complaint with the then-new General
Accounting Office (“GAO”),5, alleging that the officials of the
Panama Canal had written specifications for a truck that were
“wired” to a particular brand name and that unfairly precluded
the complaining firm from fair consideration for the contract.6
GAO, after some internal hesitation, decided to consider the
complaint as part of the office’s responsibility to ensure that
funds appropriated by Congress were lawfully spent—what is
4 See Comptroller General McCarl to the Governor, the Panama Canal, 5 Comp. Gen. 712, A-11259 (Mar. 9, 1926).5 Effective July 7, 2004, the GAO's legal name became the Government Accountability Office. See GAO Human Capital Reform Act of 2004, Pub. L. 108-271, § 8(a), 118 Stat. 811 (2004)Effective July 7, 2004, the GAO's legal name became the Government Accountability Office. Pub. L. 108-271, 118 Stat. 811 (2004).6 5 Comp. Gen. 712, 713.
3
referred to as GAO’s account settlement function.7 GAO
ultimately agreed with the protesting firm.8
In the course of the ensuring decades, handling bid protests
became a routine function of GAO’s Office of General Counsel.9
Some protests involved pre-award challenges by potential offerors
to solicitation terms;10 the majority were post-award challenges
by firms that had competed for a contract, contesting the award
to another offeror.11
For many years, courts did not consider bid protests, so
that GAO (and the contracting agencies themselves) represented
the only place to file a protest.12 Then, for three decades
after the decision of the U.S. Court of Appeals for the District
of Columbia Circuit in Scanwell,13 U.S. district courts had bid
7 In the Beginning: The Earliest Bid Protests Filed with the US General Accounting Office, 13 PUBLIC PROCUREMENT L. REV. 5 (2004); Daniel I. Gordon, Annals of Accountability: The First Published Bid Protest Decision, 39 PROCUREMENT LAWYER , no. 2, Winter 2004, at 11.In the Beginning: The Earliest Bid Protests Filed with the US General Accounting Office, 13 PUBLIC PROCUREMENT L. REV. 5 (2004); Annals of Accountability: The First Published Bid Protest Decision, THE PROCUREMENT LAWYER , Vol. 39, No. 2 (Winter 2004).8 5 Comp. Gen. 712, 7135 Comp. Gen. 712, A-11259 (Mar. 9, 1926).9 See William E. Kovacic, Procurement Reform and the Choice o Forum in Bid Protest Disputes, 9 ADMIN. L. REV. AM. U. 461 , 470 (1995)10 See, e.g., New York Tel. Co. v. Sec’y of Army, 67 F. Supp. 18, 19 (D.D.C. 1986)11 12 13 Scanwell Labs., Inc. v. United States, 424 F.2d 859 (D.C. Cir. 1970).
4
protest jurisdiction, until that jurisdiction “sunset” in 2001.14
From the enactment of CICA in 198415 until its jurisdiction was
ended through section 5101 of the Clinger Cohen Act of 1996,16
Pub. L. No. 104-106, there was another administrative forum with
jurisdiction over some protests, those related to information
technology, and that was the General Services Administration’s
Board of Contract Appeals, the GSBCA.17 In addition, a statutory
change in 1996 meant that the Court of Federal Claims,18 which
had only pre-award protest jurisdiction for many years, was given
post-award jurisdiction as well.19
The result is that, for more than a decade now, the only
places outside the contracting agency where disappointed bidders
have been able to protest are GAO and the Court of Federal
Claims.20 From time to time there are differences between GAO
14 The Administrative Dispute Resolution Act of 1996, Pub. L. No. 104-320, § 12, 110 Stat. at 3874, provided for the District Court jurisdiction to sunset on January 1, 2001.15 16 17 18 The Court of Federal Claims was previously called the United States Claims Court prior to Congress’s enactment of the Federal Courts Administration Act of 1992, Pub. L. No. 102-572, 106 Stat. 4506, 4516. Also, Prior to Congress’s enactment of the Federal Courts Improvement Act of 1982, Pub. L. No. 97-164, 96 Stat. 25, 42, the court generally existed as the United States Court of Claims, Trial Division. 19 Administrative Dispute Resolution Act of 1996, Pub. L. No. 104-320, section 12(d). [Note to student editors: Should we refer back to the citation in the earlier footnote?]20
5
and the Court, with respect to both process and outcomes.21 The
author views occasional differences between two fora as
inevitable, and that is particularly the case here, where one
forum is administrative and the other is judicial. In any event,
having two fora hearing bid protests may be healthy for the
procurement system. While the discussion below regarding the
costs and benefits of protests to the procurement system is
focused on GAO, the analysis should apply, at least in broad
terms, to the Court of Federal Claims as well.
III. SPREAD OF THE PROTEST PROCESS OUTSIDE THE U.S.
Before turning to that analysis, it is worth looking outside
the U.S., because the protest process has been receiving
substantial attention around the world.22 More than ever in the
past, a protest system has come to be seen as a required part of
a good public procurement system.23 For example, in every free
trade agreement that the U.S. has negotiated over the past 20
years, there has been a provision requiring our trading partners
to have a protest mechanism.24 In Canada, for instance, the
Canadian International Trade Tribunal was created to satisfy the
requirement of NAFTA, the North America Free Trade Agreement,
21 22 23 It should be noted that the term “protest” (or “bid protest”) is rarely used outside the United States; instead, what we would call protests are called ”challenges,” “domestic review procedures,” “remedies,” or simply ”complaints.”24
6
that each partner have a protest forum.25 Similarly, the World
Trade Organization’s Agreement on Government Procurement (GPA)
includes a provision requiring WTO members that accede to it to
have a protest forum (called a domestic review procedure).26 In
addition, there is a protest provision in Chapter VIII of the
model procurement law of the United Nations Commission on
International Trade Law (UNCITRAL).27
Perhaps most interesting is the attention that protests have
received over the past 20 years in the European Union (“E.U.”).
25 http://www.international.gc.ca/trade-agreements-accords-commerciaux/agr-acc/nafta-alena/bereczky.aspx?view=d: “Article 1017 of the NAFTA calls for the promotion of “fair, open and impartial procurement procedures,” whereby “each party shall adopt and maintain bid challenge procedures for procurement covered” in accordance with a variety of principles, including that of “establish[ing] or designat[ing] a reviewing authority with no substantial interest in the outcome of procurements to receive bid challenges and make findings and recommendations concerning them.” As a result, the Canadian government established the Canadian International Trade Tribunal (CITT). NEEDS CITE. The tribunal’s mandate is to receive complaints and to conduct the necessary investigation to see whether the procurement project challenged falls outside the respectable limits of the NAFTA procurement procedures and to provide for remedies where procedural breaches occur.” NEEDS CITE.[Note to student editors: Please double check proper use of quotes in the preceding paragraph]26 See Article XX of the existing GPA and Article XVIII of the 2011 revised version, which is to come into effect shortly. http://www.ustr.gov/sites/default/files/GPA%20113%20Decision%20on%20the%20outcomes%20of%20the%20negotiations%20under%20Article%20XXIV%207.pdf happening?].27 See Challenge Proceedings, Chapter VIII, UNCITRAL Model Law on Public Procurement (2011). http://www.uncitral.org/pdf/english/texts/procurem/ml-procurement-2011/ML_Public_Procurement_A_66_17_E.pdf.
7
Not mentioned in the EU’s Public Procurement Directives,28
protests were first addressed by the European Commission in what
is known as the Remedies Directive.29 Initially issued in 1989,30
the Remedies Directive was revised in 2007.31 The Remedies
Directive has had an enormous impact, requiring all member states
to have a protest forum,32 and a good number of EU member states
have recently seen a significant increase in the number of
protests being filed (whether that is a positive or a negative
development is a separate question).33 The Court of Justice of
the European Union has issued decisions that have reshaped the
protest process in the E.U., in particular, through the Alcatel
decision34 that led to the requirement (codified in Article 2a of
the 2007 revision to the Remedies Directive) that there be a
“standstill” period (typically 10 days) between the announcement
of the apparent winner of the competition for a contract and the
28 See Preamble, Council Directive 89/665/EEC (1989).29 See id.30 [Id.insert reference]31 See Directive 2007/66/EC of the European Parliament and of the Council (2007).[insert reference]32 See id. at Article 1, Scope and Availability of Review Procedures.33 Jeremy Glover, Challenging the Tender Process- What is the Effect of Recent Case Law? 10 (2009).34 Case C-81/98, Alcatel Austria AG and Others, Siemens AG Österreich and Sag-Schrack Anlagentechnik AG v Bundesministerium für Wissenschaft und Verkehr, I-7708 (2009).
8
signing of the contract, in order to allow potential protesters
to file before the contract is actually awarded.35
IV. CORRECTING MISPERCEPTIONS ABOUT PROTEST STATIISTICS
In the circle of people who are interested in federal
procurement, there are a number of misperceptions about protest
statistics that should be addressed, since they can taint
judgments about the benefits and costs of protests. In
particular, even people quite familiar with the federal
acquisition system believe that protests are more common than
they really are, and they often believe, inaccurately, that
protesters frequently use the protest process to win contracts.
A. Protests are rare events
The frequency or rarity of protests needs to be judged in
context in order for the judgment to be sensible. If a
contracting officer is asked whether, in the procurements she or
he has worked on over the prior 3 years, protests were frequent,
an affirmative answer is often provided; but if one asks how many
procurements the contracting officer has worked on during that
period, that number often dwarfs the number of protests. Put
another way, while the numerator (the absolute number of
protests) is important, the denominator (the total number of
procurements) is critical to a determination of whether protests 35 See Article 2(a), Standstill period, Directive 2007/66/EC of the European Parliament and of the Council, (2007).http://eur-lex.europa.eu/LexUriServ/LexUriServ.do?uri=OJ:L:2007:335:0031:0046:EN:PDF.
9
can reasonably be said to be frequent. In assessing the
frequency of bid protests in the federal procurement system,
there are difficulties with both the denominator and the
numerator – respectively, the number of federal procurements that
occur each year, and the number of protests filed each year.
Regarding the denominator, perhaps surprisingly, there are
not good statistics on the number of federal procurements that
occur each year. Any such count would need to include, not only
the number of contracts awarded, but also any task and delivery
orders awarded that can be protested. The latter includes all
orders placed under the GSA Federal Supply Schedule and orders
issued under multiple-awarded indefinite-delivery, indefinite-
quantity contracts, where the orders have a value above $10
million.36 A recent RAND Corporation study of Air Force
procurements that were protested to GAO indicated that
approximately 20,000 contracts with a value above $25,000 were
awarded by the Air Force in 2008, representing approximately $63
billion.37 Since overall procurement spending in 2008 was over
36 The Fiscal Year (FY) 2008 National Defense Authorization Act (NDAA), NEEDS CITE, amended FASA, NEEDS CITE, to grant GAO jurisdiction to hear protests concerning task or delivery orders valued at more than $10 million. See Pub. L. No. 110-181, 122 Stat. 3, 237 (2008). [Note to Student editors: Please update the citation to also include references to the FY 2011 and FY2012 NDAAs, which extended the jurisdiction past the sunset period]37 http://www.rand.org/content/dam/rand/pubs/technical_reports/2012/RAND_TR883.pdf at 12. [Note to student editors: Please reference the name of the Rand report]
10
$500 billion (eight times the amount spent by the Air Force
alone),38 that would suggest that the overall number of contracts
awarded was approximately 160,000. The author suspects that the
number is low and that a better estimate, including FSS orders
and ID/IQ orders above $10 million, would probably substantially
exceed 250,000. For the purpose of the analysis in this paper,
it will be assumed that the total number of federal contracts and
protestable orders awarded in a year is 200,000.
With respect to the numerator – the number of protests filed
—there has been confusion, for reasons that can be clarified
here. One challenge has been a methodological anomaly that is
worth explaining. Since the days when protest filings were
tracked on 3” x 5” cards, GAO has used a methodology that can
cause people to believe that protest numbers are higher than they
actually are. When a company files a protest challenging the
terms of a solicitation, GAO assigns it a docket number, referred
to as a “B number,” since it begins with a “B” – for example, B-
123456.39 If the protester later learns new information that
constitutes a new ground of protest and files a supplemental
protest of that same solicitation’s terms, GAO will docket that
as B-123456.2.40 If another potential offeror also protests the
solicitation’s terms, GAO will docket its protest as B-123456.3,
38 39 40
11
and if that firm supplements its protest, that will be docketed
as B-123456.4.41 However those pre-award protests are resolved,
once the agency awards a contract, a losing competitor may file a
protest, which GAO will docket as B-123456.5 and, if there is a
supplemental protest once the protester sees the agency report,
that will be docketed as B-123456.6.42 And finally, if another
losing competitor files a protest and then supplements it, they
will be docketed as B-123456.7 and B-123456.8, respectively.43
Overall, GAO’s statistics will indicate eight protests, even
though only one procurement has been protested. While eight
protests of one procurement would be unusual, having two protests
is routine, and three would not be out of the ordinary.
What that means is that, when GAO reports the number of
protests filed in a year, that number substantially overstates
the number of procurements protested. For Fiscal Year (FY) 2008,
for example, while GAO reported 1,652 cases filed,44, elsewhere
GAO reported that 1,027 procurements were protested in that
41 42 43 44 GAO’s reported number of cases filed apparently also includes requests for reconsideration of a prior GAO decision as well as requests for reimbursement of costs, since either such request would be assigned the same B number as the related protest (in the example used in the text here, a request for reconsideration of the decision on the protests of the award would be docketed as B-123456.9 and a subsequent request by the two protesters that their protest costs be reimbursed would be docketed as B-123456.10 and B-123456.11.
12
period.45 In other words, GAO indicated that, on average, there
are approximately 1.6 docket numbers assigned (“cases filed”) for
each protested procurement. Assuming that this ratio is stable
over time, it would mean that the 2,353 “cases filed” in FY
201146 represented approximately 1,470 protested procurements.
While the number of federal procurements was probably not the
same in FY 2008 and FY 2011, if we assume, for the sake of
simplicity and since this is only a rough estimate, that there
were 200,000 procurements in each of those two years, that would
suggest that 0.51 percent of procurements were protested in FY
2008 and 0.7 percent were protested in FY 2011. In other words,
between 99.3 and 99.5 percent of procurements were not protested.
This calculation has been confirmed through the recent RAND
study mentioned above.47 In that study, researchers at the RAND
Corporation found that, in the Air Force, “[t]he number of [GAO]
protests as a percentage of total contract awards fell fairly
steadily from about 1.7 percent in 1995 to 0.5 percent in
2008.”48 That is to say, as of 2008, 99.5 percent of Air Force
45 Cf. B-401197 (supra note XX) at 7, fig. 1, and GAO’s GAO Bid Protest Annual Report to the Congress for Fiscal Year 2008, B-158766, Dec. 22, 2008.46 47 48 F. Camm, M.E. Chenoweth, T. Light, M.A. Lorell, J.C. Graser, P. Lewis and R. Rudavsky, Government Accountability Office Bid Protests in Air Force Source Selections, in American Bar Association Section of Public Contract Law, “The Changing Budgetary Environment: Legal and Fiscal Challenges in Federal Procurement,” from the ABA Annual Meetings in Chicago (August
13
procurements went forward without being protested to GAO. Even
if GAO protests of some other agencies’ procurements were twice
as common as for the Air Force (and there is no reason to assume
that that is the case), it would still be true that 99 percent of
their procurements went forward without being protested to GAO.
While the RAND study refers to GAO protests, including the
Court of Federal Claims would not alter the picture, since the
Court receives fewer than one-tenth the number of protests each
year that GAO receives.49 And while protesters can file protests
within the Air Force and statistics on the number of those
“agency-level protests” are not available, there is no reason to
believe that they would increase the total percentage of
protested Air Force procurements much above 0.5 percent.
It is, of course, true that very high-dollar procurements
are much more likely to be protested—the higher the dollar value,
the greater the likelihood of a protest. For a company that
loses the competition for a $100 million contract, with all the
bid and proposal costs that competing entails, the additional
cost of filing a protest may seem minimal, so that filing a
protest can be very tempting. That does not change the overall
2012), at 3. [It appears that the more appropriate reference should be to the RAND study itself.]49 Thus, the Court received 79 protests in FY 2008. http://www.crowell.com/files/2011-Bid-Protests-Trends-and-Developments.pdf
14
picture, however, especially since very high-dollar procurements
are themselves few in number: protests are rare.
What about the mantra we often hear about increases in
protest numbers? It is true that GAO has reported a substantial
increase in the number of cases filed over the past few years,50
but even if the numbers doubled, from 0.5 percent of procurements
to a full percent, it would still mean that something like 99
percent of procurements are not protested. In terms of absolute
numbers, GAO has reported that the number of protests rose from
1,327 in FY 2006 to 2,353 in FY 2011, an increase of more than 70
percent.51 Adjusted to eliminate the overcounting explained
above,52 that would represent an increase from approximately 830
to approximately 1,470 protested procurements (representing the
same percentage increase). During that same period, however,
federal procurement spending increased from $432 billion in FY
2006 to $537 billion in FY 2011.53 Put another way, in FY 2006,
there were approximately 1.92 protests for each billion in
federal procurement spending, while in FY 2011, there were 2.74
protests per billion. Those figures are similar to the ones that
GAO provided in a congressional report in 2009, when it stated
that the number of protested procurements per billion dollars in
50 51 52 53 Source: usaspending.gov.
15
Department of Defense contract spending ranged from 1.4 to 1.9
during the period FY 2004 to FY 2008.54 While the FY 2011 figure
reflects an increase, the number of protests for each billion in
federal procurement spending is still extremely low: fewer than
three protests for each billion dollars that the government
spends on contracts.
B. It is rare for a protester to win a protest, and even rarer for a winning protester to go on to obtain the contract at issue in the protest.
Here again, GAO’s methodology risks misleading observers.
GAO reports a “sustain” rate that has ranged (that is, the rate
at which GAO rules in favor of the protester and sustains the
protest), over the past 5 years, from 16 to 27 percent.55 That
sounds like protesters do fairly well. For better or for worse,
the full picture is not so favorable to protesters. First, the
sustain rate has been dropping nearly consistently over the past
5 years, falling from 27 percent in FY 2007 to 16 percent in FY
2011.56 Second, the sustain rate is calculated only among the
cases for which GAO issues a merits decision, as GAO explains in
its annual reports.57 That means that, in FY 2010, for example,
GAO did not sustain 19 percent of 2,299 cases – it sustained 19
percent of 441 merit decisions.58 Third, that percentage is
54 55 56 57 58
16
distorted by the methodology of counting multiple B numbers
separately, because protests that are sustained typically have
more B numbers than protests that are denied.59 Thus, for FY
2010, GAO reported 441 merit decisions, of which 82 were reported
as sustained protests.60 A count of the actual decisions
(counting each decision as one, even if it resolves two or more B
numbers) shows that there were actually 277 (not 441) decisions,
of which 45 (not 82) were sustained.61 That represents a 16
percent sustain rate (not 19 percent).
Thus far, this analysis means that, among the hundreds of
thousands of federal procurements that occurred in FY 2010, there
were only 45 where GAO sustained protests. The next stage,
though, offers even worse news for protesters, and it is
surprising how little is reported about it. What happened in
those 45 procurements, after GAO sustained the protests? Did the
protester that was successful in the GAO litigation succeed in
obtaining the contract? The answer: Rarely. The FY 2010
numbers have been selected here for further study, because enough
time should have passed for final action in the procurement to be
available. That said, discovering the final action can be
challenging, because information on what ultimately happened in
59 This presumably derives from protesters’ filing more supplemental protests in sustained protests, for whatever reason. 60 61
17
each one of the sustained protests is not readily available, but
enough is known to give a fairly clear picture of protesters
often winning at GAO but nonetheless not receiving the contested
contracts.62 In four of the 45 cases, GAO did not recommend any
corrective action in the protested procurement, either because
the contract had already been performed or for other reasons.63
In an additional three cases, GAO did recommend corrective action
in the procurement, but the agency explicitly declined to follow
GAO’s recommendation.64 In another case, the agency cancelled
the solicitation entirely (for reasons, and with impact,
unclear).65 In 16 additional cases (more than one third of all
the protests sustained in FY 2010) , GAO recommended corrective
action, the agency followed GAO’s recommendation, but the agency
then confirmed award to the same company as before (or awarded to
a third company, neither the earlier awardee or the protester).66
62 GAO does not track information on which company ultimately receives a contract after GAO has sustained a protest. The author, working with student research assistants at the George Washington University Law School, has been endeavoring to obtain information for the post-protest outcome of each of the 45 sustained FY 2010 protests, and the results to date are set out in the text here. The effort to track down every case continues through Freedom of Information Act requests to the respective agencies.63 Note, though, that two of those four cases involved protests of public-private competitions, where the federal employees’ representative won the protest and may have been satisfied that no further competition was to be held.64 65 66
18
In only four cases identified to date did the protester
ultimately obtain the contested contract.67 While the ultimate
outcome has yet been determined in the remaining 17
procurements,68 this much is clear: winning a protest is far
from ensuring that a protester will win the contract it is
seeking.
Experienced practitioners may point out that GAO reports a
high “effectiveness rate” that would suggest that the picture is
far better than this for protesters. That “effectiveness rate,”
which was reported as 42 percent for FY 2010,69 combines the
sustained protests described above as well as cases where
agencies took voluntary “corrective action,” without action by
GAO, so that GAO closed its files without a decision.70 There is
no publicly available information on that large universe of
protests where GAO was told that the protester “obtain[ed] some
form of relief,” as GAO writes in a footnote to its annual
report.71 In particular, there is no way to know whether the
protesters ultimately obtained the contracts at issue, and
discovering the outcome in each of the affected procurement would
challenge even the most diligent researchers, since GAO does not
publicly disclose any information about the cases that it closes
67 68 69 70 71
19
due to agencies’ voluntary corrective action.72 There is,
however, no obvious reason that an agency is more likely to award
a contract to a protester whose case ends without a GAO decision
than the agency would after GAO rules in the protester’s favor.
V. COSTS OF THE PROTEST PROCESS
A key component of the harm of the protest process is the
delay that protests cause. Even when a protest is denied, it
holds up the acquisition.73 In particular, when a protester
files in time to trigger the automatic stay under CICA,74 the
agency will be required to hold off on awarding the contract (for
pre-award protests) or to direct the contractor to stop work (for
post-award protests).75 That automatic stay can last up to 100
days,76 which is longer than the automatic suspension of a
procurement in any other country’s protest system, at least among
the many systems that the author has reviewed.77 Even if GAO
dismisses a protest, whether because it was untimely filed or
because the protester does not qualify as an ‘interested party’
with standing to protest,78 can take several weeks, and even the
most promptly dismissed protests may trigger a CICA stay that is
72 73 74 75 31 U.S.C. § 3553(c), (d).76 77 Need to add cite to at least one foreign system and the length of its stay.78
20
in place for at least a few days.79 In short, the CICA stay does
disrupt procurements.
The discussion above makes clear, however, that the CICA
stay applies to only a tiny percentage of federal procurements,
so that any harm caused by the CICA stay is also more limited
than might initially appear. In FY 2011, as noted early,
approximately 1,470 procurements were protested to GAO.80 While
specific information is not publicly available, not all of those
1,470 protested procurements would have been stayed. Only
protests filed within specified deadlines trigger a CICA stay,81
and at least some of those 1,470 protests were either untimely
filed (indeed, timeliness is one of GAO’s most common bases for
dismissing protests82) and even some of the timely-filed protests
may have been filed too late to trigger a CICA stay. For
example, a protest filed 6 to 10 days after a debriefing will
usually be timely for GAO’s filing purposes, but it will not
trigger a CICA stay, because a protest must be filed within 5
days of a debriefing to trigger a stay.83
Moreover, the fact that a protest has triggered the CICA
stay does not mean that the procurement will be on hold for 100
79 80 81 82 Dismissals of Bid Protests at the General Accounting Office, THE PROCUREMENT LAWYER, Vol. 37, No. 2 (Winter 2002) at 16.
83 31 U.S.C. § 3553(d)(4)(B).21
days. Most protests are resolved well before the 100th day, the
maximum length of CICA’s automatic stay.84 In 2009, GAO reported
to Congress that it consistently closed more than half of all
protests within 30 days.85 While that report related to protests
of DoD procurements,86 there is no reason to believe that
protests of civilian agency procurements (which are fewer in
number than DoD protests)87 take longer for GAO to close. The
stay may end because the protester has withdrawn the protest, or
because GAO has dismissed the case.88 When the agency takes
corrective action, that also ends the stay, but, of course, the
corrective action itself will generally delay progress in the
procurement.89 Even for the minority of protests that go to
published decisions – which means that they form the group of
protests for which the stay remains in place the longest time –
GAO reports that, on average, the decision is issued before the
80th day.90
Not only is the delay caused by the CICA stay shorter than
it may appear – when a delay, even a relatively short one, could
cause harm, CICA provides a mechanism for agencies to move
forward with the procurement while the protest is still
84 85 GAO April 9, 2009 report at 10.86 Needs cite.87 Needs cite.88 89 90 [Insert reference]
22
pending.91 This “override” mechanism is available to agencies,
and is used, although information on the frequency of overrides
is not readily available.92
The truly long delays – disrupting the procurement for many
months – occur when GAO issues a decision sustaining a protest
and the agency then implements GAO’s recommendation, which
typically calls for the agency to re-do at least part of the
competition for the contract.93 The universe of such cases,
however, is quite small: as explained above, there are only a
few dozen sustained protests in a year (as noted above, there
were 45 procurements in which GAO sustained protests in FY
2010),94 and, of those, some did not lead to delay in the
procurement after GAO issued its decision, either because the
decision did not contain a recommendation for corrective action
or because the agency declined to follow GAO’s recommendation.95
That leaves a relatively small number of procurements – almost
certainly fewer than 40 out of the 200,000 estimate used here for
each year’s procurements – in which there is substantial delay
91 92 For FY 2002, the last year that GAO included information on overrides in its annual report on protests, GAO reported that, with respect to the 1,101 protests filed that year, there were 71 instances of agencies’ using their override authority to move forward with the procurement, notwithstanding the protest. http://gao.gov/assets/100/93966.pdf93 Needs cite.94 95
23
due to a successful protest.96 In the author’s view, there is
adequate justification for a substantial delay in a procurement
where GAO has found that the agency violated procurement law and
that the violation harmed the protester. In any event, again in
the author’s view, any delay that the agency’s unlawful action
has caused cannot fairly be blamed on the protest system.
Critics of the protest system may also view as a cost of the
protest system GAO’s recommendation that protesters be reimbursed
the costs of filing and pursuing their protests, including their
attorney fees.97 That situation arises only when GAO finds that
a protest is meritorious—meaning, again, that the contracting
agency violated procurement law to the detriment of the protester
—so that (1) at issue are only a small number of protests each
year and (2) those cases are ones where the protest system has
identified unlawful action by the government.98 In the author’s
view, reimbursing protesters for their action as “private
attorneys general” is justified.99 In any event, the
reimbursable rates for attorney fees in those situations are now
capped, except for small business protesters.100
96 97 98 99 Scanwell Lab., Inc. v. Shaffer, 424 F.2d 859, 864 (D.C. Cir. 1970).100 31 U.S.C. § 3554 (c)(2).
24
That said, critics point to abuse of the protest system in
particular contexts as causes for concern. Specifically, there
are persistent complaints that abuse arises in the form of
“frivolous” protests, and the author has often heard calls for
imposing sanctions on firms that file frivolous protests.101 In
the 2009 report to Congress mentioned earlier, GAO responded to
questions from the House Armed Services Committee to address
frivolous protests filed in connection with DoD procurements.102
GAO pointed out that the fact that a protest was denied or even
dismissed did not mean that it was frivolous; instead, GAO
expressed the view that only a protest filed in bad faith should
be viewed as frivolous.103 GAO reported that it did not
categorize protests as frivolous and therefore had no data on the
number of frivolous protests.104 It did point out that
contracting agencies rarely assert that protests are frivolous.105
In a footnote, GAO reported that the last reported decision
noting that an agency characterized a protest as frivolous had
been in 1996 and that, in that case, the agency subsequently
acknowledged that the evaluation scheme used in the protested
procurement was flawed.106
101 102 103 104 105 106 GAO 2009 report at 12 n. 13.
25
In its 2009 report, GAO pointed to its practice of promptly
dismissing protests as indicating that there was no problem with
frivolous protests that needed to be solved.107 GAO also
expressed concern that any effort to impose sanctions on
frivolous protests (such as by imposing a fine or requiring the
protester to reimburse the government for costs incurred in
defending against the protest) would risk “the unintended
consequence of harming the federal procurement system by
discouraging participation in federal contracting and, in turn,
limiting competition.”108 GAO also pointed out that penalties
could not properly be imposed on “frivolous” protesters without
adding a new layer of litigation, in which GAO would need to
determine whether the protester had filed its protest in bad
faith.109 Besides the burden that would place on GAO, distracting
it from its focus on resolving protests as quickly as possible,
that new layer of litigation could impose additional costs on
agencies and protesters, and the burden of those additional costs
might fall disproportionately heavily on small businesses and
protesters not represented by counsel, who may have protested in
good faith, even if they acted with a misunderstanding of the
facts or the law.110
107 108 GAO 2009 report at 12.109 110 It is worth noting that protesters have only limited information about what happened during a procurement at the time
26
Those who allege that some protesters abuse of the system
sometimes point to one scenario in particular: situations where
a service contractor has lost the competition for a follow-on
contract and then files a protest in order to continue working
during the period of the CICA stay.111 This concern may be
legitimate, although the extent of the problem is not clear. The
concern would be particularly great if (1) many protests were
found to have been filed by service-contract incumbents who had
lost the competitions for the follow-on contracts and (2) their
protests were completely without merit, but (3) GAO was so slow
in resolving the protests that the incumbent was able to continue
to perform well after its contract had been due to expire. The
author is not aware of data supporting those three statements.
The appropriate response, in any event, would appear to be to
press GAO to continue (or intensify) its efforts to resolve the
protests promptly – not to create a new round of litigation about
the imposition of sanctions, and certainly not to limit or
that the strict time limits require them to decide whether to file a protest. Many agencies disclose to firms that lost competitions for contract only the bare minimum required by law. See Federal Acquisition Regulation section 15.506. It is often only through the protest process that protesters (or at least their counsel) learn in detail why they lost the competition for a contract. While review of the full agency record may eventually demonstrate that some initial protests are without merit, in other cases, review of the entire file discloses that the protests are, indeed, meritorious.111
27
abolish vendors’ right to have an independent body consider their
claims of unlawful action by the contracting agency.
The final category of alleged abuse of the protest system is
composed of sequential protests – that is, situations where a
protester loses a protest at GAO and then protests at the Court
of Federal Claims.112 Presumably, the situation could be made to
sound worse by imagining a case in which a firm protests first to
the contracting agency, then to GAO, then to the Court of Federal
Claims, and finally to the Federal Circuit.113 This scenario is,
however, an instance of imagining the hypothetical, with no
evidence of the nightmarish pattern ever actually occurring.114
Indeed, if it did occur, it is not clear that the procurement
would be disrupted, since there might be no CICA stay at GAO,115
and the courts would certainly have discretion not to impose a
preliminary injunction.116 While there are some protesters who
start at GAO and then go to the Court of Federal Claims,117 the
numbers are so small (certainly fewer than 50 in a year) and the
evidence that the procurements have been held up so thin (again,
there is no automatic right to a stay at the Court), that this
cannot legitimately be seen as a significant cost of the bid
protest system. In fact, the Court occasionally reaches a 112 113 114 115 116 117
28
different outcome than did GAO,118 which suggests, if nothing
else, that the protest was not frivolous.
Another concern about the cost of the protest system relates
to what might be called its indirect impact. Fear of protests is
often given as the explanation for contracting officers’
preference for certain courses of action over others.119 In
particular, contracting officers are said to be acting to avoid
bid protests when they decide that a contract should be awarded
to the low-priced technically acceptable (LPTA) proposal, rather
than to allow a tradeoff.120 The author has never seen data that
would indicate how often contracting officers actually decide to
name LPTA as the award criterion in a solicitation for this
reason, nor how often source selection officials avoid making
tradeoffs in the award decision, even when permitted by the terms
of the solicitation, in order to avoid protests. If the
phenomenon is common, it is unfortunate, since discretion to make
tradeoffs is a positive option in the U.S. procurement system.
Similarly, the author has heard for many years that some
contracting officers prefer to make award based on initial
proposals, rather than to conduct discussions, because they fear
that conducting discussions with offerors will increase the
likelihood of a bid protest, and increase the protester’s chances
118 119 120
29
of prevailing, if a protest is filed. Again, that would
represent a loss, since the ability to conduct discussions with
offerors is a good feature of our acquisition system, which few
systems around the world have.121 As with excessive reliance on
LPTA award criteria, we lack data about how common it is for
contracting officers to award based on initial proposals merely
to reduce the likelihood of a successful protest. In both
situations, the author is skeptical that there is any good reason
to try to “protest-proof” an acquisition in this way, especially
in light of how rare protests are, and how exceedingly rare
successful protests are. Moreover, neither using LPTA as the
basis for award, nor making award based on initial proposals,
without conduct discussions, will, in fact, ensure that no
protest will be held, as GAO and Court of Federal Claims
decisions ruling on protests of LPTA awards and initial-proposal
awards will testify.122 That said, it must be recognized that in
both areas, and potentially in others as well, it is quite
possible that the fear of protests – whether justifiable or not –
is harming the acquisition system by driving bad decisions. To
mitigate that harm, efforts need to be made to improve the
knowledge of contracting officers about the rarity of protests
and the fact that making LPTA or initial-proposals awards will
not prevent protests, as well as the benefit to the government of 121 122
30
using tradeoffs and discussions as means to obtain a better deal
for the taxpayers.
VI. BENEFITS OF THE PROTEST PROCESS
As noted above, countries around the world are developing
bid protest systems, and such systems have become, or are fast
becoming, part of the norm for good government in the acquisition
arena.123 That can be attributed to several benefits associated
with protests.
First, protests introduce a relatively low-cost form of
accountability into the acquisition system by providing
disgruntled participants a forum for airing their complaints.124
Protesting firms decide which procurements are to be investigated
– if no one protests, neither GAO nor the Court of Federal Claims
will look into the procurement; if someone does protest, they
will (at least if the protest passes the procedural hurdles, such
as timeliness).125 While reliance on audits by government
officials would also provide accountability into the workings of
the procurement system, it may be more efficient to focus on the
procurements where a participant is dissatisfied by the
government agency’s conduct, and that is what the “private
attorney general” model of a protest provides.126 In blunt terms,
123 124 125 126
31
if no one is dissatisfied with the way the government conducted a
procurement, it may not be a wise use of auditors’ time to
investigate it.
Second, by being directly responsive to participants’
complaints, protests can increase potential bidders’ confidence
in the integrity of the procurement process, and therefore lead
more players to participate, thus increasing competition.
Increasing competition, in turn, can translate into bidders
offering lower prices, higher quality, or both, to the
contracting agency.127
Third, protests can increase the public’s confidence in the
integrity of the public procurement process. While the public
only rarely focuses on public contracting, having the protest
process mentioned in the press—as happened when The Boeing
Company successfully protested the Air Force’s award of the
tanker contract to Northrop Grumman—may, it can be hoped, raise
the public’s trust in the fairness of the government’s
acquisition system and the way it spends taxpayer funds.128
Fourth, because protests are a known avenue for complaints,
their availability empowers those in contracting agencies who
face pressure to act improperly. Thus, if a contracting officer
is pressed by users within the agency to award a sole-source
127 128 The Boeing Company, B-311344 et seq., June 18, 2008.
32
contract to a favored firm, the contracting officer—who may lack
the bureaucratic clout to resist the pressure—can point to the
risk of a successful protest as the reason to follow the
statutory and regulatory requirements for competition.
Fifth, protest decisions, because they are public, and have
been released publicly since GAO issued the first one in 1926,129
provide a high level of transparency into what is happening in
the federal procurement system. While, in theory, databases such
as the federal procurement data system should provide
transparency into the system,130 protests can often provide more
useful information than databases. This is particularly the case
where protests demonstrate how problematic certain issues are.
For example, when GAO sustained a significant number of protests
challenging the way agencies were conducting public/private
competitions under OMB Circular A-76 in the 1990s, that
highlighted the importance of improving the way those
competitions were conducted, ultimately leading to revisions to
the Circular as well as the creation of the congressionally-
chartered Commercial Activities Panel.131 Similarly, it was GAO’s
sustaining of a number of protests alleging organizational
129 130 131 Commercial Activities Panel, Improving the Sourcing Decisions of the Government: Final Report, April 2002. Appendix D of the report summarizes GAO bid protest decisions arising from public/private competitions under OMB Circular A-76.
33
conflicts of interest that focused attention with the procurement
world on this area, and ultimately led to congressional and
regulatory action.132
Finally, the fact that protest decisions are published and
widely read by practitioners brings an additional benefit: they
provide guidance, particularly to agency counsel and attorneys
representing potential protesters, as well as, of course, to
their clients. To give just one example, which has been true for
decades: any corporate counsel who follows GAO bid protest
decisions knows how strictly GAO applies the “late is late” rule,
so that counsel will ensure that people in the company appreciate
the importance of getting bids in on time.133
VII. CONCLUSION: THE COSTS ARE OVERSTATED, AND THE BENEFITS OUTWEIGH THEM
As explained above, the costs that bid protests impose on
the acquisition system are often misunderstood and therefore
overstated, in terms of the frequency of protests, the length of
time that they last, and the risk that the agency’s choice of
contractor will be overturned in the process.134 Moreover, the
benefits of the protest system may not be fully appreciated, as
is the fact that the United States is required by its
132 See Daniel I. Gordon, Organizational Conflicts of Interest: A Growing Integrity Challenge, 35 PUB. CONT. L.J. 1 (2005), and cases cited therein.
133 134
34
international trade agreements to have a protest system.135
Whatever costs protests impose on the procurement system are
outweighed, at least in the author’s view, by the benefits that
protests bring, in terms of transparency, accountability,
education, and protection of the integrity of the U.S. federal
acquisition system.
135 35