bharat heavy electricals limited report

26
BHARAT HEAVY ELECTRICALS LIMITED Heavy Power Equipment Plant, Ramachandrapuram, Hyderabad-502032 Industrial training report in BHEL Hyderabad is submitted by the K L University student under the fulfillment of B.Tech (II Year) during May-June 2014 by D VIJAY VARMA (ME-12007410) Under the guidance of R . KIRAN DY MANAGER(THERMAL) Signature of the Guide/Seal

Upload: vijay-varma

Post on 23-Jan-2018

335 views

Category:

Documents


3 download

TRANSCRIPT

Page 1: BHARAT HEAVY ELECTRICALS LIMITED report

BHARAT HEAVY ELECTRICALS LIMITED Heavy Power Equipment Plant, Ramachandrapuram, Hyderabad-502032

Industrial training report in BHEL Hyderabad is submitted by the K L University

student under the fulfillment of B.Tech (II Year) during May-June 2014 by D

VIJAY VARMA (ME-12007410)

Under the guidance of

R . KIRAN DY MANAGER(THERMAL)

Signature of the Guide/Seal

Page 2: BHARAT HEAVY ELECTRICALS LIMITED report

K.L.UNIVERSITY

Greenfields,vaddeswaram,Guntur dist

I declare that the project work entitled” Analytical study of Steam

turbines & Power plant cycles ” was carried out by ME during May

- june 2014, and this work is not the same as that of any other and has not

been submitted for award of any other degree/diploma.

PLACE: D VIJAY VARMA

(12007410)

DATE:

Page 3: BHARAT HEAVY ELECTRICALS LIMITED report

CERTIFICATE

This is certifying that this project work entitled “Analytical study of Steam turbines & Power plant cycles” By D VIJAY VARMA(

12007410), is a bonified work carried out by him in BHEL Hyderabad.

Page 4: BHARAT HEAVY ELECTRICALS LIMITED report

Signature of Project guide

ACKNOWLEDGMENT

We express my sincere gratitude to R.KIRAN for encouraging and guiding

us to undertake this project work. We express my deep sense of

gratitude to our beloved parents and friends for their encouragement.

Place: D VIJAY VARMA

(12007410)

Page 5: BHARAT HEAVY ELECTRICALS LIMITED report

Date:

CONTENTS

1. Introduction about BHEL

2. Equipment manufactured

3. Power plant cycles

4. Power plant equipment

Page 6: BHARAT HEAVY ELECTRICALS LIMITED report

5. Steam turbines

6. Blade Design & Casing

7. Sealing & lube oil system

8. Governing & bearings

INTRODUCTION TO

BHEL

Bharat Heavy Electricals Limited (BHEL) owned by Government of

India, is a power plant equipment manufacturer and operates as

an engineering and manufacturing company based in New Delhi, India.

Page 7: BHARAT HEAVY ELECTRICALS LIMITED report

Established in 1964, BHEL is India's largest engineering and

manufacturing company of its kind. The company has been earning profits

continuously since 1971-72 and paying dividends uninterruptedly since

1976-77. In recognition of its consistent high performance, BHEL has been

conferred with the 'Maharatna' status by the Government of India on 1st

February 2013. It is now one among seven Maharatna PSEs.

Page 8: BHARAT HEAVY ELECTRICALS LIMITED report

It is engaged in the design, engineering, manufacture, construction, testing,

commissioning and servicing of a wide range of products, systems and services for the core sectors of the economy, viz. Power, Transmission,

Industry, Transportation, Renewable Energy, Oil & Gas and Defence.

With a widespread network of 17 manufacturing units, two repair units, four regional offices, eight service centres, eight overseas offices, 15 regional

centres, seven joint ventures, and infrastructure to execute more than 150 project sites across India and abroad, BHEL provides products, systems

and services to customers efficiently and at competitive prices. The company has established capability to deliver 20,000 MW p.a. of power

equipment to address the growing demand for power generation equipment. BHEL places strong emphasis on innovation and development

of new technologies. Its research and development (R&D) efforts enables a strong customer orientation for responding to changes in the market. The

high level of quality & reliability of its products is due to adherence to international standards by acquiring and adapting some of the best

technologies from leading companies in the world including General Electric Company, Alstom SA, Siemens AG and Mitsubishi Heavy

Industries Ltd., together with technologies developed in our own R&D centres. Most of its manufacturing units and other entities have been

accredited to Quality Management Systems (ISO 9001:2008),

Environmental Management Systems (ISO 14001:2004) and Occupational Health & Safety Management Systems (OHSAS 18001:2007).

BHEL has retained its market leadership position during 2013-14 with 72% market share in the Power Sector, even while operating in a difficult

business environment. Improved focus on project execution enabled BHEL record highest ever commissioning/synchronization of 13,452 MW of

power plants in domestic and international markets in 2013-14, marking a 30% increase over 2012-13. The company has added more than 1,24,000

MW to the country's installed power generating capacity so far.

It also has been exporting its power and industry segment products and

services for over 40 years. BHEL's global references are spread across over 76 countries across all the six continents of the world. The cumulative

overseas installed capacity of BHEL manufactured power plants exceeds 9,000 MW across 21 countries including Malaysia, Oman, Iraq, the UAE,

Bhutan, Egypt and New Zealand. Our physical exports range from turnkey

projects to after sales services.

Page 9: BHARAT HEAVY ELECTRICALS LIMITED report

EQUIPMENT

MANUFACTURED

1. GAS TURBINES

2. STEAM TURBINES

3. COMPRESSORS

4. TURBO GENERATORS

5. HEAT EXCHANGERS

6. PUMPS

7. PULVERISERS

8. SWITCH GEARS

9. GEAR BOXES

10. OIL RIGS

11. PROJECT ENGINEERING

Page 10: BHARAT HEAVY ELECTRICALS LIMITED report

POWER PLANT

CYCLES

RANKINE CYCLE:

The Rankine cycle is a model that is used to predict the performance

of steam engines. The Rankine cycle is an idealisedthermodynamic

cycle of a heat engine that converts heat into mechanical work. The heat

is supplied externally to a closed loop, which usually uses water as

the working fluid. The Rankine cycle, in the form of steam engines,

generates about 90% of all electric power used throughout the

world,[1] including virtually all biomass, coal, solar

thermal and nuclear power plants. It is named after William John Macquorn

Rankine, a Scottish polymath and Glasgow University professor.

Page 11: BHARAT HEAVY ELECTRICALS LIMITED report

There are four processes in the Rankine cycle. These states are identified

by numbers (in brown) in the above Ts diagram.

Process 1-2: The working fluid is pumped from low to high pressure. As the fluid is a liquid at this stage the pump requires little input energy.

Process 2-3: The high pressure liquid enters a boiler where it is heated at constant pressure by an external heat source to become a dry

saturated vapour. The input energy required can be easily calculated using mollier diagram or h-s chart or enthalpy-entropy chart also known

as steam tables.

Process 3-4: The dry saturated vapor expands through a turbine, generating power. This decreases the temperature and pressure of the

vapour, and some condensation may occur. The output in this process can be easily calculated using the enthalpy-entropy chart or the steam

tables.

Process 4-1: The wet vapour then enters a condenser where it is

condensed at a constant pressure to become a saturated liquid.

Page 12: BHARAT HEAVY ELECTRICALS LIMITED report

In an ideal Rankine cycle the pump and turbine would be isentopic, i.e., the

pump and turbine would generate no entropy and hence maximize the net work output. Processes 1-2 and 3-4 would be represented by vertical lines

on the t-s diagram and more closely resemble that of the Carnot cycle. The Rankine cycle shown here prevents the vapor ending up in the superheat

region after the expansion in the turbine, which reduces the energy removed by the condensers.

REHEAT:

The purpose of a reheating cycle is to remove the moisture carried by the

steam at the final stages of the expansion process. In this variation, two turbines work in series. The first accepts vapor from the boiler at high

pressure. After the vapor has passed through the first turbine, it re-enters the boiler and is reheated before passing through a second, lower-

pressure, turbine. The reheat temperatures are very close or equal to the

inlet temperatures, whereas the optimum reheat pressure needed is only one fourth of the original boiler pressure. Among other advantages, this

prevents the vapor from condensing during its expansion and thereby damaging the turbine blades, and improves the efficiency of the cycle,

given that more of the heat flow into the cycle occurs at higher temperature. The reheat cycle was first introduced in the 1920s, but was not operational

for long due to technical difficulties. In the 1940s, it was reintroduced with the increasing manufacture of high-pressure boilers, and eventually double

reheating was introduced in the 1950s. The idea behind double reheating is to increase the average temperature. It was observed that more than two

stages of reheating are unnecessary, since the next stage increases the cycle efficiency only half as much as the preceding stage. Today, double

reheating is commonly used in power plants that operate under supercritical pressure.

Page 13: BHARAT HEAVY ELECTRICALS LIMITED report

REGENRATIVE:

The regenerative Rankine cycle is so named because after emerging from the condenser (possibly as a subcooled liquid) the working fluid is heated

by steam tapped from the hot portion of the cycle. On the diagram shown, the fluid at 2 is mixed with the fluid at 4 (both at the same pressure) to end

up with the saturated liquid at 7. This is called "direct contact heating". The Regenerative Rankine cycle (with minor variants) is commonly used in real

power stations.

Another variation is where bleed steam from between turbine stages is sent

to feedwater heater to preheat the water on its way from the condenser to the boiler. These heaters do not mix the input steam and condensate,

function as an ordinary tubular heat exchanger, and are named "closed feedwater heaters".

The regenerative features here effectively raise the nominal cycle heat

input temperature, by reducing the addition of heat from the boiler/fuel source at the relatively low feedwater temperatures that would exist without

regenerative feedwater heating. This improves the efficiency of the cycle, as more of the heat flow into the cycle occurs at higher temperature. This

process ensures cycle economy.

Page 14: BHARAT HEAVY ELECTRICALS LIMITED report

COMBINED CYCLE:

In electric power generation a combined cycle is an assembly of heat

engines that work in tandem from the same source of heat, converting it into mechanical energy, which in turn usually drives electrical generators.

The principle is that after completing its cycle (in the first engine), the working fluid of the first heat engine is still low enough in its Entropy that a

second subsequent heat engine may extract energy from the waste heat (energy) of the working fluid of the first engine. By combining these multiple

streams of work upon a single mechanical shaft turning an electric

generator, the overall net efficiency of the system may be increased by 50 – 60 percent. That is, from an overall efficiency of say 34% (in a single

Page 15: BHARAT HEAVY ELECTRICALS LIMITED report

cycle) to possibly an overall efficiency of 51% (in a mechanically

combination of two (2) cycles) in net Carnot thermodynamic efficiency. This can be done because heat engines are only able to use a portion of the

energy their fuel generates (usually less than 50%). In an ordinary (non combined cycle) heat engine the remaining heat (e.g., hot exhaust fumes)

from combustion is generally wasted.

Combining two or more thermodynamic cycles results in improved overall

efficiency, reducing fuel costs. In stationary power plants, a widely used combination is a gas turbine (operating by the brayton cycle)

burning natural gas or synthesis gas from coal, whose hot exhaust powers a steam power plant (operating by the Rankine cycle). This is called a

Combined Cycle Gas Turbine (CCGT) plant, and can achieve a thermal efficiency of around 60%, in contrast to a single cycle steam power plant

which is limited to efficiencies of around 35-42%. Many new gas power plants in North America and Europe are of this type. Such an arrangement

is also used for marine propulsion, and is called a combined gas and

steam (COGAS) plant. Multiple stage turbine or steam cycles are also common.

Other historically successful combined cycles have used hot cycles with mercury vapour turbines, magnetohydrodynamic generators or molten

, with steam plants for the low temperature "bottoming" cycle. Bottoming cycles operating from a steam condenser's heat exhaust are theoretically

possible, but uneconomical because of the very large, expensive equipment needed to extract energy from the small temperature

differences between condensing steam and outside air or water. However, it is common in cold climates (such as finland) to drive community heating

systems from a power plant's condenser heat. Such cogeneration systems can yield theoretical efficiencies above 95%.

Page 16: BHARAT HEAVY ELECTRICALS LIMITED report
Page 17: BHARAT HEAVY ELECTRICALS LIMITED report

POWER PLANT

EQUIPMENT

1. BOILER

2. STEAM TURBINE

3. CONDENSER

4. PUMP

5. FEED WATER HEATER

6. HEAT EXCHANGERS

7. GENERATOR

Page 18: BHARAT HEAVY ELECTRICALS LIMITED report

STEAM TURBINE

A steam turbine is a device that extracts thermal energy from

pressurized steam and uses it to do mechanical work on a rotating output shaft. Its modern manifestation was invented by Sir charles parson in

1884.[1]

Because the turbine generates rotary motion, it is particularly suited to be

used to drive an electrical generator – about 90% of all electricity generation in the United States (1996) is by use of steam turbines. [2] The

steam turbine is a form of heat engine that derives much of its improvement

in thermodynamic efficiency from the use of multiple stages in the expansion of the steam, which results in a closer approach to the ideal

reversible expansion process.

COMPONENTS & SYSTEMS:

1. ROTOR 2. IMPULSE/REACTION BLADES

3. THRUST BEARING 4. JOURNAL BEARING

5. SEALING SYSTEM 6. LUBE OIL SYSTEM

7. CASING 8. GOVERNING SYSTEM

9. NOZZLES

10. AUXILARY SYSYTEMS

Page 19: BHARAT HEAVY ELECTRICALS LIMITED report

ROTOR

A rotor is single component made up of nickel based alloy which is machined to the required specifications and upon which the blades are

fixed circumferentially. Guide blades and reaction/impulse blades are fixed according to the design. The end part of the rotor is connected to the

generator shaft with the help of a coupling. There are two bearings namely

thrust bearing and journal bearing mounted on the rotor each side. Clearance is provided axially and laterally as there may be lateral

Page 20: BHARAT HEAVY ELECTRICALS LIMITED report

expansion due to high temp and axial movement towards one side due to

the rotationl force. At startup or at the end the rotor is rotated with the help of a process called barring.

BLADES

Page 21: BHARAT HEAVY ELECTRICALS LIMITED report

A stage in a turbine consists of a row of fixed blade and a row of moving

blade. The fixed blades are generally known as guide blades upon which

maximum pressure drop occurs. The moving blades are of two types

(a)impulse (b)reaction. Along the rotor as we move towards the end the

blade height increases gradually as the pressure at the end is less and in

order to occupy the high volume steam .

BEARING

Page 22: BHARAT HEAVY ELECTRICALS LIMITED report

Thrust bearing is used to provide axial tolerance on the shaft. The thrust

pads will be there at the front part or non drive end of the turbine which

are usually used for limitibg axial displacement of the rotor. There are two

types (a)thrust (b) journal .Journal bearing is used to support the rear end

of rotor and reduce friction.

Sealing system

FUNCTION:

To prevent steam leakage between rotating and stationary components if

the steam pressure is higher than atmospheric pressure.

To prevent entrance of atm air into the rotating and stationary components

if the steam pressure is less than atmospheric pressure.

Page 23: BHARAT HEAVY ELECTRICALS LIMITED report

PROCESS:

The leaked steam passes through the fins and is sent to the turbine in

between. Some more steam is leaked as the pr is more than atm pr which

is sent to the rear end of the turbine after the blades to the region where

the air from outer atm tries to enter into the turbine. As this is higher in pr it

will not allow air to come in. And this steam is sent to Gland steam

condenser.

LUBE OIL SYSTEM

The primary function of the Lube Oil system is to supply lubricating oil at

the proper pressure and temperature to the main propulsion turbines and

reduction gears. The lube oil not only lubricates the machinery, but it also

cools and helps reduce rusting. Secondary functions include purifying oil

that has become contaminted and transferring oil to or from the sump tank,

gravity tank, storage tank, settling tank, sludge tank, or deck connections.

Casing

Page 24: BHARAT HEAVY ELECTRICALS LIMITED report

The casing is the outer part of the turbine which covers the rotor

circumferentially. Its main objective is to prevent the outside atm air to enter

.There are mainly two types of casing (a)single casing where in it is closed

and the rotor is assembled using a push mechanism. (b) split casing where

Page 25: BHARAT HEAVY ELECTRICALS LIMITED report

in the bottom part is kept and the rotor is assembled and then the upper

part is fixed .

Governing system

Steam turbine governing is the procedure of controlling the flow rate of

steam into a steam turbine so as to maintain its speed of rotation as

constant. The variation in load during the operation of a steam turbine can

have a significant impact on its performance. In a practical situation the

load frequently varies from the designed or economic load and thus there

always exists a considerable deviation from the desired performance of the

turbine. The primary objective in the steam turbine operation is to maintain

a constant speed of rotation irrespective of the varying load. This can be

achieve by means of governing in a steam turbine.

There are three types of governing:

1. Throttle

2. Nozzle

Page 26: BHARAT HEAVY ELECTRICALS LIMITED report

3. By-pass

1. Throttle:

Throttle Governing is the most widely used method in steam turbine

governing for smaller turbines where the steam flow is less. As the name

indicates. in throttle governing the governor throttles the inlet steam flow

through the turbine according to the steam turbine steam. When there is a

load reduction than the desired economic load, then the speed increases

to control this the governor closes the governor valve. This results in

decreasing the steam flow reduces the steam turbine speed.

2. Nozzle:

Nozzle governing is an alternative efficient method of steam turbine

governing. Simple schematic of nozzle governing of steam turbine are

shown in below figure. In this method of governing, the nozzles are grouped

together as 3 or 5 and the supply of steam through this nozzles are

controlled by regulating valves. Under full full load conditions all the

regulating valves of nozzles are fully open.

3. By-pass:

The above two methods of steam turbine governing i.e. nozzle governing

and throttle governing controls the steam at inlet of the first stage or high pressure stage of turbine. When the load is greater than desired load, the

additional steam required could not pass through the first stage since additional nozzles are not available.

Bypass regulation governing, the steam is by-passed through a valve to the lower stage turbines which results in increasing the turbine power.

Once the bypass valve opens it is under control of turbine governor to control the speed of the turbine. Because if it not controlled by the governor

it may allow more steam to lower stage which results in increase in turbine speed.